In order to verify the feasibility of the multi-resource transient voltage emergency cooperative control strategy based on the transient voltage similarity partitioning of the multiple-two-element notation criterion, this study improves the standard arithmetic example of the AC/DC hybrid system CSEE-FS [
21] shown in
Figure 7. In addition, the standard example of the sending-end power system is improved to the receiving-end power system by adjusting the generator output as well as the load after DC reverse transmission. The improved standard arithmetic features 3 HVDC circuits, 47 critical nodes, 8 conventional units (5700 MW: 3400 MW thermal; 2000 MW hydro; 300 MW synchronous condenser), 7250 MW renewables (3150 MW wind; 3750 MW PV; 350 MW ESS), 55.99% renewable penetration, 5525.5 MW active load, and 2628 Mvar reactive load.
5.3. Analysis of the Effect of Transient Voltage Emergency Control Strategy with Multi-Resource Participation
The simulation fault scenario is set as an N-1 fault, set explicitly as follows: the three-phase ground short-circuit occurs on the B02 side of the node B01-B02 of the line, and the fault start time is set to 1 s, with the circuit breaker on the B02 side operating at 1.09 s and the circuit breaker on the B01 side operating at 1.1 s. The transient response curve of 500 KV bus voltage after the fault is shown in
Figure 10, and the machine-terminal voltage of new energy units with off-grid risk is shown in
Figure 11.
To verify the rationality and effectiveness of the control strategy proposed in this paper, four comparison schemes are established:
Scheme 1: The system uses the steady state partitioning method and takes the coordinated control strategy of multiple resources and load-cutting measures.
Scheme 2: The system is not partitioned and employs a coordinated control strategy for multiple resources and load-cutting measures.
Scheme 3: The system is partitioned based on transient voltage similarity, and only a single control measure, load shedding, is implemented.
Scheme 4: The system is partitioned based on transient voltage similarity and employs a coordinated control strategy for multiple resources and load-cutting measures, which constitutes the emergency control model proposed in this paper.
As shown in
Figure 10 and
Figure 11, owing to the inadequate reactive support capability in the receiving-end power system, the following fault inception prevents effective bus voltage recovery. In turn, the commutation failure of the HVDC system occurs continuously, which impacts the receiving-end system again and ultimately leads to system instability.
Scheme 1 is partitioned based on reactive power–voltage sensitivity in a steady state, and its 500 kV grid partitioning scheme is shown in
Figure 12.
The parameters of the regulation resources in zone 1 are shown in
Table 4. Notably, the fault scenario presented in this case study occurs in zone 1; therefore, this section will utilize only regulation resources within zone 1 to participate in emergency control, reflecting the advantages of the partition method and control strategy proposed in this paper. Additionally, the following preconditions are established prior to emergency control implementation:
(1) The excitation current of synchronous condensers is regulated following reference [
11], with the emergency control per-unit limit set at 3.5 p.u;
(2) Cumulative load shedding is constrained to ≤30% of steady-state load;
(3) Renewable units participate in transient voltage control exclusively through residual capacity utilization, without active power curtailment;
(4) The voltage stability margin lower bound is defined as ;
(5) The renewable off-grid margin threshold is defined as .
According to the transient voltage stability margin and transient off-grid margin calculation formula based on multiple-element notation criterion proposed in the previous section, the transient voltage stability margin of the nodes and transient off-grid margin of the new energy units are calculated in order to search for voltage-weak nodes and new energy grid nodes with off-grid risk. The results of searching for weak-voltage nodes and new energy units with off-grid risk, along with their associated margins, are presented in
Table 5 and
Table 6.
Table 5 and
Table 6 show that if only the resources within zone 1 are used to participate in the emergency control under the control strategy of scheme 1, the transient stability margin of the voltage weak node within the system is still less than the lower limit of 0.67, which fails to satisfy the system stability requirements. In addition,
Table 7 shows that the amount of resource regulation in zone 1 reaches its upper limit, indicating that the partitioning result of scheme 1 using the steady-state partitioning method is unreasonable. Therefore, there are not enough regulation resources in zone 1, which means the transient voltage stability margin cannot be restored in time after an N-1 fault. Consequently, it is necessary to call upon the resources of adjacent partitions to participate in voltage emergency control.
- 2.
Scheme 2:
Research on voltage emergency control predominantly optimizes strategies through the coordination of different resources, while overlooking the critical impact of voltage zoning control on emergency control efficacy. Therefore, the comparison scheme 2 is designed as a voltage emergency control strategy without considering grid partitioning. Based on Equations (10) and (11), the control sensitivity of the whole network resources is calculated, and then emergency control is conducted in order of sensitivity from high to low. The network-wide regulating resource parameters are shown in
Table 8.
The results of searching for weak-voltage nodes and new energy units with off-grid risk and their margins in scheme 2 are shown in
Table 9 and
Table 10.
Table 9 and
Table 10 show that the control strategy proposed in scheme 2 can improve the voltage transient stabilization margins of the nodes to more than 0.67, and the new energy transient off-grid margins are greater than 0, which satisfies the system stability requirements.
Figure 13 and
Figure 14 show that the emergency control measures of scheme 2 stabilized the bus nodes of the grid and the voltage at the point of common coupling (PCC) for renewable energy.
Table 11 illustrates the amount of regulation provided by network-wide regulation resources, and it can be seen that costly control measures, such as load shedding, will be avoided as much as possible to participate in emergency control without grid partitioning. However, scheme 2, on one hand, does not follow the secondary voltage control principle of grid partitioning control, which does not meet the practical requirements; on the other hand, due to the large number of resources in the whole network, it is necessary to calculate the sensitivity of all the resources through the trajectory sensitivity, and the calculation time of the sensitivity matrix is longer, while the total optimization time is about 23 min. Considering the additional regulatory resources that will be present in the actual grid, adopting the control strategy of scheme 2 will be more time-consuming.
- 3.
Scheme 3:
The prevailing methodologies primarily use limited resource types for voltage regulation. This fails to capitalize on the multi-resource coordination potential inherent in practical power systems. Therefore, scheme 3 is designed to use the transient voltage similarity partitioning method, but with a single control measure: load cutting. Since the fault occurs in zone 1, emergency control is performed using only the resources of zone 1, in the same manner as in scheme 1, to reflect the advantages of the partition method and control strategy proposed in this paper. When the 360 MW load is removed from zone 1 (the maximum load removal from zone 1), the results of searching for weak-voltage nodes and new energy units with off-grid risk, along with their margins in scheme 3, are shown in
Table 12 and
Table 13.
Table 12 and
Table 13 show that the transient stability margin of the node voltage under the strategy of using a single control measure in the fault area cannot meet the system stability requirements, and the system is still in a destabilized state, so it is necessary to fully exploit the regulation potential of the resources in the zone to utilize the control strategy of multi-resource cooperation.
- 4.
Scheme 4:
Since the existing research does not follow the secondary voltage control principle of grid zoning control and the problem of voltage emergency control in the single regulation measures, scheme 4 is designed to use the transient voltage similarity zoning and multi-resource coordinated participation in the control strategy in order to highlight the advantages of the scheme proposed in this paper. The parameters of the zone 1-regulating resources in this scheme are shown in
Table 14.
The results of searching for weak-voltage nodes and new energy units with off-grid risk and their margins in scheme 4 are shown in
Table 15 and
Table 16.
Table 15 and
Table 16 show that transient voltage similarity-based partitioning can improve the voltage transient stability margins of the weak nodes in the grid and the stability margins of the new energy grid-off-grid to reasonable ranges by fully utilizing the regulation capability of the resources in the fault area, which meets the system stability requirements. It reflects the advantages of the partition method proposed in this paper compared to the partition method based on the steady-state electrical quantity of the power grid, as well as the necessity of adopting an emergency control strategy for multi-resource coordination.
Figure 15 and
Figure 16 show the curves of the bus voltage and the machine terminal voltage for the new energy unit under the strategy proposed in this paper.
Table 17 shows the amount of regulation provided by resources in zone 1, and it can be seen that scheme 4 takes the control strategy of load shedding and other resource coordination in order to maintain the bus voltage stability, so the control cost is increased compared with scheme 2. However, scheme 4 follows the principle of voltage partition control on the one hand, which meets the control requirements of the actual grid; on the other hand, the number of regulation resources involved in scheme 4 is much smaller than that of scheme 2. It reduces the solving time of the sensitivity matrix for the regulation resources, and the total optimization time is approximately 4 min, which represents an 82.61% reduction in solving time compared to scheme 2 while guaranteeing the stability of the system voltage. Therefore, the superiority of the scheme proposed in this paper is demonstrated.