Next Article in Journal
Optimized Multiple Unmanned Surface Vehicle Strategies for Target Tracking with Field of View Constraints
Previous Article in Journal
Integrating Actual Decision-Making Requirements for Intelligent Collision Avoidance Strategy in Multi-Ship Encounter Situations
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Dynamic Response Analysis of a Novel Tension-Leg Dual-Module Offshore Wind Turbine System During Both Installation and Removal Processes

1
China Southern Power Grid Technology Co., Ltd., Guangzhou 510080, China
2
National Institute of Guangdong Advanced Energy Storage Co., Ltd., Guangzhou 510410, China
3
School of Marine Science and Engineering, Hainan University, Haikou 570228, China
4
School of Civil Engineering and Transportation, South China University of Technology, Guangzhou 510641, China
*
Author to whom correspondence should be addressed.
J. Mar. Sci. Eng. 2025, 13(5), 888; https://doi.org/10.3390/jmse13050888
Submission received: 24 March 2025 / Revised: 24 April 2025 / Accepted: 29 April 2025 / Published: 29 April 2025
(This article belongs to the Special Issue Advanced Studies in Marine Structures)

Abstract

:
To facilitate both the installation and the removal of floating offshore wind turbines (FOWTs), a novel tension-leg dual-module offshore wind turbine system has been proposed. This system primarily consists of a DTU 10 MW wind turbine (WT) module and a supporting tension-leg platform (TLP) module. Considering both mechanical and hydrodynamic coupling effects of the dual-module system, this study focuses on its dynamic responses during both the installation and the removal of the WT module under typical sea states. The effect of different installation vessel positions and key parameters of the clamping device on the dynamic response of the system during the WT module removal has been clarified. Based on the findings, preliminary recommendations are provided regarding the optimal positioning of the installation vessel and the optimal design parameters of the clamping device. Furthermore, an auxiliary sleeve has been proposed to facilitate the WT module removal. The results indicate that the application of the auxiliary sleeve can significantly improve the dynamic response of the system. The results of this study can serve as a reference for the design, installation, and removal of floating offshore wind turbines.

1. Introduction

With the increasing consumption of non-renewable energy sources such as coal and oil, coupled with worsening environmental pollution, there has been a global shift toward clean and renewable energy sources. Among these, wind energy has gained significant attention. Compared to onshore wind energy, offshore wind energy offers advantages such as higher turbulence intensity, reduced noise pollution, and more abundant resources [1,2].
In shallow waters, offshore wind turbines are typically installed on fixed foundations [3,4]. However, as water depth increases, the cost of fixed foundations rises exponentially, making floating foundations a more economically viable alternative [5]. Common types of floating offshore platforms include semi-submersible platforms, spar platforms, and tension-leg platforms (TLPs). Among these, TLPs exhibit superior stability due to their high stiffness in the vertical direction, which effectively controls heave and pitch motions, ensuring the stable operation of the wind turbine (WT) [6,7,8].
The installation of offshore wind turbines is a highly demanding technical operation, requiring extreme precision regardless of whether a segmented or integrated installation approach is adopted [9]. Typically, WT installation involves the use of jack-up crane vessels or floating crane vessels, with specific installation methods selected based on water depth, lifting capacity, and vessel performance, either independently or in combination [10,11,12]. Various types of wind turbine installation vessels are available, and each project selects the most reasonable and cost-effective option based on crane capacity and load capability.
Significant research has been conducted on the installation of floating wind turbines. Liu et al. [13] evaluated the dynamic response of two novel installation vessels—a catamaran and a small-waterplane-area twin hull (SWATH)—during the installation of a spar-type floating wind turbine, providing insights into vessel selection for offshore turbine installation. Hong et al. [14] proposed an innovative on-site installation method for floating offshore wind turbines, utilizing a catamaran to assemble the turbine directly at the operation site, thereby reducing dependence on port infrastructure. They introduced a fender system and pretension wires to optimize the dynamic response during turbine docking, offering a novel installation strategy for floating wind turbines. Liu et al. [15] compared the dynamic responses of the NREL 5 MW and IEA 15 MW offshore wind turbine installation systems, analyzing the impact of waves and wind on the motion of catamarans and spar platforms, as well as the relative motion at connection points, to enhance installation stability. Hassan et al. [16] assessed the dynamic response and adaptability of a novel floating monohull vessel (Nordic Wind) during offshore wind turbine installation, focusing on the effects of wind, waves, and currents on the motion responses of both the installation vessel and the floating foundation, as well as the loading conditions of the gripper system. Their findings provide insights into the design and operational strategies of future wind turbine installation vessels. Ma et al. [17] proposed an integrated transportation and installation method for the tower–nacelle–rotor (TNR) assembly, investigating the influence of environmental loads on the turbine lowering process. They analyzed the interactions between components and the foundation during lifting, as well as the effects of lowering speed and timing on the system’s dynamic response, contributing to advancements in floating wind turbine installation techniques.
Based on this background, although various installation strategies for floating offshore wind turbines have been proposed, research on floating foundations that facilitate both installation and removal remains limited. To address this gap, this study proposes a novel tension-leg dual-module offshore wind turbine system aimed at enhancing the ease of installation, removal, and maintenance. The system mainly consists of a DTU 10 MW wind turbine (WT) [18] module and a supporting tension-leg platform (TLP) module. Considering the mechanical coupling effect and hydrodynamic coupling effect, this study focuses on the dynamic response during the installation and removal of the WT module. During the removal process of the WT module, the impact of different installation vessel configurations and key design parameters of the clamping device on the system’s dynamic response is analyzed. Preliminary optimization recommendations are provided based on these findings. The main results of this study can serve as a reference for the design, installation, and removal of floating wind turbines.

2. Theoretical Basis and Numerical Model

2.1. Conceptual Design of the Novel Tension-Leg Dual-Module Offshore Wind Turbine System

This study proposes a novel tension-leg dual-module offshore wind turbine system, which primarily consists of the following components:
(1)
A DTU 10 MW floating wind turbine (WT) module.
Considering that the wind turbine is parked during both installation and removal processes, the detailed information of its aerodynamic performance during operation is not included here, but more detailed information of its aerodynamic performance can be found in reference [18].
(2)
A tension-leg platform (TLP) module.
(3)
A clamping device that connects the TLP and the wind turbine support tower.
The DTU 10 MW wind turbine module, positioned at the center of the TLP module, exhibits a self-balancing characteristic through gravity and buoyancy equilibrium. The TLP module features a central column with a hollow cylindrical passage whose inner diameter is slightly larger than the outer diameter of the wind turbine tower, maintaining a clearance of 0.5 m. The TLP module and the WT module are securely connected via a vertically arranged multi-layer symmetric clamping device. The conceptual design of the system is illustrated in Figure 1, and its primary design parameters are listed in Table 1.
During the removal of the WT module, the clamping device must be released. To prevent collisions between the tower and the TLP central column during the upward extraction of the wind turbine, fenders are incorporated into the clamping device to absorb impact forces. The clamping devices are positioned at depths of 4 m and 8 m underwater to ensure secure fixation while allowing controlled removal.

2.2. Overview of the WT Installation Vessel

This study references the ORION I, a large-scale wind turbine installation vessel built by COSCO Shipping Co., Ltd., Shanghai, China, to investigate the installation and removal process of the proposed novel system. The ORION I is equipped with a 5000-ton full-rotation heavy-duty crane with a maximum lifting height of 170 m, capable of transporting the heaviest monopile foundations, jacket foundations, and various wind turbine components currently available on the market. It is one of the largest and most technologically advanced wind turbine installation vessels in the world.
Since detailed specifications of ORION I are not available, this study approximates the vessel as a simplified box-shaped structure for subsequent calculations. The key parameters used for this approximation are listed in Table 2.
During the removal process of the WT module, cables are required to connect the installation vessel to the wind turbine tower. In this study, four cables are deployed at four sides of the wind turbine tower for controlled extraction. The wind turbine tower extends 35 m below the water surface, and to ensure its complete emergence, the simulation is configured to lift the turbine 40 m upward.
In the installation process, when the top of the wind turbine tower reaches 5 m above the water surface, the lower end is further lowered by 40 m to complete the installation process.

2.3. Hydrodynamic Model

In this study, AQWA code [19] is employed to develop a numerical hydrodynamic model of the novel tension-leg dual-module offshore wind turbine system and the jack-up crane vessel ORION I. The model is based on potential flow theory, taking into account hydrodynamic coupling effects, as illustrated in Figure 2.
During the simulation process, the offshore wind turbine jack-up crane vessel is assumed to remain stationary to simplify the analysis and focus on the hydrodynamic interactions between the floating wind turbine system and the surrounding environment.
The motion equation governing the novel tension-leg dual-module floating offshore wind turbine system is expressed as follows:
M i X ¨ i + C i X ˙ i + K i X i = F i , w a v e + F i , w i n d + F i , t l p + F i , c a b l e + F i , f e n d e r
where M is the mass matrix; X is the displacement matrix; C is the damping matrix; K is the stiffness matrix; Fi,wave is the wave load matrix; Fi,wind is the wind load matrix; Fi,tlp is the tension-leg load matrix; Fi,cable is the cable load matrix representing the forces exerted by the cable between the wind turbine tower and the installation vessel; Fi,fender is the clamping device load matrix, which accounts for the forces between the wind turbine tower and the TLP module. Here, i = 1, 2 represents the two modules of the tension-leg dual-module floating offshore wind turbine system.

3. Results and Discussion

To evaluate the dynamic response of the system during the wind turbine removal process, simulations were conducted under typical sea conditions. The impact of different positions of the wind turbine installation vessel was analyzed to determine the optimal vessel positioning. To prevent collisions between the wind turbine tower and the TLP module, four pairs of fenders were introduced as buffering devices, and their key parameters were optimized. Additionally, an additional auxiliary sleeve scheme was proposed to effectively reduce the system’s dynamic response. Furthermore, a comparative analysis of the dynamic response during both installation and removal processes was conducted to provide reference guidance for future offshore wind turbine installation and removal.

3.1. Effect of Different Installation Vessel Positions

During actual wind turbine installation, the position of the installation vessel can significantly affect the dynamic response of the system. Therefore, three possible installation vessel locations were considered to analyze the possible effect, as shown in Figure 3. The main results are listed in Table 3.
In Table 3, the results indicate that when the installation vessel is located at position 1 (facing incoming waves), the surge is minimal, and the relative motion between the WT module and the TLP module is the smallest. The main reason for this is that the installation vessel acts as a wave shield, reducing wave impact on the system.
Based on the findings, for subsequent removal and installation operations of the WT module, position 1 is recommended as the primary working position to ensure minimal dynamic response and enhanced operational stability.
The distance between the installation vessel and the system significantly affects the dynamic response. To analyze this effect, numerical simulations were conducted under regular wave conditions (H = 2 m, T = 5, 7, 9, and 11 s). The minimum distance between the WT module center and the nearest end of the installation vessel was set to S = 11, 13, 15, 17, and 19 m. The dynamic response of the TLP module and WT module at different distances were compared, as shown in Figure 4.
In Figure 4, under varying wave periods, the surge of both the TLP module and WT module increases as S increases. Moreover, at larger wave periods, the variation trend of surge with respect to S becomes more pronounced. The effect of wave period variation on the surge is more significant than the effect of S variation.
In addition, it is observed that for the same wave period, the surge of the TLP module and WT module increases progressively as S increases. This suggests that reducing the distance between the system and the installation vessel improves the dynamic response.
Further analysis was performed by comparing two extreme distances S-11 (s = 11 m) and S-19 (s = 19 m) under typical regular wave condition (H = 2 m, T = 7 s), as shown in Figure 5. In Figure 5a, the fender force shows a slight increase with increasing S, but the difference remains within 2%. In Figure 5b, the cable force exhibits a similar overall trend across different distances. However, as S decreases, the fluctuations in cable force are reduced. Around t = 400 s, a transient fluctuation in the force occurs due to the step change in cable pull-out speed from 0.1 m/s to 0 in AQWA simulations. In practical scenarios, the pull-out speed decreases gradually, which is a limitation that AQWA cannot simulate. Considering the above findings, to optimize the dynamic response while avoiding collisions between the installation vessel and the system it is recommended to minimize the vessel’s distance from the system within safe operational limits.
To further analyze the effect of wave height, additional simulations were conducted under regular wave conditions (H = 1, 2, 3, 4, and 5 m, T = 7 s). As shown in Figure 6, with increasing wave height the maximum surge of both the TLP and WT modules increases proportionally. Additionally, their relative displacement also increases with larger wave heights, indicating that higher waves induce stronger dynamic responses on the system.

3.2. Effect of Fender Parameters

To prevent collisions between the wind turbine tower and the TLP module inner wall during the removal process, two pairs of fenders were installed at 8 m below and 4 m above the water surface to provide buffering effects. The fender parameters include stiffness and size, both of which were analyzed for their effect on the system. Three different stiffness values were considered: k = 5 × 108 N/m (baseline stiffness), k05 = 0.5 × k (half stiffness), 2k = 2 × k (double stiffness).
As shown in Figure 7a, the fender force increases with increasing stiffness. In this case, lower-stiffness fenders provide a greater buffering effect, reducing excessive force transmission. However, in Figure 7b, the cable force fluctuates more significantly with lower-stiffness fenders, whereas higher-stiffness fenders result in a more stable cable force profile.
After a comprehensive evaluation of fender force reduction and cable force stability, the middle stiffness value (k = 5 × 108 N/m) was selected for subsequent studies.
To analyze the effect of fender size, simulations were conducted with a fixed clearance of 0.5 m between the WT module and the TLP module. The main results are shown in Figure 8. The following three fender sizes were considered: fender35 = 0.35 m, fender45 = 0.45 m, fender5 = 0.5 m.
In Figure 8a, when the fender size is 0.5 m, the fender force of fender5 is significantly lower compared to fender35 and fender45. Furthermore, the peak fender force is minimized at 0.5 m fender size. In Figure 8b, when the fender size is 0.5 m, the cable force fluctuations are also reduced.
Based on the above findings, a fender size of 0.5 m is preliminarily recommended as the optimal choice to achieve a balanced dynamic response while minimizing excessive force transmission in the system.

3.3. Additional Auxiliary Sleeve Scheme

To enhance the safety of wind turbine removal, an auxiliary sleeve scheme is proposed, which involves adding a support sleeve at 30 m above the water surface. The inner diameter of the sleeve is designed to have a clearance of 0.5 m from the wind turbine tower.
To prevent collisions between the sleeve and the tower, four fenders are installed inside the sleeve to provide a buffering effect. The detailed auxiliary sleeve design is illustrated in Figure 9. The preliminary design of the auxiliary sleeve device is like an additional “arm” from the jack-up vessel to limit the motion of the wind turbine module during both the installation and the removal conditions. In the numerical model, the proposed auxiliary sleeve device is simplified as a horizontal constrain.
To evaluate the effectiveness of the auxiliary sleeve, simulations were conducted under typical irregular wave conditions (significant wave height Hs = 2 m; spectral peak period Tp = 7 s), and the dynamic response of the system was compared with and without the sleeve. The results are shown in Figure 10.
In Figure 10a, the TLP module surge shows only a slight difference between the two cases, with a maximum variation of approximately 0.002 m. In Figure 10b, the maximum fender force increases by more than 25% when the sleeve is used, indicating a stronger buffering effect. In Figure 10c, the cable force is more stable in the sleeve-assisted removal process, which improves overall operational safety and control.
Based on these findings, the additional auxiliary sleeve scheme demonstrates better dynamic response characteristics, making it a safer and more stable option for wind turbine removal operations.

3.4. WT Module Removal Under the Combined Wind and Wave Conditions

To further investigate the dynamic response of the system during wind turbine removal, simulations were conducted under a typical wind–wave combined condition (NPD wind spectrum, average wind speed Va = 15 m/s, significant wave height Hs = 2 m, and spectrum peak period Tp = 7 s, λ = 3.3). Since the wind turbine remains in a shutdown state during removal, the wind load is calculated as F = 1 2 C d ρ A v 2 , (where A is the windward area of the wind turbine, v is the wind speed, Cd is the drag coefficient, and ρ is the air density). The main results are shown in Figure 11.
In Figure 11a, the effect of wind load on the TLP module’s surge is minimal, with the extreme surge differing by only 3% compared to wave-only conditions. In Figure 11b,c, under wind–wave combined conditions, the peak cable force and fender force increase by approximately 5% compared to wave-only conditions. This indicates that wind load has a limited effect on the wind turbine removal process.
The results demonstrate that wave loads dominate the system’s dynamic response, while wind load has a relatively minor effect during the wind turbine removal process.

3.5. WT Module Installation Simulation

To analyze the dynamic response of the system during wind turbine installation, simulations were conducted under irregular wave conditions (Hs = 2 m, Tp = 5 s, 7 s, 9 s, 11 s). For the installation process, the inner DTU 10 MW wind turbine module will be gradually put into the outer TLP module by the lifting cable with the assistant of the auxiliary sleeve scheme, until the both the gravity and the displacement of the inner TU 10 MW wind turbine module are equal (as shown in Figure 9). On the contrary, for the removal process, the inner DTU 10 MW wind turbine module will be gradually pulled out of the outer TLP module by the lifting cable with the assistant of the auxiliary sleeve scheme until the inner DTU 10 MW wind turbine module is totally out of the water.
Figure 12 compares cable forces between installation and removal processes, showing an opposite trend in force variation. Therefore, the primary focus is on the fender force analysis during wind turbine installation.
In Figure 13, the fender force increases with wave period due to its dependence on fender stiffness and relative displacement between the TLP and WT module.
In Figure 14, the relative surge between the TLP module and WT module grows with increasing wave period. At Tp = 11 s, the peak fender force reaches 1.4 × 107 N, indicating high impact forces in long-period waves. To ensure safety, large-period wave conditions should be avoided during installation.
In Figure 15, additional simulations were performed under irregular wave conditions (Tp = 7 s, Hs = 1, 1.5, 2, 2.5, 3 m). Fender force increases with wave height, and excessive fender force may shorten fender lifespan.
For wind turbine installation, it is crucial to select moderate sea conditions (optimal wave height and wave period) to minimize the fender force and relative displacement, reducing impact forces that could affect the system, and ensuring safe and efficient installation operations. The responses of the fender forces, the cable forces, and the most significant motions (surge) during both installation and removal processes can be used as the input information for the further FEM analysis of the novel dual-module FOWT system. Then, the bending moment and local structure stress information can be obtained for assessing the structural reliability and fatigue safety of the novel system.
In addition, tendons of the novel system are not sensitive to both the installation and the removal process, and all tendons are verified to be safe due to the two special operation sea conditions (Hs < 3 m) being much smaller than the designed extreme sea conditions (usually Hs > 10 m).

4. Conclusions

This study proposes a novel tension-leg dual-module offshore wind turbine system and conducts installation and removal simulations under typical sea conditions. Effects of installation vessel positions and the key parameters of fenders on system’s dynamic responses have been further studied. In addition, an additional auxiliary sleeve scheme has been proposed to improve the dynamic responses during the WT module removal process. Main conclusions are drawn as follows:
(1)
The installation vessel position plays a crucial role in the WT removal process. When the installation vessel is positioned between the wave direction and the system, it provides an effective shielding effect, reducing wave impact on the system. As the distance between the TLP module and WT module increases, the relative displacement between them also increases. To optimize stability, the installation vessel should be placed as close to the platform as possible, within safe operational limits.
(2)
An additional auxiliary sleeve is added 30 m above the water surface to assist in the WT module removal process. Results indicate that surge between the WT module and TLP module is slightly reduced with the sleeve, but the effect is minor. Cable force is more stable when the sleeve is present, improving system control. Although the fender force increases due to four additional fenders inside the sleeve, the overall dynamic response with the sleeve is superior to the case without it.
(3)
Under combined wind–wave conditions, the wind turbine remains inoperative during the removal process. The wind load effect on the TLP module and WT module is comparable to that in wave-only conditions, with a numerical difference of less than 5%. Normal wind–wave conditions do not pose significant adverse effects on the turbine removal operation.

5. Future Works

This study provides a foundation for the dynamic response analysis of a novel TLP dual-floating module offshore wind turbine system during installation and removal. However, several works require further investigation, including physical model tests to validate numerical results, finite element analysis of the novel structure system to improve the reliability of the proposed system, and the optimization of cable and fender systems.

Author Contributions

Conceptualization, N.R. and C.C.; methodology, S.L. and S.W.; software, Y.Y.; validation, N.R. and H.W.; formal analysis, S.L. and X.G.; investigation, S.L. and S.W.; data curation, Y.Y. and H.W.; writing—original draft preparation, S.L. and X.G.; writing—review and editing, N.R.; supervision, N.R.; project administration, C.C.; funding acquisition, N.R. and C.C. All authors have read and agreed to the published version of the manuscript.

Funding

This research was supported by the Natural Science Foundation of Hainan Province (Grant NO. SQ2025SHFZ0141), the National Natural Science Foundation of China (Grant No. 52161041, 52201311). The financial supports are greatly acknowledged.

Institutional Review Board Statement

The study was conducted in accordance with the Declaration of Helsinki and approved by the Institutional Review Board.

Data Availability Statement

Data are contained within the article.

Conflicts of Interest

Authors Shi Liu, Xinran Guo, Yi Yang, Hongxing Wang and Shenghua Wei were employed by the company China Southern Power Grid Technology Co., Ltd. Authors Shi Liu and Yi Yang were employed by the company National Institute of Guangdong Advanced Energy Storage Co., Ltd. The remaining authors declare that the research was conducted in the absence of any commercial or financial relationships that could be construed as a potential conflict of interest.

Abbreviations

The following abbreviations are used in this manuscript:
WTWind turbine
TLPTension-leg platform
FOWTFloating offshore wind turbine

References

  1. Bahaj, A.S. Generating electricity from the oceans. Renew. Sustain. Energy Rev. 2011, 15, 3399–3416. [Google Scholar] [CrossRef]
  2. Sun, X.; Huang, D.; Wu, G. The current state of offshore wind energy technology development. Energy 2012, 41, 298–312. [Google Scholar] [CrossRef]
  3. Chandrasekaran, S.; Jain, A.K. Ocean Structures: Construction, Materials and Operations; CRC Press: Boca Raton, FL, USA, 2016; ISBN 978-149-87-9742-9. [Google Scholar]
  4. Chandrasekaran, S.; Serino, G.; Sanghvi, Y.J.C.C.; Gohil, A. Feasibility study of offshore triceratops supporting floating offshore wind turbine. Inst. Eng. India Ser. A 2024, 105, 295–305. [Google Scholar] [CrossRef]
  5. Myhr, A.; Bjerkseter, C.; Ågotnes, A.; Nygaard, T.A. Levelised cost of energy for offshore floating wind turbines in a life cycle perspective. Renew. Energy 2014, 66, 714–728. [Google Scholar] [CrossRef]
  6. Ren, N.; Gao, Z.; Moan, T.; Wan, L. Long-term performance estimation of the Spar–Torus-Combination (STC) system with different survival modes. Ocean Eng. 2015, 108, 716–728. [Google Scholar] [CrossRef]
  7. Zhao, Y.; Yang, J.; He, Y. Preliminary design of a multi-column TLP for a 5MW offshore wind turbine. Energies 2012, 5, 225–232. [Google Scholar] [CrossRef]
  8. Ma, Z.; Wang, S.; Wang, Y.; Ren, N.; Zhai, G. Experimental and numerical study on the multi-body coupling dynamic response of a novel serbuoys-TLP wind turbine. Ocean Eng. 2019, 192, 106570. [Google Scholar] [CrossRef]
  9. Ren, Z.; Jiang, Z.; Skjetne, R.; Gao, Z. Development and application of a simulator for offshore wind turbine blades installation. Ocean Eng. 2018, 166, 380–395. [Google Scholar] [CrossRef]
  10. Guo, Y.; Wang, H.; Lian, J. Review of integrated installation technologies for offshore wind turbines: Current progress and future development trends. Energy Convers. Manag. 2022, 255, 115319. [Google Scholar] [CrossRef]
  11. Jiang, Z. Installation of offshore wind turbines: A technical review. Renew. Sustain. Energy Rev. 2021, 139, 110576. [Google Scholar] [CrossRef]
  12. Wang, W.; Bai, Y. Investigation on installation of offshore wind turbines. J. Mar. Sci. Appl. 2010, 9, 175–180. [Google Scholar] [CrossRef]
  13. Liu, T.; Halse, K.H.; Leira, B.J.; Jiang, Z. Comparative study of the mating process for a spar-type floating wind turbine using two alternative installation vessels. Appl. Ocean Res. 2023, 132, 103452. [Google Scholar] [CrossRef]
  14. Hong, S.; Zhang, H.; Nord, T.S.; Halse, K.H. Effect of fender system on the dynamic response of onsite installation of floating offshore wind turbines. Ocean Eng. 2022, 259, 11830. [Google Scholar] [CrossRef]
  15. Liu, J.; Xiao, Z.; Wang, K.; Huang, S.; Du, Y. Comparative study on dynamic responses of integrated installation process of a 5-MW and a 15-MW offshore wind turbine considering a pre-installed foundation. Ocean Eng. 2024, 299, 117399. [Google Scholar] [CrossRef]
  16. Hassan, M.; Guedes Soares, C. Dynamic analysis of a novel installation method of floating spar wind turbines. J. Mar. Sci. Eng. 2023, 11, 1373. [Google Scholar] [CrossRef]
  17. Ma, C.; Zhang, T.; Jiang, Z.; Ren, Z. Dynamic analysis of lowering operations during floating offshore wind turbine assembly mating. Renew. Energy 2025, 243, 122528. [Google Scholar] [CrossRef]
  18. Christian, B.; Zahle, F.; Bitsche, R. Description of the DTU 10 MW Reference Wind Turbine; DTU Wind Energy, Technical University of Denmark: Kongens Lyngby, Denmark, 2013. [Google Scholar]
  19. Ansys. AQWA Reference Manual Release 2019 R1; USA, Ansys Inc.: Canonsburg, PA, USA, 2019. [Google Scholar]
Figure 1. Schematic diagram of the novel tension-leg dual-module offshore wind turbine system: (a) section view; (b) top view.
Figure 1. Schematic diagram of the novel tension-leg dual-module offshore wind turbine system: (a) section view; (b) top view.
Jmse 13 00888 g001
Figure 2. Hydrodynamic model of the novel tension-leg dual-module floating offshore wind turbine system and the wind turbine installation vessel.
Figure 2. Hydrodynamic model of the novel tension-leg dual-module floating offshore wind turbine system and the wind turbine installation vessel.
Jmse 13 00888 g002
Figure 3. Schematic diagram of different installation vessel positions.
Figure 3. Schematic diagram of different installation vessel positions.
Jmse 13 00888 g003
Figure 4. Effect on surge of the distance between the installation vessel and the system: (a) TLP module surge; (b) WT module surge.
Figure 4. Effect on surge of the distance between the installation vessel and the system: (a) TLP module surge; (b) WT module surge.
Jmse 13 00888 g004
Figure 5. Effect on force of the distance between the installation vessel and the system: (a) fender force; (b) cable force.
Figure 5. Effect on force of the distance between the installation vessel and the system: (a) fender force; (b) cable force.
Jmse 13 00888 g005
Figure 6. Effect on surge under different wave heights.
Figure 6. Effect on surge under different wave heights.
Jmse 13 00888 g006
Figure 7. Effect on force of fender stiffness: (a) fender force; (b) cable force.
Figure 7. Effect on force of fender stiffness: (a) fender force; (b) cable force.
Jmse 13 00888 g007
Figure 8. Effect on force of fender size: (a) fender force; (b) cable force.
Figure 8. Effect on force of fender size: (a) fender force; (b) cable force.
Jmse 13 00888 g008
Figure 9. Schematic diagram of the novel tension-leg dual-module floating offshore wind turbine system with an additional auxiliary sleeve.
Figure 9. Schematic diagram of the novel tension-leg dual-module floating offshore wind turbine system with an additional auxiliary sleeve.
Jmse 13 00888 g009
Figure 10. Effect on system’s dynamic responses with and without sleeve: (a) TLP module surge; (b) fender force; (c) cable force.
Figure 10. Effect on system’s dynamic responses with and without sleeve: (a) TLP module surge; (b) fender force; (c) cable force.
Jmse 13 00888 g010
Figure 11. Effect on system’s dynamic responses under the combined of wind and waves conditions: (a) TLP module surge; (b) cable force; (c) fender force.
Figure 11. Effect on system’s dynamic responses under the combined of wind and waves conditions: (a) TLP module surge; (b) cable force; (c) fender force.
Jmse 13 00888 g011
Figure 12. Cable force between WT module installation and removal processes.
Figure 12. Cable force between WT module installation and removal processes.
Jmse 13 00888 g012
Figure 13. Fender force comparison during WT module installation processes under different wave periods.
Figure 13. Fender force comparison during WT module installation processes under different wave periods.
Jmse 13 00888 g013
Figure 14. Relative surge during WT module installation processes under different wave periods.
Figure 14. Relative surge during WT module installation processes under different wave periods.
Jmse 13 00888 g014
Figure 15. Fender force comparison diagram under different wave heights.
Figure 15. Fender force comparison diagram under different wave heights.
Jmse 13 00888 g015
Table 1. Main parameters of the novel tension-leg dual-module offshore wind turbine system.
Table 1. Main parameters of the novel tension-leg dual-module offshore wind turbine system.
ParameterValue
10 MW WT module [18]
Blade diameter (m)178.3
Tower height (m)119
Hub, Nacelle, Tower mass (t)229, 446, 605
Tower diameter (m)9
Tower draft (m)−35
TLP module
Water depth (m)80
Column length (m)24
Column outer diameter (m)14
Spoke length, height, width (m)25, 8, 8
Center of gravity (m)−8.3
Inertia moment IXX = IYY, IZZ (kg m2)1.3 × 1010; 4.3 × 108
Column inner diameter (m)10
Total mass (t)4512
Total displacement (m3)8512
Table 2. Main parameters of ORION I.
Table 2. Main parameters of ORION I.
ParameterValue
Length of overall (m)216.57
Breadth (m)49
Depth (m)16.8
Draft (m)8.5
Design speed (knot)14
Maximum lifting height (m)170
Maximum lifting capacity (t)5000
Table 3. Surge comparison under different installation vessel positions.
Table 3. Surge comparison under different installation vessel positions.
PositionSurge of TLP Module (m)Surge of WT Module (m)Relative Surge Between Two Modules (m)
11.71 × 10−37.86 × 10−41.26 × 10−3
21.45 × 10−28.07 × 10−38.22 × 10−3
35.76 × 10−25.59 × 10−23.45 × 10−3
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Liu, S.; Guo, X.; Yang, Y.; Wang, H.; Wei, S.; Ren, N.; Chen, C. Dynamic Response Analysis of a Novel Tension-Leg Dual-Module Offshore Wind Turbine System During Both Installation and Removal Processes. J. Mar. Sci. Eng. 2025, 13, 888. https://doi.org/10.3390/jmse13050888

AMA Style

Liu S, Guo X, Yang Y, Wang H, Wei S, Ren N, Chen C. Dynamic Response Analysis of a Novel Tension-Leg Dual-Module Offshore Wind Turbine System During Both Installation and Removal Processes. Journal of Marine Science and Engineering. 2025; 13(5):888. https://doi.org/10.3390/jmse13050888

Chicago/Turabian Style

Liu, Shi, Xinran Guo, Yi Yang, Hongxing Wang, Shenghua Wei, Nianxin Ren, and Chaohe Chen. 2025. "Dynamic Response Analysis of a Novel Tension-Leg Dual-Module Offshore Wind Turbine System During Both Installation and Removal Processes" Journal of Marine Science and Engineering 13, no. 5: 888. https://doi.org/10.3390/jmse13050888

APA Style

Liu, S., Guo, X., Yang, Y., Wang, H., Wei, S., Ren, N., & Chen, C. (2025). Dynamic Response Analysis of a Novel Tension-Leg Dual-Module Offshore Wind Turbine System During Both Installation and Removal Processes. Journal of Marine Science and Engineering, 13(5), 888. https://doi.org/10.3390/jmse13050888

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop