In order to verify the rationality and scientificity of the method, a hydraulic tunnel is applied in this paper. According to the characteristics and general construction procedures of concrete structures in hydraulic tunnels, they can be divided into six main stages: construction survey, tunnel excavation, support construction, anti-drainage construction, secondary lining concrete construction and tunnel grouting.
4.4. Construction Quality Evaluation Process of Concrete Structures in Hydraulic Tunnels
This paper takes a concrete structure of a hydraulic tunnel as an example to carry out construction quality evaluation research. Indicator grading and grading standards are shown in
Table 4. In order to ensure the validity and accuracy of the evaluation results, this paper assigns values to the construction quality indicators by inviting five experts in different aspects, including design units, construction units, supervisory units and scientific research institutes, with the score range of [0,100], and the better the quality control of the indicators, the larger the score. The results of the assigned values are shown in
Table 5.
4.4.1. IAHP Method to Determine the Subjective Weight
- (1)
Combined with expert opinions and similar literature, the importance of the construction process of concrete structures in hydraulic tunnels is ranked. According to the provisions of
Table 1, the evaluation indexes of the construction quality of hydraulic tunnels are compared two by two to quantify their relative importance, and the judgment matrix of the evaluation indexes is established as shown below:
The judgment matrix of the construction quality index layer of hydraulic tunnels is as follows:
The judgment matrix of the construction measurement indicator layer is as follows:
The judgment matrix of the tunnel excavation index layer is as follows:
The judgment matrix of the support construction indicator layer is as follows:
The judgment matrix of the anti-drainage construction indicator layer is as follows:
The judgment matrix of the secondary lining concrete construction index layer is as follows:
The judgment matrix of the tunnel grouting index layer is as follows:
- (2)
According to Equations (2)–(7), the subjective weight value of each indicator is calculated, as shown in
Table 6.
4.4.2. CRITIC Method to Determine the Objective Weight
According to the assignment results of quality indicators in
Table 5, it is standardized through Equation (8) to obtain a standardized matrix. Then, according to Equations (9)–(13), the variability, conflict, information content and weight values of evaluation indicators can be calculated by writing MATLAB code in turn, as shown in
Table 7.
4.4.3. Calculate Combination Weights
- (1)
Rationality analysis of combined weights
According to the subjective and objective weights calculated by the above IAHP method and CRITIC method, the weights are sorted, as shown in
Table 8.
The consistency coefficient can be calculated from Equation (14) as . The calculation shows that the weights calculated using the IAHP method and the CRITIC method satisfy the consistency requirements and can be combined and assigned.
- (2)
Calculate combination weights
Finally, the MIE principle is utilized to eliminate the subjective and objective weight bias, and by substituting the calculation results into Equation (16), the final combined weight calculation results can be obtained, as shown in
Table 9.
4.4.4. Construct Uncertain Measure Function and Matrix of Single Index
In the process of using an unascertained measure theory to evaluate construction quality, it is necessary to construct uncertain measure function and matrix of a single index scientifically and reasonably.
The evaluation level space must conform to a certain order; that is, or , where represents the th evaluation level, and its corresponding grading standard is represented as . Then conforms to or . Assuming that the measured value of the indicator at belongs to level , when the measured value changes from to , its state value at level gradually changes from 1 to 0, and its state value at level gradually changes from 0 to 1.
The unconfirmed function constructed according to the above method only obtains non-zero values on two adjacent intervals, and the values are zero everywhere else. It is obvious that the unconfirmed function constructed according to the above method meets the requirements of its definition, i.e., satisfies the non-negativity, additivity and normalization, which is one of the biggest differences between the unconfirmed measurement function and the fuzzy affiliation function. In practical problems, the uncorroborated function can be expressed in different forms at different level intervals, and the decision-maker can choose different function forms according to the specific situation. The common forms of the uncertain measure function are mainly four types: straight line, parabola, exponential curve and sinusoidal curve type [
32], of which the more widely used is the straight line type, and its function expression is shown in Equation (23).
Based on the classification standard of tunnel construction quality in
Table 4 and the expression of the unascertained measure function in Equation (23), the unascertained measure function of the index can be determined as follows:
Based on the evaluation results of quality evaluation indicators in
Table 5, the expected value of five experts’ scores for each indicator is taken as the measurement value, as shown in
Table 10. It is put into the unascertained measure function, and the unascertained measure matrix of a single indicator can be calculated as follows:
4.4.5. Calculate Multi-Index Unascertained Measure Vector
According to the combined weights of the evaluation indicators in
Table 9 and the unascertained measure matrix of the single index mentioned above, the multi-index unascertained measure vector of the construction quality of the hydraulic tunnel can be calculated by Equation (21):
Construction measurement:
Tunnel excavation:
Support construction:
Anti-drainage construction:
Secondary lining concrete construction:
Tunnel grouting:
Total weight value:
4.4.6. Construction Quality Evaluation of Concrete Structures in Hydraulic Tunnels
According to the multi-indicator unconfirmed measurement vector of hydraulic tunnel construction quality in
Section 4.4.5, set the confidence level
, and the quality evaluation results of each stage and the whole in the tunnel construction process can be obtained from Equation (22), which is shown in
Table 11.
From the above results, it can be seen that the overall construction quality of the concrete structure in the hydraulic tunnel is grade III, i.e., the overall construction quality of this section of the tunnel is qualified, and there are relatively more problems. Therefore, the construction process needs to formulate a corresponding monitoring and management system to strictly control the construction quality. At the same time, it can also be concluded that the quality level of tunnel excavation, support construction and secondary lining concrete construction is grade II, and the construction quality level of construction measurement, anti-drainage construction and tunnel grouting is grade III. This is conducive to the construction personnel controlling the construction quality of the concrete structure in hydraulic tunnel from the details of the construction process and making the corresponding measures to improve, thus ensuring the overall construction quality of the tunnel.
4.5. Comparative Study
In order to illustrate the science and rationality of the method, this paper adopts the matter-element extension theory to evaluate the construction quality of hydraulic tunnels, which is used as a comparative study with the above. No further explanation about the matter-element extension theory is given, and specific reference can be made to the literature [
33,
34]. The focus here is on the calculation of the correlation function value of the matter-element grade of hydraulic tunnels to be evaluated.
- (1)
Correlation of evaluation indicators
The correlation of the construction quality level
t of the hydraulic tunnel to be evaluated is shown in Equation (24):
where
where
is the
th construction quality evaluation index;
is the magnitude range of the
th index divided by the evaluation grade
;
is the magnitude range of the
th index divided under each level; and
is the interval length.
- (2)
Determine the construction quality evaluation grade of the hydraulic tunnel
By combining the weights of the indicators and the value of the correlation function, the comprehensive correlation of the evaluation object can be calculated; see Equation (27). If
, the evaluation object
belongs to level
.
where
is the comprehensive correlation degree of
with respect to grade
; and
takes the objective weight value
of the CRITIC method.
According to the grading standards of each evaluation index in
Section 4.3, the classical domain and node domain of the construction quality evaluation index of the hydraulic tunnel can be determined, as shown in
Table 12.
Based on the expected value of each evaluation indicator in
Table 11, the correlation degree matrix of the evaluation indicators of hydraulic tunnel construction quality can be obtained from Equations (24)–(26):
The weight value of each secondary index calculated using the CRITIC method is as follows:
(0.2937, 0.2196, 0.1930, 0.2937); (0.2603, 0.2405, 0.2088, 0.2904); (0.3903, 0.3303, 0.2794); (0.3475, 0.2852, 0.3674);
(0.2383, 0.2275, 0.3172, 0.2169); (0.2850, 0.3569, 0.3580).
According to Equation (27), the comprehensive correlation degree of the evaluation level t for the construction quality of the hydraulic tunnel can be calculated as follows:
Construction measurement:
Tunnel excavation:
Support construction:
Anti-drainage construction:
Secondary lining concrete construction:
Tunnel grouting:
The weight values of the primary indicators calculated using the CRITIC method are as follows: (0.1723, 0.1890, 0.1818, 0.1377, 0.2043, 0.1150). According to Equation (27), the comprehensive correlation degree of the target layer for hydraulic tunnel construction quality with respect to the evaluation level can be calculated as follows:
Overall Construction:
According to the principle of maximum affiliation, the construction quality evaluation grade of the hydraulic tunnel can be determined, as shown in
Table 13.
A comparative analysis of the evaluation results of
Section 4.4 and
Section 4.5 shows that the results of both are consistent. This paper adopts the IAHP method and the CRITIC method to calculate the subjective and objective weights of the evaluation indexes, respectively, which avoids the one-sidedness of the weight calculation, gives comprehensive consideration to the subjective intention of the decision-maker and the objective attributes of the data itself, and results in evaluation outcomes that are more scientific and reasonable. At the same time, the CWM-UM model constructed in this paper can calculate the combination weights of each indicator, calculate the unconfirmed measures of single and multiple indicators, and then determine the construction quality level based on the confidence identification criterion. The results obtained are consistent with part of the comparative study. In summary, the evaluation index system and evaluation model of concrete structure construction quality for hydraulic tunnels established in this paper are scientific and reasonable.