3.1. Survey Results
For the state-of-practice survey, out of the 51 DOTs contacted, a total of 30 DOTs responded, resulting in a survey response rate of 58.8%. A summary of the key findings of the survey is given here. Question Q1 asked about the contract time administration used by DOTs for roadway construction projects. Out of 30 responding DOTs, 25 (83%, all percentages are based on the number of DOTs who responded to the specific question) indicated that they use completion date contracts, which specify a fixed date by which the project must be completed, regardless of the start date. In comparison, 20 (67%) DOTs use calendar-day contracts, which are based on a specified date or notice to proceed and include provisions for adjusting the completion date based on the agreed calendar number of days after notice to start is received. Question Q2 sought to identify construction factors that contribute most to construction project delays. Material shortage, poor project management, and adverse weather conditions were ranked as the top three factors for delays.
Among the 18 DOTs that currently have guidance to determine non-workdays due to inclement weather, 12 (67%) DOTs indicated that state workday weather charts/tools are the guidance used in their agencies, and 7 (39%) DOTs used project manager knowledge/experience to account for non-workdays due to adverse weather when developing the roadway project contract. When asked if the agency has plans to develop any guidance to estimate non-workdays due to adverse weather for roadway project contracts, 11 of the 12 respondents said “No”, while only one state said “Yes”, corresponding to 92% vs. 8%. Most DOT representatives from states without guidance in determining the impact of adverse weather on the duration of roadway project contracts believe that the existing methodologies for estimating contract durations are satisfactory.
To achieve more precise estimations of contract durations while considering inclement weather, six DOTs (33%) relied on guidance that considers climate characteristics of specific geographic areas. Similarly, six respondents (33%) based their guidance on the administrative district/region/area offices of the DOTs. Fourteen DOTs had some general criteria to determine non-workdays: (1) minimum precipitation of 0.25 cm (0.1 in.), (2) daily precipitation of 0.25 cm (0.1 in.) or 0.64 cm (0.25 in.) or 1.3 cm (0.5 in.), and (3) minimum temperature of 0 °C (32 °F) or 0–7.2 °C (32–45 °F). Even though the above information is meaningful/useful, our national survey also did not reveal any directly usable thresholds, which is similar to the SDOT study; their contacts with other state DOTs (equivalent to a survey) did not identify specific thresholds of weather parameters to define the non-working days [
8]. The survey participants mentioned using various tools and documentation to verify the non-workdays claimed by contractors. The field engineer diary is the most relied-upon resource, with 16 DOTs (94% out of 17 responses) indicating its usage. Additionally, 12 DOTs (71%) employ weekly progress reports to verify the reported non-workdays due to adverse weather. A total of 15 DOTs, or 88% of the respondents, conduct proactive meetings with contractors to preemptively address delays caused by adverse weather, thereby reducing potential conflicts and legal disputes.
3.2. AAWDs in Alabama
The method presented above and the VBA tools developed during the study were first applied to 88 weather stations (10–122 years, average 42 years of data) in Alabama, USA, to determine AAWDs.
Table 3 shows an example of the results of classifying daily climate data for Talladega, AL (station number: USC00018024), in 2018. NWDR2T40 and WDayR2T40 are the number of non-workdays (NWs) and workdays (WDays, also called AWDs) in each month for the threshold P13 (R2 stands for P > 0.51 cm [0.2 in.] and T40 stands for T < 4.4 °C [40 °F]). The spreadsheet outputs 45 columns of results for each month, including 30 columns of NW and AWD (columns 2 and 3 in
Table 3) results for 15 combinations of thresholds (
Table 2), plus other general rainfall characteristics (columns 4 to 15 in
Table 3) in addition to station number, year, and month information.
The number of workdays ranges from only 8 days in January and November to 20 days in October 2018 at Talladega. One day with missing rainfall data (TotRainMiss) occurred in November 2018, so 8 days of AWDs in November 2018 were not used to determine AAWDs in November for Talladega to reduce the uncertainty of or increase the accuracy of AAWDs. Monthly rainfall characteristics, e.g., minimum and maximum daily rainfall, average rainfall on rainy days, and average rainfall over the month, are also determined. Large rainfall events (LRGradR1, LRGradR2, and LRGradR3) account for days of rainfall larger than 1.9 cm [0.75 in.] and the next day for a rainy day with rainfall > 0.25 cm (0.1 in.), 0.51 cm (0.2 in.), and 0.76 cm (0.3 in.), respectively. When daily rainfall P > 1.9 cm (0.75 in.), it was classified as a stormwater field inspection for construction projects. It could have 30 stormwater inspections (ToInspect, out of a total of 111 rainy days) in 2018 at Talladega (
Table 3), which is connected to the Construction General Permit (CGP) inspection requirements.
Figure 2a shows variations in the monthly non-workdays and workdays from 2018 to 2020 in Talladega. The non-workdays in colder months, November through March, tend to have higher numbers due to the low temperature of the winter in combination with early spring effects (
Figure 2a). The workdays ranged from 6 (February 2022) to 21 (July 2019) days in these three years.
Figure 2b shows January’s available workdays (AWDs) from 1901 to 2020 and the determined AAWDs at Talladega. The AWDs in January (
Figure 2b) range from only 2 days in 1940, 1977, and 1978 to 20 days in 1933. January’s AAWDs are 11 days with a standard deviation (StdDev) of 4 days after processing 199 years of daily weather data.
Table 4 shows an example of the statistical summary of monthly AWDs, including minimum, maximum, median, average, standard deviation from the average, skewness coefficient, and 80th percentile of AWDs. AAWDs for Talladega, AL, from January to December range from 11 to 19 days, with standard deviations of 2 to 4 days (i.e., StdDev in
Table 4). Monthly AWDs’ median values (50th percentiles) are the same as or one day larger than AAWDs. The eighty percentile values (80PerT in
Table 4) of monthly AWDs are one to three days larger than the corresponding AAWDs, with larger differences in colder months. In the winter months (December, January, and February), monthly AWDs had a large variation, e.g., from 2 to 20 in January (18 days of difference, more than 3 weeks of available workdays or AWDs), with an AAWD of 11 days. In the past two studies (1989 and 2013), ALDOT engineers used weather data over a few years (about five years, personal communication) to determine AAWDs to represent AAWDs for the stations. This practice is not recommended because of larger variations in the monthly AWDs over the years, especially in the winter months. North Dakota DOT used weather stations containing at least 30 years of climate data to determine available workdays. This study used 10 to 122 years of weather data from 88 stations to determine AAWDs (
Table 1), with an average of 42 years of daily weather data.
There are 122 years of weather data in Talladega, but the years used to determine AAWDs range from 105 to 119 years (
Table 4) because of excluding months with missing data. The skewness coefficients are mostly negative, meaning more AWDs are larger than AAWDs for those months.
Figure 3a shows the AWD distribution in May using a histogram at Talladega, which is a left-skewed distribution (skewness coefficient of −0.737). The AAWDs in May are 18 days, with AWDs from 12 to 21 days, 45 years of AWDs < 18 days, and 54 years of AWDs > 18 days.
Figure 3b shows the AWDs’ average (i.e., AAWDs), minimum, maximum, and 80th percentile values in twelve months that indicate a seasonal pattern. There are lower AAWDs in the colder months (11 or 12 days) and not much difference in the warmer months (AAWDs of 17 to 19 days) in Talladega.
Table 5 lists the example statistical parameters of monthly AAWDs in a region, and the numbers are for 14 stations in the ALDOT East Central Region based on threshold condition P13 (
Table 2). AAWDs in the second column of
Table 5 are the average monthly AAWDs from 13 or 14 stations representing AAWDs for the region. Monthly AAWDs determined from less than 10 years of AWDs were not used for calculating the region’s AAWDs. The ALDOT Southeast Region has 24 weather stations, but up to 6 stations in some months do not have 10 years of AWDs for determining valid AAWDs. In some months, the standard deviations are zero, so AAWDs from these stations are the same or with a one-day difference. In winter months, monthly AAWDs differ up to 7 days, e.g., 9 to 16 days in January and 10 to 17 days in December. The above results on the variations in monthly AAWDs over stations in the East Central Region are the same for the other four regions (
Figure 1) [
21]. In 1989 and 2013, ALDOT engineers selected/used one weather station (large city) in each region to determine AAWDs to represent AAWDs for the whole region. Based on
Table 5 and the results in the other four regions, determining monthly AAWDs from a weather station with long weather data records is acceptable, especially in warmer months, because AAWDs have small variations among weather stations in the same region. It is worth determining the regional AAWDs from more stations for construction projects in colder months due to larger variations (
Table 5).
After comparing and examining regional average AAWDs in all five ALDOT Regions, it is recommended that ALDOT’s West Central Region and East Central Region be combined into ALDOT Central Region, and ALDOT Southeast Region and Southwest Region be combined into ALDOT South Region, since the differences between the two regions are small.
Table 6 shows the summary results for monthly Average Available Workdays or AAWDs in three Alabama climate zones: North, Central, and South Regions.
Table 6 lists the monthly AAWDs in the three climate zones from January to December, including the standard deviations, ranges (minimum to maximum), and number of stations used inside the brackets. For example, January’s AAWD is 13 days in the South Regions and ranges from 10 to 15 days with a standard deviation of 1 day from 21 stations. Again, variations in monthly AAWDs are small in warmer months and slightly larger in the colder months (December, January, and February). Annual AAWDs are 185, 193, and 200 days for the North, Central, and South Alabama Regions, 51% to 55% of 365 days. These annual AAWDs are eight (Divisions 1 and 2), five, or seven (Divisions 3 to 5) and two to five (Divisions 6 to 9) more days when compared with AAWDs from the ALDOT 1998 and 2003 studies [
16].
To understand variations in AWDs in each month, a statistical summary (minimum, maximum, average) of the minimum and maximum AWDs and the AWD differences (maximum minus minimum AWDs) out of all stations in each ALDOT climate zone was determined.
Figure 4 shows the statistical summary results for the North Region, and similar results for the other two climate zones are given in a report by Mejia Reyes et al. [
21]. January’s minimum AWDs range from 1 to 5 days, and the maximum AWDs range from 9 to 21 days (
Figure 4a) out of 21 weather stations (
Table 6) in the North Region. The maximum and minimum AWDs differ from 6 to 19 days in January and 4 to 11 days in July (
Figure 4b). There are smaller variations in the warmer months and more in the winter months. The minimum difference (MinDiff in
Figure 4b) typically occurs in those stations with 10–25 years of AWD data to determine AAWDs (smaller variations with fewer years of weather data). For example, the Central Regions have 33 weather stations (19 + 14,
Table 1) and 31 or 32 stations with 10 or more years of AWDs to determine monthly AAWDs. In January, 2 stations had AWDs for only 9 years (not used for AAWD determination), 8 stations had AWDs from 10 to 21 years (where MinDiff occurs), and the other 23 stations had AWDs for 28 to 110 years with an average of 45 years of AWDs to compute AAWDs, which indicates that long periods of weather data have been used to determine representative and reliable AAWDs in this study.
The results from
Figure 2,
Figure 3 and
Figure 4 and
Table 3,
Table 4,
Table 5 and
Table 6 were derived using the adverse threshold parameter P13 (P > 0.51 cm [0.2 in.] and T < 4.4 °C [40 °F]) to specify non-workdays for construction projects. The results for the other 14 adverse threshold parameters (
Table 2) were also derived from the VBA programs.
Figure 5 shows the results of a sensitivity analysis: how AAWDs are affected by the rainfall thresholds (P > 0.0 cm [0.0 in.], 0.25 cm [0.1 in.], 0.51 cm [0.2 in.], 0.64 cm [0.25 in.], and 0.76 cm [0.3 in.]) when the daily mean temperature threshold was fixed as T < 4.4 °C (40 °F). The AAWDs for all regions consistently increased as the precipitation threshold increased, since a higher precipitation threshold leads to fewer adverse weather conditions (non-workdays). Additionally, a similar curve pattern emerged, reflecting the impact of seasonal changes among all ALDOT Regions: more AAWDs in the summer months and fewer in the winter months.
Figure 5 is for the ALDOT North Region, and similar results for the other regions were developed and presented by Mejia Reyes [
16]. Also, larger AAWDs with lower temperature thresholds across all regions were observed in the colder months (November, December, January to March) when fixing the precipitation threshold >0.51 cm (0.2 in.) [
16], but there was no influence on AAWDs in the summer months since daily mean temperatures are greater than 4.4 °C (40 °F).
3.3. Verification Using Completed Construction Projects
To validate and ensure the accuracy of the spreadsheet tools (with all VBA codes) created to determine AAWDs due to adverse weather for roadway projects, project daily records from five completed representative ALDOT projects, each from a different ALDOT Region, were processed. For each completed project, the ALDOT representative provided the research team with the following essential information: (1) project information, (2) contract information, (3) key project/construction dates, (4) daily work report, and (5) time charges summary. The weather station closest to the project location was selected for verification based on the project information. The calculated AWDs and non-workdays (NWDs) from the weather station were compared to the recorded AWDs and NWDs from the project’s records based on what was claimed and/or reported by the contractor to ALDOT. Analyzing any discrepancies between calculated and recorded AWDs and NWDs data was to determine whether calibration adjustments may be required.
As an illustration, typical verification results are presented for a completed project in the North Region (DeKalb County, AL). This was a construction project for the replacement of the grade, drain, pave, and retaining wall of the bridge located at SR-117 over the west fork of the Little River in Mentone, AL. The project extended from January 2018 through to August 2021 for about 1320 days (~3.5 yrs), but the contract time was only 170 workdays. The closest station “Valley Head 1 SSW–USW00063862” (4.0 km [2.5 mi] from the project site) with available daily data from 2007 to 2022 was used for verification. Throughout the project’s duration, from the project’s daily records, a total of 611 days were claimed as non-workdays due to factors related to the study criteria (adverse weather: 131 rainy days, 44 wet days, 31 cold days, 445 weekends and state holidays); there were 223 workdays, and 487 days were considered as non-workdays due to other factors non-related to the study (or weather) criteria, such as utility coordination, punch items, waiting for final inspection, department actions, and others. Based on the data of the closest weather station processed using weather condition P13 (P > 0.51 cm [0.2 in.] and T < 4.4 °C [40 °F]), a total of 690 days were classified as non-workdays and 631 days as AWDs [
16]. When comparing the results of USW00063862 versus the project’s daily records, there is a difference of 79 days for the study-defined non-workdays (+13% from climate data) and a difference of 408 AWDs (+183%). The large difference in AWDs is because the contractor or project claimed 487 non-workdays due to other factors. For these 487 days, the project daily record from the contractor did not provide any weather information about rain, wet conditions, or cold temperatures. This was reflected in the large difference between 131 project rainy days and 362 rainy days from the closest station. For those 131 rainy days in the project record, the closest station reported 119 days with rainfall, with 12 days of discrepancy. The distance between the project site and the closest station is 4.0 km (2.5 mi). The non-uniformity of rainfall spatial distribution may explain this difference.
The project record did not report rainfall depth or air temperature but only stated the rain, wet, and cold conditions for 131 non-workdays. There were 119 days with rainfall at the closest station, 18 days with daily rainfall P < 0.25 cm (0.1 in.), 16 days with 0.25 cm (0.1 in.) ≤ P < 0.51 cm (0.2 in.), 3 days with 0.51 cm (0.2 in.) ≤ P < 0.64 cm (0.25 in.), 3 days with 0.64 cm (0.25 in.) ≤ P < 0.76 cm (0.3 in.), and 79 days with P > 0.76 cm (0.3 in.); therefore, it seemed that the contractor used P > 0 cm (0 in.) to classify the rainy days, which is the current ALDOT adverse weather threshold for rainfall. If we used the P > 0.51 cm (0.2 in.) threshold, only 85 of 119 days could be classified as non-workdays. When the daily rainfall is greater than 1.9 cm (0.75 in.), the following day can be considered a wet day or non-workday for construction projects. The project record reported 44 wet days, and the closest station had 45 wet days for 175 project’s rainy/wet days. However, over the whole project period, the closest station had 436 rainy/wet days; again, the discrepancy is 487 non-workdays due to other factors without climate information. In summary, the large number of non-workdays due to other factors (not weather-related) affected not only the project completion date but also the comparison between calculated AAWDs based on rainfall and temperature thresholds and the project records. This is true for all five completed projects examined in the verification process.