Next Article in Journal
Overall Buckling Behavior and Design of Steel Stiffened Box Section Columns Under Axial Compression
Previous Article in Journal
Construction and Analysis of Social Structure Model of Public Space in Fuzhou Cangxia Community from Dual Network Perspective
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Factors Driving Construction Material Price Volatility in Qatar’s Construction Industry: An Investigation Using Generalized Structured Component Analysis (GSCA)

by
Murat Gunduz
1,*,
Khalid K. Naji
1 and
Hadi Al-Marri
2
1
Department of Civil and Environmental Engineering, Qatar University, Doha P.O. Box 2713, Qatar
2
Department of Engineering Management, College of Engineering, Qatar University, Doha P.O. Box 2713, Qatar
*
Author to whom correspondence should be addressed.
Buildings 2025, 15(9), 1475; https://doi.org/10.3390/buildings15091475
Submission received: 18 March 2025 / Revised: 18 April 2025 / Accepted: 24 April 2025 / Published: 26 April 2025
(This article belongs to the Section Building Materials, and Repair & Renovation)

Abstract

Although earlier studies had connected material scarcity and price fluctuation to cost overruns and delays in Qatar’s building projects, the root causes of this volatility had not been investigated. To close this crucial gap, this study looked into these drivers. The research analyzed the factors affecting construction material prices by addressing three key objectives. First, it identified and categorized factors based on a comprehensive literature review. Second, it examined the influence of these factors and categories on material prices using Generalized Structured Component Analysis (GSCA). Third, it proposed strategies for mitigating price volatility within the Qatari construction sector. Fourteen factors were identified and grouped into three constructs: Economic and Regulatory, Logistics, and Market. Data were collected through an online survey, producing 195 responses. The GSCA method was applied to assess the model, which met the goodness-of-fit, reliability, and validity criteria for component-based structural equation modeling. The findings showed that all three constructs positively affected material prices. The Economic and Regulatory construct exerted the most significant influence, with a t-value of 5.987, followed by the Logistics construct with a t-value of 2.292. The Market construct had the lowest impact, with a t-value of 0.099. The model’s R-square value of 0.41 indicated that the three constructs accounted for 41% of the variation in construction material prices in Qatar.

1. Introduction

The construction industry is an integral component of global economies, contributing significantly to the global gross domestic product (GDP). By 2030, the industry is expected to be worth approximately USD 15 trillion, accounting for 13.5% of the global GDP [1]. In Qatar, the construction sector has experienced considerable growth, becoming a vital part of the nation’s economy. In 2015, the sector was responsible for 5.1% of the country’s GDP, making it the third-largest contributor [2]. The sector began expanding around 2000 and peaked in 2014. Despite a gradual decline from 2017 to 2019 due to the completion of many major infrastructure projects, it is projected to experience 3% annual growth between 2024 and 2027 [3], with a compound growth rate of 10.5% from 2021 to 2026 [4].
The COVID-19 pandemic of 2020 and 2021 caused a slowdown in the industry, delaying the launch of new projects and hindering progress on ongoing developments. Growth in Qatar’s construction industry is also closely linked to developments in the North Field Expansion project, which is expected to further stimulate the sector [5].
The key factors of project management include time, cost, and scope, commonly known as the “Project Management Triangle” [6]. Cost is often considered the most important factor, especially in the early stages of a project, where estimation helps determine the project’s feasibility; thus, effective cost management is critical to construction project success. Materials account for a large portion of construction costs, ranging from 30% to 70% of the total project budget [7]. Studies have revealed that in some cases, material costs can exceed 55% of total project expenditures [8].
Price fluctuations in construction materials constitute a common challenge worldwide and are among the leading causes of cost overruns. For instance, a study in Malaysia found that material price instability was the leading factor contributing to cost increases in construction projects [9]. In Oman, rising material costs have led to delays and cost overruns in both public and private projects [10]. Similarly, research from India, Botswana, Egypt, and Nigeria has underscored the role that material price fluctuations play a role in construction costs [11,12,13].
In Qatar, material price instability remains a significant issue, with fluctuations driven by a variety of local, regional, and global factors. Bitumen prices have recently surged after temporary disruptions in supply chains, and diesel and steel prices have also been subject to volatility in recent years. Despite price adjustment clauses in many construction contracts, there is no established index for monitoring and managing material price fluctuations in Qatar, making it difficult to predict and mitigate these changes [14].
While prior research had linked cost overruns and delays in Qatar’s construction projects to material scarcity and price volatility, the underlying causes of such volatility remained unexplored. This study investigated these drivers to fill this critical gap.
Understanding the drivers of construction material price volatility is critical for Qatar’s construction sector, where supply chain vulnerabilities and market uncertainties significantly impact project delivery. This study systematically investigated the key factors influencing price fluctuations through Generalized Structured Component Analysis (GSCA). These evidence-based insights will empower policymakers to refine import policies, contractors to optimize procurement strategies, and developers to enhance budget contingency planning, ultimately strengthening Qatar’s construction resilience.

2. Literature Review

Numerous studies have explored the factors driving the volatility of construction material prices. This review focuses on research linking such fluctuations to supply–demand imbalances, technological limitations, and economic pressures. These studies provided a broad understanding of the key issues involved in pricing volatility across diverse regions.
The Dedoose (SocioCultural Research Consultants, LLC, 2022) tool was used to analyze 25 research studies, focusing on the determinants of construction material prices. Journal articles comprised 76% of the reviewed literature while conference proceedings comprised 24%. Regarding the studies’ geographical distributions, 60% were conducted in Africa (with the majority in Nigeria) and 28% in Asia, with notable contributions from Malaysia, China, and India.
In terms of research methodology, 88% of the reviewed studies employed quantitative methods, with others using qualitative or mixed methods. The most frequently studied factors influencing material price fluctuations were exchange rates (11%), fiscal policy and interest rates (10% each), inflation (10%), and supply–demand imbalances (9%). Other contributors included transportation costs, fuel and energy costs (8% each), and raw material scarcity (6%).
A quantitative study was conducted in Adanawa State, Nigeria, focusing on material price fluctuations from 2014 to 2016 [15]. The researchers identified key factors such as high exchange rates, transportation costs, and petrol prices as the primary drivers of price instability. A sample size of 210 respondents, comprising private residential owners, building professionals, and suppliers, highlighted the broad impacts of these factors on real estate and the economy. Similarly, a study of price volatility was conducted in Aboja, Nigeria, identifying 17 factors, with inflation, crude oil prices, and high import duties being the most influential [16].
Adegbembo and Adeniyi focused on macroeconomic indicators such as inflation, exchange rates, and interest rates in Nigeria. Their results indicate a positive correlation between these variables and material price fluctuations [17]. Similarly, Oladipo and Oni found that inflation and exchange rates had the most significant influence on construction materials in Nigeria [18]. Musarat et al. further confirmed inflation’s impact on material prices in Pakistan, finding strong correlations between inflation and the prices of cement, steel, sand, and other materials. Their study recommended the use of strategic approaches for managing inflation rates to stabilize construction costs [19].
In the Malaysian context, Samsir et al. examined price fluctuations in Johor, concluding that inflation plays a critical role in determining material costs, alongside interest rates and energy costs. Their analysis demonstrated a strong correlation between these factors and the price volatility of construction materials [20].
In South Africa, Windapo and Cattell identified eight factors that influence material prices, including transportation, energy costs, and raw material availability. Their study revealed that rising transportation and fuel costs, alongside labor expenses, significantly impact material prices [21].
Lastly, the study by Abdel-Wahab et al. in Egypt showed that exchange rates, raw material shortages, and supplier monopolies are the most significant contributors to construction cost overruns [12].
The underlying causes of this volatility had not been examined, despite prior research linking material scarcity and price fluctuations to cost overruns and delays in Qatar’s construction projects. This study investigated these drivers in order to close this important gap. While many factors affect construction material prices, this paper compiles only the relevant factors pertaining to the Qatari construction industry and the views of local industry professionals. Table 1 lists the identified factors and the corresponding references.

3. Data Collection and Research Methodology

The research process followed a systematic approach, beginning with the identification of the core research problem and concluding with a detailed analysis of the results. The field of study chosen for this research was construction material price volatility, a topic that has gained increasing relevance due to market fluctuations and their impact on the construction industry.
Following identification of the problem, an extensive literature review was conducted. The aim was to analyze existing studies, reports, and academic articles discussing construction material prices and the variables that affect them. The literature review played a crucial role in forming the study’s theoretical framework as the factors influencing material price volatility were identified through the review process. These factors were systematically grouped into three broad categories based on their nature and impact. This classification was instrumental in designing the next stage of the research: data collection.
A survey was then developed to capture industry professionals’ perspectives and perceptions regarding the identified factors. The survey was distributed exclusively among industry professionals, encompassing a diverse range of roles, including manufacturers, suppliers, consultants, contractors, and clients, and it was structured to ensure that respondents could provide feedback on the probability and potential impact of each identified factor.
Once the survey data were collected, they was subjected to a thorough analysis using both descriptive statistical methods and Generalized Structured Component Analysis (GCSA). The descriptive analysis provided an overview of the data, highlighting general trends and patterns. Meanwhile, GCSA was employed to delve deeper into the relationships between the identified factors, offering a more comprehensive understanding of the dynamics at play.
Generalized Structured Component Analysis (GSCA) is a component-based structural equation modeling technique that offers robust analysis of complex relationships between observed and latent variables. GSCA accommodates both reflective and formative measurement models while requiring smaller sample sizes and fewer distributional assumptions [39]. The method employs alternating least squares optimization to estimate (1) component weights for latent constructs, (2) path coefficients for structural relationships, and (3) fit indices (FIT/AFIT) for model evaluation.
GSCA offers significant advantages for studies with smaller sample sizes and non-normal data distributions, and is designed to yield robust outcomes even when the number of observations is limited. In addition, GSCA does not rely on the assumption of multivariate normality; this makes it a more adaptable approach for analyzing various types of data, including those with skewed or non-normally distributed characteristics [39]. This adaptability makes GSCA particularly useful for exploratory research, especially when the data do not fulfill the assumptions typically required for SEM [40]. Additionally, as GSCA approximates latent variables through weighted composites of observed variables, it can represent abstract concepts without the strict assumptions of SEM.
It was assumed that the factors derived from the literature review exhibited a positive impact on their respective categories/constructs. These three constructs, in turn, had a positive influence on unforeseen conditions affecting the construction material prices in Qatar, as shown in Figure 1. The following hypotheses were thus formulated:
Hypothesis I.
Market factors have a positive impact on construction material prices in Qatar.
Hypothesis II.
Logistic factors have a positive impact on construction material prices in Qatar.
Hypothesis III.
Economic and regulatory factors have a positive impact on construction material prices in Qatar.
The online questionnaire was developed using Google Forms, which provided the option to customize the questionnaire according to the needs of the data analysis.
The data collection period of the questionnaire took almost four months. The total number of completed responses was 207, of which 195 were found to be responsive and acceptable. The demographics of the sample are presented in the following sections.

3.1. Sample Size

To ensure sufficient confidence in the results, the minimum acceptable sample size was set to 100 survey respondents. This threshold was higher than the minimum sample size required for GSCA, which can effectively be applied to smaller samples, even as low as 50 respondents [39]. G*Power 3.1 was also used to calculate the sample size with the setting, as in [41]. The total required sample size was 77.

3.2. Respondent Profiles

The first part of the survey collected general information about the respondents’ profiles, including their organization, position, years of experience, area of expertise, and specialization. This categorization of the respondents facilitated the comparison of various groups during the data analysis.
In terms of organizational distribution, clients represented the largest portion at 36% of the respondents, followed by contractors at 29.0%, consultants at 18%, suppliers at 11%, subcontractors at 5%, and others at 1%, as shown in Figure 2.
In terms of the positions held by the respondents, the data showed a diverse range. The most common positions, as shown in Figure 3, were of a senior engineer at 25% and engineer or supervisor at 17%. Other positions included department managers, executive managers, quantity surveyors, project managers, and a category labeled “other.”
The respondents also varied in terms of their years of experience. The largest group comprised individuals with between 11 and 15 years of experience, accounting for 28% of the sample. Respondents with five or fewer years of experience equated to only 6% of the surveyed individuals. There was also a relatively even distribution of respondents across different experience levels, ranging from six years to more than twenty-five years, as depicted in Figure 4.
The respondents’ areas of expertise were categorized into various fields within the construction industry, as detailed in Figure 5. The most common area of expertise was contracts and procurement, accounting for 28% of the respondents. Other areas included project management, engineering and design, project control, quality control, construction supervision, site execution, and a category labeled “other.”
Lastly, the respondents’ specializations within the construction industry are presented in Figure 6. Most respondents specialized in infrastructure, representing 41% of the total, while 25% and 24% of the respondents specialized in building construction and utilities, respectively. The remainder of the respondents specialized equally in industrial facilities and a category labeled “other.”
These characteristics provide an overview of the composition of the respondents in terms of their organizational affiliation, position, experience level, area of expertise, and specialization within the construction industry, as shown in Table 2.

3.3. Analysis of Factors

The participants were asked to rate each factor and category’s probability of occurrence and potential impact on a five-point Likert scale.
The likelihood was broken down thus—1. UN: Unlikely, 2. SL: Somehow Unlikely, 3. ML: Moderate, 4. L: Likely, and 5. VL: Very Likely. The potential impact was broken down thus—1. VL: Very Low, 2. L: Low, 3. Medium, 4. H: High, and 5. VH: Very High.
Table 3 shows the respondents’ ratings of the likelihood and potential impact of the Market factors. M.1 [Imbalance between supply and demand] scored 44.4% for moderate likelihood, and M.4 [Low level of technology used for production] was the second highest response at 41.1% for moderate likelihood. In terms of impact, M.3 [Scarcity of raw material] had the highest response with 42.2% for high impact, and M.4 [Low level of technology] scored the same percentage for medium impact.
The respondents’ ratings of Logistics factors are shown in Table 4. L.2 [Increase in fuel and energy costs] had the highest response at 46.4% for moderate likelihood, followed by L.1 [Increase in transportation costs] by 44.4% for moderate likelihood. L.1 and L.3 [Inadequate infrastructure facilities] scored 40.1% for high and medium impact, respectively.
For the Economic and Regulatory factors, Table 5 shows that E.6 [Government fiscal policy on interest rates] scored 49.8% for moderate likelihood, followed by E.2 [Increase in inflation rates] with 47.8%. On the other hand, ratings for impact were quite similar and mostly for medium and high impacts. E.5 [Changes in government policies and legislation] scored 38.6% for high impact, followed by E.6 with 38.2%.
Figure 7 summarizes the likelihood of occurrence and the potential impact for all the factors using radar charts.
The participants were also asked to rank the potential impact of each category. The results are shown in Table 6.

4. Data Analysis

The GSCA method was used to analyze the data obtained from the respondents. GSCA is a versatile multivariate statistical technique used to analyze complex structural relationships among variables. Unlike traditional methods, GSCA simultaneously evaluates measurement models, which link observed factors to latent variables, and structural models, which define relationships between these latent variables. Additionally, GSCA assesses the overall model fit, ensuring a comprehensive understanding of the data [40].
The GSCA model evaluation was conducted in three stages:
  • Evaluation of the measurement model (outer model);
  • Evaluation of the structural model (inner model);
  • Overall model evaluation (goodness of fit).

4.1. Normality Assessment

Table 7 lists the skewness and kurtosis of each factor. For each factor, skewness lay within the range of −1 and 1, which was excellent; a value of 2 was generally considered acceptable. Meanwhile, kurtosis was also considered normal for each factor, falling within the range of −2 to 2. Values closer to 0 for both skewness and kurtosis were better and were considered to show a normal distribution [42].

4.2. Evaluation of the Measurement Model (Outer Model)

This stage consisted of testing the relationship between the factors and the latent variables using the following methods:

4.2.1. Convergent Validity

This test was intended to check the estimated loading values of each factor. The loadings had to exceed 0.5, as established by previous studies [43]. The results in Table 8 show that all factors had a loading above 0.5, confirming validity. The critical ratio was a measure for assessing the significance of factor loading within each construct, and it was calculated as the estimate (loading) divided by its standard error.
All the factors under the Market construct had a significant effect. However, M2 [Shortage of locally manufactured/available materials] was the dominant factor, with a loading of 0.849 and a critical ratio of 37.3.
L1 [Increase in transportation costs] and L2 [Increase in fuel and energy costs] had almost the same loading, and the critical ratio of L1 and L2 was the highest, indicating its determining effect within the construct. L3 [Inadequate infrastructure facilities] had a much lower loading of 0.691 and a critical ratio of 12, which suggests that this factor was less significant within the construct.
E3 [Force majeure] had the weakest association while E6 [Government fiscal policy on interest rates] was the most influential factor within the Economic and Regulatory construct. Within this construct, Logistics Impact had the highest loading.

4.2.2. Convergent Reliability

Convergent reliability refers to the degree to which multiple factors of a specific construct share a high proportion of variance, demonstrating that they consistently represent the same underlying concept. This ensures the internal consistency of the construct, typically assessed using measures such as composite reliability (rho), Cronbach’s alpha, and proportion of variance explained (PVE). Alpha and rho values of 0.7 or higher and a PVE value of 0.5 or higher are generally considered to indicate good convergent reliability, signifying that the construct reliably explains more than half of the variance of its factors. The alpha, rho, and PVE values of the model are presented in Table 9.
As shown above, the alpha, rho, and PVE values of each latent variable met or exceeded the criteria; hence, the variables used were reliable.

4.2.3. Discriminant Validity

Three tests were conducted to verify the validity of the latent variables. Table 10 shows that each latent variable had a positive relation with the rest of the variables. Additionally, the value of √AVE for each latent variable exceeded the correlation value of the remainder latent variables. Therefore, the discriminant validity was found to be satisfactory.

4.3. Evaluation of the Structural Model (Inner Model)

The structural model was assessed by examining collinearity (VIF), estimated parameter coefficients, and the model’s R-square value. The purpose of evaluating a structural model is to understand the relationships between the constructs (latent variables).
The variance inflation factor (VIF) was used to reveal any multicollinearity in the model. The ideal value is <3, and a VIF value of between 3 and 5 indicates possible collinearity issues [44]. As shown in Table 11, the VIFs in this study were all below 3; hence, collinearity was not a significant issue.
Path coefficient is the significance of the impact between the constructs, which was assessed by examining the t-value (T-statistics), as shown in Table 12. According to [45], it is acceptable if the t-values of a two-tailed test are above 1.65 (significance level = 10%), 1.96 (significance level = 5%), and 2.58 (significance level = 1%).
The results in Table 11 indicate that Market factors had no significant impact on construction material prices. However, Logistics factors had a medium impact, and Economic and Regulatory factors had the highest impact.
Hypothesis I is rejected as the Market score t-value was 0.099, which was lower than the critical value of 1.96. Hypotheses II and III are accepted as both Logistics and Economic and Regulatory factors had a positive influence on construction material prices, with t-values higher than the critical value of 1.96.
The overall effect weight of the factors was calculated by multiplying the factor’s outer loading by the construct path coefficient. The results are shown in Table 12, whereby E6 [Government fiscal policy on interest rates], E4 [Increase in import duties], and E5 [Changes in government policies and legislation] were the top three with the highest overall effect weights.
The model’s R-square value of 0.41 indicates that the Market, Economic and Regulatory, and Logistics latent variables accounted for 41% of the causes of material price changes. The remaining 59% was influenced by factors not included in the model, suggesting that future analyses should consider additional variables affecting construction material prices. The R-square value was found to be acceptable and exceeded the minimum of 0.26 set by Cohen et al [46].
Figure 8 presents the relationships between each construct, the related factors, and the path coefficients among the constructs.

4.4. Evaluation of the Overall Model (Goodness of Fit)

The model’s overall goodness of fit was assessed by examining the FIT, AFIT, GFI, and SRMR values. Table 13 presents the estimation results for the overall model. The FIT value was 0.497, meaning that the model explained 49.7% of the diversity of data from all variables. Additionally, the AFIT value obtained was 0.491, meaning that 49.1% of the variance could be explained by the model and the rest by other factors.
GFI values near 1 and SRMR values close to 0 both indicate a good fit. For this model, the GFI value was 0.956, which was very close to 1, signifying an excellent fit. The SRMR value was 0.088, which was marginally above the acceptable cutoff of 0.08, suggesting a good fit.
According to Gyeongcheol Cho et al [47], when the sample size exceeds 100, the recommended cutoff values for the GFI and SRMR are 0.93 and 0.08, respectively. Their study also suggested that neither is one measure preferred over the other nor can one differentiate between the use of both collectively or individually.
In summary, the GFI value of 0.956 reflected a very good overall fit. The FIT and AFIT SRMR values shown in Figure 9 indicated that the model generally had a good fit.

5. Recommendation

Based on the GSCA structural equation model, the following recommendations should be considered to better forecast and control the price fluctuations of construction materials.

5.1. Market Factors

The Market construct had the lowest path coefficient and the least effect on construction material prices. However, the effect was positive, and thus, whenever it increased, construction material prices also increased. Shortages of locally manufactured or available materials had the greatest effect within the construct while low levels of technology used in production scored the lowest loading, which may be attributed to the industry preference for using more labor-based production processes or retaining the existing level of technology. The factor loadings were relatively similar, and all factors should be considered by relevant stakeholders seeking improvement and risk avoidance effect minimization.
As the major client for construction projects, the government plays an important role in controlling these effects by planning the initiation and staging of projects effectively, avoiding adverse effects relating to supply and demand or locally available materials. The government can also import and store strategic construction materials in bulk to avoid the effects of the factors included in this construct and other factors such as force majeure.
The enhancement of production technology and use of green and recycled materials should also be encouraged through government incentives as adopting these can improve production capacity and reduce running costs. The use of locally available materials should be promoted by the government and designers when planning new projects.

5.2. Logistics Factors

The Logistics construct had the second greatest impact on construction material prices. Increases in fuel and energy costs had the highest loading within the construct, but were equal in t-value to increases in transportation costs. These factors were influenced by many variables such as the price of crude oil, government fees, and modes of transportation.
Fuel price regulation, tariff and tax reduction, easing customs clearance, and improving the transportation infrastructure are some of the key strategic approaches that can help control these factors. Stakeholders should properly plan their supply arrangements and consider these factors to avoid any price volatility and the subsequent impact on the project’s financial and temporal requirements.

5.3. Economic and Regulatory Factors

The factors within this construct had the highest effect weight on construction material prices in Qatar, so the following recommendations can be made. Clients should consider other forms of contract based on partnership and risk-sharing by the parties involved in the project. Contractors and suppliers should consider the effect of government policy on interest rates in their proposals.
Increases in import duties and changes in government policies have the second-highest impact and should be accounted for in final proposals by suppliers and contractors. The government should implement a construction material index to track the volatility of construction material prices and support the industry. The index will serve as a reference for the adoption of price adjustment clauses in construction contracts.

6. Conclusions

This study pursued three key objectives to address construction material price volatility in Qatar’s dynamic market. First, we systematically identified and categorized price-influencing factors through an extensive literature review and expert validation, ultimately distilling them into three constructs: (1) Market factors, (2) Logistics factors, and (3) Economic and Regulatory factors.
Second, employing Generalized Structured Component Analysis (GSCA), we quantified each construct’s relative impact, revealing that Economic and Regulatory factors had the highest and most significant impact on the construction materials price in Qatar. This was a finding that underscored the urgent need for policy interventions to stabilize Qatar’s construction market. The validated model demonstrated good explanatory power (FIT = 49.7% and GFI = 95.6%).
Our third objective translated these findings into actionable mitigation strategies, including a proposed policy framework for streamlined material approvals and a risk-sharing mechanism for long-term projects. Based on the GSCA structural equation model findings, strategic interventions were proposed to mitigate construction material price volatility in Qatar. Market factors, while having the lowest impact (path coefficient = 0.007), require government-led initiatives such as bulk material stockpiling and technology adoption incentives to address local material shortages and production inefficiencies. For Logistics factors—the second most influential construct—fuel price regulation and infrastructure improvements emerge as key solutions to counter transportation cost volatility. Most critically, Economic and Regulatory factors demand immediate policy attention, evidenced by their dominant path coefficient (0.473). We recommend the following: (1) implementing a national construction material price index, (2) adopting risk-sharing contract models, and (3) stabilizing import duty policies. These measures offer stakeholders a comprehensive framework for cost forecasting and risk mitigation. The government’s dual role as market regulator and primary client positions it to effectively implement these strategies through policy reforms and project planning interventions.
This study was conducted by identifying the factors of construction material price volatility from a literature review of relevant studies. More data should be collected to identify other factors influencing construction material prices. The outcome of this study could lead to the development of risk assessment models for the identified factors.

Author Contributions

Conceptualization, M.G. and K.K.N.; Methodology, M.G. and K.K.N.; Software, H.A.-M.; Validation, H.A.-M.; Formal analysis, H.A.-M.; Investigation, M.G. and K.K.N.; Resources, M.G. and K.K.N.; Data curation, H.A.-M.; Writing—original draft, H.A.-M.; Writing—review & editing, M.G. and K.K.N.; Supervision, M.G. and K.K.N. All authors have read and agreed to the published version of the manuscript.

Funding

This research received no external funding.

Data Availability Statement

The original contributions presented in the study are included in the article, further inquiries can be directed to the corresponding author.

Conflicts of Interest

The authors declare no conflict of interest.

References

  1. Sweet, R. Construction Growth to Outpace Manufacturing this Decade, Says New Global Forecast. Global Construction Review. Available online: https://www.globalconstructionreview.com/construction-growth-to-outpace-manufacturing-this-decade-says-new-global-forecast/ (accessed on 11 October 2021).
  2. Country Reports—Qatar. In Qatar Country Monitor; IHS Markit Ltd.: London, UK, 2015; pp. 1–20. Available online: https://eres.qnl.qa/login?url=https://search.ebscohost.com/login.aspx?direct=true&db=awr&AN=101367169&site=eds-live&scope=site (accessed on 20 November 2022).
  3. Qatar’s Energy, Transport Projects to Drive Construction Growth—Qatar 2024—Oxford Business Group. Available online: https://oxfordbusinessgroup.com/reports/qatar/2024-report/construction-real-estate/sustainable-frontiers-energy-and-transport-projects-drive-construction-growth-while-new-regulations-encourage-expatriates-to-purchase-properties-overview/ (accessed on 20 May 2024).
  4. Kumar, S. Qatar’s Construction Market to Reach $76.98bn by 2026. The Peninsula Newspaper. Available online: https://thepeninsulaqatar.com/article/06/09/2021/Qatar%E2%80%99s-construction-market-to-reach-$76.98bn-by-2026 (accessed on 6 September 2021).
  5. Mishra, A. Qatar Construction Overview (Construction Sector, p. 21). Consulting HAUS. 2022. Available online: https://consulting-haus.com/wp-content/uploads/2024/01/CH_Construction-Sector-Overview_2022.pdf (accessed on 20 May 2024).
  6. Lu, W.; Cheung Lai, C.; Tse, T. BIM and Big Data for Construction Cost Management; Routledge: London, UK, 2018. [Google Scholar]
  7. Ayegba, C. An Assessment of Material Management on Building Construction Sites. Civ. Environ. Res. 2013, 3, 18–22. [Google Scholar]
  8. Tedla, Y.; Patel, D. Improving Effective Material Management by Identifying common Factors in Building Construction Project. Int. Res. J. Eng. Technol. 2018, 5, 146–150. [Google Scholar]
  9. Abdul Rahman, I.; Memon, A.H.; Abd Karim, A.T. Relationship between Factors of Construction Resources Affecting Project Cost. Modern Appl. Sci. 2013, 7, 67–75. [Google Scholar] [CrossRef]
  10. Al Amri, T.; Marey-Perez, M. Project delays and cost overruns between public and private sectors in Oman. J. Public Aff. 2021, 21, e2262. [Google Scholar] [CrossRef]
  11. Adeyemi, Y.A.; Kagiso, N. Factors Contributing to Construction Costs in Botswana—Perspective from Construction Contractors. Civ. Environ. Res. 2019, 11, 44–50. [Google Scholar]
  12. Abdel-Wahab, M.; Ibrahim, A.; Ghatass, H.; Abdel-Galil, E. Factors Affecting the Cost of Construction Materials in Egypt. Port-Said Eng. Res. J. 2018, 22, 82–89. [Google Scholar] [CrossRef]
  13. Simon-Eigbe, B.O.; Aiminhiefe, M.I.; Bamidele, B.O. Factors Affecting Project Performance of Building Construction Projects in Federal Capital Territory (FCT) Abuja, Nigeria. Curr. J. Appl. Sci. Technol. 2022, 41, 44–53. [Google Scholar] [CrossRef]
  14. Senouci, A.; Ismail, A.; Eldin, N. Time Delay and Cost Overrun in Qatari Public Construction Projects. Procedia Eng. 2016, 164, 368–375. [Google Scholar] [CrossRef]
  15. Haruna, A.C.; Muhammad, U.D.; Mohammed, A.; Yusuf, Y.H.; Oraegbune, O.M. Analysis of Building Materials Price Fluctuation in Adamawa State, Nigeria. FUW Trends Sci. Technol. 2018, 527–531. [Google Scholar]
  16. Muhammed, A.O.; Siyaka, H.O.; Adindu, C.C.; Muhammed, A.A. Appraising the Causes and Effects of Construction Materials Price Fluctuation on Built Environment Project Delivery in Abuja Metropolis. In Proceedings of the 2nd International Azerbaijan Congress on Life, Social, Health, and Art Sciences, Baku, Azerbaijan, 13–14 August 2022. [Google Scholar]
  17. Adegbembo, T.F.; Adeniyi, O. Evaluating the effect of macroeconomic indicators on building materials prices. In Proceedings of the 2nd Nigerian Institute of Quantity Surveyors: 2nd Research Conference–ReCon2, Akure, Nigeria, 1–3 September 2015; pp. 406–413. [Google Scholar]
  18. Oladipo, F.; Oni, O. Review of Selected Macroeconomic Factors Impacting Building Material Prices in Developing Countries—A Case Of Nigeria. Ethiop. J. Environ. Stud. Manag. 2012, 5, 131–137. [Google Scholar] [CrossRef]
  19. Musarat, M.A.; Alaloul, W.S.; Liew, M.S.; Maqsoom, A.; Qureshi, A.H. Investigating the impact of inflation on building materials prices in construction industry. J. Build. Eng. 2020, 32, 101485. [Google Scholar] [CrossRef]
  20. Samsir, M.S.; Khalid, Z.; Attan, N.; Chen, G.K.; Shafii, H. A Study on Inflation: Reason Behind Rising Price of Construction Materials in Johor Bahru. Res. Manag. Technol. Bus. 2023, 4, 1203–1220. [Google Scholar]
  21. Windapo, A.; Cattell, K. Examining the Trends in Building Material Prices: Built Environment Stakeholders’ Perspectives. Manag. Constr. Res. Pract. 2012, 1, 187–201. Available online: https://nrl.northumbria.ac.uk/id/eprint/38620/1/CIB%20MCRP2012%20conference%20proceedings%20Volume%201.pdf#page=201 (accessed on 19 August 2024).
  22. Hosny, S.; Elsaid, E.; Hosny, H. Investigating the significance of Material Prices Indicators in the Egyptian Construction Projects. Egypt. Int. J. Eng. Sci. Technol. 2024, 46, 91–104. [Google Scholar] [CrossRef]
  23. Ahmed, M.K.; Najihah, M.N.; Wahida, W. Factors Influencing the Price of Selected Building Materials in Northern Malaysia. Borneo J. Sci. Technol. 2020, 2, 7–12. [Google Scholar]
  24. Makarov, S.I.; Sevastyanova, S.A.; Ralyk, D.V. Modeling and Forecasting of Economic Indicators for Building Materials Producers. In Proceedings of the 2nd International Scientific Conference GCPMED 2019, Samara, Russia, 7–8 November 2019; pp. 1071–1079. [Google Scholar] [CrossRef]
  25. Obeng-Ahenkora, N.K.; Danso, H. Principal component analysis of factors influencing pricing decisions of building materials in Ghana. Int. J. Constr. Manag. 2020, 20, 122–129. [Google Scholar] [CrossRef]
  26. Thilakshan, K.; Arsecularatne, B.; Sandanayake, Y.G. Impact of economic decisions on building construction material prices in Sri Lanka. In Proceedings of the 11th World Construction Symposium, Colombo, Sri Lanka, 21–22 July 2023; p. 570. [Google Scholar] [CrossRef]
  27. Windapo, A. Factors Causing Differentiation in Building Material Prices in South Africa: The Perspectives of Retailers. In Conference Proceedings International Research Conference 2017: Shap. Tomorrow’s Built Environ; University of Salford: Manchester, UK, 2017. [Google Scholar]
  28. Zhou, H.; Zhao, J.H. Analysis on Factors to Cause the Price Change of Building Materials. Adv. Mater. Res. 2013, 683, 668–671. [Google Scholar] [CrossRef]
  29. Akanni, P.O.; Oke, A.E.; Omotilewa, O.J. Implications of Rising Cost of Building Materials in Lagos State Nigeria. SAGE Open 2014, 4, 215824401456121. [Google Scholar] [CrossRef]
  30. Danso, H.; Obeng-Ahenkora, N.K. Major Determinants of Prices Increase of Building Materials on Ghanaian Construction Market. Open J. Civ. Eng. 2018, 8, 142–154. [Google Scholar] [CrossRef]
  31. Ihuah, P.W. Building materials costs increases and sustainability in real estate development in Nigeria. Afr. J. Econ. Sustain. Dev. 2015, 4, 218–233. [Google Scholar] [CrossRef]
  32. Memon, A.H.; Rahman, I.A.; Aziz, A.A.A.; Ravish, K.V.; Hanas, N.I.M. Identifying Construction Resource Factors Affecting Construction Cost: Case of Johor. In Proceedings of the Malaysian Technical Universities International Conference on Engineering & Technology (MUiCET 2011), Subang Jaya, Malaysia, 16–19 January 2011; pp. 1–7. [Google Scholar]
  33. Abdulhaqq, M.O.; Abdulsamad, M.A. Correlation between Petroleum Pump Price Volatility and Selected Building Materials Prices of Construction Projects in Nigeria, 2011–2020. Int. J. Bus. Manag. 2021, 9, 42–51. [Google Scholar] [CrossRef]
  34. Jesna, N.M.; Dilip, D.K. Macroeconomic Indicators as Potential Predictors of Construction Material Prices. Sustain. Agri Food Environ. Res. 2022, 10, 1–9. [Google Scholar] [CrossRef]
  35. Nwafor, I.; Ugonabo, C.; Christian, O. Effects of Macroeconomic Indicators on Cost of Building Materials in Nigeria. Afr. J. Soc. Sci. Humanit. Res. 2023, 6, 166–176. [Google Scholar] [CrossRef]
  36. Mohamed, E.B.E.; Mahmoud, S.Y.M. An Assessment of the Impact of Inflation on the Prices of Selected Construction Materials in Sudan. Int. J. Multidiscip. Res. Publ. (IJMRAP) 2020, 2, 41–44. [Google Scholar]
  37. Oghenekevwe, O.; Olusola, O.; Chukwudi, U.S. An Assessment of the Impact of Inflation on Construction Material Prices in Nigeria. PM World J. 2014, 3, 1–22. [Google Scholar]
  38. Khodahemmati, N.; Shahandashti, M. Diagnosis and Quantification of Postdisaster Construction Material Cost Fluctuations. Nat. Hazards Rev. 2020, 21, 04020019. [Google Scholar] [CrossRef]
  39. Hwang, H.; Takane, Y. Generalized Structured Component Analysis: A Component-Based Approach to Structural Equation Modeling, 1st ed.Chapman and Hall/CRC Press: Boca Raton, FL, USA, 2014. [Google Scholar] [CrossRef]
  40. Chin, W.W.; Marcolin, B.L.; Newsted, P.R. A Partial Least Squares Latent Variable Modeling Approach for Measuring Interaction Effects: Results from a Monte Carlo Simulation Study and an Electronic-Mail Emotion/Adoption Study. Inf. Syst. Res. 2003, 14, 189–217. [Google Scholar] [CrossRef]
  41. Memon, M.A.; Ting, H.; Cheah, J.-H.; Thurasamy, R.; Chuah, F.; Cham, T.H. Sample Size for Survey Research: Review and Recommendations. J. Appl. Struct. Equ. Model. 2020, 4, i–xx. [Google Scholar] [CrossRef]
  42. Hair, J.F.; Hult, G.T.M.; Ringle, C.M.; Sarstedt, M. A Primer on Partial Least Squares Structural Equation Modeling (PLS-SEM), 3rd ed.; Sage: Thousand Oaks, CA, USA, 2022. [Google Scholar]
  43. Hair, J.F.; Howard, M.C.; Nitzl, C. Assessing measurement model quality in PLS-SEM using confirmatory composite analysis. J. Bus. Res. 2020, 109, 101–110. [Google Scholar] [CrossRef]
  44. Hair, J.F.; Risher, J.J.; Sarstedt, M.; Ringle, C.M. When to use and how to report the results of PLS-SEM. Eur. Bus. Rev. 2019, 31, 2–24. [Google Scholar] [CrossRef]
  45. Hair, J.F.; Ringle, C.M.; Sarstedt, M. PLS-SEM: Indeed a Silver Bullet. J. Mark. Theory Pract. 2011, 19, 139–152. [Google Scholar] [CrossRef]
  46. Cohen, J.; Cohen, P.; West, S.G.; Aiken, L.S. Applied Multiple Regression/Correlation Analysis for the Behavioral Sciences; Routledge: London, UK, 2013. [Google Scholar]
  47. Cho, G.; Hwang, H.; Sarstedt, M.; Ringle, C.M. Cutoff criteria for overall model fit indexes in generalized structured component analysis. J. Mark. Anal. 2020, 8, 189–202. [Google Scholar] [CrossRef]
Figure 1. Conceptual model.
Figure 1. Conceptual model.
Buildings 15 01475 g001
Figure 2. Respondents’ organizations.
Figure 2. Respondents’ organizations.
Buildings 15 01475 g002
Figure 3. Respondents’ positions.
Figure 3. Respondents’ positions.
Buildings 15 01475 g003
Figure 4. Respondents’ years of experience.
Figure 4. Respondents’ years of experience.
Buildings 15 01475 g004
Figure 5. Respondents’ areas of expertise.
Figure 5. Respondents’ areas of expertise.
Buildings 15 01475 g005
Figure 6. Respondents’ specialization.
Figure 6. Respondents’ specialization.
Buildings 15 01475 g006
Figure 7. Impact and likelihood of occurrence for all factors.
Figure 7. Impact and likelihood of occurrence for all factors.
Buildings 15 01475 g007
Figure 8. Structural model path diagram.
Figure 8. Structural model path diagram.
Buildings 15 01475 g008
Figure 9. Overall model fit.
Figure 9. Overall model fit.
Buildings 15 01475 g009
Table 1. Categorized factors and corresponding references.
Table 1. Categorized factors and corresponding references.
CategoryFactorReferences
MarketM1. Imbalance between the supply and demand of construction materials[12,15,20,21,22,23,24,25,26,27,28,29]
M2. Shortage of locally manufactured/available materials[14,15,22,25,30,31,32]
M3. Scarcity of raw materials [12,20,21,22,24,25,27,29,30]
M4. Low level of technology used for the production of materials[20,25,30,31]
LogisticsL1. Increase in transportation costs[12,15,16,21,22,23,24,25,26,27,29,30]
L2. Increase in fuel and energy costs[15,16,20,21,22,23,24,25,27,29,30,33]
L3. Inadequate infrastructure facilities [22,29,30,31,34]
Economic and RegulatoryE1. Increase in exchange rates[12,15,16,17,18,21,22,23,25,26,27,28,29,30,31,34]
E2. Increase in inflation rates [16,17,18,19,20,22,23,26,27,29,34,35,36,37]
E3. Force majeure [12,15,16,26,38]
E4. Increase in import duties[15,16,21,23,27,30]
E5. Changes in government policies and legislation[22,25,26,28,29,30,31]
E6. Government fiscal policy on interest rate[15,16,18,20,22,23,24,25,26,29,30,31,34,35]
E7. High running costs of suppliers[21,22,25,29,30]
Table 2. Characteristics of respondents.
Table 2. Characteristics of respondents.
Characteristics of Respondent
Total Number of Respondents 195
Counts% of TotalCumulative %
Organization
Client7036%36%
Consultant3518%54%
Contractor5729%83%
Subcontractor105%88%
Supplier2111%99%
Other21%100%
Position
Department Manager2312%12%
Executive Manager137%18%
Project Manager2814%33%
Quantity Surveyor2814%47%
Senior Engineer4925%72%
Engineer or Supervisor3317%89%
Other2111%100%
Years of Experience
Less than or Equal to 5126%6%
(6–10)2814%21%
(11–15)5528%49%
(16–20)3216%65%
(21–25)3518%83%
More than 253317%100%
Area of Expertise
Project Management4624%24%
Engineering and Design116%29%
Contracts & Procurement5528%57%
Project Control2814%72%
Quality Control179%81%
Construction Supervision2010%91%
Site Execution105%96%
Other84%100%
Specialization
Building Construction4825%25%
Industrial facilities116%30%
Infrastructure7941%71%
Utilities 4624%94%
Other116%100%
Table 3. Respondents’ ratings of Market factors.
Table 3. Respondents’ ratings of Market factors.
LikelihoodPotential Impact
CodeUNSLMLLVLVLLMHVH
M.11.90%8.20%44.40%25.10%20.30%0.50%2.90%36.20%32.40%28.00%
M.21.00%18.80%28.50%34.80%16.90%0.50%5.30%34.30%37.20%22.70%
M.33.40%16.90%41.10%24.20%14.50%1.00%4.30%31.40%42.50%20.80%
M.43.90%20.80%39.10%25.10%11.10%2.90%13.50%42.50%28.00%13.00%
Table 4. Respondents’ ratings of Logistics factors.
Table 4. Respondents’ ratings of Logistics factors.
LikelihoodPotential Impact
CodeUNSLMLLVLVLLMHVH
L.11.00%9.20%44.40%29.00%16.40%1.00%7.70%32.90%40.10%18.40%
L.22.40%13.00%46.40%26.10%12.10%2.40%12.10%38.60%31.90%15.00%
L.321.8%33.80%30.90%13.50%7.70%9.20%32.40%40.10%18.40%9.20%
Table 5. Respondents’ ratings of Economic and Regulatory factors.
Table 5. Respondents’ ratings of Economic and Regulatory factors.
LikelihoodPotential Impact
CodeUNSLMLLVLVLLMHVH
E.118.40%13.00%37.20%26.60%4.80%15.00%10.60%30.00%33.80%10.60%
E.23.40%11.60%47.80%25.60%11.60%2.90%10.60%31.90%37.20%17.40%
E.313.50%35.70%29.50%13.50%7.70%4.30%11.60%29.00%32.40%22.70%
E.45.30%18.80%45.40%22.20%8.20%3.90%15.90%32.90%33.80%13.50%
E.55.30%20.80%45.90%22.20%5.80%3.90%13.00%32.90%38.60%11.60%
E.66.30%15.90%49.80%23.20%4.80%5.80%13.00%34.80%38.20%8.20%
E.71.00%14.50%41.10%31.90%11.60%1.40%7.70%35.70%36.20%18.80%
Table 6. Impact by category.
Table 6. Impact by category.
Potential Impact
CategoryVLLMHVH
Market1.00%6.80%43.50%37.20%11.60%
Logistics1.40%6.30%37.20%44.90%10.10%
Economic & Regulatory1.40%10.10%33.80%37.20%17.40%
Table 7. Skewness and kurtosis of factors.
Table 7. Skewness and kurtosis of factors.
FactorSkewnessKurtosis
M1−0.154−0.301
M2−0.075−0.8
M3−0.105−0.32
M4−0.006−0.346
L1−0.172−0.253
L2−0.073−0.22
L30.353−0.253
E1−0.389−0.8
E2−0.2570.017
E3−0.025−0.065
E4−0.18−0.15
E5−0.3050.054
E6−0.5260.197
E7−0.165−0.303
MI−0.1−0.034
LI−0.4440.408
EI−0.32−0.373
Table 8. Factor loadings and critical ratios.
Table 8. Factor loadings and critical ratios.
ConstructFactorOuter LoadingStandard Error95%CICritical Ratio
MarketM10.841 0.026 0.785 0.886 32.8
M20.849 0.023 0.801 0.891 37.3
M30.788 0.038 0.703 0.853 21
M40.636 0.066 0.486 0.743 10
LogisticsL10.859 0.024 0.806 0.901 36
L20.868 0.024 0.814 0.91 35.7
L30.691 0.058 0.553 0.785 12
Economic and RegulatoryE10.704 0.045 0.606 0.783 16
E20.648 0.059 0.52 0.752 11
E30.592 0.068 0.444 0.71 9
E40.788 0.038 0.703 0.854 20.5
E50.748 0.035 0.673 0.811 21
E60.833 0.026 0.778 0.878 32
E70.688 0.049 0.579 0.773 14
Construction Material PriceMI0.804 0.033 0.727 0.86 -
LI0.88 0.019 0.838 0.913 -
EI0.749 0.04 0.66 0.817 -
Table 9. Convergent reliability.
Table 9. Convergent reliability.
VariableComposite Reliability (Rho)Cronbach’s AlphaProportion of Variance Explained (PVE)
Market0.860.780.61
Logistics0.850.730.66
Economic0.880.840.52
CMP0.850.740.66
Table 10. Factors’ cross-loadings.
Table 10. Factors’ cross-loadings.
FactorMarketLogisticsEconomicCMP
M10.8410.3280.2780.278
M20.8490.4570.2800.177
M30.7880.4740.3090.297
M40.6360.4380.4830.269
L10.4820.8590.4970.397
L20.4400.8680.5370.495
L30.3770.6910.5480.389
E10.1870.4380.7040.448
E20.3690.4860.6480.427
E30.2590.3750.5920.248
E40.2290.4530.7880.416
E50.2600.4520.7480.485
E60.2560.4460.8330.509
E70.5520.5970.6880.521
MI0.4220.4670.4790.804
LI0.3060.5080.5130.880
EI0.0390.3020.5160.749
Table 11. Path coefficient and VIF values.
Table 11. Path coefficient and VIF values.
Path(β)SE95% CIt-ValueVIFSignificance
Market → CMP0.0070.071−0.1320.1410.099 *1.4Not Significant
Logistics → CMP0.220.0960.020.42.292 *2.0Significant
Economic → CMP0.4730.0790.3190.6295.987 *1.74Significant
* p < 0.05.
Table 12. Overall normalized effect and ranks of the factors.
Table 12. Overall normalized effect and ranks of the factors.
CodeFactorOverall Effect WeightOverall Rank
E6Government fiscal policy on interest rate0.13501
E4Increase in import duties0.12772
E5Changes in government policies and legislation0.12123
E1Increase in exchange rates0.11424
E7High running costs of suppliers0.11165
E2Increase in inflation rates 0.10516
E3Force majeure0.09597
L2Increase in fuel and energy costs0.06548
L1Increase in transportation costs0.06479
L3Inadequate infrastructure facilities0.052110
M2Shortage of locally manufactured/available materials0.001911
M1Imbalance between the supply and demand of construction materials0.001912
M3Scarcity of raw materials0.001813
M4Low level of technology used for the production of materials0.001414
Table 13. Overall model goodness of fit.
Table 13. Overall model goodness of fit.
MeasureCriteriaResultComments
FIT≥0.500.497Good
AFIT≥0.500.491Good
GFI≥0.900.956Excellent
SRMR≤0.080.088Good
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Gunduz, M.; Naji, K.K.; Al-Marri, H. Factors Driving Construction Material Price Volatility in Qatar’s Construction Industry: An Investigation Using Generalized Structured Component Analysis (GSCA). Buildings 2025, 15, 1475. https://doi.org/10.3390/buildings15091475

AMA Style

Gunduz M, Naji KK, Al-Marri H. Factors Driving Construction Material Price Volatility in Qatar’s Construction Industry: An Investigation Using Generalized Structured Component Analysis (GSCA). Buildings. 2025; 15(9):1475. https://doi.org/10.3390/buildings15091475

Chicago/Turabian Style

Gunduz, Murat, Khalid K. Naji, and Hadi Al-Marri. 2025. "Factors Driving Construction Material Price Volatility in Qatar’s Construction Industry: An Investigation Using Generalized Structured Component Analysis (GSCA)" Buildings 15, no. 9: 1475. https://doi.org/10.3390/buildings15091475

APA Style

Gunduz, M., Naji, K. K., & Al-Marri, H. (2025). Factors Driving Construction Material Price Volatility in Qatar’s Construction Industry: An Investigation Using Generalized Structured Component Analysis (GSCA). Buildings, 15(9), 1475. https://doi.org/10.3390/buildings15091475

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop