Study on the Governance of Opportunistic Behavior by Contractors in Subway Construction Based on SEM-SD
Abstract
1. Introduction
2. Literature Review
2.1. Opportunistic Behavior
2.1.1. Opportunistic Behavior by Contractors
2.1.2. Client Opportunistic Behaviour
2.2. Study on Opportunistic Governance in Subway Construction
2.3. Dynamic Governance
3. Theoretical Background
3.1. Accident Case Statistics
- (1)
- Due to inadequate pre-construction surveys and lax construction management, identified cable risks were not incorporated into effective control measures. Under schedule pressure, field operations ultimately resulted in damage to four cables. Specific opportunistic behaviors manifested as risky operations and reckless rushing to meet deadlines.
- (2)
- A fire broke out during the construction of a subway project. The investigation revealed that the cause of the fire was the use of substandard insulation materials in the cooling tower. The construction company procured materials of unknown quality without undergoing national standard testing, demonstrating opportunistic behavior involving cutting corners.
- (3)
- A secondary collapse occurred at a subway construction site, primarily due to management personnel lacking technical competence. Following the initial incident, they failed to implement immediate remedial measures, leading to the subsequent accident. The specific opportunistic behavior manifested as inadequate enforcement of technical management protocols.
3.2. Identification of Factors Influencing the Governance of Opportunistic Behavior by Contractors
- (1)
- Behavioral pressure refers to external or internal pressures faced by individuals or organizations that drive them to engage in opportunistic behavior as a means of coping with or alleviating these pressures.
- (2)
- Opportunity for opportunistic behavior refers to the chance for an individual or organization to engage in opportunistic actions within a specific context without being easily detected or deterred.
- (3)
- Behavioral rationalization refers to the process by which individuals or organizations provide justifications or excuses for opportunistic behavior, making their actions appear reasonable and justified.
4. Constructing SEM Model
4.1. Research Hypothesis
4.2. Questionnaire Design
- (1)
- Gender characteristics. Among the returned survey samples, the proportion of males was significantly higher than that of females. Specific data shows that males accounted for 92.521% of the total sample, while females constituted only 7.479%. The primary reason lies in the challenging conditions typical of subway construction sites. These include high noise levels, significant dust and particulate matter, and underground tunnel environments that are generally warmer and more humid than surface areas. Furthermore, subway construction involves physically demanding work with elevated risks, requiring substantial physical strength and stamina—areas where men are generally considered to have a comparative advantage.
- (2)
- Age Distribution. Overall, the age distribution of subway construction workers exhibits distinct characteristics. Over 60% of respondents fall within the 25 to 45 age bracket, while conversely, those under 25 account for only 10.803% of the total sample. This reflects the industry’s specific employment patterns, where younger workers are relatively scarce and the age distribution skews toward middle age.
- (3)
- Educational Background Distribution. Among the survey participants, those with vocational high school, senior high school, or junior college degrees constituted the largest group, accounting for over 67% of respondents. Bachelor’s degree holders represented 27.701%, while postgraduate degree holders and above comprised 4.709%. All respondents possessed a certain level of education, ensuring the reliability of the questionnaire survey results.
- (4)
- Years of Experience Distribution. The vast majority of respondents had over five years of experience, with the highest proportion (34.626%) having 10 to 14 years of experience, while those with over 15 years of experience accounted for 25.208%. The survey findings indicate that personnel from the surveyed subway project contractors generally possess extensive work experience. This discovery provides valuable reference information for this study. It implies that they have considerable understanding and accumulated experience in subway project construction, thereby lending credibility and representativeness to their views and attitudes regarding the governance of opportunistic behavior.
- (5)
- Job Position Distribution. 54.294% of respondents were managers, while 45.706% were frontline workers. The survey results demonstrate a balanced distribution of job positions, making them more likely to reflect the opinions and perspectives of the entire construction contractor, thereby enhancing their representativeness.
4.2.1. Reliability Test and Validity Tests
4.2.2. Exploratory Factor Analysis
4.2.3. Confirmatory Factor Analysis
4.2.4. Discrimination Validity Analysis
4.3. Structural Equation Modeling Analysis
4.3.1. Modeling and Goodness-of-Fit Tests
4.3.2. SEM Model-Based Governance Pathway Identification
5. Case Studies Based on System Dynamics Models
5.1. Case Background
5.2. Predicting Governance Levels Based on the SEM-SD Model
- Case1: F1; F6; F3; F4; Interaction Governance.
- Case2: F2; F6; F3; F4 Interaction Governance.
- Case3: F6; F3; F4 Interaction Governance.
- Case4: F5; F4 Interaction Governance.
- Case5: F3; F4 Interaction Governance.
5.3. Critical Path Governance
- (1)
- External oversight mechanisms have failed to effectively constrain internal controls within the construction organization.
- (2)
- Internal control over the construction organization failed to effectively enhance project governance quality.
- (3)
- The quality of project governance has failed to bring about a substantial improvement in the level of construction process management.
- (4)
- The effectiveness of construction process management in addressing opportunistic behavior has not been optimized.
5.4. Governance Strategy
- (1)
- Enhance public oversight.
- (2)
- Enhance the risk management and prevention system.
- (3)
- Strengthen communication mechanisms and improve the assessment system.
- (4)
- Increase the frequency of on-site inspection rounds.
6. Results and Discussion
6.1. Theoretical Contributions
6.2. Comparison of Research Findings with Existing Studies
7. Conclusions
Author Contributions
Funding
Institutional Review Board Statement
Informed Consent Statement
Data Availability Statement
Conflicts of Interest
References
- Xu, W.; Lin, L.; Zhu, N.; Zhao, Y.; Yang, H.; Mei, Y.; Zhou, D. Three-Dimensional Numerical Analyses of a Monitored Deep Excavation Pit: A Case Study in the Guangzhou Metro. Buildings 2025, 15, 4018. [Google Scholar] [CrossRef]
- Huo, X.; Du, S.; Jiao, L. Critical Causal Path Analysis of Subway Construction Safety Accidents Based on Text Mining. ASCE-ASME J. Risk Uncertain. Eng. Syst. Part A Civ. Eng. 2025, 11, 04024075. [Google Scholar] [CrossRef]
- Williamson, O.E. Transaction cost economics. J. Econ. Behav. Organ. 1987, 8, 617–625. [Google Scholar] [CrossRef]
- Wen, Y.; Huang, D.; Cao, Z. Study on the Identification of Opportunistic Behavior of Subway Project Construction Enterprises. Buildings 2024, 14, 2297. [Google Scholar] [CrossRef]
- Yung, K.; Askarzadeh, A. International evidence on the relationship between fraud tolerance and stock price crash risk. Int. Rev. Financ. Anal. 2025, 97, 103853. [Google Scholar] [CrossRef]
- Ibrahim, C.K.I.C.; Manu, P.; Belayutham, S.; Cheung, C.; Mohammad, M.Z.; Yunusa-Kaltungo, A.; Ismail, S.; Samsudin, N.S.; Prabhakaran, A.; Perez, P.; et al. Tripartite collaboration for design for safety in construction: A co-creation framework integrating academia, industry, and government. Saf. Sci. 2026, 194, 107040. [Google Scholar] [CrossRef]
- Han, W.; Yin, Y. Influence of Project Governance on Opportunistic Behavior: Taking a Dynamic Perspective. Buildings 2022, 12, 1659. [Google Scholar] [CrossRef]
- Liu, D.; Xu, W.; Li, H.; Zhang, W.; Wang, W. Moral hazard and adverse selection in Chinese construction tender market: A case of Wenchuan earthquake. Disaster Prev. Manag. Int. J. 2011, 20, 363–377. [Google Scholar] [CrossRef]
- Dai, D.; Gui, J.; Xue, L.; Zhang, H. A case study on the identification of opportunistic behaviors in a substitute construction unit. Manag. Case Stud. Rev. 2019, 12, 548–559. [Google Scholar]
- Li, Y.; Ning, Y. Mitigating Opportunistic Behaviors in Consulting Projects: Evidence from the Outsourced Architectural and Engineering Design. J. Constr. Eng. Manag. 2022, 148, 04022044. [Google Scholar] [CrossRef]
- Yan, L.; Pan, Y.; Chen, Y. Understanding the Double-Edged Sword Effect of Contract Flexibility on Contractor’s Opportunistic Behavior in Construction Project: Moderating Role of BIM Application Degree. J. Constr. Eng. Manag. 2024, 150, 04024124. [Google Scholar] [CrossRef]
- Shang, T.; Ye, K.; Wu, L.; Shang, J. Opportunism or symbiosis? A case study on contractors’ unsustainable highway construction in China. Resour. Conserv. Recycl. Adv. 2022, 14, 200082. [Google Scholar] [CrossRef]
- Bu, Z.; Liu, J.; Liu, J. The double-edged effect of social media in the collaborative governance of PPP projects from a value perception perspective. Sustain. Cities Soc. 2025, 128, 106468. [Google Scholar] [CrossRef]
- Yang, R.J.; Zou, P.X.W. Stakeholder-associated risks and their interactions in complex green building projects: A social network model. Build. Environ. 2014, 73, 208–222. [Google Scholar] [CrossRef]
- Eisenberg, M.A. The Structure of Corporation Law. Columbia Law Rev. 1989, 89, 1461. [Google Scholar] [CrossRef]
- Bagasi, O.; Nawari, N.O.; Alsaffar, A. BIM and AI in Early Design Stage: Advancing Architect–Client Communication. Buildings 2025, 15, 1977. [Google Scholar] [CrossRef]
- Alemayehu, K.T. Assessing Current Practices of Client Requirement Change Management in Building Construction Projects in Ethiopia. Adv. Civ. Eng. 2025, 2025, 6248206. [Google Scholar] [CrossRef]
- Yu, H.; Peng, Z.; Wu, Z.; He, Z.; Huang, C. Coupled analysis and simulation of safety risk in subway tunnel construction by shallow-buried excavation method based on system dynamics. J. Intell. Fuzzy Syst. Appl. Eng. Technol. 2025, 49, 495–511. [Google Scholar] [CrossRef]
- Luo, Z.; Guo, J.; Han, J.; Wang, Y. Research on the construction safety risk assessment of prefabricated subway stations in China. Eng. Constr. Archit. Manag. 2024, 31, 1751–1787. [Google Scholar] [CrossRef]
- Liu, R.; Neisch, P.M. Micro-level walkability and station-level transit use: Integrating perceptual and spatial measures in Guiyang, China. Sustain. Cities Soc. 2025, 131, 106775. [Google Scholar] [CrossRef]
- Alsehaimi, A.; Baarimah, A.O.; Ramu, M.B.; Alajmi, M.; Ahmed, W. Integration of BIM in project management phases for achieving sustainable success in small construction projects: A SEM-based approach. Ain Shams Eng. J. 2025, 16, 103649. [Google Scholar] [CrossRef]
- Zhan, Z.; Wu, J.; Xia, P.; Hu, Y. Toward Low-Carbon and Cost-Efficient Prefabrication: Integrating Structural Equation Modeling and System Dynamics. Sustainability 2025, 17, 8307. [Google Scholar] [CrossRef]
- Gao, Y.; Gao, P.; Yu, N.; Sun, J.; Gao, Z.; Li, T.; Wang, J. Research on the Development Path of Green Buildings based on the Integrated Model of Structural Equation and System Dynamics. Sci. J. Econ. Manag. Res. 2025, 7, 144–151. [Google Scholar] [CrossRef]
- Shi, X.; Gu, Z.; Opoku, A.; Yuan, Z.; Qiao, Y. System dynamics modeling of life cycle energy-saving and CO2 emissions-reducing design scheme for prefabricated building envelope. Energy Build. 2025, 342, 115911. [Google Scholar] [CrossRef]
- Albrecht, W.S.; Albrecht, C.; Albrecht, C.C. Current Trends in Fraud and its Detection. Inf. Secur. J. A Glob. Perspect. 2008, 17, 2–12. [Google Scholar] [CrossRef]
- Dai, G. Research on Identifying and Addressing Opportunistic Behavior in Construction Project Transactions. Master’s Thesis, Nanjing Southeast University, Nanjing, China, 2022. (In Chinese). [Google Scholar]
- Innes, J.E. Information in Communicative Planning. J. Am. Plan. Assoc. 1998, 64, 52–63. [Google Scholar] [CrossRef]
- Zhou, Z.; Zhuo, W.; Cui, J.; Luan, H.; Chen, Y.; Lin, D. Developing a deep reinforcement learning model for safety risk prediction at subway construction sites. Reliab. Eng. Syst. Saf. 2025, 257, 110885. [Google Scholar] [CrossRef]
- Tam, N.T.; Hadikusumo, B.H. Modelling of trust and working relationship in construction project management: A case study of Vietnam. Int. J. Proj. Organ. Manag. 2016, 8, 366. [Google Scholar] [CrossRef]
- Pyle, W. Contractual Disputes and the Channels for Interfirm Communication. J. Law Econ. Organ. 2005, 21, 547–575. [Google Scholar] [CrossRef]
- Bekkers, V.; Edwards, A.; de Kool, D. Social media monitoring: Responsive governance in the shadow of surveillance? Gov. Inf. Q. 2013, 30, 335–342. [Google Scholar] [CrossRef]
- Sharafat, A.; Latif, K.; Seo, J. Risk analysis of TBM tunneling projects based on generic bow-tie risk analysis approach in difficult ground conditions. Tunn. Undergr. Space Technol. 2021, 111, 103860. [Google Scholar] [CrossRef]
- Zhu, Y.T. A Study on Bid Rigging Issues and Their Legal Regulation in the Bidding Process. Master’s Thesis, Lanzhou University, Lanzhou, China, 2016. (In Chinese). [Google Scholar]
- Fu, C. An Analysis of the Contract of the Owners and the Contractor in Engineering Project. Soft Sci. 2009, 23, 51–53. [Google Scholar]
- Jezzini, Y.; Assaad, R.H.; El-Adaway, I.H. Risk Allocation Model for Price Escalations in Construction Projects: Integrating Bargaining Game Theory and Probabilistic Bayesian Modeling. J. Constr. Eng. Manag. 2025, 151, 04025134. [Google Scholar] [CrossRef]
- Co, M.F.J.; Saeb, A.; Danuri, M.S.M.; Mohamed, O.; Zakaria, N. A Mechanism for Dispute Resolution in the Iranian Construction Industry. J. Constr. Dev. Ctries. 2021, 26, 205–226. [Google Scholar] [CrossRef]
- Jang, Y.; Son, J.; Yi, J.-S. Classifying the Level of Bid Price Volatility Based on Machine Learning with Parameters from Bid Documents as Risk Factors. Sustainability 2021, 13, 3886. [Google Scholar] [CrossRef]
- Luo, J. An evolutionary game analysis of the prefabricated building supply side under dynamic government reward and punishment mechanisms. J. Comput. Methods Sci. Eng. 2024, 24, 4004–4018. [Google Scholar] [CrossRef]
- Zhang, P. A Study on the Mechanism of the Impact of Project Manager’s Moral Risk on Project Success. Ph.D. Thesis, Dalian University of Technology, Dalian, China, 2016. (In Chinese). [Google Scholar]
- Han, Y.; Fang, X.; Zhao, X.; Wang, L. Exploring the impact of incentive policy on the development of prefabricated buildings: A scenario-based system dynamics model. Eng. Constr. Archit. Manag. 2024, 31, 4697–4725. [Google Scholar] [CrossRef]
- Cherkos, F.D.; Asfaw, F.A. Exploring the Interplay between Risk Management and Construction Risks: Implications for Project Performance through Structural Equation Modeling. J. Leg. Aff. Disput. Resolut. Eng. Constr. 2025, 17, 04525012. [Google Scholar] [CrossRef]
- Graafland, J.J. Collusion, reputation damage and interest in codes of conduct: The case of a Dutch construction company. Bus. Ethics A Eur. Rev. 2010, 13, 127–142. [Google Scholar] [CrossRef]
- Hwang, J.; Kim, J.; Yoon, S. DT-BEMS: Digital twin-enabled building energy management system for information fusion and energy efficiency. Energy 2025, 326, 136162. [Google Scholar] [CrossRef]
- Zou, P.X.; Lun, P.; Cipolla, D.; Mohamed, S. Cloud-based safety information and communication system in infrastructure construction. Saf. Sci. 2017, 98, 50–69. [Google Scholar] [CrossRef]
- Mavi, R.K.; Standing, C. Critical success factors of sustainable project management in construction: A fuzzy DEMATEL-ANP approach. J. Clean. Prod. 2018, 194, 751–765. [Google Scholar] [CrossRef]
- Luo, Y.; Chen, Y. How does contractual governance affect construction project performance? The mediating role of the contractor’s behavior. J. Asian Archit. Build. Eng. 2025, 24, 3879–3897. [Google Scholar] [CrossRef]
- Arvikar, S.; Aung, P.P.W.; Cha, G.; Park, S. Augmented Reality-based construction site management using optimized BIM and project schedule integration. Autom. Constr. 2025, 175, 106204. [Google Scholar] [CrossRef]








| Causes | Literature Support |
|---|---|
| Environmental (industry, social) factors | Soundness of the legal system [29] |
| Trade associations play a regulatory role [30] | |
| Public and Media Monitoring [31] | |
| Insufficient construction experience [32] | |
| Institutional factors | Project reporting relief system [33] |
| Accountability mechanisms [34] | |
| Risk-sharing mechanisms [35] | |
| Dispute resolution mechanism [36] | |
| Reasonable tender prices [37] | |
| Regulatory factors | Punishment mechanism [38] |
| Reasonableness of appraisal frequency [39] | |
| Construction site inspection [19] | |
| Reasonable incentive system [40] | |
| Risk Management [41] | |
| Subject factors | Professional ethics training system [39] |
| Mental behavior [42] | |
| Integrated management [43] | |
| Adoption of the Project Information Communication System (PICS) [44] |
| Factors | Factors | ||
|---|---|---|---|
| S1 | Industry system and laws, and regulations | S6 | Transparency in information sharing |
| S2 | Economic environment and competitive situation | S7 | Culture of integrity: code of ethics |
| S3 | Public opinion survey and public opinion monitoring | S8 | Incentive and assessment mechanisms |
| S4 | Project design and contract management | S9 | Risk management |
| S5 | Project quality control | S10 | Technical and managerial level |
| Preliminary Classification | Dimension | Factors |
|---|---|---|
| Industry, degree of market regulation | F1 Degree of industry regulation | S1 |
| S2 | ||
| Public opinion monitoring | F2 External oversight mechanisms | S3 |
| Project governance | F3 Quality of project governance | S4 |
| S6 | ||
| S8 | ||
| Construction project implementation management | F4 Construction process management | S5 |
| S10 | ||
| F5 Constructor credit evaluation system | S7 | |
| F6 Internal control of the construction organization | S9 |
| Variant | Categories | Number | Percentage (%) |
|---|---|---|---|
| Gender | Male | 334 | 92.521 |
| Female | 27 | 7.479 | |
| Age | 1–25 | 39 | 10.803 |
| 26–36 | 120 | 33.241 | |
| 37–45 | 122 | 33.795 | |
| >46 | 80 | 22.161 | |
| Educational level | Secondary or high school | 105 | 29.086 |
| Three-year college | 139 | 38.504 | |
| Undergraduate | 100 | 27.701 | |
| Graduate students and above | 17 | 4.709 | |
| Years in current position | 1–4 | 79 | 21.884 |
| 5–9 | 66 | 18.283 | |
| 10–14 | 125 | 34.626 | |
| >15 | 91 | 25.208 | |
| Position | Managerial staff | 196 | 54.294 |
| Elementary worker | 165 | 45.706 |
| Cronbach’s α | Standardized Cronbach’s α | Item | Sample |
|---|---|---|---|
| 0.924 | 0.924 | 27 | 361 |
| KMO | 0.906 | |
|---|---|---|
| Bartlett’s test of sphericity | approximate chi-square | 5408.299 |
| df | 496 | |
| p | 0.000 *** | |
| Title | Rotational Forward Difference Resolution | Rotation Variance Interpretation Rate | ||||
|---|---|---|---|---|---|---|
| Eigenroot | Variance Explained (%) | Cumulative Variance Explained (%) | Eigenroot | Variance Explained (%) | Cumulative Variance Explained (%) | |
| 1 | 9.071 | 33.596 | 33.596 | 386.043 | 14.298 | 14.298 |
| 2 | 2.325 | 8.613 | 42.209 | 330.369 | 12.236 | 26.534 |
| 3 | 1.899 | 7.032 | 49.241 | 325.33 | 12.049 | 38.583 |
| 4 | 1.828 | 6.77 | 56.011 | 282.118 | 10.449 | 49.032 |
| 5 | 1.532 | 5.674 | 61.684 | 269.014 | 9.963 | 58.995 |
| 6 | 1.369 | 5.071 | 66.755 | 209.521 | 7.76 | 66.755 |
| 7 | 0.634 | 2.349 | 69.105 | |||
| 8 | 0.611 | 2.263 | 71.368 | |||
| 9 | 0.589 | 2.183 | 73.551 | |||
| 10 | 0.537 | 1.99 | 75.541 | |||
| 11 | 0.53 | 1.961 | 77.502 | |||
| 12 | 0.52 | 1.925 | 79.427 | |||
| 13 | 0.514 | 1.903 | 81.33 | |||
| 14 | 0.486 | 1.799 | 83.129 | |||
| 15 | 0.461 | 1.707 | 84.836 | |||
| 16 | 0.425 | 1.575 | 86.411 | |||
| 17 | 0.418 | 1.549 | 87.96 | |||
| 18 | 0.385 | 1.425 | 89.385 | |||
| 19 | 0.371 | 1.373 | 90.758 | |||
| 20 | 0.359 | 1.328 | 92.086 | |||
| 21 | 0.349 | 1.294 | 93.381 | |||
| 22 | 0.335 | 1.239 | 94.62 | |||
| 23 | 0.309 | 1.144 | 95.764 | |||
| 24 | 0.304 | 1.127 | 96.891 | |||
| 25 | 0.302 | 1.118 | 98.009 | |||
| 26 | 0.278 | 1.029 | 99.038 | |||
| 27 | 0.26 | 0.962 | 100 | |||
| Variable | Title | Variable | |||||
|---|---|---|---|---|---|---|---|
| Factor 1 | Factor 1 | Factor 1 | Factor 1 | Factor 1 | Factor 1 | ||
| F1 | a1 | 0.142 | 0.759 | 0.098 | 0.117 | 0.169 | 0.094 |
| a2 | 0.102 | 0.745 | 0.141 | 0.121 | 0.210 | 0.047 | |
| a3 | 0.114 | 0.760 | 0.143 | 0.086 | 0.121 | 0.179 | |
| a4 | 0.097 | 0.773 | 0.158 | 0.211 | 0.074 | 0.056 | |
| a5 | 0.154 | 0.734 | 0.141 | 0.118 | 0.114 | 0.089 | |
| F2 | a6 | 0.154 | 0.137 | 0.185 | 0.193 | 0.112 | 0.747 |
| a7 | 0.116 | 0.102 | 0.147 | 0.184 | 0.103 | 0.791 | |
| a8 | 0.149 | 0.146 | 0.106 | 0.105 | 0.116 | 0.782 | |
| F3 | a9 | 0.731 | 0.133 | 0.161 | 0.175 | 0.075 | 0.038 |
| a10 | 0.720 | 0.050 | 0.149 | 0.075 | 0.208 | 0.138 | |
| a11 | 0.767 | 0.131 | 0.098 | 0.080 | 0.192 | 0.168 | |
| a12 | 0.759 | 0.043 | 0.142 | 0.137 | 0.222 | 0.026 | |
| a13 | 0.786 | 0.153 | 0.121 | 0.099 | 0.039 | 0.139 | |
| a14 | 0.765 | 0.150 | 0.121 | 0.072 | 0.024 | 0.047 | |
| F4 | a15 | 0.135 | 0.190 | 0.751 | 0.118 | 0.092 | 0.136 |
| a16 | 0.176 | 0.115 | 0.760 | 0.204 | 0.108 | 0.041 | |
| a17 | 0.194 | 0.187 | 0.755 | 0.055 | 0.223 | 0.081 | |
| a18 | 0.155 | 0.117 | 0.740 | 0.107 | 0.159 | 0.088 | |
| a19 | 0.100 | 0.099 | 0.725 | 0.083 | 0.142 | 0.175 | |
| F5 | a20 | 0.198 | 0.172 | 0.165 | 0.156 | 0.744 | 0.109 |
| a21 | 0.17 | 0.186 | 0.184 | 0.051 | 0.751 | 0.073 | |
| a22 | 0.124 | 0.129 | 0.223 | 0.162 | 0.736 | 0.085 | |
| a23 | 0.152 | 0.182 | 0.113 | 0.170 | 0.750 | 0.121 | |
| F6 | a24 | 0.154 | 0.155 | 0.077 | 0.775 | 0.123 | 0.129 |
| a25 | 0.171 | 0.189 | 0.113 | 0.779 | 0.112 | 0.102 | |
| a26 | 0.104 | 0.098 | 0.147 | 0.792 | 0.188 | 0.158 | |
| a27 | 0.119 | 0.173 | 0.185 | 0.758 | 0.096 | 0.137 | |
| Latent Variable | Items | Unstd | Standardized Factor Loadings | p | AVE | CR |
|---|---|---|---|---|---|---|
| F1 | a1 | 1 | 0.756 | - | 0.561 | 0.865 |
| a2 | 0.998 | 0.747 | *** | |||
| a3 | 1.063 | 0.757 | *** | |||
| a4 | 1.045 | 0.765 | *** | |||
| a5 | 0.98 | 0.719 | *** | |||
| F2 | a6 | 1 | 0.755 | - | 0.547 | 0.783 |
| a7 | 1.019 | 0.758 | *** | |||
| a8 | 0.967 | 0.706 | *** | |||
| F3 | a9 | 1 | 0.726 | - | 0.565 | 0.886 |
| a10 | 0.964 | 0.727 | *** | |||
| a11 | 1.139 | 0.793 | *** | |||
| a12 | 1.07 | 0.763 | *** | |||
| a13 | 1.067 | 0.773 | *** | |||
| a14 | 0.99 | 0.718 | *** | |||
| F4 | a15 | 1 | 0.759 | - | 0.558 | 0.863 |
| a16 | 0.991 | 0.754 | *** | |||
| a17 | 1.067 | 0.803 | *** | |||
| a18 | 0.979 | 0.725 | *** | |||
| a19 | 0.925 | 0.700 | *** | |||
| F5 | a20 | 1 | 0.783 | - | 0.563 | 0.837 |
| a21 | 0.895 | 0.736 | *** | |||
| a22 | 0.91 | 0.728 | *** | |||
| a23 | 0.902 | 0.75 | *** | |||
| F6 | a24 | 1 | 0.756 | - | 0.599 | 0.857 |
| a25 | 1.032 | 0.781 | *** | |||
| a26 | 1.046 | 0.795 | *** | |||
| a27 | 1.003 | 0.764 | *** |
| Variant | F1 | F2 | F3 | F4 | F5 | F6 |
|---|---|---|---|---|---|---|
| F1 | 0.749 | |||||
| F2 | 0.36 | 0.740 | ||||
| F3 | 0.364 | 0.362 | 0.752 | |||
| F4 | 0.419 | 0.391 | 0.419 | 0.747 | ||
| F5 | 0.449 | 0.362 | 0.428 | 0.469 | 0.750 | |
| F6 | 0.418 | 0.425 | 0.373 | 0.388 | 0.414 | 0.774 |
| Fitness Index | χ2 | DF | p | χ2/DF | GFI | RMSEA | CFI | NFI | NNFI |
|---|---|---|---|---|---|---|---|---|---|
| Actual | - | - | >0.05 | <3 | >0.9 | <0.10 | >0.9 | >0.9 | >0.9 |
| Scope | 382.760 | 313.000 | 0.004 *** | 1.223 | 0.922 | 0.025 | 0.985 | 0.922 | 0.983 |
| Path Relationship | Non-Standardization Coefficient | Standardized Coefficient | S.E. | C.R. | p | Assumption | ||
|---|---|---|---|---|---|---|---|---|
| F1 | → | F5 | 0.627 | 0.552 | 0.073 | 8.571 | 0.000 *** | Support |
| F1 | → | F6 | 0.202 | 0.192 | 0.079 | 2.556 | 0.011 ** | Support |
| F5 | → | F6 | 0.135 | 0.092 | 0.098 | 1.380 | 0.168 | Not supported |
| F2 | → | F6 | 0.357 | 0.342 | 0.071 | 5.022 | 0.000 *** | Support |
| F1 | → | F3 | 0.287 | 0.291 | 0.066 | 4.322 | 0.000 *** | Support |
| F6 | → | F3 | 0.283 | 0.302 | 0.064 | 4.436 | 0.000 *** | Support |
| F1 | → | F4 | 0.166 | 0.165 | 0.077 | 2.159 | 0.031 ** | Support |
| F2 | → | F4 | 0.204 | 0.204 | 0.064 | 3.194 | 0.001 *** | Support |
| F5 | → | F4 | 0.262 | 0.296 | 0.060 | 4.358 | 0.000 *** | Support |
| F3 | → | F4 | 0.209 | 0.205 | 0.060 | 3.475 | 0.001 *** | Support |
| Impact Pathways | Direct Effect | Sequences | Indirect Effect | Sequences | Combined Effect | Sequences |
|---|---|---|---|---|---|---|
| F1 → G | 0.83 | 2 | 1.140 | 1 | 1.970 | 1 |
| F2 → G | 0.55 | 6 | 0.501 | 2 | 1.051 | 2 |
| F6 → G | 0.67 | 5 | 0.265 | 3 | 0.935 | 4 |
| F5 → G | 0.75 | 3 | 0.260 | 4 | 1.010 | 3 |
| F3 → G | 0.70 | 4 | 0.180 | 5 | 0.880 | 5 |
| F4 → G | 0.88 | 1 | 0.880 | 5 |
| Variant | R | Weights | R2 | SD Initial Value |
|---|---|---|---|---|
| Degree of industry regulation | 0.554 | |||
| a1 | 0.750 | 0.202 | 0.563 | 0.563 |
| a2 | 0.741 | 0.199 | 0.549 | 0.549 |
| a3 | 0.753 | 0.202 | 0.567 | 0.567 |
| a4 | 0.761 | 0.204 | 0.579 | 0.579 |
| a5 | 0.715 | 0.192 | 0.511 | 0.511 |
| External oversight mechanisms | 0.548 | |||
| a6 | 0.753 | 0.339 | 0.567 | 0.567 |
| a7 | 0.764 | 0.344 | 0.584 | 0.584 |
| a8 | 0.702 | 0.316 | 0.493 | 0.493 |
| Quality of project governance | 0.565 | |||
| a9 | 0.727 | 0.161 | 0.529 | 0.529 |
| a10 | 0.729 | 0.162 | 0.531 | 0.531 |
| a11 | 0.789 | 0.175 | 0.623 | 0.623 |
| a12 | 0.761 | 0.170 | 0.579 | 0.579 |
| a13 | 0.781 | 0.173 | 0.610 | 0.610 |
| a14 | 0.719 | 0.160 | 0.517 | 0.517 |
| Construction process management | 0.548 | |||
| a15 | 0.752 | 0.203 | 0.566 | 0.566 |
| a16 | 0.745 | 0.202 | 0.555 | 0.555 |
| a17 | 0.798 | 0.216 | 0.637 | 0.637 |
| a18 | 0.715 | 0.193 | 0.511 | 0.511 |
| a19 | 0.687 | 0.186 | 0.472 | 0.472 |
| Constructor credit evaluation system | 0.566 | |||
| a20 | 0.781 | 0.260 | 0.610 | 0.610 |
| a21 | 0.742 | 0.247 | 0.551 | 0.551 |
| a22 | 0.729 | 0.242 | 0.531 | 0.531 |
| a23 | 0.756 | 0.251 | 0.572 | 0.572 |
| Internal control of the construction organization | 0.598 | |||
| a24 | 0.756 | 0.245 | 0.572 | 0.572 |
| a25 | 0.783 | 0.253 | 0.613 | 0.613 |
| a26 | 0.792 | 0.256 | 0.627 | 0.627 |
| a27 | 0.761 | 0.246 | 0.579 | 0.579 |
| Variant | Variational Equation |
|---|---|
| State variable | |
| G | INTEG(rate of change; 10) |
| F1 | INTEG(rate of change; 0.561) |
| F2 | INTEG(rate of change; 0.548) |
| F3 | INTEG(rate of change; 0.563) |
| F4 | INTEG(rate of change; 0.559) |
| F5 | INTEG(rate of change; 0.562) |
| F6 | INTEG(rate of change; 0.599) |
| Fate variable | |
| Rate of change of G | (F1 × 0.830 + F2 × 0.550 + F3 × 0.700 + F4 × 0.880 + F5 × 0.750 + F6 × 0.670) × 0.010 |
| Rate of change of F1 | Strength of accountability × 0.340 |
| Rate of change of F2 | Strength of accountability × 0.204 |
| Rate of change of F3 | F6 × 0.302 + F1 × 0.291 |
| Rate of change of F4 | (F5 × 0.296 + F2 × 0.204 + F3 × 0.205F1 × 0.165) × 0.400 |
| Rate of change of F5 | F1 × 0.552 + Education and training × 0.730 |
| Rate of change of F6 | F2 × 0.342 + F1 × 0.192 + Education and training × 0.756 |
| Auxiliary variable | |
| Education and training | Frequency of opportunistic behavior × 0.003 |
| Strength of accountability | Frequency of opportunistic behavior × 0.003 |
| Frequency of opportunistic behavior | 100 − G × 0.730 |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2025 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
Wen, Y.; Zhang, C.; Cao, P.; Wang, Y. Study on the Governance of Opportunistic Behavior by Contractors in Subway Construction Based on SEM-SD. Buildings 2025, 15, 4249. https://doi.org/10.3390/buildings15234249
Wen Y, Zhang C, Cao P, Wang Y. Study on the Governance of Opportunistic Behavior by Contractors in Subway Construction Based on SEM-SD. Buildings. 2025; 15(23):4249. https://doi.org/10.3390/buildings15234249
Chicago/Turabian StyleWen, Yanfang, Chenyu Zhang, Ping Cao, and Yunhe Wang. 2025. "Study on the Governance of Opportunistic Behavior by Contractors in Subway Construction Based on SEM-SD" Buildings 15, no. 23: 4249. https://doi.org/10.3390/buildings15234249
APA StyleWen, Y., Zhang, C., Cao, P., & Wang, Y. (2025). Study on the Governance of Opportunistic Behavior by Contractors in Subway Construction Based on SEM-SD. Buildings, 15(23), 4249. https://doi.org/10.3390/buildings15234249

