1. Introduction
Retrofit in the UK is highly fragmented from the point of view of contractors. Usually, one contractor undertakes only one measure. Due to this reason, the homeowner needs to go to several contractors to get all the required retrofit measures installed. This is a hassle for the homeowner [
1,
2]. Professional institutions such as BSI or TrustMark recommend the whole-house approach to housing retrofit [
3,
4,
5]. Due to the fragmented nature of the retrofit market, it is difficult to drive the whole-house retrofit approach in a single iteration [
2]. In addition to the above, transaction costs (non-construction costs during the process) associated with the retrofit works are discouraging homeowners from engaging in retrofit due to the existing fragmented nature of the retrofit industry [
6]. If a single contractor is installing all the retrofit measures, they can save costs by sharing tools, equipment and services. For example, scaffolding for external wall insulation can be used to install solar panels on the roof. A proper stakeholder engagement model is required to drive housing retrofit, where all the parties can collaboratively achieve their objectives. The government, professional bodies, supply chains, and standards will work together for a synergistic outcome [
7].
Retrofitting houses needs to be initiated by the homeowners or the landlord. There are government grants available for housing retrofit such as HUG, SHDF or ECO. These government grants should deploy a necessary contract administration activity according to the government procurement guidelines [
8]. The scope of contract administration shall cover the activities related to the execution of a suitable contract document to allocate rights and obligations among the project parties [
9]. A total of 82.2% of the houses are owned by individual parties and these people are not expected to have a proper idea about contract administration in retrofit. This creates a situation of “moral hazard” [
10], where the principal (homeowner or landlord) employs a contractor (agent) to carry out a retrofit. Since the homeowner/landlord is not a technical person, they do not know whether the contractor would work in the best interest of the client or not.
As far as the retrofit standards are concerned, PAS 2030:2023 [
3] and PAS 2035:2023 [
5] can be considered as government-endorsed quality specifications. Apart from those, there are other standards such as the AECB Carbonlite standard [
11] and RICS residential retrofit standard [
12] in the UK context. The AECB standard is complementary to the PAS 2035. The RICS residential retrofit standard was published in March 2024 and is still new to the industry. Considering these factors as well as the government endorsement, PAS 2035 was considered as the key standard for this study.
As per the PAS 2030:2023 and PAS 2035:2023, these specifications do not cover the supply chain directly. The contractors are called installers. They can be designers as well. Installers are required to take care of the supply chain side [
3,
5]. As the retrofit supply chain is highly fragmented, there is no collaboration among the supply chain/contractors [
7,
13]. In this case, the project management approach proposed by PAS 2035:2023 plays a vital role in creating the required collaboration of the retrofit measures provided by various installers. This will remove the unintended consequences, poor design, shallow retrofit, performance gap, accountability, and defects prevailing in the retrofit industry [
5]. Each home counts report was commissioned by Dr. Peter Bonfield as a response to the failure of the Green Deal in 2013. The report made 27 recommendations to address the quality concerns of housing retrofit [
14]. PAS 2035 was published accordingly to bring the required quality of retrofit and to avoid unintended consequences. The whole idea is to protect the interests of both the houses and their occupants [
5]. Each Home Counts report recommends a single contract for every retrofit project. Neither the Each Home Counts report nor the PAS 2035 have proper recommendations about procurement or contract administration.
As far as the PAS 2035:2023 specification is further evaluated, there is a professional role called “Retrofit coordinator” to manage the whole retrofit project from start to end. The project delivery is the responsibility of the retrofit coordinator. A retrofit coordinator is an independent party who should ensure the best interest of the client and the public. Ideally, a retrofit coordinator is employed by the client directly or through an organisation to run retrofit assessment, design, installation, commissioning, monitoring, or evaluation. Any conflict of interest is to be declared by the retrofit coordinator [
5]. The client shall make direct contracts with the contractors and suppliers, coordinated by the retrofit coordinator. The retrofit coordinator is obliged to deliver the project without bias to any party, ensuring the proper commissioning of the retrofit project under PAS 2035:2023 specification [
5]. The role of the retrofit coordinator shall remove the “moral hazard” to a greater level.
The literature does not show significant journal articles related to contract administration in housing retrofit in the UK context. It seems that contract administration in housing retrofit is a poorly discussed topic. Even the PAS 2035:2023 specification is silent on contract administration. The RICS retrofit standard has identified this gap and suggested the role of a retrofit contract administrator. It has further discussed the contract administration in retrofit projects [
12]. The government policies related to contract administration in construction are described under “The Construction Playbook” [
8]. In line with the same, the Social Housing Retrofit Accelerator (SHRA) has published a toolkit for procurement in social housing retrofit. SHRA has recommended using a suitable contract form and given the flexibility to use either a custom contract or a standard form of contract. In the case of standard forms, they have recommended JCT (Joint Contract Tribunal) and NEC (New Engineering Contracts) [
15]. JCT forms of contract under the options of the design build, intermediate contracts with the contractor’s design portion, and measured term contracts were observed to have been successfully used in the industry [
16].
Considering the lack of academic publications and discussion, this article critically analyses the existing procurement routes and forms of contract in the UK housing retrofit industry with recommendations for industry best practices.
4. Results
4.1. Main Procurement Route in Housing Retrofit
As far as the existing contracts in the retrofit industry are concerned, two scenarios can be identified. One is how the large contractors procure subcontractors. The other is how the contractors enter into agreements with the clients. All seven large-scale contractors said they procure subcontractors through framework agreements. The situation is complicated when these contractors are engaged with the clients.
When the three small-scale contractors were concerned, they were providing single measures to the clients. Two contractors were engaged in loft conversions, extensions, and wall and loft insulations. The other contractor was mainly involved in installing doors, windows, decks, and conservatories. According to the findings, they have never used formal agreements, neither bespoke contracts nor standard forms of contract. When there is work, they will first issue a quotation. After the installation, they will issue an invoice to be paid. Depending on the circumstances, a guarantee is given considering the materials, components, and the nature of the work.
Four large-scale contractors provided integrated retrofit measures. Mainly, they focused on the able-to-pay sector. Some of them were engaged in government-funded projects as well. These contractors were reported to provide overall retrofit services from assessment to evaluation. One of them said that they use bespoke contracts to enter into agreements with the clients. The interviewees said they were happy about the particular bespoke contract as it clearly defined the scope of the work. The contract defines what services to provide, what level of performance is expected, and what the guarantees and the dispute resolution procedure are. One contractor said they use the JCT design and build contracts for contract administration. The other two interviewees said they usually use quotations and invoices like small-scale contractors. When there was a need for a contract, they used some other forms. Although one contractor did not use a contract for retrofit, they were using JCT design build contracts for their new-build housing projects.
There is a different situation observed with the large-scale contractors working with the government grant schemes. These three contractors were contracted by the managing agent of the government grant on behalf of the local authority. A framework agreement was used to procure these contractors. These three contractors provided only certain measures in the project. Two contractors were mainly involved in insulation measures, and the other contractor was involved with heat pump solutions. Two scenarios could be identified with these contractors.
Two contractors who worked for the Home Upgrade Grant installed insulation measures for properties owned by owner-occupiers and private landlords. The clients apply for funding from the local authority. Once approved, the retrofit measures were installed by the contractors. The Local Authority paid the invoices on behalf of the clients under the government grant. The clients received the guarantees and warranties from the contractor according to the conditions imposed by PAS 2035. From the point of contract administration, there was no direct form of contract executed between the subcontractor and the client. In the other scenario, the heat pump installer was installing heat pump solutions. They were MCS certified. Accordingly, they had a contract executed between the client and the company under MCS certification guidelines.
The interviewees generally stated that the design part of some retrofit measures cannot be separated from the installation part. The replacement nature of retrofit installations has discouraged the industry from thinking about procurement routes in housing retrofit. This situation is mainly applicable to single measures. When it comes to retrofit projects with several retrofit measures, mostly there is a designer involved. Two interviewees (supplying integrated measures) said they had in-house retrofit designers to design retrofit measures. Further, subcontractors were working with them to install these measures. They were procured under framework agreements.
In general, the retrofit industry is not as straightforward as the new-build industry. The contractors are observed to be comfortable without formal contracts. There are bespoke agreements observed under the design build procurement route in housing retrofit in the able-to-pay sector projects. According to one large-scale contractor, the traditional procurement route can also be noted in some of the cases with the able-to-pay sector, where the homeowner approaches a designer and construction aspects are handed over to another party. Even if there was a separate designer involved in the retrofit project, it was unlikely that the works would be carried out under a properly executed traditional contract.
Considering these aspects, it can be noted that the main type of procurement in housing retrofit is design build. Large-scale contractors employ a designer to design the retrofit project and employ several installers to install the measures. Mainly, the retrofit designers, assessors, and coordinators are in-house while the installers are subcontracted. As the homeowner is not involved in selecting the installers or designers, design build seems to be the most appropriate term, compared to management contracting.
4.2. The Main Form of Contract in Housing Retrofit
The four contractors who provided integrated retrofit services have focused on the able-to-pay sector. They were also involved in delivering projects under government grants. It was found that there were contracts executed between the homeowner and the contractor only in the able-to-pay sector where the homeowner paid for the retrofit. Apart from one contractor, these contracts were mainly bespoke contracts. The interviewees stated that they had seen JCT and Federation of Master Builders contracts on some occasions. One contractor who was involved in integrated retrofit services clearly said they use JCT design build contracts in all of the projects. They found that the use of a JCT design build contract properly allocates rights and obligations between the parties. Further, they wanted to reduce the potential disputes by using the JCT design to build a standard form of contract.
The three small-scale contractors had never used a formal contract, apart from the occasions they were procured by a main contractor under framework agreements. The reason for not using a formal contract was explained as the hesitation to enter into binding legal contracts with the clients. They see entering into formal contracts as an unnecessary commitment. Furthermore, they did not have the skills and resources to provide these administrative services. One small-scale contractor said that, although there are no formal contracts, they provide an invoice which creates obligations for them to ensure the performance of the installation. One of the large-scale contractor representatives said the small-scale contractors do whatever possible to avoid entering into formal agreements. He further said small-scale contractors do not realise the benefits and protections available with standard forms of contract.
When it comes to retrofit projects under government grants, there were no contracts executed between the homeowners and the contractors. There are warranties, guarantees, and certifications provided as a part of the service delivery. In the case of social housing, there were bespoke contracts executed between the social landlord and the managing agent. The managing agent used a framework agreement to procure retrofit installers. The purpose of the framework agreement is to work with a pre-selected set of installers and to reduce the hassle and time involved with the formal tendering process. Small-scale housing retrofit installers work with the homeowners directly or they work under framework agreements with larger organisations. In any case, they only provide quotations and invoices to the homeowners. None of the small-scale contractors in the sample had ever used a formal contract with homeowners for their work.
Considering the scenario, the only standard form of contract used by any of these contractors was a JCT Design Build or MCS prescribed contract for heat pump installation. Apart from this, the other three large-scale contractors used bespoke contracts. They agreed that the enforceability of these contracts was unknown as they had never been faced with a legal dispute at the litigation level.
4.3. Problems Associated with Existing Contracts
None of the interviewees answered this question properly. They did not have a proper idea about the nature of the issues involved with the existing contracts. None of the small-scale or large-scale contractors had faced a contractual dispute which escalated into arbitration or litigation. (The literature was also not helpful in finding contractual disputes in housing retrofit). When the small-scale contractors were asked why they did not need a contract, they all said there was nothing wrong with their existing practice. One contractor said none of the private clients had asked them for a contract. He further said,
“When everyone is happy with the way things are happening, why do we make our lives harder by bringing contracts?”
All the small-scale contractors agreed that they provide a satisfactory guarantee of their work to the client. They agreed that there were some defects in their work and there were some disputes sometimes. They had managed these disputes mutually without them being escalated to higher levels. On the other hand, these disputes were minor and there was no scope for lengthy and expensive arbitration procedures.
Another small-scale contractor highlighted the shortage of skills and resources required to draft, review, and execute contracts. As they cannot do these by themselves, they have to get support from a third party for contract administration. This increases the project cost. From one point of view, the clients are not asking for contracts. From another point of view, it will increase the project cost and diminish their competitive advantage. All these factors lead to one conclusion for them: no formal contracts are required.
When it comes to interviews with large-scale contractors, they usually need two contracts as discussed before. One is with the subcontractors. Almost all the subcontractor agreements were identified as framework agreements in the sample of seven large-scale contractors. Under the framework agreements, the subcontractors needed to give a defect notification period as agreed with the main contractor. For the purpose of this research, the question was about the contractual disputes with the homeowners/landlords in housing retrofit, not with the subcontractors.
The large-scale contractors had the experience of executing contracts with either the able-to-pay clients or social housing landlords. They also have not faced any extreme disputes that were escalated to arbitration or litigation levels. When they were asked about the problems associated with the existing bespoke contracts, they could not point out proper issues. One interviewee admitted that they do not have any idea about the performance levels of their bespoke contracts. Another interviewee (from the company that used JCT design build) said they have higher confidence about their contractual security as they have used a standard form of contract.
In general, it can be concluded that there are no considerable problems associated with the existing way of managing rights and obligations in housing retrofit without standard forms of contract. Further, a case law search was done to identify any housing retrofit disputes between contractors and clients. The search did not yield any substantial findings. It can be argued that the term “Retrofit” is relatively new and the contract administration was not an outstanding area of concern in housing retrofit so far.
4.4. Perceptions Towards Standard Forms of Contract
The four large-scale contractors (mainly provided services to the able-to-pay sector) had an overall positive idea about adopting standard forms of contract for the housing retrofit projects. However, they did not see a clear requirement to adopt standard forms of contract, as the existing bespoke contracts and other forms of correspondence with the homeowners were already doing the right job. The interviewee (from the company using JCT design build) had confidence in their legal protection and the allocation of responsibilities. The other large-scale contractors also expressed that it would be better to use a standard form of contract over their existing bespoke contracts. One interviewee was already determined to explore the standard forms of contract for their projects with the insights received from the interview. In general, the perception towards the use of standard forms of contract was positive with the large-scale contractor segment work in the able-to-pay sector.
The three large-scale contractors working with retrofit projects under government grants were indifferent to the use of standard forms of contract. One contractor said they did not need to have a contract with the owner-occupiers and private landlords as they were already in a framework contract with the council under the government grant. They acknowledged that they would consider adopting a proper standard form of contract if they happened to work with homeowners directly.
The small-scale contractors needed answers to the problems of how to manage the additional back office and the additional costs associated with using standard forms of contract for contract administration. They said that they would consider standard forms of contract when it became clear that the use of standard forms of contract was beneficial to them. The general perception towards the standard form of contract was slightly negative. One small-scale contractor said they preferred anything which limited their responsibility in the project. This was endorsed by a representative of a large-scale contractor.
“The small-scale installers will do anything not to have a contract, although having a contract is beneficial for both the parties” in his own words.
In conclusion, it was clear that none of the interviewees had focused on the contract administration aspects of the retrofit projects. Contract administration was not their favourite topic to talk about. In reality, they had bigger challenges in housing retrofit projects. For example, managing skilled workers or addressing technical challenges. Some of the interviewees understood the importance of proper contract administration in retrofit projects, despite the relatively lower project values of housing retrofit projects compared to civil or new-build construction projects. In conclusion, large-scale contractors had a relatively positive attitude towards standard forms of contract, while small-scale contractors were not interested.
5. Discussion
Retrofit work deals with both risk and construction processes. In this sense, there is no difference between retrofit and other construction projects from a contract administration point of view. As far as the JCT contracts are considered, there are suitable forms of contract for small-scale retrofit projects and larger projects. For example, JCT has homeowner contracts for housing renovations with or without a consultant [
31]. The retrofit coordinator works as a construction consultant who oversees the project delivery in the best interest of the client [
5].
When it comes to the UK government’s recommendations for procurement in construction projects, the construction playbook provides valuable insights [
8]. According to the construction playbook, the characteristics of procurement are emphasised under three topics: award method, responsibility for design, and responsibility for project management. The focus is related to tendering: open tendering or restricted tendering. The playbook further discusses framework agreements as they are commonly used to reduce procurement costs and keep prices low. Another important document for retrofit procurement is the guidance issued for social housing projects [
15]. According to this toolkit, there are five procurement routes. They are focused on the openness and restrictiveness of the tendering process for the contractors, but not the allocation of responsibilities to the project parties. For the contract types, the toolkit introduces four types: NEC 3/4, FIDIC, JCT, and PPC 2000.
As far as the above-discussed procurement routes are concerned, traditional procurement can be more time-consuming and heavily complex for a housing retrofit project as there is a separate consultant who undertakes the design and consultancy responsibilities. The same goes for the management contracting procurement route as it requires a separate consultant for design and consultancy. Considering the nature and the scope of housing retrofit projects, both traditional and management contracting routes are not recommended. This is the same for mass-scale retrofit projects such as multi-family residential complexes, housing terraces, or city-wide retrofit projects under social housing retrofit projects. Even though the houses can share the same architectural plans, the state of maintenance and the retrofit requirements can be highly different from one house to another.
Another procurement route is design build. There is a possibility to use the design build procurement route when there is a large-scale contractor involved with the retrofit. These contractors have their own team consisting of retrofit subcontractors, designers, as well as retrofit coordinators. The design build contracts can be used with any type of client discussed before. This can be individual clients such as owner-occupiers and private landlords. Otherwise, design build contracts can be used with social landlords. There is no difference observed in the client type. Currently, one-stop shop retrofit solution providers are emerging in the UK retrofit industry. These contractors provide integrated retrofit services to clients from initial advice to monitoring and evaluation [
43]. Practical constraints can be observed with the limited number of available contractors who provide such integrated housing retrofit solutions.
Finally, the construction management procurement route can be identified as the most aligned procurement route, when there is no large-scale contractor involved. This procurement route will work best with both individual clients and social housing landlords. The retrofit coordinator can work as the construction manager, which is already endorsed by the PAS 2035:2023. As there are different installers for different measures in the UK housing retrofit industry, the retrofit coordinator will manage them for effective project delivery. The contractual agreement will be between the homeowner and the contractors. In the case of social housing, the agreement will be between the social housing landlord and the subcontractors.
When it comes to deciding the contract administration in housing retrofit, the first aspect that needs to be focused on is the nature of the client. If the client is an individual such as an owner-occupier or a private landlord, the next focus needs to be on the supply chain. The contractor can be an entity which provides integrated services, or a one-stop shop solution provider. In this situation, a design build procurement route is recommended. A JCT or NEC design build contract is recommended as the standard form of contract. Further, the JCT building contract and consultancy agreement for homeowners/occupiers can also be recommended as it is designed to work with a single contractor.
In the case of a fragmented supply chain where the works are attended by different subcontractors, the construction management procurement route can be recommended. For a recommendation for a standard form of contract, a JCT construction management contract is recommended. The client needs to evaluate several factors when deciding the supply chain type. Currently, the contractors providing integrated retrofit services are limited. In this case, the market availability of integrated contractors is a matter of concern. The other important aspect is the cost. Due to the single point of contact and the low risk and hassle to the contractor, the cost of the integrated retrofit services can be higher. In this situation, cost and availability can be the key determinants of the supply chain type.
If the client is a social landlord, similar recommendations can be given. If the social landlord is looking for integrated contractors, the design build procurement can be suggested. This can be a reason why the LBHF council has entered a design build contract with Energiesprong UK to retrofit 27 houses under the SHDF grant [
30]. It is not practical to expect to have these types of one-stop shop solution or integrated retrofit delivery services. In such a situation, the social landlord can easily use the construction management procurement route to procure several subcontractors to install the retrofit measures with a separate retrofit coordinator service. In this situation, both the design build and construction management procurement routes can be considered. The selection depends on the social landlord’s risk appetite and the expertise to run projects. A highly expertise risk-seeking landlord may use construction management where they can have more control over the project.
The availability of government funding is another important aspect to look at. Most of the social housing projects are run by government funding, for example SHDF, the Social Housing Decarbonisation Fund [
15]. These grants are delivered through local authorities and combined authorities. There will be a greater influence from the funding body on the project for the selection of the procurement route and the contract type if the project is government-funded. According to the literature, most of the government-funded projects procure contractors through framework agreements [
15,
37]. They expect the contractors to enter into their own contracts with the clients.
By taking into consideration the above discussion, the following summary findings can be given. The execution of construction contracts is highly rare in the residential retrofit industry. The framework agreements used for government-funded projects only secure the interests of the local authority involved in the project delivery. The proper allocation of rights and obligations between the contractor and the client (homeowner/landlord) is not evident. Due to the scope of individual projects (single houses) and the growing stage of the housing retrofit industry, contractual disputes are not yet evident in the onset. Accordingly, the need for proper contract administration in the retrofit industry has not been visible for now.
6. Conclusions
The purpose of this study was to critically analyse the existing procurement routes and forms of contract in housing retrofit. As the number of procurement routes and forms of contract are exhaustive, the study focused only on five main procurement routes and two main standard forms of contract. Finally, empirical data collection was conducted with the retrofit contractors to ascertain their exposure towards contract administration and procurement in the UK housing retrofit industry. Considering the interview findings, the housing retrofit industry does not use construction contracts to a considerable level. In the cases where the contracts are executed, they are bespoke contracts. JCT and NEC contracts were reported to be used in some instances. As the industry has just started to grow, there are not many case studies available where the contract administration of the retrofit went wrong. Because of this reason, there is no demand for formal contracts and the client awareness of the importance of formal contracts is low.
The UK has more than 30.1 million houses [
44], and almost all the houses need some level of retrofit [
45]. When the number of retrofitted houses grows, the disputes related to retrofit will also grow. According to the RIBA Construction and Law Report 2022, 27% of the construction projects in the UK have faced at least one dispute [
46]. By adopting this ratio, it can be expected that 8.1 million projects will face some level of dispute. In monetary terms, this will equal GBP 221.4 billion, with an estimated total housing retrofit budget of GBP 820 billion [
47]. In that situation, both the clients and the contractors may realise the need for a standard form of contract to resolve these disputes, although it is too late.
It is not rational to assume that only the guarantees, warranties, and invoices will be helpful to resolve these disputes. Even with the bespoke contracts, the problem might not be resolved well. Legal firms can find a point to make claims by identifying loopholes in these bespoke contracts. Considering these points, it is important to clearly define the responsibilities of the parties and have uniformity in contract administration in housing retrofit, preferably by using a standard form of contract.
The study recommends the design build procurement route to work with contractors who provide integrated retrofit services (one-stop shops). The construction management procurement route is recommended to work when there is more than one contractor. Digital versions of one-stop shops or Integrated Project Delivery (IPD) models adapted for housing retrofit shall promote industry collaboration, while supporting better contract administration [
48,
49]. These technological inputs may ease the adoption of standard forms of contract. Future research is recommended to evaluate how technological tools can facilitate contract administration in housing retrofit, providing ease of use and cost-efficiency to contractors.