Next Article in Journal
Exploring Sidewalk Built Environment Design Strategies to Promote Walkability in Tropical Humid Climates
Previous Article in Journal
Addressing Energy Performance Challenges in a 24-h Fire Station Through Green Remodeling
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

IoT Monitoring and Evaluating System for the Construction Quality of Foundation Pile

1
Jiangsu Power Transmission & Transformation Company, Nanjing 210028, China
2
College of Transportation Science & Engineering, Nanjing Tech University, Nanjing 211816, China
3
College of Civil Engineering, Jiangsu Open University, Nanjing 210036, China
*
Authors to whom correspondence should be addressed.
Buildings 2025, 15(15), 2660; https://doi.org/10.3390/buildings15152660
Submission received: 13 May 2025 / Revised: 29 June 2025 / Accepted: 2 July 2025 / Published: 28 July 2025
(This article belongs to the Section Building Structures)

Abstract

The quality of foundation pile is greatly influenced by human factors, and quality assessment is delayed. This paper introduces a new evaluation system based on Internet of Things (IoT) monitoring data of the foundation pile construction process. First, an IoT monitoring system of foundation pile construction process quality is established to monitor the key parameters for quality control in the foundation pile construction process, such as pile length, position, verticality, water–cement ratio, grouting volume, drilling/lifting speed, etc. Next, the absolute gray relational degree analysis method and the analytic hierarchy process (AHP) entropy-weighted combination weighting method are used to divide the monitoring data into different levels and determine the weight coefficients for quality indicators during foundation pile construction. Last, the IoT monitoring and evaluation system of the foundation piles construction process quality is applied to engineering. The results indicate that the monitoring system is convenient and efficient, and the quality evaluation method is reliable. The construction process quality of cement-mixing piles is rated as excellent. The construction process quality of bored piles Z0103 and Z0232 is excellent, and pile Z0012 is qualified.

1. Introduction

Foundation pile is a foundation form with high bearing capacity, a wide application range, and various types. It is widely used in high-rise buildings, ports, bridges, and other projects. Foundation pile construction has many steps, and quality control is difficult.
Bored piles and cement–soil mixing piles are common types of foundation piles [1,2]. Cement–soil mixing pile is commonly used to improve the soft soil foundation as it is simple, highly effective, and low cost [3,4,5,6,7]. As a foundation form, the bored pile is broadly exploited in highways, bridges, sluices, and other engineering fields due to its strong adaptability, moderate cost, and simplicity [8,9,10,11]. However, the construction quality of bored piles is often difficult to control due to the high concealment of the construction site and the low level of automation of the construction equipment. At present, the construction of piles in China is still mostly completed by manual operation. Thus, the construction quality depends on the experience and responsibility of the operators and is often difficult to control. As a result of the uneven quality of supervisors and inadequate staffing, the outcome of on-site construction supervision is often unsatisfactory. The sampling test after construction is based on the idea of probability theory, that is, the quality of several piles is used to judge the construction effect of all piles on the whole site. However, due to the dark box operation, the selection of the test piles is non-random, and the test results cannot reflect the entire construction quality of the site. Since the quality inspection happens after the construction, remediation, or rework is required if the construction is unqualified, which will affect the construction progress. Additionally, the currently used post-construction sampling inspection methods are mainly laboratory-based and on-site tests such as load tests, coring tests, and unconfined compressive strength tests of core samples, which are time consuming and labor intensive [12,13,14,15,16,17,18,19,20].
The IoT technology has become a key technology to solve the interaction and integration between physical entities and data virtualization in intelligent manufacturing [21,22]. Through the integration of artificial intelligence, IoT, and other technologies, it is applied in equipment monitoring, pile operation and maintenance, and dispatch operation. The integration of new IT technologies, such as big data, meets the needs of intelligent manufacturing and cyber–physical systems. The IoT pile model is established based on the 5D model of the IoT [23,24,25]. Through the real-time interaction of data and operations between the physical pile and the IoT pile, the data integration and business integration in the whole lifecycle of the pile are improved, and the process of design, construction, operation, and maintenance is realized in the pile. By installing various sensors, one can monitor the cement mixing pile and related equipment in real time. Surrounding security, through the SCADA system and electronic equipment instruments to transmit voltage and other signals while receiving the process analyzer, one can achieve real-time monitoring of the construction status of cement mixing piles. On this basis, the real-time data of the pile is uploaded to the IoT pile and pile service system, the data of the pile is converted, cleaned, and packaged, and the data of the pile body is integrated [26,27].
Quality evaluation of the construction process is closely linked to quality inspection. With the continuous improvement of testing methods, construction data that were previously unobtainable can now be extracted, providing a basis for better evaluation of the pile foundation construction process. He J. combined fuzzy synthesis with AHP to study a bridge foundation pile construction quality evaluation method based on acoustic wave reflection pile foundation monitoring results. Peng J. and others proposed a pile foundation quality evaluation method based on the BP neural network artificial intelligence algorithm. Xu H. et al. proposed a core-drilling pile quality evaluation method based on AHP and gray theory. Qin Y. et al. used the entropy weight method to evaluate the bearing capacity of PHC pipe piles, concrete durability, and other indicators. Momeni et al. [28,29,30] developed a hybrid model by combining artificial neural networks (ANN) with a genetic algorithm (GA) for predicting the bearing capacity of piles. Similarly, other AI techniques have also been successfully implemented for predicting the ultimate bearing capacity of different types of piles using ANN: support vector machines (SVM), relevance vector machines (RVM), multivariate adaptive regression splines (MARS), extreme learning machines (ELM) and functional networks (FN) [31,32,33,34]. Apart from the load-bearing capacity of piles, ANN has also been used for predicting the settlement of piles based on cone penetration tests (CPT) [35,36,37,38,39].
This paper takes cement–soil mixing piles and bored piles as the research objects. On the basis of the IoT monitoring system and management platforms for the construction process of foundation piles, the evaluation system of pile foundation construction process quality based on the multi-objective fuzzy synthesis and AHP is developed and applied to engineering.

2. IoT Monitoring Platforms for the Pile Construction Process

2.1. Monitoring System and Information Platform

(1) Monitoring System
Figure 1 shows overal structure diagram of the monitoring system The quality monitoring of foundation pile is developed to transmit, store, and browse data and evaluate quality by Internet and IoT technologies. The sensor’s data are connected to a monitoring host, and the communication module of the monitoring host is responsible for uploading information to the cloud server, which can be accessed via client-side and mobile-end interfaces.
The IoT monitoring system is based on a combined wired and wireless transmission format. Instruments such as rangefinders, hydrometers, and dual-axis angular displacement sensors are connected via RVV cable-type RS485 bus to form a group of address-independent slave devices. These devices are networked with the monitoring host using the MODbus protocol and establish communication connections. Once the network connection is successfully established, the monitoring host sends read/write data requests to the various sensors.
Upon receiving these requests, the sensors send corresponding index data to the main station. After reading the data, the monitoring host displays it and transmits the data externally via an antenna and a SIM card. The antenna converts electrical signals into radio frequency signals and transmits them to the base station via radio waves. The SIM card sends data signals to the base station using protocols such as GSM, UMTS, and LTE. Upon receiving signals from the antenna or SIM card, the base station converts them into digital signals and forwards them to the core network for processing. The core network processes the received signals, including decoding, decrypting, and routing, before forwarding the signals to the target device, which is the server.
Client terminals, such as PCs or mobile devices, establish TCP connections with the server via the TCP protocol and send data reading and upload requests to the server using the TCP protocol. After receiving the request data, the server processes it and returns the corresponding data as needed. During data transmission, the TCP/IP protocol performs operations such as packet segmentation, ordering, and retransmission to ensure data integrity and reliability.
(2) Information platform
The information platform included four modules: project management, data management, alarm management, and quality evaluation, which include features such as inputting design data and evaluation standards, real-time monitoring of construction data, quality analysis during the pile-driving process, and generation of inspection reports, as shown in Figure 2. The information platform includes a client and a mobile terminal.
The client application included seven main functions are project mapping, equipment management, project management, alarm management, data management, quality evaluation, and personnel management. Design drawings, construction specifications, and personal information for engineering projects can be added through the management backend. The quality evaluation module evaluates completed pile construction processes by scoring them based on the actual parameters monitored by the IoT monitoring system, comparing them to the specifications for pile foundation construction. Each pile location is assigned a score ranging from 0 to 100, corresponding to evaluations of excellent, qualified, or unqualified. The alarm management module allows for the setting of construction requirements, referred to as alarm thresholds, based on pile foundation construction specifications, on-site construction conditions, and project circumstances. When the actual values of monitored indicators during construction exceed these thresholds, alarms are triggered. The personnel management module is used for assigning roles to project personnel and managing on-site construction staff. Different system permissions are allocated to workers with different responsibilities, ensuring the security of engineering data and the orderly operation of project management structures.
The mobile application offers four main functions: map monitoring, data management, alarm management, and project management, as shown in Figure 3. Construction management personnel can use this platform to access pile construction information at any time.

2.2. IoT Monitoring System for Cement–Soil Mixing Pile Construction

2.2.1. Quality Control Parameters for Cement–Soil Mixing Pile Construction

Construction quality parameters are crucial for controlling the quality of cement–soil mixing pile construction. Key factors affecting the quality of cement–soil mixing pile construction include the uniformity of mixing during construction and the amount of cement admixture. Mixing uniformity is mainly influenced by the drilling/lifting speed and the rotation speed of the mixing head. The amount of cement admixture is primarily affected by the grouting volume and the water–cement ratio, with the grouting volume determined by the drilling/lifting speed and grouting speed, and the water–cement ratio determined by the slurry density and viscosity.
The main construction processes of cement–soil mixing piles include machine positioning, pre-mixing and submerging, pre-mixing and lifting, re-mixing and submerging, and re-lifting, among others. The construction processes and quality control indicators are shown in Figure 4. Based on the construction technology of cement–soil mixing piles and the conditions at the construction site, this paper combines the assurance items, general items, and allowable deviation items in the quality inspection standards for cement–soil mixing piles. It outlines monitoring parameters related to pile location, pile length, pile position, verticality, grouting rate, drilling/lifting speed, mixing head speed, slurry density, slurry viscosity, and others. These parameters are comprehensively considered to ensure the quality of the cement–soil mixing pile construction process. The control standards and alarm values for these indicators are provided in Table 1.

2.2.2. Sensors for Cement–Soil Mixing Pile Construction

The monitoring sensors fixed on the drilling system contained a position sensor, a verticality sensor, and a depth sensor for monitoring the retracting velocity and verticality of the drill, and the position of slurry spraying. The monitoring sensors fixed on the feeding system contained an electromagnetic flowmeter for monitoring the flow rate of grouting. An inserted sound fork was used in the pulping system for real-time monitoring of the water–cement ratio. Table 2 shows the information about the sensors. Figure 5 shows the installation of monitoring sensors.

2.3. IoT Monitoring System for the Construction of Bored Pile

2.3.1. Quality Control Parameters for Forward/Reverse Circulation Bored Pile Construction

Construction process quality parameters are crucial for controlling the quality of bored pile construction. This paper focuses on the Internet of Things (IoT) monitoring and evaluation of the quality of upward/downward circulation drilling cast in situ piles. The main construction processes for upward/downward circulation bored pile construction include stakeout of pile locations, site leveling, sinking, installation of casings, erection of pile frames, positioning of drilling machines, slurry preparation, drilling, fabrication and installation of steel reinforcement cages, hole cleaning, underwater concrete pouring, and casing extraction, among others. The construction processes and quality control indicators for bored pile construction are shown in Figure 6. The chosen monitoring parameters include verticality, pile length, pile location deviation, as well as slurry-specific gravity and viscosity. The control standards and alarm values for these parameters are presented in Table 3.

2.3.2. Sensors for the Construction of Bored Pile

The drilling construction of forward/reverse circulation bored piles adopts the drilling construction of continuous fixed-length drill pipes. The laser range finder is welded and installed on the top of the drill pipe. The real-time distance of the bearing horizontal disk estimates the drilling length of a single drill pipe. The infrared counter is installed at the horizontal position of the slewing bearing horizontal plate to record the number of consecutive drill pipes. The real-time measurement data can also estimate the drilling rate of the drilled piles.
The monitoring sensors fixed on the drilling system contained a position sensor and a verticality sensor for monitoring the verticality of the drill and the position of slurry spraying. An inserted sound fork was used in the feed system for real-time monitoring of the slurry density. Table 4 shows the information about the sensors. Figure 7 shows the installation of monitoring sensors.

3. Evaluation of Foundation Pile

A quality evaluation indicator system is established based on IoT monitoring data. The absolute gray correlation analysis method is employed to determine the evaluation standard thresholds for construction quality indicators. The AHP, combined with entropy weighting, is used to assign weights to different construction quality indicators. Finally, the fuzzy comprehensive evaluation method is applied to conduct construction quality evaluation based on IoT monitoring data. This paper requires experts to be engaged in the field of underground engineering construction for at least 10 years.

3.1. Evaluation Indicators

The quality evaluation indicators for pile construction include pile position deviation, drilling depth, verticality, mud-specific gravity, and mud viscosity. According to different quality control objects, it is divided into three categories: pile structure B1, pile position deviation B2, and mud index B3, where B1 = (drilling speed, drilling depth, verticality), B2 = (pile position deviation), B3 = (sand content, mud viscosity, mud specific gravity, mud flow rate).

3.2. Evaluation Thresholds

To handle the fluctuations in construction quality monitoring data, the gray theory is applied. This involves analyzing how closely the quality monitoring values correlate with the specified thresholds, thereby determining how accurately the quality data reflect the actual conditions [40]. The calculation process is as follows:
(1) Determining data sequences
Collect real-time quality monitoring data at minute intervals. Suppose there are n data points for quality indicator i. These data points together constitute the quality monitoring data sequence Xi.
X i = x i 1 , x i 2 , , x i n
For each quality monitoring indicator, there exists a corresponding set of specified values denoted as x0 (n). These specified values collectively form the specified value sequence X0.
X 0 = x 0 1 , x 0 2 , , x 0 n
If the specified values are given as a range, the reference value is taken as the average of the upper and lower limits of that range.
(2) Calculating correlation [41].
This paper departs from traditional models that only consider the area between curves. Instead, it uses methods that calculate both the absolute value of the area and the area difference between the two curves.
Given that xi and x0 have the same length, let:
s i s 0 = 1 n | x i x 0 | d t
ρ i 0 = 1 1 + | s i s 0 |
where  ρ i 0  represents how closely the i-th quality indicator monitoring value during foundation pile construction correlates with the specified value. n is the number of monitoring results. i is monitoring times.

3.3. Calculation of Indicator Weight

The weight calculation for indicators is performed using a combination of the AHP and entropy-based weighting. AHP is used to calculate subjective weight values for the indicators, while entropy-based weighting calculates objective weight values for the evaluation indicators. Finally, these weights are combined to determine the comprehensive weight.
(1) Subjective Weight Calculation
The AHP is employed for the subjective weight calculation. This process includes the following steps: constructing the indicator hierarchy, creating pairwise comparison matrices, computing the weight coefficient vectors for these matrices, conducting a consistency check, and ultimately ranking the hierarchy.
(2) Objective Weight Calculation
Entropy-based weighting, on the other hand, is used to calculate objective weights for the evaluation indicators. The process involves the following steps:
① Constructing pairwise comparison matrices for m piles and r indicators:
D p i = ρ p i p = 1 , 2 , , m ; i = 1 , 2 , , r
where  ρ p i is ρ i 0  of the i index of the p pile foundation.
② Normalizing the judgment matrix  ρ ˙ p i
③ Among the r evaluation indexes, the entropy of the i evaluation index is
S i = In   r i = 1 r ρ ˙ p i In   ρ ˙ p i 1
④ The entropy weight of the i-th evaluation index is
w i = 1 S i r i = 1 r S i
where  w i  represents the objective weight value for the i-th evaluation indicator, and the objective weight vector is denoted as W″ = (w″1, w″2, …, w″n)T.
(3) Comprehensive Weight Calculation
To avoid the drawbacks associated with either purely subjective or purely objective weightings, a linear combination of weights is used. Let the comprehensive weight vector for the various indicators be denoted as W = (w1, w2, , wr)T. Then, the comprehensive weight for the i-th indicator, wi, is calculated as follows:
w i = ( 1 δ ) w i + δ w i
where  δ  is a weight coefficient that ranges between 0 and 1. δ  = 0 indicates that the evaluation relies solely on subjective judgment. δ  = 1 indicates that the evaluation relies solely on objective evaluation. δ  = 0.5 indicates that both subjective and objective evaluations are equally relevant.
If there are differences in the accuracy of subjective and objective evaluations, δ  can be adjusted accordingly to reflect this discrepancy.

3.4. Evaluation of the Construction Process

The construction process quality evaluation is carried out using the fuzzy comprehensive evaluation method, which is based on fuzzy mathematics. It involves constructing membership functions and making a comprehensive judgment through methods such as the maximum membership principle or weighted average. The steps are as follows:
(1)
Determine the Factor Set: Based on the established evaluation indicator system and the evaluation standard thresholds for construction process quality indicators, the relevance of the monitoring values of each evaluation indicator to their respective normative values is represented as: U = (u1, u2, …, ui).
(2)
Determine the Scheme Set: The quality of the construction process indicators is categorized as excellent, qualified, or unqualified.
(3)
Establish Membership Functions: The relationship between the factor set and the scheme set is expressed through membership functions. In this paper, trapezoidal distribution membership functions are selected. The distribution curve of the membership function is shown in Figure 8.
A v 3 x = 0 x < c x c d c c x d 1 d < x
outstanding
A v 2 x = x a b a a x b 1 b x c d x d c c x d 0 x < a   or   d < x
Up to standard
A v 1 x = 1 x < a b x b a a x b 0 b < x
Below standard
a, b, c, and d represent the boundary values for the distribution of the membership function, and these boundary values may vary for different indicators and are determined by the standard values. The fuzzy evaluation matrix for r indicators can be represented as:
R i = r 11 r 12 r 13 r 21 r 22 r 23 r r 1 r r 2 r r 3
(4)
Calculate the comprehensive evaluation vector
H p = W R = h 1 , h 2 , h 3
where  H p  is the comprehensive evaluation vector. W is the comprehensive weight matrix. h 1 , h 2 , h 3  are the membership degrees of the construction process quality indicators relative to the first, second, and third evaluation grades. “ ” represents the fuzzy composition operator.

4. Field Test

4.1. Field Test of Cement–Soil Mixing Pile

4.1.1. Test Result of Cement–Soil Mixing Pile

The experiment site is located in Yangzhou, Jiangsu Province, China. The predominant soil composition at the site comprises Quaternary deposits, specifically fine-grained clay, silty loam, and clayey silt, resulting from Quaternary alluvial deposits of the Upper and Middle Yangtze River.
For this project, 600 mm diameter cement mixing piles were utilized. The piles were solidified using 42.5 OPC as the curing agent, with a cement admixture rate of 18%. The water–cement ratio was 0.5. Construction followed the four-mixing and three-injection technique, with the lifting rate strictly controlled not to exceed 1 m/min.
The test piles were selected randomly in various areas of the project site, which were identified as Z0102, Z0130, and Z0062. The layout of the cement–soil mixing test pile is shown in Figure 9.
Throughout the testing process, real-time data were continuously collected by various monitoring systems and subsequently transmitted to a cloud-based platform. The results obtained during the testing phase are presented in Figure 10. Results revealed that the actual values of all parameters fluctuated within the allowable limits specified by the standards, demonstrating that the construction results met the required standards. The IoT monitoring systems operated seamlessly, ensuring stable data transmission. The on-site testing has unequivocally demonstrated that this system is a powerful asset for construction management personnel, providing them with effective control and oversight of the site.

4.1.2. Construction Quality Evaluation of Cement–Soil Mixing Pile

(1) Index system
Figure 11 shows Quality evaluation index system for cement–soil mixing pile construction process.
(2) Index analysis
Table 5 shows correlation be tween measured values and normative values of various indicators of Cement–Soil Mixing Pile.
(3) Index weight
Table 6 shows combination weights of quality evaluation indicators for the construction process.
(4) Comprehensive Evaluation Results
The comprehensive evaluation calculations for the construction process quality of different piles yielded the following results:
H Z 0102 = W R = 0.531 , 0.413 , 0.056
H Z 0130 = W R = 0.608 , 0.299 , 0.093
H Z 0062 = W R = 0.682 , 0.300 , 0.018
According to the “take the larger value” principle, the construction process quality evaluation results for the tested foundation piles of cement mixing piles are as follows: piles Z0102, Z0130, and Z0062 all achieved excellent construction process quality. The order of the three piles was Z0062 > Z0130 > Z0102.

4.2. Field Test of Bored Piles

4.2.1. Test Result of Bored Piles

The field test site is located in Nantong, Jiangsu Province, China. The foundation mainly consists of Quaternary alluvial deposits, including sandy silt, silty sand with sandy silt interlayers, silt, sandy silt with sandy interlayers, and silty clay of unified origin. The project used 350 bored piles with a diameter of 600 mm and an effective pile length of about 27 m. The layout of test bored piles is shown in Figure 12.
Two test piles were selected from each of the three areas, resulting in a total of nine single piles with the IDs of Z0012 and Z0103. Figure 13 shows the construction data monitoring curve of test piles. Results revealed that the actual values of various indicators exhibited fluctuations within the permissible limits during the construction process, and the construction results met the required standards. The monitoring system operated normally during construction, ensuring stable data transmission.

4.2.2. Construction Quality Evaluation

(1) Index system
Based on the IoT monitoring data for the construction process quality of foundation piles, the correlation between the actual construction process data and the specified values was calculated using Formulas (3) and (4), as shown in Table 7.
(2) Index weight calculation
(1) Primary Weights
The project-level judgment matrix is obtained separately for the three project-level criteria, B1 (Pile Body Structure), B2 (Pile Position Deviation), and B3 (Slurry Parameters), and the five indicator-level criteria, C1 (Drilling Depth), C2 (Verticality), C3 (Pile Position Deviation), C4 (Mud Density), and C5 (Mud Viscosity), based on expert ratings. The judgment matrix is as follows:
A = B 1 B 2 B 3 B 1 1 2 2 B 2 1 / 2 1 1 B 3 1 / 2 1 1
The judgment matrix is normalized
A ˙ = 0.50 0.50 0.50 0.25 0.25 0.25 0.25 0.25 0.25
According to Formulas (7) and (8), WA = (0.500, 0.250, 0.250)
Find the maximum eigenvector λ max
λ max = i = 1 3 A W B i i r w i = 3.00
The consistency test judgment matrix is obtained by calculating the consistency index
C I = λ max r r 1 = 0
C R = 0
A consistency ratio is CR < 0.1 indicates good consistency in the judgment matrix. Therefore, the project-level criteria weights are as follows:
WA = (WB1, WB2, WB3) = (0.500, 0.250, 0.250)
Similarly, the indicator-level judgment matrices and weights are as shown in Table 8, Table 9 and Table 10.
Table 11 shows the subjective weight of the quality evaluation index of the construction process of the cast pile.
(2) Objective weight calculation
The initial matrix is obtained according to the above calculation results
D = C 1 C 2 C 3 C 4 C 5 Z 0012 0.942 0.108 0.359 0.039 0.021 Z 0103 0.873 0.111 0.462 0.026 0.001 Z 0232 0.864 0.122 0.511 0.031 0.017
Normalized judgment matrix
D ˙ = 0.35 0.32 0.27 0.40 0.53 0.33 0.32 0.35 0.27 0.04 0.32 0.36 0.38 0.32 0.44
The objective weights for evaluation indicators of drilled cast-in-place piles are as shown in Table 12.
(3) Combined Weights
The combined weights are calculated with β = 0.5, as shown in Table 13.
(4) Quality Evaluation of Pile Construction
Process Based on the construction standards for drilled cast-in-place piles and the quality requirements of site management personnel, the limit values for the membership degree distribution functions are determined, as presented in Table 14.
Calculate the fuzzy synthesis matrix
R 1 = v 1 v 2 v 3 C 1 1 0 0 C 2 1 0 0 C 3 0 1 0 C 4 0 0.895 0.105 C 5 0 1 0
Pile Z0012
R 2 = v 1 v 2 v 3 C 1 0.879 0.121 0 C 2 1 0 0 C 3 0.769 0.231 0 C 4 0 0.332 0.668 C 5 0 1 0
Pile Z0103
R 2 = v 1 v 2 v 3 C 1 0.838 0.162 0 C 2 1 0 0 C 3 1 0 0 C 4 0 0.533 0.467 C 5 0 1 0
Pile Z0232
The comprehensive evaluation results for the construction process quality of different piles are as follows:
H Z 0012 = W R = 0.478 , 0.506 , 0.016
H Z 0103 = W R = 0.606 , 0.292 , 0.103
H Z 0232 = W R = 0.643 , 0.285 , 0.072
Based on the principle of selecting the highest evaluation result, the construction process quality evaluation results for the tested piles of bored piles are as follows: pile Z0012 has a qualified construction process quality, while piles Z0103 and Z0232 have excellent construction process quality. The order of the three piles was Z0232 > Z0103 > Z0012.

5. Economic Analysis

5.1. Direct Economic Benefits

Traditional pile foundation construction relies on manual layout, monitoring, and recording, requiring the collaboration of multiple surveyors. In contrast, the IoT monitoring system enables real-time data collection, reducing the need for on-site layout personnel by over 60%, eliminating manual inspection steps, and shortening project timelines. The system monitors parameters such as grout volume in real time, preventing over-pouring or under-pouring issues. It reduces the concrete over-pour rate from 8% in traditional construction to within 3%, saving approximately 15% in material costs per pile.

5.2. Indirect Economic Benefits

Traditional pile foundation issues, such as tilted holes and insufficient depth, result in a rework rate of 10% to 15%. The IoT monitoring system enhances the first-time pass rate to over 98% through intelligent monitoring of verticality (e.g., deviation ≤ 5 mm per meter), avoiding rework losses. The cloud platform enables real-time sharing of construction data, reducing management response time from hours to minutes and lowering coordination costs. Automated report generation replaces manual statistics, saving 30% in management hours.
Traditional pile foundation inspections require personnel to enter boreholes, posing higher risks. The monitoring device can reduce the accident rate, reduce the number of on-site personnel, and directly avoid the risk of mechanical injury by replacing manual detection. The traditional reliance on empirical judgment can easily lead to insufficient bearing capacity. The IoT monitoring system can avoid the deviation of design parameters by analyzing the monitoring data in real time. Data link certificates (such as grouting volume and verticality records) provide a tamper-proof basis for acceptance and reduce disputes.

5.3. Cost Composition Analysis

The application costs of IoT monitoring technology primarily include initial investments (sensors, control terminals, etc., accounting for 60% to 70% of total investment), such as approximately RMB 50,000 to 100,000 per pile machine monitoring system. Operational costs include data transmission fees and platform maintenance fees (approximately 10% of the initial investment annually). As shown in Table 15, taking a 10-m long, 800 mm diameter cement–soil mixing pile as an example, the cost comparison between using the IoT monitoring system and traditional construction methods reveals savings of RMB 150 in labor costs, RMB 150 in materials, and an increase of RMB 100 in equipment costs, resulting in a net saving of RMB 100.
The economic benefits of IoT monitoring technology in pile foundation construction are characterized by “short-term investment, long-term returns,” with its value chain encompassing direct cost savings, risk avoidance, and data-driven value creation.
By optimizing resource allocation, reducing waste, and improving quality and efficiency, IoT monitoring technology ultimately achieves cost reduction across the entire project lifecycle. As sensor prices decrease and 5G networks become more widespread, the economic benefits of IoT in pile foundation construction will become even more pronounced.

6. Conclusions

This study focused on the IoT monitoring and evaluation of pile construction, applying it to cement-mixing piles and bored piles. The main conclusions are as follows:
(1)
The key control parameters for cement-mixing pile construction include pile position deviation, grout volume, water–cement ratio, drilling and lifting speed, verticality, and pile length.
(2)
The key control parameters for bored pile construction include verticality, pile length, pile position deviation, mud density, and mud viscosity.
(3)
The structure of the IoT monitoring system for pile construction includes three main components: on-site data acquisition, data transmission, and monitoring modules. Field tests demonstrated that the system operates stably, data collection is reliable, data transmission is stable, and the cloud platform effectively receives, displays, and processes data on time.
(4)
Based on the field test results of cement-mixing piles, the construction process quality of cement-mixing piles is all rated as excellent, and the order is Z0062 > Z0130 > Z0102.
(5)
Based on the field test results of bored piles, pile Z0012 has a qualified construction process quality, while piles Z0103 and Z0232 have excellent construction process quality. The order of the three piles was Z0232 > sZ0103 > Z0012.

Author Contributions

Methodology, P.Z.; Software, J.Y.; Formal analysis, K.W.; Data curation, R.Q.; Writing—original draft, X.Q.; Writing—review & editing, P.Z.; Supervision, K.W. All authors have read and agreed to the published version of the manuscript.

Funding

This research received no external funding.

Data Availability Statement

The original contributions presented in this study are included in the article. Further inquiries can be directed to the corresponding author.

Conflicts of Interest

Authors Kai Wu and Jiejun Yuan were employed by the company Jiangsu Power Transmission & Transformation Company. The remaining authors declare that the research was conducted in the absence of any commercial or financial relationships that could be construed as a potential conflict of interest.

References

  1. Frank, R.; Stavros, A.S.; Jens, R. Web-based Data and Monitoring Platform for Complex Geotechnical Engineering Projects. Geotech. Geol. Eng. 2013, 31, 927–939. [Google Scholar]
  2. Wan, Y.; Song, L.; Zhu, Z.; Peng, Y. Research on Construction Quality Monitoring and Evaluating Technology of Soil-Cement Mixing Piles. Soil Mech. Found. Eng. 2021, 58, 85–91. [Google Scholar] [CrossRef]
  3. Wan, Y.; Zhu, Z.; Song, L.; Xu, X.; Liu, J. Research on Intelligent Control and Evaluation Technology for Soil-Cement Mixing Pile Construction; Springer: Cham, Switzerland, 2020. [Google Scholar] [CrossRef]
  4. Kuang, Y.D. Research on application of bored pile in bridge engineering construction. Theor. Res. Urban Constr. 2013, 9, 1–7. [Google Scholar]
  5. Ong, D.E.L.; Chong, E.E.M. Soil–Structure Interactions in a Capped CBP Wall System Triggered by Localized Hydrogeological Drawdown in a Complex Geological Setting. Geosciences 2023, 13, 304. [Google Scholar] [CrossRef]
  6. Umit, O.; Abdulkadir, K.; Ulku, K.S.; Meric, C.O.; Zeynep, S.; Mustafa, K.G.; İbrahim, S.; Cevdet, B.Z. An analytical and applied blasting approach to facilitate rock-socketed bored pile excavation. Arab. J. Geosci. 2020, 13, 497. [Google Scholar] [CrossRef]
  7. Shao, Y.; Macari, E.J.; Cai, W. Compound deep soil mixing columns for retaining structures in excavations. J. Geotech. Geoenvironmental Eng. 2005, 131, 1370–1377. [Google Scholar] [CrossRef]
  8. Bao, Z. Study of Construction Technology of Large Diameter and Ultradeep Cement Mixing Pile in Road Engineering. J. Highw. Transp. Res. Dev. (Engl. Ed.) 2022, 16, 10–15. [Google Scholar] [CrossRef]
  9. Zheng, W.F.; Cheng, J.; Zhao, Z. Study on design and construction parameters of mixing piles (wet) and rotary jetting piles. Constr. Technol. 2016, 45, 172–174. [Google Scholar]
  10. Jung, D.; Park, J.; Kim, S.; Kim, G.; Kim, K.; Kim, J. Development of 4D CAD-based real time progress management system. In Proceedings of the 2011 6th International Conference on Computer Sciences and Convergence Information Technology (ICCIT), Seogwipo, Republic of Korea, 29 November–1 December 2011. [Google Scholar]
  11. Sardroud, J.M. Influence of RFID technology on automated management of construction materials and components. Sci. Iran. 2012, 19, 381–392. [Google Scholar] [CrossRef]
  12. Kang, L.; Moon, H.; Kim, H.; Choi, G.; Park, N.; Kom, C. Visualizing Work Progress Information of Construction Project by Web and VR Application. In Proceedings of the 2011 Fifth Asia Modelling Symposium, Manila, Philippines, 24–26 May 2011. [Google Scholar]
  13. Wan, Y.; Zhu, Z.; Xu, X.; Song, L. An intelligent soil-cement mixing column driver. Autom. Constr. 2022, 142, 104474. [Google Scholar] [CrossRef]
  14. Al-Darraji, F.; Sadique, M.; Čebašek, T.M.; Ganguli, A.; Yu, Z.; Hashim, K. A Systematic Review of the Geotechnical and Structural Behaviors of Fiber-Reinforced Polymer Composite Piles. Geosciences 2023, 13, 78. [Google Scholar] [CrossRef]
  15. Mitelman, A.; Yang, B.; Urlainis, A.; Elmo, D. Coupling Geotechnical Numerical Analysis with Machine Learning for Observational Method Projects. Geosciences 2023, 13, 196. [Google Scholar] [CrossRef]
  16. Shen, H.; Li, X.; Duan, R.; Zhao, Y.; Zhao, J.; Che, H.; Liu, G.; Xue, Z.; Yan, C.; Liu, J.; et al. Quality evaluation of ground improvement by deep cement mixing piles via ground-penetrating radar. Nat. Commun. 2023, 14, 3448. [Google Scholar] [CrossRef]
  17. Liu, H.; Liu, W.; Sui, S.; Xu, H.; Wang, J. Dynamic monitoring technique of bored pile pouring process based on multi-frequency ultrasound. J. Civ. Struct. Health Monit. 2022, 12, 411–425. [Google Scholar] [CrossRef]
  18. Nguyen, H.; Adachi, Y.; Kizuki, T.; Maeba, H.; Inazumi, S. Intergration of Information and Communication Technology (ICT) Into Cement Deep Mixing Method. Int. J. Geomate 2020, 19, 194–200. [Google Scholar] [CrossRef]
  19. Qian, X.; Zhang, P.; Wang, S.; Guo, S.; Hou, X. Grouting Additives and Information-Based Construction of Jet Grouting in the Water-Rich Sand Stratum. Appl. Sci. 2022, 12, 12586. [Google Scholar] [CrossRef]
  20. Muduli, P.K.; Das, S.K.; Das, M.R. Prediction of lateral load capacity of piles using extreme learning machine. Int. J. Geotech. Eng. 2013, 4, 388–394. [Google Scholar] [CrossRef]
  21. Wu, R.; Jiang, Y.; Zhao, S.; Chen, M.; Shang, S.; Lang, X. Application and comparative analysis of Intelligent Monitoring Technology for Grouted Pile Construction based on abaqus. Sci. Rep. 2025, 14, 9253. [Google Scholar] [CrossRef]
  22. Rawat, P.S.; Barthwal, A. LANDSLIDE MONITOR: A real-time landslide monitoring system. Environ. Earth Sci. 2024, 83, 226. [Google Scholar] [CrossRef]
  23. Moghanaki, A.A.; Gavarti, A.B.; Javid, A.A.S.; Malaekeh, S. Innovative IoT-Integrated Sensors for Real-Time Monitoring of Chloride Penetration in Concrete Structures. J. Nondestruct. Eval. 2025, 44, 33. [Google Scholar] [CrossRef]
  24. Qaffas, A.A. AI-driven distributed IoT communication architecture for smart city traffic optimization. J. Supercomput. 2025, 81, 916. [Google Scholar] [CrossRef]
  25. Ding, G.; Wang, J.; Wu, Q.; Yao, Y.; Li, R.; Zhang, H.; Zou, Y. On The Limits of Predictability in Real-World Radio Spectrum State Dynamics: From Entropy Theory To 5G Spectrum Sharing. IEEE Commun. Mag. 2020, 53, 178–183. [Google Scholar] [CrossRef]
  26. Kanniga Devi, R.; Gurusamy, M.; Vijayakumar, P. An Efficient Cloud Data Center Allocation to the Source of Requests. J. Organ. End User Comput. 2020, 2, 23–36. [Google Scholar] [CrossRef]
  27. Laghate, M.; Cabric, D. Learning Wireless Networks’ Topologies Using Asymmetric Granger Causality. IEEE J. Sel. Top. Signal Process. 2018, 12, 233–247. [Google Scholar] [CrossRef]
  28. Baziar, M.H.; Azizkandi, A.S.; Kashkooli, A. Prediction of pile settlement based on cone penetration test results: An ANN approach. KSCE J. Civ. Eng. 2015, 19, 98–106. [Google Scholar] [CrossRef]
  29. Momeni, E.; Nazir, R.; Jahed Armaghani, D.; Maizir, H. Prediction of pile bearing capacity using a hybrid genetic algorithm-based ANN. Measurement 2014, 57, 122–131. [Google Scholar] [CrossRef]
  30. Mohanty, R.; Suman, S.; Das, S.K. Prediction of vertical pile capacity of driven pile in cohesionless soil using artificial intelligence techniques. Int. J. Geotech. Eng. 2018, 2, 209–216. [Google Scholar] [CrossRef]
  31. Jiang, Z.; Yang, C.; Yue, H. Multi-Objective Optimization of Steel Pipe Pile Cofferdam Construction Based on Improved Sparrow Search Algorithm. Appl. Sci. 2024, 14, 10407. [Google Scholar] [CrossRef]
  32. Yin, Q.; Li, J.; Zhou, L.; Liu, X.; Zhang, Y.; Song, S.; Li, H. Classification and recognition method of rice situation based on gray correlation degree. J. Stored Prod. Res. 2024, 109, 102448. [Google Scholar] [CrossRef]
  33. Abowitz, D.A.; Toole, T.M. Mixed method research: Fundamental issues of design, validity, and reliability in construction research. J. Constr. Eng. Manag. 2010, 136, 108–116. [Google Scholar] [CrossRef]
  34. Das, S.K.; Basudhar, P.K. Undrained lateral load capacity of piles in clay using artificial neural network. Comput. Geotech. 2006, 33, 454–459. [Google Scholar] [CrossRef]
  35. Tarawneh, B. Pipe pile setup: Database and prediction model using artificial neural network. Soils Found. 2013, 53, 607–615. [Google Scholar] [CrossRef]
  36. Samui, P. Application of relevance vector machine for prediction of ultimate capacity of driven piles in cohesionless soils. Geotech. Geol. Eng. 2012, 30, 1261–1270. [Google Scholar] [CrossRef]
  37. Samui, P. Determination of ultimate capacity of driven piles in cohesionless soil: A Multivariate Adaptive Regression Spline approach. Int. J. Numer. Anal. Methods Geomech. 2012, 36, 1434–1439. [Google Scholar] [CrossRef]
  38. Samui, P.; Das, S.; Kim, D. Uplift capacity of suction caisson in clay using multivariate adaptive regression spline. Ocean. Eng. 2011, 38, 2123–2127. [Google Scholar] [CrossRef]
  39. Suman, S.; Das, S.K.; Mohanty, R. Prediction of friction capacity of driven piles in clay using artificial intelligence techniques. Int. J. Geotech. Eng. 2016, 10, 469–475. [Google Scholar] [CrossRef]
  40. Kurttila, M.; Pesonen, M.; Kangas, J.; Kajanus, M. Utilizing the analytic hierarchy process (AHP) in SWOT analysis—A hybrid method and its application to a forest-certification case. For. Policy Econ. 2000, 1, 41–52. [Google Scholar] [CrossRef]
  41. Asadoullahtabar, S.R.; Asgari, A.; Tabari, M.M.R. Assessment, identifying, and presenting a plan for the stabilization of loessic soils exposed to scouring in the path of gas pipelines, case study: Maraveh-Tappeh city. Eng. Geol. 2024, 342, 107747. [Google Scholar] [CrossRef]
Figure 1. Overall structure diagram of the system.
Figure 1. Overall structure diagram of the system.
Buildings 15 02660 g001
Figure 2. The client application.
Figure 2. The client application.
Buildings 15 02660 g002aBuildings 15 02660 g002b
Figure 3. The mobile application.
Figure 3. The mobile application.
Buildings 15 02660 g003
Figure 4. Construction process and quality control indicators of cement–soil mixing pile.
Figure 4. Construction process and quality control indicators of cement–soil mixing pile.
Buildings 15 02660 g004
Figure 5. Installation positions of all sensors for Cement–Soil Mixing Pile Construction.
Figure 5. Installation positions of all sensors for Cement–Soil Mixing Pile Construction.
Buildings 15 02660 g005
Figure 6. Flowchart of the pile construction procedure.
Figure 6. Flowchart of the pile construction procedure.
Buildings 15 02660 g006
Figure 7. Installation positions of all sensors for the Construction of Bored Pile.
Figure 7. Installation positions of all sensors for the Construction of Bored Pile.
Buildings 15 02660 g007
Figure 8. Distribution of trapezoidal membership function.
Figure 8. Distribution of trapezoidal membership function.
Buildings 15 02660 g008
Figure 9. Layout of cement–soil mixing test pile.
Figure 9. Layout of cement–soil mixing test pile.
Buildings 15 02660 g009
Figure 10. Construction data monitoring curve of test piles of Cement–Soil Mixing Pile.
Figure 10. Construction data monitoring curve of test piles of Cement–Soil Mixing Pile.
Buildings 15 02660 g010
Figure 11. Quality evaluation index system for cement–soil mixing pile construction process.
Figure 11. Quality evaluation index system for cement–soil mixing pile construction process.
Buildings 15 02660 g011
Figure 12. Layout of test section of bored pile.
Figure 12. Layout of test section of bored pile.
Buildings 15 02660 g012
Figure 13. Construction data monitoring curve of test piles of Bored Piles.
Figure 13. Construction data monitoring curve of test piles of Bored Piles.
Buildings 15 02660 g013
Table 1. Quality inspection standards for cement–soil mixing piles.
Table 1. Quality inspection standards for cement–soil mixing piles.
Serial NumberKey ParameterStandard ValueAlarm Value
1Pile deviation50 mm>50 mm
2Spray volumeDesign values ±1%≠Design values ±1%
3Water–cement ratioDesign values ±0.05 g/cm3≠Design values ±0.05 g/cm3
4Trip and lift speedDesign values ±0.05 m/min≠Design values ±0.05 m/min
5Borehole depthNot less than the design value<Design values
6Verticality1%>1%
Table 2. Sensors for cement–soil mixing piles.
Table 2. Sensors for cement–soil mixing piles.
Serial NumberKey ParameterMethodSensor
1Pile deviationGNSSGNSS receiver
2Spray volumeMonitoring slurry flowElectromagnetic flowmeter
3Water–cement ratioMud-induced vibrationPlug in tuning fork
4Trip and lift speedDepth meter velocity measurementDepth sensor
5Borehole depthDepth gaugeDepth sensor
6VerticalityInclination sensorDual-axis angle sensor
Table 3. Quality inspection standards for bored piles.
Table 3. Quality inspection standards for bored piles.
Serial NumberIndexStandard ValueAlarm Value
1Pile deviation100 + 0.01 H>100 + 0.01 H
2Borehole depth100% Design value<80% Design value
3Verticality1%≥1%
4Mud weight1.15–1.20<1.15 or >1.20
5Mud viscosity16~21 s<16 s or >21 s
Table 4. Sensors for the bored piles.
Table 4. Sensors for the bored piles.
Serial NumberKey ParameterMethodSensor
1Pile deviationGNSSGNSS receiver
2Borehole depthPile extension timesElectromagnetic flowmeter
3VerticalityInclination sensorDual-axis angle sensor
4Mud weightMud-induced vibrationPlug in tuning fork
5Mud viscosityRotating torque principleOnline rotary viscometer
Table 5. Correlation between measured values and normative values of various indicators of Cement–Soil Mixing Pile.
Table 5. Correlation between measured values and normative values of various indicators of Cement–Soil Mixing Pile.
Pile PositionDegree of RelevanceBorehole DepthPerpendicularityPile DeviationWater-Cement RatioCement Slurry FlowDrill Down Speed
Z0102 s i s 0 0.0377.2890.1620.3461.4320.576
ρ i 0 0.964 0.1210.8610.7430.4110.635
Z0130 s i s 0 0.3508.5340.1040.4181.3810.420
ρ i 0 0.7410.1050.906 0.7050.4200.704
Z0062 s i s 0 0.0897.9110.0970.2191.6800.331
ρ i 0 0.9180.112 0.912 0.820 0.3730.751
Table 6. Combination weights of quality evaluation indicators for the construction process.
Table 6. Combination weights of quality evaluation indicators for the construction process.
Borehole DepthPerpendicularityPile DeviationWater-Cement RatioCement Slurry FlowDrill Down Speed
Subjective weights W 0.2540.1530.1020.1360.1360.220
Objective weighting W 0.2210.1430.1430.1460.1460.200
Combined weights W 0.2380.1480.1220.1410.1410.210
Table 7. Correlation between measured values and normative values of various indicators of Bored Piles.
Table 7. Correlation between measured values and normative values of various indicators of Bored Piles.
Pile PositionDegree of RelevanceBorehole DepthVerticalityPile DeviationSpecific Gravity of MudMud Viscosity
Z0012 s i s 0 0.5708.2250.0611.78624.843
ρ i 0 0.0210.1080.9420.3590.039
Z0103 s i s 0 0.0408.0240.1451.16737.003
ρ i 0 0.0010.1110.8730.4620.026
Z0232 s i s 0 0.4707.1900.1570.95831.539
ρ i 0 0.0170.1220.8640.5110.031
Table 8. Indicator layer judgment matrix and weights of B1.
Table 8. Indicator layer judgment matrix and weights of B1.
B1Borehole Depth C2Verticality C3Weight
Borehole depth C21.002.000.67
Verticality C30.501.000.33
Table 9. Indicator layer judgment matrix and weights of B2.
Table 9. Indicator layer judgment matrix and weights of B2.
B2Pile Deviation C3Weight
Borehole depth C21.001.00
Table 10. Indicator layer judgment matrix and weights of B3.
Table 10. Indicator layer judgment matrix and weights of B3.
B3Mud Viscosity C6Specific Gravity of Mud C7Weight
Mud viscosity C61.001.000.50
Specific gravity of mud C71.001.000.50
Table 11. Subjective weights of quality evaluation indicators for the construction process of bored pile.
Table 11. Subjective weights of quality evaluation indicators for the construction process of bored pile.
Project LayerWeightMetrics LayerWeightPrimary Weights
B10.50depth C10.670.33
Verticality C20.330.17
B20.25Pile position C31.000.25
B30.25Specific gravity C40.500.13
Viscosity C50.500.13
Table 12. Objective weights of quality evaluation indicators for the construction process of bored pile.
Table 12. Objective weights of quality evaluation indicators for the construction process of bored pile.
Borehole DepthVerticalityPile DeviationSpecific Gravity of MudMud Viscosity
si0.510.680.680.680.67
Objective weighting0.2760.1790.1790.1820.183
Table 13. Combination weights of quality evaluation indicators for the construction process of bored pile.
Table 13. Combination weights of quality evaluation indicators for the construction process of bored pile.
WeightBorehole DepthPerpe
Ndicularity
Pile DeviationSpecific Gravity of MudMud Viscosity
Subjective weights W 0.3300.1700.2500.1250.125
Objective weighting W 0.2760.1790.1790.1820.183
Combined weights W 0.3030.1750.2150.1540.154
Table 14. Boundary value of membership degree distribution function.
Table 14. Boundary value of membership degree distribution function.
Bounds ValueBorehole DepthPerpendicularityPile DeviationSpecific Gravity of MudMud Viscosity
d0.90.1050.480.0860.05
c0.680.0850.40.0630.03
b0.490.0650.320.0410
a0.330.0450.240.019−0.05
Table 15. Economic comparison of two construction methods.
Table 15. Economic comparison of two construction methods.
Cost ItemTraditional Construction/RMBIoT Monitoring Construction/RMB
Labor350200
Materials1000850
Equipment650750
Total Cost19001800
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Wu, K.; Zhang, P.; Yuan, J.; Qian, X.; Qi, R. IoT Monitoring and Evaluating System for the Construction Quality of Foundation Pile. Buildings 2025, 15, 2660. https://doi.org/10.3390/buildings15152660

AMA Style

Wu K, Zhang P, Yuan J, Qian X, Qi R. IoT Monitoring and Evaluating System for the Construction Quality of Foundation Pile. Buildings. 2025; 15(15):2660. https://doi.org/10.3390/buildings15152660

Chicago/Turabian Style

Wu, Kai, Peng Zhang, Jiejun Yuan, Xiaqing Qian, and Runen Qi. 2025. "IoT Monitoring and Evaluating System for the Construction Quality of Foundation Pile" Buildings 15, no. 15: 2660. https://doi.org/10.3390/buildings15152660

APA Style

Wu, K., Zhang, P., Yuan, J., Qian, X., & Qi, R. (2025). IoT Monitoring and Evaluating System for the Construction Quality of Foundation Pile. Buildings, 15(15), 2660. https://doi.org/10.3390/buildings15152660

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop