Article

Factors Affecting Contract Compliance and Execution of Public Works in the Executing Unit: Special Project Huallaga Central and Bajo Mayo in Peru, 2022

by
Anjhinson Romero
1 and
Doris Esenarro
1,2,*
1
Graduate Universidad School, Federico Villarreal National University, Lima 15084, Peru
2
Inern Unfv Specialized Institute of Ecosystems and Natural Resources Investigation, Lima 15084, Peru
*
Author to whom correspondence should be addressed.
Buildings 2024, 14(9), 2664; https://doi.org/10.3390/buildings14092664
Submission received: 4 March 2024 / Revised: 9 June 2024 / Accepted: 18 June 2024 / Published: 27 August 2024
(This article belongs to the Section Construction Management, and Computers & Digitization)

Abstract

Cost overruns, delays, and poor quality are frequent in public investment projects under the contract modality, executed by the Executing Unit: Special Project Huallaga Central and Bajo Mayo (PEHCBM). The purpose of this research is to identify the factors that affect the fulfillment of contracts for the execution of public works in the PEHCBM. This research includes the determination of the most influential factors using the relative importance index (RII), as well as surveys administered to a sample of 25 experts. A total of 91 articles from 48 academic journals were selected. With the application of the RII, 21 factors were determined, distributed among the dimensions of cost, time, and quality, and validated by the experts with a Spearman’s coefficient of value 0.521. In the case study, seven relevant factors were determined in PEHCBM execution contracts, identifying overtime between 4.7% and 524.2%, as well as a cost increase between 8.8% and 52.2%. Similarly, adverse situations detected by the Comptroller’s Office were determined, with an accumulated economic damage of about PEN 19 million, determining the high influence of the cost, time, and quality dimensions on them. In conclusion, this study shows the high overtime and the deficient quality of the works carried out by the contracting modality, which generated economic damage to the State.
Keywords: building projects; impact factors; public procurement building projects; impact factors; public procurement

Share and Cite

MDPI and ACS Style

Romero, A.; Esenarro, D. Factors Affecting Contract Compliance and Execution of Public Works in the Executing Unit: Special Project Huallaga Central and Bajo Mayo in Peru, 2022. Buildings 2024, 14, 2664. https://doi.org/10.3390/buildings14092664

AMA Style

Romero A, Esenarro D. Factors Affecting Contract Compliance and Execution of Public Works in the Executing Unit: Special Project Huallaga Central and Bajo Mayo in Peru, 2022. Buildings. 2024; 14(9):2664. https://doi.org/10.3390/buildings14092664

Chicago/Turabian Style

Romero, Anjhinson, and Doris Esenarro. 2024. "Factors Affecting Contract Compliance and Execution of Public Works in the Executing Unit: Special Project Huallaga Central and Bajo Mayo in Peru, 2022" Buildings 14, no. 9: 2664. https://doi.org/10.3390/buildings14092664

APA Style

Romero, A., & Esenarro, D. (2024). Factors Affecting Contract Compliance and Execution of Public Works in the Executing Unit: Special Project Huallaga Central and Bajo Mayo in Peru, 2022. Buildings, 14(9), 2664. https://doi.org/10.3390/buildings14092664

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop