Implications of ‘Lock-in’ on Public Sector Project Management in a Small Island Development State

by
Aaron Anil Chadee
1,*,
Xsitaaz Twinkle Chadee
2,
Abrahams Mwasha
1 and
Hector Hugh Martin
3
1
Department of Civil and Environmental Engineering, The University of the West Indies, St Augustine 330110, Trinidad and Tobago
2
Department of Physics, The University of the West Indies, St Augustine 330110, Trinidad and Tobago
3
School of Civil Engineering and Built Environment, Liverpool John Moores University, Liverpool 72046, UK
*
Author to whom correspondence should be addressed.
Buildings 2021, 11(5), 198; https://doi.org/10.3390/buildings11050198
Submission received: 24 March 2021 / Revised: 3 May 2021 / Accepted: 4 May 2021 / Published: 8 May 2021

Abstract

The concept of ‘Lock-In’, or the escalating cost of overcommitment on a project to a failing course of action, has unforeseeable implications in project management. This paper presents a case study on the occurrence and consequences of lock-in within the context of public sector housing projects in a small island developing state (SIDS). It demonstrates that cost overruns continue beyond the commissioning phase and throughout the project’s lifecycle, even though technical contingencies were implemented to deliver the intended project benefits. The findings unpack the implications of political expediency as a strategic tool mobilised to supersede proper technical decision-making prior to project execution. It concludes that project practitioners’ commitment to select and continue with a sub-optimal project can lead to the implementation of ineffective solutions to justify their actions, resulting in failed outcomes with negative social consequences. This research helps to advance project management knowledge in the us-er/operation phase, because previous scholarly work was limited to investigating lock-in from project conceptualisation to the commissioning phase.
Keywords: cost overruns; political influences; root causes; public housing programmes; small island developing states cost overruns; political influences; root causes; public housing programmes; small island developing states

Share and Cite

MDPI and ACS Style

Chadee, A.A.; Chadee, X.T.; Mwasha, A.; Martin, H.H. Implications of ‘Lock-in’ on Public Sector Project Management in a Small Island Development State. Buildings 2021, 11, 198. https://doi.org/10.3390/buildings11050198

AMA Style

Chadee AA, Chadee XT, Mwasha A, Martin HH. Implications of ‘Lock-in’ on Public Sector Project Management in a Small Island Development State. Buildings. 2021; 11(5):198. https://doi.org/10.3390/buildings11050198

Chicago/Turabian Style

Chadee, Aaron Anil, Xsitaaz Twinkle Chadee, Abrahams Mwasha, and Hector Hugh Martin. 2021. "Implications of ‘Lock-in’ on Public Sector Project Management in a Small Island Development State" Buildings 11, no. 5: 198. https://doi.org/10.3390/buildings11050198

APA Style

Chadee, A. A., Chadee, X. T., Mwasha, A., & Martin, H. H. (2021). Implications of ‘Lock-in’ on Public Sector Project Management in a Small Island Development State. Buildings, 11(5), 198. https://doi.org/10.3390/buildings11050198