Figure 1.
Fundamental curve for LVRT specifications.
Figure 1.
Fundamental curve for LVRT specifications.
Figure 2.
Capability for reactive current is necessary for different GCs.
Figure 2.
Capability for reactive current is necessary for different GCs.
Figure 3.
The two-stage PV power production system’s design and management approach.
Figure 3.
The two-stage PV power production system’s design and management approach.
Figure 4.
(a) PV’s equivalent circuit and (b) characteristics.
Figure 4.
(a) PV’s equivalent circuit and (b) characteristics.
Figure 5.
(a) Linear ADRC scheme; (b) LESO pole-placement method.
Figure 5.
(a) Linear ADRC scheme; (b) LESO pole-placement method.
Figure 6.
Diagram of SOGI structure.
Figure 6.
Diagram of SOGI structure.
Figure 7.
Schematic diagram of SOGI-FLL.
Figure 7.
Schematic diagram of SOGI-FLL.
Figure 8.
Schematic diagram of DSOGI-FLL-based PNSC.
Figure 8.
Schematic diagram of DSOGI-FLL-based PNSC.
Figure 9.
LADRC-based control structure with GPOA-P&O for the DC–DC converter.
Figure 9.
LADRC-based control structure with GPOA-P&O for the DC–DC converter.
Figure 10.
I–V characteristics of three PV modules under (a) different uniform irradiance and (b) partial shading.
Figure 10.
I–V characteristics of three PV modules under (a) different uniform irradiance and (b) partial shading.
Figure 11.
Relationship between solar irradiance and ∣G1 − G2∣ mismatch.
Figure 11.
Relationship between solar irradiance and ∣G1 − G2∣ mismatch.
Figure 12.
Proposed GPOA-P&O MPPT and LADRC-based control.
Figure 12.
Proposed GPOA-P&O MPPT and LADRC-based control.
Figure 13.
Schematic representation of the GMPP search procedure.
Figure 13.
Schematic representation of the GMPP search procedure.
Figure 14.
System responses under different MPPT methods during an SLG fault, (a) PV power, (b) DC-link voltage, (c) grid power, (d) reactive power, and (e–h) inverter currents. (Case 01).
Figure 14.
System responses under different MPPT methods during an SLG fault, (a) PV power, (b) DC-link voltage, (c) grid power, (d) reactive power, and (e–h) inverter currents. (Case 01).
Figure 15.
Inverter’s 3-phase voltage (a), PCC voltages (b), output currents (c) during fault and post-fault conditions. (Case 01).
Figure 15.
Inverter’s 3-phase voltage (a), PCC voltages (b), output currents (c) during fault and post-fault conditions. (Case 01).
Figure 16.
System responses under different MPPT methods during an SLG fault, (a) PV Radiation, (b) PV power, (c) DC-link voltage, (d) grid power, (e) reactive power, and (f–i) inverter currents. (Case 02).
Figure 16.
System responses under different MPPT methods during an SLG fault, (a) PV Radiation, (b) PV power, (c) DC-link voltage, (d) grid power, (e) reactive power, and (f–i) inverter currents. (Case 02).
Figure 17.
Inverter’s 3-phase voltage (a), PCC voltages (b), and output currents (c) during fault and post-fault conditions. (Case 2).
Figure 17.
Inverter’s 3-phase voltage (a), PCC voltages (b), and output currents (c) during fault and post-fault conditions. (Case 2).
Figure 18.
Comparative MPPT performance under identical irradiance variation: (a) PV irradiance profile, (b) PV output power response using P&O, PSO, GWO, HHO, and the proposed GPOA-P&O method, (c) DC-link voltage response, (d) MPPT tracking efficiency comparison, and (e) absolute PV power tracking error.
Figure 18.
Comparative MPPT performance under identical irradiance variation: (a) PV irradiance profile, (b) PV output power response using P&O, PSO, GWO, HHO, and the proposed GPOA-P&O method, (c) DC-link voltage response, (d) MPPT tracking efficiency comparison, and (e) absolute PV power tracking error.
Figure 19.
System responses under different MPPT methods during an 2LG fault, (a) PV power, (b) DC-link voltage, (c) grid power, (d) reactive power, and (e–h) inverter currents. (Case 03).
Figure 19.
System responses under different MPPT methods during an 2LG fault, (a) PV power, (b) DC-link voltage, (c) grid power, (d) reactive power, and (e–h) inverter currents. (Case 03).
Figure 20.
Inverter’s 3-phase voltage (a), PCC voltages (b), and output currents (c) during fault and post-fault conditions. (Case 3).
Figure 20.
Inverter’s 3-phase voltage (a), PCC voltages (b), and output currents (c) during fault and post-fault conditions. (Case 3).
Figure 21.
System responses under different MPPT methods during an 3LG fault, (a) PV power, (b) DC-link voltage, (c) grid power, (d) reactive power, and (e–h) inverter currents. (Case 03).
Figure 21.
System responses under different MPPT methods during an 3LG fault, (a) PV power, (b) DC-link voltage, (c) grid power, (d) reactive power, and (e–h) inverter currents. (Case 03).
Figure 22.
Inverter’s 3-phase voltage (a), PCC voltages (b), and output currents (c) during fault and post-fault conditions. (Case 4).
Figure 22.
Inverter’s 3-phase voltage (a), PCC voltages (b), and output currents (c) during fault and post-fault conditions. (Case 4).
Figure 23.
NI PXIE-1071 HIL simulator setup.
Figure 23.
NI PXIE-1071 HIL simulator setup.
Figure 24.
NI PXIE-1071 HIL simulator output results.
Figure 24.
NI PXIE-1071 HIL simulator output results.
Figure 25.
NI PXIE-1071 HIL simulator output results for Case two.
Figure 25.
NI PXIE-1071 HIL simulator output results for Case two.
Figure 26.
Comparison of system performance under pre-fault, 0.5 pu 2LG fault, and post-fault conditions using the proposed GPOA-P&O–ESF–LADRC–DSOGI-FLL control strategy and conventional PI control.
Figure 26.
Comparison of system performance under pre-fault, 0.5 pu 2LG fault, and post-fault conditions using the proposed GPOA-P&O–ESF–LADRC–DSOGI-FLL control strategy and conventional PI control.
Figure 27.
Performance comparison between the proposed ADRC–DSOGI-FLL– GPOA-P&O–ESF control and SCSO-tuned PI under pre-fault, fault, and post-fault conditions.
Figure 27.
Performance comparison between the proposed ADRC–DSOGI-FLL– GPOA-P&O–ESF control and SCSO-tuned PI under pre-fault, fault, and post-fault conditions.
Table 1.
Comparison of related LVRT control methods for grid-connected PV systems.
Table 1.
Comparison of related LVRT control methods for grid-connected PV systems.
| Ref. | Method | System/Application | Main Contribution | Limitation/Gap |
|---|
| [1] | DRL-based controller | Grid-connected PV system | Improves LVRT capability using deep reinforcement learning | Requires complex training and broader validation |
| [2] | Grid-following/grid-forming converter control | Grid-connected PV converters | Compares LVRT performance under current limitations | Transient stability and current constraints remain challenging |
| [3] | RL-based adaptive sliding mode control | Multilevel grid-connected inverter | Enhances LVRT performance and robustness | Higher implementation complexity |
| [4] | Grid-forming LVRT strategy | Grid-forming converter | Considers current limitation and transient stability | Requires careful protection coordination |
| [25] | Grid-following/grid-forming mode control | Grid-connected converter | Supports symmetrical and asymmetrical fault ride-through | Synchronization under severe imbalance remains difficult |
| [6] | Single-stage PV LVRT control | Three-phase grid-connected PV system | Improves fault ride-through capability | Less flexible than two-stage PV structures |
| [8] | ADRC + DSOGI-FLL | Three-phase grid-connected PV system | Improves LVRT, synchronization, and disturbance rejection | MPPT performance and partial-shading response can be further improved |
| This work | GPOA-P&O MPPT + LADRC + DSOGI-FLL | Two-stage three-phase grid-connected PV system | Enhances LVRT under symmetrical and asymmetrical faults, suppresses power oscillations, regulates DC-link voltage, improves phase-locking, and supports reactive current injection | Future work may extend validation to broader hardware conditions, aging effects, and multi-inverter PV plants |
Table 2.
A compilation of a few criterion for the power grid connection of PVPGS.
Table 2.
A compilation of a few criterion for the power grid connection of PVPGS.
| Country Grid Code (GC) | Rated Freq. (Hz) | Grid Freq. Boundaries (Hz) | Max Allowed Time | LVRT | HVRT |
|---|
| Within Fault | After Fault | Through Voltage Swell |
|---|
| V1 (%) | t2 (s) | V2 (%) | 13 (s) | V% | t (s) |
|---|
| Germany (GC) | 50 | fg > 51.5 | Disconnection (Trip) | | | | | | |
| 47.5 < fg < 51.5 | Continue operate (No Trip) | 0 | 0.15 | 90 | 1.5 | 120 | 0.1 |
| fg < 47.5 | Disconnection (Trip) | | | | | | |
| Italy (GC) | 50 | ND | ND | 0 | 0.2 | 85 | 1.5 | 125 | 0.1 |
| Spain (GC) | 50 | fg > 51.5 | Disconnection (Trip) | | | | | | |
| 47.5 < fg < 51.5 | Continue operate (No Trip) | 20 | 0.5 | 80 | 1 | 130 | 0.25 |
| 48 < fg < 47.5 | 3 s | | | | | | |
| fg < 47.5 | Disconnection (Trip) |
| Australia (GC) | 50 | fg > 52 | 2 s | 0 | 0.45 | 80 | 0.45 | 130 | 0.06 |
| 47.5 < fg < 52 | Continue operate (No Trip) |
| fg < 47.5 | 2 s |
| China (GC) | 50 | fg > 50.2 | 2 min | 20 | 0.15 | 90 | 2 | ND | ND |
| 49.5 < fg < 50.2 | Continue operate (No Trip) |
| 48 < fg < 49.5 | 10 min |
| fg < 48 | Characteristics of PV Inverter |
| Malaysia (GC) | 50 | fg > 52 | Disconnection (Trip) | 0 | 0.15 | 90 | 1.5 | 120 | Continuous |
| 47 < fg < 52 | Continue operate (No Trip) |
| fg < 47 | Disconnection (Trip) |
| S. Africa (GC) | 50 | fg > 52 | 4 s | 0 | 0.15 | 85 | 2 | 120 | 0.15 |
| 51 < fg < 52 | 60 s |
| 49 < fg < 51 | Continue operate (No Trip) |
| 48 < fg < 49 | 60 s |
| 47 < fg < 48 | 10 s |
| fg < 47 | 0.2 s |
Table 3.
Sensitivity analysis of LADRC controller and observer bandwidths under LVRT operating conditions.
Table 3.
Sensitivity analysis of LADRC controller and observer bandwidths under LVRT operating conditions.
| Case | Controller Bandwidth | Observer Bandwidth | DC-Link Voltage Overshoot | Settling Time | Current Ripple | LVRT Stability | Observation |
|---|
| Low bandwidth | (0.5 ωc) | (0.5 ωo) | High | Long | Low | Stable but slow | Slow disturbance rejection and delayed recovery |
| Moderate–low bandwidth | (0.75 ωc) | (0.75 ωo) | Medium | Medium–long | Low | Stable | Improved stability, but recovery is still slower |
| Nominal bandwidth | (ωc) | (ωo) | Low | Short | Low–medium | Stable | Best compromise between response speed and robustness |
| Moderate–high bandwidth | (1.25 ωc) | (1.25 ωo) | Low–medium | Short | Medium | Stable | Faster response, but ripple begins to increase |
| High bandwidth | (1.5 ωc) | (1.5 ωo) | Low | Very short | High | Stable but less robust | Higher noise sensitivity and increased voltage/current ripple |
Table 4.
Component-wise contribution of the proposed coordinated control framework.
Table 4.
Component-wise contribution of the proposed coordinated control framework.
| Component | Control Layer | Main Function | Main Affected Variables | Contribution |
|---|
| GPOA-P&O | PV-side MPPT control | Global MPP tracking under partial shading | PV power, PV voltage, MPPT tracking speed | Avoids local maximum points and reduces PV power fluctuation. |
| LADRC | DC–DC converter and inverter-control loops | Voltage/current regulation and disturbance rejection | DC-link voltage, inverter current, settling time, overshoot | Suppresses DC-link overvoltage and improves transient recovery during LVRT. |
| DSOGI-FLL | Grid synchronization and sequence extraction | Positive/negative-sequence extraction and phase tracking | Phase angle, frequency, reactive current reference | Improves synchronization accuracy and enables reactive current injection under unbalanced faults. |
| Coordinated framework | Complete two-stage grid-connected PV system | Integrated LVRT control | PV power, DC-link voltage, inverter current, active/reactive grid power | Enhances LVRT capability under symmetrical and asymmetrical grid faults. |
Table 5.
Performance assessment of the proposed LVRT control method under 1LG and 2LG fault conditions.
Table 5.
Performance assessment of the proposed LVRT control method under 1LG and 2LG fault conditions.
| Fault Type | Fault Duration (s) | PV Power (kW) | DC-Link Voltage (V) | Grid Real Power (kW) | Grid Reactive Power (kVAR) | Current THD (%) | Recovery Time (s) |
|---|
| 1LG, 0.3 pu sag | 0.0–0.3 | 50 → 50 ± 2% | 900 ± 15 | 100 → 100 ± 2% | 0 → 0 | <3 | ~0.04 |
| 2LG, 0.5 pu sag | 0.4–0.7 | 100 → 60 → 100 | ~900 | 100 → 60 → 100 | 0 → 100 → 0 | <3 | <0.1 |
Table 6.
Dynamic response characteristics of key PV system parameters under fault conditions.
Table 6.
Dynamic response characteristics of key PV system parameters under fault conditions.
| Subplot | Parameters | Values |
|---|
| Grid Voltage | Settling time | 0.07 |
| | Overshoot | 5% |
| | Undershoot | 5% |
| | Steady-state error | 0 |
| PNSC Extraction | Settling time | 0.08 |
| | Overshoot | 6% |
| | Undershoot | 8% |
| | Steady-state error | 0 |
| PV power | Settling time | 0.1 |
| | Overshoot | 10% |
| | Undershoot | 0 |
| | Steady-state error | 0 |
| Active Power | Settling time | 0.12 |
| | Overshoot | 5% |
| | Undershoot | 20% |
| | Steady-state error | 0 |
| DC-Link Voltage | Settling time | 0.05 |
| | Overshoot | 2% |
| | Undershoot | 5% |
| | Steady-state error | 0 |
Table 7.
Comparison of PV system fault-response methods.
Table 7.
Comparison of PV system fault-response methods.
| Feature | Proposed Method | Ref. [8] | Ref. [6] |
|---|
| Connection | Two-stage PV system using GPOA-P&O with ESF, LADRC, and DSOGI-FLL | Double-stage | Single-stage |
| Energy dissipation | ADRC clamps DC-link | None | Resistive discharge required |
| Efficiency | >99% (simulation) | High | Lower (power dissipated) |
| Complexity | Moderate control structure | Very simple | High |
| Fault response | Smooth power, <5% overshoot, <0.1 s settling | Smooth response | Large oscillations |
| PV Operational Point | Temporarily moves from MPP during LVRT | Moves away from MPP | Always at MPP |
| DC-link voltage | Within ±10% of nominal | Up to +20% | Nearly constant |
Table 8.
Quantitative comparison between simulation and HIL results under 2LG fault condition.
Table 8.
Quantitative comparison between simulation and HIL results under 2LG fault condition.
| Performance Indicator | Simulation Result | HIL Result | Difference/Deviation | Comment |
|---|
| Fault condition | 2LG, 0.5 pu sag | 2LG, 0.5 pu sag | — | Same fault condition |
| Fault duration | 0.4–0.7 s | 0.4–0.7 s | — | Same test interval |
| PV power during fault | 100 → 60 → 100 kW | 100 → 60 → 100 kW | Very small | HIL follows simulation trend |
| DC-link voltage | ~900 V/900 ± 15 V | ~900 V/900 ± 15 V | Within ±15 V | Stable DC-link regulation |
| Grid real power | 100 → 60 → 100 kW | 100 → 60 → 100 kW | Very small | Active power tracks fault condition |
| Grid reactive power | 0 → 100 → 0 kVAR | 0 → ~100 → 0 kVAR | Very small | Reactive current support is achieved |
| Current THD | <3% | ≤3% | Negligible | Satisfies power-quality requirement |
| Recovery time | <0.1 s | 0.08–0.10 s | Close agreement | HIL validates real-time feasibility |
| DC-link settling time | 0.05 s | approximately 0.08–0.10 s | Slightly higher in HIL | Due to real-time delay and hardware interface |
| DC-link overshoot | 2% | within ±15 V around 900 V | Acceptable | Overvoltage is effectively suppressed |
| Steady-state error | 0 | approximately 0 | Negligible | Stable post-fault recovery |