The case study focuses on the optimization of the production line layout in a selected company. The manufacturing company deals with the mass production of a wide range of frozen food products.
Based on a series of analyses carried out on the production lines, the aim was to find bottlenecks in the production process of the selected product, and to propose a more efficient positioning of the new production line in terms of technical and production area.
3.1. Phase 1—Input Analysis of Production on the Original Line
This paper focuses on a production line producing frozen, packaged food. From the wide range of frozen foods that the company produces, products that fall under the category of “Ready-made foods” were selected, specifically focusing on breaded cheese, breaded vegetables, breaded chicken schnitzel, and breaded pork schnitzel. The production volumes of these products are shown in
Table 1.
Figure 1 graphically shows the production volumes that were produced in 2021 on the original production line and their percentage in relation to the total production of these products. The figure shows that the largest share of production is in the production of breaded cheeses, with 75%. Because of the highest production share, breaded cheese was chosen as the representative sample on which all calculations are calculated. Specifically, 100 g of breaded cheese with a rectangular shape.
Once the production volume was established, a market analysis was carried out, which led to the conclusion that there was a need to increase production to meet customer demand. To increase production capacity and understand the situation, it was first necessary to calculate the performance of the individual machines on the production line and to calculate their unknown outputs. Three critical pieces of machinery that are part of the production line were examined. These were the forming machine, the freezing tunnel, and the frying tunnel. The wet and dry coater, mixers, cutter, and packing lines need not be addressed further. In the figures below, the forming machine and freezing tunnel (
Figure 2), and the frying tunnel and the wet and dry coater (
Figure 3) can be seen.
Subsequently, calculations of the output and usability of the original machinery were made. The efficiency calculations of the original devices are shown below.
Maximum efficiency of the forming machine:
Number of pieces molded in 1 h:
where:
i1—the number of pieces produced per 1 cycle
i2—number of cycles in 1 min
Weight 1 pc immediately after shaping: 55 g = 0.055 kg
Total weight of pieces produced in 1 h:
where:
The resulting weight of one piece at the end of the line:
where:
The efficiency of the forming machine according to the calculation was PT = 228 kg/h. Efficiency of the frying tunnel PF = 1500 kg/h and freezing tunnel PZ = 600 kg/h were known from the technical documentation of the machines.
Furthermore, the usability calculations of the individual three main machines were performed. The forming machine had the lowest efficiency at 4140 pcs/h, and in the calculations, this value was calculated as the default value, i.e., 100% (4140 pcs/h = 100%).
Usability of the frying tunnel:
where:
Usability calculation:
where:
Usability of the freezing tunnel:
where:
Usability calculation:
where:
From the above calculations, it follows that the capacities of the forming machine and the freezing tunnel are noticeably lower than the capacity of the frying tunnel, which leads to inefficient use of all machines. It is therefore possible to replace the forming machine and the freezing tunnel.
Table 2 shows that the frying tunnel has the highest output, i.e., 15,000 pcs/h.
The aim was to calculate the required performance of all three main machines of the original production line. This was done to match the performance and maximize the availability of all parts of the production line.
It is evident from
Table 2 that the frying tunnel has the highest efficiency. The other two devices require higher efficiency. For the forming machine, the weight of one piece was only 55 g, which was 55% of the weight of one product that passes through the frying and freezing tunnels. This weight corresponds to the unwrapped cheese, which was chosen as a representative due to its highest production share.
Calculation of the necessary efficiency of the forming machine:
where:
The required efficiency of the freezing tunnel is the same as the efficiency of the frying tunnel, i.e., 1500 kg/h.
To make the initial analysis of the production complex and to determine the current state, it was necessary to describe and record the course of production on the original production line. The actual production of the breaded cheese on the original production line starts on the Seydellman cutting machine, where the Eidam cheese is cut to the required size. The cheese is then transferred to a UM 500 mixer, to which egg melange and flour are added. The mixer churns the raw materials into a mushy mass, resulting in a cheese mixture. This mixture is then transferred to the Koppens forming machine.
The Koppens forming machine consists of a pressure plate that pushes the cheese semi-finished product through a shaped hole in the shaping plate to the required shape and weight. This cheese is shaped in three pieces side by side. These already shaped cheeses fall onto a conveyor, which transports the cheese to the wet coater. In the wet coater, the cheese is coated with the first layer, and the cheese then passes through the conveyor into the dry coater, where the cheese is coated in breadcrumbs. The cheese then re-enters the second wet coater where it is coated. Next, the cheese is conveyed to a second dry coater where the cheese is coated in breadcrumbs a second time. The now breaded cheese is transported by conveyor through the frying tunnel, where the cheese is fried at temperatures of around 160 °C.
The finished cheese then enters the freezing tunnel at a temperature of around 90 °C and is constantly in motion, spiraling up to the higher part of the freezing tunnel and then exiting into the packing area. This cheese is frozen at −24 °C. This is followed by wrapping, placing in a box, and then on a pallet.
These pallets are then transported to cold store A. Depending on the need, these pallets are transported back to the packing area where they are repacked on the Econopack packing line into consumer packs of two to four pieces. They are placed on a pallet and wrapped in foil. These pallets of finished cheeses are taken back to warehouse A where they are stored until they are dispatched. The warehouses operate a FIFO (first in—first out) system. More on the FIFO method in retail, specifically in the food supply chain, is discussed in [
22].
The production flow of the breaded foodstuffs on the original production line is shown in
Figure 4. A description of the numbers of all production equipment is given in
Table 3.
The packing line consists of four separate places, which are the weighing table, the gluer, the detector, and the packing table.
In the warehouses, the company applies the FIFO system, where the pallet that enters first must exit first. The warehouses are designed in such a way that it is more challenging to apply the FIFO system because of the loading and unloading from one side. For this reason, it takes longer to unload goods than if the racks were accessed from both sides. However, this access is not possible in warehouse areas due to the small space.
It is also necessary to show where the so-called hygiene loop occurred in the production of ready-made foods, and one place for the handover of pallets within the company. Their locations are shown in
Figure 5, where the hygiene loop, intended for the passage of people between the clean and dirty zones, is highlighted by a green circle and separates the production area with the changing rooms. The pallet handover area is then highlighted with a yellow circle and is located between the production and storage areas.
3.3. Phase 3—Design of the Production Line Layout
In this section, layout designs were made for the layout of the production line in the designated production areas. For each option, the lengths of material flows were subsequently determined, and a projected calculation of the construction modifications was made. The designs were developed in relation to the hygiene requirements and path width requirements of the relevant standards.
The actual production process on the new production line is similar to that on the original production line. What is different is the way in which the cheese is shaped in five rows (originally in three rows) using the principle of continuous extrusion by means of a rotating drum. The filling of the forming machine is also different. In the new production line, the mixture is tipped into a vacuum filling machine, which pushes the cheese mixture into the forming machine.
Figure 7 shows a diagram of the production process with the designation of the individual machines (
Table 4). The start of production is at machine number 1, the Seydellman cutter, and the end at the Econopack packer.
However, the layout must consider the location of the drum washer and drum holder. The drum washer and drum holder must be located close to the vacuum filling machine.
The output of the new Merell forming machine, where the cheese is formed to the required shape and weight, can be seen in
Figure 8, with shaped cheese coming out of the five-row forming machine.
The last machine on the new production line is the Econopack packer. Automated packing into consumer boxes takes place here.
Figure 8 shows the packaging of cheese in two pieces.
In addition to breaded foods, the new production line (
Figure 7) can also produce potato croquettes or liver dumplings. For this production, however, other equipment must be connected to the production line. Sanitation is required whenever production is changed, production is shut down, etc. The sanitation itself consists of dismantling the production line and cleaning all the individual equipment. This sanitation takes three hours. The sequence of the various production facilities in the production of croquettes or liver dumplings is illustrated in
Figure 9.
When making croquettes or liver dumplings, both wet and dry coaters and the forming machine are taken off the production line. Furthermore, the Seydellman cutter and mixer are not required for production. Thus, there is only the connection of the Verbuffa, which is located under number 11 in
Figure 9. The Verbuffa is connected on the outlet side to the Mayn frying tunnel and on the inlet side to the vacuum filling machine. For other names of machinery, see
Table 4.
In terms of hygiene, it is necessary to divide production and nonproduction areas into clean and dirty zones, where clean zones are the parts of the production areas where production is carried out. Alternatively, where raw material, semifinished, or finished unpacked product is handled. The parts of the production plant are therefore divided according to
Figure 10, where the clean zone is marked in blue and the dirty zone in grey.
In production, a main traffic route with one lane for one direction of travel and one side lane for the movement of people without load was considered. The maximum width of the lift truck was assumed to be 1.6 m, the width of the side lane for unladen traffic in both directions is 750 mm, and the safety clearance is 200 mm. It was also necessary to consider the necessary structural modifications (material, work, transport, rental of construction equipment), which are often required to set up new production lines in companies [
23,
24].
The width of the main road:
where:
The production area is not used for the passage of people or materials for other production, so there is no need to consider all production locations with a width of 2010 mm. It is possible in some places to use widths of only 1460 mm in places where it is necessary to reach with a pallet truck. In the most extreme case, it is possible to consider a gap of only 1100 mm, where there will be a clearance of only 40 mm, but the possibility of transporting pallets will still be ensured. In places where there is only movement of people, it will be necessary to leave an aisle with a width of at least 600 mm for the movement of people in one direction, or 750 mm for the movement of people in both directions [
23,
24].
For the location of the production line in the chosen production area, two main options were offered, where one option has the production direction from left to right and the other from right to left.
Option 1—left direction of production
In the following Option 1, there is no significant saving of empty space that could be used for other production. Compared to Option 2, this option requires fewer construction changes. For example, the existing interim storage of pallets can be used. Existing hygiene loops and material transfer points can also be used.
Figure 11 shows the material flows for Option 1—left direction of production.
Material flows for Option 1 were also calculated. To do this, it was necessary to determine the proportions of individual raw materials, semifinished products, and packaging needed to produce one piece of product. For each item, the distance to transport the pallet from the warehouse to the point of consumption, as well as the number of pieces or weight per pallet, were defined. From this, it can then be derived how many pallets of raw material, semifinished goods, or packaging need to be transported from or to the warehouse (
Table 5).
The production line runs in three shifts of 7.5 h, seven days a week. In the calculations, continuous cheese production for one week was assumed. Including one sanitation, the production will be 3 h less in one week. This is only the theoretical maximum production time if the line runs continuously without breakdowns, and there will be no exchange to produce croquettes or liver dumplings. A total of 231,750 kg (2,317,500 pieces) of breaded 100 g cheese should be produced in this time. The consumption of all semifinished products, raw materials, and packaging for this production was then calculated. In addition, the number of pallets transported, and the total distance travelled with pallets in one week were given. The total distance travelled in one week for Option 1 was 155,979 km (
Table 6); after conversion to one year, this value is 8,110,908 km.
Distance travelled in 1 year:
where:
In the next part of the design, the path widths in the production areas were checked. This was based on the relevant standards, for example, the Czech standards CSN 26 9010 for materials handling, including requirements for the width and height of roads and aisles, and CSN 73 5105 dealing with industrial buildings for production purposes. The lift truck movement is shown in green and the movement of people in pink. The arrow indicates only one direction of travel. However, the return of the lift truck and persons is also considered. There should not be frequent passing in both directions. The bottlenecks are dimensioned in
Figure 12, which shows that a smooth passage will be ensured. The pallet locations are purely indicative. The pallet can be placed as per the actual need of the production operator. The narrowest space (750 mm) for operator passage in this Option 1 is between the Econopack packer and the back wall. Here, however, occasional operator passage in one direction is envisaged. The narrowest space (1.7 m) for transporting pallets is between the vacuum filling machine and the column. Here, the transport of pallets and the occasional passage of persons is envisaged. All freezer doors can also be considered as bottlenecks because of their usual width (1.9–2 m). However, these passageways are usually only used when coming in or out of a shift or during breaks [
23,
24].
The next necessary step was the construction changes (
Figure 13), which had to be calculated to determine the cost of this option. Demolition of 36 m of PUR panel walls (80 mm wide) and 3.6 m of masonry with a constant width of 390 mm would be required. In addition, three freezer doors and one lamellar screen will need to be dismantled. The ceiling height is 3.5 m. All costs in the calculations were converted from CZK to EUR according to the current exchange rate.
The calculations included the following: the total area of the walls to be demolished, an estimate of the demolition price, the area of the walls to be completed, an estimate of the price for the PUR panels (material), an estimate of the installation price, and an estimate of the transport price.
Wall area to be demolished:
where:
lp1—length of the PUR panel wall for the Option 1 (m)
lz1—length of masonry wall for Option 1 (m)
v1—wall height for Option 1 (m)
Demolition price estimate:
where:
Sd1—area of walls to demolish for Option 1 (m2)
cd—price of wall demolition (EUR/m2)
m1—number of freezer doors to remove for Option 1 (pcs)
cdm—the price of dismantling the freezer door (EUR/pcs)
lc1—the number of lamella screens to be dismantled for Option 1 (pcs)
cdlc—the price of disassembling lamella blinds (EUR/pcs)
Area of walls to be completed:
where:
Price estimate for PUR panels (material):
where:
Installation price estimate:
where:
Sv1—wall area to be completed for Option 1 (m2)
p1—price for the installation of PUR panels (EUR/m2)
p4—price for assembly—screws (EUR/m2)
Lm1—the number of screens needed for Option 1 (pcs)
cl—price for 1 slat (EUR/m)
v1—wall height for Option 1 (m)
Price estimate for transport and rental fees:
where:
dd—cost of transportation of workers (EUR/day)
n1—estimated length of reconstruction (day)
hp—rental hydraulic platforms and scaffolding (EUR/day)
In this option, the use of existing hygiene loops and material transfer points was envisaged. The need for a new refrigerated or freezer warehouse was not assumed.
The estimated total cost of the construction changes for Option 1 is very low, amounting to less than EUR 1000. In this variant, it is necessary to demolish only a few meters of walls and cover two opposite walls with PUR panels.
The total estimated price of the space modifications:
Option 2—right direction of production
The second variant is the location for the opposite direction of production—from right to left. The main advantage of this variant is the saving of two unused spaces of 25 m
2 and 51 m
2, which can be connected and used for other production. On the contrary, the disadvantage at first glance is the greater construction changes of the production areas. The creation of a new cold store is needed to bring in semifinished products and raw materials before production starts. In this variant, raw materials and semifinished goods are brought in from warehouses outside the main pallet transfer point. Therefore, a new pallet transfer point must be created between the storage area (dirty zone) and the production area (clean zone). Workers can then move through the main hygiene loop, which is one in these areas, at the changing rooms on the opposite side of the production plant. It will also be necessary to allocate (or purchase) one pallet truck specifically for these areas, as the trolley cannot go to other production areas without going through the dirty zone. A representation of the material flows for Option 2 is shown in
Figure 14.
In this option, pallets of raw material/semifinished goods will be loaded through the transfer point to the new cold store before production starts. After the actual start of production, the pallets of raw material/semifinished goods will be transported to the individual machines as required.
As with the previous option, material flows were subsequently determined. The proportions of each raw material, semifinished product, and packaging required to produce one piece of product were defined (
Table 7).
The production line runs in three shifts of 7.5 h, 7 days a week. In the calculations, continuous cheese production for one week was assumed. If one sanitation is included, the production will be 3 h shorter in one week, which is 154.5 h. Again, this is only the theoretical maximum production time if the line runs continuously without breakdowns, and there will be no exchange to produce croquettes or liver dumplings. A total of 231,750 kg (2317 500 pieces) of breaded 100 g cheese should be produced in this time. Subsequently, the consumption of all semifinished products, raw materials, and packaging for this production was calculated. The number of pallets transported, and the total distance travelled with pallets in one week were also given. The total distance travelled in one week for Option 2 was 206,289 km (
Table 8); after conversion to one year, this value was 10,727,028 km.
Distance travelled in one year:
where:
In the next part of the design, the widths of the paths in the production areas were checked according to CSN 26 9010 and CSN 73 5105, as in Option 1 [
23,
24]. The lift truck movement is shown in green in the figure and the movement of people is shown in pink. The arrow indicates only one direction of movement, but movement in both directions is possible. It is not anticipated to have regular movement of the pallet truck or persons in both directions at the same time. The bottlenecks are indicated in
Figure 15. As can be seen from the figure, the smooth passage of people and trucks will also be ensured in this variant. The pallet locations are approximate, and the pallets can be positioned at will according to the actual needs of the production operator. The narrowest space (950 mm) for the passage of people is at the Econopack packer between the table behind the detector and the wall. Here, the occasional passage of two production operators to the conveyor belt is envisaged. In addition, one production operator works in the so-called bottleneck. However, he can approach the table from a different angle. The narrowest place for the movement of the lift truck is again at the Econopack packer, but now on the other side of the inserter. However, there is enough space (1.37 m) for loading or unloading pallets. The box packing line can also be folded at an angle, which is more suitable in this case, and gives an extra 500 mm of walk-through width. Another advantage will be the optimal positioning of the pallet, which will not block the passage of two operators working from opposite sides of the packer.
The next necessary step was the construction changes (
Figure 16), which had to be calculated to determine the cost of Option 2. Here, 52 m of PUR panel walls (80 mm wide) had to be demolished. Six freezer doors and one lamellar screen will have to be dismantled. See
Figure 16 for demolition. The walls to be demolished are highlighted in orange. In this option, the pallet transfer area must be extended with PUR panel partitions (80 mm wide) by a total of 2.7 m to a height of 3.5 m. It is also planned to complete the cold store, which will require the addition of 14.5 m of PUR panel walls to a height of 3.5 m. There will also be a need for the installation of refrigeration doors. In the picture, the new PUR panels are highlighted in orange, with the door in green and the lamellar screen in black. All costs in the calculations were converted from CZK to EUR according to the current exchange rate.
The calculations included the following: the total area of the walls to be demolished, an estimate of the demolition price, the area of the walls to be completed, an estimate of the price for the PUR panels (material), an estimate of the installation price, and an estimate of the transport price.
Wall area to be demolished:
where:
lp1—length of PUR panel wall for Option 2 (m)
lz1—length of masonry wall for Option 2 (m)
v2—wall height for Option 2 (m)
Demolition price estimate:
where:
Sd2—area of walls to demolish Option 2 (m2)
cd—price of wall demolition (EUR/m2)
m2—number of freezer doors to be dismantled for Option 2 (pcs)
cdm—the price of dismantling the freezer door (EUR/pcs)
lc2—number of lamellar screens to be dismantled for Option 2 (pcs)
cdlc—the price of disassembling lamella screens (EUR/pcs)
Area of walls to be completed:
where:
lp3—the length of the PUR panel wall to complete the place for handing over the pallets (m)
lp4—the length of the PUR panel wall for the completion of the cold store (m)
v2—wall height for Option 2 (m)
Estimated price for PUR panels (material):
where:
Installation price estimate:
where:
Sv2—wall area to be completed for Option 2 (m2)
p1—price for the installation of PUR panels (EUR/m2)
p4—price for assembly—screws (EUR/m2)
Lm2—the number of screens needed for Option 2 (pcs)
c2—price for one screen (EUR/m)
v2—wall height for Option 2 (m)
mv—the number of installed doors (pcs)
cv—door installation price (EUR/pcs)
mcl—the number of installed screens (pcs)
cmcl—the price of installing screens (EUR/pcs)
Estimated price for transport and rental fees:
where:
dd—cost of transportation of workers (EUR/day)
n2—estimated length of reconstruction (day)
hp—rental hydraulic platforms and scaffolding (EUR/day)
dm—the cost of transporting the material (EUR)
The estimated total cost of the construction changes for Option 2 is approximately EUR 6800. In addition, a new cold store and pallet transfer area had to be created for this option, which significantly increased the price. However, due to the circumstances that the entire premises already had PUR panel roofs, there was no need to create new roofs, thus saving a significant part of the investment.
The total estimated price of the space modifications:
A relatively important advantage of Option 2 is the saving of 25 m
2 and 51 m
2 of space that can be used for setting up other production machines. The empty spaces are shown in
Figure 17.
These spaces have a floor at the same floor height and, therefore, after a possible structural check and possible strengthening of the ceiling, the bearing wall between them could be broken through, thus connecting these spaces.