Prioritization of Hazardous Zones Using an Advanced Risk Management Model Combining the Analytic Hierarchy Process and Fuzzy Set Theory
Abstract
:1. Introduction
2. Materials and Methods
2.1. Analytic Hierarchy Process (AHP)
2.2. Fuzzy Set Theory (FST)
3. Proposed Approach
3.1. Risk Identification
3.2. Risk Analysis
3.2.1. Impact Analysis
3.2.2. Probability Analysis
3.3. Risk Evaluation
4. Case Study
4.1. Project Overview
4.2. Identification of Risks
4.3. Results of Risk Analysis
4.4. Results of Risk Evaluation
4.5. Implications of the Proposed Approach
5. Conclusions
- All causal combinations associated with the highest-impact accident (i.e., significant tunnel convergence) are determined to be relatively fatal, but those associated with the low-impact accidents indicate minimal risk. It can be attributed to the imbalanced impact values between the highest-impact accident and the others.
- The prioritization results reveal that the locations where the gripper TBM excavates under unstable ground formations such as weathered rock and fault zones are the most vulnerable. Hence, the most recommended countermeasure is adopting a shield TBM instead of a gripper TBM or implementing ground reinforcement. Continuous supervision during the excavation of these sections is required owing to their proximity and high risk.
- FST effectively considers the inherent vagueness in expert surveys, facilitating a comprehensive estimation of both probability and risk. In addition, the causal combination composition addresses the impact of concurrent sources on accidents. The selection criterion adopted in risk evaluation supports rational risk management by excluding insignificant causal combinations. The obtained prioritization results of hazardous zones enable the formulation of an optimal countermeasure plan.
- The limitation of the developed model is due to the impact and probability being equally weighted in the risk evaluation, which may be inconsistent with each tunnel project’s objective and financial margin. Furthermore, the results derived from the developed model can depend on the experts involved. Future research can address these limitations by introducing a weight distribution between impact and probability based on appropriate weighting schemes and establishing an expert composition that is sufficient and not biased.
Author Contributions
Funding
Institutional Review Board Statement
Informed Consent Statement
Data Availability Statement
Conflicts of Interest
References
- Sharafat, A.; Latif, K.; Seo, J. Risk analysis of TBM tunneling projects based on generic bow-tie risk analysis approach in difficult ground conditions. Tunn. Undergr. Space Technol. 2021, 111, 103860. [Google Scholar] [CrossRef]
- Kwon, K.; Choi, H.; Oh, J.Y.; Kim, D. A study on EPB shield TBM face pressure prediction using machine learning algorithms. J. Korean Tunn. Undergr. Space Assoc. 2022, 24, 217–230. [Google Scholar] [CrossRef]
- Broere, W. Urban underground space: Solving the problems of today’s cities. Tunn. Undergr. Space Technol. 2016, 55, 245–248. [Google Scholar] [CrossRef] [Green Version]
- Gong, Q.M.; Yin, L.J.; She, Q.R. TBM tunneling in marble rock masses with high in situ stress and large groundwater inflow: A case study in China. Bull. Eng. Geol. Environ. 2013, 72, 163–172. [Google Scholar] [CrossRef]
- Lin, P.; Xiong, Y.; Xu, Z.; Wang, W.; Shao, R. Risk assessment of TBM jamming based on Bayesian networks. Bull. Eng. Geol. Environ. 2022, 81, 47. [Google Scholar] [CrossRef]
- Eskesen, S.D.; Tengborg, P.; Kampmann, J.; Holst Veicherts, T. Guidelines for tunnelling risk management: International Tunnelling Association, Working Group No. 2. Tunn. Undergr. Space Technol. 2004, 19, 217–237. [Google Scholar] [CrossRef]
- Hyun, K.C.; Min, S.; Choi, H.; Park, J.; Lee, I.M. Risk analysis using fault-tree analysis (FTA) and analytic hierarchy process (AHP) applicable to shield TBM tunnels. Tunn. Undergr. Space Technol. 2015, 49, 121–129. [Google Scholar] [CrossRef]
- Chung, H.; Park, J.; Kim, B.K.; Kwon, K.; Lee, I.M.; Choi, H. A causal network-based risk matrix model applicable to shield tbm tunneling projects. Sustainability 2021, 13, 4846. [Google Scholar] [CrossRef]
- Chung, H.; Lee, I.M.; Jung, J.H.; Park, J. Bayesian Networks-based Shield TBM Risk Management System: Methodology Development and Application. KSCE J. Civ. Eng. 2019, 23, 452–465. [Google Scholar] [CrossRef]
- Hong, E.S.; Lee, I.M.; Shin, H.S.; Nam, S.W.; Kong, J.S. Quantitative risk evaluation based on event tree analysis technique: Application to the design of shield TBM. Tunn. Undergr. Space Technol. 2009, 24, 269–277. [Google Scholar] [CrossRef]
- Chen, S.M. Fuzzy system reliability analysis using fuzzy number arithmetic operations. Fuzzy Sets Syst. 1994, 64, 31–38. [Google Scholar] [CrossRef]
- Mentes, A.; Helvacioglu, I.H. An application of fuzzy fault tree analysis for spread mooring systems. Ocean Eng. 2011, 38, 285–294. [Google Scholar] [CrossRef]
- Wang, D.; Zhang, P.; Chen, L. Fuzzy fault tree analysis for fire and explosion of crude oil tanks. J. Loss Prev. Process. Ind. 2013, 26, 1390–1398. [Google Scholar] [CrossRef]
- Hosseini, N.; Givehchi, S.; Maknoon, R. Cost-based fire risk assessment in natural gas industry by means of fuzzy FTA and ETA. J. Loss Prev. Process. Ind. 2020, 63, 104025. [Google Scholar] [CrossRef]
- Kuzu, A.C.; Senol, Y.E. Fault tree analysis of cargo leakage from manifold connection in fuzzy environment: A novel case of anhydrous ammonia. Ocean Eng. 2021, 238, 109720. [Google Scholar] [CrossRef]
- Jamshidi, A.; Yazdani-Chamzini, A.; Yakhchali, S.H.; Khaleghi, S. Developing a new fuzzy inference system for pipeline risk evaluation. J. Loss Prev. Process. Ind. 2013, 26, 197–208. [Google Scholar] [CrossRef]
- Rafie, M.; Samimi Namin, F. Prediction of subsidence risk by FMEA using artificial neural network and fuzzy inference system. Int. J. Min. Sci. Technol. 2015, 25, 655–663. [Google Scholar] [CrossRef]
- Gallab, M.; Bouloiz, H.; Alaoui, Y.L.; Tkiouat, M. Risk evaluation of Maintenance activities using Fuzzy Logic. Procedia Comput. Sci. 2019, 148, 226–235. [Google Scholar] [CrossRef]
- Arbabsiar, M.H.; Farsangi, M.A.E.; Mansouri, H. Fuzzy logic modelling to predict the level of geotechnical risks in rock tunnel boring machine (TBM) tunnelling. Rud.-Geološko-Naft. Zb. 2020, 35, 1–14. [Google Scholar] [CrossRef]
- Nezarat, H.; Sereshki, F.; Ataei, M. Ranking of geological risks in mechanized tunneling by using Fuzzy Analytical Hierarchy Process (FAHP). Tunn. Undergr. Space Technol. 2015, 50, 358–364. [Google Scholar] [CrossRef]
- Kang, M.; Kim, S.; Lee, J.; Choi, H. Development of FE model for simulating electrical resistivity survey to predict mixed ground ahead of a tunnel face. Geomech. Eng. 2022, 29, 301–310. [Google Scholar] [CrossRef]
- Kim, J.; Kim, C.; Kim, G.; Kim, I.; Abbas, Q.; Lee, J. Probabilistic tunnel collapse risk evaluation model using analytical hierarchy process (AHP) and Delphi survey technique. Tunn. Undergr. Space Technol. 2022, 120, 104262. [Google Scholar] [CrossRef]
- Xu, J.-S.; Xu, H.; Sun, R.-F.; Zhao, X.-W.; Cheng, Y. Seismic risk evaluation for a planning mountain tunnel using improved analytical hierarchy process based on extension theory. J. Mt. Sci. 2020, 17, 244–260. [Google Scholar] [CrossRef]
- Saaty, T.L. The analytic hierarchy process: A new approach to deal with fuzziness in architecture. Arch. Sci. Rev. 1982, 25, 64–69. [Google Scholar] [CrossRef]
- Pourghasemi, H.R.; Pradhan, B.; Gokceoglu, C. Application of fuzzy logic and analytical hierarchy process (AHP) to landslide susceptibility mapping at Haraz watershed, Iran. Nat. Hazards 2012, 63, 965–996. [Google Scholar] [CrossRef]
- Zadeh, L.A. Fuzzy sets. Inf. Control 1965, 8, 338–353. [Google Scholar] [CrossRef] [Green Version]
- Guiffrida, A.L.; Nagi, R. Fuzzy set theory applications in production management research: A literature survey. J. Intell. Manuf. 1998, 9, 39–56. [Google Scholar] [CrossRef]
- Naghadehi, M.Z.; Mikaeil, R.; Ataei, M. The application of fuzzy analytic hierarchy process (FAHP) approach to selection of optimum underground mining method for Jajarm Bauxite Mine, Iran. Expert Syst. Appl. 2009, 36, 8218–8226. [Google Scholar] [CrossRef]
- Lin, C.T.; Wang, M.J.J. Hybrid fault tree analysis using fuzzy sets. Reliab. Eng. Syst. Saf. 1997, 58, 205–213. [Google Scholar] [CrossRef]
- Mahmood, Y.A.; Ahmadi, A.; Verma, A.K.; Srividya, A.; Kumar, U. Fuzzy fault tree analysis: A review of concept and application. Int. J. Syst. Assur. Eng. Manag. 2013, 4, 19–32. [Google Scholar] [CrossRef]
- Thaker, S.; Nagori, V. Analysis of fuzzification process in fuzzy expert system. Procedia Comput. Sci. 2018, 132, 1308–1316. [Google Scholar] [CrossRef]
- Siraj, N.B.; Fayek, A.R. Risk Identification and Common Risks in Construction: Literature Review and Content Analysis. J. Constr. Eng. Manag. 2019, 145, 03119004. [Google Scholar] [CrossRef]
- Hillson, D. Extending the risk process to manage opportunities. Int. J. Proj. Manag. 2002, 20, 235–240. [Google Scholar] [CrossRef] [Green Version]
- Ma, Y.; Yang, J.; Li, L.; Li, Y. Analysis on ultimate water pressure and treatment measures of tunnels operating in water rich areas based on water hazard investigation. Alex. Eng. J. 2022, 61, 6581–6589. [Google Scholar] [CrossRef]
- Kang, S.; Cho, G. Numerical study on tunnel design for securing stability at connection between submerged floating tunnel and bored tunnel. J. Korean Tunn. Undergr. Space Assoc. 2020, 22, 77–89. [Google Scholar] [CrossRef]
- Sousa, R.L.; Einstein, H.H. Lessons from accidents during tunnel construction. Tunn. Undergr. Space Technol. 2021, 113, 103916. [Google Scholar] [CrossRef]
Matrix Order | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
---|---|---|---|---|---|---|---|---|---|---|
RI value | 0.00 | 0.00 | 0.58 | 0.90 | 1.12 | 1.24 | 1.32 | 1.41 | 1.45 | 1.49 |
Intensity of the Relative Importance | Definition |
---|---|
1 | Two items are equally influential. |
3 | One is considered slightly influential over another. |
5 | One is considered strongly influential over another. |
Reciprocals of above numbers | When the ith item compared to the jth item is assigned one of the above numbers, the jth item compared to the ith item is assigned its reciprocal. |
Linguistic Class | Fuzzy Set (a, b, c, d) |
---|---|
Very-low | (0, 0, 0.05, 0.1) |
Low | (0.05, 0.1, 0.15, 0.2) |
Medium-low | (0.15, 0.2, 0.25, 0.3) |
Medium | (0.25, 0.3, 0.35, 0.4) |
Medium-high | (0.35, 0.4, 0.55, 0.6) |
High | (0.55, 0.6, 0.75, 0.8) |
Very-high | (0.75, 0.8, 1, 1) |
Symbol | Accident |
---|---|
A1 | Significant tunnel convergence |
A2 | TBM jamming |
A3 | Insufficient TBM reaction force |
A4 | Significant deformation of adjacent infrastructures |
Symbol | Source |
---|---|
S1 | Weathered rock ground |
S2 | Fault zone |
S3 | High groundwater level (>30 m from tunnel depth) |
S4 | Excavation of an enlarged tunnel |
S5 | Connection b/w twin tunnels and an enlarged tunnel |
S6 | Connection b/w a vertical shaft and tunnel |
S7 | Connection b/w double-track tunnels and an enlarged tunnel |
S8 | Tunnel excavation adjacent to infrastructures |
S9 | Cavity |
Accident | Source |
---|---|
Significant tunnel convergence | Weathered rock ground |
Fault zone | |
High groundwater level | |
Excavation of an enlarged tunnel | |
Connection b/w twin tunnels and an enlarged tunnel | |
Connection b/w a vertical shaft and tunnel | |
Connection b/w double-track tunnels and an enlarged tunnel | |
TBM jamming | Weathered rock ground |
Fault zone | |
Insufficient TBM reaction force | Weathered rock ground |
Fault zone | |
Significant deformation of adjacent infrastructures | High groundwater level |
Tunnel excavation adjacent to infrastructures | |
Cavity |
Hazardous Zone Number | Causal Combination | ||
---|---|---|---|
Symbol | Accident | Source | |
1 | A1-S2 | Significant tunnel convergence | Fault zone |
A2-S2 | TBM jamming | Fault zone | |
A3-S2 | Insufficient TBM reaction force | Fault zone | |
2 | A1-[S1,S2] | Significant tunnel convergence | Weathered rock ground |
Fault zone | |||
A2-[S1,S2] | TBM jamming | Weathered rock ground | |
Fault zone | |||
A3-[S1,S2] | Insufficient TBM reaction force | Weathered rock ground | |
Fault zone | |||
A4-S8 | Significant deformation of adjacent infrastructures | Tunnel excavation adjacent to infrastructures | |
3 | A1-[S4,S5,S6] | Significant tunnel convergence | Excavation of an enlarged tunnel |
Connection b/w twin tunnels and an enlarged tunnel | |||
Connection b/w a vertical shaft and tunnel | |||
A4-S8 | Significant deformation of adjacent infrastructures | Tunnel excavation adjacent to infrastructures | |
4 | A1-[S3,S4,S5] | Significant tunnel convergence | High groundwater level |
Excavation of an enlarged tunnel | |||
Connection b/w twin tunnels and an enlarged tunnel | |||
A4-[S3,S8] | Significant deformation of adjacent infrastructures | High groundwater level | |
Tunnel excavation adjacent to infrastructures | |||
5 | A1-[S2,S3] | Significant tunnel convergence | Fault zone |
High groundwater level | |||
A4-S3 | Significant deformation of adjacent infrastructures | High groundwater level | |
6 | A1-[S3,S6] | Significant tunnel convergence | High groundwater level |
Connection b/w a vertical shaft and tunnel | |||
A4-S3 | Significant deformation of adjacent infrastructures | High groundwater level | |
7 | A1-[S2,S3] | Significant tunnel convergence | Fault zone |
High groundwater level | |||
A4-S3 | Significant deformation of adjacent infrastructures | High groundwater level | |
8 | A1-[S3,S6] | Significant tunnel convergence | High groundwater level |
Connection b/w a vertical shaft and tunnel | |||
A4-S3 | Significant deformation of adjacent infrastructures | High groundwater level | |
9 | A1-[S2,S3,S6,S7] | Significant tunnel convergence | Fault zone |
High groundwater level | |||
Connection b/w a vertical shaft and tunnel | |||
Connection b/w double-track tunnels and an enlarged tunnel | |||
A4-[S3,S8,S9] | Significant deformation of adjacent infrastructures | High groundwater level | |
Tunnel excavation adjacent to infrastructures | |||
Cavity | |||
10 | A1-[S3,S6] | Significant tunnel convergence | High groundwater level |
Connection b/w a vertical shaft and tunnel | |||
A4-S3 | Significant deformation of adjacent infrastructures | High groundwater level | |
11 | A1-[S2,S3] | Significant tunnel convergence | Fault zone |
High groundwater level | |||
A4-S3 | Significant deformation of adjacent infrastructures | High groundwater level |
Symbol | Impact |
---|---|
A1 | 0.471 |
A2 | 0.267 |
A3 | 0.137 |
A4 | 0.125 |
Symbol | Probability |
---|---|
A1-[S1,S2] | 0.681 (High) |
A1-S2 | 0.536 (Medium-high) |
A1-[S2,S3] | 0.573 (Medium-high to High) |
A1-[S2,S3,S6,S7] | 0.699 (High) |
A1-[S3,S6] | 0.457 (Medium-high) |
A1-[S3,S4,S5] | 0.544 (Medium-high) |
A1-[S4,S5,S6] | 0.569 (Medium-high to High) |
A2-[S1,S2] | 0.558 (Medium-high to High) |
A2-S2 | 0.538 (Medium-high) |
A3-[S1,S2] | 0.619 (High) |
A3-S2 | 0.521 (Medium-high) |
A4-S3 | 0.407 (Medium-high) |
A4-[S3,S8,S9] | 0.741 (High) |
A4-[S3,S8] | 0.629 (High) |
A4-S8 | 0.572 (Medium-high to High) |
Hazardous Zone Number | Causal Combination | Risk | |||
---|---|---|---|---|---|
Symbol | Impact | Probability | Risk | ||
1 | A1-S2 | 0.471 | 0.536 | 0.253 | 0.396 |
A2-S2 | 0.267 | 0.538 | 0.144 | ||
A3-S2 | 0.137 | 0.521 | 0.071 | ||
2 | A1-[S1,S2] | 0.471 | 0.681 | 0.321 | 0.470 |
A2-[S1,S2] | 0.267 | 0.558 | 0.149 | ||
A3-[S1,S2] | 0.137 | 0.619 | 0.085 | ||
A4-S8 | 0.125 | 0.572 | 0.072 | ||
3 | A1-[S4,S5,S6] | 0.471 | 0.569 | 0.268 | 0.268 |
A4-S8 | 0.125 | 0.572 | 0.072 | ||
4 | A1-[S3,S4,S5] | 0.471 | 0.544 | 0.256 | 0.256 |
A4-[S3,S8] | 0.125 | 0.629 | 0.079 | ||
5 | A1-[S2,S3] | 0.471 | 0.573 | 0.270 | 0.270 |
A4-S3 | 0.125 | 0.407 | 0.051 | ||
6 | A1-[S3,S6] | 0.471 | 0.457 | 0.215 | 0.215 |
A4-S3 | 0.125 | 0.407 | 0.051 | ||
7 | A1-[S2,S3] | 0.471 | 0.573 | 0.270 | 0.270 |
A4-S3 | 0.125 | 0.407 | 0.051 | ||
8 | A1-[S3,S6] | 0.471 | 0.457 | 0.215 | 0.215 |
A4-S3 | 0.125 | 0.407 | 0.051 | ||
9 | A1-[S2,S3,S6,S7] | 0.471 | 0.699 | 0.329 | 0.329 |
A4-[S3,S8,S9] | 0.125 | 0.741 | 0.093 | ||
10 | A1-[S3,S6] | 0.471 | 0.457 | 0.215 | 0.215 |
A4-S3 | 0.125 | 0.407 | 0.051 | ||
11 | A1-[S2,S3] | 0.471 | 0.573 | 0.270 | 0.270 |
A4-S3 | 0.125 | 0.407 | 0.051 |
Rank | Hazardous Zone Number | Risk |
---|---|---|
1 | 2 | 0.470 |
2 | 1 | 0.396 |
3 | 9 | 0.329 |
4 | 5, 7, 11 | 0.270 |
5 | 3 | 0.268 |
6 | 4 | 0.256 |
7 | 6, 8, 10 | 0.215 |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2023 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
Kwon, K.; Kang, M.; Kim, D.; Choi, H. Prioritization of Hazardous Zones Using an Advanced Risk Management Model Combining the Analytic Hierarchy Process and Fuzzy Set Theory. Sustainability 2023, 15, 12018. https://doi.org/10.3390/su151512018
Kwon K, Kang M, Kim D, Choi H. Prioritization of Hazardous Zones Using an Advanced Risk Management Model Combining the Analytic Hierarchy Process and Fuzzy Set Theory. Sustainability. 2023; 15(15):12018. https://doi.org/10.3390/su151512018
Chicago/Turabian StyleKwon, Kibeom, Minkyu Kang, Dongku Kim, and Hangseok Choi. 2023. "Prioritization of Hazardous Zones Using an Advanced Risk Management Model Combining the Analytic Hierarchy Process and Fuzzy Set Theory" Sustainability 15, no. 15: 12018. https://doi.org/10.3390/su151512018
APA StyleKwon, K., Kang, M., Kim, D., & Choi, H. (2023). Prioritization of Hazardous Zones Using an Advanced Risk Management Model Combining the Analytic Hierarchy Process and Fuzzy Set Theory. Sustainability, 15(15), 12018. https://doi.org/10.3390/su151512018