Next Article in Journal
Life Cycle Assessment of Selected Single-Use Plastic Products towards Evidence-Based Policy Recommendations in Sri Lanka
Previous Article in Journal
Recovery of Valuable Metals from Spent LiNi0.8Co0.1Mn0.1O2 Cathode Materials Using Compound Leaching Agents of Sulfuric Acid and Oxalic Acid
Previous Article in Special Issue
Indoor Thermal Environment and Energy Characteristics with Varying Cooling System Capacity and Restart Time
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Analysis of the Impact of Building Shape on Safety Management Cost

1
Department of Architectural Engineering, Daejin University, Pocheon-si 11159, Korea
2
Department of Architectural Engineering, U1 University, Yeongdong-gun 29131, Korea
3
Department of Architectural Engineering, Mokpo National University, Muan-gun 58554, Korea
*
Author to whom correspondence should be addressed.
Sustainability 2022, 14(21), 14171; https://doi.org/10.3390/su142114171
Submission received: 7 September 2022 / Revised: 20 October 2022 / Accepted: 27 October 2022 / Published: 30 October 2022
(This article belongs to the Special Issue Research and Practice of Sustainable Construction Project Management)

Abstract

:
Even if a building has the same building area or number of floors, the effect on construction safety varies depending on the building shape, and thus, safety management cost (SMC) should be calculated differently. If the effect of the building shape on the SMC is clearly analyzed and reflected, a reasonable SMC could be calculated. This study analyzes building shape’s impact on SMC, including apartment buildings’ impact. Following the data collection from 21 projects for this study, an analysis was conducted using the independent variables of the building perimeter (BP), building floor area (BA), and the building shape factor (BSF), and the dependent variable of SMC. As a result of analyzing the correlation between the three main factors and SMC, it was found that the BP, BSF, and BA have a very strong positive Pearson correlation coefficient of 0.876, 0.801, and 0.792, respectively. In the future, the results of this study can be used as supporting data for improving the safety management cost-related system and will develop into a more reliable model through continuous data accumulation and utility verification.

1. Introduction

Despite ongoing attempts to reduce on-site safety accidents, the construction industry is still classified as a high-risk sector with a high fatal-accident rate [1]. According to the data from the Korean Ministry of Employment and Labor (MOEL, 2021), an analysis of accident status in 10 industries in 2019 showed that the construction industry had the highest work accident rate (26.9%) with 25,298 people, followed by the manufacturing industry (25.18%) with 23,684 people, and transportation, warehouse, and telecommunication industry (5.8%) with 5464 people. As per the mortality rate by industry, the construction industry had the highest mortality rate (50.1%) with 428 people, followed by manufacturing (24.1%) with 206 people and others (service) (13.8%) with 118 people. The death toll in construction sites worldwide is alarming as well [2]. In terms of the number of deaths per 100,000 workers on construction sites in Organization for Economic Co-operation and Development countries (International Labor Organization, 2016), Israel had the most at 24.8 people, followed by Mexico (19.5 people), Korea (17.6 people), and Portugal (15.6 people). Additionally, the building site in Israel had the highest mortality toll, with more than 2000 deaths per year when calculated with the whole population.
Design for Safety (DFS), a safety management system for preventing construction accidents by managing risk factors at all stages of construction activity, such as planning, design, construction, and project management, is being used to reduce the construction safety accident rate [3,4,5]. Many construction site safety accidents are related to design. Thus, the accident rate can be reduced if the degree of construction difficulty is accurately considered and reflected during the design stage [6,7,8]. Safety accidents can be decreased if DFS is conducted on structures of varied shapes, and efforts are concentrated on reducing safety accidents at the construction stage. This is because there is a high incidence rate of safety accidents, including fatal accidents, during the construction stage. However, designers with inadequate knowledge of construction safety and site environment often fail to recognize how design might cause risks during the lifecycle of building facilities, including construction, operation, and maintenance [9]. Therefore, even if safety management is implemented using the DFS concept, there are limitations in lowering the safety accident rate during the construction stage [10,11,12,13]. The safety management cost (SMC) suitable for the characteristics of the construction site must be invested in for efficient construction site safety management. Even though structures have the same building area (BA), the cost of safety facilities such as fall prevention nets and safety fences, which account for most SMCs, will vary depending on the shape of the structure [14].
Tang et al. (1997) investigated 576 safety accidents at 18 sites. Therefore, they discovered that the amount of loss caused by accidents, including death at construction sites, exceeded the SMC used to prevent safety accidents [15]. Tam et al. (2004) investigated the safety management status of construction sites in China and concluded that the most influential factor affecting the safety of construction sites is the investment of SMCs suitable for the characteristics of construction sites so that factors related to safety management, such as the provision of personal protective devices, regular safety meetings, and safety education, can be properly implemented [16]. Ahn et al. (2021) identified a reason for the high disaster rate in the construction industry as SMCs that did not match the features of the construction site. They stated that the cost to strengthen safety management cannot be covered if the cost is calculated at a ratio derived in proportion to the overall construction cost without reflecting the characteristics of the building shape, number of floors, and construction period [17]. As such, various studies have been conducted on the importance of SMCs reflecting the characteristics of construction sites.
Therefore, the purpose of this study is to analyze the effect of the building shape on SMCs in the case of apartment buildings. Even if a building has the same BA or number of floors, the effect on construction safety varies depending on the building shape, and thus, SMCs should be calculated differently. If the effect of the building shape on the safety management cost is clearly analyzed and reflected, a reasonable SMC could be calculated. The result of this study could be used as a basis for calculating SMCs reflecting the characteristics of construction sites and will further contribute to lowering the safety accident of the construction industry.

2. Literature Review

2.1. Definition and Calculation Method of Safety Management Cost

The SMC for construction projects in Korea is the cost stipulated to activate safety and health management under the Occupational Safety and Health Act of the MOEL. Depending on the type of construction, a certain amount should separately be appropriated in the construction contract. The ordering body and the constructor will use it only for the safety of workers, such as safety facility expenses, safety-related personnel expenses, and safety reporting equipment. When calculating the construction cost, the direct construction cost is calculated by adding up the direct construction costs for each type of construction process. Afterward, the indirect construction cost is calculated by multiplying the direct construction cost by a certain ratio. One of the indirect construction cost items is the calculation standard of the SMC. Table 1 shows the appropriation standard of the SMC which is determined according to the standards based on the MOEL Occupational Safety and Health Act, Article 72-1 (Appropriation for Occupational Safety and Health Management Expenses of Construction Projects, etc.) [18].
The problem with the SMC calculation method presented in Table 1 is that it is calculated by applying the same ratio to the construction cost once the project is classified, without reflecting the project characteristics such as the building perimeter (BP), building shape, and BA. When the SMC is calculated in this way, the installation cost of safety facilities varies depending on the building shape and the number of floors even for a construction project with the same total floor area. The more complex the building shape, the longer the construction period, increasing the labor cost of the safety manager as well. Under the current system, except for the SMCs calculated by the standard, the construction company must pay for the increased SMCs.
To examine the SMC calculation methods of foreign construction sites, the Labor Ministry’s Labor and Technology Standards Bureau is committed to determining SMCs at overseas building sites in Japan, and it is comparable to the system used in Korea. SMC is included in the common temporary work cost, and safety evaluation is conducted in advance, but the characteristics of the project are not reflected [19]. In the case of Switzerland, as in Korea, SMC is appropriated according to the ratio for each construction type based on the total amount of construction, with no regard to project characteristics [20]. In contrast, the United Kingdom has the Health and Safety Executive which is an agency dedicated to determining time-specific risks under the Construction Design Management system and planning safety precautions to calculate the amount and quantity of safety management measures separately [21].
SMC on construction sites has the highest safety accident and mortality rates worldwide and is a crucial factor directly linked to safety accidents. Therefore, safe and sustainable site management cannot be achieved if the degree of construction difficulty, including the building shape, is not reflected and the SMC is uniformly calculated with a ratio of the construction amount [22,23,24].

2.2. Factors That Influence the Calculation of Safety Management Cost

The following review studies the calculation and influencing factors of SMC. Guha et al. (2013) stated that most of the construction industry’s SMCs are set lower than the actual budget required. They also stated that since the budget for safety management is limited, SMCs should be appropriated based on reasonable standards [25].
Okoye et al. (2014) stated that a large portion of SMCs is safety facility and labor costs. They argued that the SMC must surely be preferentially allocated as per the site’s characteristics for safety performance at construction sites. However, they mentioned that the smaller the construction company, the lower the set SMC than the necessary budget. Consequently, more investment is needed in terms of time and effort [26].
Jin (2011) stated that the most important factor in SMC is safety management labor cost. He stated that if the construction project is prolonged, the burden of labor costs for safety managers will increase, causing insufficient SMCs. In this case, he described that the cost of installing safety facilities such as safety nets to prevent accidents due to falls, etc. would become insufficient [27].
Smallwood (2004) mentioned the designer’s influence on safety accidents at construction sites and said that the safety accident rate at construction sites might vary depending on the design of the building. He claimed that the designer is a critical factor that directly or indirectly affects safety management to lower the safety accident rate at construction sites. In addition, it is possible to improve the design and procurement stage for realistic safety management [28].
Choi et al. (2014) pointed out that SMC does not adequately protect workers from accidents because it is used more in the operation of safety managers than personal protective equipment. In other words, it is difficult to allocate a balanced budget because costs are allocated according to the reinforced regulations within the limited SMC. Thus, balanced safety management cannot be conducted [29].
Hamid (2012) investigated the importance of construction site safety management and the improvements to be made by collecting and analyzing the case data on construction site accidents from the Department of Occupational Safety and Health in Malaysia. He pointed out that unsystematic safety management and poor safety facilities and equipment resulting from inadequate SMCs are the main causes of safety accidents at construction sites. In addition, he said that the expenses paid due to safety accidents at construction sites are 10 times the SMC and that unreasonable SMC causes more expenditure [30].
Ahn et al. (2021) investigated and analyzed the actual spent SMCs for 23 high-rise residential building sites, considering the building shape, the number of floors, and the construction period, and presented an SMC calculation model reflecting the characteristics of the construction sites. According to the analysis of the actual SMC spent at the case sites, the items whose cumulative ratio satisfies more than 80% were facility and labor costs, with safety net installation costs accounting for the biggest percentage of facility costs [17].
As shown above, most studies cited safety-related facility costs, labor costs, and designer’s influence as impacting factors in calculating SMCs. However, no studies have analyzed the direct correlation between building shape and SMCs. Suppose the correlation between the building shape and the SMC is verified. In that case, accurate and reasonable SMCs could be calculated via the building shape. Additionally, when accurate and reasonable SMCs can be calculated by reflecting the characteristics of construction sites, it will be possible to efficiently spend SMCs, such as investing in additional safety facilities or deploying additional safety management personnel. Therefore, this study analyzes the correlation between the building shape and SMC by collecting and analyzing the actual spent SMC data from 21 apartment building sites.

3. Methodology

3.1. Research Method

This study is conducted as shown in Figure 1. First, the existing safety management cost calculation process is investigated. Through this, the problem of the existing safety management cost calculation method is derived. Second, actual safety management cost data are collected for case sites. In addition, BP, BSF, and BA data at the case site are collected. Third, the correlation between the three main factors and SMC is analyzed. Finally, we discuss the results of the study.

3.2. Case Projects Overview

This study collected data on actual spent SMC and building shape factor (BSF) data for 33 apartment building construction sites completed in Korea. The survey period was for 13 months, from July 2020. As a result of reviewing the collected data, 12 sites were excluded because their data on personnel input to safety and the volume of safety nets were unreliable.
Table 2 shows the analyzed 21 sites. The 21 selected apartment building projects had an average construction duration of 33 months, an average of 8 buildings, a total floor area of 174,467 m2, an average BA of 9866 m2, and an average of 18 floors, most of which began to be constructed in 2016 and completed in 2020.
This study investigated the actual spent SMCs for each case project in Table 2. Furthermore, the correlations between the factors affecting the building shape and SMCs were analyzed. The factors for the building shape are discussed in detail in Section 3.3.

3.3. Data Collection for Case Projects

To analyze the correlation between the building shape and the SMC, the BP, BA, and SMC of the 21 construction sites were investigated, and the BSF was calculated based on the additionally investigated data. According to the study by Ahn et al. (2021), the change in the BP due to the building shape in the case of the same BA was described using the BSF. The BSF, which represents the complexity of the building shape, is calculated as shown in Equation (1) [17].
B S F = B P ÷ ( B A × 4 )
Here, BSF: building shape factor, BP: building perimeter, BA: building area.
As shown in Equation (1), the BSF is calculated by dividing the BP of the case building by the BP when it is squared. In other words, the BSF of the case building is determined by the relative ratio of the building when the BSF of the square building is set to 1.
Compared with a square-type building, the BP of a rectangular-type building increases by about 25%, and that of a polygonal-type building increases by about 67%. Figure 2 shows the difference in the BP compared to the similar BA at the case site. The BA of cases A and B are similar to 1050 and 1000 m2, respectively. However, the BP of cases A and B are 170 and 130 m, respectively, showing a difference of about 24%. In other words, in the case of the same BA, if the BP is longer than that of a square building, SMCs increase due to installing fall-preventing nets and additional safety fences and the resulting increase in labor costs. Therefore, the building shape is a critical factor reflecting the characteristics of the construction.
The BP is the sum of the total BPs of the building for each case site. The SMC is calculated as the sum of eight costs: the safety manager’s labor, safety facility, personal protection equipment, safety inspection, safety education, worker healthcare, construction disaster prevention guidance, and headquarters overhead. In this study, the building’s BP, BSF, and BA were selected as the main factors, and the correlation between them and the actual SMC of the case project was analyzed. Through this, the impact of the BP, BSF, and BA on SMCs are to be confirmed. Table 3 shows the BP, BSF, BA, and SMC for each project.

4. Result and Finding

When analyzing the correlation between the SMC and major factors using the data collected at the case site, the correlation coefficients between the SMC and the BP, BSF, and BA were relatively high, respectively at 0.876, 0.801, and 0.792, as shown in Table 4. These correlations are statistically significant because the p-values are less than 0.05. The one most closely related to SMC is the BP, followed by the BSF, and then the BA. In particular, the high correlation between SMC and BP implies that BP has a good influence on SMC.
Additionally, as a result of regression analysis, a strong positive correlation between SMC and BP was established, as shown in Figure 3a. In addition, the regression model has a high explanation power (goodness of fit) with an R2 value of 0.768. This indicates that SMC increases in proportion to the BP. As shown in Figure 3b, there is a strong positive correlation between SMC and BSF. As shown in Table 4, the R2 value is 0.642, which has a relatively high explanation power (goodness of fit). This indicates that the BSF also affects the increase in SMC. As shown in Figure 3c, there is a strong positive correlation between SMC and BA, and the regression model has a high explanation power (goodness of fit) with an R2 value of 0.627, as shown in Table 4. This represents that SMC increases in proportion to the BA. The results are shown in Table 5.
However, the SMC calculated at a legally determined ratio relative to the construction amount does not reflect these characteristics. Therefore, construction companies are paying safety facility expenses, safety manager labor costs, etc., in addition to the legally determined SMC. To meet the strengthened safety management standards, SMC that reflects the site’s characteristics must be calculated.

5. Conclusions

This study used the actual data from 21 apartment construction sites and analyzed the correlation between the building’s BP, BSF, BA, and SMC. However, in this study, only the correlation between the building shape and the safety management cost was analyzed due to the difficulty in data collection. In addition to the building shape, factors such as the number of floors, the number of buildings, the number of workers, and the difficulty of construction are expected to affect safety management costs. In the future, we plan to continuously collect data to prove the relationship between additional factors and safety management costs.
The results of this study are as follows:
First, the correlations between the SMC and the BP, BSF, and BA were analyzed based on the collected data. As a result of analyzing the correlation between the three main factors and SMC, it was found that the BP, BSF, and BA have a very strong positive Pearson correlation coefficient of 0.876, 0.801, and 0.792, respectively. The probability of significance obtained is 0.05 or less, which was statistically significant. The most closely related to SMC is BP, followed by BSF, and then BA. In particular, the high correlation between SMC and BP implies that BP has a good influence on SMC.
Second, the regression analysis showed a strong positive correlation between the SMC and the BP. The regression model had a high explanation power (goodness of fit) with an R2 value of 0.768. This indicates that the SMC increases in proportion to the BP. It was analyzed that a strong positive correlation exists between the SMC and the BSF with an R2 value of 0.642, which signifies a high explanation power (goodness of fit). This indicates that BSF also influences the increase in SMC. Finally, a strong positive correlation is established between the SMC and the BA, and the regression model has a high explanation power (goodness of fit) with an R2 value of 0.627. This indicates that SMC increases in proportion to the BA.
As shown above, the SMC of the construction sites should be calculated by reflecting the characteristics of the construction site, such as the BP, BSF, and BA. Even with a similar residential building as in the case project, the BSF and BP are mostly different. Nevertheless, the same ratio is legally applied when calculating the SMC in the method under the current system. The existing method may cause an insufficient SMC and safety resources such as safety managers or safety facilities not being spent in accordance with the characteristics of the site. Therefore, the calculation method of the SMC must be improved urgently.
An SMC suitable for the characteristics of the construction site must be spent for the safe and efficient safety management of the construction site. Safety facilities such as fall prevention nets and safety fences, which account for the largest portion of SMC, will vary depending on the building shape, even for the same BA. Hence, SMC should be calculated according to the characteristics of the construction site, not the ratio of construction costs.
In the future, the results of this study can be used as supporting data for improving the safety management cost-related system and will develop into a more reliable model through continuous data accumulation and utility verification. In addition, it will be applied to the development of an appropriate safety management cost calculation model for other works such as general construction, civil engineering, and plants.

Author Contributions

Conceptualization, S.S. and B.H.; methodology, B.H.; formal analysis, B.H.; literature survey, B.H. and Y.N.; data curation, B.H.; writing—original draft preparation, B.H. and S.S.; writing—review and editing, B.H. and Y.N.; visualization, B.H.; supervision, S.S.; project administration, B.H.; funding acquisition, B.H. All authors have read and agreed to the published version of the manuscript.

Funding

This research was supported by a grant (NRF-2021R1F1A1046321 and NRF-2021R1C1C2091677) from the National Research Foundation of Korea by the Ministry of Science, ICT, and Future Planning.

Institutional Review Board Statement

Not applicable.

Informed Consent Statement

Not applicable.

Data Availability Statement

Data sharing is not applicable to this article.

Conflicts of Interest

The authors declare no conflict of interest. The funders had no role in the design of the study; in the collection, analyses, or interpretation of data; in the writing of the manuscript; or in the decision to publish the results.

References

  1. Lingard, H.; Rowlinson, S. Occupational Health and Safety in Construction Project Management, 1st ed.; Routledge: London, UK, 2004; pp. 1–460. [Google Scholar] [CrossRef]
  2. Analysis of Industrial Accident Status in 2019. Seoul (Korea): Ministry of Employment and Labor. Available online: https://www.moel.go.kr/english/ (accessed on 13 June 2021).
  3. Goh, Y.M.; Chua, S. Knowledge, attitude and practices for design for safety: A study on civil & structural engineers. Accid. Anal. Prev. 2016, 93, 260–266. [Google Scholar] [CrossRef]
  4. Hadikusumo, B.H.W.; Rowlinson, S. Capturing safety knowledge using design-for-safety-process tool. J. Constr. Eng. Manag. 2004, 130, 281–289. [Google Scholar] [CrossRef]
  5. Hadikusumo, B.H.W.; Rowlinson, S. Integration of virtually real construction model and design-for-safety-process database. Autom. Constr. 2002, 11, 501–509. [Google Scholar] [CrossRef]
  6. Atkinson, A.R.; Westall, R. The relationship between integrated design and construction and safety on construction projects. Constr. Manag. Econ. 2010, 28, 1007–1017. [Google Scholar] [CrossRef]
  7. Dewlaney, K.S.; Hallowell, M. Prevention through design and construction safety management strategies for high performance sustainable building construction. Constr. Manag. Econ. 2012, 30, 165–177. [Google Scholar] [CrossRef]
  8. Ghaderi, R.; Kasirossafar, M. Construction safety in design process. In Proceedings of the Architectural Engineering Conference (AEI) 2011, Oakland, CA, USA, 30 March–2 April 2011; pp. 464–471. [Google Scholar] [CrossRef]
  9. Hossain, M.A.; Abbott, E.L.; Chua, D.K.; Nguyen, T.Q.; Goh, Y.M. Design-for-safety knowledge library for BIM-integrated safety risk reviews. Autom. Constr. 2018, 94, 290–302. [Google Scholar] [CrossRef]
  10. Fonseca, E.D.; Lima, F.P.; Duarte, F. From construction site to design: The different accident prevention levels in the building industry. Saf. Sci. 2014, 70, 406–418. [Google Scholar] [CrossRef]
  11. Zhou, W.; Whyte, J.; Sacks, R. Construction safety and digital design: A review. Autom. Constr. 2012, 22, 102–111. [Google Scholar] [CrossRef]
  12. Hinze, J.; Wiegand, F. Role of designers in construction worker safety. J. Constr. Eng. Manag. 1992, 118, 677–684. [Google Scholar] [CrossRef]
  13. Toole, T.M. Increasing engineers’ role in construction safety: Opportunities and barriers. J. Prof. Issues Eng. Educ. Pract. 2005, 131, 199–207. [Google Scholar] [CrossRef]
  14. Alkaissy, M.; Arashpour, M.; Ashuri, B.; Bai, Y.; Hosseini, R. Safety management in construction: 20 years of risk modeling. Saf. Sci. 2020, 129, 104805. [Google Scholar] [CrossRef]
  15. Tang, S.L.; Lee, H.K.; Wong, K. Safety cost optimization of building projects in Hong Kong. Constr. Manag. Econ. 1997, 15, 177–186. [Google Scholar] [CrossRef]
  16. Tam, C.M.; Zeng, S.X.; Deng, Z.M. Identifying elements of poor construction safety management in China. Saf. Sci. 2004, 42, 569–586. [Google Scholar] [CrossRef]
  17. Ahn, H.; Son, S.; Park, K.; Kim, S. Cost assessment model for sustainable health and safety management of high-rise residential buildings in Korea. J. Asian Archit. Build. Eng. 2021, 21, 3. [Google Scholar] [CrossRef]
  18. Ministry of Employment and Labor. Notice No. 2019-64, Occupation Safety and Health Acts. 13 December 2019. Available online: http://www.law.go.kr/lsInfoP.do?lsiSeq=206708#J30:0 (accessed on 14 June 2020).
  19. Horie, S. Occupational Health Policies on Risk Assessment in Japan. Saf. Health Work 2010, 1, 19–28. [Google Scholar] [CrossRef] [PubMed] [Green Version]
  20. Reinhardt, U.E. The Swiss Health System: Regulated Competition without Managed Care. JAMA 2004, 292, 1227–1231. [Google Scholar] [CrossRef]
  21. Cameron, I.; Hare, B. Planning tools for integrating health and safety in construction. Constr. Manag. Econ. 2008, 26, 899–909. [Google Scholar] [CrossRef]
  22. Buica, G.; Antonov, A.E.; Beiu, C.; Pasculescu, D.; Remus, D. Occupational health and safety management in construction sector-the cost of work accidents. Calitatea 2017, 18 (Suppl. S1), 35. Available online: https://search.proquest.com/docview/1855035362?pq-origsite=gscholar (accessed on 14 April 2020).
  23. Bianchini, A.; Donini, F.; Pellegrini, M.; Saccani, C. An Innovative Methodology for Measuring the Effective Implementation of an Occupational Health and Safety Management System in the European Union. Saf. Sci. 2017, 92, 26–33. [Google Scholar] [CrossRef]
  24. Choi, G.H.; Loh, B.G. Control of Industrial Safety based on Dynamic Characteristics of a Safety Budget-Industrial Accident Rate Model in Republic of Korea. Saf. Health Work 2017, 8, 189–197. [Google Scholar] [CrossRef]
  25. Guha, H.; Biswas, P.P. Measuring construction site safety in Kolkata, India. Int. J. Sci. Eng. Res. 2013, 4, 2138–2143. [Google Scholar]
  26. Okoye, P.U.; Okolie, K.C. Exploratory study of the cost of health and safety performance of building contractors in South-East Nigeria. Br. J. Environ. Sci. 2014, 2, 21–33. [Google Scholar]
  27. Jin, B.G. A Study on the Optimal Allocation of Occupational Safety and Health Expenses According to a Construction Type of Apartment Houses. Master’s Thesis, Chonnam National University, Gwangju, Korea, 16 February 2011. [Google Scholar]
  28. Smallwood, J.J. The influence of engineering designers on health and safety during construction. J. S. Afr. Inst. Civ. Eng. 2004, 46, 2–8. [Google Scholar]
  29. Choi, S.H.; Oh, S.W.; Kim, Y.S. Development of Enforcement Rate for Occupational Safety and Health Management Expense by Construction Project Types and the Percentage of Completion. J. Archit. Inst. Korea Struct. Constr. 2014, 30, 105–114. [Google Scholar] [CrossRef]
  30. Hamid, A.R.A.; Abd Majid, M.Z.; Singh, B. Causes of accidents at construction sites. Malays. J. Civ. Eng. 2008, 20, 242–259. [Google Scholar] [CrossRef]
Figure 1. Research method.
Figure 1. Research method.
Sustainability 14 14171 g001
Figure 2. Comparison of building perimeter relative to building area.
Figure 2. Comparison of building perimeter relative to building area.
Sustainability 14 14171 g002
Figure 3. Scatter diagram of SMC and influence factors.
Figure 3. Scatter diagram of SMC and influence factors.
Sustainability 14 14171 g003
Table 1. Safety management cost appropriation standard [18]. Unit: 1000 USD.
Table 1. Safety management cost appropriation standard [18]. Unit: 1000 USD.
DivisionUnder 436436~43604360 or More
RatioBase Amount
General construction (A)2.93%1.86%4.671.97%
General construction (B)3.09%1.99%4.752.10%
Heavy construction3.43%2.35%4.712.44%
New railroad
and track construction
2.45%1.57%3.851.66%
Special and other constructions1.85%1.20%2.841.27%
Note: 1146 Won = 1 USD as of 30 March 2022 (Bank of Korea).
Table 2. Brief description of the case projects.
Table 2. Brief description of the case projects.
No.Duration
(Months)
No. of
Buildings
Highest FloorAverage FloorTotal Floor Area (m2)Building Area (m2)Total Const. Cost
(1000 USD)
13012221853,717302562,553
2295232163,423295169,736
3352371150,410458172,412
427115756,358782876,584
5278241775,483455478,361
62772720102,252512992,144
73582720106,107535692,301
8422491691,274557393,729
93162920211,53210,46797,781
102962920125,8496325120,475
112972217143,0448668149,576
1227122419157,2138436153,364
134154918146,5528348176,647
143383723160,9017127184,028
1532182013241,06818,242205,560
163111514270,40619,536214,903
1733103522195,6038773224,600
1828152519261,78313,831231,663
193116252077,2783936240,964
2036124325293,55511,653283,148
2136173519811,61942,902377,505
Avg.3383018174,4679866157,133
Note: 1146 Won = 1 USD as of 30 July 2021 (Bank of Korea).
Table 3. Actual BP, BSF, BA, and SMC of case projects. (Unit: 1000 USD).
Table 3. Actual BP, BSF, BA, and SMC of case projects. (Unit: 1000 USD).
No.BP (1) (m)BSF (2)BA (3) (m2)SMC (4)
13759.217.130251089.1
25188.523.929511333.5
33291.812.245811095.1
4916.02.67828939.1
55766.021.445541200.6
67262.825.451291527.2
78528.029.153561338.3
81263.14.255731521.0
95795.214.210,4671261.7
1010,157.431.963252044.6
114459.911.986682064.3
128129.722.283902032.4
139748.026.783482482.8
147379.621.971272877.9
1516,441.730.418,2423217.3
169397.916.819,5362726.2
1717,305.346.287732761.6
1823,590.750.213,8313451.3
1918,879.075.239363040.5
2021,525.749.911,6533627.9
2123,284.080.042,9025373.0
Note: (1) Building perimeter, (2) Building shape factor, (3) Building area, (4) Safety management cost. Exchange rate is 1146 Won/USD as of 30 July 2021 (Bank of Korea).
Table 4. Result of the correlation analysis.
Table 4. Result of the correlation analysis.
DescriptionBPBSFBA
SMCPearson correlation coefficient0.8760.8010.792
Significance probability (both)0.0000.0000.000
N212121
Table 5. Results of regression analysis.
Table 5. Results of regression analysis.
ModelUnstandardized
Coefficients
Standardized
Coefficients
tSig.R2
BStd. ErrorBeta
1Constant980.030242.905 4.0350.0010.768
BP0.1570.0200.8767.9270.000
2Constant1114.804301.717 3.6950.0020.642
BSF49.6548.5050.8015.8380.000
3Constant1430.657266.193 5.3750.0000.627
BA0.1150.0200.7925.6510.000
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Han, B.; Na, Y.; Son, S. Analysis of the Impact of Building Shape on Safety Management Cost. Sustainability 2022, 14, 14171. https://doi.org/10.3390/su142114171

AMA Style

Han B, Na Y, Son S. Analysis of the Impact of Building Shape on Safety Management Cost. Sustainability. 2022; 14(21):14171. https://doi.org/10.3390/su142114171

Chicago/Turabian Style

Han, Bumjin, Youngju Na, and Seunghyun Son. 2022. "Analysis of the Impact of Building Shape on Safety Management Cost" Sustainability 14, no. 21: 14171. https://doi.org/10.3390/su142114171