Reliability-Oriented Distribution System Reinforcement Planning with Renewable Resources Considering Network Restoration and Intentional Islanding
Abstract
1. Introduction
- Integrated Reinforcement-Oriented Reliability Planning Framework: Unlike existing approaches that separately address operational scheduling or switch allocation, this paper proposes a unified planning framework that simultaneously optimizes tie line allocation, normally open (NO) switch placement, feeder upgrades, and substation reinforcement. The framework directly embeds regulatory reliability constraints within the investment decision process, ensuring that infrastructure expansion is both technically and economically justified.
- Hierarchical Contingency Recovery Strategy: To address limitations of single-mode restoration models, a two-level operational hierarchy is developed. The first level performs network reconfiguration for load restoration, followed by a secondary transition to intentional islanded operation when feasible. This coordinated sequencing enhances load recovery capability while reducing excessive capital investment in redundant infrastructure.
- Probabilistic Analytical Reliability Assessment under Multi-Source Uncertainty: In contrast to computationally intensive Monte Carlo-based approaches, the proposed method formulates an analytical probabilistic reliability model that captures load variability, renewable DG intermittency, and component failure uncertainties within a unified optimization framework. This enables efficient evaluation of long-term planning alternatives without sacrificing modeling rigor.
2. Research Design and Modeling
2.1. Probabilistic Operating Scenarios for Integrating Uncertainty into Systems
2.1.1. Load Modeling
2.1.2. PV- and Wind-Based DG Modeling
2.1.3. Developing the Probabilistic Operating Scenario
2.2. Proposed Model for the Reliability-Based Reinforcement Planning
2.2.1. Problem Formulation
- denotes the energy not served at bus during stage , and represents the associated interruption cost penalty in $/MWh.
- is the investment cost of tie line at stage , while represents the investment cost of normally open switch at stage .
- is a binary variable equal to 1 if tie line is selected at stage , and 0 otherwise. Similarly, equals 1 if switch is selected at stage , and 0 otherwise.
- and correspond to the costs of upgrading existing substations and feeders, respectively, with and representing the chosen alternatives for substations and feeders.
- represents the length of feeder in kilometers.
- and are binary variables associated with substation and feeder upgrade decisions, respectively.
- denotes the set of system buses, the set of candidate tie lines, and the set of normally open switches.
- and represent the sets of existing substations and feeders, respectively.
- and correspond to the sets of available upgrade alternatives for substations and feeders.
2.2.2. Distribution System Reliability Assessment with DGs
- Sequence-Path Set for each Bus (): This set includes every element situated on the direct series route that links the main substation to a specific bus. A bus’s operational status is fundamentally governed by the availability of the components within this trajectory. Consequently, a malfunction in any single component along this sequence path triggers a bus outage. This state of inactivity persists until the faulty item is restored, causing a transient loss of power to all associated loads. In other words, if any element in the sequence path fails, the bus experiences downtime until the component is repaired, resulting in a temporary interruption of the connected load.
- Affected Bus Set for Each Contingency (): In the event of a contingency, protection devices isolate the faulty section of the network, causing sustained interruptions for all downstream loads. This set contains only the buses that are impacted by the specific contingency.
- Potential Solutions for Restoration per Contingency (): In the event of a system outage, the protection devices may isolate a portion of the network, forming an island. The restoration process involves repairing the fault and reconnecting the affected loads. However, if alternative restoration paths exist, customers in the isolated section can be reconnected to the main source via switching operations, reducing their downtime from the full repair time to the switching duration.
- A.
- Successful Restoration Conditions (Success Mode 1): Restoration is deemed successful when all of the upcoming conditions are satisfied:
- At-least one restoration path reconnects the isolated island to the main source.
- The restoration path does not exceed the thermal limit of the receiving feeder.
- The substation receiving the transferred loads is not overloaded:
- Bus voltages along the restoration path remain within permissible limits:
- The power balance constraint is satisfied, ensuring that all generation sources supply the total demand and system losses:
- B.
- Successful Islanding Requirements (Success Mode 2): To ensure successful island mode for disconnected loads, it is crucial that the total power generated by the distributed generators (DGs) within the island matches the total load and losses of that island:where is the total DG power inside island , is the total load, and is the total system loss within the island, assumed to be 5% of the islanded load [7]. The outcome consists of two successful modes, namely successful restoration and successful islanding, and one failure mode. The algorithm needs to choose one of these modes for each contingency scenario. Figure 5 presents the flowchart of the proposed general methodology for evaluating distribution system reliability in the presence of DGs.
- C.
- Reliability Indices Calculation: To ensure successful island mode for disconnected loads, it is crucial that the total power generated by the DGs within the island can meet the total demand and losses of that island:
3. Results
3.1. Overview of the Distribution System Studied
3.2. Cases Under Studies and Results
3.2.1. Reliability-Based Reinforcement Planning Considering CDGs
3.2.2. Reliability-Based Reinforcement Planning with Controllable, Wind, and PV
4. Discussion
4.1. Application Limitations and Deficiencies
4.2. Future Research Directions
- Integration of energy storage systems (ESSs): Incorporating ESSs into the planning model to mitigate the intermittency of renewable resources, particularly during extended periods of intentional islanding.
- Dynamic Stability Analysis: Incorporating transient stability constraints into the planning phase would ensure that formed islands remain stable during the initial moments of grid disconnection.
- Dynamic Microgrid Management: Developing advanced algorithms for dynamic boundary definitions of intentional islands, allowing for more flexible load-resource matching across different feeder sections.
- Active Network Management: Integrating demand response programs and real-time distribution automation to enhance the flexibility and speed of the network restoration process.
- Resilience Enhancement: Extending the reliability framework to include resilience metrics that account for HILP events and multi-component failure scenarios.
- Multi-Objective Optimization: Expanding the GA-based metaheuristic to a multi-objective approach could allow planners to simultaneously optimize for reliability, carbon footprint reduction, and power quality indices.
5. Conclusions
Funding
Data Availability Statement
Acknowledgments
Conflicts of Interest
References
- Abid, M.S.; Apon, H.J.; Morshed, K.A.; Ahmed, A. Optimal planning of multiple renewable energy-integrated distribution system with uncertainties using artificial hummingbird algorithms. IEEE Access 2022, 10, 40716–40730. [Google Scholar] [CrossRef]
- Kalantari, A.; Lesani, H. Operation Scheduling of Distribution Network with Photovoltaic/Wind/Battery Multi-Microgrids and Reconfiguration considering Reliability and Self-Healing. Int. J. Energy Res. 2024, 2024, 5724653. [Google Scholar] [CrossRef]
- Sangeetha, P.; Suresh Babu, G.; Vidyasagar, E. Reliability Assessment of Distribution System with the Integration of Distributed Energy Resources and Electric Vehicle Charging Stations. WSEAS Trans. Power Syst. 2025, 20, 14–28. [Google Scholar] [CrossRef]
- Luo, F.; Ge, N.; Xu, J. Power Supply Reliability Analysis of Distribution Systems Considering Data Transmission Quality of Distribution Automation Terminals. Energies 2023, 16, 7826. [Google Scholar] [CrossRef]
- Allan, R.N.; Billinton, R. Reliability Evaluation of Power Systems; Springer Science & Business Media: New York, NY, USA, 2013. [Google Scholar]
- Wang, P.; Billinton, R. Reliability benefit analysis of adding WTG to a distribution system. IEEE Trans. Energy Convers. 2001, 16, 134–139. [Google Scholar] [CrossRef]
- Wang, M.; Yang, M.; Fang, Z.; Wang, M.; Wu, Q. A practical feeder planning model for urban distribution system. IEEE Trans. Power Syst. 2022, 38, 1297–1308. [Google Scholar] [CrossRef]
- Conti, S.; Rizzo, S.A. Monte Carlo simulation by using a systematic approach to assess distribution system reliability considering intentional islanding. IEEE Trans. Power Deliv. 2015, 30, 64–73. [Google Scholar] [CrossRef]
- Conti, S.; Nicolosi, R.; Rizzo, S. Generalized systematic approach to assess distribution system reliability with renewable distributed generators and microgrids. IEEE Trans. Power Deliv. 2012, 27, 261–270. [Google Scholar] [CrossRef]
- Atwa, Y.M.; El-Saadany, E.F. Reliability evaluation for distribution system with renewable distributed generation during islanded mode of operation. IEEE Trans. Power Syst. 2009, 24, 572–581. [Google Scholar] [CrossRef]
- Pirouzi, S.; Zaghian, M.; Aghaei, J.; Chabok, H.; Abbasi, M.; Norouzi, M.; Shafie-khah, M.; Catalão, J.P. Hybrid planning of distributed generation and distribution automation to improve reliability and operation indices. Int. J. Electr. Power Energy Syst. 2022, 135, 107540. [Google Scholar] [CrossRef]
- Wang, P.; Billinton, R. Time-sequential simulation technique for rural distribution system reliability cost/worth evaluation including wind generation as alternative supply. IEE Proc.-Gener. Transm. Distrib. 2001, 148, 355–360. [Google Scholar] [CrossRef]
- Zou, K.; Agalgaonkar, A.P.; Muttaqi, K.M.; Perera, S. An analytical approach for reliability evaluation of distribution systems containing dispatchable and nondispatchable renewable DG units. IEEE Trans. Smart Grid 2014, 5, 2657–2665. [Google Scholar] [CrossRef]
- Celli, G.; Ghiani, E.; Pilo, F.; Soma, G.G. Reliability assessment in smart distribution networks. Electr. Power Syst. Res. 2013, 104, 164–175. [Google Scholar] [CrossRef]
- Conti, S.; Faraci, G.; La Corte, A.; Nicolosi, R.; Rizzo, S.A.; Schembra, G. Effect of islanding and telecontrolled switches on distribution system reliability considering load and green-energy fluctuations. Appl. Sci. 2016, 6, 138. [Google Scholar] [CrossRef]
- Chen, C.; Wu, W.; Zhang, B.; Singh, C. An analytical adequacy evaluation method for distribution networks considering protection strategies and distributed generators. IEEE Trans. Power Deliv. 2014, 30, 1392–1400. [Google Scholar] [CrossRef]
- Alotaibi, M.A.; Salama, M. An efficient probabilistic-chronological matching modeling for DG planning and reliability assessment in power distribution systems. Renew. Energy 2016, 99, 158–169. [Google Scholar] [CrossRef]
- Escalera, A.; Hayes, B.; Prodanovic, M. Reliability assessment of active distribution networks considering distributed energy resources and operational limits. In CIRED Workshop; IET: Stevenage, UK, 2016; pp. 1–4. [Google Scholar]
- Li, W.; Wang, P.; Li, Z.; Liu, Y. Reliability evaluation of complex radial distribution systems considering restoration sequence and network constraints. IEEE Trans. Power Deliv. 2004, 19, 753–758. [Google Scholar] [CrossRef]
- Guo, H.; Levi, V.; Buhari, M. Reliability assessment of smart distribution networks. In Proceedings of the Innovative Smart Grid Technologies-Asia (ISGT ASIA), Bangkok, Thailand, 3–6 November 2015; pp. 1–6. [Google Scholar]
- Neto, C.; da Silva, M.G.; Rodrigues, A.B. Impact of distributed generation on reliability evaluation of radial distribution systems under network constraints. In Proceedings of the International Conference on Probabilistic Methods Applied to Power Systems (PMAPS), Stockholm, Sweden, 11–15 June 2006; pp. 1–6. [Google Scholar]
- da Silva, A.M.L.; Nascimento, L.C.; da Rosa, M.A.; Issicaba, D.; Lopes, J.A.P. Distributed energy resources impact on distribution system reliability under load transfer restrictions. IEEE Trans. Smart Grid 2012, 3, 2048–2055. [Google Scholar] [CrossRef]
- Karafotis, P.A.; Evangelopoulos, V.A.; Georgilakis, P.S. Reliability-oriented reconfiguration of power distribution systems considering load and RES production scenarios. IEEE Trans. Power Deliv. 2022, 37, 4668–4678. [Google Scholar] [CrossRef]
- Villarreal, M.I.Z.; Téllez, A.A.; Krishnan, N.; García, M. Expansion Planning of Electrical Distribution Systems Considering Voltage Quality and Reliability Criteria. Energies 2025, 18, 2822. [Google Scholar] [CrossRef]
- Aguila Téllez, A.; Krishnan, N.; García, E.; Carrión, D.; Ruiz, M. A Probabilistic Framework for Reliability Assessment of Active Distribution Networks with High Renewable Penetration Under Extreme Weather Conditions. Energies 2025, 18, 6525. [Google Scholar] [CrossRef]
- He, C.; Zhou, Y.; Liu, X.; Nan, L.; Liu, T.; Wu, L. Reliability-constrained distributionally robust expansion planning of integrated electricity-gas distribution system with demand response. Energy 2025, 321, 135409. [Google Scholar] [CrossRef]
- Konar, S.; Srivastava, A.K. Mpc-based black start and restoration for resilient DER-rich electric distribution system. IEEE Access 2023, 11, 69177–69189. [Google Scholar] [CrossRef]
- Alanazi, A.; Alanazi, T.I. Multi-Objective Framework for Optimal Placement of Distributed Generations and Switches in Reconfigurable Distribution Networks: An Improved Particle Swarm Optimization Approach. Sustainability 2023, 15, 9034. [Google Scholar] [CrossRef]
- Alotaibi, M.; Salama, M. An incentive-based multistage expansion planning model for smart distribution systems. IEEE Trans. Power Syst. 2018, 33, 5469–5485. [Google Scholar] [CrossRef]
- Alotaibi, M.A. Modeling of Renewable Resources in Distribution System Planning and Operation. Master’s Thesis, University of Waterloo, Waterloo, ON, Canada, 2014. [Google Scholar]
- Alotaibi, M.A. Incentive-Based Expansion Planning and Reliability Enhancement Models for Smart Distribution Systems. Ph.D. Thesis, University of Waterloo, Waterloo, ON, Canada, 2018. [Google Scholar]
- Romero, R.; Franco, J.F.; Leão, F.B.; Rider, M.J.; De Souza, E.S. A new mathematical model for the restoration problem in balanced radial distribution systems. IEEE Trans. Power Syst. 2015, 31, 1259–1268. [Google Scholar] [CrossRef]
- Borges, L.; Falcao, D.M. Optimal distributed generation allocation for reliability, losses, and voltage improvement. Int. J. Electr. Power Energy Syst. 2006, 28, 413–420. [Google Scholar] [CrossRef]
- Moradi, M.; Fotuhi-Firuzabad, M. Optimal switch placement in distribution systems using trinary particle swarm optimization algorithm. IEEE Trans. Power Deliv. 2008, 23, 271–279. [Google Scholar] [CrossRef]
- Allan, R.N.; Billinton, R.; Sjarief, I.; Goel, L.; So, K.S. A reliability test system for educational purposes—Basic distribution system data and results. IEEE Trans. Power Syst. 1991, 6, 813–820. [Google Scholar] [CrossRef]























| Category | References | Methodology | Key Contributions | Research Gaps Addressed by This Paper |
|---|---|---|---|---|
| Traditional Simulation | [6,7,8,14,20] | Monte Carlo (MCS)/Sequential MCS | Detailed probabilistic modeling; captures time-varying wind and load behavior | High computational burden; limited suitability for long-term planning optimization |
| Analytical & Simplified | [9,10,11,12,13,15,16,17,22] | Point Estimate Techniques (POT), Markov Chains, Data Clustering | Improved computational efficiency; suitable for adequacy evaluation | Reduced modeling granularity; limited coordination with restoration strategies |
| Operational & Recovery | [19,21] | Power Flow, Restoration modeling | Focus on thermal limits and backup capacity during contingencies | Often neglects DG intermittency and long-term reinforcement planning |
| Recent ADN Planning | [23,24,25,26,27,28] | Robust Optimization, IPSO, Weather-aware Models | Integration of SAIDI/ENS; self-healing and black-start capabilities | Absence of a unified reinforcement planning framework incorporating hierarchical contingency recovery |
| Cut-in Speed m/s | 3 |
| Rated speed ( m/s | 12 |
| Cut-out speed () m/s | 25 |
| Parameter | Value |
|---|---|
| Nominal Power | (+/−5%) 75.0 W |
| Voltage at Pmax | 46.9 V |
| Current at Pmax | 1.6 A |
| Open Circuit Voltage | 60.1 |
| Short Circuit Current | 1.82 |
| Temperature Coeff. of Voc | (−0.2%/C) |
| Temperature Coeff. of Isc | (+0.04%/C) |
| Nominal Cell Operating Temp. | 43 C |
| Bus (i) | Sequence Path | |
|---|---|---|
| Bus 1 | S/S ⇒ Line 1 | S/S, Line 1 |
| Bus 2 | S/S ⇒Line1 ⇒Line2 | S/S, Line 1, Line 2 |
| Bus 3 | S/S ⇒ Line 1 ⇒ Line 2 ⇒ Line 3 | S/S, Line 1, Line 2, Line 3 |
| Bus 4 | S/S ⇒ Line 1 ⇒ Line 2 ⇒ Line 3 ⇒ Line 4 | S/S, Line 1, Line 2, Line 3, Line 4 |
| Bus 5 | S/S ⇒ Line 1 ⇒ Line 2 ⇒ Line 3 ⇒ Line 4 ⇒ Line 5 | S/S, Line 1, Line 2, Line 3, Line 4, Line 5 |
| Bus 6 | S/S ⇒ Line 1 ⇒Line 2⇒Line 3⇒Line 4⇒Line 5 ⇒Line 6 | S/S, Line 1, Line 2, Line 3, Line 4, Line 5, Line 6 |
| Bus 7 | S/S ⇒ Line 1 ⇒ Line 7 | S/S, Line 1, Line 7 |
| Bus8 | S/S ⇒ Line 1 ⇒ Line 7 ⇒ Line 8 | S/S, Line 1, Line 7, Line 8 |
| Bus 9 | S/S ⇒ Line 1 ⇒ Line 7 ⇒ Line 8 ⇒ Line 9 | S/S, Line 1, Line 7, Line 8, Line 9 |
| Bus 10 | S/S ⇒ Line 1 ⇒ Line 2 ⇒ Line 3 ⇒ Line 10 | S/S, Line 1, Line 2, Line 3, Line 10 |
| Bus 11 | S/S ⇒ Line 1 ⇒ Line 2 ⇒ Line 3 ⇒ Line 10 ⇒ Line 11 | S/S, Line 1, Line 2, Line 3, Line 10, Line 11 |
| Contingency (C) | Set of Affected Buses (ABC) | Potential Restoration Paths (PRC) |
|---|---|---|
| S/S | 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11 | |
| Line 1 | 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11 | |
| Line 2 | 2, 3, 4, 5, 6, 10, 11 | Tie2 |
| Line 3 | 3, 4, 5, 6, 10, 11 | Tie2 |
| Line 4 | 4, 5, 6 | Tie1, Tie2 |
| Line 5 | 5, 6 | Tie1 |
| Line 6 | 6 | Tie1 |
| Line 7 | 7, 8, 9 | Tie2 |
| Line 8 | 8, 9 | |
| Line 9 | 9 | |
| Line 10 | 10, 11 | Tie1 |
| Line 11 | 11 | Tie1 |
| Feeders | 0.21/km | 8 h |
| Substation | 0.6/100 | 24 h |
| Case No | Stage No | (Location, Sizing) * |
|---|---|---|
| Case Study 1 | 1 | 6 (0), 8 (0.7), 10 (1.5), 16 (0.4), 17 (0.1), 23 (0.9), 25 (0.7), 26 (1.1) 28 (0.4), 34 (2.6), 36 (0.4), 37 (0.3), 38 (0.9), 48 (1.3), and 50 (0.4) |
| 2 | 6 (0.5), 8 (1.4), 10 (1.8), 16 (1.3), 17 (0.7), 23 (1.4), 25 (0.7), 26 (1.2), 28 (0.5), 34 (2.6), 36 (0.5), 37 (0.6), 38 (2.2), 48 (1.4), and 50 (0.7) | |
| 3 | 6 (0.9), 8 (1.9), 10 (2.5), 16 (2), 17 (1.1), 23 (1.7), 25 (0.8), 26 (1.2) 28 (0.5), 34 (2.7), 36 (0.5), 37 (1.2), 38 (3.5), 48 (1.4), and 50 (1.3) | |
| Case Study 2 | 1 | CDG: 6 (0.1), 8 (0.8), 10 (1.5), 16 (0.4), 17 (0.1), 23 (0.8), 25 (0.7), 26(1.1), 28 (0.3), 34 (2.4), 36 (0.5), 37 (0.0), 38 (1.0), 48 (0.9), and 50 (0.8) Wind-DG: 3 (0.1), 13 (1.3), 19 (1.0), 31 (1.9), and 42 (0.3) PV-G: 6 (2.0), 22 (0.6), 32 (1.2), 40 (0.8), and 44 (0.1) |
| 2 | CDG: 6 (0.3), 8 (1.0), 10 (2.1), 16 (1.1), 17 (0.8), 23 (1.1), 25 (0.9), 26(1.4), 7 728 (0.5), 34 (2.5), 36 (0.5), 37 (0.3), 38 (2.2), 48 (1.9), and 50 (0.8) | |
| Wind-DG: 3 (0.1), 13 (1.3), 19 (1.0), 31 (1.9), and 42 (0.3) | ||
| 3 | CDG: 6 (0.3), 8 (1.0), 10 (2.3), 16 (1.7), 17 (1.0), 23 (1.6), 25 (0.9), 26(1.4), 28 (0.5), 34 (2.7), 36 (0.5), 37 (1.2), 38 (2.3), 48 (2.1), and 50 (0.9) Wind-DG: 3 (0.1), 13 (1.3), 19 (1.0), 31 (1.9), and 42 (0.3) PV-DG: 6 (2.0), 22 (0.6), 32 (1.2), 40 (0.8), and 44 (0.1) |
| Installed Tie Lines and N/O Switches | System Components to Upgrade |
|---|---|
| Tie-3 | Feeder route 14–15 (A2, S1) |
| Tie-4 | Feeder route 15–16 (A2, S1) |
| Tie-5 | Feeder route 16–40 (A1, S1) |
| Tie-7 | Feeder route 33–39 (A2, S1) |
| Tie-8 |
| Reinforcement Planning Cost Component | Cost (USD) |
|---|---|
| CENS | 792,680 |
| CTL | 6,992,000 |
| CNOS | 23,500 |
| CUPG | 1,037,040 |
| NPV of total cost | 8,845,220 |
| Installed Tie Lines and NO Switches | Upgraded System Assets |
|---|---|
| Tie 3 | Feeder route 9–10 (A2, S1) |
| Tie 5 | Feeder route 31–37 (A2, S1) |
| Tie 7 | Feeder route 37–43 (A2, S1) |
| Tie 8 | Feeder route 30–43 (A3, S1) |
| Feeder route n104–30 (A3, S1) | |
| Feeder route 16–40 (A2, S2) |
| Reinforcement Planning Costs Breakdown | Cost (USD) |
|---|---|
| CENS | 784,010 |
| CTL | 5,868,000 |
| CNOS | 18,800 |
| CUPG | 2,469,491.9 |
| NPV of total cost | 9,140,302 |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2026 by the author. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license.
Share and Cite
Alotaibi, M.A. Reliability-Oriented Distribution System Reinforcement Planning with Renewable Resources Considering Network Restoration and Intentional Islanding. Energies 2026, 19, 1581. https://doi.org/10.3390/en19061581
Alotaibi MA. Reliability-Oriented Distribution System Reinforcement Planning with Renewable Resources Considering Network Restoration and Intentional Islanding. Energies. 2026; 19(6):1581. https://doi.org/10.3390/en19061581
Chicago/Turabian StyleAlotaibi, Majed A. 2026. "Reliability-Oriented Distribution System Reinforcement Planning with Renewable Resources Considering Network Restoration and Intentional Islanding" Energies 19, no. 6: 1581. https://doi.org/10.3390/en19061581
APA StyleAlotaibi, M. A. (2026). Reliability-Oriented Distribution System Reinforcement Planning with Renewable Resources Considering Network Restoration and Intentional Islanding. Energies, 19(6), 1581. https://doi.org/10.3390/en19061581

