Next Article in Journal
Power System Transition Planning: A Planner-Oriented Optimization Model
Previous Article in Journal
Quantifying and Mapping Biomass Resources in Ireland: A Holistic Assessment of Primary and Secondary Feedstocks
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Strategies to Mitigate Reverse Power Flow in Distribution Networks with High Penetration of Solar Photovoltaic Generation

by
Ivan Santos Pereira
1,
Gustavo da Costa Vergara
1,
Jesús M. López-Lezama
2,
Nicolás Muñoz-Galenao
2 and
Lina Paola Garcés Negrete
1,*
1
Electrical, Mechanical and Computer Engineering School, Federal University of Goiás (UFG), Av. Universitária No. 1488, Goiânia 74605-010, Brazil
2
Research Group in Efficient Energy Management (GIMEL), Departamento de Ingeniería Eléctrica, Universidad de Antioquia, Calle 67 No. 56-108, Medellin 050010, Colombia
*
Author to whom correspondence should be addressed.
Energies 2026, 19(4), 1069; https://doi.org/10.3390/en19041069
Submission received: 28 January 2026 / Revised: 11 February 2026 / Accepted: 17 February 2026 / Published: 19 February 2026

Abstract

The power industry has undergone significant recent changes due to the growing demand for a cleaner and more sustainable energy mix. In this context, the Brazilian government began encouraging distributed generation (DG), making photovoltaic generation a strong trend in the country. However, the expansion of DG may cause negative impacts on the grid, such as reverse power flow (RPF) and overvoltages, which motivates research aimed at mitigating these effects. This study proposes strategies to mitigate RPF in distribution networks with high penetration of photovoltaic generation and evaluates their impacts on the electrical system. Three strategies were analyzed: a battery energy storage system (BESS), a control mechanism using a Grid Zero inverter, and PV Curtailment. The strategies were implemented in OpenDSS on a real distribution network located in São Paulo, Brazil. The assessment involved analyzing power flow in critical transformers and at the substation, as well as monitoring bus voltages and network energy losses. The quantitative results demonstrate that BESS allocation was the superior strategy, reducing technical losses by 61.3% and fully mitigating reverse power flow under steady-state conditions. The Grid Zero inverter eliminated power injection into the grid; however, it increased substation dependency by 59% compared to the baseline scenario. PV curtailment, although achieving the smallest reduction in RPF, proved to be the most effective technique for power quality, limiting the average voltage rise to 0.7%.

1. Introduction

The energy transition stands among the most significant trends in today’s power sector. The formulation of the Sustainable Development Goals (SDGs) by the United Nations underscores the global concern of sustainability, understood as the ability to meet present needs without compromising those of future generations. Among the goals established to promote sustainability, SDG 7 is particularly notable, as it aims to ensure universal access to clean and renewable energy [1]. The fundamental principle is that a sustainable society must be able to meet its energy demands through sources that do not harm the environment or intensify climate change. As a result, governments around the world have come under pressure from society to encourage the adoption of clean and renewable energy sources.
Electricity generation in Brazil is predominantly based on renewable sources, as shown in Table 1 [2]. This profile is largely attributable to long-standing public policies that have promoted renewable energy development, reinforcing the country’s historical dependence on hydropower while enabling the expansion of other renewable technologies, including wind, solar, and biomass. Within this framework, and as part of broader strategies to increase the share of sustainable sources in the national energy mix and to accelerate the energy transition with private-sector involvement, the Brazilian government established a regulatory framework for distributed generation (DG). This process began in 2012 with Resolution No. 482 issued by the Brazilian National Electric Energy Agency (ANEEL) and was later consolidated through the Legal Framework for Distributed Generation, enacted in 2022 [3,4].
The attractiveness of the partial energy credit compensation system, which allows consumers to offset their electricity bills by injecting surplus generation in the distribution system, has driven the growth of solar photovoltaic generation, which currently predominates among DG systems in Brazil. According to data from the Brazilian Photovoltaic Solar Energy Association (ABSOLAR), between 2021 and October 2025, the installed capacity of solar photovoltaic power increased from 14,415 MW to 62,388 MW, representing a growth of 330.6% in only four years [5]. Of this total, approximately 68% comes from DG, which further highlights the relevance of this sector [6]. Unfortunately, the increasing penetration of solar photovoltaic generation into the power grid may also lead to significant technical challenges for electricity utilities. The occurrence of the so-called “duck curve”, a phenomenon in which a period of low demand coincides with the peak generation of photovoltaic plants, is frequent in industrial environments with large distributed generation systems and in power networks with high levels of solar energy penetration [7].
The reversal of power flow—occurring when DG units inject electricity into the distribution system as their production exceeds local demand—can lead to several technical challenges, including bus overvoltage and transformer overloading, thereby jeopardizing the safe and efficient operation of the electrical network [8,9,10].
The interest in harnessing the benefits provided by DG, together with the need to mitigate the adverse effects it may cause, has motivated numerous studies aimed at attenuating reverse power flow (RPF), mitigating voltage rise issues, and improving reliability [11,12,13]. In the specialized literature, several studies can be found that propose strategies to minimize these technical impacts. The authors of [14] showed that the optimized allocation of BESS can effectively reduce energy losses across several benchmark distribution test systems, while simultaneously limiting RPF in distribution networks. In this case, the authors also implement reactive control (RC); nonetheless, smart inverters (SIs) were not considered. In [15], the authors propose several strategies to mitigate overvoltages in a benchmark distribution network with high photovoltaic penetration. Among these, two strategies are shown to be effective in both controlling overvoltages and mitigating reverse power flows: battery-based self-consumption and PV curtailment. In [16], several technologies aimed at mitigating RPF in distribution systems are analyzed, including SIs and BESS. The study concludes that these devices can enhance the electrical system and reduce impacts on centralized resources, although their implementation requires significant structural modifications. The study focuses on the integration of Distributed Energy Resources (DERs) in distribution networks; however, it does not present real-world applications and is limited to a purely theoretical analysis.
In [17], the authors propose an approach for the optimal siting and sizing of a BESS to mitigate RPF in a PV power plant connected to a real distribution system in Thailand. The analysis is divided into three scenarios, each considering a different PV plant capacity. The results show that the proposed BESS configuration effectively reduces RPF, enhances the smoothing of the distribution load curve, and contributes to both energy loss reduction and lower peak power demand. In [18], the authors analyze RPF caused by solar PV integration in low-voltage network branches of a real distribution system in Ghana. Using predictive models derived from simulation data, they estimate average levels of RPF and line overloading at maximum PV penetration. The results further indicate that total branch losses are minimized when PV penetration reaches its highest level. A hybrid algorithm is proposed in [19] to monitor RPF caused by DERs in benchmark IEEE test systems. The proposed approach combines an impedance-based method with a power balance index. Flexible AC power flow control is proposed in [20] to mitigate RPF in distribution networks with PV generation and BESS. The authors evaluate the proposed approach through a series of tests conducted on a real radial distribution system derived from the electricity networks of New South Wales, Australia. An approach to identify possible scenarios of RPF and feasible solutions are proposed in [21]. In this case, the authors present their results using a benchmark IEEE test system instead of a real distribution system.
Studies that assess the impacts of photovoltaic systems and propose strategies to mitigate the adverse effects of RPF are essential for providing technical guidance to utilities in monitoring distribution networks and preventing potential damage. As highlighted in the literature review, most of these studies are conducted using benchmark distribution systems. While this ensures result reproducibility due to data availability, it also limits the demonstration of the real-world applicability of many proposed approaches. Table 2 summarizes the main features of previous studies on RPF in distribution systems, as well as the mitigation strategies adopted, where PVC denotes photovoltaic curtailment. Note that the proposed approach stands out for considering not only a real distribution system but also real irradiance data. Furthermore, three different strategies are implemented to mitigate RPF. The first strategy involves allocating BESS at the buses of the generating units, allowing them to absorb surplus energy during periods of excess generation and discharge it to supply consumers when demand exceeds generation. This control can be implemented in a straightforward manner through electronic inverters in current photovoltaic systems. The second strategy consists of directly blocking the injection of energy into the grid through inverters that monitor the power flow at the bus and are designed to prevent flow reversal, equipment commonly employed in Grid Zero systems. Finally, the third strategy involves dynamically limiting the rated power of photovoltaic modules through a control implemented in an inverter that uses the bus voltage as a reference signal.
All simulations were carried out using OpenDSS, developed by the Electric Power Research Institute (EPRI) [22]. The tests were applied to a distribution network in the state of São Paulo over a two-day period, using real solar irradiance data for the modeling of photovoltaic modules and the definition of their operating conditions.
To summarize, the main features and contributions of this research are as follows:
  • The proposed approach leverages Geographic Information System (GIS) georeferencing to collect real solar irradiance data and is validated using a real distribution system to assess its effectiveness in mitigating RPF.
  • Three different strategies for mitigating reverse power flow are implemented and compared, namely the use of BESS, smart inverters, and photovoltaic curtailment.
  • All simulations are carried out using OpenDSS, a free and open-source software that enables the modeling and analysis of distribution networks, ensuring accessibility and reproducibility of the results for the scientific community.

2. Materials and Methods

The methodology of this work initially comprises the description of the technical data of the network used in the simulations, including the definition of photovoltaic module parameters and the criteria for selecting the buses for their installation. Subsequently, the process of extracting, processing, and georeferencing irradiance data is detailed, which serve as input variables for the modeling of photovoltaic modules. Finally, the three case studies adopted are presented, detailing their implementation in the software and the expected results.
The electrical network data were imported into Python 3.11.9 to generate the OpenDSS version 10.1.0.1 scripts with their corresponding parameters. Using the geographic coordinates of each network bus, the buses were associated with grid cells. The irradiance data acquisition process consisted of creating equidistant points spaced at 500 m covering the feeder area, for which irradiance data were downloaded. These data were then processed in Python, linked to the corresponding grid cell of each point, and used to compute both the overall average and the hourly average irradiance values for each bus.

2.1. Network Data and System Modeling with Distributed Generation

The distribution network used is a real and simplified system of a feeder circuit in the state of São Paulo. This electrical network comprises 2932 buses interconnected by 2622 distribution line segments, 335 step-down transformers, and 333 loads. The system is three-phase, unbalanced, and operates at medium voltage (13.8 kV) and low voltage (380 V phase-to-phase or 220 V phase-to-ground). To ensure reproducibility, all the information used in the research is available in [23].

2.1.1. Line Segments

The distribution line segments interconnect the buses of the electrical system and operate at both voltage levels of the network. The information related to these lines is presented in Table 3. In this case, the first column indicates the label of the line segments as provided by the utility. In addition to this information, the original database also includes conductances (G0 and G1) and susceptances (B0 and B1), both expressed in μ S.

2.1.2. Loads

The load data were organized according to the standard of Table 4. The parameters considered relevant for modeling in OpenDSS include nominal voltage, number of phases, apparent, active, and reactive power, as well as the power factor. The power values reported for the loads correspond to the maximum values for each load and were obtained from the local electric utility. Most loads in the network are three-phase, although single-phase loads are also present. All loads operate at low voltage: three-phase loads at 380 V and single-phase loads at 220 V. In addition, load curves were assigned to the consumption points to enable the visualization of energy consumption variations throughout the day. These curves were modeled using three typical profiles (residential, commercial, and industrial), based on the study presented in [24], representing different types of consumers. The curves, illustrated in Figure 1, were randomly distributed among the loads of the network.
It is important to note that the distribution network used in the study is a simplified model, which implies that each load does not represent an individual consumer, but an aggregate consumption point connected to the secondary side of a step-down transformer. Therefore, no explicit power limits were considered for low voltage loads in the modeling framework.

2.1.3. Transformers

All distribution transformers in the network are step-down units, reducing the medium-voltage level (13.8 kV) to either 380 V or 220 V. Transformers that step down to 380 V are three-phase, while those that step down to 220 V are single-phase. All transformers are connected in a delta–wye configuration and exhibit typical apparent power ratings ranging from 5 kVA to 300 kVA. Table 5 shows the format of the data used. In addition to the listed information, the original database also provides the positive-sequence impedance in per unit (p.u.).

2.1.4. PVSystem

The photovoltaic modules were installed at the 90 buses of the distribution network that exhibited the highest power demands. The calculation of the rated power of each module was performed using Equation (1) which was developed using a strategy analogous to that adopted for the sizing of photovoltaic generators in [25].
P module = C ( p . u . ) · P load · 30 T min 0.8 · P S H · 30
where
  • C (p.u.) represents the load consumption in per unit at the same bus where the generator is allocated. This value is obtained using the load curve assigned to the corresponding bus.
  • P l o a d is the rated power of the load installed at the bus, expressed in kW.
  • T m i n corresponds to the energy consumption value associated with the availability charge, in accordance with ANEEL regulations. This represents the amount that will always be billed by the utility, even if the consumer does not consume any energy during the billing period. For single-phase loads, the value is 30 kWh, while for three-phase loads it is 100 kWh [26].
  • Peak Sun Hours (PSH) refer to the number of daily hours during which solar radiation would have an intensity equivalent to 1000 W/m2 (1 kW/m2) to generate the same total daily energy received at the site. They were empirically calculated using irradiance data collected through GIS. The irradiance data were obtained from satellite sources using the Python pvlib library. For the test system, this value was calculated based on the regional irradiance data, collected from the same satellite-derived dataset, and results in 5.18 h.
In Equation (1), a constant value of 0.8 was included to account for the energy losses of the inverter. The power ratings of the modules calculated using Equation (1) were inserted into the software as the maximum power point (Pmpp) of each generator. The irradiance curves assigned to the modules were defined based on the obtained data and processed as described in the next subsection. The irradiance curves were subsequently normalized using a factor of 0.98 kW/m2. For the remaining technical parameters of the generators, such as the inverter efficiency curve as a function of input power and the temperature curve, typical values provided in the OpenDSS tutorials were adopted [27]. The photovoltaic modules were modeled using the element PVSystem from OpenDSS and all the parameters mentioned. Finally, the number of phases of each module was defined in accordance with the type of load connected to the corresponding bus.
Note that the substation was configured with a per-unit voltage of 1.05 and three-phase and single-phase short-circuit power levels of 20 MVA and 21 MVA, respectively. These values are traditionally adopted for systems with characteristics similar to those of the test system.

2.2. Data Extraction via GIS

This study stands out for employing irradiance data derived from a satellite-based dataset in the modeling of photovoltaic modules, ensuring greater fidelity in the simulation of the analyzed scenarios. The acquisition and processing of these data were carried out using the method presented in [28], which employs the libraries pvlib, pandas, geopandas, matplotlib and shapely in Python, in addition to Geographic Information System (GIS) tools. Based on this procedure, daily irradiance curves were generated and subsequently assigned to the feeder buses according to their respective geographic coordinates.
To facilitate the understanding of the method, its description is organized into two stages: (i) data extraction and (ii) assignment of these data to the system buses.

2.2.1. Extraction of Irradiance Data

The data used in this study were obtained through the library pvlib python [29], which accesses the databases of the PV-GIS platform (Photovoltaic Geographical Information System). This platform is an online tool developed to provide solar irradiance data and photovoltaic module performance information for any region of the world, with the exception of the North and South Poles. The platform is managed by Joint Research Centre, a European Commission service for science and knowledge that provides independent scientific advice to support European Union policies. The database used in this study is “PVGIS-SARAH3”. To determine the coordinates from which the irradiance data would be collected, the following information is indicated [28].
  • The initial coordinate: The geographic coordinate [960,200, 8,142,500] was selected as the initial coordinate and defined as a vector. This coordinate represents the first sampling point.
  • An equation to generate the new sampling points: A point is parameterized around another point using a radius and an angle. In other words, the equation makes it possible to obtain a new point ( X 2 , Y 2 ) from an initial point ( X 1 , Y 1 ) by shifting it in a direction defined by the angle k π / 2 by a given distance p, as shown in Equation (2).
    X 2 Y 2 = X 1 Y 1 + p sin ( k π 2 ) cos ( k π 2 )
    In this work, the step distance p between the points was defined as 500 m, and k is a constant that assumes integer values from 0 to 4. Using this equation, new points were generated up to a maximum radius of 7 km, restricted to the feeder area, which has an extension of 14 km. Figure 2 illustrates the process of creating these sampling points.
    In Figure 2, Point 1, shown in green, corresponds to the point generated in the first iteration, while point 2, shown in orange, represents the point obtained in the second iteration, calculated from the coordinates of point 1. To facilitate visualization, points that would originally overlap were displayed side by side. Thus, point 1 and the point identified as “k = 3” (in orange) occupy the same position, as do point 2 and the point identified as “k = 1” (in green). However, the process does not generate overlapping points; whenever a newly generated point coincides with an existing one, it is simply discarded. In this work, a total of 841 points were generated, covering the entire area occupied by the feeder.
  • Irradiance data acquisition: Using the Python pvlib library, irradiance records were obtained for the coordinates of the 841 generated points. The retrieved data correspond to the period from 2011 to 2015 and are provided as global irradiance values for each hour of every day within this interval. The selection of this period was based on data availability, following the methodology adopted in [28].
  • Calculation of hourly averages: After extraction, the irradiance data were stored in a Python list, and from this data, both the average irradiance values for each point—using records from 2011 to 2015 and disregarding null values—and the hourly average irradiance values at each point were calculated, obtained by grouping the measurements according to the hour of the day. The former were used to generate a grid with different color intensities representing the irradiance level at each location, while the latter served as the basis for constructing the irradiance curves employed in the modeling of the photovoltaic modules.

2.2.2. Allocation and Processing of Irradiance Data

Once the irradiance data were extracted, the following procedure was carried out [28]:
  • Creation of Irradiance Grids: Using Equation (3), four new points are generated from each sampled point generated in the previous procedure. The new points serve as the vertices of the squares that make up the grid.
    X 2 Y 2 = X 1 Y 1 + p 2 2 sin ( k π 4 ) cos ( k π 4 )
    The above equation is applied iteratively until all 841 sampled points have been processed. This procedure is illustrated in Figure 3.
  • Assignment of Irradiance Values to the Grid: The formed grids are polygons whose geographic coordinates have been recorded in a GeoDataFrame. After their creation, the average irradiance values and the hourly average irradiance values were incorporated into the GeoDataFrame of the grids.
  • Irradiance Data Allocation to the Buses: For this purpose, the geographic coordinates of the system buses were cross-referenced with those of the grids created in the previous steps. It was necessary to load the electric grid data into the code in Python and convert it into a GeoDataFrame containing each bus and its respective geographic coordinate. Finally, the buses were assigned the irradiance data from the grids in which they were spatially located.
The grids were plotted on a map with their respective average irradiance values, and the network data were subsequently modeled for the creation of the map shown in Figure 4.

2.3. Case Studies

The case studies were defined by comparing the original electrical grid with the grid incorporating DG, and evaluating its performance after applying three different strategies to mitigate RPF.
In all cases, the simulation mode used was daily for a 48-h period (two days). This mode was chosen to allow the observation of the effects of generation and consumption variations throughout the day and, additionally, to enable the analysis of battery operation under steady-state conditions. This is due to the fact that, in OpenDSS, the batteries start the simulation fully charged, which influences their operational behavior during the first day.

2.3.1. Base Case

The electric grid was initially simulated in its normal operating state, without the presence of photovoltaic plants. The conditions obtained under this configuration allow for a comparison of the grid’s performance after the integration of photovoltaic plants and after the application of the evaluated RPF mitigation strategies. Thus, the results of this base case serve as a reference for the analysis of the other simulated scenarios.

2.3.2. DG Base Case

The electric grid was simulated considering the allocation of 90 photovoltaic solar plants, selected among the load buses with the highest installed power. Together, these 90 buses represent approximately 66% of the feeder’s total consumption power, characterizing a scenario of high photovoltaic solar generation penetration.
The modeling of the photovoltaic modules follows the procedure described in Section 2.1.4. The solar plants were allocated to the 45 loads with the highest nominal power. The evaluated strategies were applied only to these buses, as implementing them to all solar-equipped buses would be economically unfeasible. Table 6 presents the descriptive statistics of the 45 allocated solar plants.

2.3.3. Case 1—Battery Storage System

This case corresponds to the electric grid of the standard scenario with distributed generation (90 solar plants), augmented by the allocation of 45 batteries installed at the 45 buses with the highest load power. Each battery has a nominal power equal to twice the installed power of the load at its respective bus, as well as a storage capacity equal to eight times its own nominal power.
The sizing of these two parameters was carried out empirically, after observing that the simulations exhibited better performance in mitigating RPF when the adopted power was equivalent to twice the load. In comparison, adopting a power equal to the load for the battery connected to the same bus resulted in inferior performance, even when the stored energy was sized to be numerically equivalent to 20 times its nominal power. Power losses and RPF levels were increased in the last case because the amount of energy that needed to be injected to neutralize the reverse flow, at certain times, exceeded the battery’s maximum power capacity, limiting its ability to fully mitigate RPF.
The battery’s storage capacity was sized to ensure operational autonomy for up to 8 h, based on the understanding that continuous periods of generation surplus or demand for energy supply do not exceed this interval.
The batteries’ charge and discharge curve was calculated to simulate the operation of an electronic inverter capable of monitoring the power flow at the bus. The curve was designed to mitigate RPF, absorbing excess energy and then injecting it when consumption exceeds generation. For this calculation, DG Base Case was first simulated, and the generation curve s of the PV Systems were extracted and compared with the load curves (Load Shapes) from the same bus. The batteries’ curves were calculated by subtracting the load curve values for the generation curve values.

2.3.4. Case 2—Inverter of a Grid Zero System

This case considers the grid operating with an inverter capable of monitoring the power flow and blocking the export of energy from the photovoltaic plants to the network, thereby mitigating RPF. Since this control is not directly implemented in OpenDSS, it was manually implemented using the element “generator” of the software. The generation curves of the PV Systems were extracted from the DG Base Case and modified so that subsequent generation would not exceed the bus load. Therefore, generation was kept unchanged while consumption remained higher than it, and was only adjusted at moments when generation would surpass consumption, at which point it was set to match it. This new generation curve was used in the modeling of the 45 generators located at the buses with the highest load density in the network, while the remaining 45 generators were kept constant and identical to those in DG Base Case.

2.3.5. Case 3—PV Curtailment

In this case, the electric grid was simulated with a control that limits the energy generation of the PV Systems using the bus voltage as a reference. The proposed control was implemented using the “InvControl” element, which performs inverter control in OpenDSS controlling the injection of active or reactive power based on an analyzed parameter, such as the bus voltage.
Given the characteristic of the software’s native control OpenDSS, which prioritizes nodal variables over the direct monitoring of power flow in the branches, the adopted strategy was based on the direct physical correlation between the occurrence of RPF and the rise in voltage levels [15]. Thus, the control function (Volt–Watt), native to OpenDSS was parameterized to act in the joint mitigation of RPF at the transformer and overvoltages at the buses, and was applied to the 45 buses with the highest loads.
The inverter control followed the relationship defined in Figure 5, limiting the active power (Pmpp) in per unit according to the voltage recorded at the bus. Additionally, the OpenDSS inverter parameter “delta P” was set to 0.3, defining the maximum allowed variation in output power between consecutive control intervals.

3. Tests and Results

System performance was assessed by analyzing bus voltage profiles, technical energy losses, substation energy demand, and RPF measured at selected points within the network. This comprehensive evaluation enables a clear comparison of the benefits and limitations associated with each strategy, thereby supporting informed conclusions regarding their practical feasibility, operational suitability, and the potential adaptations required for real-world implementation.

3.1. Reverse Power Flow

3.1.1. Base Case

To enhance the objectivity of the analysis, attention was focused on the two transformers exhibiting the most severe RPF conditions, namely those with the highest magnitudes of injected power, as well as on the substation output to assess the overall system behavior. For comparison purposes, Figure 6, Figure 7 and Figure 8 present the power flow profiles of these elements under the Base Case scenario, which represents the distribution network without photovoltaic generation. In all cases, the reported power flows correspond to three-phase values.
Note that the power flow profiles of Transformers 28 and 70 follow the residential and industrial load curves, respectively, as these are the only load types connected to the secondary sides of the corresponding transformers. The monitoring and recording of the power flow of these elements were performed using the “Monitor” element of OpenDSS.

3.1.2. DG Base Case

Figure 9, Figure 10 and Figure 11 are also included as reference cases for comparison with the three mitigation strategies evaluated in this work. The corresponding scenario is generically referred to as the “DG Base Case,” representing the distribution network with the integration of 90 photovoltaic plants. For completeness, the Base Case curves for the same elements—corresponding to the network without photovoltaic generation—are also displayed in the figures. A simple analysis reveals a pronounced pattern of RPF in both the transformers and at the substation output, indicating a concerning scenario for the network in question.
The two transformers selected for the analysis (28 and 70), are three-phase transformers with nominal powers of 225 kVA and 112.5 kVA, respectively. Therefore, transformer 70 is overloaded, as the RPF recorded reached peaks of 125 kW. This also represents a critical scenario for this study case.

3.1.3. Case 1—Battery Storage System

The results for Case 1 are presented in Figure 12, Figure 13 and Figure 14. In this scenario, 45 BESS were allocated at the buses with the highest nominal load levels. The results show an almost complete attenuation of RPF on the second day of the simulation, that is, after the initial 24 h period. The behavior observed during the first day reflects the transient operation associated with the batteries starting at a 100% state of charge, which limits their ability to absorb all excess energy during this interval. For validation purposes, the system performance on the second day is considered representative of cyclic steady-state operation, during which the batteries fully absorb surplus generation and effectively mitigate RPF.

3.1.4. Case 2—Inverter of a Grid Zero System

The simulation results for Case 2 are illustrated in Figure 15, Figure 16 and Figure 17, which correspond to the transformers and the substation input analyzed in this study, as well as to the remaining network elements affected by the proposed method.
Case 2 represents the operation of electronic inverters that restrict energy injection into the grid by manually shaping the generation output curve. As expected, the results exhibit an almost complete suppression of reverse power flow at the two analyzed transformers.
However, applying this control strategy to only 45 buses proved insufficient to fully eliminate reverse power flow at the substation output. Similar to the PV Curtailment approach, this outcome highlights the main economic trade-off associated with the method: network protection is achieved through aggressive generation curtailment, which directly affects the photovoltaic system’s payback by discarding available energy.

3.1.5. Case 3—PV Curtailment

Figure 18, Figure 19 and Figure 20 illustrate the power flows of the sampled elements for Case 3, in which the PV Curtailment was applied. A more irregular behavior can be observed, as RPF was not eliminated in transformer 70, and in transformer 28, the attenuation of the flow led to the return of consumption predominance over generation, even during peak solar incidence periods. Therefore, the strategy was less effective in mitigating the RPF of transformer 70 compared to the strategies in Case 1 and Case 2.
The reduced effectiveness of PV Curtailment in mitigating RPF is primarily attributed to the physical characteristics of the network. In low-impedance (strong) circuits, substantial power injections may occur without inducing significant voltage deviations, rendering Volt–Watt control schemes largely insensitive to reverse current flow at the point of connection. Nevertheless, despite this limitation at the local level, the strategy achieved a noticeable reduction in RPF at the substation output, effectively attenuating upstream reverse flows and improving overall system performance.

3.2. Energy Injected into the Network

In a more general scenario, the power flows of all 335 transformers were computationally analyzed to calculate the total amount of energy injected into the grid by the photovoltaic modules in each case. The transformer power flows were exported to CSV (Excel) files, whose data were read and managed via Python for the total sum of all negative instantaneous powers. As a result of this procedure, it was concluded that there was an injection of 47,737.24 kWh in DG Base Case; 23,925.45 kWh in Case 1; 17,105.15 kWh in Case 2; and 21,074 kWh in Case 3. All cases reduced the amount of energy injected, with Case 2 showing the largest reduction and Case 1 the smallest. However, some observations should be noted:
(1) Case 2 presents the results of an ideal inverter operation, simulated through a manually designed generation curve and assigned to a generator.
(2) Case 1 was influenced by the initial state of the battery, since the battery starts the simulation fully charged due to the configuration of OpenDSS. Therefore, it cannot absorb all the excess energy to mitigate the RPF on the first day, as already observed in the figures showing the power flow of transformers 70 and 28. As a result, the energy injected ended up being higher for this case.

3.3. Voltage Levels

The evaluation of bus voltage levels was performed using the “Monitor” element of OpenDSS, which can be configured to record hourly values of voltage, current, and instantaneous power for a specific network element. A total of 333 monitors were deployed to track the voltage at the output terminals of all loads in the system. The recorded bus voltages were compared against those obtained in the Base Case, and the differences were computed to quantify voltage rises or drops across the network.
To ensure a more objective presentation of the results, the average percentage voltage rise was computed for each study case by considering all buses in the network. In addition, the maximum percentage voltage rise observed in each scenario was also determined. These metrics are summarized in Table 7.
From the results, it was observed that Case 3, the PV Curtailment, showed the greatest reduction in voltage rise among the three proposed cases, likely because it synchronized the reduction of energy injection with the voltage peaks. Case 1 exhibited the highest average voltage rise, while Case 2 presented the highest individual voltage peak among the three cases. Despite differing efficiencies in reducing voltage rises, all three cases achieved better results than DG Base Case, which showed the highest voltage increase levels.

3.4. Energy Losses and Energy Supplied by the Substation

The analysis of energy losses was carried out using the element “Energymeter”, from OpenDSS, which is associated with an element and is capable of obtaining energy losses, maximum power demand, and the energy flow recorded in the network downstream of the element to which the meter is assigned (Energymeter). The meter in question was installed on the distribution line segment connected to the system substation and was used to record energy losses, as well as the energy supplied by the substation in each of the cases. The results are illustrated in Figure 21.
The two cases with the highest energy losses were the Base Case and the DG Base Case, with losses of 3077 kWh and 2312 kWh, respectively. Thus, it can be observed that the three evaluated strategies provided technical improvements to the electrical network in this regard.
It is worth noting that, when allocating 30 photovoltaic plants to the buses with the highest load density of Base Case—following the same modeling and bus selection criteria as in DG Base Case—the network presented losses of 2143 kWh, a value lower than that of DG Base Case (2312 kWh), in which 90 photovoltaic modules were installed. This result indicates that, in DG Base Case, the electrical network may already be operating near or beyond its accommodation capacity, as the increase in photovoltaic generation ended up increasing losses compared to the case with fewer modules, thereby reducing operational efficiency.
Regarding Cases 1, 2, and 3, the adoption of the strategies allowed a reduction in energy losses from the Base Case by 61.36% in Case 1, 44.72% in Case 2, and 37.73% in Case 3. In comparison, DG Base Case reduced losses by only 24.86%. The allocation of batteries to mitigate RPF, a strategy tested in Case 1, produced the best results regarding losses, followed by Cases 2 and 3, respectively.
This result can be explained by the fact that the allocation of batteries favors local energy storage within the system, reducing losses related to transportation through the distribution lines and energy conversion in the transformers.
It is important to highlight that the results of Case 1 were superior, despite the fact that the allocated batteries could not mitigate part of the RPF on the first day due to the initial configuration. In other words, it is possible that the steady-state operation of the batteries could produce even better results.
Finally, the energy supply analysis yielded the results shown in Table 8, which presents the overall results of the simulation involving the most important operational parameters of the network. According to this analysis, Cases 1, 2, and 3 reduced the amount of energy the substation had to supply to the network compared to the Base Case; however, only Case 1 achieved a lower substation demand than the DG Base Case. The substation supplied the network with 42,781 MWh in Case 1, 51,038 MWh in DG Base Case, 81,164 MWh in Case 2, and 81,806 MWh in Case 3.
The logical conclusion is that, although the allocation of photovoltaic modules reduced the amount of energy the substation had to supply—which was 140,694 MWh in the Base Case—the implementation of inverters that limit energy injection into the network, as in Cases 2 and 3, increased the distribution network’s demand for energy from the substation. This indicates that Case 1 provided benefits, while Cases 2 and 3 caused detriment to the network compared to DG Base Case, since reducing the amount of energy that needs to be supplied by large central power plants is one of the main objectives of government incentives for the solar energy sector.
It was observed that the strategy of allocating batteries to the buses with the highest power injections—adopted in Case 1—was the one that provided the greatest reduction in both the energy demand from the substation and the technical losses in the network.
The strategy of PV Curtailment (Case 3), which consisted of controlling the power injected by the photovoltaic modules based on the bus voltage, proved to be the most effective in mitigating voltage rise, and is therefore the most efficient approach for preventing overvoltage.
On the other hand, Case 2, which simulated the ideal performance of inverters capable of monitoring the bus power flow to control energy injection, presented the best results in reducing the energy injected into the network. It is worth noting, however, that the performance of Case 1 in this regard was limited by the initial configuration of the battery.
The analysis of power flow in transformers 70 and 28 indicated greater suppression of RPF in Case 1, considering only the period in which the battery operated properly on the second day. Regarding the flow at the substation output, the three cases showed similar results, in which they attenuated a large part of the 2 MW three-phase reverse flow.
The fact that none of the strategies managed to fully mitigate this flow raises questions about the scale of investments that would need to be made if a scenario similar to this were encountered in practice.

4. Conclusions

The analysis conducted in this study shows that RPF represents a significant impact associated with the increasing penetration of photovoltaic generation in distribution networks. To address this issue, three mitigation strategies are proposed: (i) the allocation of battery energy storage systems; (ii) the use of inverters operating under a Grid Zero scheme, which prevent power injection into the network by monitoring the power flow at the connection bus; and (iii) the implementation of inverters that regulate the power injected by photovoltaic modules as a function of the bus voltage.
Among the three evaluated scenarios, the battery allocation strategy achieved the best overall performance. It demonstrated high effectiveness in suppressing RPF, reducing technical losses, and significantly lowering the demand for energy supplied by the substation. This reduction in substation demand also translates into decreased reliance on energy generated by large centralized power plants, thereby aligning with public policies that promote the integration of distributed generation.
It is concluded that no universal solution exists, as the results obtained for the test system indicate distinct trade-offs among the evaluated strategies. The BESS-based approach exhibits superior technical performance, effectively eliminating RPF and reducing power losses, albeit at the expense of higher investment costs. In contrast, curtailment-based strategies (Grid Zero and Volt–Watt) shift the burden toward operational inefficiency and are therefore viable mainly in scenarios where utilities impose penalties for RPF or enforce strict injection limits. Additionally, the PV curtailment strategy shows further potential for application in distribution systems experiencing overvoltage issues, yielding positive results in mitigating this condition. Future work will incorporate real-world inverter constraints to provide a more realistic and comprehensive assessment.

Author Contributions

Conceptualization, I.S.P., G.d.C.V. and L.P.G.N.; methodology, I.S.P., G.d.C.V. and L.P.G.N.; software, I.S.P., G.d.C.V. and L.P.G.N.; validation, I.S.P., G.d.C.V. and L.P.G.N.; formal analysis, I.S.P., G.d.C.V., J.M.L.-L., N.M.-G. and L.P.G.N.; investigation, I.S.P., G.d.C.V., J.M.L.-L., N.M.-G. and L.P.G.N.; resources, I.S.P., G.d.C.V., J.M.L.-L., N.M.-G. and L.P.G.N.; data curation, I.S.P., G.d.C.V. and L.P.G.N.; writing—original draft preparation, I.S.P., G.d.C.V. and L.P.G.N.; writing—review and editing, I.S.P., G.d.C.V., J.M.L.-L., N.M.-G. and L.P.G.N.; visualization, I.S.P., G.d.C.V., J.M.L.-L., N.M.-G. and L.P.G.N.; supervision, I.S.P., G.d.C.V., J.M.L.-L., N.M.-G. and L.P.G.N.; project administration, I.S.P., G.d.C.V. and L.P.G.N.; funding acquisition, I.S.P., G.d.C.V. and L.P.G.N. All authors have read and agreed to the published version of the manuscript.

Funding

This research was supported by the Programa de Apoio à Pós-Graduação (PROAP) of CAPES—Coordenação de Aperfeiçoamento de Pessoal de Nível Superior. Process SEI/UFG No. 23070.034610/2025-45.

Data Availability Statement

The original contributions presented in this study are included in the article. Further inquiries can be directed to the corresponding author.

Acknowledgments

The authors acknowledge the Conselho Nacional de Desenvolvimento Científico e Tecnológico (CNPq) for the support provided for the development of this work through Call CNPq/MCTI/FNDCT No. 18/2021—Track A—Emerging Groups, process No. 408898/2021-6. The authors also acknowledge the Graduate Program in Electrical and Computer Engineering (PPGEEC) at the Federal University of Goiás and the Department of Electrical Engineering at Universidad de Antioquia.

Conflicts of Interest

The authors declare no conflicts of interest.

References

  1. United Nations. Sustainable Development Goals. Available online: https://brasil.un.org/pt-br/sdgs (accessed on 28 May 2025).
  2. Canal Solar. Energia Solar Amplia Participação na Matriz Elétrica Enquanto Outras Fontes Recuam. Available online: https://canalsolar.com.br/energia-solar-participacao-matriz-eletrica-2/ (accessed on 7 July 2025).
  3. Official Gazette of the Union. Brazil. Law No. 14,300 of 6 January 2022: Legal Framework for Distributed Generation. Available online: https://www.planalto.gov.br/ccivil_03/_ato2019-2022/2022/lei/l14300.htm (accessed on 22 June 2025).
  4. Brazilian Electricity Regulatory Agency (ANEEL). Normative Resolution No. 482 of 17 April 2012. Available online: https://www.aneel.gov.br/sala-de-imprensa-detalhe/resolucao-normativa-no-482-de-17-de-abril-de-2012 (accessed on 22 June 2025).
  5. Brazilian Photovoltaic Solar Energy Association (ABSOLAR). Infographic on the Photovoltaic Solar Energy Market. Available online: https://www.absolar.org.br/mercado/infografico/ (accessed on 28 May 2025).
  6. Agência Brasil. With 22% of the Electricity Matrix, Solar Energy Is the Second Largest Source in the Country. Available online: https://agenciabrasil.ebc.com.br/meio-ambiente/noticia/2025-03/com-22-da-matriz-eletrica-energia-solar-e-a-2-maior-fonte-do-pais (accessed on 28 March 2025).
  7. Ferreira, G.F. Analysis of Power Flow Inversion in an Industrial Electrical Installation with Photovoltaic Solar Energy Generation. Bachelor’s Thesis, Federal University of Goiás, Goiânia, Brazil, 2024. Available online: http://repositorio.bc.ufg.br/handle/ri/26128 (accessed on 27 May 2025).
  8. Stecanella, P.A.J.; Vieira, D.; Vasconcelos, M.V.L.; Ferreira Filho, A.D.L. Statistical Analysis of Photovoltaic Distributed Generation Penetration Impacts on a Utility Containing Hundreds of Feeders. IEEE Access 2020, 8, 175009–175019. [Google Scholar] [CrossRef]
  9. Saldarriaga-Zuluaga, S.D.; López-Lezama, J.M.; Muñoz-Galeano, N. Optimal Coordination of Over-Current Relays in Microgrids Using Unsupervised Learning Techniques. Appl. Sci. 2021, 11, 1241. [Google Scholar] [CrossRef]
  10. Pérez Posada, A.F.; Villegas, J.G.; López-Lezama, J.M. A Scatter Search Heuristic for the Optimal Location, Sizing and Contract Pricing of Distributed Generation in Electric Distribution Systems. Energies 2017, 10, 1449. [Google Scholar] [CrossRef]
  11. León, L.F.; Martinez, M.; Ontiveros, L.J.; Mercado, P.E. Devices and Control Strategies for Voltage Regulation under the Influence of Photovoltaic Distributed Generation: A Review. IEEE Lat. Am. Trans. 2022, 20, 731–745. [Google Scholar] [CrossRef]
  12. Landbrug, A.G.; Dranka, G.G.; Vasques de Oliveira, R. Voltage Control Approach with Dynamic Voltage Reference for PV Distributed Generation Operating under Cloud-Induced Shading Conditions. IEEE Access 2025, 13, 49092–49106. [Google Scholar] [CrossRef]
  13. Karngala, A.K.; Singh, C.; Xie, L. Predictive Reliability Assessment of Distribution Grids with Residential Distributed Energy Resources. CSEE J. Power Energy Syst. 2025, 11, 2598–2609. [Google Scholar] [CrossRef]
  14. Silva, D.J.; Belati, E.A.; López-Lezama, J.M.; Pourakibari-Kasmaei, M. Optimal Allocation and Operation of Battery Energy Storage Systems with Photovoltaic Generation in Modern Distribution Networks: A New Hybrid Approach. IET Renew. Power Gener. 2025, 19, e70114. [Google Scholar] [CrossRef]
  15. Camilo, F.M.; Castro, R.; Almeida, M.E.; Pires, V.F. Assessment of Overvoltage Mitigation Techniques in Low-Voltage Distribution Networks with High Penetration of Photovoltaic Microgeneration. IET Renew. Power Gener. 2018, 12, 649–656. [Google Scholar] [CrossRef]
  16. Hasan, S.; Tan, C.S.; Toh, C.L. Reverse Power Flow in Distribution Networks: Impacts, Challenges, Issues, and Technologies. In Proceedings of the 2024 IEEE 22nd Student Conference on Research and Development (SCOReD); IEEE: New York, NY, USA, 2024; pp. 19–24. [Google Scholar] [CrossRef]
  17. Unahalekhaka, P.; Sripakarach, P. Reduction of Reverse Power Flow Using the Appropriate Size and Installation Position of a BESS for a PV Power Plant. IEEE Access 2020, 8, 102897–102906. [Google Scholar] [CrossRef]
  18. Majeed, I.B.; Nwulu, N.I. Reverse Power Flow Due to Solar Photovoltaic in the Low Voltage Network. IEEE Access 2023, 11, 44741–44758. [Google Scholar] [CrossRef]
  19. Dahe, N.A.; Saliba, L.; Mougharbel, I.; Kanaan, H.Y.; Saad, M. Hybrid Algorithm for Monitoring Reverse Power Flow Caused by Distributed Renewable Energy Sources. In Proceedings of the 5th International Conference on Renewable Energies for Developing Countries (REDEC); IEEE: New York, NY, USA, 2020; pp. 1–4. [Google Scholar] [CrossRef]
  20. Ranamuka, D.; Muttaqi, K.M.; Sutanto, D. Flexible AC Power Flow Control in Distribution Systems by Coordinated Control of Distributed Solar-PV and Battery Energy Storage Units. IEEE Trans. Sustain. Energy 2020, 11, 2054–2062. [Google Scholar] [CrossRef]
  21. Holguin, J.P.; Rodriguez, D.C.; Ramos, G. Reverse Power Flow (RPF) Detection and Impact on Protection Coordination of Distribution Systems. IEEE Trans. Ind. Appl. 2020, 56, 2393–2401. [Google Scholar] [CrossRef]
  22. Electric Power Research Institute (EPRI). OpenDSS Manual. Available online: https://sourceforge.net/projects/electricdss/files/OpenDSS/OpenDSSManual.pdf/download (accessed on 15 June 2025).
  23. Santos Pereira, I. Strategies-to-Mitigate-Reverse-Power-Flow—Paper. GitHub Repository. 2025. Available online: https://github.com/Ivanictor/Strategies-to-Mitigate-Reverse-Power-Flow---Paper (accessed on 10 February 2026).
  24. Andrades, G.C.B.; Calaça, M.S.A. Simulation of the Operation of Electric Power Distribution Systems Using OpenDSS. Bachelor’s Thesis, Federal University of Goiás, Goiânia, Brazil, 2016. (In Portuguese) [Google Scholar]
  25. Pinho, J.T.; Galdino, M.A. (Eds.) Engineering Manual for Photovoltaic Systems; CEPEL/CRESESB: Rio de Janeiro, Brazil, 2014. [Google Scholar]
  26. Brazilian Electricity Regulatory Agency (ANEEL). Normative Resolution No. 1,000 of 20 December 2021: Establishes the Rules for the Provision of the Public Electricity Distribution Service. Official Gazette of the Union. Available online: https://www2.aneel.gov.br/cedoc/ren20211000.html (accessed on 2 January 2024).
  27. Radatz, P. OpenDSS Time-Series: Introduction. YouTube Tutorial, Introductory Video of the OpenDSS Time-Series Series. Available online: https://www.youtube.com/watch?v=FbITFvo-vJg&list=PLhdRxvt3nJ8yBSb1r64NB0JS5XHinBgGa (accessed on 15 June 2025).
  28. Arantes, P.C.G. Spatial Simulation of Distributed Generation Integration in Electric Power Distribution Networks. Bachelor’s Thesis, Federal University of Goiás, Goiânia, Brazil, 2023. (In Portuguese) [Google Scholar]
  29. Pvlib Python Development Team. Pvlib Python (Version 0.9.4). Available online: https://pvlib-python.readthedocs.io/en/stable/ (accessed on 15 June 2025).
Figure 1. Load Curves.
Figure 1. Load Curves.
Energies 19 01069 g001
Figure 2. Creation of the sampling points.
Figure 2. Creation of the sampling points.
Energies 19 01069 g002
Figure 3. Generation of Points for Grid Formation.
Figure 3. Generation of Points for Grid Formation.
Energies 19 01069 g003
Figure 4. Feeder map and irradiance intensity levels.
Figure 4. Feeder map and irradiance intensity levels.
Energies 19 01069 g004
Figure 5. Power Injection vs. Bus Voltage.
Figure 5. Power Injection vs. Bus Voltage.
Energies 19 01069 g005
Figure 6. Power Flow of Transformer 28 in the Base Case.
Figure 6. Power Flow of Transformer 28 in the Base Case.
Energies 19 01069 g006
Figure 7. Power Flow of Transformer 70 in the Base Case.
Figure 7. Power Flow of Transformer 70 in the Base Case.
Energies 19 01069 g007
Figure 8. Power Flow at the Substation Output in the Base Case.
Figure 8. Power Flow at the Substation Output in the Base Case.
Energies 19 01069 g008
Figure 9. Power Flow of Transformer 28 in DG Base Case.
Figure 9. Power Flow of Transformer 28 in DG Base Case.
Energies 19 01069 g009
Figure 10. Power Flow of Transformer 70 in DG Base Case.
Figure 10. Power Flow of Transformer 70 in DG Base Case.
Energies 19 01069 g010
Figure 11. Power Flow at the Substation Output in DG Base Case.
Figure 11. Power Flow at the Substation Output in DG Base Case.
Energies 19 01069 g011
Figure 12. Power Flow of Transformer 28 in Case 1 (Batteries).
Figure 12. Power Flow of Transformer 28 in Case 1 (Batteries).
Energies 19 01069 g012
Figure 13. Power Flow of Transformer 70 in Case 1 (Batteries).
Figure 13. Power Flow of Transformer 70 in Case 1 (Batteries).
Energies 19 01069 g013
Figure 14. Power Flow at the Substation Output in Case 1 (Batteries).
Figure 14. Power Flow at the Substation Output in Case 1 (Batteries).
Energies 19 01069 g014
Figure 15. Power Flow of Transformer 28 in Case 2 (Grid Zero).
Figure 15. Power Flow of Transformer 28 in Case 2 (Grid Zero).
Energies 19 01069 g015
Figure 16. Power Flow of Transformer 70 in Case 2 (Grid Zero).
Figure 16. Power Flow of Transformer 70 in Case 2 (Grid Zero).
Energies 19 01069 g016
Figure 17. Power Flow at the Substation Output in Case 2 (Grid Zero).
Figure 17. Power Flow at the Substation Output in Case 2 (Grid Zero).
Energies 19 01069 g017
Figure 18. Power Flow of Transformer 28 in Case 3 (PV Curtailment).
Figure 18. Power Flow of Transformer 28 in Case 3 (PV Curtailment).
Energies 19 01069 g018
Figure 19. Power Flow of Transformer 70 in Case 3 (PV Curtailment).
Figure 19. Power Flow of Transformer 70 in Case 3 (PV Curtailment).
Energies 19 01069 g019
Figure 20. Power Flow at the Substation Output in Case 3 (PV Curtailment).
Figure 20. Power Flow at the Substation Output in Case 3 (PV Curtailment).
Energies 19 01069 g020
Figure 21. Network Technical Losses in Each Case.
Figure 21. Network Technical Losses in Each Case.
Energies 19 01069 g021
Table 1. Electricity generation sources in Brazil.
Table 1. Electricity generation sources in Brazil.
Generation SourceParticipation (%)Installed Capacity (MW)
Hydropower42.6110,238
Solar Photovoltaic24.162,388
Wind13.334,473
Natural Gas7.719,869
Biomass and Biogas7.018,022
Oil and Other Fossil Fuels3.07832
Coal1.53951
Nuclear0.81990
Importation3.28170
Table 2. Comparison of reviewed studies to mitigate RPF in distribution systems.
Table 2. Comparison of reviewed studies to mitigate RPF in distribution systems.
RefReal SystemReal Irradiance DataStrategies
YesNoYesNoBESSSIPVCRC
[14] x xx x
[15] x xx x
[16] x x x
[17]x x x
[18]x x x
[19] x x x
[20]x xxx
[21] x x x
This Studyx x xxx
Table 3. Distribution Line Segments.
Table 3. Distribution Line Segments.
LinePhaseOrigin BusDestination BusLength (m)R0 ( Ω )R1 ( Ω )
2964ABC2963296448.210.0960.074
2965ABC2964296527.460.0540.042
2966ABC29652966435.710.0430.026
2967ABC2966296737.070.0450.027
2968ABC2967296835.430.0430.025
2969ABC2968296936.550.0440.026
2970ABC2969297035.220.0430.025
2971ABC2970297133.260.0400.024
Table 4. Load Data.
Table 4. Load Data.
NodePhasekVAkWkvarPF (%)
2400ABC21.0918.659.9688.21
2406ABC18.4916.388.7588.21
2424ABC16.2814.397.6888.21
2438ABC43.5438.4820.5588.21
2448A31.3527.6514.8988.05
2452ABC55.3848.9726.1588.21
2454ABC16.0114.177.5788.21
2472ABC28.4925.2513.4988.21
2481ABC23.8221.0511.2488.21
2518A0.420.370.2088.05
2522A0.500.440.2388.05
2531A1.301.150.6288.05
2539A1.611.420.7688.05
2544A0.100.090.0588.05
Table 5. Presentation of Transformer Data.
Table 5. Presentation of Transformer Data.
From BusTo BusPhasekVAPrimary (kVLL)Secondary (kVLL)Connection
6869B1513.80.22D-Yg
7374ABC11213.80.38D-Yg
5976ABC11213.80.38D-Yg
Table 6. Descriptive statistics of the allocated solar plants.
Table 6. Descriptive statistics of the allocated solar plants.
StatisticValue (kVA)
Mean43.9787
Standard deviation15.9996
Minimum31.9115
25th percentile35.3804
Median (50th percentile)39.5613
75th percentile48.7586
Maximum133.7897
Table 7. Voltage Levels at Network Buses.
Table 7. Voltage Levels at Network Buses.
Study CasesAverage Percentage Rise (%)Maximum Percentage Rise (%)
DG Base Case1.12105.2416
Case 11.23194.3721
Case 21.03475.0665
Case 30.70053.1257
Table 8. Electrical Network Operation Parameters.
Table 8. Electrical Network Operation Parameters.
Study CasesEnergy Supplied by the Substation (kWh)Energy Losses (kWh)Maximum Voltage Rise (%)Energy Injected into the Network (kWh)
Base Case140,69430770%0
DG Base Case51,03823125.2416%47,737.24
Case 142,78111894.3721%23,925.45
Case 281,16417015.0665%17,105.15
Case 381,80619163.1257%21,074.21
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Pereira, I.S.; da Costa Vergara, G.; López-Lezama, J.M.; Muñoz-Galenao, N.; Garcés Negrete, L.P. Strategies to Mitigate Reverse Power Flow in Distribution Networks with High Penetration of Solar Photovoltaic Generation. Energies 2026, 19, 1069. https://doi.org/10.3390/en19041069

AMA Style

Pereira IS, da Costa Vergara G, López-Lezama JM, Muñoz-Galenao N, Garcés Negrete LP. Strategies to Mitigate Reverse Power Flow in Distribution Networks with High Penetration of Solar Photovoltaic Generation. Energies. 2026; 19(4):1069. https://doi.org/10.3390/en19041069

Chicago/Turabian Style

Pereira, Ivan Santos, Gustavo da Costa Vergara, Jesús M. López-Lezama, Nicolás Muñoz-Galenao, and Lina Paola Garcés Negrete. 2026. "Strategies to Mitigate Reverse Power Flow in Distribution Networks with High Penetration of Solar Photovoltaic Generation" Energies 19, no. 4: 1069. https://doi.org/10.3390/en19041069

APA Style

Pereira, I. S., da Costa Vergara, G., López-Lezama, J. M., Muñoz-Galenao, N., & Garcés Negrete, L. P. (2026). Strategies to Mitigate Reverse Power Flow in Distribution Networks with High Penetration of Solar Photovoltaic Generation. Energies, 19(4), 1069. https://doi.org/10.3390/en19041069

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop