Next Article in Journal
Heat Transfer Performance of a Multi-Branch Well System for In-Situ Conversion of Steeply Dipping Oil Shale Reservoirs
Previous Article in Journal
Thermodynamic–Economic Co-Optimization of Condenser Cooling Water Flow Under Time-of-Use Spot Pricing: Marginal Sensitivity and Negative-Price Superposition
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Optimal Placement of Sectionalizing Devices in Radial Distribution Networks for Reliability Improvement Using the Aquila Optimizer

by
Juan José Gaibor Fierro
*,
Alexander Aguila Téllez
* and
Manuel Darío Jaramillo Monge
GIREI Research Group, Electrical Engineering Department, Universidad Politécnica Salesiana, Quito 170146, Ecuador
*
Authors to whom correspondence should be addressed.
Energies 2026, 19(15), 3472; https://doi.org/10.3390/en19153472
Submission received: 29 June 2026 / Revised: 9 July 2026 / Accepted: 21 July 2026 / Published: 23 July 2026

Abstract

Radial distribution networks are highly exposed to sustained service interruptions because faults occurring along upstream feeder sections can affect large groups of downstream customers. This condition motivates the development of cost-effective planning strategies capable of reducing expected energy not supplied (EENS) and improving reliability indices such as the System Average Interruption Frequency Index (SAIFI), System Average Interruption Duration Index (SAIDI), and Customer Average Interruption Duration Index (CAIDI). This study formulates the optimal placement of sectionalizing devices as a binary combinatorial optimization problem in which the objective function minimizes the total expected cost, defined as the sum of customer interruption cost and the annualized investment and installation cost of the selected devices. The formulation considers candidate-branch eligibility, the maximum number of devices, the available investment budget, and the maximum allowable restoration time, while preserving the radial topology of the base feeder by construction. The Aquila Optimizer (AO) is implemented and compared with the Grey Wolf Optimizer (GWO) and a hybrid Genetic Algorithm–Particle Swarm Optimization (GA-PSO) algorithm using the IEEE 69-bus test system under identical population size, iteration budget, number of independent runs, and pseudo-random seed conditions. The results show that the best identified installation of eight sectionalizing devices reduces SAIDI by approximately 58% and the total expected cost by nearly 50% with respect to the base case. SAIFI remains unchanged because the analyzed radial configuration does not include load-transfer paths; therefore, sectionalizing primarily reduces interruption duration rather than interruption frequency. The three algorithms reached solutions of comparable quality around the best identified configuration. GWO exhibited the highest robustness, AO showed a slightly lower computational time than GWO under the adopted MATLAB R2025b-based evaluator, and GA-PSO converged to the same best identified configuration found by GWO. These findings indicate that AO is a competitive computational alternative for sectionalizing-device placement and that a moderate investment in sectionalizing infrastructure can support economically justified reliability improvements in radial distribution networks.

1. Introduction

The continuity of electric power supply is a critical attribute of service quality in distribution systems and is commonly quantified through reliability indices such as the System Average Interruption Frequency Index (SAIFI), the System Average Interruption Duration Index (SAIDI), and the Customer Average Interruption Duration Index (CAIDI), as defined in IEEE Std. 1366 [1]. In radial distribution networks, the existence of a single electrical path between the substation and downstream customers causes faults located in upstream feeder sections to affect large groups of users. This structural characteristic makes the optimal placement of sectionalizing devices one of the most cost-effective alternatives for improving service continuity in distribution feeders [2,3]. Sectionalizing devices allow the faulted section to be isolated and enable the restoration of healthy feeder segments before the definitive repair of the damaged component is completed, either through manual operation or remote-controlled switching depending on the installed technology [4]. Consequently, the placement of these devices has been widely formulated as a mixed-integer optimization problem within distribution-system reliability planning [2,5].
The installation of sectionalizing devices must be planned by balancing the investment required for new equipment against the expected customer interruption cost. For this reason, a total-cost formulation consistent with the actual operating behavior of the feeder is essential [6,7]. Insufficient or poorly located sectionalizing may increase the expected energy not supplied (EENS) and deteriorate regulatory reliability indices. Conversely, excessive sectionalizing may increase capital expenditure without producing a proportional reduction in EENS, thereby compromising the economic feasibility of the reliability-improvement project [4,8]. The problem becomes even more complex when the failure probability of the switching device itself, the coordination between protection and switching equipment, and the operational heterogeneity between manual and remotely controlled devices are considered [4,8,9]. Therefore, the scientific question addressed in this study is how efficiently a recent metaheuristic algorithm can solve a total Scost-based formulation for the optimal placement of sectionalizing devices when applied to the IEEE 69-bus radial distribution system.
Recent studies on sectionalizing-device placement have addressed the problem using increasingly detailed mathematical formulations. Early approaches formulated the problem through mixed-integer programming models that integrate reliability and cost within a single objective function [5]. Subsequent mixed-integer linear programming (MILP)-based formulations incorporated the distinction between manual and remotely controlled devices, enabling a more detailed representation of fault isolation and service restoration processes [2]. Other contributions extended the reliability assessment by evaluating interruptions event by event, estimating outage duration through operational simulations, and validating the resulting model in complex distribution networks [6]. Additional studies introduced the failure probability of the switching device into the customer interruption cost model, showing that neglecting this factor may alter the optimal solution [8]. The scope has also been extended to active distribution networks with distributed generation and uncertainty, where mixed-integer nonlinear programming (MINLP) formulations explicitly include the economic value of power losses [7]. More recent works have differentiated manual and remotely controlled sectionalizing devices through multiobjective formulations based on Pareto fronts between cost and EENS [4]. Alam et al. [10] studied the optimal placement of reclosers in radial distribution systems for reliability improvement, showing that protective-device location has a direct effect on reliability indices and service-continuity performance. At a more advanced level, the simultaneous coordination of reclosers, sectionalizers, and disconnectors, including the relocation of pre-existing equipment, has also been investigated [9]. Despite these advances, the Aquila Optimizer (AO) has received limited attention in the optimal placement of sectionalizing devices in radial distribution networks, mainly because it is a relatively recent metaheuristic in the optimization field [11]. Moreover, there is still a clear need for rigorous and controlled comparisons between AO and consolidated optimization approaches such as the Grey Wolf Optimizer (GWO) and hybrid Genetic Algorithm–Particle Swarm Optimization (GA-PSO) methods under the same mathematical formulation and equivalent experimental conditions [12,13,14,15].
Distribution-system planning has also been studied from broader perspectives that include voltage quality, structural expansion, active losses, generation adequacy, distributed generation, power-electronic interfaces, and reliability under uncertainty. Meng et al. [16] addressed dissipativity-based multiport stability root-cause identification and mitigation for solid-state transformers, showing the increasing relevance of stability and control constraints in modern active distribution systems. However, this contribution is related to power-electronic stability rather than reliability-oriented placement of sectionalizing devices. However, several of these works focus on reliability indices, network expansion, or cost reduction as separate objectives rather than integrating technical and economic criteria into a unified decision-making framework [17,18,19]. This separation limits the practical applicability of the proposed solutions in real planning environments, where the placement of sectionalizing devices must be justified simultaneously in terms of operational impact, implementation cost, and contribution to service continuity [2,4,7]. Zuñiga Villarreal et al. [17] formulated the radial distribution-network expansion problem through a multicriteria objective function that integrates voltage quality, active power losses, and average failure rate. Their study evaluated the effect of demand growth on conductors over a ten-year planning horizon using the IEEE 15-bus and 33-bus systems, showing that early interventions in critical branches may defer investments by up to five years. Nevertheless, their formulation explicitly excludes the placement of sectionalizing devices and does not consider the expected customer interruption cost as a decision variable. Peña et al. [20] assessed the reliability of the Ecuadorian National Interconnected System through a recursive convolution model applied to 369 generation units, calculating loss of load expectation (LOLE), EENS, and the energy index of reliability (EIR) for 2023 and 2024, with projections to 2029 under four availability scenarios. Their results reported LOLE values of 90.71 days per year in 2024, well above the international reference threshold of 0.1 days per year recommended by the North American Electric Reliability Corporation (NERC), identifying hydropower dependence as the main structural vulnerability of the system. However, this work operates at the generation level and does not address distribution-level reliability-improvement mechanisms, particularly the optimal placement of sectionalizing devices for reducing energy not supplied.
Aguila Téllez et al. [19] proposed a probabilistic framework for reliability assessment in active distribution networks with high photovoltaic penetration under extreme weather conditions. Their approach used Monte Carlo simulation on the IEEE 33-bus system with stochastic synthesis of load and generation profiles at a 15 min resolution. The results showed that storm events increased SAIDI by 204.1% with respect to the base scenario and that the benefits of photovoltaic penetration saturated at approximately 30–35%, losing effectiveness under high climatic exposure. Nevertheless, that study modeled protection devices through aggregated failure-rate and restoration-time parameters without incorporating the optimal placement of sectionalizers or a total interruption-cost objective function. Aguila Téllez et al. [18] developed a methodology for the optimal placement of reclosers in radial systems by combining Monte Carlo simulation with a multicriteria assessment weighted through the criteria importance through intercriteria correlation (CRITIC) method over SAIFI, SAIDI, CAIDI, and average energy not supplied (AENS). The methodology generated pseudo-random variables within predefined ranges to represent uncertainty in failure rates and repair times, and its validation through exhaustive search on the IEEE 15-bus system confirmed agreement in more than 90% of the generated scenarios. However, that study considered reclosers as the only device type, did not extend the analysis to sectionalizers, and did not compare the performance of different metaheuristics under a total-cost function that jointly integrates investment cost and expected customer interruption cost. The recurring gap in this body of literature is the absence of a unified and reproducible assessment framework that simultaneously integrates technical and economic criteria for the optimal placement of sectionalizing devices [17,18,19,20], evaluates the behavior of a recently developed metaheuristic such as the Aquila Optimizer [11], and compares it under controlled experimental conditions with consolidated reference algorithms such as GWO and hybrid GA-PSO [12,13,14,15] on a standardized test system such as the IEEE 69-bus feeder. In this context, the scientific contribution is not limited to introducing another optimizer into a known binary placement problem; rather, it lies in quantifying how solution quality, robustness, convergence behavior, computational effort, and reliability improvement interact when different stochastic search mechanisms are applied to the same cost-based sectionalizing-device placement formulation.
Based on these limitations, this work proposes the application of the Aquila Optimizer to the optimal placement of sectionalizing devices in radial distribution networks and compares its performance with GWO and a hybrid GA-PSO algorithm [11,12,13,14]. The proposed framework simultaneously considers reliability performance and economic restrictions within a single optimization model [2,4,7]. The general objective is to determine the optimal location of sectionalizing devices in a radial feeder by using AO as the main optimization technique and by evaluating its behavior against two consolidated metaheuristic references. The decision variables are encoded as a binary vector that indicates the presence or absence of a sectionalizing device in each candidate branch of the IEEE 69-bus system. The objective function minimizes the total expected cost, composed of the customer interruption cost and the installation cost of the selected devices [2,5]. The formulation is subject to candidate-branch eligibility, maximum number of devices, maximum available budget, and maximum allowable restoration time, while the radial topology of the base feeder is preserved by construction [2,8]. SAIFI, SAIDI, and CAIDI are computed as evaluation outputs to verify the reliability improvement obtained with respect to the base case, without being directly embedded in the objective function [1].
The main contribution of this paper is threefold. First, it formulates the sectionalizing-device placement problem as a cost-based binary optimization model in which investment cost and expected customer interruption cost are jointly evaluated, while SAIFI, SAIDI, CAIDI, and EENS are used as post-optimization reliability indicators. Second, it provides a controlled and reproducible evaluation of the Aquila Optimizer for this planning problem by comparing it with GWO and hybrid GA-PSO under identical population sizes, iteration budgets, independent runs, binarization criteria, and pseudo-random seed conditions. Third, it establishes a comparative decision criterion that jointly considers best and mean objective-function values, convergence behavior, dispersion across independent runs, computational time, number of installed devices, and reliability-index improvement. This contribution is intended to clarify the planning value and limitations of AO rather than to claim unconditional superiority over the benchmark algorithms. The main findings show that the best identified installation of eight sectionalizing devices substantially reduces SAIDI and the total expected cost with respect to the base case, while SAIFI remains unchanged because the analyzed radial configuration does not include load-transfer paths. The comparative assessment also shows that the three algorithms reach solutions of similar quality around the best identified configuration, but with differentiated performance profiles: GWO exhibits the highest robustness and lowest dispersion, GA-PSO confirms the best identified configuration by reaching the same optimum, and AO provides the lowest computational time with a near-optimal cost value. These results support the interpretation of AO as a computationally efficient alternative for rapid sectionalizing-device planning analyses, while final investment decisions should still consider economic performance, robustness, and reproducibility across independent runs.
The remainder of this paper is organized as follows. Section 2 presents the theoretical framework, including radial distribution-network modeling, the fundamentals of sectionalizing-device placement, the metaheuristic algorithms considered, and the reliability indices used for performance assessment. Section 3 defines the problem formulation and describes the general planning framework adopted for the IEEE 69-bus test system, including the base-case configuration used as the reference scenario. Section 4 develops the mathematical formulation, including the decision variables, objective function, operational constraints, reliability-output metrics, fitness evaluation, computational-complexity considerations, and implementation details of AO, GWO, and GA-PSO. Section 5 describes the case study, the candidate branches, the reliability and cost parameters, and the base-case configuration. Section 6 presents and discusses the numerical results, including the optimal device locations, reliability improvements, convergence behavior, computational performance, comparative analysis among the algorithms, and practical implementation considerations. Finally, Section 7 summarizes the main conclusions, highlights the practical implications of the proposed approach, and outlines future research directions.

2. Theoretical Framework

This section establishes the theoretical foundations required to support the proposed formulation for the optimal placement of sectionalizing devices in radial distribution networks. The discussion is organized around three complementary axes: the operational characteristics of radial feeders and their relationship with sectionalizing-device placement, the metaheuristic algorithms adopted for solving the resulting binary combinatorial problem, and the reliability indices used to evaluate the technical impact of each candidate solution. This theoretical basis provides the conceptual connection between distribution-network operation, reliability-oriented planning, and the comparative optimization framework developed in this study.

2.1. Radial Distribution Networks and Fundamentals of Sectionalizing-Device Placement

2.1.1. Operation and Modeling of Radial Distribution Networks

Radial distribution networks constitute the most widely used topology in low- and medium-voltage power systems because of their operational simplicity, reduced construction cost, and straightforward implementation of selective protection schemes [21]. In this configuration, each load point is supplied through a single electrical path from the substation. This characteristic simplifies protection coordination and feeder operation, but it also increases the exposure of downstream customers to upstream contingencies, particularly as distribution systems incorporate distributed generation, non-conventional loads, and more complex operating conditions [22]. Therefore, any reliability-improvement strategy in radial feeders must be consistent with the topological structure of the network and with the way faults propagate through the feeder.
The electrical modeling of radial distribution systems requires a precise representation of branch impedances, nodal loads, feeder topology, and power-flow conditions, since these elements determine both the operating state of the system and the technical feasibility of any planning decision [23]. In reliability studies, this modeling must also be complemented by the characterization of failure rates, restoration times, load-point demand, and customer distribution along the feeder. These parameters provide the basis for estimating the expected interruption impact caused by faults and for quantifying the effect of sectionalizing-device placement on service continuity. In the context of this research, the radial topology is preserved by construction, since the candidate solutions only determine the installation or non-installation of sectionalizing devices on predefined branches and do not introduce additional tie lines or network reconfiguration alternatives.

2.1.2. Combinatorial Nature of the Sectionalizing-Device Placement Problem

The optimal placement of sectionalizing devices is naturally formulated as a binary combinatorial optimization problem. Each candidate branch may either receive a sectionalizing device or remain unchanged, which leads to a decision vector whose components represent mutually exclusive installation states. Under this representation, the optimization process must identify the configuration that provides the best balance between the reduction of expected interruption cost and the investment associated with the selected devices, while satisfying technical and economic restrictions [24]. This formulation is consistent with reliability-oriented distribution planning because the value of a sectionalizing configuration cannot be assessed only from its technical effect on interruption indices, but must also account for the economic effort required for its implementation.
The binary encoding of the decision variables causes the search space to grow exponentially with the number of candidate branches. For a feeder with n candidate locations, the number of possible configurations is 2 n , which rapidly makes exhaustive enumeration impractical for realistic distribution systems. This exponential growth, together with the presence of operational constraints and nonlinear reliability responses, motivates the use of metaheuristic optimization techniques capable of exploring large discrete spaces within reasonable computational times [25]. Consequently, the quality of the final solution depends not only on the optimization algorithm itself, but also on the mathematical consistency of the objective function, the definition of the candidate-branch set, the constraint-handling strategy, and the reliability model used to evaluate each binary configuration.

2.1.3. Operational and Economic Constraints of the System

The optimal placement of sectionalizing devices must satisfy a set of operational and economic constraints that ensure the practical feasibility of the solution. In the present research, these constraints include the eligibility of candidate branches, the maximum number of installable devices, the available investment budget, and the maximum allowable restoration time. Since the base feeder remains radial and no new branches are added, radiality is preserved by construction [26]. Therefore, the topological feasibility of the solution is guaranteed by restricting the search to the predefined set of candidate branches, which avoids configurations that would alter the operating structure of the feeder or compromise the coordination logic of the distribution system [27].
The investment budget acts as an economic feasibility constraint because the acquisition, installation, operation, and maintenance costs of sectionalizing devices must remain compatible with the resources available for the reliability-improvement project. Similarly, the maximum restoration-time constraint ensures that candidate configurations remain aligned with the expected operational response of the feeder after a fault. These constraints are directly connected with reliability evaluation because the location of sectionalizing devices modifies the isolation sequence, the portion of the feeder affected by a fault, and the restoration time experienced by load points [28]. The feasible region of the optimization problem is therefore defined by the simultaneous satisfaction of topological, operational, and economic conditions, within which the metaheuristic algorithms search for the minimum-cost reliability-improvement strategy.

2.2. Fundamentals of the Aquila Optimizer and the Reference Algorithms GWO and GA-PSO

2.2.1. Aquila Optimizer (AO)

The Aquila Optimizer is a population-based metaheuristic inspired by the hunting behavior of the golden eagle. It was proposed as an optimization strategy that combines global exploration and local exploitation through four differentiated search mechanisms [11]. These mechanisms represent successive hunting behaviors of the eagle and determine how the population alternates between diversification and intensification during the search process.
The first mechanism is high soaring with expanded exploration, in which the eagle scans a wide region of the search space from a high altitude. In optimization terms, this mechanism promotes global exploration and helps the population identify promising regions without prematurely concentrating around a local solution. The second mechanism is contour flight with short gliding attack, where the eagle moves around the selected region using a more directed trajectory. This stage still contributes to exploration, but it begins to bias the search toward potentially better areas by combining random movement and local guidance. The third mechanism is low flight with expanded exploitation, in which the eagle descends toward the selected prey region and intensifies the search around the best solutions found so far. The fourth mechanism is walking and prey capture, which represents the final attack stage and performs intensive local exploitation around the most promising candidate solution. This staged structure allows AO to progressively transition from global diversification to local intensification as the iterations advance [11].
AO has attracted attention because of its modular search structure and its ability to alternate between exploration and exploitation without requiring a large number of control parameters. Several hybridizations have also been proposed to improve its performance in high-dimensional or complex optimization problems, particularly when premature convergence and local optima may affect the search process [29]. These characteristics make AO a relevant candidate for the sectionalizing-device placement problem studied in this paper, where the algorithm must explore a discrete and highly combinatorial space while identifying configurations that satisfy budget, device-number, and restoration-time constraints. Since the original AO operates in a continuous search space, its application to this research requires a binarization mechanism that maps continuous positions into installation decisions for candidate branches.

2.2.2. Grey Wolf Optimizer (GWO)

The Grey Wolf Optimizer is a bioinspired metaheuristic based on the social hierarchy and cooperative hunting behavior of grey wolf packs. It has been widely used in power-system planning problems because of its simple structure, reduced parameterization, and effective balance between exploration and exploitation [30]. The algorithm represents the search process through four categories of agents, namely alpha, beta, delta, and omega wolves. The alpha, beta, and delta wolves correspond to the best candidate solutions found during the search and guide the movement of the remaining population toward promising regions of the solution space [12].
In distribution-system applications, GWO has been used for problems such as capacitor placement, distributed-generation sizing, and network reconfiguration, and it is frequently adopted as a benchmark algorithm for evaluating the performance of new or less explored optimization methods [31]. Its inclusion in this study is therefore justified by its maturity in electrical-engineering optimization and by its suitability as a consolidated reference for comparison with AO. As with AO, the application of GWO to the present problem requires a binary adaptation of the continuous position-updating process so that each candidate solution represents the presence or absence of sectionalizing devices on the candidate branches.

2.2.3. Hybrid GA-PSO Algorithm

The hybrid GA-PSO algorithm combines the evolutionary operators of the Genetic Algorithm with the social-learning mechanism of Particle Swarm Optimization. This integration seeks to exploit the strengths of both approaches: the genetic component contributes diversity through selection, crossover, and mutation, whereas the PSO component accelerates convergence by updating candidate solutions according to individual and global best experiences [13]. In this way, the hybrid structure improves the balance between population diversification and search intensification, which is particularly useful in discrete planning problems with multiple local optima.
The genetic component helps preserve diversity and reduce the risk of premature convergence, while the PSO component provides a directed search mechanism based on the best positions identified by the population [14]. Hybrid GA-PSO schemes have shown robust performance in distributed-generation planning, network reconfiguration, and reliability-improvement problems, often achieving greater stability than the standalone versions of the individual algorithms when the search space is nonlinear and multimodal [32]. In this research, GA-PSO is adopted as a mature hybrid benchmark against which the performance of AO can be assessed under equivalent experimental conditions.

2.2.4. Comparative Assessment of Metaheuristics for Sectionalizing-Device Placement

The selection of a metaheuristic algorithm for sectionalizing-device placement must consider several performance dimensions, including the quality of the best solution, convergence speed, robustness under stochastic variability, and computational cost [15]. Since the problem is formulated through a binary decision vector, the same representation must be applied consistently across the compared algorithms. This requirement is essential to ensure that differences in performance are attributable to the search mechanisms of the algorithms rather than to unequal encodings, distinct stopping criteria, or inconsistent experimental settings.
A fair comparison among metaheuristics requires equivalent conditions in terms of population size, maximum number of iterations, independent runs, and pseudo-random seeds, thereby improving reproducibility and statistical traceability [33]. This principle is especially important when assessing a recent algorithm such as AO against more established references such as GWO and GA-PSO. In this study, AO is the main algorithm under evaluation, while GWO and GA-PSO are selected as comparative benchmarks because of their widespread use and demonstrated maturity in power-system planning problems. The adoption of metaheuristics is justified by the combinatorial nature of the sectionalizing-device placement problem, whose search space expands exponentially with the number of candidate branches and becomes impractical for exhaustive enumeration in realistic radial feeders.

2.3. Reliability Indices and Comparative Assessment of Algorithmic Performance

2.3.1. Reliability in Electrical Distribution Systems

The reliability of an electrical distribution system refers to its ability to supply energy to customers with the expected level of continuity and quality despite the random occurrence of component failures. This condition is commonly quantified through standardized statistical indices that summarize the frequency and duration of sustained interruptions over a defined evaluation period [34]. IEEE Std. 1366 provides the methodological basis for calculating SAIFI, SAIDI, and CAIDI, which are among the most widely adopted reliability indicators for distribution systems and serve as regulatory references in several power sectors [1].
Strategically located sectionalizing devices constitute a cost-effective measure for improving distribution reliability because they enable the isolation of faulted sections and the restoration of service to healthy feeder portions in less time [3]. However, the impact of sectionalizing devices depends on the operating characteristics of the feeder. In radial systems without load-transfer paths, sectionalizing may mainly reduce interruption duration rather than interruption frequency, since customers downstream of a fault may still experience an interruption but can be restored more rapidly once the affected section is isolated. This distinction is central to the present study because SAIFI, SAIDI, and CAIDI are not minimized directly in the objective function; instead, they are computed as output metrics to interpret the reliability effect of the optimized sectionalizing configuration.

2.3.2. System Average Interruption Frequency Index (SAIFI)

The System Average Interruption Frequency Index (SAIFI) measures the average number of sustained interruptions experienced by each customer during the evaluation period, commonly expressed in interruptions per customer per year [1]. In radial distribution networks, this index is associated with the exposure of customers to faults in upstream feeder sections and with the system’s ability to isolate the affected portion of the network. The strategic placement of sectionalizing devices may reduce the number of customers affected by a given contingency when the feeder has restoration alternatives or switching paths that allow unaffected sections to be re-energized [2,5,6].
From a calculation perspective, SAIFI is obtained by dividing the total number of customer interruptions by the total number of customers served, which makes it a direct measure of interruption frequency at the system level [1]. In planning studies, its interpretation must be consistent with the operating assumptions of the network. When no load transfer is available and the feeder remains strictly radial, as in the configuration analyzed in this study, the installation of sectionalizing devices may not necessarily reduce interruption frequency for all affected customers; instead, its main effect may be reflected in shorter outage durations. Nevertheless, SAIFI remains an essential output indicator because it verifies whether the optimized sectionalizing configuration alters the frequency component of the reliability performance [35].

2.3.3. System Average Interruption Duration Index (SAIDI)

The System Average Interruption Duration Index (SAIDI) quantifies the average total duration of sustained interruptions experienced by each customer during the evaluation period, generally expressed in minutes or hours per customer per year. This index is one of the most relevant metrics for evaluating the continuity of electricity service because it captures the accumulated effect of both the occurrence of faults and the time required to restore supply [32]. In sectionalizing-device placement studies, SAIDI is particularly important because the location of switching devices directly influences the time required to isolate a faulted section and restore service to healthy feeder segments [35].
An adequate placement of sectionalizing devices can significantly reduce the isolation and restoration times associated with feeder contingencies, allowing service restoration to portions of the network before the complete repair of the damaged component is finalized [36]. For this reason, SAIDI is one of the most informative output metrics for assessing the technical effectiveness of the proposed optimization framework. In the context of the present research, a reduction in SAIDI provides direct evidence that the selected sectionalizing configuration improves operational response and reduces customer exposure to long-duration interruptions.

2.3.4. Customer Average Interruption Duration Index (CAIDI)

The Customer Average Interruption Duration Index (CAIDI) represents the average duration of each sustained interruption experienced by affected customers. It is computed as the ratio between SAIDI and SAIFI and is commonly interpreted as the mean restoration time per interruption event [1]. This index provides complementary information about the effectiveness of operational response processes, including fault detection, crew dispatch, switching actions, isolation of the faulted section, and service restoration [37].
The behavior of CAIDI under different sectionalizing-device configurations helps distinguish between improvements caused by fewer customer interruptions and improvements caused by shorter restoration times [38]. This distinction is relevant for radial feeders because a sectionalizing plan may leave interruption frequency nearly unchanged while producing significant reductions in restoration duration. Therefore, the joint evaluation of SAIFI, SAIDI, and CAIDI provides a comprehensive interpretation of the reliability performance achieved by each optimized configuration and complements the cost-based comparison among AO, GWO, and GA-PSO. In this study, these indices are used as post-optimization evaluation metrics, supporting a technically meaningful assessment of the reliability benefits produced by the total-cost minimization model.

3. Problem Formulation

This section defines the planning problem addressed in this study: the optimal placement of sectionalizing devices in a radial distribution network for cost-effective reliability improvement. The formulation is conceived as a constrained binary combinatorial optimization problem in which each candidate branch can either receive a sectionalizing device or remain unchanged. The objective is to identify the configuration that minimizes the total expected cost associated with customer interruptions and device installation, while satisfying technical and economic constraints related to candidate-branch eligibility, maximum number of devices, investment budget, and allowable restoration time. The problem statement also establishes the general computational workflow used to compare the Aquila Optimizer (AO), the Grey Wolf Optimizer (GWO), and the hybrid GA-PSO algorithm under equivalent experimental conditions.

3.1. General Structure of the Proposed Problem

The proposed framework follows a sequential planning structure composed of six main stages. First, the IEEE 69-bus radial distribution system is characterized, and the set of candidate branches for sectionalizing-device installation is defined. Second, the objective-function evaluator is constructed by combining the expected customer interruption cost, the annualized investment cost, and the penalty terms associated with constraint violations. Third, an initial population of candidate binary solutions is generated for each metaheuristic algorithm. Fourth, the iterative search process is executed according to the specific updating rules of AO, GWO, and GA-PSO. Fifth, the feasibility of each candidate solution is assessed through the operational constraints, and the best solution found up to each iteration is recorded. Finally, the algorithms are compared in terms of solution quality, convergence behavior, robustness, computational effort, and reliability improvement. This type of controlled and reproducible workflow is consistent with the validation protocols commonly used for metaheuristic optimization in distribution-system planning [15].
It is important to emphasize that the sequential structure of the workflow does not imply that every solution generated during the search is feasible. Because population-based metaheuristics explore the solution space stochastically, infeasible configurations may appear during the optimization process. Instead of discarding these solutions, which could reduce population diversity and prematurely restrict the search, constraint violations are incorporated into the fitness function through a penalty mechanism. In this way, infeasible candidates remain available to the algorithm but receive a degraded fitness value, which progressively guides the population toward the feasible region as the iterations advance. This strategy allows the optimization process to remain stable even when early candidate solutions violate one or more operational or economic constraints.
The proposed formulation is therefore structured to preserve a clear separation between the physical system, the optimization model, and the algorithmic comparison. The physical layer is represented by the radial feeder topology, the load points, the branch failure rates, and the restoration characteristics. The optimization layer is represented by the binary decision vector, the total expected cost function, and the feasibility constraints. The algorithmic layer is represented by the three metaheuristic solvers evaluated under identical computational conditions. To make the overall research logic explicit, Figure 1 presents a systematic flowchart of the proposed framework, linking the characterization of the IEEE 69-bus feeder, the definition of candidate branches, the construction of the penalized objective-function evaluator, the execution of the metaheuristic search, the verification of constraints, and the final comparative performance assessment.
As illustrated in Figure 1, the optimization process starts from the characterization of the IEEE 69-bus system and the definition of the candidate branches. These inputs are then used to construct the binary search space and the cost-based fitness evaluator with penalty terms for constraint violations. Each metaheuristic algorithm generates and updates candidate configurations, which are subsequently evaluated in terms of constraint satisfaction and objective-function value. The best solution found during the search is stored at each iteration, enabling the comparative assessment of convergence trajectories, computational time, reliability indices, and final total expected cost. This sequence also indicates how the physical feeder data, the mathematical formulation, and the algorithmic comparison are connected within a single reproducible workflow.

3.2. IEEE 69-Bus Test System

The proposed problem is evaluated using the IEEE 69-bus radial distribution system, a 12.66 kV benchmark feeder widely adopted in distribution-network optimization studies [39]. This test system consists of one supply node, 68 load nodes, and 68 branches arranged in a radial configuration. Its total demand is approximately 3.80 MW and 2.69 MVAr, distributed along a main feeder and several lateral branches. The IEEE 69-bus system is particularly suitable for the present study because it provides an intermediate-scale radial topology that is sufficiently complex to represent realistic planning conditions while remaining fully traceable for comparative and reproducible analysis [39,40].
From a reliability-planning perspective, the radial nature of the IEEE 69-bus feeder is especially relevant. Since each load point is supplied through a unique upstream path, a fault in a feeder section may affect all downstream customers until the faulted segment is isolated and healthy portions of the network are restored. Therefore, the location of sectionalizing devices directly influences the number of affected load points, the duration of interruptions, and the expected energy not supplied. In this study, the base radial structure of the feeder is preserved throughout the optimization process. The candidate solutions only determine the placement of sectionalizing devices on eligible branches and do not modify the network topology by adding tie lines, changing feeder connections, or enabling load-transfer alternatives.
Let G = ( N , E ) denote the radial graph associated with the IEEE 69-bus system, where N represents the set of buses and E represents the set of branches. The subset of eligible branches for sectionalizing-device installation is denoted by C E . This candidate set is obtained by excluding terminal branches that already have load-side transformer protection and branches immediately adjacent to the source node, where protection is associated with the general feeder scheme and is not considered relocatable within the scope of this planning problem [33,41]. After applying these exclusion criteria to the 68 branches of the IEEE 69-bus feeder, the candidate set contains | C | = 59 eligible branches. Consequently, the binary search space evaluated by the metaheuristic algorithms contains 2 59 = 5.76 × 10 17 possible sectionalizing configurations before considering the device-number, budget, and restoration-time constraints. Table 1 reports the resulting candidate-branch set to support reproducibility of the optimization process.
The exclusion of non-candidate branches is also justified from an optimization standpoint. Branches with negligible contribution to system-level interruption-cost reduction, or branches whose protection function is not compatible with sectionalizing-device relocation, may introduce unnecessary binary variables without improving the quality of the final solution. Removing these branches from C improves computational efficiency and avoids unrealistic installation alternatives. Previous studies on radial distribution feeders have shown that this type of candidate-branch filtering can reduce the search space without compromising the ability to identify high-quality sectionalizing configurations [2,8,41]. Therefore, the candidate set C defines the feasible installation domain used by the metaheuristic algorithms, while the complete branch set E remains necessary for evaluating fault propagation, affected load points, interruption duration, and reliability indices.

3.3. Base-Case Configuration

The base case used as the reference condition corresponds to the original IEEE 69-bus radial feeder without additional sectionalizing devices installed on the candidate branches. In this configuration, the feeder preserves its original radial topology, and no tie lines, load-transfer paths, network reconfiguration actions, or remotely controlled restoration alternatives are introduced. Therefore, when a fault occurs on a feeder section, the affected downstream load points remain interrupted according to the original isolation and restoration logic of the radial system.
This base-case configuration is used only as the reference scenario against which the optimized sectionalizing-device placements are evaluated. The comparison quantifies the reduction in expected energy not supplied, customer interruption cost, total expected cost, System Average Interruption Duration Index, and Customer Average Interruption Duration Index produced by the installation of sectionalizing devices. Because the analyzed feeder does not include load-transfer paths, the placement of sectionalizing devices mainly affects interruption duration and restoration time, whereas the interruption-frequency component represented by the System Average Interruption Frequency Index is not expected to change significantly.

4. Methodology

This section presents the mathematical and computational methodology adopted to solve the optimal placement problem of sectionalizing devices in radial distribution networks. The formulation is based on the mixed-integer reliability-planning framework proposed by Shahbazian et al. [2], adapted in this study for its solution through population-based metaheuristic algorithms. The methodology defines the binary decision variables, the search space, the total expected cost function, the operational and economic constraints, the reliability-output indices, the constraint-handling strategy, and the implementation of the Aquila Optimizer (AO), Grey Wolf Optimizer (GWO), and hybrid GA-PSO algorithm. The objective is to guarantee a technically consistent, reproducible, and statistically traceable comparison among the three algorithms under identical experimental conditions.

4.1. Decision Variable and Search Space

Let the radial distribution network be represented by the graph G = ( N , E ) , where N denotes the set of buses or load points and E denotes the set of branches connecting them. Let C E be the subset of candidate branches where sectionalizing devices can be installed, with | C | = n . For the IEEE 69-bus case study, n = 59 , as reported in Table 1. The decision to install or not install a sectionalizing device on each candidate branch is encoded through the binary vector [2,5]
x = x 1 , x 2 , , x n T { 0 , 1 } n ,
where x j = 1 indicates that a sectionalizing device is installed on candidate branch j C , whereas x j = 0 indicates that no device is installed on that branch.
Equation (1) defines a discrete combinatorial search space with 2 n possible configurations. In the IEEE 69-bus case study, the n = 59 candidate branches lead to 2 59 = 5.76 × 10 17 possible binary configurations before applying the operational and economic constraints. This exponential growth prevents exhaustive enumeration and motivates the use of metaheuristic optimization techniques capable of identifying high-quality solutions within reasonable computational times [2,5,6,15]. In the proposed formulation, each vector x represents a complete sectionalizing plan for the feeder. Therefore, the quality of a candidate solution depends on its ability to reduce expected interruption costs while satisfying device-number, investment-budget, restoration-time, and network-operating constraints.

4.2. Objective Function

The optimization problem is formulated as the minimization of the total expected cost of the system. This cost is defined as the sum of the expected customer interruption cost and the annualized investment and installation cost of the selected sectionalizing devices. This two-component formulation provides a direct balance between reliability improvement and the economic effort required to implement the solution [2,4,8]. The objective function is expressed as
min x F ( x ) = C int ( x ) + C inv ( x ) ,
where F ( x ) is the total expected cost associated with the sectionalizing configuration x , C int ( x ) is the expected customer interruption cost, and C inv ( x ) is the annualized investment cost of the installed devices.
The interruption-cost component is calculated as the product between the expected energy not supplied and the unit interruption cost c u , which assigns an economic value to each kilowatt-hour not delivered to customers [7,8]:
C int ( x ) = c u EENS ( x ) .
The expected energy not supplied is obtained by summing, over all load points i N , the product between the annual unavailability U i ( x ) and the average demand L i of each load point [5,8]:
EENS ( x ) = i N U i ( x ) L i .
In this expression, U i ( x ) represents the annual unavailability of load point i, usually expressed in hours per year, and L i represents the average active power demand associated with that point. The value of U i ( x ) depends on the sectionalizing configuration because the installed devices modify the set of customers affected by each fault and the time required to isolate the faulted section and restore the healthy portions of the feeder [3,5,6].
The annualized investment component is calculated as the sum of the individual costs of all devices installed in the candidate branches [2,4,6]:
C inv ( x ) = j = 1 n x j c j ,
where c j is the annualized cost of the sectionalizing device assigned to candidate branch j, including acquisition, installation, operation, and maintenance costs. The structure of (2) penalizes two undesirable planning conditions: insufficient sectionalizing, which increases EENS and customer interruption cost, and excessive sectionalizing, which increases capital expenditure without a proportional improvement in reliability [2,4,8].

4.3. Operational and Economic Constraints

The optimal solution must belong to the feasible region of the problem, defined by all binary configurations that satisfy the topological, economic, and operational requirements of the distribution system. The constraints considered in this study ensure that the sectionalizing plan is technically implementable, economically admissible, and consistent with the radial operating structure of the feeder.

4.3.1. Candidate-Branch Eligibility

Because the study is performed on the IEEE 69-bus system in its base radial configuration, the installation of sectionalizing devices does not modify the original connectivity of the feeder and does not introduce new tie lines. Therefore, candidate solutions can only select branches belonging to the predefined candidate set C E , while maintaining the radial operation of the system [2,5]. This condition is expressed as
x j { 0 , 1 } , j C .

4.3.2. Maximum Number of Sectionalizing Devices

To avoid oversized solutions and preserve the economic feasibility of the reliability-improvement project, the total number of installed sectionalizing devices is limited by the maximum admissible value N max [2,4,8]:
j = 1 n x j N max .
This constraint prevents the optimization algorithm from selecting configurations that achieve reliability improvements only by installing an excessive number of devices.

4.3.3. Available Investment Budget

The total investment cost of the installed sectionalizing devices must not exceed the available budget B assigned to the reliability-improvement project [2,4,8]:
C inv ( x ) B .
This constraint guarantees that the selected configuration remains compatible with the financial limits of the planning problem.

4.3.4. Maximum Allowable Restoration Time

For any load point affected by a fault, the service restoration time must not exceed the maximum allowable threshold T max , which is defined as a planning parameter [5,6]:
T i rest ( x ) T max , i N .
This constraint links the optimization model with the expected operational response of the feeder, since the placement of sectionalizing devices modifies the isolation sequence and the restoration time experienced by downstream load points.

4.3.5. Branch Current Limit

The operating current in each branch must remain below its admissible thermal limit. This condition prevents a candidate configuration from being considered feasible if it produces branch loading beyond the allowable current rating:
I i j I i j max , ( i , j ) E ,
where I i j is the current flowing through branch ( i , j ) , and I i j max is its maximum admissible current.
The feasible region of the optimization problem is defined by the simultaneous satisfaction of (6)–(10):
F = x { 0 , 1 } n : x satisfies ( 6 ) ( 10 ) .

4.4. Load, Customer, and Reliability Parameters

The objective-function evaluation requires the definition of electrical, economic, and reliability parameters associated with each load point and branch. In the implemented workflow, the feeder topology, branch identifiers, branch lengths, nodal active-power demands, and branch-current limits are extracted from the verified PowerFactory model and processed in MATLAB. The average nodal demand L i is considered equivalent to the average active power consumed at load point i during the analysis period [2,5,6]:
L i = P i , avg .
When the input demand is available as peak active power, the average demand used in the EENS calculation is obtained as P i , avg = L F P i , peak , where L F is the load factor reported in Table 2. This treatment keeps the reliability-cost calculation consistent with the annual energy-not-supplied formulation while preserving the original nodal load distribution of the IEEE 69-bus benchmark.
In the present formulation, branch failure rates and restoration times are treated as deterministic planning parameters. Therefore, outages caused by extreme weather events are not modeled as a separate stochastic process in the optimization loop. Their effect is only implicitly represented to the extent that the adopted reliability parameters reflect average historical operating conditions. Explicit weather-dependent outage modeling would require time-varying or scenario-dependent failure rates, restoration times, and repair-resource constraints, which are outside the scope of the deterministic benchmark formulation adopted in this study.
The annual failure rate of each branch can be obtained from the product between the failure rate per kilometer-year and the length of the corresponding branch [2,5,6,28]:
λ i j = λ i j km l i j ,
where λ i j km is the failure rate per kilometer-year of branch ( i , j ) , and l i j is the length of that branch. In the case study, l i j corresponds to the branch length associated with each line element of the IEEE 69-bus feeder, exported from the PowerFactory model using the same branch identifiers reported for the candidate set. The same reference failure rate per kilometer-year is applied to all overhead line sections, as summarized in Table 2; therefore, the branch-specific annual failure rate differs according to the length of each branch.
The equivalent interruption rate of load point i depends on the set of branch faults that interrupt its supply under the sectionalizing configuration x . Let a m n , i ( x ) be a binary affectation parameter equal to 1 if a fault on branch ( m , n ) interrupts the supply of load point i under configuration x , and equal to 0 otherwise [1,5,6]. In the MATLAB implementation, the affectation matrix is constructed from the radial upstream–downstream relationship of the feeder. For each simulated faulted branch ( m , n ) , the algorithm identifies the downstream set of load points and verifies whether the installed sectionalizing devices allow a healthy portion of the feeder to be isolated from the faulted section. Since no tie lines or load-transfer paths are considered, the matrix modifies the duration assigned to affected load points but does not create alternative supply paths that would reduce the branch-failure frequency contribution. The equivalent interruption rate is then expressed as
λ i ( x ) = ( m , n ) E λ m n a m n , i ( x ) .
The annual unavailability of load point i is calculated by considering the failure rate of each branch, the corresponding restoration time, and the affectation condition of the load point under the sectionalizing configuration [1,3,5]:
U i ( x ) = ( m , n ) E λ m n r m n , i ( x ) a m n , i ( x ) ,
where r m n , i ( x ) is the restoration time experienced by load point i when a fault occurs on branch ( m , n ) under configuration x . This restoration-time matrix is obtained from the fault location and the nearest installed sectionalizing devices that delimit the isolated section. Load points that remain within the isolated faulted section are assigned the repair time r, whereas load points that can be restored after switching operations are assigned the switching time t s . If no sectionalizing device separates a healthy downstream portion from the faulted section, the corresponding load points remain associated with the repair-time condition. The values of r and t s used in the case study are reported in Table 2. Thus, r m n , i ( x ) changes with the selected device locations and provides the mechanism by which sectionalizing reduces SAIDI, CAIDI, and EENS in the strictly radial feeder.
The equivalent mean restoration time of load point i is obtained as the ratio between its annual unavailability and its equivalent interruption rate [1,3,5]:
r i ( x ) = U i ( x ) λ i ( x ) , λ i ( x ) > 0 .
Equations (14)–(16) define the reliability model used to quantify how each sectionalizing configuration modifies interruption frequency, interruption duration, and expected energy not supplied across the feeder.

4.5. Reliability Indices as Evaluation Outputs

The reliability indices defined in IEEE Std. 1366 [1] are calculated as post-optimization evaluation outputs. They are not included directly in the objective function because the optimization model is cost-based and because derived indices, particularly CAIDI, introduce nonlinear relationships that may generate redundancy within the metaheuristic search process [1,2,4]. Instead, SAIFI, SAIDI, and CAIDI are used to interpret the technical reliability effect of the best-identified solution obtained from the total expected cost minimization.
The interpretation of these indices is conditioned by the operating assumptions of the study. The IEEE 69-bus feeder is analyzed as a strictly radial network without tie lines, load-transfer paths, automatic feeder reconfiguration, or distributed restoration alternatives. Under these assumptions, the installation of sectionalizing devices does not create alternative supply paths capable of eliminating the occurrence of customer interruptions caused by upstream faults. Therefore, SAIFI is expected to remain nearly unchanged, whereas SAIDI, CAIDI, and EENS can improve because sectionalizing devices reduce the duration of interruptions by isolating faulted sections and enabling faster restoration of healthy feeder portions.
Let N i be the number of customers connected to load point i, and let N T be the total number of customers served by the system. The System Average Interruption Frequency Index is calculated as [1]
SAIFI ( x ) = i N λ i ( x ) N i N T .
The System Average Interruption Duration Index is calculated as [1]
SAIDI ( x ) = i N U i ( x ) N i N T .
The Customer Average Interruption Duration Index is computed as the ratio between SAIDI and SAIFI [1]:
CAIDI ( x ) = SAIDI ( x ) SAIFI ( x ) .
Equation (19) shows that CAIDI is a derived metric whose value depends simultaneously on the frequency and duration components of the interruption process. Therefore, its evaluation is reserved for post-optimization interpretation, while SAIFI and SAIDI provide direct information about the interruption frequency and interruption duration experienced by customers [2,4,8]. In the present study, this distinction is important because sectionalizing devices in a strictly radial feeder may primarily reduce interruption duration rather than interruption frequency.

4.6. Compact Statement of the Optimization Problem

Integrating the previous definitions, the optimal placement of sectionalizing devices is formulated as the following constrained binary combinatorial optimization problem:
min x F ( x ) = c u EENS ( x ) + j = 1 n x j c j ,
subject to
x F .
The formulation in (20) and (21) defines a large-scale discrete optimization problem whose exhaustive solution becomes computationally impractical as the number of candidate branches increases [15,41]. This condition justifies the use of the Aquila Optimizer as the main population-based search strategy [11], compared under identical experimental conditions with the Grey Wolf Optimizer [12,30] and the hybrid GA-PSO algorithm [13,14]. The comparison is performed using the same population size, iteration budget, number of independent runs, and pseudo-random seeds to guarantee statistical traceability and methodological reproducibility [13,15].

4.7. Rationale for Metaheuristic Solution and Exact Benchmarking Scope

For the IEEE 69-bus case study, the candidate-branch set contains n = 59 binary decision variables, as reported in Table 1. Therefore, a complete exhaustive enumeration would require evaluating 2 59 = 5.76 × 10 17 possible configurations before applying the operational and economic constraints. Even if each candidate configuration were evaluated rapidly in MATLAB, this number of combinations makes full enumeration computationally impractical for the adopted benchmark system.
An exact mixed-integer linear programming or mixed-integer programming benchmark was also not used as the main solution method because the reliability evaluation adopted in this study depends on topology-dependent affectation and restoration-time matrices, a m n , i ( x ) and r m n , i ( x ) , which are updated according to the selected sectionalizing-device locations and the radial fault-isolation logic. These matrices determine which load points are affected by each branch fault and whether they are assigned repair time or switching time. Consequently, the resulting evaluator is not a direct linear cost function of the binary placement vector unless additional auxiliary variables and logic constraints are introduced to explicitly encode all radial downstream relationships and restoration states.
For this reason, the present work focuses on a controlled comparison of stochastic metaheuristic algorithms under the same binary encoding, candidate set, fitness function, penalty treatment, population size, iteration budget, and pseudo-random seed set. The reported solution should therefore be interpreted as the best-identified configuration under the adopted comparative protocol rather than as a mathematically certified global optimum. Developing an exact MILP/MIP reformulation or an exhaustive benchmark for reduced candidate sets is a relevant extension for future work.

4.8. Objective-Function Evaluation and Constraint Handling

Population-based metaheuristics generally operate through a fitness function that evaluates the quality of each candidate solution. Since these algorithms do not inherently enforce explicit operational constraints, the objective function is augmented with a penalty term that degrades the fitness of infeasible solutions [14,15,41]. The penalized fitness function adopted in this study is
Φ ( x ) = F ( x ) + ρ k max 0 , g k ( x ) 2 ,
where F ( x ) is the total expected cost defined in (20), g k ( x ) 0 is the k-th operational or economic constraint expressed in inequality form, and ρ is the penalty coefficient. The penalty term increases the fitness value of infeasible solutions, reducing their probability of being selected as the search progresses [14,15,41].
To avoid combining constraint violations with different physical units, the violations were normalized before applying the quadratic penalty. In the numerical implementation, the constraint functions associated with the maximum number of devices, budget, restoration time, and branch-current limit were evaluated as
g N ( x ) = j = 1 n x j N max N max , g B ( x ) = C inv ( x ) B B , g T ( x ) = max i N T i rest ( x ) T max T max , g I ( x ) = max ( i , j ) E | I i j | I i j max I i j max .
Only positive values of these functions contribute to the penalty term through max ( 0 , g k ( x ) ) . The penalty coefficient was set to ρ = 10 6 USD/year, which makes infeasible configurations less competitive than feasible configurations while preserving the original total expected cost F ( x ) for all candidates satisfying the constraints.
A quadratic penalty is adopted because it mildly penalizes small violations near the feasible boundary while strongly penalizing large violations. This behavior is convenient when the best solution may lie close to the boundary of the feasible region [42]. For each candidate vector x , the evaluation of F ( x ) requires calculating the annual unavailability U i ( x ) of every load point, the equivalent interruption rates, the restoration times, the expected energy not supplied, and the associated investment cost. These calculations are performed according to the radial topology of the feeder and the location of the sectionalizing devices, which jointly determine the affected customers and the restoration sequence after each fault [5,6,41].

4.9. Implementation of the Aquila Optimizer (AO)

The Aquila Optimizer models the four hunting strategies described in Section 2.2.1 through differentiated updating rules that alternate between global exploration and local exploitation throughout the iterative process [11]. These four strategies are high soaring with expanded exploration, contour flight with short gliding attack, low flight with expanded exploitation, and walking and prey capture. Let X ( t ) be the continuous position vector of an individual at iteration t, X best ( t ) be the best solution found up to that iteration, X M ( t ) be the mean position of the population, and T be the maximum number of iterations.
Phase 1: High soaring with expanded exploration. This phase emulates high-altitude flight to identify promising regions of the search space [11]:
X 1 ( t + 1 ) = X best ( t ) 1 t T + X M ( t ) X best ( t ) rand .
Here, rand is a uniformly distributed random number in [ 0 , 1 ] . The factor ( 1 t / T ) progressively reduces the exploratory influence as the algorithm approaches the final iterations.
Phase 2: Contour flight with short gliding attack. This phase combines local exploration around promising regions with stochastic perturbations based on Lévy flight [11]:
X 2 ( t + 1 ) = X best ( t ) Levy ( d ) + X R ( t ) + ( y x ) rand .
In (25), X R ( t ) is a randomly selected position from the current population, Levy ( d ) is a Lévy-flight vector of dimension d, and x and y define the spiral trajectory used by the algorithm. The Lévy distribution introduces occasional long jumps that help reduce the probability of premature convergence to local optima [11].
Phase 3: Low flight with expanded exploitation. This phase represents the initial descending attack toward the selected prey and intensifies the search around promising regions [11]:
X 3 ( t + 1 ) = α X best ( t ) X M ( t ) rand + ( U B L B ) rand + L B δ .
Here, U B and L B are the upper and lower bounds of the continuous search space, respectively, while α and δ are exploitation parameters set to 0.1 according to the values recommended in the original AO formulation [11].
Phase 4: Walking and prey capture with intensive exploitation. This final phase represents the definitive attack and concentrates the search around the best candidate solution [11]:
X 4 ( t + 1 ) = Q F X best ( t ) G 1 X ( t ) rand G 2 Levy ( d ) + G 1 rand .
In (27), Q F is the quality function that regulates the search intensity during the final stage, G 1 is a random perturbation factor, and G 2 is a coefficient that decreases with the iterations to concentrate the search progressively around the best solution [11].
The transition between AO phases is governed by the iteration index. The exploratory phases are activated when t ( 2 / 3 ) T , whereas the exploitative phases are activated when t > ( 2 / 3 ) T [11]. Since the sectionalizing-device placement problem requires binary variables, the continuous positions generated by (24)–(27) are mapped into the binary search space through the sigmoid transfer function.
S ( x j ) = 1 1 + e x j , x j , bin = 1 , S ( x j ) rand , 0 , S ( x j ) < rand ,
This transformation allows AO to be applied to the proposed binary combinatorial problem without modifying its continuous updating structure [15]. In the computational implementation, the sigmoid transfer is applied consistently to the continuous-position algorithms, and the binary state is assigned according to the stochastic comparison with rand , as described in (28).

4.10. Implementation of the Grey Wolf Optimizer (GWO)

The Grey Wolf Optimizer models the social hierarchy and collective hunting behavior of grey wolves through four categories of agents: alpha ( α ) , beta ( β ) , delta ( δ ) , and omega ( ω ) . The alpha, beta, and delta wolves represent the three best solutions found during the search and guide the position update of the remaining population [12]. For each candidate solution, the distances from the leading wolves are calculated as
D α = C 1 X α X , D β = C 2 X β X , D δ = C 3 X δ X .
The candidate movements induced by the three leading wolves are then computed as
X 1 = X α A 1 D α , X 2 = X β A 2 D β , X 3 = X δ A 3 D δ .
The updated position is obtained as the average of these three candidate movements:
X ( t + 1 ) = X 1 + X 2 + X 3 3 .
The coefficient vectors A and C control the balance between exploration and exploitation and are defined as [12]
A = 2 a r 1 a , C = 2 r 2 ,
where r 1 and r 2 are uniformly distributed random vectors in [ 0 , 1 ] , and a decreases linearly from 2 to 0 during the iterative process. This decreasing behavior enables the algorithm to move gradually from global exploration toward local exploitation [12]. As in AO, the continuous position vector generated by GWO is converted into a binary configuration using the sigmoid transformation in (28), which ensures that both algorithms use a consistent binary representation and can therefore be compared under equivalent methodological conditions [15].

4.11. Implementation of the Hybrid GA-PSO Algorithm

The hybrid GA-PSO algorithm combines the evolutionary operators of the Genetic Algorithm with the social-learning dynamics of Particle Swarm Optimization. The purpose of this hybridization is to integrate the diversification capability of GA with the accelerated convergence behavior of PSO [13,14]. In each iteration, the population is updated through a coordinated PSO–GA mechanism: the PSO component guides the search toward the best individual and global experiences, whereas a predefined fraction of the population is renewed through genetic operators, including selection, crossover, and mutation. This structure preserves population diversity while maintaining a directed search toward high-quality regions of the solution space.
PSO component. The velocity and position of each particle are updated according to
v i ( t + 1 ) = w v i ( t ) + c 1 r 1 p i best x i ( t ) + c 2 r 2 g best x i ( t ) ,
and
x i ( t + 1 ) = x i ( t ) + v i ( t + 1 ) ,
where w is the inertia coefficient, c 1 and c 2 are the cognitive and social acceleration coefficients, r 1 and r 2 are random numbers uniformly distributed in [ 0 , 1 ] , p i best is the historical best position of particle i, and g best is the best global position found by the population [13,14].
GA component. The genetic operators are applied to the portion of the population selected for renewal through binary tournament selection, uniform crossover with probability p c , and bit-flip mutation with probability p m . Unlike AO and GWO, this component operates directly on the binary representation of the decision vector and therefore does not require a sigmoid transformation [13,14]. The sequential PSO–GA integration adopted in each iteration increases diversity and mitigates premature convergence, which is a common limitation of pure PSO implementations in combinatorial optimization problems [13,14].

4.12. General Comparative Algorithm

Table 3 summarizes the general procedure applied to the three metaheuristic methods. The structure is algorithm-independent and uses the specific updating rules of each method: (24)–(28) for AO, (29)–(32) for GWO, and (33), (34) together with the genetic operators for GA-PSO. In algorithms with continuous position updates, the generated positions are transformed into binary configurations using the sigmoid function defined in (28).

4.13. Computational Complexity and Scalability Considerations

The computational burden of the proposed approach is mainly determined by the number of fitness evaluations required by each metaheuristic algorithm and by the cost of evaluating the reliability and economic performance of each candidate configuration. For a population size P and a maximum number of iterations T, each independent run requires approximately P × T candidate-solution evaluations, in addition to the initial population evaluation. In the case study, P = 30 and T = 200 , which results in approximately 6000 fitness evaluations per run and 180,000 evaluations for the 30 independent runs of each algorithm.
The dimensionality of each candidate solution is governed by the number of candidate branches n = | C | . For the IEEE 69-bus feeder, n = 59 , which produces a complete binary search space of 2 59 = 5.76 × 10 17 configurations. The metaheuristic algorithms therefore evaluate only a very small fraction of the complete search space, which is the main reason why they are suitable for this type of combinatorial planning problem. In general, increasing n enlarges the binary search space exponentially, whereas the computational budget of the metaheuristic search grows approximately linearly with P, T, and the number of independent runs selected by the analyst.
The cost of one fitness evaluation also depends on the reliability model. In the present implementation, the evaluator uses the radial topology, the branch-failure data, the affectation matrix, and the restoration-time matrix to compute U i ( x ) , EENS, total expected cost, and the reliability indices. Therefore, larger feeders with more branches and load points would increase the cost of each evaluation because more fault-location and load-point combinations must be processed. Nevertheless, the use of preprocessed topology and static electrical data allows the MATLAB-based evaluator to avoid repeated external power-flow simulations during the optimization loop.
From a scalability perspective, the proposed framework is suitable for medium-scale radial benchmark feeders and can be extended to larger feeders if the candidate set is properly screened and the reliability evaluator is efficiently implemented. However, for large real distribution systems with thousands of branches, automated switching devices, tie lines, distributed generation, and network reconfiguration actions, additional computational strategies may be required. These may include candidate-location preselection, feeder partitioning, parallel fitness evaluation, surrogate reliability models, or hybrid exact–metaheuristic approaches. Therefore, the reported computational times should be interpreted as representative of the IEEE 69-bus benchmark and the adopted MATLAB-based evaluator, not as universal runtime guarantees for all distribution systems.

4.14. Experimental Protocol and Reproducibility

The comparative assessment is performed under identical experimental conditions to ensure statistical traceability and methodological validity [15]. In this study, the population size is set to P = 30 , the maximum number of iterations to T = 200 , and the number of independent runs to 30 for each algorithm. These settings allow the relative performance of the three methods to be evaluated under equivalent computational budgets [15]. A population size of 30 individuals provides a practical balance between search diversity and computational cost, while 200 iterations were sufficient for the three algorithms to stabilize their best objective values before the end of the optimization process, as later observed in the convergence curves. The use of 30 independent runs follows standard practice for stochastic algorithm assessment, since it allows the mean behavior and result dispersion to be characterized through statistical indicators such as the mean value and standard deviation [15,38].
The configuration parameters are summarized in Table 4 and Table 5. Table 4 reports the parameters common to all three algorithms, which were kept identical to guarantee comparable experimental conditions. Table 5 reports the algorithm-specific parameters, selected according to the values recommended by the original authors and the reference literature [11,12,13,14].
The parameters of each algorithm were selected according to the reference literature and the experimental conditions defined for this study. For AO, α = δ = 0.1 was used [11]. For GWO, the control coefficient a decreases linearly from 2 to 0 [12]. For GA-PSO, the inertia coefficient w decreases linearly from 0.9 to 0.4, the cognitive and social coefficients are fixed as c 1 = c 2 = 2.0 , the crossover probability is p c = 0.8 , the mutation probability is p m = 0.1 , and the fraction of the population replaced through genetic operators is 0.3 [13,14]. The computational implementation was developed using MATLAB and DIgSILENT PowerFactory 2024. PowerFactory was used to build and verify the IEEE 69-bus feeder model and to extract the static network data required by the optimization process, including feeder topology, branch identifiers, nodal loads, branch thermal limits, and base operating currents. The objective-function evaluation, the execution of the metaheuristic algorithms, and the recording of comparative results were then performed in MATLAB using these preprocessed data.
No full AC power-flow calculation was called from PowerFactory at each candidate-solution evaluation. This is consistent with the adopted planning model because the installation of sectionalizing devices does not add tie lines, modify nodal demands, or change the radial load-flow paths of the base feeder. Therefore, branch-current feasibility was verified using the base radial operating condition and the corresponding thermal limits, while the optimization loop focused on the reliability and cost effects of the sectionalizing locations. The reported computational times consequently correspond to the MATLAB-based reliability and cost evaluations rather than to repeated external PowerFactory simulations.

4.15. Metrics for Algorithm Comparison

The relative performance of AO, GWO, and GA-PSO is evaluated using four complementary metrics that quantify solution quality, convergence behavior, robustness, and computational efficiency, following comparative protocols commonly adopted in the metaheuristic optimization literature [15,38].
Solution quality and statistical dispersion. The minimum total cost F min , the mean total cost F ¯ , the standard deviation σ F , the coefficient of variation C V F , and the 95% confidence interval of the mean cost are calculated over the 30 independent runs. These indicators make it possible to distinguish algorithms that consistently reach high-quality solutions from those whose performance is more dispersed across runs [15,38]. The coefficient of variation is calculated as
C V F = σ F F ¯ × 100 % ,
whereas the 95% confidence interval of the mean objective-function value is estimated as
C I 95 % ( F ¯ ) = F ¯ ± t 0.975 , n 1 σ F n ,
where n = 30 is the number of independent runs and t 0.975 , n 1 is the Student coefficient for n 1 degrees of freedom. This descriptive statistical assessment is used to strengthen the interpretation of robustness and mean performance without assuming that a single best run is representative of the stochastic behavior of the algorithm.
Convergence speed. The convergence speed is quantified through the average iteration at which each algorithm reaches a solution within 5% of its final best objective value. This metric provides a direct measure of the iterative effort required by each method to enter a high-quality region of the search space in a minimization problem [15,38].
Computational time. The average execution time per run is recorded for each algorithm. This metric is relevant in planning applications because utilities and planners require optimization tools that provide reliable solutions within practical computational times [15,41].
Reliability-index improvement. After the optimal vector x best is identified, SAIFI, SAIDI, and CAIDI are calculated using (17)–(19) and compared with the base-case values obtained without additional sectionalizing devices. The improvement is expressed as a percentage reduction with respect to the original system [1,2,5,6,34]. This post-optimization verification confirms the technical relevance of the selected solution and translates the cost-based optimization result into reliability metrics that are directly interpretable by distribution utilities and regulatory agencies.

5. Case Study

The proposed formulation is evaluated using the IEEE 69-bus test system, which is a medium-scale radial distribution feeder widely used as a benchmark in distribution-network optimization studies. This system is suitable for assessing the effect of sectionalizing-device placement because it provides a radial topology with sufficient structural complexity to represent practical feeder behavior, while still allowing the traceability required for verifying the optimization results. In this study, the base case is used as the reference operating condition against which the total expected cost, expected energy not supplied, and reliability indices are compared after installing sectionalizing devices at different candidate branches. The selection of this benchmark also facilitates methodological comparison with previous studies in which the IEEE 69-bus system has been used for optimization, loss-reduction, and radial-network operation analyses [39,40]. However, the use of a single benchmark feeder means that the reported results should be interpreted as a controlled benchmark-based evaluation rather than as a universal validation of the method for all distribution systems.
Figure 2 shows the IEEE 69-bus feeder model implemented in DIgSILENT PowerFactory. This model constitutes the electrical and topological basis used to extract the feeder configuration, nodal loads, branch connections, base operating currents, and conductor limits required for evaluating each candidate sectionalizing configuration during the optimization process. The PowerFactory model was used as a verified source of network data, whereas the repeated fitness evaluations of the metaheuristic algorithms were performed in MATLAB using the exported static information.
As shown in Figure 2, the network preserves a radial configuration supplied through the substation transformer and composed of buses, lines, and loads distributed along the main feeder and several lateral branches. The nomenclature adopted in the PowerFactory model identifies each bus with the prefix B and each line section with the prefix L, for example, L1_2, L2_3, and L9_53. This notation facilitates the correspondence between the graphical feeder representation and the numerical data subsequently processed in MATLAB. Several laterals branch out from the main feeder, including the sections associated with buses 28–35, 36–46, 47–50, 51–52, 53–65, 66–67, and 68–69. Loads are identified with the prefix C and are located at the buses where demand is connected, while the line elements preserve the electrical connection between consecutive buses or between the main feeder and its laterals. This representation is used as the base case for extracting the topology, nodal demands, and conductor operating limits needed to evaluate each candidate solution within the metaheuristic optimization process.
Table 6 summarizes the main input data used in the MATLAB evaluation stage and indicates how each dataset contributes to the reliability and cost calculation.
The reliability and economic parameters adopted for the case study are summarized in Table 2. These parameters define the fault behavior of the feeder, the restoration assumptions, the economic valuation of unsupplied energy, and the investment limits considered in the optimization model. Together with the topology, branch-length, and load data summarized in Table 6, these parameters provide the information required to reproduce the reliability and cost evaluation of each candidate sectionalizing configuration.
A uniform annualized sectionalizing-device cost c j is adopted for all candidate branches because the IEEE 69-bus benchmark does not provide location-dependent installation data such as accessibility, civil-work requirements, terrain conditions, communication infrastructure, or utility-specific labor costs. This assumption allows the optimization process to isolate the effect of electrical location and feeder topology on reliability improvement without introducing site-dependent cost factors that are not available in the benchmark dataset. Therefore, the reported economic results should be interpreted as a standardized planning comparison under homogeneous device-cost assumptions. In practical utility applications, c j can be replaced by branch-specific annualized costs to reflect installation complexity, accessibility, communication requirements, and maintenance conditions.
The values reported in Table 2 are consistent with typical ranges used in distribution-system reliability studies. The failure rate of 0.10 failures/km·year is adopted as a representative value for medium-voltage overhead lines, whereas the repair time of 4.0 h and the switching time of 1.0 h are consistent with common operating intervals for manually operated sectionalizing devices [7]. The value of lost load is set to 3.0 USD/kWh as a representative value for a feeder with a mixed customer composition. Customer interruption-cost models reported in the literature assign differentiated costs depending on customer type and outage duration, ranging from relatively low values for residential users to substantially higher values for industrial customers [7,8]. Therefore, the adopted value provides an intermediate reference that avoids biasing the objective function toward a particular customer class. The annualized sectionalizer cost is obtained from a capital cost of 8000 USD distributed through the capital recovery factor, considering a 10% discount rate and a 10-year planning horizon. The maximum number of devices is selected to bound the search space to economically reasonable configurations without predetermining the result, since the optimal solution is located below this limit. The annual budget is defined to restrict oversized configurations while still allowing technically relevant candidate solutions to be explored [7,8].
The reliability performance of the system under its initial operating condition, without additional sectionalizing devices, is summarized in Table 7. This base case represents the feeder operating only with the upstream protection device at the head of the feeder and provides the reference values used to quantify the improvement achieved by the optimized sectionalizing configurations.
The values in Table 7 establish the initial reliability condition of the IEEE 69-bus feeder before the installation of additional sectionalizing devices. Since the base case considers only the feeder-head interrupting device, faults occurring along the radial feeder may interrupt all downstream customers until the faulted section is isolated and the service restoration process is completed. Consequently, these initial values define the benchmark against which each optimized configuration is evaluated. The reduction in EENS and C int , together with the variation of SAIFI, SAIDI, and CAIDI, provides the quantitative basis for assessing the technical and economic benefit of the sectionalizing-device placement obtained by AO, GWO, and GA-PSO.

6. Results and Discussion

The analysis starts from the base case of the IEEE 69-bus feeder operating only with the feeder-head interrupting device and without additional sectionalizing devices. Under this initial condition, the system presents a SAIFI of 6.80 interruptions/customer·year, a SAIDI of 27.20 h/customer·year, and a CAIDI of 4.00 h/interruption. The expected energy not supplied is 43,383 kWh/year. When this unsupplied energy is monetized using the adopted value of lost load, the base case produces an annual interruption cost of 130,150 USD/year. These values constitute the reference condition against which the technical and economic improvements achieved by each optimization algorithm are evaluated.
Starting from this benchmark condition, the three optimization algorithms considered in this study, namely AO, GWO, and GA-PSO, were applied under the same experimental protocol: 30 individuals, 200 iterations, and 30 independent runs. In all cases, the best configurations were obtained with eight sectionalizing devices. Therefore, the number of installed devices was not imposed as the final value of the solution, but emerged from the trade-off between the annualized installation cost and the economic benefit produced by the reduction in expected energy not supplied.

6.1. Aquila Optimizer Results

The convergence behavior of the Aquila Optimizer is shown in Figure 3. This curve reports the evolution of the best objective-function value during the iterative search and allows the stabilization pattern of AO to be examined.
The optimal configuration obtained with AO places the sectionalizing devices on branches L3_36, L4_47, L5_6, L8_51, L9_10, L9_53, L13_14, and L28_3. Several of these locations correspond to the beginning of lateral feeders, such as L3_36 and L4_47, which provide access to the laterals associated with buses 36–46 and 47–50, respectively. Other selected locations are placed along the main feeder upstream of load concentration areas. This spatial distribution is consistent with the operating principle of sectionalizing devices: when installed at lateral-head sections or strategically along the main feeder, they allow the faulted portion of the network to be isolated and reduce the time during which healthy downstream sections remain interrupted.
Table 8 summarizes the reliability and cost improvements achieved by the AO configuration with respect to the base case. The table compares the initial values with the optimized AO results and reports the corresponding percentage improvement.
As shown in Table 8, the AO solution substantially improves the reliability performance of the feeder. SAIDI decreases from 27.20 to 11.50 h/customer·year, which corresponds to a reduction of 57.7%. CAIDI decreases from 4.00 to 1.69 h/interruption, while EENS decreases from 43,383 to 18,342 kWh/year. As a result, the total expected cost is reduced from 130,150 to 65,443 USD/year, corresponding to a reduction of 49.7%. SAIFI remains unchanged at 6.80 interruptions/customer·year because the considered feeder operates as a strictly radial system without load-transfer paths, automatic feeder reconfiguration, or alternative restoration routes. Under this operating assumption, sectionalizing devices mainly affect the duration of interruptions by accelerating isolation and restoration actions in healthy feeder sections, but they do not modify the branch-failure frequency or create alternative supply paths capable of reducing the number of interruptions experienced by customers. Since SAIFI remains constant, the percentage reduction of CAIDI follows the same proportional trend as SAIDI. In automated or reconfigurable feeders, this behavior could differ because switching actions, tie lines, and service-transfer schemes may reduce not only interruption duration but also the number of customers affected by each fault.
The graphical comparison between the base case and the AO solution is presented in Figure 4. This figure complements the numerical results of Table 8 by illustrating the reduction obtained in the reliability and cost indicators after the optimized placement of sectionalizing devices.

6.2. Grey Wolf Optimizer Results

The convergence curve of the Grey Wolf Optimizer is presented in Figure 5. This curve shows the evolution of the best solution identified by GWO during the optimization process and provides a basis for comparing its convergence behavior with the other algorithms.
The GWO placed the eight sectionalizing devices on branches L3_36, L4_5, L4_47, L8_51, L9_53, L10_11, L12_13, and L28_3. As in the AO solution, the selected locations are concentrated at the heads of lateral feeders and at main-feeder sections upstream of relevant load groups. However, the GWO configuration differs slightly from the AO configuration, indicating the presence of neighboring solutions with very similar cost values around the best identified region of the search space.
The reliability and cost indicators obtained with the GWO configuration are reported in Table 9. This table compares the base case with the optimized GWO solution and quantifies the corresponding improvement.
The GWO configuration reduces SAIDI from 27.20 to 11.41 h/customer·year, equivalent to an improvement of 58.1%. EENS decreases from 43,383 to 18,202 kWh/year, and the total expected cost decreases to 65,023 USD/year, which represents a 50.0% reduction with respect to the base case. As with the AO solution, SAIFI remains unchanged at 6.80 interruptions/customer·year because the radial feeder does not include load-transfer paths. Therefore, the sectionalizing devices reduce interruption duration but do not alter the frequency component associated with branch failure occurrence. The best cost reached by GWO is slightly lower than that obtained by AO, namely 65,023 USD/year compared with 65,443 USD/year, which indicates a marginal advantage for GWO in terms of the best objective-function value.
Figure 6 presents the graphical comparison between the base case and the reliability indices obtained with GWO. This figure illustrates the same behavior observed in Table 9: a substantial reduction in duration-related indicators and interruption cost, with no change in SAIFI.

6.3. Hybrid GA-PSO Results

The convergence behavior of the hybrid GA-PSO algorithm is shown in Figure 7. This curve allows the convergence trajectory of the hybrid strategy to be assessed and compared with those obtained by AO and GWO.
The hybrid GA-PSO algorithm converged to the same best configuration identified by GWO, placing the eight sectionalizing devices on branches L3_36, L4_5, L4_47, L8_51, L9_53, L10_11, L12_13, and L28_3. This result is relevant because two algorithms with different search mechanisms, one based on the social hierarchy of grey wolves and the other on the hybridization of genetic operators with swarm dynamics, independently identified the same best configuration. This coincidence provides strong evidence that the solution is located in the most competitive region of the search space for the proposed formulation.
Table 10 reports the reliability and cost indicators obtained with GA-PSO. Since GA-PSO reached the same best configuration as GWO, the resulting values are identical to those reported for the GWO best solution.
As shown in Table 10, the GA-PSO solution produces a SAIDI of 11.41 h/customer·year, corresponding to a 58.1% improvement. EENS decreases to 18,202 kWh/year, and the total expected cost decreases to 65,023 USD/year, equivalent to a 50.0% reduction with respect to the base case. SAIFI remains constant at 6.80 interruptions/customer·year, consistent with the strictly radial operating condition of the feeder. Consequently, the difference between GA-PSO and GWO does not lie in the quality of their best solution, but in their statistical behavior over the 30 independent runs, which is analyzed in the comparative assessment.
Figure 8 illustrates the comparison between the base case and the GA-PSO solution. The figure confirms that the improvement is concentrated in duration-related and cost-related indicators, while the interruption frequency remains unchanged.

6.4. Comparative Assessment of the Algorithms

After evaluating the three algorithms individually, a comparative analysis was performed to examine their convergence behavior, robustness, computational effort, and cost performance across the 30 independent runs. Figure 9 superimposes the average convergence curves of AO, GWO, and GA-PSO, allowing their stabilization patterns and relative convergence speeds to be compared.
Figure 10 compares the mean cost and standard deviation obtained by each algorithm over the 30 independent runs. This comparison provides a direct graphical interpretation of robustness, since a lower dispersion indicates that the algorithm reaches similar solution quality across repeated stochastic executions.
The mean computational time per run is compared in Figure 11. This metric is relevant because optimization tools for distribution-planning applications must provide high-quality solutions within practical computation times.
Because the full search space contains 2 59 = 5.76 × 10 17 possible configurations, the comparative analysis is based on the best configurations identified by the stochastic algorithms under the adopted computational protocol. Therefore, the term “best” in the following discussion refers to the best solution found among the 30 independent runs of each algorithm, not to a certified global optimum obtained by exhaustive enumeration.
The comparative results show that the three algorithms achieved solutions of equivalent quality in their best runs, with best total costs around 65,000 USD/year. This confirms that the proposed optimization problem has a robust best-performing region that can be reached by different metaheuristic search mechanisms. Nevertheless, relevant differences were observed in statistical performance across the 30 independent runs. GWO achieved the best overall behavior: it reached the lowest best cost, equal to 65,023 USD/year, the lowest mean cost, equal to 66,004 USD/year, and the lowest dispersion among runs, with a standard deviation of 760 USD. These results identify GWO as the most robust and consistent algorithm among the three tested methods. GA-PSO reached the same best solution as GWO but showed higher variability, with a standard deviation of 1389 USD. AO obtained a solution very close to the best identified configuration, with a best cost of 65,443 USD/year, but it presented the highest dispersion, with a standard deviation of 2314 USD. In terms of computational time, AO and GWO showed very similar average execution times, equal to 1.49 s and 1.50 s per run, respectively, whereas GA-PSO required 2.14 s per run.
The statistical cost performance of the three algorithms over the 30 independent runs is summarized in Table 11. This table reports the best, mean, and worst objective-function values obtained by each method.
Table 11 confirms that GWO provides the most consistent cost performance. Although GA-PSO reaches the same best objective value as GWO, its mean and worst costs are higher, indicating a larger dispersion across independent runs. AO reaches a competitive best solution but exhibits the largest difference between its best and worst values, which reflects lower robustness under the adopted stochastic settings. The coefficient of variation reinforces this interpretation: GWO presents the lowest relative dispersion with C V F = 1.15 % , followed by GA-PSO with C V F = 2.07 % , whereas AO presents the highest relative dispersion with C V F = 3.35 % . The 95% confidence intervals of the mean cost also separate the three average-performance levels under the reported run dispersion, with GWO showing the lowest interval, GA-PSO an intermediate interval, and AO the highest interval. Therefore, the evidence supports the interpretation that GWO is the most robust method in terms of mean objective-function behavior, while AO should be interpreted mainly as a fast near-optimal alternative rather than as the statistically most consistent optimizer.
Table 12 complements the cost comparison by reporting the standard deviation, mean computational time, and number of installed sectionalizing devices for each algorithm.
The results in Table 12 show that all three algorithms selected eight sectionalizing devices in their best configurations, reinforcing that this number provides the best balance between interruption-cost reduction and investment cost under the adopted assumptions. GWO has the lowest standard deviation and coefficient of variation, which confirms its superior robustness. AO and GWO have nearly identical mean computational times, differing by only 0.01 s per run under the MATLAB-based evaluation. Therefore, the small time advantage of AO over GWO should not be overemphasized from a practical planning perspective. GA-PSO requires a longer mean computational time but remains competitive because it reaches the same best solution as GWO and exhibits intermediate dispersion.
The reported computational times should be interpreted together with the evaluation budget discussed in Section 4.13. Each run uses approximately 6000 candidate-solution evaluations, and the reported mean times correspond to the MATLAB-based reliability and cost evaluator applied to the IEEE 69-bus benchmark. Therefore, the results demonstrate that the proposed implementation is computationally tractable for the analyzed medium-scale feeder. However, larger feeders, larger candidate sets, or more detailed operational models involving reconfiguration, automated switching, or repeated power-flow calculations would increase the computational burden and may require parallelization or additional screening of candidate locations.
From a methodological perspective, this comparative behavior is relevant because it shows that the planning value of a metaheuristic cannot be inferred only from the best objective-function value. In the present problem, the best identified configuration can be reached by more than one algorithm, but the algorithms differ in robustness, convergence trajectory, and execution time. Therefore, the novelty of the comparative analysis lies in characterizing these differentiated performance profiles under the same sectionalizing-device placement formulation and the same computational budget.
These results indicate that economic efficiency and computational efficiency should be coordinated through a two-level decision criterion rather than by selecting the fastest algorithm alone. In the first level, the best and mean objective-function values should be used to identify the configurations that provide the greatest economic benefit in terms of total expected cost. In the second level, computational time and dispersion across independent runs should be used to assess whether the algorithm can provide sufficiently stable solutions within the available planning time. Under this interpretation, GWO is preferable when the main planning criteria are robustness and minimum expected cost, whereas AO is attractive for rapid screening of candidate configurations because it provides near-optimal cost values with the shortest execution time. Therefore, AO should be interpreted as a computationally efficient alternative for preliminary or repeated planning analyses, while the final investment decision should consider the combined evidence of cost, robustness, and execution time.
The convergence behavior shown in Figure 9 supports this interpretation. GWO and GA-PSO decrease rapidly during the first iterations and stabilize around iteration 40. AO, by contrast, maintains its best value with nearly no changes during a large portion of the exploratory stage and reduces the objective function more noticeably after approximately iteration 130. This behavior is consistent with the structure of AO, which allocates the first two-thirds of the iterations to exploration and reserves the final stage for intensive exploitation. Consequently, AO requires a larger number of iterations to approach its final solution, although it ultimately reaches a competitive objective value.
Finally, Figure 12 presents a comparative radar chart that synthesizes the performance of the three algorithms across the evaluated criteria. This representation provides a compact visualization of the trade-offs among solution quality, robustness, computational time, and reliability improvement.
Overall, the results demonstrate that the strategic installation of eight sectionalizing devices can reduce the total expected cost by approximately 50% and improve feeder reliability by nearly 58% in terms of SAIDI and EENS. For the proposed problem, GWO provides the most robust overall performance because it combines the best objective-function value with the lowest dispersion across independent runs. AO stands out as the fastest algorithm in terms of mean computational time, while GA-PSO remains highly competitive because it reaches the same best configuration as GWO. Therefore, each algorithm exhibits a differentiated strength: GWO in consistency and robustness, AO in computational speed, and GA-PSO in its ability to reproduce the best identified solution.

6.5. Reliability-Model Assumptions and Operational Interpretation

The reliability improvements reported in this study must be interpreted according to the operational assumptions of the adopted feeder model. The IEEE 69-bus system is considered in its original radial configuration, without normally open tie lines, load-transfer paths, network reconfiguration actions, distributed generation support, or automated restoration schemes. Consequently, sectionalizing devices do not prevent the initial interruption caused by a fault located upstream of a load point. Their contribution is represented through the reduction of the interruption duration assigned to healthy feeder portions after the faulted section is isolated.
This modeling assumption explains why SAIFI remains unchanged in the optimized configurations, while SAIDI, CAIDI, EENS, and the total expected cost are reduced. In a strictly radial feeder, the frequency component of the interruption process is governed mainly by branch failure rates and the radial exposure of each load point. Since the optimized sectionalizing configurations do not modify branch failure rates or create alternative supply paths, the interruption frequency contribution is not significantly altered. In contrast, the duration component is directly affected by the placement of sectionalizing devices because selected healthy portions of the feeder can be restored after switching actions instead of remaining interrupted for the complete repair time.
These conclusions should not be directly extrapolated to automated or reconfigurable distribution networks. In feeders equipped with remotely controlled switches, tie lines, feeder automation, distributed energy resources, or fault-location, isolation, and service-restoration schemes, sectionalizing devices may also reduce the number of customers interrupted by transferring load to alternative supply paths. Under those conditions, SAIFI may change, and the optimization problem would require additional variables representing switching sequences, communication availability, restoration paths, protection coordination, voltage limits, and post-restoration loading conditions. Therefore, the present results are representative of a deterministic radial planning case and provide a benchmark for manual or simplified sectionalizing behavior, while automated and reconfigurable networks require an extended formulation.

6.6. Practical Implementation Considerations

The practical deployment of sectionalizing devices in distribution feeders requires additional considerations beyond the numerical optimization of device locations. Although the proposed formulation identifies candidate branches that provide the greatest reliability and economic benefit under the adopted benchmark assumptions, an actual utility implementation must also consider field accessibility, installation feasibility, protection coordination, crew-operation procedures, maintenance requirements, and the availability of communication infrastructure.
For manually operated sectionalizing devices, the reliability benefit depends strongly on crew dispatch time, field accessibility, switching procedures, and the ability of operators to identify and isolate the faulted section safely. In this case, the restoration improvement is mainly associated with reducing the portion of the feeder that remains interrupted during repair. For remotely controlled sectionalizing devices, additional benefits may be obtained by reducing switching time and enabling faster isolation and restoration actions. However, these benefits require reliable communication channels, supervisory control and data acquisition integration, cybersecurity provisions, auxiliary power supply, remote-control hardware, and periodic testing of automation functions.
Maintenance and utility deployment constraints can also affect the final placement decision. Locations with difficult access, exposure to environmental stress, high installation complexity, or limited communication coverage may increase the effective annualized cost of the device. Similarly, protection settings and coordination with upstream reclosers, fuses, and feeder breakers must be reviewed before field deployment to avoid undesired miscoordination during fault isolation. Therefore, the optimized locations reported in this benchmark study should be interpreted as technically and economically attractive planning candidates. A final utility deployment would require a field-engineering assessment that incorporates location-dependent costs, communication feasibility, maintenance planning, safety requirements, and protection-coordination verification.

6.7. Economic-Sensitivity Considerations

The economic performance of sectionalizing-device placement depends directly on the relationship between the annualized device cost c j , the unit interruption cost c u , and the reduction in expected energy not supplied achieved by each candidate configuration. From the objective function in (20), installing an additional sectionalizing device is economically justified only if the associated reduction in customer interruption cost is greater than the additional annualized investment cost. Therefore, for a candidate configuration x that differs from x by the installation of one additional device, the marginal condition can be expressed as
c u EENS ( x ) EENS ( x ) > c j .
Equation (37) shows that higher interruption-cost values increase the economic attractiveness of additional sectionalizing devices, whereas higher annualized device costs reduce the number of economically justified installations. Under the homogeneous-cost assumption adopted in this benchmark study, c j is identical for all candidate branches; therefore, the optimization prioritizes locations according to their ability to reduce EENS and interruption duration. In real utility applications, however, branch-specific costs could modify the optimal placement by penalizing locations with difficult access, higher installation complexity, or additional communication requirements.
The results reported in this study should therefore be interpreted as the best identified solution under the adopted cost ratio between interruption cost and annualized sectionalizing-device cost. The selection of eight devices indicates that, for the parameter set summarized in Table 2, the marginal reduction in interruption cost remains economically attractive up to that device count, while additional installations are limited by the cost–benefit balance and by the operational and budget constraints. A full parametric sensitivity analysis over c j , c u , restoration time, and investment budget would provide additional utility-specific insight and is identified as a relevant extension of the present benchmark-based evaluation.

6.8. Scope of Validation and Generality

The numerical results reported in this study are based on the IEEE 69-bus radial distribution feeder and on the reliability and economic parameters adopted for the benchmark case. Therefore, the conclusions should be interpreted within this controlled evaluation scope. The IEEE 69-bus system is useful for methodological assessment because it provides a traceable radial topology, a sufficiently large number of branches and load points, and a widely used reference for comparison in distribution-network optimization studies [39,40]. However, feeder size, lateral distribution, customer composition, protection philosophy, restoration practices, interruption costs, and available switching infrastructure may differ significantly across real distribution systems.
For this reason, the present results demonstrate the behavior of AO, GWO, and GA-PSO under a common cost-based sectionalizing-device placement formulation, but they should not be interpreted as proof of universal superiority or general applicability in all radial feeders. Additional benchmark feeders and real utility networks would be required to evaluate scalability, robustness under different topologies, and sensitivity to utility-specific operating practices. The present benchmark-based evaluation is therefore intended to provide a reproducible methodological reference and a technically consistent comparison among the algorithms, while broader validation across other feeders is identified as a necessary extension.

7. Conclusions

This study addressed the optimal placement of sectionalizing devices in radial distribution networks using the Aquila Optimizer and compared its performance with two consolidated metaheuristic approaches, namely the Grey Wolf Optimizer and a hybrid GA-PSO algorithm. The analysis was carried out on the IEEE 69-bus test system under a unified technical and economic formulation that minimizes the total expected cost, defined as the sum of the customer interruption cost and the annualized investment cost of the installed sectionalizing devices. The formulation incorporated candidate-branch eligibility, maximum number of devices, available budget, maximum allowable restoration time, and preservation of the radial operating structure of the feeder.
The IEEE 69-bus feeder was modeled in its radial configuration and used as the reference test system for evaluating the proposed methodology. The base case, corresponding to the feeder operating only with the upstream interrupting device and without additional sectionalizing devices, presented a SAIFI of 6.80 interruptions/customer·year, a SAIDI of 27.20 h/customer·year, a CAIDI of 4.00 h/interruption, an EENS of 43,383 kWh/year, and an annual interruption cost of 130,150 USD/year. These values established a consistent benchmark for quantifying the technical and economic impact of the optimized sectionalizing configurations.
The three algorithms were implemented using the same objective-function evaluator and were executed under identical experimental conditions, with 30 individuals, 200 iterations, and 30 independent runs. This protocol ensured that the comparison was based on equivalent computational budgets and reproducible stochastic conditions. The best solutions obtained by the three methods installed eight sectionalizing devices, indicating that this number emerged from the economic balance between interruption-cost reduction and investment cost rather than from a prescribed final configuration. This result confirms the coherence of the proposed total-cost formulation for identifying economically justified reliability improvements.
The optimized placement of sectionalizing devices produced substantial improvements in the duration-related reliability indices. The best configurations reduced SAIDI from 27.20 to approximately 11.4 h/customer·year, corresponding to an improvement close to 58%. EENS was reduced from 43,383 to approximately 18,200 kWh/year, and the total expected cost decreased from 130,150 USD/year to approximately 65,000 USD/year, representing an economic reduction close to 50% with respect to the base case. CAIDI followed the same reduction trend as SAIDI because SAIFI remained unchanged. This behavior is technically consistent with the analyzed system, since the feeder was modeled as a strictly radial network without load-transfer paths. Under this operating condition, sectionalizing devices reduce the duration of interruptions by accelerating fault isolation and service restoration in healthy sections, but they do not modify the frequency of fault occurrence, which is governed by the branch failure rates.
The comparative assessment showed that the three algorithms reached solutions of similar quality, confirming that the best-performing region of the search space is robust and can be approached through different metaheuristic mechanisms. GWO achieved the best overall statistical performance, with the lowest best cost, the lowest mean cost, and the smallest standard deviation across the 30 independent runs. The hybrid GA-PSO algorithm reached the same best identified configuration as GWO, which reinforces the consistency of that configuration under the adopted comparative protocol, although GA-PSO exhibited higher dispersion and longer computational time. AO reached a very competitive solution with a slightly lower mean computational time than GWO under the adopted MATLAB-based evaluator, but it exhibited greater variability among runs. Therefore, the results indicate differentiated strengths rather than absolute dominance of a single method: GWO provides the highest robustness and consistency, AO offers the greatest computational speed for rapid candidate screening, and GA-PSO confirms its competitiveness by reproducing the best solution found by GWO. From a planning perspective, the coordination between economic efficiency and computational efficiency requires that final device-placement decisions be based on the joint interpretation of total expected cost, dispersion among runs, convergence behavior, and execution time.
From a planning perspective, and under the homogeneous-cost assumptions adopted in the IEEE 69-bus benchmark, the results demonstrate that a moderate and strategically located investment in sectionalizing infrastructure can produce a substantial reduction in interruption costs and a significant improvement in reliability performance for radial distribution feeders. Within the benchmark conditions analyzed, the proposed framework provides a quantitative decision-support tool for distribution utilities because it links investment decisions with expected interruption cost, EENS, and standard reliability indices. The results also show that AO is a viable and competitive alternative for sectionalizing-device placement, particularly when computational speed is a relevant criterion. However, its higher dispersion across independent runs suggests that additional mechanisms may be required to improve its robustness when compared with more consolidated metaheuristic approaches. The conclusions should be interpreted within the deterministic reliability and strictly radial operating assumptions adopted in the study, since extreme-weather-driven outages, load-transfer paths, automatic feeder reconfiguration, remotely controlled restoration schemes, and location-dependent device costs were not explicitly modeled as scenario-dependent variables.

Future Work

Future research should extend the proposed formulation by incorporating remotely controlled sectionalizing devices. Unlike manually operated devices, remotely controlled equipment can reduce switching and restoration times, which may further decrease SAIDI, CAIDI, EENS, and interruption cost. This extension would also make it possible to analyze the economic trade-off between higher investment cost, communication infrastructure requirements, maintenance needs, and additional reliability improvement, particularly in feeders where automation schemes are technically and economically feasible.
Another relevant extension is the inclusion of normally open tie lines, load-transfer alternatives, and network reconfiguration actions. In the present study, the feeder was analyzed as a strictly radial system without transfer paths, which explains why sectionalizing devices reduced interruption duration but did not change SAIFI. Incorporating network reconfiguration and service-transfer schemes would allow the assessment of sectionalizing devices under more flexible operating conditions, where the number of customers affected by each fault may also be reduced. Such an extension would require additional decision variables and constraints to represent switching sequences, communication availability, alternative restoration paths, voltage limits, thermal loading limits, and protection-coordination requirements.
The reliability and economic parameters used in this study were adopted from representative values reported in the literature. Future work should calibrate the model using utility data, including real failure rates, repair times, switching times, customer composition, load profiles, interruption-cost estimates, location-dependent device costs, and available investment budgets. This calibration would improve the practical applicability of the methodology and would allow the proposed framework to be validated under the operating conditions of real distribution systems. In the same direction, the analytical reliability evaluation could be complemented with Monte Carlo simulation to represent the stochastic nature of failures, restoration processes, and load variability in greater detail. A particularly relevant extension would be the incorporation of extreme-weather scenarios through weather-dependent failure rates, storm-dependent restoration times, and probabilistic repair-resource availability. This would allow the placement of sectionalizing devices to be evaluated not only under average operating conditions, but also under high-impact low-probability outage conditions.
Future studies should also perform a full sensitivity analysis of c j , c u , restoration time, switching time, and budget limits to quantify how economic and operational assumptions affect the optimal number and location of sectionalizing devices. In addition, future comparative studies should retain and report the complete run-level objective-function vectors to enable non-parametric statistical tests, such as Wilcoxon pairwise comparisons or Friedman ranking tests, when comparing stochastic optimization algorithms. Another relevant extension is the development of an exact MILP/MIP reformulation or an exhaustive-search benchmark for reduced candidate sets, which would make it possible to quantify the optimality gap of the metaheuristic solutions when a certified global optimum is computationally attainable.
The methodology should also be tested on additional benchmark feeders, such as the IEEE 33-bus and IEEE 118-bus distribution systems, as well as on real utility networks. This broader validation would make it possible to evaluate scalability, computational performance, and generality across systems with different sizes, topologies, lateral structures, load distributions, protection schemes, and restoration practices. Such extensions are particularly important because the present study uses a single benchmark feeder and deterministic parameter values; therefore, the conclusions should be interpreted as evidence obtained under controlled benchmark conditions rather than as universal performance guarantees. In addition, the formulation could be extended to the coordinated placement of different protection and switching devices, including reclosers, sectionalizers, fuses, remotely controlled switches, and tie switches, leading to an integrated protection and service-restoration planning framework for automated and reconfigurable distribution networks.
Finally, since AO achieved competitive solution quality with low computational time but showed higher variability across independent runs, future research should explore enhanced or hybrid AO variants aimed at improving convergence stability and robustness. These variants could be compared with other recent metaheuristics under the same cost-based formulation, statistical protocol, and reliability-evaluation framework proposed in this study.

Author Contributions

Conceptualization, J.J.G.F. and A.A.T.; methodology, J.J.G.F. and A.A.T.; software, J.J.G.F.; validation, J.J.G.F., M.D.J.M. and A.A.T.; formal analysis, J.J.G.F.; investigation, J.J.G.F. and A.A.T.; data curation, J.J.G.F. and M.D.J.M.; writing—original draft preparation, J.J.G.F., A.A.T. and M.D.J.M.; writing—review and editing, A.A.T. and M.D.J.M.; visualization, J.J.G.F.; supervision, A.A.T. and M.D.J.M. All authors have read and agreed to the published version of the manuscript.

Funding

This research received no external funding.

Institutional Review Board Statement

Not applicable.

Informed Consent Statement

Not applicable.

Data Availability Statement

The data and code used in this study are available from the corresponding author upon reasonable request.

Acknowledgments

The authors acknowledge Universidad Politécnica Salesiana for the academic and institutional support provided during the development of this research.

Conflicts of Interest

The authors declare no conflicts of interest.

References

  1. IEEE Std 1366-2022; IEEE Guide for Electric Power Distribution Reliability Indices. IEEE: New York, NY, USA, 2022. Available online: https://standards.ieee.org/ieee/1366/7243/ (accessed on 10 June 2026).
  2. Shahbazian, A.; Fereidunian, A.; Manshadi, S.D. Optimal Switch Placement in Distribution Systems: A High-Accuracy MILP Formulation. IEEE Trans. Smart Grid 2020, 11, 5009–5018. [Google Scholar] [CrossRef]
  3. Wang, C.; Pang, K.; Shahidehpour, M.; Wen, F.; Ren, H.; Liu, Z. Flexible Joint Planning of Sectionalizing Switches and Tie Lines Among Distribution Feeders. IEEE Trans. Power Syst. 2022, 37, 1577–1590. [Google Scholar] [CrossRef]
  4. Costa Gomes, A.; Leão, R.P.S.; De Athayde Prata, B.; Tofoli, F.L.; Sampaio, R.F.; Barroso, G.C. Optimal placement of manual and remote-controlled switches based on the Pareto front. Int. J. Electr. Power Energy Syst. 2023, 147, 108894. [Google Scholar] [CrossRef]
  5. Farajollahi, M.; Fotuhi-Firuzabad, M.; Safdarian, A. Simultaneous Placement of Fault Indicator and Sectionalizing Switch in Distribution Networks. IEEE Trans. Smart Grid 2019, 10, 2278–2287. [Google Scholar] [CrossRef]
  6. Wang, L.; Lin, J.; Liu, G.; Wang, G.; Zhong, Q.; Zhao, Y. An MIP-based model for the deployment of fault indicators and sectionalizing switches in distribution networks. Electr. Power Syst. Res. 2020, 179, 106076. [Google Scholar] [CrossRef]
  7. Gholizadeh, N.; Hosseinian, S.H.; Abedi, M.; Nafisi, H.; Siano, P. Optimal placement of fuses and switches in active distribution networks using value-based MINLP. Reliab. Eng. Syst. Saf. 2022, 217, 108075. [Google Scholar] [CrossRef]
  8. Karimi, H.; Niknam, T.; Aghaei, J.; GhasemiGarpachi, M.; Dehghani, M. Switches optimal placement of automated distribution networks with probability customer interruption cost model: A case study. Int. J. Electr. Power Energy Syst. 2021, 127, 106708. [Google Scholar] [CrossRef]
  9. Azarhazin, S.; Farzin, H.; Mashhour, E. An MILP model for reliability-based placement of recloser, sectionalizer, and disconnect switch considering device relocation. Sustain. Energy Grids Netw. 2023, 35, 101127. [Google Scholar] [CrossRef]
  10. Alam, A.; Tariq, M.; Zaid, M.; Verma, P.; Alsultan, M.; Ahmad, S.; Sarwar, A.; Hossain, M.A. Optimal Placement of Reclosers in a Radial Distribution System for Reliability Improvement. Electronics 2021, 10, 3182. [Google Scholar] [CrossRef]
  11. Abualigah, L.; Yousri, D.; Abd Elaziz, M.; Ewees, A.A.; Al-qaness, M.A.A.; Gandomi, A.H. Aquila Optimizer: A novel meta-heuristic optimization algorithm. Comput. Ind. Eng. 2021, 157, 107250. [Google Scholar] [CrossRef]
  12. Mirjalili, S.; Mirjalili, S.M.; Lewis, A. Grey Wolf Optimizer. Adv. Eng. Softw. 2014, 69, 46–61. [Google Scholar] [CrossRef]
  13. S. Sharma, J.S. Comparative research on genetic algorithm, particle swarm optimization and hybrid GA-PSO. In Proceedings of the 2015 2nd International Conference on Computing for Sustainable Global Development (INDIACom); IEEE: New York, NY, USA, 2015; pp. 110–114. [Google Scholar]
  14. Duan, B.; Guo, C.; Liu, H. A hybrid genetic-particle swarm optimization algorithm for multi-constraint optimization problems. Soft Comput. 2022, 26, 11695–11711. [Google Scholar] [CrossRef]
  15. Valencia-Rivera, G.H.; Benavides-Robles, M.T.; Morales, A.V.; Amaya, I.; Cruz-Duarte, J.M.; Ortiz-Bayliss, J.C.; Avina-Cervantes, J.G. A systematic review of metaheuristic algorithms in electric power systems optimization. Appl. Soft Comput. 2024, 150, 111047. [Google Scholar] [CrossRef]
  16. Meng, X.; Xie, D.; Lin, H.; Lin, C.; Ge, X.; Liu, Z. Dissipativity-Based Multiport Stability Root-Cause Identification and Mitigation for Solid-State Transformers. IEEE Trans. Ind. Electron. 2026, 73, 9850–9862. [Google Scholar] [CrossRef]
  17. Villarreal, M.I.Z.; Téllez, A.A.; Krishnan, N.; García, M. Expansion Planning of Electrical Distribution Systems Considering Voltage Quality and Reliability Criteria. Energies 2025, 18, 2822. [Google Scholar] [CrossRef]
  18. Téllez, A.A.; Ortiz, L.; Ruiz, M.; Narayanan, K.; Varela, S. Optimal Location of Reclosers in Electrical Distribution Systems Considering Multicriteria Decision Through the Generation of Scenarios Using the Montecarlo Method. IEEE Access 2023, 11, 68853–68871. [Google Scholar] [CrossRef]
  19. Aguila Téllez, A.; Krishnan, N.; García, E.; Carrión, D.; Ruiz, M. A Probabilistic Framework for Reliability Assessment of Active Distribution Networks with High Renewable Penetration Under Extreme Weather Conditions. Energies 2025, 18, 6525. [Google Scholar] [CrossRef]
  20. Peña, D.; Téllez, A.A.; Jurado, F. Reliability Assessment of Ecuador’s Power System: Metrics, Vulnerabilities, and Strategic Perspectives. Energies 2025, 18, 3059. [Google Scholar] [CrossRef]
  21. El-Fergany, A.A. Reviews, Challenges, and Insights on Computational Methods for Network Reconfigurations in Smart Electricity Distribution Networks. Arch. Comput. Methods Eng. 2024, 31, 1233–1253. [Google Scholar] [CrossRef]
  22. Meskin, M.; Domijan, A.; Grinberg, I. Impact of distributed generation on the protection systems of distribution networks: Analysis and remedies—Review paper. IET Gener. Transm. Distrib. 2020, 14, 5944–5960. [Google Scholar] [CrossRef]
  23. El-Fergany, A.A. Reviews on Load Flow Methods in Electric Distribution Networks. Arch. Comput. Methods Eng. 2025, 32, 1619–1633. [Google Scholar] [CrossRef]
  24. Zare-Bahramabadi, M.; Farzin, H.; Ehsan, M. An MILP model for risk-based placement of RCSs, DDGs, and tie lines in distribution systems with complex topologies. IET Renew. Power Gener. 2023, 17, 829–839. [Google Scholar] [CrossRef]
  25. Swaminathan, D.; Rajagopalan, A.; Montoya, O.D.; Arul, S.; Grisales-Noreña, L.F. Distribution Network Reconfiguration Based on Hybrid Golden Flower Algorithm for Smart Cities Evolution. Energies 2023, 16, 2454. [Google Scholar] [CrossRef]
  26. Alam, A.; Pant, V.; Das, B. Optimal placement of protective devices and switches in a radial distribution system with distributed generation. IET Gener. Transm. Distrib. 2020, 14, 4847–4858. [Google Scholar] [CrossRef]
  27. Cortés Sanabria, P.J.; Tabares Pozos, A.; Álvarez-Martínez, D.; Noriega Barbosa, D.A. An Innovative Approach to Radiality Representation in Electrical Distribution System Reconfiguration: Enhanced Efficiency and Computational Performance. Energies 2024, 17, 2633. [Google Scholar] [CrossRef]
  28. Gholami, M.; Ahmadi, I.; Pouriani, M. Optimal placement of fault indicator and remote-controlled switches for predetermined reliability of selected buses. IET Gener. Transm. Distrib. 2023, 17, 2799–2810. [Google Scholar] [CrossRef]
  29. Wang, S.; Jia, H.; Abualigah, L.; Liu, Q.; Zheng, R. An Improved Hybrid Aquila Optimizer and Harris Hawks Algorithm for Solving Industrial Engineering Optimization Problems. Processes 2021, 9, 1551. [Google Scholar] [CrossRef]
  30. Nasir, M.; Sadollah, A.; Mirjalili, S.; Mansouri, S.A.; Safaraliev, M.; Jordehi, A.R. A Comprehensive Review on Applications of Grey Wolf Optimizer in Energy Systems. Arch. Comput. Methods Eng. 2025, 32, 2279–2319. [Google Scholar] [CrossRef]
  31. Bhadouria, V.P.S.; Srivastava, L. Grey Wolf optimization Algorithm for Optimal Siting and Sizing of Capacitors. In Proceedings of the 2018 2nd IEEE International Conference on Power Electronics, Intelligent Control and Energy Systems (ICPEICES), Delhi, India, 22–24 October 2018; pp. 23–28. [Google Scholar] [CrossRef]
  32. Ali, A.; Saand, A.S.; Ali, S.; Siddiqui, R.A.; Koondhar, M.A.; Albasha, L.; Alsaif, F. A novel hybrid multi operator evolutionary algorithm for dynamic distributed generation optimization and optimal feeder reconfiguration. Sci. Rep. 2025, 15, 32715. [Google Scholar] [CrossRef] [PubMed]
  33. Ghorbani-Juybari, M.Z.; Gholizade-Narm, H.; Damchi, Y. Optimal Recloser Placement in Distribution System Considering Maneuver Points, Practical Limitations, and Recloser Malfunction. Int. Trans. Electr. Energy Syst. 2022, 2022, 5062350. [Google Scholar] [CrossRef]
  34. Ghosh, B.; Chakraborty, A.K.; Bhowmik, A.R. Reliability and efficiency enhancement of a radial distribution system through value-based auto-recloser placement and network remodelling. Prot. Control Mod. Power Syst. 2023, 8, 1. [Google Scholar] [CrossRef]
  35. Hajiabadi, M.E.; Samadi, M.; Lotfi, H. Reliability Assessment of Distribution Systems Using Graph Theory With Optimal Protection, Telecontrol Switch Placement and Distributed Generation Units. IET Gener. Transm. Distrib. 2025, 19, e70202. [Google Scholar] [CrossRef]
  36. Zhang, Y.; Xu, X.; Zhang, N.; Zhang, K.; Dong, W.; Li, X. Adaptive Aquila Optimizer Combining Niche Thought with Dispersed Chaotic Swarm. Sensors 2023, 23, 755. [Google Scholar] [CrossRef] [PubMed]
  37. Pan, C.; Ren, L.; Wan, J. Reliability Prediction of Distribution Network Using IAO-Optimized Mixed-Kernel LSSVM. Energies 2023, 16, 7448. [Google Scholar] [CrossRef]
  38. Lei, T.; Riaz, S.; Raziq, H.; Batool, M.; Pan, F.; Wang, J. A Comparison of Metaheuristic Techniques for Solving Optimal Sitting and Sizing Problems of Capacitor Banks to Reduce the Power Loss in Radial Distribution System. Complexity 2022, 2022, 4547212. [Google Scholar] [CrossRef]
  39. Kumar, S.; Mandal, K.K.; Chakraborty, N. Comparative performance study of various PSO techniques for multiple allocations of DG units in radial distribution system. In 2015 IEEE Power, Communication and Information Technology Conference (PCITC); IEEE: Bhubaneswar, India, 2015; pp. 878–883. [Google Scholar] [CrossRef]
  40. Swarnalaxmi, V.; Anbuselvan, N.; Yuvaraj, T. Improving the Total Operating Cost of IEEE 69 Bus System Using Fuzzy Lighting Search Algorithm Compared with Firefly Algorithm by Mitigating the Real Power Loss. In Proceedings of the 2024 International Conference on Recent Innovation in Smart and Sustainable Technology (ICRISST), Bengaluru, India, 15–16 March 2024; pp. 1–5. [Google Scholar] [CrossRef]
  41. Ebrahimi, M.; Rastegar, M. Learning-Assisted Model for Optimal Placement of Protective Devices and Switches in Power Distribution Systems. IEEE Trans. Power Syst. 2024, 39, 5091–5102. [Google Scholar] [CrossRef]
  42. Michalewicz, Z.; Schoenauer, M. Evolutionary Algorithms for Constrained Parameter Optimization Problems. Evol. Comput. 1996, 4, 1–32. [Google Scholar] [CrossRef]
Figure 1. Flowchart of the proposed research framework for the optimal placement of sectionalizing devices.
Figure 1. Flowchart of the proposed research framework for the optimal placement of sectionalizing devices.
Energies 19 03472 g001
Figure 2. IEEE 69-bus test system implemented in PowerFactory.
Figure 2. IEEE 69-bus test system implemented in PowerFactory.
Energies 19 03472 g002
Figure 3. Convergence of the Aquila Optimizer (AO).
Figure 3. Convergence of the Aquila Optimizer (AO).
Energies 19 03472 g003
Figure 4. Comparison of AO results with respect to the base case.
Figure 4. Comparison of AO results with respect to the base case.
Energies 19 03472 g004
Figure 5. Convergence of the Grey Wolf Optimizer (GWO).
Figure 5. Convergence of the Grey Wolf Optimizer (GWO).
Energies 19 03472 g005
Figure 6. Comparison of GWO reliability indices with respect to the base case.
Figure 6. Comparison of GWO reliability indices with respect to the base case.
Energies 19 03472 g006
Figure 7. Convergence of the hybrid GA-PSO algorithm.
Figure 7. Convergence of the hybrid GA-PSO algorithm.
Energies 19 03472 g007
Figure 8. Comparison of GA-PSO reliability indices with respect to the base case.
Figure 8. Comparison of GA-PSO reliability indices with respect to the base case.
Energies 19 03472 g008
Figure 9. Average convergence of the algorithms.
Figure 9. Average convergence of the algorithms.
Energies 19 03472 g009
Figure 10. Comparison of mean cost and standard deviation among algorithms.
Figure 10. Comparison of mean cost and standard deviation among algorithms.
Energies 19 03472 g010
Figure 11. Comparison of the mean computational time of the algorithms.
Figure 11. Comparison of the mean computational time of the algorithms.
Energies 19 03472 g011
Figure 12. Comparative radar chart of the three algorithms.
Figure 12. Comparative radar chart of the three algorithms.
Energies 19 03472 g012
Table 1. Candidate-branch set used for sectionalizing-device placement in the IEEE 69-bus feeder.
Table 1. Candidate-branch set used for sectionalizing-device placement in the IEEE 69-bus feeder.
ItemDescription
Complete branch set | E | = 68 branches.
Excluded branches L 1 _ 2 , L 26 _ 27 , L 34 _ 35 , L 45 _ 46 , L 49 _ 50 , L 51 _ 52 , L 64 _ 65 , L 66 _ 67 , and L 68 _ 69 .
Candidate branches L 2 _ 3 , L 3 _ 4 , L 4 _ 5 , L 5 _ 6 , L 6 _ 7 , L 7 _ 8 , L 8 _ 9 , L 9 _ 10 , L 10 _ 11 , L 11 _ 12 , L 12 _ 13 , L 13 _ 14 , L 14 _ 15 , L 15 _ 16 , L 16 _ 17 , L 17 _ 18 , L 18 _ 19 , L 19 _ 20 , L 20 _ 21 , L 21 _ 22 , L 22 _ 23 , L 23 _ 24 , L 24 _ 25 , L 25 _ 26 , L 28 _ 3 , L 28 _ 29 , L 29 _ 30 , L 30 _ 31 , L 31 _ 32 , L 32 _ 33 , L 33 _ 34 , L 3 _ 36 , L 36 _ 37 , L 37 _ 38 , L 38 _ 39 , L 39 _ 40 , L 40 _ 41 , L 41 _ 42 , L 42 _ 43 , L 43 _ 44 , L 44 _ 45 , L 4 _ 47 , L 47 _ 48 , L 48 _ 49 , L 8 _ 51 , L 9 _ 53 , L 53 _ 54 , L 54 _ 55 , L 55 _ 56 , L 56 _ 57 , L 57 _ 58 , L 58 _ 59 , L 59 _ 60 , L 60 _ 61 , L 61 _ 62 , L 62 _ 63 , L 63 _ 64 , L 11 _ 66 , and L 12 _ 68 .
Number of candidate branches | C | = 59 .
Binary search space 2 59 = 5.76 × 10 17 possible configurations.
Table 2. Initial parameters of the IEEE 69-bus test system.
Table 2. Initial parameters of the IEEE 69-bus test system.
ParameterSymbolValue
Failure rate λ 0.10 f/km-year
Repair timer4.0 h
Switching time t s 1.0 h
Value of lost load V O L L 3.0 USD/kWh
Annualized cost of each sectionalizer c j 1302 USD/year
Load factor L F 0.6
Maximum number of devices N max 10
Annual budgetB13,020 USD/year
Note: The annualized sectionalizing-device cost c j is assumed uniform across all candidate branches under the homogeneous-cost benchmark assumption.
Table 3. General comparative procedure for the optimal placement of sectionalizing devices.
Table 3. General comparative procedure for the optimal placement of sectionalizing devices.
Item Description
Input:Network G = ( N , E ) , candidate-branch set C , reliability parameters { λ i , r i } , nodal demand L i , number of customers N i , costs { c u , c j } , budget B, maximum number of devices N max , maximum restoration time T max , population size P, maximum number of iterations T, and set of pseudo-random seeds S .
Output:Best solution x best , best objective value F best , SAIFI, SAIDI, and CAIDI.
1:Define the set of algorithms A { AO , GWO , GA - PSO } .
2:For each algorithm a A , do:
3:   For each seed s S , do:
4:      Set the pseudo-random seed s.
5:      Initialize the population X = { x 1 , x 2 , , x P } .
6:      For i = 1 , , P , do:
7:         If the algorithm uses a continuous representation, binarize x i .
8:         Evaluate Φ ( x i ) using the penalized fitness function.
9:      End for.
10:      Set x best as the best initial solution.
11:      For t = 1 , , T , do:
12:         For i = 1 , , P , do:
13:            If a = AO , update x i using the AO rules.
14:            Else if a = GWO , update x i using the GWO rules.
15:            Else if a = GA - PSO , update x i using the PSO component and GA operators.
16:            If required, binarize x i .
17:            Verify operational and economic constraints.
18:            Evaluate Φ ( x i ) .
19:            If Φ ( x i ) < Φ ( x best ) , set x best x i .
20:         End for.
21:         Record Φ ( x best ) , iteration t, and computational time.
22:      End for.
23:      Calculate F ( x best ) , SAIFI, SAIDI, and CAIDI.
24:      Store the results of seed s for algorithm a.
25:   End for.
26:   Calculate the statistical performance metrics for algorithm a.
27:End for.
28:Compare AO, GWO, and GA-PSO in terms of total cost, convergence, computational time, and reliability indices.
29:Return the best-performing algorithm and its optimal vector x best .
Table 4. Common parameters used for the three algorithms.
Table 4. Common parameters used for the three algorithms.
ParameterSymbolValue
Population sizeP30
Maximum iterationsT200
Independent runs30
Pseudo-random seed set S { 1 , 2 , , 30 }
Binarization functionSigmoid transfer function with stochastic threshold rand U ( 0 , 1 )
Penalty coefficient ρ 10 6 USD/year
Constraint-violation treatmentNormalized quadratic penalty according to (22) and (23)
Table 5. Specific parameters used for each algorithm.
Table 5. Specific parameters used for each algorithm.
AlgorithmParameterSymbolValue
AOLévy exponent β 1.5
AOExploitation constants α , δ 0.1
GWOControl coefficienta 2 0 linearly
GA-PSOInertia coefficientw 0.9 0.4 linearly
GA-PSOCognitive/social coefficients c 1 , c 2 2.0/2.0
GA-PSOCrossover probability p c 0.8
GA-PSOMutation probability p m 0.1
GA-PSOFraction renewed by GA0.3
Table 6. Input data and processing workflow used in the case study.
Table 6. Input data and processing workflow used in the case study.
Input DataSource or TreatmentUse in the Model
Feeder topology and branch identifiersExported from the verified PowerFactory modelConstruction of the radial upstream–downstream incidence structure and candidate-branch mapping.
Branch lengths l i j Line-element data of the IEEE 69-bus feederCalculation of branch annual failure rates through λ i j = λ i j km l i j .
Nodal active-power demandIEEE 69-bus load data represented in PowerFactoryCalculation of L i = P i , avg and EENS through i U i ( x ) L i .
Load factor L F Adopted case-study parameterConversion from peak demand to average demand when required.
Reliability parameters λ km , r, and t s Adopted values summarized in Table 2Construction of branch failure rates and restoration-time matrix r m n , i ( x ) .
Affectation matrix a m n , i ( x ) Computed in MATLAB from radial topology and selected devicesIdentification of load points interrupted by each branch fault under each candidate configuration.
Restoration-time matrix r m n , i ( x ) Computed in MATLAB from fault location, sectionalizing-device positions, repair time, and switching timeCalculation of annual unavailability U i ( x ) , SAIDI, CAIDI, and EENS.
Economic parameters V O L L , c j , and BAdopted case-study parametersCalculation of interruption cost, annualized investment cost, budget feasibility, and total expected cost.
Table 7. Reliability indices of the base case without additional sectionalizing devices.
Table 7. Reliability indices of the base case without additional sectionalizing devices.
IndicatorSymbolValue
System average interruption frequency indexSAIFI6.80 interruptions/customer·year
System average interruption duration indexSAIDI27.20 h/customer·year
Customer average interruption duration indexCAIDI4.00 h/interruption
Expected energy not suppliedEENS43,383 kWh/year
Annual interruption cost C int 130,150 USD/year
Table 8. Improvement of reliability and cost indicators obtained with the Aquila Optimizer.
Table 8. Improvement of reliability and cost indicators obtained with the Aquila Optimizer.
IndicatorBase CaseAOImprovement
SAIFI6.806.800.0%
SAIDI [h]27.2011.5057.7%
CAIDI [h]4.001.6957.7%
EENS [kWh/year]43,38318,34257.7%
Total cost [USD/year]130,15065,44349.7%
Number of sectionalizing devices8
Table 9. Reliability and cost indicators obtained with the Grey Wolf Optimizer.
Table 9. Reliability and cost indicators obtained with the Grey Wolf Optimizer.
IndicatorBase CaseGWOImprovement
SAIFI6.806.800.0%
SAIDI [h]27.2011.4158.1%
CAIDI [h]4.001.6858.1%
EENS [kWh/year]43,38318,20258.0%
Total cost [USD/year]130,15065,02350.0%
Number of sectionalizing devices8
Table 10. Reliability and cost indicators obtained with the hybrid GA-PSO algorithm.
Table 10. Reliability and cost indicators obtained with the hybrid GA-PSO algorithm.
IndicatorBase CaseGA-PSOImprovement
SAIFI6.806.800.0%
SAIDI [h]27.2011.4158.1%
CAIDI [h]4.001.6858.1%
EENS [kWh/year]43,38318,20258.0%
Total cost [USD/year]130,15065,02350.0%
Number of sectionalizing devices8
Table 11. Statistical comparison of objective-function values over 30 independent runs.
Table 11. Statistical comparison of objective-function values over 30 independent runs.
AlgorithmBest F
[USD/Year]
Mean F
[USD/Year]
Worst F
[USD/Year]
σ F
[USD]
CV F
[%]
95% CI of F ¯
[USD/Year]
AO65,44369,03474,76523143.35[68,170, 69,898]
GWO65,02366,00467,5087601.15[65,720, 66,288]
GA-PSO65,02367,17771,37513892.07[66,658, 67,696]
Table 12. Comparison of dispersion, computational time, and number of devices among algorithms.
Table 12. Comparison of dispersion, computational time, and number of devices among algorithms.
Algorithm σ F [USD] CV F [%]Mean Time [s]No. Devices in Best Configuration
AO23143.351.498
GWO7601.151.508
GA-PSO13892.072.148
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Gaibor Fierro, J.J.; Aguila Téllez, A.; Jaramillo Monge, M.D. Optimal Placement of Sectionalizing Devices in Radial Distribution Networks for Reliability Improvement Using the Aquila Optimizer. Energies 2026, 19, 3472. https://doi.org/10.3390/en19153472

AMA Style

Gaibor Fierro JJ, Aguila Téllez A, Jaramillo Monge MD. Optimal Placement of Sectionalizing Devices in Radial Distribution Networks for Reliability Improvement Using the Aquila Optimizer. Energies. 2026; 19(15):3472. https://doi.org/10.3390/en19153472

Chicago/Turabian Style

Gaibor Fierro, Juan José, Alexander Aguila Téllez, and Manuel Darío Jaramillo Monge. 2026. "Optimal Placement of Sectionalizing Devices in Radial Distribution Networks for Reliability Improvement Using the Aquila Optimizer" Energies 19, no. 15: 3472. https://doi.org/10.3390/en19153472

APA Style

Gaibor Fierro, J. J., Aguila Téllez, A., & Jaramillo Monge, M. D. (2026). Optimal Placement of Sectionalizing Devices in Radial Distribution Networks for Reliability Improvement Using the Aquila Optimizer. Energies, 19(15), 3472. https://doi.org/10.3390/en19153472

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop