Next Article in Journal
CO2 Geothermal Power Generation: Laboratory Experiment on the Interaction Between Carbonated Water and Rishiri Island Basalt in the Vicinity of Injection Wells
Previous Article in Journal
Day-Ahead Optimal Scheduling of an Integrated Electricity-Heat-Gas-Cooling-Hydrogen Energy System Considering Stepped Carbon Trading
Previous Article in Special Issue
Route-Based Optimization Methods for Energy Consumption Modeling of Electric Trucks
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Design of Multi-Objective Energy Management for Remote Communities Connected with an Optimal Hybrid Integrated Photovoltaic–Hydropower–Battery Energy Storage System (PV-HP-BESS) Using Improved Particle Swarm Optimization

by
Chaimongkol Pengtem
1,
Saksit Deeum
2,
Amirullah
3,
Hideaki Ohgaki
4,
Sillawat Romphochai
1,
Pimnapat Bhumkittipich
5 and
Krischonme Bhumkittipich
1,*
1
Department of Electrical Engineering, Faculty of Engineering, Rajamangala University of Technology Thanyaburi (RMUTT), Thanyaburi 12110, Pathum Thani, Thailand
2
Department of Science Service, Ministry of Higher Education, Science, Research and Innovation, Thanon Rama VI, Thung Phayathai, Ratchathewi, Bangkok 10400, Thailand
3
Department of Electrical Engineering, Faculty of Engineering, Universitas Bhayangkara Surabaya, Surabaya 60231, Indonesia
4
Graduate School of Energy Science, Institute of Advanced Energy, Kyoto University, Gokasho, Uji 611-0011, Kyoto, Japan
5
Department of Social Science, Faculty of Liberal Arts, Rajamangala University of Technology Thanyaburi (RMUTT), Khlong Luang 12110, Pathum Thani, Thailand
*
Author to whom correspondence should be addressed.
Energies 2025, 18(9), 2250; https://doi.org/10.3390/en18092250
Submission received: 31 March 2025 / Revised: 26 April 2025 / Accepted: 27 April 2025 / Published: 28 April 2025

Abstract

:
The potential for electricity distribution in power systems has significantly increased over the years. This is mainly because of the discovery of alternative electricity generation sources, such as renewable energy, coupled with distributed generation (DG), making electricity more widely accessible. However, challenges remain in distributing electricity to remote area communities (RACs), especially because of difficult terrain and the complexity of installing power plants, leaving some areas without access to electricity. In this study, we used an improved particle swarm optimization (IPSO) technique to propose multi-objective energy management for remote area communities within a hybrid integrated Photovoltaic–(PV)–Hydropower plant (HPP)–Battery Energy Storage System (BESS). The multi-objective functions enhance power quality and voltage stability to meet grid code requirements. The proposed method was applied to the IEEE 15-bus system, which is consistent with systems commonly used in remote area communities, under the following scenarios: Case I—random installation of PV-HPP-BESS and PI parameter control of BESS; Case II—optimal location of PV-HP-BESS and PI parameter control of BESS using IPSO; Case III—sudden short circuit of the transmission line in Case II. Effectiveness was verified through hardware-in-the-loop (HIL) testing. The experimental results indicate that the proposed method significantly improves power quality and stability under disturbances, demonstrating superior performance.

1. Introduction

Energy is a crucial factor for electrical systems worldwide. As human resources expand and technology advances, energy demand continues to rise. The lack of sufficient energy can have widespread consequences, potentially leading to system failures. To avoid these effects, a power system must maintain a high enough balance to satisfy demand. Even if the existing power system can maintain equilibrium, overall stability is still lacking. Demand response in remote areas remains a challenge, as the cost of transmission increases with distance, and a limited production capacity contributes to shortages in these areas [1]. When energy from the power system cannot supply remote areas, renewable energy sources (RESs) such as solar power, wind, and biofuels can serve as alternatives.
A key advantage of RESs is their ability to reduce greenhouse gas emissions. Thus, they provide clean and environmentally friendly energy solutions. As a result, many RES studies have focused on addressing energy enhancement challenges in remote areas. Irshad A. S. [2] proposed an optimal system configuration for a hybrid solar photovoltaic (PV), wind, and hydropower plant (HPP) system by using the multi-objective genetic algorithm (MOGA) optimization technique to determine the ideal size of the renewable energy system. The suggested installation methods were PV (88 kW), wind turbine (18 kW), hydropower no. 1 (215 kW), and hydropower no. 2 (197 kW). This configuration was able to enhance electrical systems in remote areas without requiring a battery energy storage system (BESS). However, this method has limitations related to the location and weather conditions required for installation; these factors need to be evaluated prior to the application of the proposed RESs. The installation space requirement of RESs is another important factor to consider. Therefore, researchers have explored the use of RESs alongside loads to reduce the demand for energy consumption in electrical systems. Eihab E.E. Ahmed et al. [3] proposed a PV system for load use with multi-objective optimization and minimal installation using loss of load probability (LLP) and life cycle cost (LCC). The particle swarm optimization (PSO) algorithm and a new Python version 3.10.5 package were used to determine the optimal number and size of PV installations to meet the load requirements. However, usage duration is still a concern in this method. Relying on PV energy requires an adequate production period to support the load. A major limitation of RESs is inconsistent energy production, which depends on local environmental conditions.
In this context, BESSs help address the limitations of RESs by storing excess energy during production periods and supplying it to the system when needed. BESSs are thus often integrated with RESs to overcome energy challenges in remote areas. Prabpal P. et al. [4] proposed a BESS based on a symmetrical concept, utilizing the symmetrical volt/var control technique for regulation. Integrating the BESS into the conventional distribution system notably influenced energy consumption. The optimal BESS solution was achieved by applying genetic algorithm (GA) optimization and the PSO technique. The simulation results demonstrated that the BESS, directly connected to the power grid using GA and PSO, effectively optimized its size and location. This optimization helped minimize the impact of load demand on total system losses and balanced energy demand within the power system network. Despite this, installing a BESS in a looped system may have a limited impact, as some systems are already designed to manage load distribution. In such cases, BESS installation may primarily contribute to reducing energy production. Installing BESSs along with RESs may cause an imbalance in energy control. Therefore, subsequent studies have focused on improving energy distribution methods combined with BESSs and RESs [5,6,7]. Following the integration of a BESS with RESs, available energy control methods include using a voltage source to supply energy through the BESS, setting multiple objectives for regulating energy injection, and designing controllers to operate alongside the BESS inverter. These methods lead to appropriate energy control outcomes when the BESS is connected to the power system. However, the time frame for injecting energy into the system remains a critical factor, and it cannot be resolved when energy cannot be drawn from the power system over the long term.
Due to this limitation, hybrid energy systems (HESs) have gained significant interest among researchers. Hybrid energy systems integrate synchronous generators powered by diesel fuel with RESs and BESSs, significantly improving power distribution stability within the grid code. A distributed generator (DG) is the primary power source, while a RES is an auxiliary generator, and a BESS serves as backup energy storage. This combined operation enhances power system stability, even in remote areas [8]. As a result, HESs have become a widely explored research topic. For instance, the authors of [9,10,11] proposed the integration of DGs with RESs and BESSs to improve the stability of a power system, with various solutions such as changing the battery type in the HES, installing capacitors alongside the BESS, and scheduling energy injection periods. While the proposed methods can address some of the issues, their objectives and constraints do not cover all the challenges identified, potentially leading to solutions that are only partially effective. To fully resolve these issues, Hosseini E. et al. [12] proposed an innovative optimal energy management system (EMS) that utilizes a nonlinear constrained multi-variable function to enhance BESS operation in an HP plant combining wind turbines (WTs) and photovoltaic (PV) plants. The hybrid system employs a battery-stored impedance-based cascaded multilevel inverter to efficiently integrate renewable energy sources, including PV plants, WTs, and BESSs, into the grid. The proposed algorithm achieved grid power while efficiently distributing excess deficit power among the BESSs. However, the rate at which excess energy is removed and injected into the system creates control limitations, resulting in delays in enhancing the power system. Despite the development of HESs via the co-installation of a DG along with RESs and BESSs, minor issues with energy distribution in remote areas persist. While the production side can meet demand during specific periods, transient power system disturbances can lead to system changes. If these issues are overlooked, they could damage sensitive devices [13].
Transient analysis is essential for solving problems in remote areas, as integrating RESs into electrical systems leads to issues such as increased inertia and a delayed recovery of system balance. To tackle this, researchers have begun to explore HES device control [14]. The authors of [15,16,17] proposed enhancing the control of HES devices by defining method objectives, constraints, and analyses through algorithms to help maintain energy balance in the electrical system. This effectively reduces power system disturbances, including inertia from RES installation and sudden disruptions in remote areas. However, improving HES equipment control is highly complex. To tackle this challenge, large electrical systems with enhanced HES control are divided into smaller sections, known as microgrid systems [18].
Microgrid systems have steadily gained popularity because of advancements in automation systems, power electronics, and small-scale power equipment, as well as a decline in the cost of energy produced by small-scale RESs. Microgrids can be viewed as a practical approach to decentralizing power systems [19]. This decentralization has been shown to positively impact the reliability of energy supply, especially in remote areas. Microgrids are effective in improving system reliability and resilience while lowering greenhouse gas emissions through the integration of HER [20]. To evaluate the concept of such microgrids, studies [21,22,23] propose solutions to the power flow challenge in remote regions by using simulations based on the standard IEEE 15-bus test system, which mirrors the load characteristics typical of these areas. They apply widely used optimization techniques—including GA, PSO, and Flower Pollination Algorithm (FPA)—to optimize the location and sizing of components in the distribution network. By simulating the test system to resemble the actual power system closely, the results can be applied to the real power system. Various approaches have been utilized to improve the efficiency of microgrid systems for more comprehensive analysis; for instance, some studies [24,25,26] have proposed optimal schedules for microgrids. The analysis of a microgrid’s power distribution schedule relies on forecasting and algorithms to determine the power distribution. Efficiency is influenced by the quality of previously collected and enhanced data and the strengths of the chosen algorithm. However, the challenge in improving efficiency through forecasting and algorithms lies in data recorded before microgrid optimization, as these data may contain transient disturbances. To achieve accurate, error-free results, collecting data from multiple points over the same period as forecasting data may be necessary. For cases in which forecasting depends on large datasets, some studies have investigated the use of algorithms to identify the optimal controller values; for example, the authors of [27,28] analyzed HES device control in microgrid systems and utilized various algorithms to improve the system’s stability during electrical disturbances in both steady-state and dynamic conditions. The results address disturbances in electrical systems under these conditions. However, these studies focus on single objectives and lack a thorough analysis, offering a solution to the symptoms rather than addressing the root cause. Thus, a comprehensive study on different factors ranging from installation to time-based control is needed to address this core issue.
This study presents a methodology for determining the optimal locations and sizing of HESs and controlling the design parameters for BESSs using improved particle swarm optimization (IPSO) to improve power quality and stability in remote communities. The analysis is guided by a multi-objective function consisting of minimizing power loss, minimizing the line voltage stability index, and minimizing fuel costs. The method involves two steps: First, steady-state analysis is performed to determine the optimal location and size of the HES during a peak RES energy production period. Then, disturbances in the power system are investigated during the transient period, utilizing the results from the first step. During this period, the BESS controller parameters are optimized using IPSO, with a hardware-in-the-loop (HIL) setup and a 5-s resolution. Our approach considers multiple factors, including load distribution, HER output variability, and grid code requirements, to provide a robust solution for various grid configurations. A summary of prior studies on the topic is provided in the table below.

2. Remote Area Communities

The distribution of energy to remote areas presents a significant challenge for a power system. As power demand continues to rise and the need for power transmission to distant locations grows, energy generation at the source must also increase [29]. This study proposes a method to address this issue and investigates potential solutions. A remote community (RAC) was simulated using the IEEE 15-bus system, as its load resembles those of remote areas, including a voltage stability index (VSI) below the acceptable range of 0.95–1.05 p.u. and considerable power losses that result in high energy production costs. The IEEE 15-bus system was thus used to test an integrated multi-objective energy management method in a remote area community, as illustrated in Figure 1.
It analyzed the challenges a remote area community faces using the backward–forward sweep (BFS) method for power flow analysis and examined problems within the power system, such as generation, transmission, and distribution. The BFS method consists of four steps, which are outlined below.

2.1. Nodal Current

The reference voltage magnitude and phase angle are set at the root node, serving as the initial voltage for all other nodes in the distribution network. The node current at bus i can be shown in Equation (1).
I i , p k = P i + j Q i V i ( k 1 ) f o r i = 2 , 3 , , N
where P i and j Q i are the active and reactive power consumed by loads at the i th nodes; V i ( k 1 ) is the complex nodes voltage of the i th nodes calculation round at k 1 .

2.2. Backward Sweep

The currents through the i th branch are calculated starting from the last nodes and moving toward the root node, as shown in Equation (2).
I ¯ b r l = I ¯ n + k M I ¯ b r k
where I ¯ b r l is the current flowing through line segment l ; M is the set of branches connected downstream of node n .

2.3. Forward Sweep

Starting at the root node and progressing toward the outer layers of the network, the voltage at the i th node is calculated along with the resistance of the transmission line R using Equation (3).
V ¯ n = V ¯ m R m n I ¯ b r h   n = 2 , 3 , , N   and   m = 1 , 2 , , N

2.4. Convergence Criterion

This criterion is met as long as the maximum value of the real or theoretical value of the difference between the calculated and specified power injection exceeds the acceptable mismatch ε , as defined in Equation (4):
Δ V ¯ = V ¯ r V ¯ r 1 < ε

3. Hybrid Energy System

3.1. Mathematical Analysis of Fluctuating PV Generation

PV penetration into the distribution network has been demonstrated to enhance the voltage profile and minimize power losses [30]. Therefore, PV should be planned based on its capacity and installation point in the distribution network. PV output power data, irradiance, and temperature at the reference location of the distribution system have been used to estimate the amount of PV generated. Based on [31,32], the amount of power generated via PV is estimated using Equation (5).
P P V = P R , P V × R s u n R r e f × 1 + η × T P V T r e f
where P R , P V is the PV panels rated power W , R s u n is the radiation intensity, R r e f is the referent radiation intensity, T P V is the temperature of PV panels (°C), T r e f is the corresponds to the reference test temperature for PV panels, set at 25 °C, and η is the panel efficiency, respectively.

3.2. Mathematical Analysis of Fluctuating HPP Generation

Run-of-the-river HPP generates turbine water flow largely dependent on the upstream river level. The generated power primarily relies on key factors such as water discharge and hydraulic head. Equation (6) expresses the formula for calculating the power output of an HPP plant [33].
P H P P = ρ × g × H × Q × η
where P H P P represents the output power ( kW ), ρ is the water density (1000 kg / m 3 ), and g represents the gravitational acceleration (9.81 m / s 2 ). Additionally, Q refers to the water flow rate or discharge ( m 3 / s ), H represents the hydraulic head ( m ), and η is the plant’s overall efficiency. The power generated by the HPP is thus directly determined.

3.3. Mathematical Analysis of BESSs

The deployment of BESSs within global power electricity networks is increasing. Numerous countries have integrated BESSs to maintain grid stability and manage power balance [32]. BESSs are crucial in reducing output power fluctuations and improving voltage stability. By applying the proposed optimization model, the optimal BESS capacity and charging/discharging cycle can be determined [31]. When P B E S S t > 0 , the discharge energy in the BESS for each period is mathematically expressed in Equation (7).
C t = C t 1 P B E S S t Δ T η d i s
On the other hand when P B E S S t < 0 , the discharge energy in the BESS for each period is mathematically expressed in Equation (8).
C t = C t 1 P B E S S t Δ T η c h g
where t represents the time interval under consideration and T denotes the total time horizon in hours. P B E S S t refers to the BESS power output at the t th time interval and C t is the energy stored in the BESS at the end of the t th interval. Δ T indicates the duration of each time interval, η d i s is the discharge efficiency of the BESS, and η c h g represents its charging efficiency. Additionally, the energy stored in the battery at the end of the t th interval must remain within the minimum state of charge (SOC) limit and the BESS energy rating, as shown in Equation (9).
S O C min C r a t e d C t C r a t e d

4. Problem Statement

The problem outlined in this study breaks down the objective function into three separate tasks. The optimal solution must be evaluated within the given conditions of the proposed power system. The multi-objective function equations consider three objective functions: reducing active power loss, minimizing fuel costs of the grid system, and reducing the line voltage stability index (LVSI), as described below. By utilizing IPSO, more suitable and advantageous variants are selected, making IPSO an effective technique for solving optimization problems. In this method, the model starts with random solutions and progressively finds the optimal solution through iteration based on the defined objectives.

4.1. Multi-Objective Function Formulation

The optimal location and sizing of the PV, HPP, and BESS units within the distribution system are determined according to the multi-objective function defined in Equation (10).
F x = min ( w 1 f 1 + w 2 f 2 + w 3 f 3 )
subject   to   g ¯ x , u = 0
and   h x , u 0
where g ¯ represents the equality and h the inequality constraints of all objective functions, and w 1 , w 2 ,   and   w 3 are the weights for the analysis function.

4.1.1. Active Power Loss Reduction

The first objective function is the active power loss ( P l o s s ) reduction, which is expressed in Equation (13).
f 1 = min ( P l o s s )
where f 1 represents the first objective function, and P l o s s denotes the active power loss in the distribution system. The active power loss is calculated according to Equation (14).
min P l o s s = i = 1 n j = 1 n a i j ( P i P j + Q i Q j ) + b i j ( Q i P j P i Q j )
where P i and P j represent the active power at nodes i and j , respectively; Q i and Q j denote the reactive power at nodes i and j ; a i j and b i j are the constants associated with each node.

4.1.2. Fuel Cost Reduction

The second objective function is to minimize fuel costs, as defined by Equation (15).
f 2 = min ( C f )
where f 2 represents the second objective function, and C f represents the total fuel cost of the power system. The total fuel cost of the power system is calculated according to Equation (16).
min C f = i = i N G a i P G i 2 + b i P G i + c i
where N G represents the number of the power generators in the grid system; P G i represents the power generated by the grid system for load; a i , b i and c i represent the grid constraints of fuel cost for power generation.

4.1.3. Line Voltage Stability Index

The third objective function is LVSI reduction, expressed in Equation (17).
f 3 = min ( L V I S )
where f 3 represents the third objective function, and L V I S represents the line voltage stability index. The LVSI is calculated according to Equations (18) and (19).
min L V I S = i = 1 N l i n e L V S I i
L V S I = 4 R P r V s cos θ δ 2
where N l i n e represents the number of transmission lines connected between the nodes, R represents the resistance of the transmission lines, P r represents the active power generation at the receiving nodes, V s represents the voltage at the sending nodes, θ represents the line impedance angle, and δ represents the different voltage phase angles between the start and end nodes.

4.2. Constraints of Multi-Objective Function Formulation

The constraints proposed in our study are categorized into six groups and are summarized below.

4.2.1. Power Balance Formulation

The power balance Eqn. for a power system is determined using Equations (20) and (21), while the power demand is determined using Equation (22).
P G i + P H E S , i + P D R , i = P D R , i 0 + P l o s s , i
P H E S , i = s u m ( i = 1 N G P P V , i , i = 1 N G P H P P , i , i = 1 N G P B E S S , i )
P D R , i = s u m ( P G i , P H E S , i ) P l o s s , i
where P G i represents the active power of the grid system, P H E S represents the active power of the hybrid energy system, P D R represents the total active power demand in the grid system, P D R 0 represents the total active power demand in first-time analysis, and N G represents the number of the power generator in nodes.

4.2.2. Generation Limits

Batteries store the surplus energy generated from renewable sources. If they reach their power or energy limits, any excess energy will be absorbed by the grid system (negative power). Consequently, the grid system can accommodate positive and negative power values, as indicated in Equation (23).
< P G i <
The HPP generator will produce energy during periods when P D R is high. Since energy production from HPP cannot be continuous, it will produce energy to reduce P D R or be used with the BESS system. Therefore, the operational limits of the HPP generator are determined by the capacity of the equipment and the volume of fluid flowing through the turbine using Equation (24).
P H P P min < P H P P < P H P P max
PV generators produce a minimum power of zero when there is no solar radiation, and they can generate a maximum power equal to their nominal capacity. Therefore, their operational limits are defined using Equation (25).
P P V , i min < P P V , i < P P V , i max
Batteries can operate either as generators or as loads, producing positive or negative power, respectively, while ensuring they do not exceed their generation and consumption limits, as indicated in Equation (26).
P B E S S , i min < P B E S S , i < P B E S S , i max

4.2.3. BESS Limits of Charging and Discharging

Batteries have upper and lower energy storage limits that should not be exceeded to prevent damage [34]. These constraints are specified in Equation (27).
S O C B E S S , i min < S O C B E S S , i < S O C B E S S , i max
Batteries can function either as generators or as consumers, with their stored energy levels updated at each time interval based on power and operating duration, as defined by Equation (28).
S O C B E S S , i t = S O C B E S S , i t 1 Δ t × P i t × η c Δ t × P i t η d f o r P i t < 0 f o r P i t > 0
where η c and η d are the charging and discharging efficiencies of BESS, respectively, and Δ t is the sampled time period, defined as the entire day.

4.2.4. Voltage Constraints

The node’s voltage profile must be defined to ensure compliance with the voltage stability limits specified in the grid code, as shown in Equations (29) and (31).
V min 0.95 p . u . V i V max 1.05 p . u .
L V S I max L V S I lim i t
L V S I max = max ( L V S I i ) ; i = 1 , 2 , , N l i n e
where L V S I lim i t represents the imposed limit of the LVSI, set to 0.9 in this study, and L V S I max represents the maximum LVSI value within the grid system.

5. Battery Energy Storage System Controller

The BESS controller, integrated with the grid-connected PV and HPP, demonstrates effective performance in system frequency control, charging requests, and battery management through the SOC balance method described. Consequently, utilizing droop characteristics, the BESS power is regulated in response to frequency deviations ( Δ f ):
P B E S S = K B E S S Δ f i f K B E S S Δ f P max P max i f P max < K B E S S Δ f
K B E S S = K max 1 S O C S O C l o w ( h i g h ) S O C max ( min ) S O C S O C l o w ( h i g h )
where K B E S S represents the BESS gain, and P B E S S represents the maximum BESS power. Additionally, K B E S S , based on Equation (33), where S O C l o w , S O C h i g h , S O C max , and S O C min are the SOC design parameters. SOC is regulated using SOC deviation control.

6. The Proposed Improved Particle Swarm Optimization Technique

6.1. Conventional Particle Swarm Optimization Technique

Conventional PSO is inspired by swarm intelligence, mimicking the collective behavior of bird flocks and fish schools. In conventional PSO, each particle dynamically adjusts its velocity based on its own experience and the movements of its peers. The position of a particle is updated considering its current location, velocity, and relative distances to both its personal best position ( p b e s t ) and the global best position ( g b e s t ) found by any particle in the swarm. Unlike other optimization techniques, the neighborhood structure in conventional PSO remains relatively stable and does not change as frequently as in other metaheuristic algorithms [35]. In this study, we utilized conventional PSO to analyze the optimal solutions for specific objective functions. The optimal values were obtained by iteratively searching for the best particle value (individual particle′s best and global best values among all particles). The particle set is represented by Equation (34).
p i = [ P G i , , P N G V G i , , V N G , P p i , P N P , V p i , , V N P , D R 1 , , D R N B ]
Conventional PSO begins by initializing the population and evaluating each particle′s fitness value. Next, it updates the p b e s t and g b e s t positions. In the final step, the velocity and position of all particles are adjusted. The new velocity of the particles is calculated using Equation (35).
v i t + 1 = w v i t + c 1 r 1 ( p b e s t i t p i t ) + c 2 r 2 ( g b e s t i t p i t )
The process of fitness evaluation, updating p b e s t and g b e s t , and adjusting the velocity and position is repeated iteratively until a predefined stopping condition is satisfied. The new positions of particles can be calculated as expressed in Equation (36).
p i t + 1 = p i t + v i t + 1
where p i is the position of the ith particle, V G i is the voltage magnitude of the generator, P p i is the active power of a generator, and D R N B is the actual power demand for node NB.

6.2. Improved Particle Swarm Optimization (IPSO)

Drawing inspiration from the PSO technique [36], we first performed particle discretization. In this model, the discrete operators “⊗”, “⊖”, “⊕”, and “⊙” replace the continuous operators in the PSO algorithm, defining the discretization process as follows:
P i t + 1 = P i t v i t + 1
During particle updates, each dimension of every particle was discretely computed asynchronously. The local modularity incremental function was then utilized to explore each node′s current local information fully. This allowed for the integration of drifting particle modeling. If the electron’s position was considered the candidate solution, and the potential energy function represented the objective function, the electron’s motion was considered similar to searching for the minimum solution. Consequently, the particle update equation was reformulated as follows:
P i t + 1 = P i t + v i t + 1
v i t + 1 = α c 1 t x i , j t φ i , j t + β p i t x i , j t
Parameter α is known as the compression–expansion coefficient, while β is referred to as the acceleration coefficient. These two key parameters can be adjusted to balance the particles’ global and local search capabilities. Higher α and β values enhance the global search ability, whereas lower values improve local search performance.
In Figure 2, a comparison is presented between the traditional PSO algorithm and an improved PSO variant. The left figure illustrates the behavior of the traditional PSO, where it is observed that the particles take a longer path to converge toward the optimal solution. This limitation arises from a known flaw in the traditional PSO approach: increasing the swarm size can accelerate convergence per iteration, but it also leads to a significant increase in the amount of data that needs to be processed. To address this issue, the improved PSO algorithm introduces a partial area analysis strategy centered around the p b e s t point, as shown in the right figure. In this approach, local searches are performed near the p b e s t point, generating new candidate points that are closer to the optimal solution than the original p b e s t . After completing the local analysis, the algorithm proceeds with a more focused convergence phase, leading to faster and more efficient optimization.

7. Simulation Results

This study presents the simulation parameters. Consisting of the population and iteration process for the proposed method, they were determined based on bus voltage sensitivity, with the population size set to 30 and the number of iterations set to 100. The optimal location and sizing of the HES units were determined using the IPSO method. Finally, in Case III, a sudden short circuit of the transmission line in Case II was investigated. The effectiveness of the method was verified through HIL testing.

7.1. Case I: Random Installation of PV-HP-BESS and PI Parameter Control of BESS

For this test case, the initial parameters included a search population of 30 groups and an infinite number of iterations. The HES was installed at a single point; the installation size ranged from 10 to 65 kW for PV, 10 to 100 kW for HP, and f10 to 100 kW for the BESS. This setup allowed u to find the best location and size. The results of the random installation indicate that it can enhance the voltage level of the IEEE 15-bus system. However, the HES was installed on wire ends, with more than 30 iterations, as shown in Figure 3. The random installation of the PV, HPP, and BESS in locations 13, 12, and 5 had a size of 90.86, 62.41, and 65 kW, respectively. This setup reduced the power loss in the grid system to 44.23 kW and lowered the fuel cost of the grid system to 3832.1 USD/h.
The findings on the optimal location and size of the HES suggest that selecting the best location supports maintaining voltage stability in the power distribution system during periods of increased load. The voltage level in the tested scenario was higher than that in the base case. Consequently, these findings do not align with the objectives of this study.

7.2. Case II: Optimal Location of PV-HP-BESS and PI Parameter Control of BESS

In Case II, the initial parameters were kept the same as those in Case I. Additionally, the IPSO method was applied to determine the optimal location and size of the HES, with the multi-objective function weights randomly assigned values between 1 and 100. IPSO begins by adjusting the parameters in Equation (20) to determine the optimal position and size of the HES. Once these parameters are fine-tuned, the results are used to refine the solutions for the weights of the three main objectives, as outlined in Equation (10). The optimization process then aims to minimize the value according to the defined objective ( f 1 , f 2 , f 3 ). The optimization results obtained through the IPSO method, adjusted based on these weights, are presented in Figure 4. Consisting of three axes: the X-axis represents power loss, the Y-axis represents the fuel cost of the grid system, and the Z-axis represents the LVSI. When one of the objectives is assigned the least weight (or a value of 0), it results in the highest optimal value, forming a triangular area of optimal solutions. The best solution in each iteration will adjust the weights of the main objectives differently, leading to unique results. The most optimal values presented in Figure 4 are those with the adjusted weights.
The optimal locations for the PV, HP, and BESS units at locations 8, 15, and 13, with sizes of 65 kW, 100 kW, and 50 kW, respectively, reduced the power losses in the grid system to 43.873 kW and decreased the fuel cost to 3825.7 USD/h. The test results from the various cases were compared using LVSI, as shown in Figure 5.
To obtain the most appropriate results for further development in Case 3, the outcomes of various algorithms were compared with those from other studies using a similar research approach, as presented in Table 1.
As shown in Table 1, the IPSO method demonstrates superior performance compared with other techniques by efficiently identifying optimal values that align with the defined objectives. This includes adjusting weights accordingly and improving voltage levels to satisfy the minimum criteria set in this study. As a result, the IPSO method was chosen to analyze the challenge in Case 3. The detailed results obtained using this method are presented in Table 2.
As presented in Table 2, the IPSO method confirms that the predefined objectives produce the most optimal results. In Case Study 2, we assigned random integer weights to each objective— w 1 = 33, w 2 = 32, and w 3 = 35. It can be explained that the highest weight, w 3 , corresponds to the component variable LVSI. Since an LVSI greater than 1 p.u. indicates a voltage failure in the power system, minimizing LVSI becomes the top priority. To enhance clarity, LVSI values were converted from p.u. to percentages (%). The next weight, w 1 , corresponds to the component variable power loss. Installation of the HES into the IEEE 15-bus test system reduced power losses during power transmission and, meanwhile, lowered fuel costs by decreasing upstream generation. Consequently, w 2 was the smallest weight. A side-by-side comparison of these outcomes is illustrated in Figure 6.
The BESS system parameters were optimally adjusted using the IPSO method within the MATLAB Simulink program version 2021b, utilizing the test model illustrated in Figure 7. Due to Case III, involving a dynamic test over a 5-s duration, it required the development of an IEEE 15-bus power distribution test system model in MATLAB Simulink for initial analysis. The optimization approach involved transmitting Δ f from the power system model to control blocks. The initial output values from these control blocks were then processed using the IPSO method to fine-tune the BESS parameters. These refined parameters replaced the previous ones, and the cycle was repeated throughout the 5-s simulation. The optimized results of the BESS parameter tuning using the IPSO method are summarized in Table 3.

7.3. Case III: Sudden Short Circuit of Transmission Line

Case III builds upon the result of Case II, which determined the optimal location, sizing, and PI parameter control of the BESS using the IPSO method. These results were further validated through HIL testing. The OP4512 RCP/HIL FPGA real-time simulator, an internationally recognized platform for virtual hardware testing, is connected to a computer and displayed on a monitor, as illustrated in Figure 7. In this scenario, a short circuit was introduced to the IEEE 15-bus power distribution test system model for 3 s, then cleared at 3.5 s. During the fault, the BESS PI controller—tuned with the optimal PI parameters—was required to inject energy into the IEEE 15-bus power distribution test system to support voltage stability. Additionally, both the HPP and PV systems were expected to supply maximum energy throughout the testing period.
This case study aims to validate the outcomes related to Objective 3, which focuses on minimizing LVSI and ensuring voltage stability during sudden disturbances. The findings demonstrate that location and sizing, combined with PI controller parameter optimization, effectively sustain voltage stability over time, as illustrated in Figure 8.
Figure 8 displays the VSI values of buses 13 and 14, for which the voltage was reduced to below 0.95 p.u. This demonstrates that the proposed method can help mitigate the impact of a short circuit occurring at the 3 s and clearing at the 3.5 s. However, since addressing short circuits is not within the scope of this research, our method only minimizes the resulting changes rather than resolving them completely. Another key factor is that the BESS control circuit is still a basic PI controller, leading to an unbalanced response and control. As shown in Figure 8, significant voltage oscillations occurred in buses 13 and 14. Overall, however, the proposed approach helps reduce the impact of a short circuit on the power system.

8. Discussion

This study centers on evaluating three objectives: minimizing power loss, minimizing fuel costs in the grid system, and minimizing LVSI to enhance voltage stability during both steady-state and transient conditions. The approach involves determining the optimal location and size of the HES, along with fine-tuning the PI controller to support voltage stability. Using the IPSO method, the analysis was divided into three cases to identify the best configuration based on these objectives. In Case I, the HES location, size, and PI controller parameters were assigned randomly. The results, illustrated in Figure 3, show that the HES tends to be located at the end of the feeder line. While the selected HES type can inject energy and improve the voltage to an acceptable level, the solution does not align with the defined objectives. As such, Case I is not considered effective for addressing the targeted goals.
Case II involves determining the optimal location and size of the HES, along with tuning the PI controller parameters using the IPSO method. This case is divided into two main steps: Step 1 focuses on identifying the most suitable location and size for the HES, while Step 2 involves refining the PI controller parameters. In Step 1, the IPSO method is applied to determine the optimal location and sizing of the HES components, which include PV, HP, and BESS units. The convergence results, shown in Figure 4, reveal 30 potential optimal solutions, with one point identified as the most effective. The best locations for the PV, HP, and BESS units are buses 8, 15, and 13, respectively, with sizes of 65 kW, 100 kW, and 50 kW, as illustrated in Figure 4. Optimizing the location and size of the HES significantly enhances voltage stability. Additionally, when compared with other algorithms, the IPSO method proves to be the most effective in achieving the study’s objectives. Therefore, it can be concluded that the IPSO-based optimization of HES location and size successfully meets the primary goals and improves voltage stability, as shown in Figure 6. In Step 2, the results from Step 1 were used to design a test model in MATLAB Simulink to refine the PI controller parameters further, as shown in Figure 7. The IPSO method is again used to optimize these parameters. Output signals from the PI controller are analyzed to determine suitable values, which then replace the initial settings, leading to more effective PI controller performance. The optimized results obtained in Case II serve as the foundation for further validation and testing in Case III.
Case III serves to validate the analysis results through real-time testing using the OP4512 RCP/HIL FPGA simulator, focusing on Objective 3: minimizing LVSI while maintaining voltage stability during sudden disturbances. In this scenario, a short circuit is introduced to the test model for 3 s and cleared at 3.5 s. During the fault, the BESS system is required to inject energy into the test model, while both the HPP and PV systems supply their maximum available energy. The results confirm that with the optimal location and sizing of the HES, combined with PI controller parameters, the system can effectively maintain voltage stability during transient faults, as demonstrated in Figure 8. This study thus proposes the design of multi-objective energy management for remote communities connected with an optimal HES using IPSO. The approach successfully achieves the defined objectives and enhances the stability of the power system.

9. Conclusions

This study presented a multi-objective energy management method for HES units in a power distribution system suitable for RACs. Testing all three cases to determine the most effective approach for achieving the defined objectives—minimizing power loss, minimizing fuel costs, and minimizing LVSI—Case I involved random location and sizing of the HES components along with arbitrary PI controller settings. At the same time, this setup provided a basic improvement in voltage stability. Specifically, the PV, hydro, and BESS units were randomly installed at locations 13, 12, and 5, with sizes of 90.86 kW, 62.41 kW, and 65 kW, respectively. It failed to meet the key objectives. As a result, it can be concluded that this approach is not suitable for addressing the specified goals. Case II of this study focuses on determining the optimal size and location of the HES, along with tuning the PI controller parameters using the IPSO method. This process is divided into two main steps. In Step 1, the IPSO algorithm is used to identify the most suitable locations and sizes of the HES components based on the defined objectives. The optimal locations for the PV, HP, and BESS units were found to be at buses 8, 15, and 13, respectively, with capacities of 65 kW, 100 kW, and 50 kW. This configuration reduced power loss in the grid to 43.873 kW and lowered fuel costs to 3825.7 USD/h. These outcomes align well with the specified objectives and demonstrate greater efficiency compared with other methods. To validate these results, Step 2 involved simulating the system in MATLAB Simulink using the result from Step 1. The IPSO method received the target signals to optimize the PI controller parameters within the designated time frame. The findings confirmed that the refined PI parameters effectively maintained voltage stability during transient events. The successful outcomes of Case II provide the foundation for further validation and real-time testing in Case III. Finally, Case III utilizes the results from Case II to evaluate voltage stability during a simulated short circuit using the HIL testing device—specifically, the op4512 rcp/hil fpga real-time simulator. When a short circuit occurs in the test model, the BESS system, guided by the optimized PI controller, injects energy into the model testing. At the same time, both the HPP and PV systems deliver their maximum power output to support system stability. The results demonstrate that the optimal location and sizing of the HES, along with the PI controller tuning achieved through the IPSO method, effectively maintain voltage stability during sudden short-circuit events. The findings from all three cases offer valuable insights for improving active distribution systems, providing a practical approach to mitigating the impact of unexpected faults. Additionally, these results serve as a reference for future enhancements of power systems tested through HIL equipment. Future research will explore innovative control strategies for distributed generation and RES to further advance and strengthen power system performance.

Author Contributions

Conceptualization, C.P.; methodology, C.P., S.D., S.R. and K.B.; software, C.P.; validation, S.R., H.O. and K.B.; formal analysis, K.B.; investigation, P.B. and K.B.; resources, C.P. and S.D.; data curation, S.R. and K.B.; writing—original draft preparation, H.O. and K.B.; writing—review and editing, P.B., A. and K.B.; visualization, C.P. and S.T; supervision, C.P. and S.D.; project administration, K.B. All authors have read and agreed to the published version of the manuscript.

Funding

High-performance post-doctoral and post-master level research personnel development project in leading-edge research in materials technology to drive the clean energy industry [Contract code: B13F680080] and the National Science, Research and Innovation Fund, Thailand Science Research and Innovation (TSRI), through Rajamangala University of Technology Thanyaburi (FRB68E0707) (Grant No.: FRB680045/0168).

Data Availability Statement

The author has implemented the work on the simulator. No data set is used for the same.

Conflicts of Interest

The authors declare no conflicts of interest.

Abbreviations

The following abbreviations are used in this manuscript.
BESSBattery energy storage system
BFSBackward–Forward sweep
DGDistributed generation
EMSEnergy management system
FPAFlower pollination algorithm
GAGenetic algorithm
HESsHybrid energy systems
HILHardware-in-the-loop
HPPHydropower plant
IHAThe indicators of hydrological alteration algorithm
IPSOImproved particle swarm optimization
LCCLife cycle cost
LVSILine voltage stability index
LLPLoss of load probability
MOGAMulti-objective genetic algorithm
PSOParticle swarm optimization
PVPhotovoltaic
RACsRemote area communities
RESRenewable energy sources
TSMTotal Suspended Matter Algorithm
VSIVoltage stability index
a i , b i , c i The grid constraints
a i j , b i j The constants associated with each node
C t The energy stored in the BESS
C f The total fuel cost of the grid system
g The gravitational
g ¯ The equality
g b e s t The global best position
h Constraints of all objective functions
H The hydraulic head
i th The set of nodes
I ¯ b r l Current flowing
j Q i Reactive power load
K I Controller of integral control
K P Controller of proportional control
l Length of transmission line
M The set of connected nodes
N G The number of points connected to the grid system
N l i n e The number of transmission lines
P B E S S t The BESS power output
p b e s t The personal best position
P D R 0 The total active power demand in first-time analysis
P D R The total active power demand in the grid system
P G i The power generated by the grid system
P H E S The active power of the hybrid energy system
P H P P Power output
p i The position of the particle
P i , P j Active power load at nodes i and j
P l o s s Active power loss
P r The active power generation at the receiving node
P R , P V PV panels rated power
Q Water flow rate
Q i , Q j Reactive power at nodes i and j
R The resistance of the transmission lines
R r e f Referent radiation intensity
R s u n Radiation intensity
S O C State of charging
t t h Time interval
T P V Temperature of PV panels
T r e f The reference test temperature for PV panels
V i ( k 1 ) Complex bus voltage in round
V s The voltage at the sending node
w 1 , w 2 , w 3 The weights for the analysis function
x 1 , x 2 , x 3 , x 4 Parameter of proportional control
y 1 , y 2 , y 3 , y 4 Parameter of integral control
ε The acceptable
η The plant efficiency
η c h g The charging efficiency of the BESS
η d i s The discharge efficiency of the BESS
Δ f Frequency deviations
Δ T The duration of each time interval
θ The line impedance angle
δ The different voltage phase angles between the start and end node
α The compression–expansion coefficient
β The acceleration coefficient

References

  1. Smaoui, M.; Rekik, M.; Krichen, L. Optimal design of an off-grid electrical system in remote areas with different renewable energy scenarios. Energy 2025, 318, 134821. [Google Scholar] [CrossRef]
  2. Irshad, A.S.; Samadi, W.K.; Fazli, A.M.; Noori, A.G.; Amin, A.S.; Zakir, M.N.; Bakhtyal, I.A.; Karimi, B.A.; Ludin, G.A.; Senjyu, T. Resilience and reliable integration of PV-wind and hydropower based 100% hybrid renewable energy system without any energy storage system for inaccessible area electrification. Energy 2023, 282, 128823. [Google Scholar] [CrossRef]
  3. Ahmed, E.E.; Demirci, A. Multi-stage and multi-objective optimization for optimal sizing of stand-alone photovoltaic water pumping systems. Energy 2022, 252, 124048. [Google Scholar] [CrossRef]
  4. Prabpal, P.; Kongjeen, Y.; Bhumkittipich, K. Optimal Battery Energy Storage System Based on VAR Control Strategies Using Particle Swarm Optimization for Power Distribution System. Symmetry 2021, 13, 1692. [Google Scholar] [CrossRef]
  5. Ganesan, S.; Subramaniam, U.; Ghodke, A.A.; Elavarasan, R.M.; Raju, K.; Bhaskar, M.S. Investigation on Sizing of Voltage Source for a Battery Energy Storage System in Microgrid with Renewable Energy Sources. IEEE Access 2020, 8, 188861–188874. [Google Scholar] [CrossRef]
  6. Chegari, B.; Tabaa, M.; Simeu, E.; El Ganaoui, M. Optimal Energy Management of a Hybrid System Composed of PV, Wind Turbine, Pumped Hydropower Storage, and Battery Storage to Achieve a Complete Energy Self-Sufficiency in Residential Buildings. IEEE Access 2024, 12, 126624–126639. [Google Scholar] [CrossRef]
  7. Jeong, J.; Kim, S.W.; Kim, H. Deep Reinforcement Learning Based Real-Time Renewable Energy Bidding with Battery Control. IEEE Trans. Energy Mark. Policy Regul. 2023, 1, 85–96. [Google Scholar] [CrossRef]
  8. Liu, K.; Cai, Y.; Sun, W.; Feng, Q.; Wang, G.; Yang, W. Optimal configuration of a stand-alone PV/diesel/battery hybrid energy system based on modified PSO for a translational sprinkler irrigation machine applied in remote and water-scarce areas. Energy 2025, 320, 135113. [Google Scholar] [CrossRef]
  9. Mitrofanov, S.V.; Zubova, N.V.; Zhilnikova, M.M.; Anosova, E.I. Mode Optimization of a Hybrid Power Supply System Based on Criterion of Minimizing Fuel Consumption in a Diesel Power Plant. In Proceedings of the 2023 IEEE XVI International Scientific and Technical Conference Actual Problems of Electronic Instrument Engineering (APEIE), Novosibirsk, Russian, 10–12 November 2023; pp. 480–485. [Google Scholar] [CrossRef]
  10. Zhang, L.; Zhang, T.; Zhang, K.; Hu, W. Research on Optimal Allocation Strategy of Hybrid Energy Storage for Wind-Photovoltaic Hybrid Generation System. In Proceedings of the 2023 8th International Conference on Power and Renewable Energy (ICPRE), Shanghai, China, 22–25 September 2023; pp. 1321–1326. [Google Scholar] [CrossRef]
  11. Zhao, J.; Liang, Y.; Fan, D.; Ren, H.; Zhu, L.; Zhang, X. Capacity Optimization of lithium Battery-Flywheel Hybrid Energy Storage System. In Proceedings of the 2023 3rd International Conference on Energy Engineering and Power Systems (EEPS), Dali, China, 28–30 July 2023; pp. 186–189. [Google Scholar] [CrossRef]
  12. Hosseini, E.; Horrillo-Quintero, P.; Carrasco-Gonzalez, D.; García-Triviño, P.; Sarrias-Mena, R.; García-Vázquez, C.A.; Fernández-Ramírez, L.M. Optimal energy management system for grid-connected hybrid power plant and battery integrated into multilevel configuration. Energy 2024, 294, 130765. [Google Scholar] [CrossRef]
  13. Li, S.; Qin, W.; Zhu, Z.; Lu, R.; Zhang, Y.; Li, X. Transient Stability Assessment of Power Systems Containing Wind Power Based on Hybrid Simulation and Deep Learning. In Proceedings of the 2023 International Conference on Power System Technology (PowerCon), Jinan, China, 21–22 September 2023; pp. 1–5. [Google Scholar] [CrossRef]
  14. Du, C.; Guo, W.; Guo, S.; Cai, W.; Shi, Q. Transient Current Optimal Control of the Hybrid Three Level Dual Active Bridge Converters Based on Triple-Phase-Shifting Control. In Proceedings of the 2021 IEEE 12th International Symposium on Power Electronics for Distributed Generation Systems (PEDG), Chicago, IL, USA, 28 June–1 July 2021; pp. 1–8. [Google Scholar] [CrossRef]
  15. Li, Y.; Ding, Q.; Li, S.; Valtchev, S. Optimal controller design for non-affine nonlinear power systems with static var compensators for hybrid UAVs. Tsinghua Sci. Technol. 2022, 27, 196–206. [Google Scholar] [CrossRef]
  16. Saleh, A.; Magdy, G.; Ali, A.M. Multi-Trial Vector-Based Sine Cosine Algorithm-Based Optimal Frequency Control of Interconnected Hybrid Power Systems Including Renewables. In Proceedings of the 2024 25th International Middle East Power System Conference (MEPCON), Cairo, Egypt, 17–19 December 2024; pp. 1–6. [Google Scholar] [CrossRef]
  17. Koley, I.; Sarkar, B.; Datta, A.; Panda, G.K. Load Frequency Control of a Wind Energy Integrated Multiarea Power System With CSA Tuned PIDD Controller. In Proceedings of the 2020 IEEE First International Conference on Smart Technologies for Power, Energy and Control (STPEC), Nagpur, India, 25–26 September 2020; pp. 1–6. [Google Scholar] [CrossRef]
  18. Peng, J.; Fan, B.; Liu, W. Voltage-Based Distributed Optimal Control for Generation Cost Minimization and Bounded Bus Voltage Regulation in DC Microgrids. IEEE Trans. Smart Grid 2021, 12, 106–116. [Google Scholar] [CrossRef]
  19. Pengtem, C.; Janjamraj, N.; Romphochai, S.; Ngaemngam, S.; Bhumkittipich, K. Multi-Objective Hybrid LF-GWO based Optimal Location and Sizing of Multiple PV-DSG Units for Voltage Profile Improvement. In Proceedings of the 2024 International Conference on Power, Energy and Innovations (ICPEI), Nakhon Ratchasima, Thailand, 16–18 October 2024; pp. 1–6. [Google Scholar]
  20. Mthethwa, F.; Gomes, C.; Dorrell, D. Development of Optimal Algorithm to Interconnect Multiple Microgrids in an Agricultural-based Remote Community. In Proceedings of the 2021 IEEE AFRICAN, Arusha, Tanzania, 13–15 September 2021; pp. 1–6. [Google Scholar] [CrossRef]
  21. Saw, B.K.; Bohre, A.K. Multi DG Planning with Impact of Mixed-Load Models using Intelligent Methodologies: BF-PSO, PSO and GA. In Proceedings of the 2023 IEEE 3rd International Conference on Smart Technologies for Power, Energy and Control (STPEC), Bhubaneswar, India, 10–13 December 2023; pp. 1–5. [Google Scholar] [CrossRef]
  22. Pan, S.; Maleki, S.; Lakshminarayana, S.; Konstantinou, C. Optimal Placement and Power Supply of Distributed Generation to Minimize Power Losses. In Proceedings of the 2023 IEEE International Conference on Communications, Control, and Computing Technologies for Smart Grids (SmartGridComm), Glasgow, UK, 31 October–3 November 2023; pp. 1–6. [Google Scholar] [CrossRef]
  23. Kusuma, V.A.; Wibowo, R.S.; Putra, D.F.U. Optimizing Distributed Generator Placement in Distribution Networks Using Flower Pollination Algorithm with Self-Healing Integration. In Proceedings of the 2025 International Conference on Advancement in Data Science, E-learning and Information System (ICADEIS), Bandung, Indonesia, 3–4 February 2025; pp. 1–6. [Google Scholar] [CrossRef]
  24. Li, L.; Xu, S. Optimal Day-ahead Scheduling of Microgrid Participating in Energy and Spinning Reserve Markets. In Proceedings of the 2020 5th Asia Conference on Power and Electrical Engineering (ACPEE), Chengdu, China, 4–7 June 2020; pp. 1049–1055. [Google Scholar] [CrossRef]
  25. Xu, Z.; Zhu, Y.; Dong, R.; Wang, J.; Zhang, X.; Qin, W. Optimal Scheduling Strategy of Microgrid Participating in Upper Power Grid Based on Flexibility of Distributed Power. In Proceedings of the 2020 IEEE Sustainable Power and Energy Conference (iSPEC), Chengdu, China, 23–25 November 2020; pp. 2256–2261. [Google Scholar] [CrossRef]
  26. Chen, Z.; Zuo, X.; Hou, B.; Guo, Y.; Tian, N. Privacy-Preserving Optimal Schedule for Microgrid Cluster Based on Information Masking Method. In Proceedings of the 2023 IEEE Power & Energy Society General Meeting (PESGM), Orlando, FL, USA, 16–20 July 2023; pp. 1–5. [Google Scholar] [CrossRef]
  27. Hussien, A.M.; Hasanien, H.M.; Qais, M.H.; Alghuwainem, S. Hybrid Transient Search Algorithm With Levy Flight for Optimal PI Controllers of Islanded Microgrids. IEEE Access 2024, 12, 15075–15092. [Google Scholar] [CrossRef]
  28. Tu, Z.; Fan, B.; Khazaei, J.; Zhang, W.; Liu, W. Optimal Reset-Control-Based Load Frequency Regulation in Isolated Microgrids. IEEE Trans. Sustain. Energy 2022, 13, 2239–2249. [Google Scholar] [CrossRef]
  29. Khezri, R.; Mahmoudi, A.; Haque, M.H. A Comparative Study of Optimal Battery Storage and Fuel Cell for a Clean Power System in Remote Area. In Proceedings of the 2020 IEEE International Conference on Power Electronics, Drives and Energy Systems (PEDES), Jaipur, India, 16–19 December 2020; pp. 1–5. [Google Scholar] [CrossRef]
  30. Nugraha, S.D.; Ashari, M.; Riawan, D.C. Multi-Objective Approach for Optimal Sizing and Placement of EVCS in Distribution Networks With Distributed Rooftop PV in Metropolitan City. IEEE Access 2025, 13, 40883–40898. [Google Scholar] [CrossRef]
  31. Amraj, N.J.; Boonrach, N.; Bhumkittipich, K. Optimal Allocation and Sizing of Photovoltaic-Battery Energy Storage Systems in Distribution Network for Power Loss Minimization. In Proceedings of the 2021 International Conference on Power, Energy and Innovations (ICPEI), Nakhon Ratchasima, Thailand, 20–21 October 2021; pp. 33–36. [Google Scholar] [CrossRef]
  32. Manmai, S.; Romphochai, S.; Janjamraj, N.; Ngaemngam, S.; Bhumkittipich, K. Load Frequency Control of Large-Scale PV-BESS Generation Installation using Power System Stabilizer. In Proceedings of the 2021 24th International Conference on Electrical Machines and Systems (ICEMS), Gyeongju, Republic of Korea, 31 October–3 November 2021; pp. 2378–2381. [Google Scholar] [CrossRef]
  33. Alberizzi, J.C.; Estevez, M.A.P.; Renzi, M.; Jin, L.; Rossi, M.; Alberizzi, A. Optimal Management of a Hydro—Wind Energy System with Hydrogen Storage. In Proceedings of the 2023 12th International Conference on Power Science and Engineering (ICPSE), Eskisehir, Turkiye, 22–24 September 2023; pp. 46–50. [Google Scholar] [CrossRef]
  34. Deeum, S.; Charoenchan, T.; Janjamraj, N.; Romphochai, S.; Baum, S.; Ohgaki, H.; Mithulananthan, N.; Bhumkittipich, K. Optimal Placement of Electric Vehicle Charging Stations in an Active Distribution Grid with Photovoltaic and Battery Energy Storage System Integration. Energies 2023, 16, 7628. [Google Scholar] [CrossRef]
  35. Khan, R.A.; Yang, S.; Fahad, S.; Khan, S.U.; Kalimullah. A Modified Particle Swarm Optimization With a Smart Particle for Inverse Problems in Electromagnetic Devices. IEEE Access 2021, 9, 99932–99943. [Google Scholar] [CrossRef]
  36. Bin, W. A Novel Supply Chain Multi-level Inventory Model based on Improved PSO Algorithm. In Proceedings of the 2023 8th International Conference on Communication and Electronics Systems (ICCES), Coimbatore, India, 1–3 June 2023; pp. 1733–1737. [Google Scholar] [CrossRef]
  37. Abdelaziz, A.Y. Optimal sizing and locations of capacitors in radial distribution systems via flower pollination optimizationalgorithm and power loss index. Eng. Sci. Technol. Int. J. 2016, 19, 610–618. [Google Scholar]
  38. Tamilselvan, V. Optimal capacitor placement in radial distribution systems using flower pollination algorithm. Alex. Eng. J. 2018, 57, 2775–2786. [Google Scholar] [CrossRef]
  39. Ali, E.S. Improved harmony algorithm and power loss index for optimal locations and sizing of capacitors in radial distributionsystems. Int. J. Electr. Power Energy Syst. 2016, 80, 252–263. [Google Scholar] [CrossRef]
  40. Pengtem, C.; Taksana, R.; Bhumkittipich, K.; Ohgaki, H.; Romphochai, S. Optimizing V2G Charging Station Design for Improved Power Quality and Stability in Active Distribution Network. In Proceedings of the 16th Eco-Energy and Materials Science and Engineering Symposium (EMSES 2025), Kyoto, Japan, 8–10 January 2025. [Google Scholar]
  41. Pengtem, C.; Boonjiam, A.; Taksana, R.; Bhumkittpich, P.; Ohgaki, H.; Romphochai, S.; Bhumkittipich, K. Multi-Objective Energy Management in Hybrid PV-Hydro Power-BESS Integrated Remote Area Community Using Particle Swam Optimization Technique. In Proceedings of the 16th Eco-Energy and Materials Science and Engineering Symposium (EMSES 2025), Kyoto, Japan, 8–10 January 2025. [Google Scholar]
Figure 1. Single-line diagram of IEEE 15-bus power distribution test system.
Figure 1. Single-line diagram of IEEE 15-bus power distribution test system.
Energies 18 02250 g001
Figure 2. Comparison between the traditional PSO and the improved PSO Algorithm.
Figure 2. Comparison between the traditional PSO and the improved PSO Algorithm.
Energies 18 02250 g002
Figure 3. Location and voltage levels in Case I (random installation).
Figure 3. Location and voltage levels in Case I (random installation).
Energies 18 02250 g003
Figure 4. Voltage level in Case II after determination of optimal location and size.
Figure 4. Voltage level in Case II after determination of optimal location and size.
Energies 18 02250 g004
Figure 5. Location and voltage level of Case II after optimal location and sizing.
Figure 5. Location and voltage level of Case II after optimal location and sizing.
Energies 18 02250 g005
Figure 6. Comparison results in the base case, Case I, and Case II.
Figure 6. Comparison results in the base case, Case I, and Case II.
Energies 18 02250 g006
Figure 7. The IEEE 15-bus system model and PI controller of the BESS.
Figure 7. The IEEE 15-bus system model and PI controller of the BESS.
Energies 18 02250 g007
Figure 8. Voltage stability in Case III.
Figure 8. Voltage stability in Case III.
Energies 18 02250 g008
Table 1. Comparison of results for the IEEE 15-bus power distribution test system (Case II).
Table 1. Comparison of results for the IEEE 15-bus power distribution test system (Case II).
UnitBase CaseFPA [37]TSM [38]IHA [39]GA [40]PSO [41]IPSO
No. of HES-333333
Sum of size (kW)-10001300950341.5218.27215
P l o s s (kW)53.67930.711232.426231.125551.82744.23743.873
C f (USD/h)38735510587351793865.103832.103825.7
Minimum Bus Voltage (p.u.)0.94450.96760.96950.96580.95420.95480.9525
Table 2. Comparison between Case I and Case II using IPSO.
Table 2. Comparison between Case I and Case II using IPSO.
UnitBase CaseCase ICase II
PVHPBESSPVHPPBESS
Location-1351281513
Size (kW)-6590.8662.416510050
P l o s s (kW)53.67944.23743.873
C f (USD/h)38733832.13825.7
max LVSI (%)<10065.01238.89
Table 3. Comparison of results between traditional parameters and optimal parameters.
Table 3. Comparison of results between traditional parameters and optimal parameters.
Case K P K I
x 1 x 2 x 3 x 4 y 1 y 2 y 3 y 4
Base Case25010,000100500025010,0001005000
Case I
Case II680643617601417214675346
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Pengtem, C.; Deeum, S.; Amirullah; Ohgaki, H.; Romphochai, S.; Bhumkittipich, P.; Bhumkittipich, K. Design of Multi-Objective Energy Management for Remote Communities Connected with an Optimal Hybrid Integrated Photovoltaic–Hydropower–Battery Energy Storage System (PV-HP-BESS) Using Improved Particle Swarm Optimization. Energies 2025, 18, 2250. https://doi.org/10.3390/en18092250

AMA Style

Pengtem C, Deeum S, Amirullah, Ohgaki H, Romphochai S, Bhumkittipich P, Bhumkittipich K. Design of Multi-Objective Energy Management for Remote Communities Connected with an Optimal Hybrid Integrated Photovoltaic–Hydropower–Battery Energy Storage System (PV-HP-BESS) Using Improved Particle Swarm Optimization. Energies. 2025; 18(9):2250. https://doi.org/10.3390/en18092250

Chicago/Turabian Style

Pengtem, Chaimongkol, Saksit Deeum, Amirullah, Hideaki Ohgaki, Sillawat Romphochai, Pimnapat Bhumkittipich, and Krischonme Bhumkittipich. 2025. "Design of Multi-Objective Energy Management for Remote Communities Connected with an Optimal Hybrid Integrated Photovoltaic–Hydropower–Battery Energy Storage System (PV-HP-BESS) Using Improved Particle Swarm Optimization" Energies 18, no. 9: 2250. https://doi.org/10.3390/en18092250

APA Style

Pengtem, C., Deeum, S., Amirullah, Ohgaki, H., Romphochai, S., Bhumkittipich, P., & Bhumkittipich, K. (2025). Design of Multi-Objective Energy Management for Remote Communities Connected with an Optimal Hybrid Integrated Photovoltaic–Hydropower–Battery Energy Storage System (PV-HP-BESS) Using Improved Particle Swarm Optimization. Energies, 18(9), 2250. https://doi.org/10.3390/en18092250

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop