Next Article in Journal
Sliding Mode Observer-Based Phase-Locking Strategy for Current Source Inverter in Weak Grids
Previous Article in Journal
An Integrated Frequency Regulation Method Based on System Frequency Security Posture
Previous Article in Special Issue
Impact of Multiple Grid-Connected Solar PV Inverters on Harmonics in the High-Frequency Range
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Real-Time Power Regulation of Flexible User-Side Resources in Distribution Networks via Dual Ascent Method

1
College of Electrical Engineering, Zhejiang University, Hangzhou 310027, China
2
College of Science and Engineering, James Cook University, Townsville 4811, Australia
3
Sungrow Australia Group Pty. Ltd., Sydney 2060, Australia
4
China Energy Economic and Technological Research Institute Co., Ltd., Beijing 102299, China
5
State Grid Corporation of China, Beijing 100031, China
6
State Grid Energy Research Institute of China, Beijing 102209, China
*
Authors to whom correspondence should be addressed.
Energies 2024, 17(19), 4890; https://doi.org/10.3390/en17194890
Submission received: 29 March 2024 / Revised: 5 August 2024 / Accepted: 26 September 2024 / Published: 29 September 2024

Abstract

:
Flexible user-side resources are of great potential in providing power regulation so as to effectively address the challenges of reverse power flow and overvoltage issues in distribution networks characterized by high photovoltaic (PV) penetration. However, existing distributed algorithms typically implement control signals after the convergence of the algorithms, making it difficult to track frequent and rapid fluctuations in PV power outputs in real time. Given this background, an online-distributed control algorithm for the real-time power regulation of flexible user-side resources is proposed in this paper. The objective of the established control model is to minimize network losses by dynamically adjusting active power outputs of flexible user-side resources and reactive power outputs of PV inverters while respecting branch power flow and voltage magnitude constraints. Furthermore, by deconstructing the centralized problem into a primal–dual one, a distributed control strategy based on the dual ascent method is implemented. With the proposed method, agents can achieve global optimality by exchanging limited information with their neighbors. The simulation results verify the good balance between economic efficiency and voltage control performance of the proposed method.

1. Introduction

The deployment of renewable energy resources (RESs) has gained significant attention in recent years due to their potential in mitigating climate change. However, the increasing penetration of RESs poses substantial challenges to the secure and economic operation of the power grid [1,2,3]. For distributed photovoltaic (PV) systems connected to the power grid, if excessive PV power cannot be consumed locally, it will flow back into the grid, resulting in issues such as reverse power flow and overvoltage violations [4]. To address these problems, flexible user-side resources (FURs) have emerged as a promising solution. FURs refer to electricity-consuming devices (e.g., energy storage systems, electric vehicles, and adjustable loads) that can rapidly adjust their power demands in response to control signals from the grid operator or changes in system status. By actively participating in grid operations, FURs can provide system flexibility and support the large-scale integration of RESs.
Many efforts have been made in describing the regulation of FURs. Some early proposed methods are based on traditional deterministic models with minimum capacity constraints to enable scheduling results that cope with uncertainties within a certain cost [5]. In [6], a multi-timescale model for FURs in the day-ahead dispatch is proposed, achieving optimized configuration with intervals of 10, 15, and 30 min. Both [5] and [6] are based on deterministic models, which impose high requirements on the precise assessment of flexibility demands. To deal with the inevitable uncertainties, [7] demonstrates the superiority of the stochastic optimization model over the deterministic unit commitment model considering FUR provisions. The stochastic optimization method transforms a stochastic optimization problem into an optimization scheduling problem under multiple probabilistic scenarios by constructing a chance-constrained model of system-related uncertain variables and limiting the probability of these chance constraints [8,9]. Unlike the stochastic optimization method, robust optimization does not rely on the precise probability distribution of system-uncertain variables. Instead, it uses uncertainty set parameters based on statistical intervals to solve for the economic dispatch due to its ability to provide an acceptable performance for all implementations of uncertain inputs [10,11]. In [12], a flexible regulation cost is introduced into the model to balance the robustness and economic efficiency of the robust optimization results. Furthermore, methods based on new theories such as reinforcement learning have been applied to handle the optimization problems of FURs. The authors of [13] explore and utilize the uncertainty and fluctuation patterns of wind power, PV power, and multi-energy loads through deep reinforcement learning methods to achieve system optimization scheduling and decision-making under complex scenarios. Other control strategies for microgrids, energy storage systems, and electric vehicles can be found in [14,15,16], respectively. Additionally, the demand response of integrated FURs has been comprehensively considered in [17,18,19] for the coordination of integrated energy systems.
Although considerable progress has been made in the modeling of FURs, most coordination strategies are based on centralized solutions to the optimal power flow problem. A second-order cone programming (SOCP) approach is employed in [20,21] to optimize the active and reactive power output of FURs in distribution networks. These centralized methods require the control center to collect operational parameters of all distributed RESs in real time, which is challenging and infringes on user privacy, especially in complex distribution networks [22]. Distributed coordination architectures have attracted significant attention as they enable regional grids to achieve high autonomy in addressing local contingencies through interactions between neighbors [23]. Due to its excellent convergence performance, the alternating direction method of multipliers (ADMM) technique is applied in [24,25] to obtain global solutions through local optimization updates. However, conventional distributed algorithms require multiple iterations before applying the final converged solution to local controllers. By the time convergence is achieved, the control objectives may have significantly deviated from the initial states due to the fast fluctuations in PV power outputs in real time. Consequently, the response speed of local controllers cannot keep up with the rapid changes in system status, hindering the online application of the program.
In this paper, we propose a distributed control strategy based on the dual ascent method to optimize distribution network operations involving FURs. By decoupling the centralized optimization operation model of the distribution network, our approach aims to maintain voltage within acceptable ranges while minimizing the total operating cost, including network losses and the regulation cost of flexible resources. As illustrated in Figure 1, unlike traditional distributed algorithms that require complete convergence before applying the results, the proposed method is proven to have asymptotic convergence and can update and output control commands at each iteration. This facilitates a prompt and effective response to variations in PV power output.

2. Centralized Model of Power Regulation

In the centralized approach, the power system operator collects electrical parameters from all buses and assigns control commands to individual agents based on optimization results, as shown in Figure 2. Given the typical goal of optimizing power flow subject to operational constraints, the formulation of the dispatch scheme, incorporating PV systems and FURs, is summarized as follows.

2.1. Objective Function of Distribution Networks

The objective function for the entire system is to minimize the overall cost, which includes the network losses P L o s s and the compensation cost P C o s t associated with the regulation of FURs, namely
min P L o s s + P C o s t

2.1.1. Network Losses

The network losses P L o s s are determined by
P L o s s = i j L P i j 2 + Q i j 2 V i 2 r i j i j L P i j 2 + Q i j 2 V 0 2 r i j
where L represents the set of lines; r i j is the resistance of line i j ; P i j and Q i j denote the active and reactive power flow on line i j and are dependent variables influenced by the optimized decision variables; and V i and V 0 represent the voltage magnitudes at bus i and the substation bus, respectively. Given that the voltage drop along the distribution network is not significant, we make a reasonable assumption that V i V 0 1 for ease of calculation.

2.1.2. Compensation Cost

The compensation cost P C o s t is evaluated by a convex quadratic function [26] and can be expressed as
P C o s t = f P F R = N · P F R T R P F R
where P F R represents the output of FURs; and R is a positive definite matrix, and its properties will be discussed in more detail in Section 2.3. Clearly, f P F R exhibits strict monotonicity, which is consistent with the trend of the compensation cost. N denotes a correlation coefficient, where a larger value of N means a higher compensation cost and leads to reduced power support of FURs, and vice versa.

2.2. Operational Constraints of Distribution Networks

The goal of distribution networks is to optimize energy efficiency and reduce network losses by adjusting the dispatch scheme for distributed energy resources and flexible loads. To achieve these objectives, it is essential to consider operational constraints, including power flow constraints, inverter control constraints, voltage violation constraints, and power regulation constraints.

2.2.1. Power Flow Constraints

Due to the non-convexity of the branch flow model, the linearized DistFlow [27] approximation will be employed to simplify the problem. By neglecting the higher-order terms, we obtain the following equations.
A T P = P I
A T Q = Q I
M 0 + A V = M r P + M x Q
P I = P P V P F R P F L
Q I = Q P V Q F L
where P , Q , and V are matrices corresponding to P i j , Q i j , and V i , respectively; P I and Q I represent the injected active and reactive power, respectively; M r and M x are diagonal matrices with their diagonal entries corresponding to the resistance r i j and the reactance x i j of line i j ; P P V and Q P V denote the active and reactive power for the PV system; and P F L and Q F L represent the load demands. The constant matrices M 0 and A together form the adjacency matrix A 0 , where M 0 constitutes the first column of A 0 . Specifically, A 0 is expressed as A 0 = M 0   A . The adjacency matrix A 0 is mathematically defined as
A 0 i j = 1 1 0 if   line   i   departs   from   bus   j , if   line   i   enters   into   bus   j , otherwise .
where A 0 i j denotes the element in the i -th row and j -th column of matrix A 0 . It is noteworthy that A is a square matrix with full rank and, therefore, it is invertible [28].

2.2.2. Inverter Control Constraints

To facilitate the power flow in the distribution network, the IEEE 1547 standard [29] allows small-scale distributed PV inverters to engage in power flow optimization by adjusting their reactive power output.
Q _ P V Q P V Q ¯ P V
where Q _ P V and Q ¯ P V represent the lower and upper reactive power limits of the inverters.

2.2.3. Voltage Violation Constraints

To ensure proper operation, it is imperative to maintain bus voltage magnitudes within the acceptable ranges as
V _ V V ¯
where V _ and V ¯ denote the lower and upper voltage limits.

2.2.4. Power Regulation Constraints

In order to accommodate as much PV power as possible, FURs dynamically update their power output to mitigate voltage violations, responding to rapid fluctuations in PV power. These FURs typically include contracted and price-responsive resources. The modeling of different types of FURs will be addressed in future work. For the present analysis, our focus is on examining the impact of power regulation associated with FURs. Therefore, we have
P _ F R P F R P ¯ F R
P _ P P ¯
where P _ F R and P ¯ F R are the lower and upper limits of FURs’ output, and P _ and P ¯ represent the lower and upper transmission power limits. To prevent excessive PV power injection into the upstream grid and to manage the significant burden caused by evening peak load demand, power system operators periodically adjust the power regulation constraints on the grid interconnection lines based on upstream grid load levels. This proactive measure ensures efficient and balanced power distribution. Therefore, in addition to the thermal limit, the P _ and P ¯ connected to the substation bus also represent the exchanged power limit on the grid interconnection, which will be set by the power system operator.

2.3. The Compact Form of Centralized Optimization Model

Substituting (4) and (5) into (6), the bus voltage is given by
V = R P I + X Q I A 1 M 0
where R A 1 M r A T and X A 1 M x A T . Equation (14) builds a linear relationship between bus voltage magnitudes and nodal power injections. Since it has been proven in [30] that R and X are positive definite, the network losses in (2) can be further represented in matrix form as
P L o s s = i j L P i j r i j 2 + Q i j r i j 2 = M r 1 / 2 P 2 2 + M r 1 / 2 Q 2 2 = P I T R P I + Q I T R Q I
Substituting (7) and (8) into (15), the compact form of centralized optimization mode is finally obtained as follows.
min P P V P F R P F L T R P P V P F R P F L + Q P V Q F L T R Q P V Q F L + N · P F R T R P F R s . t . V = R P P V P F R P F L + X Q P V Q F L A 1 M 0 C o n s t r a i n t s 10 ( 13 )
It is worth noting that the decision variables in optimization (16) are the active power output P F R of FURs and the reactive power output Q P V of PV inverters.

3. Distributed Model of Power Regulation

In this section, a distributed architecture is applied to the distribution network with the dual ascent method. As shown in Figure 3, instead of collecting the operational state of the entire network, distributed algorithms can achieve global optimality through interactions between neighbors, thereby preserving user privacy. Additionally, the proposed method in this paper has a desirable property that facilitates the involvement of FURs in real-time power regulation. Traditional distributed algorithms always require convergence before applying the optimized results to actual outputs and reading new inputs to enter a new iteration cycle. However, the proposed dual ascent method has been proven to converge asymptotically to the optimal value, which means that each iteration result is better than the previous ones (refer to [26] for detailed proofs). As a result, the output from each iteration step can be applied even before the algorithm converges, enabling the controller to update the signal in real time. This leads to better tracking and response performance when applied to power regulation.

3.1. Dual Ascent Method

The dual ascent method solves the optimization problem by iteratively updating the primal and dual variables, alternately using the gradients. The typical iterative form of the dual ascent method is given as
x k = argmin x L x , y k
y k + 1 = y k + ρ k G y k Y
where x and y represent the primal and dual variables, respectively; ρ k denotes the step size in step k ; L x , y k is the Lagrangian function; and G y k is the gradient of the dual function G y . Since Y represents the feasible set of y , then · Y denotes the mapping projected onto set Y .

3.2. Update Rules for Dual Ascent Method

In this section, the update rules of the primal and dual variables are first presented. Subsequently, for better comprehension, the specific implementation steps of the proposed method are provided.

3.2.1. Update Rules for Primal Variables

Considering that the decision variables in optimization model (16) are P F R and Q P V , the Lagrangian function L can be reformulated by halving the objective function value and eliminating the constant terms as
L = N + 1 2 P F R T R P F R P P V P F L T R P F R + 1 2 Q P V T R Q P V Q F L T R Q P V + ω _ 1 T Q _   P V Q P V + ω ¯ 1 T Q P V Q ¯ P V + ω _ 2 T V _ + R P F R X Q P V V D E 1 + ω ¯ 2 T V ¯ R P F R + X Q P V + V D E 1 + ω _ 3 T P _ F R P F R + ω ¯ 3 T P F R P ¯ F R + ω _ 4 T P _ + A T P F R V D E 2 + ω ¯ 4 T P ¯ A T P F R + V D E 2
where V D E 1 : = R P P V P F L X Q F L + A 1 M 0 and V D E 2 : = A T P P V P F L ; ω _ 1 , ω ¯ 1 , ω _ 2 , ω ¯ 2 , ω _ 3 , ω ¯ 3 , ω _ 4 , ω ¯ 4 are dual variables or Lagrange multipliers corresponding to (10)–(13), respectively. Obviously, R and X are symmetric matrices, i.e., R T = R and X T = X . Therefore, according to the derivation of the Lagrange function (19), the update rules for primal variables P F R and Q P V in k -th step are achieved as
P F R k = P P V P F L + ω ¯ 2 k ω _ 2 k + R 1 ω _ 3 k ω ¯ 3 k + A T M r 1 ω ¯ 4 k ω _ 4 k N + 1
Q P V k = Q F L + R 1 ω _ 1 k ω ¯ 1 k + R 1 X ω _ 2 k ω ¯ 2 k

3.2.2. Update Rules for Dual Variables

The dual ascent method optimizes the dual variables by utilizing gradient ascent during each iteration. The update rules for dual variables ω _ 1 , ω ¯ 1 , ω _ 2 , ω ¯ 2 , ω _ 3 , ω ¯ 3 , ω _ 4 , and ω ¯ 4 in the k -th step are obtained as
ω _ 1 k + 1 = ω _ 1 k + ρ _ 1 k Q _ P V Q P V k +
ω ¯ 1 k + 1 = ω ¯ 1 k + ρ ¯ 1 k Q P V k Q ¯ P V +
ω _ 2 k + 1 = ω _ 2 k + ρ _ 2 k V _ V k +
ω ¯ 2 k + 1 = ω ¯ 2 k + ρ ¯ 2 k V k V ¯ +
ω _ 3 k + 1 = ω _ 3 k + ρ _ 3 k P _ F R P F R k +
ω ¯ 3 k + 1 = ω ¯ 3 k + ρ ¯ 3 k P F R k P ¯ F R +
ω _ 4 k + 1 = ω _ 4 k + ρ _ 4 k P _ P k +
ω ¯ 4 k + 1 = ω ¯ 4 k + ρ ¯ 4 k P k P ¯ +

3.2.3. Implementation of Update Rules

The proposed method only requires us to receive dual variables from neighboring buses and update the primal variables locally, as shown in Figure 3. It is worth noting that the primal and dual variables may not be within the defined domain due to approximation. Therefore, the usual approach is to map them back into the defined domain, where the primal variables adhere to Constraints (10)–(13), while the dual variables need to satisfy non-negativity, i.e., operator · + in (22)–(29). The pseudo code of dual ascent method is shown in Algorithm 1.
Algorithm 1: Dual Ascent Method
For a given n -bus distribution network,
1: Initialize primal variables P F L , Q P V and dual variables ω _ 1 , ω ¯ 1 , ω _ 2 , ω ¯ 2 , ω _ 3 , ω ¯ 3 , ω _ 4 , ω ¯ 4 , set step k = 0 .
2: Repeat
3:  For bus i , i 1 , . . . , n  do
4:  Input the local voltage magnitude V k .
5:  Update the dual variables according to (22)–(29);
6:  Send ω _ 1 k , ω _ 1 k , ω _ 2 k , ω ¯ 2 k , ω _ 3 k , ω ¯ 3 k , ω _ 4 k , ω ¯ 4 k to parents buses and ω _ 1 k , ω ¯ 1 k , ω _ 3 k , ω ¯ 3 k to child buses.
7:  Receive ω _ 1 k , ω ¯ 1 k , ω _ 3 k , ω ¯ 3 k from parent buses and ω _ 1 k , ω _ 1 k , ω _ 2 k , ω ¯ 2 k , ω _ 3 k , ω ¯ 3 k , ω _ 4 k , ω ¯ 4 k from child buses.
8:  Update the primal variables according to (20)–(21) and map them into the feasible range.
9:  Output the dispatch instruction P F R k and Q P V k .
10:    k = k + 1 .
11: Until stopping criteria V i k + 1 V i k < ε are met.

4. Case Studies

A modified IEEE 33-bus distribution system is simulated for case studies in this paper, as shown in Figure 4. The lower and upper limits of voltage magnitude are set to 0.95 p.u. and 1.05 p.u., respectively. According to the IEEE 1547 standard, distributed PV inverters are allowed to participate in voltage control by providing Var compensation at a power factor not less than 0.9 (i.e., the maximum reactive power is 0.4385 of the corresponding active power). In addition, except for the substation bus, all other buses have flexible loads that can perform power regulation within 30% of the peak load power. The profiles of PV power, active, and reactive loads in the distribution system within a day are given in Figure 5 and Figure 6. To expedite the convergence, ρ _ 1 , ρ ¯ 1 , ρ _ 2 , ρ ¯ 2 , ρ _ 3 , ρ ¯ 3 , ρ _ 4 , ρ ¯ 4 are set to be 1 / R 1 i i . The primal variables P F R , Q P V and dual variables ω _ 1 , ω ¯ 1 , ω _ 2 , ω ¯ 2 , ω _ 3 , ω ¯ 3 , ω _ 4 , ω ¯ 4 are all initialized to zero for the convenience of comparison. The terminal bus 18, which is prone to overvoltage, is selected to analyze the effectiveness of different control strategies. All numerical tests are conducted on a 2.6 GHz Intel Core i5 personal computer with 16 GB of memory. The algorithms are implemented in MATLAB R2023a, and the models are solved using the commercial solver CPLEX 12.7 via the YALMIP toolbox. All solvers are utilized with their default settings to ensure consistency and reliability in the results.

4.1. Convergence Performance of Proposed Algorithm

In this section, overvoltage events are simulated to analyze the convergence performance of the proposed algorithm under different step sizes. The parameter ρ ¯ 2 is crucial in the optimization process during the iterative steps of the distributed algorithm, as it directly impacts the effectiveness of mitigating overvoltage violations, as indicated in (26). Consequently, we focus on the values of the parameter ρ ¯ 2 while keeping the values of other step sizes unchanged to ensure overall stability and optimal performance.
Figure 7 and Figure 8 depict the convergence performance of objective values and voltage magnitudes under different values of ρ ¯ 2 . After a sufficient number of iterations, all three parameter choices in the distributed algorithm converge to the same optimal solution as the centralized problem (i.e., the objective value and voltage magnitude are 19 kW and 1.05 p.u., respectively). The step sizes ρ ¯ 2 = 0.01 and ρ ¯ 2 = 0.1 are relatively small, resulting in slower convergence speeds. In contrast, the algorithm with step size ρ ¯ 2 = 1 exhibits better convergence performance in terms of the optimization objective function, almost eliminating voltage violations after a single iteration. By comparing the curves, it can be concluded that increasing the step size ρ ¯ 2 effectively accelerates the convergence speed of the algorithm. However, a larger step size is not always preferable as it may lead to oscillations or even hinder convergence. Therefore, selecting an appropriate step size is crucial for optimizing the online application performance of the distributed algorithm.

4.2. Power Regulation Performance of FURs

To validate the long-term power regulation performance of the proposed algorithm, four representative cases are selected to demonstrate the superiority of the proposed method in optimizing the objective function and mitigating overvoltage. Considering that the proposed distributed algorithm only involves simple algebraic operations, and the majority of the time is consumed by information exchange between neighbors, it is reasonable to assume that each iteration takes approximately one second. The selected cases are as follows:
(1)
Case 1 (only Var control): In the absence of FURs, only PV inverters participate in distributed voltage control by providing reactive power.
(2)
Case 2 (traditional distributed algorithm): FURs and PV inverters modulate active and reactive power, respectively, to participate in distributed voltage control. This case utilizes the traditional dual ascent method, which requires convergence before applying the results to local controllers.
(3)
Case 3 (classical ADMM algorithm): FURs and PV inverters modulate active and reactive power, respectively, to participate in distributed voltage control. This case utilizes the ADMM algorithm, which also requires convergence before applying the results to local controllers.
(4)
Case 4 (proposed method): FURs and PV inverters modulate active and reactive power, respectively, to participate in distributed voltage control. This case employs the proposed distributed algorithm, which allows the results to be applied to local controllers in real time upon the completion of each iteration.
The parameter settings in all cases are consistent with those described in Section 4. The only differences are in the selection of decision variables and the logic of algorithm iteration for optimization.
Figure 9 and Figure 10 show the objective values and voltage magnitudes under different control strategies over a 15-minute period. Since FURs are not involved in power regulation, Case 1 requires PV inverters to absorb a significant amount of reactive power to suppress voltage rise. However, due to the relatively high ratio of R/X in the distribution network, the response of reactive power is less sensitive compared to that of active power. Additionally, the limited capacity of inverters hinders the sufficient mitigation of overvoltage violations. Consequently, Case 1 exhibits the poorest performance regarding objective values due to increased network losses. The voltage magnitudes in Case 1 frequently exceeded the upper voltage limit, leading to severe overvoltage violations.
Although Case 2 reduces operational costs by incorporating the power regulation of FURs, it employs the traditional dual ascent method, which can only apply the results to local controllers after achieving convergence. This limitation prevents it from rapidly responding to PV power fluctuations and promptly accommodating excessive PV power, resulting in voltage violations at certain instances.
Case 3, which employs the ADMM algorithm, demonstrates slightly improved convergence performances compared to the traditional dual ascent method. However, similar to the traditional dual ascent method, it requires full convergence before applying the results to local controllers.
The proposed method (i.e., Case 4) exhibits robust tracking and responsive performance. This method outputs control commands in real time at each iteration step, enabling optimized power allocation for FURs and PV inverters while maintaining voltage within an allowable range. Consequently, it effectively mitigates overvoltage violations in distribution networks with high PV penetration.

5. Conclusions

Existing distributed methods often require the algorithm to converge before issuing control instructions, which deteriorates their ability to efficiently track rapid fluctuations in PV power outputs. To improve the convergence performance of the distributed algorithm, this paper proposes an online power regulation method for flexible user-side resources based on the dual ascent method. By deconstructing the centralized problem into a primal–dual framework, the implementation method for the real-time control of flexible user-side resources is outlined.
Case studies demonstrate that the proposed model achieves a satisfactory objective value through information exchange between neighboring agents while ensuring a voltage control performance. Moreover, the appropriate values of parameters are crucial for ensuring the convergence performance of the distributed algorithm. Our future work will prioritize the modeling of different flexible user-side resources in a classified manner and integrating power coordination among heterogeneous flexible user-side resources.

Author Contributions

Conceptualization, Y.Y., F.W. and J.Y.; methodology, Y.Y., F.W. and J.Y.; software, Y.Y.; validation, F.W.; formal analysis, J.Y.; investigation, H.L.; resources, S.X., H.F. and C.W.; data curation, D.L.; writing—original draft preparation, Y.Y. and J.Y.; writing—review and editing, F.W. and J.Y.; visualization, Y.Y. and J.Y.; supervision, F.W.; project administration, S.X., H.F. and C.W.; funding acquisition, D.L. All authors have read and agreed to the published version of the manuscript.

Funding

This research was funded by National Key Research and Development Program of China entitled “Key technologies for the coordinated planning of flexible coal-fired power and large-scale renewable energy resources”, Project No. 2022YFB2403100.

Data Availability Statement

The data used to support the findings of this study are included in the paper.

Conflicts of Interest

Author Hangyue Liu was employed by the company Sungrow Australia Group Pty. Ltd. Author Dazheng Liu was employed by the company China Energy Economic and Technological Research Institute Co., Ltd. Authors Shujun Xin and Hao Fan were employed by the company State Grid Corporation of China. Author Cong Wu was employed by the company State Grid Energy Research Institute of China. The remaining authors declare that the research was conducted in the absence of any commercial or financial relationships that could be construed as a potential conflict of interest.

References

  1. Antoniadou-Plytaria, K.E.; Kouveliotis-Lysikatos, I.N.; Georgilakis, P.S.; Hatziargyriou, N.D. Distributed and decentralized voltage control of smart distribution networks: Models, methods, and future research. IEEE Trans. Smart Grid. 2017, 8, 2999–3008. [Google Scholar] [CrossRef]
  2. Yang, J.; Dong, Z.Y.; Wen, F.; Chen, Q.; Liang, B. Spot electricity market design for a power system characterized by high penetration of renewable energy generation. Energy Convers. Econ. 2021, 2, 67–78. [Google Scholar] [CrossRef]
  3. Wang, S.; Zhao, C.; Fan, L.; Bo, R. Distributionally robust unit commitment with flexible generation resources considering renewable energy uncertainty. IEEE Trans. Power Syst. 2022, 6, 4179–4190. [Google Scholar] [CrossRef]
  4. Zhao, B.; Xu, Z.; Xu, C.; Wang, C.; Lin, F. Network partition-based zonal voltage control for distribution networks with distributed PV systems. IEEE Trans. Smart Grid 2018, 9, 4087–4098. [Google Scholar] [CrossRef]
  5. Bakhtvar, M.; Keane, A. Allocation of wind capacity subject to long term voltage stability constraints. IEEE Trans. Power Syst. 2016, 3, 2404–2414. [Google Scholar] [CrossRef]
  6. Marneris, I.G.; Biskas, P.N.; Bakirtzis, E.A. An integrated scheduling approach to underpin flexibility in European power systems. IEEE Trans. Sustain. Energy 2016, 7, 647–657. [Google Scholar] [CrossRef]
  7. Vera, E.G.; Cañizares, C.A.; Pirnia, M.; Guedes, T.P.; Trujillo, J.D.M. Two-stage stochastic optimization model for multi-microgrid planning. IEEE Trans. Smart Grid 2023, 3, 1723–1735. [Google Scholar] [CrossRef]
  8. Huo, D.; Gu, C.; Ma, K.; Wei, W.; Xiang, Y.; Le Blond, S. Chance-constrained optimization for multienergy hub systems in a smart city. IEEE Trans. Ind. Electron. 2019, 2, 1402–1412. [Google Scholar] [CrossRef]
  9. Chen, S.; Wei, Z.; Sun, G.; Cheung, K.W.; Sun, Y. Multi-Linear probabilistic energy flow analysis of integrated electrical and natural-gas systems. IEEE Trans. Power Syst. 2017, 3, 1970–1979. [Google Scholar] [CrossRef]
  10. Chen, S.; Wei, Z.; Sun, G.; Cheung, K.W.; Wang, D.; Zang, H. Adaptive robust day-ahead dispatch for urban energy systems. IEEE Trans. Ind. Electron. 2019, 2, 1379–1390. [Google Scholar] [CrossRef]
  11. Li, J.; Xu, Y.; Wang, Y.; Li, M.; He, J.; Liu, C.C.; Schneider, K.P. Resilience-motivated distribution system restoration considering electricity-water-gas interdependency. IEEE Trans. Smart Grid 2021, 6, 4799–4812. [Google Scholar] [CrossRef]
  12. Diekerhof, M.; Peterssen, F.; Monti, A. Hierarchical distributed robust optimization for demand response services. IEEE Trans. Smart Grid 2018, 9, 6018–6029. [Google Scholar] [CrossRef]
  13. Mu, C.; Shi, Y.; Xu, N.; Wang, X.; Tang, Z.; Jia, H.; Geng, H. Multi-objective interval optimization dispatch of microgrid via deep reinforcement learning. IEEE Trans. Smart Grid. 2024, 3, 2957–2970. [Google Scholar] [CrossRef]
  14. Wang, J.; Zhong, H.; Tang, W.; Rajagopal, R.; Xia, Q.; Kang, C.; Wang, Y. Optimal bidding strategy for microgrids in joint energy and ancillary service markets considering flexible ramping products. Appl. Energy 2017, 205, 294–303. [Google Scholar] [CrossRef]
  15. Hu, J.; Sarker, M.R.; Wang, J.; Wen, F.; Liu, W. Provision of flexible ramping product by battery energy storage in dayahead energy and reserve markets. IET Gener. Transm. Distrib. 2018, 12, 2256–2264. [Google Scholar] [CrossRef]
  16. Zhang, B.; Kezunovic, M. Impact on power system flexibility by electric vehicle participation in ramp market. IEEE Trans. Smart Grid 2016, 7, 1285–1294. [Google Scholar] [CrossRef]
  17. Alipour, M.; Zare, K.; Abapour, M. MINLP probabilistic scheduling model for demand response programs integrated energy hubs. IEEE Trans. Ind. Inform. 2018, 14, 79–88. [Google Scholar] [CrossRef]
  18. Zhang, D.; Zhu, H.; Zhang, H.; Goh, H.H.; Liu, H.; Wu, T. Multi-objective optimization for smart integrated energy system considering demand responses and dynamic prices. IEEE Trans. Smart Grid 2022, 13, 1100–1112. [Google Scholar] [CrossRef]
  19. Zheng, S.; Sun, Y.; Li, B.; Shi, K.; Li, Y.; Tu, X. Incentive-based integrated demand response for multiple energy carriers considering behavioral coupling effect of consumers. IEEE Trans. Smart Grid 2020, 11, 3231–3245. [Google Scholar] [CrossRef]
  20. Torbaghan, S.S.; Suryanarayana, G.; Hoschle, H.; D’Hulst, R.; Geth, F.; Caerts, C.; Van Hertem, D. Optimal flexibility dispatch problem using second-order cone relaxation of AC power flows. IEEE Trans. Power Syst. 2020, 1, 98–108. [Google Scholar] [CrossRef]
  21. Xu, T.; Meng, H.; Zhu, J.; Wei, W.; Zhao, H.; Yang, H.; Li, Z.; Wu, Y. Optimal capacity allocation of energy storage in distribution networks considering active/reactive coordination. Energies 2021, 14, 1611. [Google Scholar] [CrossRef]
  22. Feng, C.; Wu, H.; Yang, J.; Li, Z.; Zhang, Y.; Wen, F. Communication-resilient and convergence-fast Peer-to-Peer energy trading scheme in a fully decentralized framework. Energy Convers. Econ. 2024, 5, 110–115. [Google Scholar] [CrossRef]
  23. Zeraati, M.; Hamedani Golshan, M.E.; Guerrero, J.M. Distributed control of battery energy storage systems for voltage regulation in distribution networks with high PV penetration. IEEE Trans. Smart Grid 2018, 9, 3582–3593. [Google Scholar] [CrossRef]
  24. Biswas, B.D.; Hasan, M.S.; Kamalasadan, S. Decentralized distributed convex optimal power flow model for power distribution system based on alternating direction method of multipliers. IEEE Trans. Ind. Appl. 2023, 1, 627–640. [Google Scholar] [CrossRef]
  25. Wen, Y.; Qu, X.; Li, W.; Liu, X.; Ye, X. Synergistic operation of electricity and natural gas networks via ADMM. IEEE Trans. Smart Grid 2018, 9, 4555–4565. [Google Scholar] [CrossRef]
  26. Li, J.; Xu, Z.; Zhao, J.; Zhang, C. Distributed online voltage control in active distribution networks considering PV curtailment. IEEE Trans. Ind. Inform. 2019, 15, 5519–5530. [Google Scholar] [CrossRef]
  27. Su, Y.; Liu, F.; Kang, K.; Wang, Z. Implicit sparsity of LinDistFlow model. IEEE Trans. Power Syst. 2023, 5, 4966–4969. [Google Scholar] [CrossRef]
  28. IEEE Std 1547-2018 (Revision of IEEE Std 1547-2003); IEEE Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces. IEEE: New York, NY, USA, 2018.
  29. West, D.B. Introduction to Graph Theory; Prentice-Hall, Inc.: Hoboken, NJ, USA, 2001. [Google Scholar]
  30. Zhu, H.; Liu, H.J. Fast local voltage control under limited reactive power: Optimality and stability analysis. IEEE Trans. Power Syst. 2016, 31, 3794–3803. [Google Scholar] [CrossRef]
Figure 1. (a) Traditional distributed algorithms. (b) Proposed distributed algorithms.
Figure 1. (a) Traditional distributed algorithms. (b) Proposed distributed algorithms.
Energies 17 04890 g001
Figure 2. Centralized architecture of distribution networks.
Figure 2. Centralized architecture of distribution networks.
Energies 17 04890 g002
Figure 3. Distributed architecture of distribution networks.
Figure 3. Distributed architecture of distribution networks.
Energies 17 04890 g003
Figure 4. Modified 33-bus distribution network.
Figure 4. Modified 33-bus distribution network.
Energies 17 04890 g004
Figure 5. PV power profile in a day.
Figure 5. PV power profile in a day.
Energies 17 04890 g005
Figure 6. Active and reactive load profiles in a day.
Figure 6. Active and reactive load profiles in a day.
Energies 17 04890 g006
Figure 7. The convergence performance of objective values with different values of ρ ¯ 2 .
Figure 7. The convergence performance of objective values with different values of ρ ¯ 2 .
Energies 17 04890 g007
Figure 8. The convergence performance of voltage magnitudes with different values of ρ ¯ 2 .
Figure 8. The convergence performance of voltage magnitudes with different values of ρ ¯ 2 .
Energies 17 04890 g008
Figure 9. Objective values under different control strategies.
Figure 9. Objective values under different control strategies.
Energies 17 04890 g009
Figure 10. Voltage magnitudes under different control strategies.
Figure 10. Voltage magnitudes under different control strategies.
Energies 17 04890 g010
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Yang, Y.; Wen, F.; Yang, J.; Liu, H.; Liu, D.; Xin, S.; Fan, H.; Wu, C. Real-Time Power Regulation of Flexible User-Side Resources in Distribution Networks via Dual Ascent Method. Energies 2024, 17, 4890. https://doi.org/10.3390/en17194890

AMA Style

Yang Y, Wen F, Yang J, Liu H, Liu D, Xin S, Fan H, Wu C. Real-Time Power Regulation of Flexible User-Side Resources in Distribution Networks via Dual Ascent Method. Energies. 2024; 17(19):4890. https://doi.org/10.3390/en17194890

Chicago/Turabian Style

Yang, Yu, Fushuan Wen, Jiajia Yang, Hangyue Liu, Dazheng Liu, Shujun Xin, Hao Fan, and Cong Wu. 2024. "Real-Time Power Regulation of Flexible User-Side Resources in Distribution Networks via Dual Ascent Method" Energies 17, no. 19: 4890. https://doi.org/10.3390/en17194890

APA Style

Yang, Y., Wen, F., Yang, J., Liu, H., Liu, D., Xin, S., Fan, H., & Wu, C. (2024). Real-Time Power Regulation of Flexible User-Side Resources in Distribution Networks via Dual Ascent Method. Energies, 17(19), 4890. https://doi.org/10.3390/en17194890

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop