Next Article in Journal
Effect of Biochar on Anaerobic Co-Digestion of Untreated Sewage Sludge with Municipal Organic Waste under Mesophilic Conditions
Next Article in Special Issue
Promoting Decarbonization in China: Revealing the Impact of Various Energy Policies on the Power Sector Based on a Coupled Model
Previous Article in Journal
Energy Efficiency Analysis of Waste-to-Energy Plants in Poland
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Active Planning for Virtual Microgrids with Demand-Side and Distributed Energy Resources

1
Department of Electrical and Electronic Engineering, Xi’an Jiaotong-Liverpool University, Suzhou 215123, China
2
Shien-Ming Wu School of Intelligent Engineering, South China University of Technology, Guangzhou 510006, China
3
Department of Electrical Engineering and Electronics, University of Liverpool, Liverpool L69 3BX, UK
*
Author to whom correspondence should be addressed.
Energies 2024, 17(10), 2391; https://doi.org/10.3390/en17102391
Submission received: 27 March 2024 / Revised: 10 May 2024 / Accepted: 13 May 2024 / Published: 16 May 2024

Abstract

:
In this paper, the notion of a cohesive and self-sufficient grid is proposed. Based on a cohesive and self-sufficient virtual microgrid, an active distribution network is optimally planned, and an optimal configuration of demand-side resources, distributed generations, and energy storage systems are generated. To cope with stochastic uncertainty from forecast error in wind speed and load, flexibility reserves are needed. In this paper, the supply relation between flexibility and uncertainty is quantified and integrated in an innovative index which is defined as cohesion. The optimization objectives are a minimized operational cost and system net-ability cohesion as well as self-sufficiency, which is defined as the abilities both to supply local load and to deal with potential uncertainty. After testing the optimal configuration in the PG&E 69 bus system, it is found that with a more cohesive VM partition, the self-sufficiency of VMs is also increased. Also, a case study on uncertainty-caused system imbalance is carried out to show how flexibility resources are utilized in real-time operational balance.

1. Introduction

Conventional distribution networks (CDNs) are facing challenges in integrating distributed energy resources (DERs), especially renewable energy sources (RESs), which are associated with intermittency and fluctuations. For example, the unidirectional power flow from the power grid to customers in CDNs may conflict with the requirement of distributed generators (DGs) to deliver power back to the grid; the increasing penetration of RESs with fluctuations and intermittency may cause higher uncertainty in operation.
To solve these issues, researchers place great emphasis on developing active distribution networks (ADN). The consensus on the definition of an ADN was proposed by CIGRE (International Council on Large Electric System) as a system in place to control a combination of DERs, including generators, loads, and storages, while distribution system operators (DSO) manage power flow in a flexible network, and DERs take some degree of responsibility for system support [1]. It has been pointed out that ADNs can support more DG connections than networks with a fit-and-forget strategy instead of ADN management [2].
Compared with CDNs, an ADN should display its “active” features in three aspects, which are active planning, active management, and active defense. Some features of ADN include, but are not limited to, the following:
  • Optimally planned configuration of DG, distributed energy storage system (DESS), and controllable load (CL), which enables bidirectional power flow and the capabilities of the prosumer selling power to the grid or to each other;
  • Corrective power flow management and control in real-time, instead of leaving significant redundancy in the planning stage preventively, as in the “fit-and-forget” strategy;
  • Defense capability considered in planning and management stage, for example, system reliability under possible grid disintegration to prevent cascading failure’s propagation.
With existing large-scale CDN infrastructure, there are challenges regarding the transition from CDNs to ADNs. Firstly, the structure and configuration of CDNs have been formed over a long period, and they cannot be extensively upgraded due to investment constraints. Secondly, if individual prosumers are allowed to directly generate power into the main grid, additional measurement and control units will be used, which leads to communication and computation difficulties. Thirdly, emerging technologies (e.g., microgrid) cannot be directly utilized for large-scale existing loads in CDNs if they cannot be subversively reconstructed.
To deal with these issues, the virtual microgrid (VM) is viewed as a possible and realistic solution. In our research, a VM is defined as a subnetwork that is partitioned from a CDN, performing as a microgrid. In contrast to conventional microgrids’ (CMs’) physical boundaries, VMs’ boundaries are from partitioning, which is virtual, so that it may not only keep existing structure and configuration of CDNs but also utilize the advantages of microgrid technologies. In past research [3,4], a VM was created in a clustering CDN for system performance optimization. Based on a complex network method, the boundaries of VMs can be identified by structural characteristics [5] so that each VM may perform with better efficiency.
Self-sufficiency denotes the ability of VMs to supply load when working in independent or even islanding mode and fulfill power demand/supply discrepancy within a VM in a certain time slot. Similar ideas have been used in past research [4,6,7,8], which mainly consider sufficiency in a static power supply capacity and not as a dynamic balance between flexibility and uncertainty. However, one key challenge in integrating renewable power generation with CDNs is their uncertainty. Then, the local sufficiency of flexibility resources is a key point that VMs must consider to construct a capable ADN. However, this has never been considered in previous research about VMs.
Power grid flexibility is defined in some research [9] as the system’s ability to cope with variability and uncertainty in both generation and demand, while maintaining a satisfactory level of reliability at a reasonable cost. In this definition, flexibility must cope with not only short-term uncertainty, derived from RESs and load fluctuations, but also long-term variability, meaning the estimable but inevitable variation in RESs, such as the seasonal changes in wind speed and solar hour. In this paper, the definition of flexibility will be focused to dealing with short-term disturbances that are fast enough to keep the system secure [10], as per the definition of many researchers (M. Bucher et al. [10,11], J. Bertsch et al. [12], and E. Lannoye et al. [13]). Long-term flexibility is inapplicable here, because RESs’ long-term variation is supposed to be foreknown, and long-term unit commitment portfolio schedules can be altered according to estimations.
In a previous study [14], an index for flexibility supply was introduced to quantify flexibility and uncertainty based on a triad of available power, ramp rate, and energy capacity. In this paper, these three elements are normalized and averaged to obtain a flexibility index (FI) for DGs, controllable loads (CLs), and DESSs. Following a similar method, the uncertainty index (UI) is formulated. The flexibility supply index (FSI), being the ratio between FI and UI, denotes the supply and demand balance of flexibility sources.
Compared with the existing literature, the contributions of this paper include the following:
  • The active planning of ADN is defined as the maximization of system active management and active defense capability. Then, based on these definitions, new meanings of self-sufficient VM are proposed;
  • Based on the meaning of self-sufficiency, an assessment method of grid flexibility and uncertainty balance is proposed and calculated via Monte Carlo simulation;
  • Based on the meaning of self-sufficiency, the definition and assessment of VM structural cohesion are put forward;
  • A bi-level optimization model for self-sufficient VMs’ active planning is designed and implemented.
This paper is structured as follows: Section 2 further explains the ideas of active distribution networks and virtual microgrids and revises the notion of net-ability in the VMs setting. Section 3 will discuss the quantification method of flexibility and uncertainty. In Section 4, a bi-level optimization based on Monte Carlo simulation (MCS) and genetic algorithm (GA) is proposed for active planning. Section 5 proposes a case study based on the PG&E 69 bus system, and comparisons are made to show improvements from existing methods. In Section 6, a discussion on the case study is provided for more concrete analysis, and the limitations of the proposed research are described. Section 7 concludes this paper.

2. Concepts for Self-Sufficient and Cohesive VM

2.1. Active Planning for VMs with IoT Supports

In our research, enabling the technology of ADNs consists of three categories: active planning, active management, and active defense. A research framework is shown in Figure 1. Active planning is defined as a smart configuration of system components that may support adequate capabilities in active management and active defense. An ADN with multiple VMs could be considered as an extended CPS system (cyber, physical, and socioeconomic) [5]. So, active planning could be performed in a physical layer, cyber layer, and socioeconomic layer. This paper mainly focuses on resource allocation in the physical layer. Further, by definition, active management refers to schedule and control technologies which enable the higher penetration of RESs with lower curtailment and the inclusion of prosumers to meet power consumption requirements with lower cost. With a transactive energy framework from planning, transactive energy control, which may utilize transactions as means to achieve specific control targets, could be implemented to perform distributed energy management [15,16]. Active defense considers the capability of an ADN in proactive strategies to safeguard operation under forecast errors, random faults, or malicious attacks.
Conventional microgrids have been widely studied as typical IoT (Internet of Things) systems [17,18]. With similar characteristics, ADNs composed of multiple VMs could also be considered as typical IoT systems. As shown in Figure 1, IoT system design would be an important part in the cyber layer, which may support data and information for the upper intelligence of decision making. IoT-enabling technologies could enhance the system’s capabilities in active management and active defense significantly.
In most previous research, ADN is normally viewed wholly in the planning stage, without considering system partition. For example, in [19], multi-level active planning is provided for RESs and energy storage systems (ESSs) using particle swamp optimization (PSO), considering cost, RES promotion, and reliability in the whole distribution network.
In [20], the honey badger algorithm (HBA), a heuristic algorithm, was used to size the DGs optimally in IEEE’s 33-bus and 69-bus power distribution test bench systems to minimize power losses. However, only a single DG is sized and allocated (i.e., at bus 61 for the IEEE 69 system). This methodology is not suitable for accommodating DERs in a modern ADN.
In [21], DGs and capacitor banks (CBs) are sized and allocated based on single-level GA optimization to reduce losses and to improve the voltage profile. In this paper, the evaluation of a GA chromosome only utilized voltage levels and transformer core impedance to calculate the losses, without considering the network’s topology and distribution line losses.
In [22], similar to a GA, a multi-objective evolutionary algorithm is proposed for optimizing the sites and sizes of DGs. The algorithm itself provides good results for conflicting objective functions with global optimal values, with a small DG size. However, the optimization objectives are given by assuming constant loads and in a case study of fixed operating cases for DGs, which is likely not to be the real management scenario.
Since VMs provide an applicable and self-sufficient solution in building cohesive ADNs, this paper focuses on planning augmented ADNs using multiple interconnected VMs with self-sufficiency and cohesion in each of them. The notions of self-sufficiency and cohesion will be explained in the next two sections.

2.2. VM Self-Sufficiency

Previously, quantified self-sufficiency was normally limited to static power balance. Self-sufficiency, together with similar concepts including self-adequacy, autonomous ability, and supply adequacy, was generally defined as a system’s ability to continue working under a power balance discrepancy. These concepts are fundamentals for building VMs focusing on power supply adequacy with ideal operation conditions, such as perfect forecast without impacts from uncertainties. In [6,23], autonomy and supply-sufficiency are constraints in optimization, without explicit quantification. In [8], self-sufficiency is measured by its total power exchange with other microgrid. In [7], power exchange and microgrid internal power balance are both considered and quantified.
However, our proposed meaning of self-sufficiency shall be two-fold. This definition covers both active management and active defense in building ADN. First, the system needs to support enough critical loads with enough power generation capacity, which follows the above-mentioned meaning. Second, the system should also have enough flexibility resources installed to locally balance potential uncertainties. Only considering the traditional first aspect, i.e., power supply and demand balance, is not adequate, because with a large RES and relatively small reserve setting, the forecast error of wind or solar power and loads may lead to potential and indeterministic power imbalance, insufficient ramp rate, and energy gap. This is critical not only for active management, which intends to maintain flexible operations without support from the main grid, but also for active defense to guarantee secure independent islanding operation in response to faults or attacks.

2.3. VM Cohesion

VMs could be viewed as subsystems which may support ADNs with flexible operation in management and independent survivability in defense. However, very few works have considered the sources where these characteristics are from. In this paper, we propose a new concept of ‘cohesion’ as a critical feature which may be positively corelated to VM independence.
For a network S , the cohesion as a feature is intuitional in analyzing partition. A subnetwork s is defined as cohesive, respective to cohesive feature mapping f , if and only if the following is true:
f s > f S , s P
where s is a subnetwork of the whole network S . P is the partitioned subnetworks set. f is a function to evaluate the performance of a network. That means that a subnetwork is cohesive if its performance evaluated by a specific metric is higher than the average performance of the entire network.
Thus, the cohesion intensity (CI) of network S with subsystem s i could be defined as
c f s = f s f S
C I S = 1 N s c f s i , s i P
where N s is the number of subsystems under P , and C I S is the averaged cohesion intensity of each subsystem’s cohesion function c f ( s ) .
The cohesive nature of the subsystem is illustrated in Figure 2. In case (a), if the network performance is evaluated by efficiency (reciprocal of distance) [24] between vertices, two partitioned subnetworks are obviously more cohesive than the average performance of the whole network, as the mean distance of the circled part is visually smaller than the whole system.
In case (b), with even distance distribution, the network has much fewer cohesive characteristics. No matter the partition method, the average distance is the same with the whole system; thus, the cohesion intensity of any partition is smaller than case (a). With more factors in the definition of performance metrics, this concept is extended to include more engineering considerations and not only distance in our research.

2.4. Net-Ability

As shown in the definition of VM cohesion, an index f to evaluate the performance of a network is needed. Net-ability could be a possible solution for power grids. Net-ability derives from graph efficiency. In complex network theory, the global efficiency of a network graph is defined by the averaged reciprocal of geodesic distances, i.e., the shortest path, between nodes [24], as follows:
E G = 1 N N 1 i j G 1 d i j
where N is total number of nodes, and d i j denotes the geodesic distance between node i and node j in graph G . If the averaged value of the reciprocal of the shortest path length is higher, then intuitively, the communication between nodes will be more efficient.
After applying this definition in power networks, S. Arianos et al. [25] proposed the idea of net-ability (NA) as
N A = 1 N G N D i G j D C i j Z i j Z i j = z i i 2 z i j + z j j
where z i j is the i t h row and j t h column element of the impedance matrix [26], and Z i j is defined as the equivalent impedance. Given a line flow limit, C i j is the equivalent transfer capacity from bus i to j , which is the maximum power transmitted from i to j, following power flow constraints. N G and N D are the numbers of generations and load buses, respectively.
In this definition, the geodesic distance is replaced by transfer capacity over impedance, indicating the “difficulty” of power transmission between node i and j . If C i j Z i j of a certain path is higher, the corresponding branches of the path are viewed as possessing more aptitude in power transmission.
Contrary to N × N 1 , which is the number of all possible connection pairs between N nodes, N G N D is the number of all electrical pairs between generators and loads.

2.5. VM, VPP, and Conventional Microgrids

In this paper, a virtual microgrid is defined as a virtually partitioned grid in which the nodes’ clustering represents better cohesion than a whole ADN, and in each cluster, optimal planning, management, and defense capabilities are improved in comparison to viewing an ADN as a whole. Previous research on VMs has not clarified the relationship between similar concepts, including virtual power plant (VPP) and conventional microgrids (CM). These three technologies are all to deal with challenges from integration of DERs based on aggregation, but the methods and operational scenarios are different.
Compared with VPP, VM and CM can work in both islanding mode and grid-connected mode. VPP has no emphasis on the spatial boundary of aggregated resources. Another difference would be that VPP has more consideration in the active management and control strategy but fewer considerations in active defense capability than VM.
Conventional microgrid (CM), on the other hand, requires a total physical reconstruction of the CDN, while VM is only partitioned based on existing grid structure. Compared with CM, VM may have better topological scalability due to flexible partitions with dynamic borders. The construction and configuration of VMs could be dynamically adjusted in accordance with the development process from CDNs to ADNs, and even further.

3. Evaluation of Self-Sufficiency, Flexibility, and Cohesion in VMs

3.1. Quantification of Flexibility and Uncertainty

In power systems, flexibility refers to the capability to manage variability and uncertainty in both generation and demand. The challenge in the current energy transition is not only influencing the level of flexibility needed but also identifying the amount of flexibility needed in power systems [27]. In [13,28], E. Lannoye et al. defined scheduled flexibility by ramp rate times, which are the system’s online times when a unit commitment issue is being considered. In [14], A. Ulbig et al. proposed the triad of power provision capacity, power ramp rate capacity, and energy provision capacity, based on the original quantification in [29]. In [9], J. Ma et al. proposed a scalar flexibility index for planning in a sustainable energy system over a long-term investment in unit commitment and construction, considering ramp rate and minimum stable generation. In [30], a Minkowski sum is used to aggregate individual generators’ flexibility into system flexibility.
As mentioned, one aspect of flexibility is defined as the ability to cope with uncertainty, i.e., forecast error and potential component failure. In [31], a Gaussian distribution is used to model forecast error in load. In [32,33], M. Milligan et al. proposed a skewed Gaussian distribution model for both wind and load forecast error with non-zero skewness and kurtosis, based on real-world data in several transmission networks in Europe and America. The similar weighted sum of skewed model was also used in [34].
Our flexibility quantification method is derived from the triad proposed in [14,28], with additional consideration in upward and downward flexibility. These previous research works focus on analyzing a given real-world power generation portfolio. Yet, in the active planning of this paper, the power generation configuration and output are optimized and simulated, which requires a Monte Carlo analysis to improve the validity.
In this paper, a flexibility array (FA) is designed as a 6-dimensional array, consisting of upwards/downwards ramp rate, power, and energy. Our proposed method is enlightened by [14], in which the quantification uses a Minkowski sum in 3-dimensional space.
To ensure that the results in uncertainty quantification can be directly compared, an uncertainty array (UA) is also construed, following a similar design of flexibility quantification.

3.2. Flexibility Supply Quantification in Active Planning Based on Monte Carlo Simulation

In this paper, flexibility is quantified with an array of available energy, power, and ramp rate. For each dispatchable DG, DESS, and controllable load, these three elements are assessed according to their working state in each sample of the Monte Carlo simulation. Moreover, flexibility is further categorized as upward/downward flexibility, which means to increase or to decrease power supply from its current working state. The quantified flexibility array (FA) is divided into each element by the quantified uncertainty array (UA), yielding the flexibility supply index (FSI). The flow chart outlining steps to defining FSI is shown in Figure 3 below and will be explained in this section.
Monte Carlo is used to produce samples of forecast load and RES power from flexibility scenario space. Then, corresponding to each sample, the day-ahead DG operation schedule will be produced by AC-OPF. According to the working states of the DG and BESS in this schedule, compared with their available capabilities, the flexibility of this sample could be quantitatively evaluated. Similarly, Monte Carlo is used to generate samples of load and RES forecast error from the uncertainty scenario space. According to these errors, the uncertainty of each sample scenario could be quantitatively assessed. With the FA and UA of all these samples, the overall FA and UA metrics could be defined as follows:
F A M C = 1 N i t e r F A Ω f l e x
U A M C = 1 N i t e r U A ( Ω u n c e r )
where F A M C and U A M C are the functions of total N i t e r samples. Ω f l e x represents sampling flexibility scenarios according to wind speed distribution, load situation, and DESS initial storage. Ω u n c e r represents sampling uncertainty scenarios including forecast errors in both wind and load power. The distributions of flexibility and uncertainty are viewed as independent, as are these two scenarios’ sets.
Concretely, the calculation of FA for each type of device in a sampling scenario will be discussed in the following section. For a dispatchable DG, the available energy is determined by its power variation capacity, both upward and downward, multiplied with the time slot for flexibility assessment. Yet, for a DESS, the available energy is related to the state of charge ( S o C ). Since a battery cannot further supply or absorb power after reaching its energy limit, its available power is the average power over the charging or discharging time slot. The assumption that the charging/discharging lasts for the whole time slot makes sure that the power is stable during this time slot.
If the charging or discharging process is interrupted by reaching the energy storage capacity limit, the upward/downward power and energy flexibility will be defined by
F l e x p , + , d e s s = m i n { P d c , E m × S o C S o C m i n T } F l e x p , , d e s s = m i n { P c , E m × S o C m a x S o C T }
F l e x e , + , d e s s = F l e x p , + , d e s s × T F l e x e , , d e s s = F l e x p , , d e s s × T
where P c is the rated charging power, P d c is the rated discharging power, E m is the maximum energy storage, and T is the flexibility assessment time slot.
A more detailed illustration of DESS flexibility per SoC is shown in Table 1. R R c denotes the charging ramp rate of the DESS, and R R d c is its discharging counterpart. In this paper, the parametric values are assumed such that in T , DESS charging/discharging is carried out at an averaged rate.
For a dispatchable DG, flexibility is related to the output percentage of the DG’s rated power, which is shown in Table 2. When DG is working at full power output, it is unable to provide more power; thus, its upward flexibility is 0. A similar situation makes the downward flexibility of a not-in-use DG zero. Non-dispatchable DGs, on the other hand, cannot provide flexibility. Due to the existence of renewable energy uncertainty, i.e., wind forecast error, non-dispatchable DGs serve as the “consumer” of power system flexibility.
Controllable loads (CL) can also be considered as a flexibility resource which behaves similarly to dispatchable generators in flexibility supply,
F l e x + , c l = P c l T , P c l , R R c l F l e x , c l = P c l T , P c l , R R c l
Once the flexibility triad of each resource is obtained, system flexibility F is the aggregated flexibility value.
F k , ± = G F l e x k , i
where G denotes the set of DGs, DESSs, and controllable loads, and F l e x i , k is the flexibility on bus i , where k represents either energy, power, or ramp rate.
In this paper, the flexibility array (FA) is defined as
F r a m p + , F r a m p , F p o w e r + , F p o w e r , F e n e r g y + , F e n e r g y
in R 6 Hilbert space with a vectorized basis representing power, ramp rate, and energy, both upwards and downwards, for a single scenario. It will be averaged during the calculation of FSI.

3.3. Uncertainty Index and Flexibility Supply Index

For short-term analysis in an advanced ADN, uncertainty is limited to load uncertainty and RES fluctuation, e.g., wind forecast error, causing power variation. The normalized uncertainty from wind forecast error is given by,
ε w t = w t w ^ ( t ) U p , + , w = ε w       ε w > 0 0             ε w 0 U p , , w = 0               ε w > 0   ε w         ε w 0
where ε w is the wind power generation forecast error, w t is the real-time wind power generation, and w ^ ( t ) is the one-day-ahead forecast value at time t .
The wind power generation forecast uncertainty in energy is given by power uncertainty multiplied with time slot length:
U e , ± , w = ε w × T
The wind power generation forecast uncertainty in ramp rate in the wind forecast is given by
U r , ± , w = ε w / T
Another source of uncertainty is the load forecast error, which follows the same method:
U p , + , l = ε l       ε l > 0 0             ε l 0 U p , , l = 0               ε l > 0   ε l         ε l 0 U e , ± , l = ε l × T U r , ± , l = ε l / T
Assuming generation is positive and demand is negative, the total uncertainties, i.e., an ADN’s flexibility lower boundaries, are given by
U p o w e r ± = U p , ± , w U p , ± , l U r a m p ± = U r , ± , w U r , ± , l U e n e r g y ± = U e , ± , w U e , ± , l
Thus, the uncertainty array (UA) is
U r a m p + , U r a m p , U p o w e r + , U p o w e r , U e n e r g y + , U e n e r g y
Finally, the flexibility supply index (FSI) is defined as the ratio between FA and UA, indicating the power system’s ability to meet flexibility demand. As mentioned above, the norm of Monte Carlo values is used to yield FSI as such:
F S I = n o r m ( F A M C ( ) U A M C ( ) )

3.4. Integration of Cohesion and Self-Sufficiency

As mentioned, net-ability (NA) describes the performance of power grid transmission and could be utilized in assessing cohesion, but to better depict the self-sufficiency of VMs in an ADN, the revised net-ability (RNA) with two factors for VM is proposed to quantify power balance.
First, capacity fitness (CF) denotes the static self-sufficiency of a power system, which is an important part of autonomous ability. It is defined as the ratio between total installed generation capacity and load capacity:
C F = Γ C G i D L i
where C G i is the installed capacity of generator i in power supply set Γ , and L i denotes the i t h load in power demand set D .
Second, to depict the flexibility, the FSI of VM should also be integrated. Thus, the RNA is given by multiplying CF and FSI with the existing NA definition:
R N A = C F F S I 1 N G N D G D C i j Z i j
Therefore, the RNA can represent not only the performance in power transmission but also local balance in power supply and flexibility supply in VM. Then, the optimized cohesion evaluated by RNA as f in equation (2) would be consistent with the requirement of self-sufficiency.

4. Active Planning of Virtual Microgrid

The goal of the active planning of ADN is to enhance active management and active defense capability via optimized locations, capacities, and types of DG and DESS. The active management level is represented by the following:
  • Optimized operational cost.
  • Self-sufficiency in local power supply of VMs represented by minimized boundary power flow.
  • Sufficient flexibility sources to cope with uncertainty in grid-connected mode.
  • The active defense capability is related to,
  • Maintaining VMs’ critical load in augmented islanding mode, represented by VMs’ capacity fitness.
  • Sufficient local flexibility sources in islanding mode to maintain stable operation.
  • Cohesive structure of VMs for optimal operating efficiency in islanding mode and robustness in restoration.

4.1. Bi-Level Optimization Model

Our proposed bi-level, mixed-integer, multi-objective optimization is illustrated in Figure 4 below. The VM partition method is based on an improved Newman algorithm [5,35], in which electrical modularity (EM) weighted by electrical coupling strength (ECS) is calculated iteratively for all merging cases, and the number of VMs is decreased from the initial maximum number of N b u s to 1. By giving the desired range of VMs, the partition method with the maximum EM can be selected.
Two objective functions are construed for outer optimization. The first objective is operational cost and boundary flow penalty cost. The boundary line flow between adjacent VMs is penalized by the corresponding line shadow cost, which is the marginal cost per unit of all DGs, explained in [36]. The second goal is RNA cohesion, denoting a beneficial system augmentation.
Decision variables in this objective function denote DGs’ and DESSs’ locations, types, and capacities. The locations of DGs refers to their connected buses. The types of DGs include dispatchable DGs and non-dispatchable DGs. Dispatchable DGs are power sources of which generation can be controlled, including gas turbines, biomass generators, etc. Non-dispatchable DGs refer to rigid power generation, with little variability. In this ADN planning, wind power and solar photovoltaic panels are regarded as non-dispatchable for critical load balancing. The capacity of DGs is defined as the maximum power generation.
As mentioned above, the first objective of outer optimization is the total cost, given by (22)
min F F = 1 M C i t e r Ω G f i P D G i X + B P F i , j X λ i , j X
where f i P D G i X denotes the generation cost function, with respect to active power generation by the i t h DG. X is the GA chromosome consisting of DG and DESS configuration, which is the decision variable in the GA. P F i , j X represents the power flow between node i and node j that are boundary nodes of VMs in node set B . λ i , j X is the shadow cost which is used as the penalty cost for boundary flow. The sum of operational cost and penalty cost are averaged via Monte Carlo scenario space Ω . In MCS, the iteration number is M C i t e r , and the combined sampling space is the tensor product of load situation distribution and wind speed distribution.
The second goal of outer optimization is the cohesion of RNA, shown in (23). The difference between the RNA of VMs and that of the whole ADN denotes the potential autonomous ability gain. FSI denotes the flexibility resources’ relative amount with respect to system uncertainty in wind power and loads. To summarize, the cohesive feature is the R N A difference between individual VMs and the total distribution network, which is the optimization goal.
max C I ( X )                                                                                                                             C I X = 1 N m V R N A i X R N A t o t X                                                      
In (23), R N A i X denotes the revised net-ability of i t h VM and R N A t o t X is the RNA of the whole ADN. N m is the number of VM partitions, i.e., number of elements in VM set V .
The inner optimization is AC-OPF, yielding the optimized operational cost and the corresponding DG active power output. Note that the Monte Carlo scenario space in Figure 4 refers to the sampling of wind speed, load, and forecast errors in Figure 3.

4.2. Constraints

In multi-objective GA optimization, inequality constraints include total installed capacity limits in both DG and DESS due to the limitation of investment in engineering practice.
Γ D G C D G , i C D G , m a x
Γ D E S S C D E S S , i C D E S S , m a x
In each VM, critical load should always be supplied.
Γ i C i Δ i L i K i
where K i is the critical load percentage, Γ i C i is the total installed capacity in the i t h VM, and Δ i L i is the total load in the i t h VM.
Another constraint regards FSI. To ensure that each VM has adequate flexibility resources, a lower boundary is added in each VM’s FSI, as follows:
F S I V M i f l i
in which f l i is the FSI limit constant for the i t h VM.
To ensure enough renewable energy penetration in each VM, the minimal wind turbine capacity is defined.
C W T , i C W T , i , m i n
C W T , i is the wind turbine installed capacity in VM i , and C W T , i , m i n is the lower bound.
In the outer layer GA, each element on the chromosome is an integer depicting DG and DESS configuration, which will be explained in Section 3. Integer constraints are the non-convex optimization constraints.
The constraints of inner optimization include the power flow balance equation, power transfer equation constraints, voltage stability constraints, and line flow thermal constraints.
Γ P D G i = Δ L i + Β T L i
P i = V i j = 1 N B V j G i j cos δ i j + B i j sin δ i j
Q i = V i j = 1 N B V j G i j sin δ i j B i j cos δ i j
V i,min V i V i,max
P i j P i j m a x
In these constraints, P D G i is the generator’s output on the i t h bus, L i is the load installed on the i t h bus, and T L i is the thermal loss on the i t h feeder in branch set Β . Equations (30) and (31) are the power transfer equations, in which P i and Q i are the active and reactive power injected into the i t h bus. G i j and B i j are the real and imaginary parts of the admittance matrix. δ i j is the phasor angle difference between bus i and bus j . V i is the bus voltage, and P i j is the active power flow from bus i to bus j .

4.3. Implementation

The outer optimization is implemented by GA through the function gamultiobj in the Global Optimization Toolbox in MATLAB, which starts from an initial population and then individual chromosomes crossover and mutate, until GA’s fitness evaluation converges or the iteration number reaches its limit.
The chromosome has two parts with the same length conjugated, and each part has a length equivalent to the number of buses in the ADN, representing the locations of the DG and DESS. Each element has values representing the tensor product of configurations of the DG and DESS.
X = X D G , X D E S S
X D G = L o c a t i o n D G T y p e D G C a p a c i t y D G
X D E S S = L o c a t i o n D E S S T y p e D E S S C a p a c i t y D E S S
The generation function, mutation function, and crossover function in GA are customized for mixed-integer programming. Two fitness functions consist of two optimization goals to be optimized.
The inner optimization is AC-OPF nested in fitness functions of GA, which is solved using the MATPOWER 7.0 package in MATLAB. Wind and load sampling space are simulated by the Weibull distribution and load data from [37].The averaged objective is then given by MCS.

5. Case Study

A case study is based on the PG&E 69-bus system with branch configuration from [38]. The coding environment is MATLAB R2022a (x86) installed on a workstation with an Intel Core i9-10920X CPU and 32 GB memory. The total running time is 54 h 12 min.

5.1. System Modelling

Wind speed is simulated by the Weibull distribution, given by
f v w i n d = k A v w i n d A k 1 exp v w i n d A k
over four seasons. Weibull parameters are given in Table 3.
Load distribution is further categorized into 8 groups, which include weekdays and weekends in spring, summer, autumn, and winter, with the load profile provided in the IEEE Reliability Test System [37]. The detailed load data and figure are shown in Appendix A.
Four levels (50 kW, 100 kW, 150 kW, 200 kW) of the DG’s installed capacity and two types (both dispatchable and non-dispatchable) are considered in our case. The energy storage system is considered to have rated charging and discharging power of 50 kW, and the maximum storage is 120 kWh. The maximum SoC in operation is 95%, and the minimum SoC is 5%. The maximum adjustable demand in controllable loads is set as 10% of loads on corresponding buses. Both upwards and downwards ramp rates of DGs are regarded as 10% of rated power per min. The power output of the DESS is fast enough to reach rated power within 1 min; thus, the averaged ramp rate is 50 kW/min in this case. The initial values of the DESS SoC are set as 50%.

5.2. DG and DESS Configuration

The optimization result when the total installed capacity is capped at 4 MW is presented by the Pareto Front shown in Figure 5. The knee point, i.e., the point with maximum marginal utilities, is specified. Note that the negative values on the y-axis result from the minimalization of −1 × RNA cohesion. The configurations of the DG and DESS are given by Figure 6 and Figure 7. To represent the installed capacity in each bus, a bar plot is given in Figure 6 to show the 4 types of capacity, i.e., 50 KW, 100 KW, 150 KW, and 200 KW.
The constraints are respected without violation, as shown in Table 4. For the table, we can tell that the critical load is fully supplied and the FSI level is far from its violation. The installed DG’s capacity is at its maximum limit, due to the attempt to increase the cohesion of FSI and RNA. The voltage level is in the safe range for power system stability.

5.3. VM Management and Defense Capability

As mentioned, active planning takes active management and defense into consideration. To enhance management capability under wind and load uncertainty, one VM should use its local flexibility resources to prevent additional boundary flow with other VMs caused by wind and load uncertainty and to deal with local supply load imbalance.
To explore flexibility resources management, a flexibility management strategy for each VM is declared as per the order shown in Table 5.
Because DESSs provide a much higher fast ramp rate than DGs and DRs, the forecast error, i.e., stochastic uncertainty, is first managed by DESS. If DESS storage is not enough, then DG power generation needs to be altered. Then, if the available capacities of DGs are not enough, a CL is further utilized.
The ratios between corresponding elements in the FA and UA of each VM are shown in Table 6, showing that VM 1 and VM 5 have the most adequate flexibility resources compared to other VMs. For VM 1, flexibility supply derives from its high penetration of dispatchable DGs, leading to an outstanding FSI. For VM 5, it has the lowest installed wind and among one of the highest numbers of DESS.
Each VM’s cohesive features are given in Table 7. In terms of FSI cohesion, a VM with positive cohesion intensity is viewed as more flexible than a combined case. It can be deduced that the relative flexibility supply in VM 1 and VM 5 is more adequate than the whole ADN, with a larger positive cohesive feature value, and these two VMs may support other VMs in dealing with uncertainty in the grid-connected mode. VM 4 has the least cohesive character of all VMs, due to its uncertainty caused by high wind turbine installation and relatively lower flexibility supply.
As observed from the results in Table 7, it is difficult to make all cohesions positive in the planning process. A reasonable balance of cohesion could be an interesting topic in further research.

5.4. Comparison with Referential Case

The cohesion of VM reduces boundary flow, which is an indicator that each VM is more self-sufficient. Compared with a previous case study in [5] that did not consider VM cohesion and flexibility sufficiency, as is shown in Table 8, which had a 1.2944 MW total boundary flow with the same system conditions, our proposed method provides lower total boundary flow at 0.9598 MW.
In this referential case, the RNA gain, i.e., RNA cohesion intensity, is 1.6962, due to RNA not being considered in the optimal planning objective. With our proposed method, the value is improved to 51.455, showing better cohesion in terms of RNA and self-sufficiency.
In comparison with the referential case, the operational cost also decreases by 15.41 USD/h due to the increased utilization of cheaper wind power. The power exchange between the main grid and the ADN also decreased from 0.7284 MW to 0.3608 MW, which means that self-sufficiency and cohesion in each partition of the VMs results in a more independent ADN overall.

5.5. VM Flexibility Resources

To further probe the efficiency of the proposed flexibility supply method, flexibility resources’ management in VM 6 are scrutinized based on the strategy in Table 5. In VM 6, two dispatchable DGs and three DESSs are optimally located, with one controllable load priorly built at bus 46. When VM 6 is working in an independent mode, it utilizes its own flexibility resources to deal with a priori forecast errors, following the order in Table 4. With different levels of total real-time error, the results are displayed in Figure 8.
When the total error is 50 kW, i.e., the real-time load exceeds planned generation by 50 kW, DG, DESS, and CL output are shown in the red bar, in which the DESS at bus 38 increases its output, while the DG output remains the same. If estimation error increases to over 400 kW, shown in the yellow and purple bar, then the DESS and DG are drained out at their maximum output. The CL then starts operating to deal with system imbalance to ensure self-sufficiency.

5.6. Flexibility Supply Indices and Installed Capacity Limit

For active planning, the installed capacity limit in Equation (24) is given by load forecast and averaging. The accuracy of this value has an effect on the optimization result. If this value is too low, then self-sufficiency will not be secured for all VMs. On the other hand, if this limit is too relaxed, then power generation may not be efficient due to excessive redundancy. Moreover, the feasibility needs to be taken into consideration when total installed capacity is too high.
A test on the relationship between the FSIs of VMs and total installed capacity limit was conducted, as shown in Figure 9. When the limit is relaxed to 6 MW, for VMs 2, 3, and 6, the FSI increases, and for VMs 1, 4, and 5, the FSI decreases. However, we can find that the FSI of the whole ADN increased significantly from 40 to 60. This situation is caused by the number of wind turbines and increased in VMs 1, 4, and 5.
If this constraint on total installed capacity is further relaxed to 8 MW, a similar increase happens in the ADN’s FSI, but the improvement is only marginal, with an increase of only 5. Individually, the FSIs of VMs 1, 4, and 5 increased from the 6 MW constraint scenario, whereas the FSIs of VMs 2, 3, and 6 slightly decreased.
The variation in the FSI shown in Figure 9 suggests that the increase in the total installed capacity limit has no significant and explicit effect on each VM’s FSI but is positively related with whole ADN’s FSI.
The variation in FSI with reference to the capacity limit is consistent with theory analysis. In this test case, the capacity limit represents the investment scale, and it is only beneficial if cost and flexibility supply are balanced under a reasonable investment. However, this issue has never been addressed in previous studies. As shown in the analysis above, our method and index for flexibility evaluation could be efficient and promising in dealing with this issue.

6. Discussion

In this section, the efficiency, running time, and qualitative comparisons are presented.

6.1. Comment on Execution of Proposed Method

The execution of the proposed active planning method takes 54 h and 12 min, which is acceptable in the planning stage of a power system. Compared with [38,39,40], where heuristic algorithms are utilized in the IEEE 69-bus system within minutes, the running time is still significantly longer. Still, when compared to Grey Wolf optimization (GWA) given in [41], the proposed bi-leveled GA is still faster than the GWA, which takes over 216 h for only 10 DGs.
The first and main reason for enhanced operational time is the determination of the FSI. In our proposed method, the FSI is calculated by MCS sampling, which takes many iterations for a flexibility assessment. The second reason is the bi-level optimization structure which, while accurately determining the power flow, delayed the algorithm. Finally, compared with the existing literature, the installed DG amount is larger, which is reported to have larger convergence than an algorithm allocating few DGs [40].

6.2. Comment on Various RES Inclusion

In this research, RESs are limited to wind turbines, but the proposed idea can be easily extended to other RESs, including photovoltaic power plants or micro-hydro sources.
For solar energy harvesting, rooftop PV panels can be adopted in a city setting, where the construction of DGs can be difficult. In the optimization process, the exact time in solar year, local latitude, and average shading factor should be considered for correctly quantifying the generation.
For micro-hydro power, the allocation is normally fixed with strict geographical restrictions. Two types of hydro power utilization methods can be adopted. The first type is water-powered turbines, extracting mechanical energy from water flow. The second type is a pumped storage hydropower system (PSH). The location is restricted as well, but PSH systems can serve as flexibility providers in ADNs.
Naturally, for wind power, the geographical difference is not negligible. Wind power is viewed as observable, but the urban environment causes interruptions compared with rural areas. In the city scenario, wind speed can be smaller than on a plain field of a rural setting, due to the turbulence of existing civil infrastructure. Based on adequate historical data on wind measurements and real civil structure modelling, the forecast of turbulence-influenced wind measurement can be more accurate. AI-based wind mapping systems, which are statistical methods based on big data technology, are promising for the assessment of wind turbulence [42]. For example, in [43], Higgins et al. proposed using an artificial neural network (ANN) to categorically predict urban wind speed based on different shapes of buildings. In [44], a dataset from SCADA is utilized for training the classification model of a wind turbulence model.

6.3. Limitations and Future Extension

One of the limits of this research is the lack of considering geographical differences in the optimization process. Though the impedance between buses can mean the geodesic length between nodes, the specific consideration of nodes’ existing infrastructure is not given. For future extensions, each node’s available building footprint can be considered as a constraint in optimization. For example, some nodes cannot accommodate large DGs and wind turbines, since they are located in a developed city area or have other limitations in building new distributed energy resources.
Another limit is in the determination of a VM boundary. The boundary is determined before the optimization process, during which it remains static. This neglects the effect of potentially allocated DERs in branch weight. In the next step, our research will probe this effect and extend this work to a more accurate scale of spatial differences in ADNs.
Another limit is the program’s running time. Even though in a realistic planning setting, there is no issue of urgency, it is believed that simplification and better algorithmic structure design will decrease the execution time, especially in flexibility supply assessment in MCS.

7. Conclusions

To conclude, this paper proposed an innovative framework including active planning, active management, and active defense for research on ADNs. Active planning has been implemented for virtual microgrids with optimal self-sufficiency and cohesion. Cohesion is a novel concept first defined in this paper. Furthermore, the meaning of self-sufficiency has been revised by considering the balance between flexibility and uncertainty, which could be quantified by a novel method based on Monte Carlo. The case study has proven that this active planning can significantly improve the capabilities of ADNs in management and defense. Compared with a referential case under the same partition of the IEEE 69-bus bar system with no consideration of ADN flexibility, this case has shown a 34.68% decrease in operational cost, a 25.85% decrease in boundary flow, and a 50.47% decrease in main grid power, indicating a self-sufficiency increase in VMs. Moreover, the CI of the FSI and RNA in the proposed case is significantly higher than the referential case.
The understanding of ADNs following the new framework could help to consider ADNs from a more comprehensive perspective and clearly identify the influence from planning to management and defense. To upgrade large-scale CDNs to ADNs, the construction of VMs could be a promising solution. However, the idea of active planning could even be extended to other methodologies in ADN construction without VMs. The quantification method to evaluate flexibility supply balance could also contribute to other planning issues in power systems. In future research, existing geographical and civil structure could be included by adding proper constraints. Also, the spatial difference will be taken into more consideration in determining the partitioning and configuration of ADNs.

Author Contributions

Conceptualization, F.X.; Methodology, L.P., S.L., L.J. and B.H.; Software, L.P.; Validation, L.P.; Formal analysis, L.P., F.X., S.L., L.J., B.H. and X.X.; Investigation, F.X., S.L., L.J. and X.X.; Resources, F.X.; Writing—original draft, L.P.; Writing—review & editing, F.X.; Supervision, F.X.; Project administration, F.X. All authors have read and agreed to the published version of the manuscript.

Funding

This work was partially supported by the XJTLU Research Development Fund (RDF-18-01-04) and partially supported by the XJTLU AI University Research Centre, Jiangsu Province Engineering Research Centre of Data Science and Cognitive Computation at XJTLU and SIP AI innovation platform (YZCXPT2022103).

Data Availability Statement

The data that support the findings of this study are available from the corresponding author upon reasonable request.

Conflicts of Interest

The authors declare no conflict of interest.

Appendix A

The load situation of Monte Carlo simulations in the optimization process is shown below in Figure A1. The load level is the percentage of maximum load in the IEEE 69-bus system.
Figure A1. Load profiles used in MCS sampling.
Figure A1. Load profiles used in MCS sampling.
Energies 17 02391 g0a1

References

  1. D’Adamo, C.; Buchholz, B.; Abbey, C.; Khattabi, M.; Jupe, S.; Pilo, F. Development and Operation of Active Distribution Networks: Results of Cigre C6. 11 Working Group. In Proceedings of the 21st International Conference on Electricity Distribution, Frankfurt, Germany, 6–9 June 2011; pp. 6–9. [Google Scholar]
  2. Chowdhury, S.; Chowdhury, S.P.; Crossley, P. Microgrids and Active Distribution Networks; The Institution of Engineering and Technology: London, UK, 2009; ISBN 9781849191029. [Google Scholar]
  3. Arefifar, S.A.; Mohamed, Y.A.R.I.; El-Fouly, T. Optimized Multiple Microgrid-Based Clustering of Active Distribution Systems Considering Communication and Control Requirements. IEEE Trans. Ind. Electron. 2015, 62, 711–723. [Google Scholar] [CrossRef]
  4. Arefifar, S.A.; Mohamed, Y.A.R.I.; El-Fouly, T.H.M. Supply-Adequacy-Based Optimal Construction of Microgrids in Smart Distribution Systems. IEEE Trans. Smart Grid 2012, 3, 1491–1502. [Google Scholar] [CrossRef]
  5. Xu, X.; Xue, F.; Wang, X.; Lu, S.; Jiang, L.; Gao, C. Upgrading Conventional Distribution Networks by Actively Planning Distributed Generation Based on Virtual Microgrids. IEEE Syst. J. 2020, 15, 2607–2618. [Google Scholar] [CrossRef]
  6. Nassar, M.E.; Salama, M.M.A. Adaptive Self-Adequate Microgrids Using Dynamic Boundaries. IEEE Trans. Smart Grid 2016, 7, 105–113. [Google Scholar] [CrossRef]
  7. Barani, M.; Aghaei, J.; Akbari, M.A.; Niknam, T.; Farahmand, H.; Korpas, M. Optimal Partitioning of Smart Distribution Systems into Supply-Sufficient Microgrids. IEEE Trans. Smart Grid 2019, 10, 2523–2533. [Google Scholar] [CrossRef]
  8. Oskouei, M.Z.; Mohammadi-Ivatloo, B.; Erdinc, O.; Erdinc, F.G. Optimal Allocation of Renewable Sources and Energy Storage Systems in Partitioned Power Networks to Create Supply-Sufficient Areas. IEEE Trans. Sustain. Energy 2021, 12, 999–1008. [Google Scholar] [CrossRef]
  9. Ma, J.; Silva, V.; Belhomme, R.R.; Kirschen, D.S.; Ochoa, L.F. Evaluating and Planning Flexibility in Sustainable Power Systems. IEEE Trans. Sustain. Energy 2013, 4, 200–209. [Google Scholar] [CrossRef]
  10. Bucher, M.A.; Chatzivasileiadis, S.; Andersson, G. Managing Flexibility in Multi-Area Power Systems. IEEE Trans. Power Syst. 2016, 31, 1218–1226. [Google Scholar] [CrossRef]
  11. Bucher, M.A.; Delikaraoglou, S.; Heussen, K.; Pinson, P.; Andersson, G. On Quantification of Flexibility in Power Systems. In Proceedings of the 2015 IEEE Eindhoven PowerTech, Eindhoven, The Netherlands, 29 June–2 July 2015. [Google Scholar] [CrossRef]
  12. Bertsch, J.; Growitsch, C.; Lorenczik, S.; Nagl, S. Flexibility Options in European Electricity Markets in High RES-E Scenarios Study on Behalf of the International Energy Agency (IEA); International Energy Agency (IEA): Paris, France, 2012; p. 108. [Google Scholar]
  13. Lannoye, E.; Flynn, D.; O’Malley, M. Evaluation of Power System Flexibility. IEEE Trans. Power Syst. 2012, 27, 922–931. [Google Scholar] [CrossRef]
  14. Ulbig, A.; Andersson, G. Analyzing Operational Flexibility of Electric Power Systems. Int. J. Electr. Power Energy Syst. 2015, 72, 155–164. [Google Scholar] [CrossRef]
  15. Yang, C.; Xie, L.; Tian, R.; Ma, Y.; Cui, J.; Wu, C.; Han, B.; Wu, Q.; Xue, F. Maximizing Wind Power Utilization Based on Optimal Transactive Energy Control. In Proceedings of the 2020 39th Chinese Control Conference (CCC), Shenyang, China, 27–29 July 2020; pp. 6123–6128. [Google Scholar] [CrossRef]
  16. Yang, C.; Xie, L.; Tian, R.; Ma, Y.; Cui, J.; Wang, X.; Han, B.; Xue, F. Aided Decision-Making in Transactive Energy Control for Wind Power Accommodation. In Proceedings of the 2020 12th IEEE PES Asia-Pacific Power and Energy Engineering Conference (APPEEC), Nanjing, China, 20–23 September 2020. [Google Scholar] [CrossRef]
  17. Gonzalez, R.M.; Wattjes, F.D.; Gibescu, M.; Vermeiden, W.; Slootweg, J.G.; Kling, W.L. Applied Internet of Things Architecture to Unlock the Value of Smart Microgrids. IEEE Internet Things J. 2018, 5, 5326–5336. [Google Scholar] [CrossRef]
  18. Lei, L.; Tan, Y.; Dahlenburg, G.; Xiang, W.; Zheng, K. Dynamic Energy Dispatch Based on Deep Reinforcement Learning in IoT-Driven Smart Isolated Microgrids. IEEE Internet Things J. 2021, 8, 7938–7953. [Google Scholar] [CrossRef]
  19. Li, R.; Wang, W.; Xia, M. Cooperative Planning of Active Distribution System with Renewable Energy Sources and Energy Storage Systems. IEEE Access 2017, 6, 5916–5926. [Google Scholar] [CrossRef]
  20. Khan, M.H.; Ulasyar, A.; Khattak, A. Optimal Sizing and Allocation of Distributed Generation in the Radial Power Distribution System Using Honey Badger Algorithm. Energies 2022, 15, 5891. [Google Scholar] [CrossRef]
  21. Cetkovic, D.; Komen, V. Optimal Distributed Generation and Capacitor Bank Allocation and Sizing at Two Voltage Levels. IEEE Syst. J. 2023, 17, 5831–5841. [Google Scholar] [CrossRef]
  22. Ali, A.; Keerio, M.U.; Laghari, J.A. Optimal Site and Size of Distributed Generation Allocation in Radial Distribution Network Using Multi-Objective Optimization. J. Mod. Power Syst. Clean Energy 2021, 9, 404–415. [Google Scholar] [CrossRef]
  23. Kirthiga, M.V.; Daniel, S.A.; Gurunathan, S. A Methodology for Transforming an Existing Distribution Network into a Sustainable Autonomous Micro-Grid. IEEE Trans. Sustain. Energy 2013, 4, 31–41. [Google Scholar] [CrossRef]
  24. Latora, V.; Marchiori, M. Efficient Behavior of Small-World Networks. Phys. Rev. Lett. 2001, 87, 198701. [Google Scholar] [CrossRef] [PubMed]
  25. Arianos, S.; Bompard, E.; Carbone, A.; Xue, F. Power Grid Vulnerability: A Complex Network Approach. Chaos 2009, 19, 013119. [Google Scholar] [CrossRef]
  26. Glover, J.D.; Sarma, S.M.; Overbye, T.J. Power System Analysis and Design, 5th ed.; Cengage Learning: Stamford, CT, USA, 2012; ISBN 978-1-111-42577-7. [Google Scholar]
  27. Heggarty, T.; Bourmaud, J.-Y.; Girard, R.; Kariniotakis, G. Quantifying Power System Flexibility Provision. Appl. Energy 2020, 279, 115852. [Google Scholar] [CrossRef]
  28. Lannoye, E.; Flynn, D.; O’Malley, M. Transmission, Variable Generation, and Power System Flexibility. IEEE Trans. Power Syst. 2015, 30, 57–66. [Google Scholar] [CrossRef]
  29. Makarov, Y.V.; Loutan, C.; Ma, J.; de Mello, P. Operational Impacts of Wind Generation on California Power Systems. IEEE Trans. Power Syst. 2009, 24, 1039–1050. [Google Scholar] [CrossRef]
  30. Zhao, L.; Zhang, W.; Hao, H.; Kalsi, K. A Geometric Approach to Aggregate Flexibility Modeling of Thermostatically Controlled Loads. IEEE Trans. Power Syst. 2017, 32, 4721–4731. [Google Scholar] [CrossRef]
  31. Hodge, B.M.; Lew, D.; Milligan, M. Short-Term Load Forecast Error Distributions and Implications for Renewable Integration Studies. In Proceedings of the 2013 IEEE Green Technologies Conference (GreenTech), Denver, CO, USA, 4–5 April 2013; pp. 435–442. [Google Scholar] [CrossRef]
  32. Hodge, B.M.; Florita, A.; Orwig, K.; Lew, D.; Milligan, M.A. Comparison of Wind Power and Load Forecasting Error Distributions. In Proceedings of the 2012 World Renewable Energy Forum, Denver, CO, USA, 13–17 May 2012; Volume 3, pp. 1850–1857. [Google Scholar]
  33. Hodge, B.-M.; Lew, D.; Milligan, M.; Holttinen, H.; Sillanpää, S.; Gómez-Lázaro, E.; Scharff, R.; Söder, L.; Larsén, X.G.; Giebel, G.; et al. Wind Power Forecasting Error Distributions: An International Comparison. In Proceedings of the 11th International Workshop on Large-Scale Integration of Wind Power into Power Systems as well as on Transmission Networks for Offshore Wind Power Plants, Lisbon, Portugal, 13–15 November 2012; pp. 1–9. [Google Scholar]
  34. Huang, Y.; Xu, Q.; Jiang, X.; Zhang, T.; Liu, J. A Comprehensive Model for Wind Power Forecast Error and Its Application in Economic Analysis of Energy Storage Systems. J. Electr. Eng. Technol. 2018, 13, 2168–2177. [Google Scholar] [CrossRef]
  35. Xu, X.; Xue, F.; Lu, S.; Zhu, H.; Jiang, L.; Han, B. Structural and Hierarchical Partitioning of Virtual Microgrids in Power Distribution Network. IEEE Syst. J. 2019, 13, 823–832. [Google Scholar] [CrossRef]
  36. Boyd, S.; Vandenberghe, L. Convex Optimization; Cambridge Unicersity Press: Cambridge, UK, 2004. [Google Scholar]
  37. Billinton, R.; Allan, N.R. Appendix 1. In Reliability Assessment of Large Electric Power Systems; Springer: New York, NY, USA, 1979; pp. 233–292. [Google Scholar]
  38. Baran, M.E.; Wu, F.F. Optimal Capacitor Placement on Radial Distribution Systems. IEEE Trans. Power Deliv. 1989, 4, 725–734. [Google Scholar] [CrossRef]
  39. Shadman Abid, M.; Apon, H.J.; Morshed, K.A.; Ahmed, A. Optimal Planning of Multiple Renewable Energy-Integrated Distribution System With Uncertainties Using Artificial Hummingbird Algorithm. IEEE Access 2022, 10, 40716–40730. [Google Scholar] [CrossRef]
  40. Roy, K.; Bansal, S.K.; Bansal, R.C. Performance Enhancement of Radial Distribution System with Optimal DG Allocation. Int. J. Model. Simul. 2023, 1–19. [Google Scholar] [CrossRef]
  41. Purlu, M.; Turkay, B.E. Optimal Allocation of Renewable Distributed Generations Using Heuristic Methods to Minimize Annual Energy Losses and Voltage Deviation Index. IEEE Access 2022, 10, 21455–21474. [Google Scholar] [CrossRef]
  42. Reja, R.K.; Amin, R.; Tasneem, Z.; Ali, M.F.; Islam, M.R.; Saha, D.K.; Badal, F.R.; Ahamed, M.H.; Moyeen, S.I.; Das, S.K. A Review of the Evaluation of Urban Wind Resources: Challenges and Perspectives. Energy Build. 2022, 257, 111781. [Google Scholar] [CrossRef]
  43. Higgins, S.; Stathopoulos, T. Application of Artificial Intelligence to Urban Wind Energy. Build. Environ. 2021, 197, 107848. [Google Scholar] [CrossRef]
  44. Liu, J.H.; Chen, J.C.; Corbita, N.T. Analysis and Comparison of Turbulence Models on Wind Turbine Performance Using SCADA Data and Machine Learning Technique. Cogent Eng. 2023, 10, 2167345. [Google Scholar] [CrossRef]
Figure 1. A research framework for active planning, active management, and active defense based on VMs.
Figure 1. A research framework for active planning, active management, and active defense based on VMs.
Energies 17 02391 g001
Figure 2. Schematic for cohesive subsystems. (a) Cohesive System Partition; (b) Non-Cohesive System.
Figure 2. Schematic for cohesive subsystems. (a) Cohesive System Partition; (b) Non-Cohesive System.
Energies 17 02391 g002
Figure 3. Calculation of flexibility supply index.
Figure 3. Calculation of flexibility supply index.
Energies 17 02391 g003
Figure 4. Flow chart of proposed active planning method.
Figure 4. Flow chart of proposed active planning method.
Energies 17 02391 g004
Figure 5. Pareto Front of proposed optimization results.
Figure 5. Pareto Front of proposed optimization results.
Energies 17 02391 g005
Figure 6. Installed DG configuration on each bus.
Figure 6. Installed DG configuration on each bus.
Energies 17 02391 g006
Figure 7. DG and DESS allocation at optimal planning knee point.
Figure 7. DG and DESS allocation at optimal planning knee point.
Energies 17 02391 g007
Figure 8. Flexible supply resources’ behavior in VM 6.
Figure 8. Flexible supply resources’ behavior in VM 6.
Energies 17 02391 g008
Figure 9. FSIs of VMs and whole ADN over three different installed capacity limits.
Figure 9. FSIs of VMs and whole ADN over three different installed capacity limits.
Energies 17 02391 g009
Table 1. DESS flexibility quantification.
Table 1. DESS flexibility quantification.
DESS SoC SituationUpward FlexibilityDownward Flexibility
( S o C m i n , S o C m i n + P d c T E m ] [ E m S o C , E m S o C T , R R d c ] [ P c T , P c , R R c ]
( S o C m i n + P d c T E m , S o C m a x P c T E m ] [ P d c T , P d c , R R d c ] [ P c T , P c , R R c ]
( S o C m a x P c T E m , S o C m a x ] [ P d c T , P d c , R R d c ] [ E m S o C m a x S o C , E m S o C m a x S o C T , R R c ]
Table 2. Dispatchable DG flexibility quantification.
Table 2. Dispatchable DG flexibility quantification.
Dispatchable DG OutputUpward FlexibilityDownward Flexibility
P g = P r a t e [ 0 , 0 , 0 ] [ P r a t e T , P r a t e , R R g ]
0 < P g < P r a t e [ ( P r a t e P g ) T , P r a t e P g , R R g ] [ P g T , P g , R R g ]
P g = 0 [ P r a t e T , P r a t e , R R g ] 0 , 0 , 0
Table 3. Weibull distribution parameters in Liverpool, U.K., over four seasons.
Table 3. Weibull distribution parameters in Liverpool, U.K., over four seasons.
Seasons A k
Spring7.09 m/s1.83
Summer8.35 m/s2.27
Autumn9.93 m/s3.00
Winter7.46 m/s2.07
Table 4. Constraints and real values in bi-level optimization results.
Table 4. Constraints and real values in bi-level optimization results.
ConstraintsLimitReal Value
Voltage Maximum Level1.1 p.u.1.003 p.u.
Voltage Lowest Level0.9 p.u.0.982 p.u.
VMs Critical CF Percentage for Load Coverage
(Listed from VM 1 to VM 6)
[20%, 5%, 10%, 10%, 10%, 10%][70.51%, 83.94%, 106%, 135%, 327%, 123%]
Lowest Level of FSI125.56
Installed DESS Capacity Limit C D E S S , m a x 1 MW0.75 MW
Installed DG Capacity Limit C D G ,   m a x 4 MW4 MW
Table 5. Flexibility resource utilization order for each VM.
Table 5. Flexibility resource utilization order for each VM.
PriorityFlexibility SourceAction
1DESSDESS charging/discharging
2DGDispatchable DG output variation
3CLCut peak load with incentive
Table 6. Flexibility supply array of VMs (Rr, ramp rate; P, power; E, energy).
Table 6. Flexibility supply array of VMs (Rr, ramp rate; P, power; E, energy).
Rr+Rr−P+P−E+E−FSI
VM 179.1390.448.5019.198.0320.31123.93
VM 243.3568.274.0720.614.5920.7886.22
VM 359.9264.206.418.966.278.9789.18
VM 418.3017.422.181.632.241.6525.56
VM 5135.54135.5520.4312.4521.3412.36194.74
VM 626.4623.354.252.174.242.9835.98
Table 7. Cohesion features of VMs and ADN FSI.
Table 7. Cohesion features of VMs and ADN FSI.
VM Number123456
Cohesive Feature59.9322.2225.18−38.43130.74−28.01
FSI of ADN63.99
Table 8. Comparison between proposed RNA cohesive case and referential case.
Table 8. Comparison between proposed RNA cohesive case and referential case.
Operational Cost (USD/h)RNA Cohesion IntensityTotal Boundary Flow (MW)Active Power from Main Grid (MW)
Proposed Method29.0351.4550.95980.3608
Referential Case44.441.69621.29440.7284
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Piao, L.; Xue, F.; Lu, S.; Jiang, L.; Han, B.; Xu, X. Active Planning for Virtual Microgrids with Demand-Side and Distributed Energy Resources. Energies 2024, 17, 2391. https://doi.org/10.3390/en17102391

AMA Style

Piao L, Xue F, Lu S, Jiang L, Han B, Xu X. Active Planning for Virtual Microgrids with Demand-Side and Distributed Energy Resources. Energies. 2024; 17(10):2391. https://doi.org/10.3390/en17102391

Chicago/Turabian Style

Piao, Lechuan, Fei Xue, Shaofeng Lu, Lin Jiang, Bing Han, and Xu Xu. 2024. "Active Planning for Virtual Microgrids with Demand-Side and Distributed Energy Resources" Energies 17, no. 10: 2391. https://doi.org/10.3390/en17102391

APA Style

Piao, L., Xue, F., Lu, S., Jiang, L., Han, B., & Xu, X. (2024). Active Planning for Virtual Microgrids with Demand-Side and Distributed Energy Resources. Energies, 17(10), 2391. https://doi.org/10.3390/en17102391

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop