Next Article in Journal
The Current State of the Art in Research on Predictive Maintenance in Smart Grid Distribution Network: Fault’s Types, Causes, and Prediction Methods—A Systematic Review
Next Article in Special Issue
A Modified Multiple-Mixing-Cell Method with Sub-Cells for MMP Determinations
Previous Article in Journal
Split Cantilever Multi-Resonant Piezoelectric Energy Harvester for Low-Frequency Application
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Technical and Economic Evaluation of CO2 Capture and Reinjection Process in the CO2 EOR and Storage Project of Xinjiang Oilfield

1
School of Petroleum Engineering, China University of Petroleum (East China), Qingdao 266580, China
2
Key Laboratory of Unconventional Oil & Gas Development, China University of Petroleum (East China), Ministry of Education, Qingdao 266580, China
3
Institute of Engineering and Technology, Xinjiang Oilfield Company, Karamay 834000, China
*
Author to whom correspondence should be addressed.
Energies 2021, 14(16), 5076; https://doi.org/10.3390/en14165076
Submission received: 20 July 2021 / Revised: 15 August 2021 / Accepted: 16 August 2021 / Published: 18 August 2021
(This article belongs to the Special Issue CO2 Enhanced Oil Recovery and Carbon Sequestration)

Abstract

:
CO2 capture and reinjection process (CCRP) can reduce the used CO2 amount and improve the CO2 storage efficiency in CO2 EOR projects. To select the best CCRP is an important aspect. Based on the involved equipment units of the CCRP, a novel techno-economic model of CCRP for produced gas in CO2 EOR and storage project was established. Five kinds of CO2 capture processes are covered, including the chemical absorption using amine solution (MDEA), pressure swing adsorption (PSA), low-temperature fractionation (LTF), membrane separation (MS), and direct reinjection mixed with purchased CO2 (DRM). The evaluation indicators of CCRP such as the cost, energy consumption, and CO2 capture efficiency and purity can be calculated. Taking the pilot project of CO2 EOR and storage in XinJiang oilfield China as an example, a sensitivity evaluation of CCRP was conducted based on the assumed gas production scale and the predicted yearly gas production. Finally, the DRM process was selected as the main CCRP associated with the PSA process as an assistant option. The established model of CCRP can be a useful tool to optimize the CO2 recycling process and assess the CO2 emission reduction performance of the CCUS project.

1. Introduction

CO2 capture and storage (CCS) has been an effective measure to reduce CO2 emissions into the atmosphere. Injecting CO2 into oil reservoirs not only can store CO2 underground, but also can achieve EOR (enhanced oil recovery). However, field experiences show that only less than 50% of the injected CO2 can be stored if no recycling of the produced CO2 is considered. A CO2 capture and reinjection process (CCRP) should be taken to reduce the purchased CO2 and increase the CO2 storage efficiency [1]. In the United States and Canada, there have been a large number of CO2 EOR and storage projects, such as the projects in Weyburn, Rangely, and Kelly-Snyder oil fields [2]. These projects have extensive sources of CO2, which are captured from natural gas reservoirs or coal gasification plants, transported, and injected in a supercritical state on a large scale. In the earlier days, there were cases using membrane separation (MS) and chemical absorption (CA) methods to capture the CO2 produced in wells [3,4,5,6]. At present, direct reinjection mixed with the necessary pure CO2 (DRM) to improve the purity of injected gas is commonly adopted especially in the mid-late stage of the CO2 EOR and storage project [7]. In China, some CO2 EOR projects have also been conducted, but most of them are on a small scale using liquid CO2 purchased from chemical plants [8,9]. Pressure swing adsorption (PSA) and low-temperature fractionation (LTF) processes are often used to capture CO2 for recycling. In recent years, as more and more natural CO2 gas reservoirs are discovered in China, the injection scale of CO2 in oil reservoirs has increased gradually [10,11,12]. How to optimize a feasible CCRP is becoming more and more important, especially in the context that China is trying to be carbon neutral in the future [13].
At present, many studies have been carried out in the design of CO2 capture and reinjection. Kwak et al. designed CO2 recovery plants for EOR application. Four types of CO2 recovery processes were assessed and a combination of amine, Selexol, and distillation processes were suggested for CO2 separation [14]. Zhou researched the CA-MDEA (chemical absorption-methyldiethanolamine), LTF, and MS processes to separate CO2 from the produced gas in the CO2 EOR project in the Shengli oilfield, and the influences of different operating parameters on the system energy consumption were analyzed [15]. These design works are simulated by commercial softwares, such as Aspen Plus and Unisim, which are suitable for detailed industrial design. For a preliminary assessment, it needs more a convenient and fast-calculation techno-economic model for CO2 capture. In recent years, Ciferno et al. conducted an economic scoping study for CO2 capture from flue gas using aqueous ammonia [16]. Kleme et al. developed an overall techno-economic model to compare the CO2 capture and storage options in coal-fired power plants in the UK, and the cost estimation relationships for the chosen options were calculated [17]. Tuinier et al. evaluated the technical and economic features of a novel cryogenic post-combustion CO2 capture technology by comparison with the absorption and membrane technology [18]. Huang et al. surveyed the studies about the techno-economic analysis and optimization models for CCS [19]. Zhang assessed the techno-economic aspect of various CCS technologies in coal-fired power plants [20]. Zohrabian et al. calculated the techno-economic indicator of CO2 capture in integrated hydrogen and powerco-generation system [21]. Zhai et al. evaluated the technical and economic indicators of carbon capture and storage combined with powerco-generation system utilization of deep saline water in the coal chemical project in Ordos, China, and discussed the economic feasibility of the large-scale application of CCS in water-scarce areas [22]. Hu and Zhai performed a systematic economic assessment of the addition of amine-based CCS to coal-fired power plants in China [23]. Liu et al. used the analogy method to establish an economic evaluation model for the entire process of CO2 capture, utilization, and storage (CCUS), which is more dependent on the relevant economic and technical parameters of the reference target equipment [24]. Decardi-Nelson et al. proposed a novel model of considering the fluctuations in flue gas flow rate to analyze the economic performance in post-combustion CO2 capture plants [25]. Yun et al. conducted a techno-economic assessment of a novel solvent absorption-based CO2 capture process for coal-fired power plants [26].
In summary, at present, a lot of techno-economic evaluations and some model studies have been conducted, but most of them are related to CO2 capture from flue gas and only evaluate the fixed process. Few studies are about the flexible and simple technical and economic evaluation model of CO2 capture and reinjection in CO2 EOR and storage project. Compared with the flue gas, the composition of the produced gas in CO2 flooding is quite complex, and the evaluation of the reinjection process needs to be further considered. Besides, since the thermal power generation is major in China, the equivalent CO2 emissions caused by equipment energy consumption in CCRP cannot be ignored, but this is rarely studied.
In this paper, a novel techno-economic evaluation model of CCRP for produced gas in CO2 EOR and storage project was established based on the involved equipment units which can flexibly combine into any CCRPs. The evaluation indicators, including the cost, energy consumption, equivalent CO2 emissions, CO2 capture efficiency, and purity of CCRP, could be calculated. Then, the pilot project of CO2 EOR and storage in XinJiang oilfield China was taken as an example to optimize the CCRP, which can verify the feasibility of the model. The results can guide the design of the CO2 project in XinJiang oilfield.

2. Potential CCRPs in the CO2 EOR and Storage Project in XinJiang Oilfield

In many oil fields in the world, CO2 EOR and storage has been already a common technology, but this is still in its infancy in China. In XinJiang oilfield China, the pilot test of CO2 EOR and storage has been conducted, but the disposal of produced gas in CO2 flooding needs to be further studied.
XinJiang oilfield is located in the Junggar Basin of China. The blocks 530 and 53D in XinJiang oilfield are the potential sites for CO2 EOR and storage, which are about 35 km and 20 km away from XinJiang city, respectively, as shown in Figure 1. After a preliminary evaluation, the Kexia group of block 530 was selected as the target reservoir. This reservoir is a sandy conglomerate formation with a buried depth of 2400 m and a thickness of 18.6 m. The average porosity and permeability are 11.40% and 19.20 md, respectively. 79 wells were deployed in an inverted seven-spot pattern with a well spacing of 280 m × 395 m for water flooding. Due to the low permeability, hydraulic fracturing was conducted in wells. At present, there are 49 wells opened with a daily fluid of 253 t, a daily oil of 68 t, a water cut of 75.9%. 66.25 × 104 t oil has been produced, and the current oil recovery degree is 26.72%.
For the disposal of produced gas in CO2 flooding in block 530, many methods have been assessed. The schemes of direct reinjection mixed with pure CO2 (DRM), combustion and flue gas reinjection (CFGR), and CO2 capture and reinjection were analyzed. The study shows that: (1) the minimum miscible pressure between pure CO2 and crude oil at the reservoir temperature of 64 °C is 21.25 MPa. Under the original formation pressure of 24 Mpa, if the CO2 content in the produced gas mixed with necessary pure CO2 is greater than 90 mol%, it can also achieve miscible flooding; (2) if the produced gas is used for combustion in a heating furnace or a gas turbine, its calorific value should be larger than 584 KJ/mol, and the CO2 content in the produced gas cannot be higher than 40 mol%, besides, the flue gas produced by combustion can cause severe corrosion and explosion risk during reinjection, hence, the CFGR scheme is unattractive; (3) to purify the CO2 in the produced gas for reinjection is a commonly used method to dispose of the produced gas, however, four types of CO2 capture processes have different applicable conditions, thus the CO2 capture process needs to be further evaluated and optimized according to the CO2 content and scale of the produced gas.
Therefore, based on the above analysis, five types of CCRPs were designed conceptually for the CO2 EOR and storage project in block 530, namely the PSA, MS, LTF, CA-MDEA capture process, and DRM process. Overall, CCRP can be divided into the following three modules: product gas treatment module, carbon capture module, and injection module, and the carbon module is the key difference between the above five types of CCRPs. Hence, taking the PSA capture process as an example (Figure 2a), the detailed capture process is explained: at first, the produced gas is separated from the produced fluid by a three-phase separator, and the solid particles and liquid droplets in the gas are removed through the gas–liquid separator and cyclone separator; then, the produced gas is compressed and pass through the molecular sieve for deep dehydration, and further, the high-purity CO2 is captured from the produced gas using the PSA system; finally, the captured CO2 is reinjected back to the oil reservoir at 20 MPa and 40 °C by compressors. For the MS and CA-MDEA processes, they have the similar CCRPs to that of the PSA process except for the CO2 capture system, while the CO2 captured in the LTF process should be injected by booster pump at a liquid state under the condition of 20MPa and −20 °C [27,28,29]. When the DRM process is adopted (Figure 2b), the produced gas can be reinjected directly after being pretreated. If necessary, before reinjection, the produced gas should be mixed with pure CO2 to reach the required gas amount and CO2 purity.
According to the function of each module, some necessary simplifications were carried out to unify the five types of CCRPs into one process for flexible technical and economic evaluation, as shown in Figure 3. In this simplified process, the main equipment units are gas–liquid separator, molecular sieve, compressor, boost pump, and carbon capture module. Among them, the gas–liquid separator and molecular sieve are units for dust removal and dehydration, compressor and boost pump are used to transport and inject liquid or gas CO2, and carbon capture module is the critical unit for capture CO2. Since the produced gas is processed on-site, the pipeline is not considered in this simplified process. The simplified process corresponding to each CCRP is shown in Table 1.

3. Establishment of Technical and Economic Evaluation Model of CCRP

To be used to flexibly calculate the process parameters, cost, energy consumption, and CO2 capture efficiency for different CCRPs, the indicator calculation model for each possible involved equipment unit was established. Based on the equipment units, the indicators of the entire CCRP can be obtained.

3.1. Calculation Method of Capital Cost

Based on the main technical parameters of each equipment unit, the capital cost and the power can be estimated [30]. The main power/energy consumption units in CCRP include compressor, booster pump, and carbon capture module. For the no energy consumption units such as the gas–liquid separator and molecular sieve, their capital costs can be estimated by the analogy method.

3.1.1. Gas–Liquid Separator and Molecular Sieve

In CCRPs, both gas–liquid separator and molecular sieve have extremely low energy consumption in the process of dust removal and dehydration for produced gas, thus the analogy method is used to obtain their capital costs. According to the scale of the disposal gas, the capital cost can be calculated based on the following empirical formula [31]:
C sep = α sep 1 × ( M train 10 5 ) α sep 2
C mol = α mol 1 × ( M train 10 5 ) α mol 2
where Csep is the capital cost of gas–liquid separator, US$; Mtrain is the mass flow rate of disposal gas, t/d; Cmol is the capital cost of molecular sieve, US$; αsep1 and αsep2 are the cost coefficients of gas–liquid separator, taking 11 US$ and 0.6, respectively; αmol1 and αmol2 are the cost coefficients of molecular sieve cost, taking 19 US$ and 0.6, respectively. The above cost coefficients are obtained based on the capital cost of the gas–liquid separator and molecular sieve in the Chinese oilfield [13,32,33].

3.1.2. Compressor

In oil fields, compressors and booster pumps are the most used equipment to increase fluid pressure. Compressors are suitable for CO2 in gas and supercritical state, while pumps are suitable for liquid CO2 or high-dense CO2. For the capital cost of compressors, it can be estimated according to the CO2 flow rate and the ratio of gas pressures at the outlet and inlet of the compressor. For the estimation of the compressor power, the physical properties of CO2 gas and the multi-stage compression process with the optimal compression ratio for each stage should be considered.
(1) For the capital cost of the compressor [34],
C comp = m train N train [ ( α comp 1 ( m train ) α comp 2 + α comp 3 ( m train ) α comp 4 ln ( P out comp P in comp ) ) ]
m train = ( 1000 × m CO 2 ) ( 24 × 3600 × N train )
where Ccomp is the total capital cost of compressor, US$; mtrain is the mass flow rate of CO2 gas in each compressor unit, kg/s; Ntrain is the number of parallel compressors, dimensionless; mCO2 is the CO2 mass flow rate, t/d; Pin-comp is the inlet pressure of compressor, MPa; Pout-comp is the outlet pressure of compressor, MPa; αcomp1, αcomp2, αcomp3 and αcomp4 are the cost coefficients of compressor, taking 0.12 × 106 US$·kg−1·s, −0.71, 1.32 × 106 US$·kg−1·s and −0.60, respectively, which are converted from into US$ at the current exchange rate [34].
(2) For the compressor power [35],
W comp = ( 1000 24 × 3600 ) ( m CO 2 Z s RT in comp M CO 2 gas η comp ) ( k s k s 1 ) [ ( CR ) k s 1 k s 1 ]
CR = ( P out comp P in comp ) 1 N stage
where Wcomp is the compressor power, kW; Zs is the average compression factor of CO2 at each stage, dimensionless; Tin-comp is the inlet temperature of compressor, K; R is the universal gas constant, 8.314 kJ/(kmol·K); MCO2gas is the molar mass of CO2 gas, if the CO2 purity of gas is 100%, MCO2gas = 44.01 kg/kmol; ηcomp is the compressor efficiency, 0.75 is often used; ks is the average heat capacity ratio of CO2 at each stage, 1.391 is often used; CR is the optimal compression ratio, 2.4–3.0 is often used; Nstage is the number of compression stages. The maximum power of a single compressor was assumed to be 40MW. If the required compression power is greater than 40 MW, several parallel compressors will be used, and the Ntrain is Wcomp/40.

3.1.3. Booster Pump

In the CCRP, after being purified and liquefied, the liquid CO2 can be transported and injected into the subsequent processes using booster pumps. The capital cost of booster pumps mainly depends on the pump power, while the pump power is selected based on the flow rate and pressures of CO2 at the inlet and outlet of the pump [36].
(1) For the capital cost of the pump,
C pump = α pump 1 × ( W pump 1000 ) + α pump 2
(2) For the pump power,
W pump = ( 1000 × 10 24 × 36 ) [ m CO 2 ( P out pump P in pump ) ρ l CO 2 η pump ]
where Cpump is the capital cost of booster pump, US$; Wpump is the booster pump power, kW; Pout-pump is the outlet pressure of booster pump, MPa; Pin-pump is the inlet pressure of booster pump, MPa; ρl-CO2 is the density of liquid CO2, 1177 kg/m3; ηpump is the efficiency of booster pump, 0.75 was assumed; αpump1 and αpump2 are the cost coefficients of pump, taking 1.14 × 106 US$·W−1 and 0.07 × 106 US$, respectively.

3.1.4. Carbon Capture Module

The commonly used CO2 capture modules include pressure swing adsorption (PSA), membrane separation (MS), low-temperature fractionation (LTF), and chemical absorption (CA-MDEA).
(1) Pressure swing adsorption (PSA)
In the PSA module, according to the difference of adsorption characteristics of different kinds of gases in physical adsorbent with pressure, specific gas (e.g., CO2) will be absorbed and desorbed through periodic pressure changes to achieve the purpose of gas separation and purification [37]. The capital cost of the PSA CO2 capture module is mainly composed of three parts: the capital cost of adsorption towers, the purchase cost of adsorbent, and the capital cost of the compressor.
First, the mass of CO2 adsorbent for PSA can be calculated based on the gas production, CO2 content in produced gas, and the adsorption capacity of the adsorbent [38].
W PSA ad = Q PSA g × t PSA ad × y PSA CO 2 / Δ q P S A × n PSA bed
where WPSA-ad is the mass of adsorbent in PSA module, kg; QPSA-g is the flow rate of the feed gas in the adsorption tower of PSA module, m3/s; tPSA-ad is the adsorption time of single bed operation of the tower in PSA module, s; yPSA-CO2 is the CO2 mole fraction of the feed gas in PSA module, dimensionless; ΔqPSA is the adsorption capacity in PSA module which depends on the adsorbent, for silica 0.35–0.50 kg/kg is taken, for activated carbon 0.40–0.50 kg/kg is taken, and for molecular sieves, 0.22–0.26 kg/kg is taken [39]; nPSA-bed is the number of beds for continuous adsorption in a single tower in PSA module, dimensionless.
Then, according to the mass of the adsorbent and the design requirements of the adsorption tower, the height, diameter, and number of the adsorption towers can be calculated [40].
H P S A = W PSA ad n PSA tower ρ PSA ad v PSA g Q PSA g
D P S A = H P S A / ( 5 ~ 8 )
n PSA tower = W PSA ad ρ PSA ad 4 3.14 D PSA 2 H PSA
where HPSA is the height of the tower in PSA module, m; nPSA-tower is the number of towers in PSA module dimensionless; ρPSA-ad is the adsorbent density in PSA module, for silica 0.70–0.82 kg/m3 is taken, for activated carbon 0.45–0.50 kg/m3 is taken, and for molecular sieves, 0.61–0.67 kg/m3 is taken; vPSA-g is the gas flow speed in the tower, 0.05 m/s was assumed according to common design of CO2 absorption tower [41]; DPSA is the diameter of the tower in PSA module, m.
Finally, through the unit height capital cost of the tower and the sizes of the tower, the capital cost of adsorption towers can be obtained [41].
C PSA tower = C PSA pc × H P S A × n PSA tower
log C PSA pc = α PSA 1 log D P S A + α PSA 2
where CPSA-tower is the capital cost of towers in PSA module, US$; CPSA-pc is the unit height capital cost of the tower in PSA module, US$/m; αPSA1 and αPSA2 are the cost coefficients of PSA module, taking 1.34 and 4.27, respectively.
CO2 adsorbent with excellent adsorption and desorption performance should be selected for PSA. The commonly used adsorbents can be classified into carbon-based adsorption materials (e.g., activated carbon) and zeolite adsorption materials (e.g., 13X molecular sieve). The 13X is often used because of its large pore volume, high adsorption capacity, and high separation coefficient. Hence, the purchase cost of adsorbent can be determined as follows [39]:
C PSA ad = P PSA ad × W PSA ad
where CPSA-ad is the purchase cost of adsorbent in PSA module, US$; PPSA-ad is the unit cost of adsorbent, for silica 1.58 US$/kg is taken, for activated carbon 0.47 US$/kg is taken, and for molecular sieves, 1.58 US$/kg is taken.
Based on the above, the capital cost of the PSA module can be calculated.
C PSA = C PSA tower + C PSA ad + C comp
where CPSA is the capital cost of the PSA module, US$.
The power consumption in the PSA module mainly occurs when the feed gas is compressed to meet the adsorption pressure in towers, thus the power of the PSA module is equal to the power of the compressor.
W PSA = W comp
where WPSA is the power of the PSA module, kW.
It should be noted that if the pressure of feed gas is high enough which can meet the requirement of adsorption pressure in towers, the compression process can be neglected in the PSA module, no power consumption is considered.
(2) Membrane separation (MS)
In the MS module, the penetrability difference of each component in feed gas through the polymer membrane under a certain pressure is used to separate the CO2 from the hydrocarbon gas. The capital cost of the MS module mainly comes from the compressor and the MS device [42]. The capital cost of the MS device, which consists of membrane material and frame, is determined by the film type and film property. The components in feed gas can be divided into the high-speed group and the low-speed group according to their difference in permeation rate through the membrane. Hence, the film area can be estimated as follows [5]:
A m = Q MS p Y MS 1 R MS f ( P MS 2 ( Y MS F Y MS R ln ( Y MS F Y MS R ) ) P MS 1 Y MS 1 ) 100
where Am is the film area in MS module, m2; YMS-F is the mole fraction of high-speed group (CO2) in feed gas in MS module, dimensionless; YMS-R is the mole fraction of the high-speed group in the nonpenetrating gas in MS module, dimensionless; YMS-1 is the mole fraction of the high-speed group in the permeation gas in MS module, dimensionless; QMS-P is the flow rate of permeation gas in MS module, kmol/s; RMS-f is the weighted average permeation velocity of the high-speed group in MS module, m/s; PMS-1 is the total pressure on the low-pressure side of the membrane in MS module, bar; and PMS-2 is the total pressure on the high-pressure side of the membrane in MS module, bar.
The membranes used for CO2 separation are mainly made of high molecular polymers, such as polydimethylsiloxane, cellulose acetate, polyimide, polysulfone, polycarbonate, etc. Due to the high permeation speed and excellent separation effect, polyimide has been widely used in China, and its hollow fiber membrane module has a low cost, high loading density, and adaptability to high pressure, which is often selected. [43] Hence, based on the film area and type, the capital cost of MS device can be estimated using the equations as follows [42]:
C M = I m + I mf
I m = A m K m
I mf = ( A m α m 1 ) α m 2 K mf
where CM is the capital cost of MS device, US$; Im is the cost of membrane material in MS device, US$; Imf is the cost of membrane frame in MS device, US$; Km is the membrane material cost of unit film area, 4.73–18.93 US$/m2 for hollow fiber membrane module; Kmf is the membrane frame cost of unit film area, 315.46 US$/m2, the above MS device costs of unit film area are from the price survey in China; and αm1 and αm2 are the cost coefficients of MS module, taking 2000 and 0.7, respectively.
Hence, based on the above, the capital cost of the MS carbon capture module can be obtained.
C MS = C M + C comp
where CMS is the capital cost of MS module, US$.
Similarly, the power consumption of the MS module mainly occurs when the feed gas is needed to be compressed to form a high-enough permeation pressure difference on both sides of the membrane, so the power of the MS module is equal to the power of the compressor.
W MS = W comp
where WMS is the power of the MS module, kW.
(3) Low-temperature fractionation (LTF)
In the LTF module, the separation of CO2 from feed gas is realized based on the difference in boiling temperature of each component in the feed gas. The pressurization effect of the compressor and the cooling effect of the heat exchanger is utilized to achieve the gas liquefaction. For the heat exchanger, after the structure is determined, the technical and economic model of the heat exchanger can be established based on the heat exchange area [15]. The heat exchange area can be determined by the parameters in the operating environment of the heat exchanger. When the heat exchanger recovers waste heat, it also needs to consume some power to overcome the flowing resistance of fluid passing through the heat exchanger and the cooler. This power consumption is the operating cost of the equipment [44].
C hx = α hx 1 + α hx 2 A hx p α hx 3
A hx p = α hx 4 Q hx K hc Δ T m
Q hx = m hf C p Δ t hx
Δ T m = ( T HI T CO ) ( T HO T CI ) ln T HI T CO T HO T CI
W hx = A hx p · K hc · Δ t hx / 1000
where Chx is the capital cost of the heat exchanger, US$; Ahx-p is the actual heat exchange area in heat exchanger, m2; αhx1, αhx2 and αhx3 are the cost coefficients of heat exchanger, taking 9.41 × 104 US$, 1.13 × 103 US$ and 0.98, respectively; αhx4 is the coefficients obtained by unit conversion, 0.28; Qhx is the heat flow in heat exchanger, kJ/h; mhf is the mass flow rate of hot fluid in heat exchanger, kg/h; Cp is the specific heat capacity of fluid in heat exchanger in heat exchanger, kJ·kg−1·°C−1; Δthx is the temperature change of hot fluid in heat exchanger, °C; ΔTm is the logarithmic mean temperature changes of heat exchanger, °C; THI is the hot fluid temperature at the inlet of the heat exchanger, °C; THO is the hot fluid temperature at the outlet of the heat exchange, °C; TCI is the cold fluid temperature at the inlet of the heat exchanger, °C; TCO is the cold fluid temperature at the outlet of the heat exchanger, °C; Whx is the power of heat exchanger, kW; and Khc is the heat transfer coefficient between the hot fluid and the cold fluid, taking 1134 W/(m2·°C) (between liquid-phase fluids) or 279 W/(m2·°C) (between gas-phase fluids).
Hence, the capital cost of the LTF module is mainly composed of the capital costs of the compressor and heat exchanger [45]. Similarly, the power of LTF covers the powers of the compressor and heat exchanger.
C LTF = C comp + C hx
W LTF = W comp + W hx
where CLTF is the capital cost of LTF module, US$; WLTF is the power of LTF module, kW.
(4) Chemical absorption (CA-MDEA)
In the CA module, CO2 is captured from the feed gas by a chemical reaction between alkaline solution and CO2. CO2 is absorbed by the alkaline solution at a low temperature and desorbed at a high temperature. The capital cost of the chemical absorption module includes the capital costs of solvent towers, booster pumps, heat exchangers, and the purchase cost of chemical absorption solution [14]. MDEA (methyldiethanolamine) is the often used solvent for CO2 chemical absorption. Hence, the MDEA is taken as a typical example to establish the capital cost calculation model of CA.
The solvent towers mainly include the absorption tower and the desorption tower. For the absorption tower, firstly, the diameter of the tower can be determined according to feed gas flow; and then, the height of the tower can be estimated according to the tower diameter and CO2 absorption capacity of MDEA; finally, based on the cost of unit height tower, the capital cost of absorption tower can be obtained [40,46,47,48].
D CA ab = 4 V CA ab 3600 π v CA ab
H CA ab = m CA CO 2 / M CO 2 gas K Ga A CA t Δ P CA m l n ( Y CO 2 inab Y CO 2 outab )
A CA t = π D CA ab 2 4
log C CA ab = α ab 1 log D CA ab + α ab 2
C CA abt = C CA ab × H CA ab
where DCA-ab is the diameter of absorption tower in CA module, m; VCA-ab is the flow rate of feed gas in the absorption tower in the CA module, m3/h; vCA-ab is the gas flow velocity in the adsorption tower which should make sure that the CO2 in feed gas can fully combine with the MDEA solution, 0.722 m/s was used according to the common design for the chemical absorption tower [41]; HCA-ab is the cumulative height of absorption towers in the CA module, m; mCA-CO2 is the mass flow rate of CO2 gas in CA module, kg/h; KGa is the mass transfer coefficient, 20 kmol/(m3·h·atm) was taken from the calculation process of Zhang [46]; YCO2-inab is the CO2 content of inlet gas in the absorption tower, g/m3; YCO2-outab is the CO2 content of outlet gas in the absorption tower, g/m3; ACA-t is the cross-section area of absorption tower in CA module, m2; ∆PCA-m is the driving pressure difference, the default value is 0.026 atm at the oilfield site; CCA-ab is the cost of the unit height tower in the CA module, US$/m; CCA-abt is the capital cost of the absorption tower in the CA module, US$; and αab1 and αab2 are the cost coefficients of the absorption tower in the CA module, taking 1.34 and 4.27, respectively, based on the data from the Chinese oilfield [12,32].
Similarly, the capital cost of desorption tower can be calculated using the following formulas [46,47]:
D CA de = 4 V CA de 3600 π v CA de
N CA t = m CA CO 2 / M CO 2 gas / α de 1
log C CA de = α de 2 ( log D CA de ) 2 + α de 3 log D CA de + α de 4
C CA det = C CA de × N CA t
where DCA-de is the diameter of the desorption tower in CA module, m; VCA-de is the flow rate of feed gas in the desorption tower in the CA module, m3/h; vCA-de is the gas flow velocity in the desorption tower which should make sure that the CO2 can be effectively separated from the MDEA solution, 0.91 m/s was used according to the common design for chemical absorption tower [41]; NCA-t is the total number of theoretical plates in the desorption tower in the CA module, dimensionless; CCA-de is the tower cost of a single plate of the desorption towers in the CA module, US$; αde1 is the mole flow rate which can be supported by one plate based on the common design of the desorption tower, 6.96 kmol/h is used [41]; αde2, αde3 and αde4 are the cost coefficients of the desorption tower in the CA module, taking 0.56, 1.06 and 3.89, respectively, based on the data from Chinese oilfield [12,32]; and CCA-det is the capital cost of the desorption tower in the CA module, US$.
The purchase cost of the MDEA solution can be calculated according to the required circulation amount of MDEA solution, which can be estimated based on the CO2 absorption capacity of MDEA [48].
M MDEA = α MDEA × m CA CO 2 / M CO 2 gas
C s = M MDEA × C us
where MMDEA is the required circulation amount of the MDEA solution, t; Cs is the purchase cost of MEDA solution, US$; Cus is the unit cost of the MEDA solution, 2176.66 US$/t was referenced; and αMDEA is the circulation amount of the MDEA solution which can be used to absorb the unit mole flow rate of CO2 gas, based on the reaction mechanism between DMEA and CO2 and the common design of the CO2 absorption tower, 0.73 t·kmol−1·h, is taken [49].
Based on the above analysis, the capital cost of the MEDA carbon capture module can be obtained.
C CA = C CA abt + C CA det + C s + C pump + C hx
Then, the power of the MEDA module can be calculated as follows.
W CA = W pump + W hx
where CCA is the capital cost of CA module, US$; WCA is the power of CA module, kW.

3.2. Calculation Method of Running Cost

The running cost of each equipment unit mainly includes the maintenance cost and operating cost. Maintenance cost refers to the fees paid to maintain or restore the technical performance of the equipment. Operating cost is mainly the energy cost of the equipment, which is generally the electric charge calculated according to the equipment power. Hence, the running cost of the entire process can be obtained as follows.
O & M annual = ( C unit × M factor + W unit × 24 × 365 × F elec )
where O&Mannual is the annual running cost of CCRP, US$; Cunit is the capital cost of equipment unit, US$; Mfactor is the ratio of annual maintenance cost to total infrastructure cost, 0.05 is often used; Wunit is the power of equipment unit, kW; Felec is the electricity price, generally 0.08 US$/kWh is taken in China.

3.3. Calculation Method of CO2 Capture Parameters

In CCRP, the gas flow rate and CO2 content will change, especially before and after the carbon capture module. Due to the limit of capture purity, part of CO2 will be lost in the separated hydrocarbon gas. Moreover, China’s power generation is still dominated by thermal power using coal at present, thus the energy consumption of each equipment unit during operation is equivalent to an additional amount of CO2 emissions. Therefore, the concepts of CO2 flow, energy consumption equivalent CO2 emissions, and CO2 capture efficiency of basic equipment units were proposed.
As shown in Figure 4, taking the CO2 capture module as an example, the CO2 flow should satisfy the material balance when the CO2-contained gas flows through the capture equipment. If the gas flow rate and CO2 content at the inlet are defined to be Qin-gas and xin-CO2, respectively, then the pure CO2 gas flow rate at the inlet is Qin-CO2 = Qin-gas × xin-CO2. For the gas flow at the outlet, Qout-gas, it is divided into the CO2 gas flow Qout-CO2gas and the hydrocarbon gas flow Qout-CH4gas; if their CO2 and hydrocarbon gas purities are xout-CO2 and yout-CH4, respectively, then the captured pure CO2 gas flow rate is Qout-CO2 = Qout-CO2gas × xout-CO2, and the CO2 lost in hydrocarbon gas is Qout-CO2-loss = Qout-CH4gas × (1 − yout-CH4). Moreover, the additional CO2 emission released by coal-fired power generation due to energy consumption during capture is Qpower-CO2, then the CO2 capture efficiency of the capture module can be calculated to be η = (Qout-CO2 − Qpower-CO2)/Qin-CO2. Similarly, the CO2 flow variation and CO2 capture efficiency of other equipment units in CCRP can also be obtained, as shown in Table 2. Based on these equations, the indicators of the entire CCRP can be determined. For the CO2 capture and reinjection efficiency (CCRE) of the CCRP, it can be calculated based on the total Qpower-CO2, Qout-CO2, and Qin-CO2 of the process, or calculated by multiplying the CO2 capture efficiencies of all units in the process.
For the Qpower-CO2, it can be estimated based on the power of the equipment unit, coal consumption required for unit power generation, and the CO2 emission per unit coal by burning, as follows [50]:
Q power CO 2 = W unit × t u × M coal × E CO 2 / ρ CO 2
where Qpower-CO2 is the energy consumption equivalent CO2 emission of equipment unit, Sm3/d; tu is the unit time, h; Mcoal is the coal consumption required for unit power generation, 0.313 kg/kWh was taken; ECO2 is the CO2 emissions per unit coal by burning, generally 2.6 kg CO2/kg coal is used; tu is unit time, taking 24 h; and ρCO2 is the density of CO2 gas, taking 1.98 kg/m3.
For the gas capture purity, we have conducted a sensitivity simulation for different kinds of carbon capture modules using the software Aspen Hysys 2006. The composition of feed gas referred to the associated gas in Block 530 in XinJiang oilfield, which has 84.98% C1, 7.21% C2, 3.04% C3, 1.23% C4, 0.54% C5, 2.60% N2, and 0.4% CO2. By mixing CO2 with the associated gas, feed gases with different CO2 contents and at different flow rates were input in the simulation models for calculation. The results show that the capture purity of gas is mainly determined by the CO2 content in the feed gas. Hence, we regressed the relation equations of gas capture purity with CO2 content in feed gas for usage in our models to calculate the CO2 flow variation, as shown in Figure 5 and Table 3. It can be seen that as the CO2 content in feed gas increases, the CO2 capture purity of PSA, MS, LTF modules gradually increases, while the CO2 capture purity of the MDEA module is always high. When the CO2 content in the feed gas is larger than 75 mol%, all the CO2 capture purities of all capture modules can reach larger than 90 mol%. Overall, the ranking of CO2 capture purity is MDEA > PSA > MS > LTF. The CO2 capture purity of the LTF module is the lowest one, because a part of liquefied C2+ can mix into liquid CO2 and hardly be separated. On the other side, the purity of natural gas ranks in an order of MDEA >LTF> PSA > MS.

3.4. Calculation Method of Unit Cost

The CO2 capture and reinjection cost (CCRC) per unit volume of CO2 gas can be calculated by the annual cost divided by the annual captured CO2 gas. The annual cost includes two parts, namely the annual operating and maintenance cost, and the annual capital cost calculated by dividing the total capital cost equally over each year of the project [35]. The specific formulas are as follows. For comparison purposes, the unit CO2 cost is expressed by the cost per 500 sm3 CO2 gas which is about one ton pure CO2.
C l e v = C t c a / Q o u t CO 2 gas / 365 × 500
C t c a = C a n n u a l + O & M a n n u a l = C u n i t × C R F + O & M a n n u a l
where Clev is the CO2 capture and reinjection cost per 500 Sm3 CO2 gas, US$/500 Sm3; Ctca is the total annual cost of CCRP, US$; Cannual is the annual capital cost by dividing the total capital cost equally over each year of the project duration, US$; CRF is the discount factor, which can be calculated according to project duration and the interest rate, in this study, it is assumed that the project lasts for 15 years, and the interest rate is 12%, hence the CRF of 0.1827 was applied.

4. Evaluation of the CCRPs in the CO2 EOR and Storage Project in XinJiang Oilfield

4.1. Evaluation of the CCRPs Based on the Assumed Gas Production and CO2 Purity

A sensitivity evaluation on the CCRP of the CO2 EOR and storage project in XinJiang oilfield was conducted according to the possible gas production scale and CO2 purity. It was assumed that the project lasts for 15 years, the discount rate is 12%, and the gas is produced at a scale of (5–50) × 104 Sm3/d with a CO2 content varying in a range of 20–80 mol%. The unit cost, unit energy consumption, CCRE, and CO2 capture purity of different CCRPs (as shown in Table 3) were calculated using the established evaluation model for CCRP, and the results are shown in Figure 6.
The calculated unit cost of CO2 capture and unit cost of CO2 capture and reinjection are shown in Figure 6a,b respectively, where the former covers the cost of equipment from the produced gas to the CO2 capture system, while the latter further covers the cost of pressure boosting equipment for reinjection. It can be seen that both the unit capture cost and the unit capture and reinjection cost decrease with the increase of CO2 content and gas production. The cost of capture accounts for the vast majority of the cost of the whole CCRP. By comparing these unit costs, the applicable CO2 content of produced gas for different CCRPs can be obtained. The unit cost of the MDEA process is weakly sensitive to the CO2 content in the produced gas, and it is economical at a low CO2 content of 20–40 mol%. The unit cost of the SPA process is relatively low, and it has a large applicable CO2 content range of 20−80 mol%. The unit costs of MS and LTF processes are high, but decrease rapidly with CO2 content increase. These two CO2 capture processes are suitable for the conditions when the produced gas CO2 contents are larger than 50 mol% and 80 mol% respectively.
Figure 6c,d show the unit energy consumptions of different CCRPs. It can be seen that the unit energy consumption is mainly decided by the CO2 content in the produced gas. The higher the CO2 content, the smaller the unit energy consumption. Similarly, the CO2 capture process consumes most of the power of the whole CCRP. By comparison, the unit energy consumptions of SPA and MS processes are much lower than those of the other two. The unit energy consumption of the MDEA process is weakly affected by the CO2 content in the produced gas, while the unit energy consumption of the LTF process is the most sensitive to the CO2 content. When the CO2 content of produced gas is larger than 40–60mol%, with the CO2 liquefaction efficiency increase, the unit energy consumption of the LTF process will be lower than that of MDEA.
As shown in Figure 6e, the CCRE of the whole CCRP is also mainly affected by the CO2 content in the produced gas. The higher the CO2 content is, the higher the CCRE is. Among the four types of the CO2 capture process, the CCRE of the PSA process is the highest. The CCRE of the MS process is lower than that of the PSA process, but it increases quickly as the CO2 content in the produced gas increases. At a low CO2 content of 20–40 mol%, due to the low gas capture purity, a large part of CO2 will be lost in the captured natural gas, resulting in a low CCRE of the MS process, even lower than that of the MDEA process. Relatively, the CCRE of the LTF process is low due to the high energy consumption and low CO2 capture purity. At a low CO2 content, the CCRE of the LTF process can be as low as 30%, while when the CO2 content in the produced gas is larger than 60mol%, the CCRE of the LTF process can exceed that of the MDEA process. The CCRE of the MDEA process will be the lowest when the CO2 content in the produced gas is above 60mol%.
Figure 6f shows the purity of CO2 captured from the produced gas. The CO2 purities captured by the MDEA and PSA processes all exceed 90 mol% when the CO2 content in the produced gas is 20–80 mol%. However, for the MS and LTF processes, only when the CO2 contents in the produced gas are more than 50 mol% and 70 mol%, respectively, the CO2 capture purities can be larger than 90 mol%. The multi-stage membrane treatment can improve the CO2 purity, while the heavy components liquefied with CO2 are also conducive to miscible flooding.
When the produced gas is reinjected directly with necessary purchased pure CO2, the unit cost, unit energy consumption, and CCRE of the DRM process are shown in Figure 7. Due to the simple process of DRM, both the unit cost and unit energy consumption are much lower than those of other CCRPs. The CCRE of the DRM process can be up to 70–93%, also larger than that of any other CCRPs. The DRM process demonstrates a strong attraction. Moreover, the unit cost of the DRM process increases with CO2 content rise because compressing CO2 needs more energy than natural gas.

4.2. Evaluation of the CCRPs Based on the Designed CO2 Flooding Schemes

In order to optimize the CO2 EOR and storage scheme in block 530, four times of CO2 flooding were predicted by reservoir numerical simulation. In this part, five types of CCRPs are assessed and compared according to the predicted gas production.

4.2.1. CO2 Injection Schemes and Predicted Gas Production

The CO2 injection schemes and predicted gas productions in XinJiang oilfield are summarized in Table 4 and Figure 8. In the simulation of CO2 − EOR schemes, after CO2 is injected into the ground, it interacts with formation water and crude oil, causing the composition and properties of liquid phase to be changed. Part of the injected CO2 is dissolved in the oil underground and cannot be produced in gaseous form. CMG software was used to simulate the above process to obtain CO2 − EOR simulation cases. The four CO2 flooding schemes are marked as cases A, B, C, and D, respectively. The CO2 injection undergoes three stages: pressure build-up for 0.5 years, continuous gas injection for 4.5 years, and water-alternating-gas (WAG) injection for 10 years.
In four cases, the simulation results are various. (1) In case A, 139.93 × 104 t of CO2 will be injected with a primary storage efficiency of 61.38%, and about 41.60 × 104 t of crude oil will be produced out with a CO2–oil ratio of 3.36 tCO2/t oil. The maximum gas production rate is expected to be 10 × 104 Sm3/d, while the CO2 content in the produced gas will be maintained at 65–76 mol% after the CO2 breaks through in the production wells in the third year. (2) Case B has lower cumulative CO2 injection and cumulative oil production, only 26.04 × 104 t and 26.93 × 104 t, respectively. CO2 breakthrough of the production well occurs in the second year, and then the CO2 content in the produced gas will gradually rise to more than 80mol %. (3) In case C, 108.22 × 104 t of CO2 will be injected into 15 wells with a high storage efficiency of 79.85%, and 33.17 × 104 t of crude oil will be produced out with a relatively higher CO2–oil ratio of 3.26 tCO2/t oil. CO2 was produced in the first year, and the CO2 content in produced gas can close to 90mol% after 5 years. (4) Case D has a similar CO2 injection scale with case A, reaching 123.93 × 104 t, but has greater oil production of 49.49 t. CO2 breaks through in the second year, and the CO2 content can also be close to 90 mol %.
Overall, case A has the largest CO2 injection scale, while case D is the most attractive scheme because of the smallest CO2–oil ratio and the little smaller gas production with the higher CO2 content. For cases B and C, the CO2 injection and gas production are small. Although their primary storage efficiencies are relatively high (66.68% and 79.85%, respectively), less amount of crude oil will be produced than that of cases A and D.

4.2.2. Comparison Analysis of the Different CCRPs

(1) Comparison between the different CCRPs
The best CO2 injection scheme, case D, was taken as an example, and different CCRPs were compared and analyzed according to their technical and economic indicators calculated based on the predicted gas production of each year.
As shown in Figure 9a,b, as the CO2 content in the produced gas increases with production, the unit CO2 capture costs of different CCRPs decrease first and tend to be stable after a 5-year injection when the CO2 content exceeds 80mol%. The unit CO2 capture costs of PSA, MS, and LTF processes become close, varying in a range of 17.63–20.35 US$/500 Sm3CO2, while the unit CO2 capture cost of the MDEA process maintains at a high level of 28.46–31.17 US$/500 Sm3CO2. When the cost of the injection process is further involved, the unit costs of CCRPs will increase by about 10 US$/500 Sm3 CO2, except for the unit cost of the LTF process, which is only improved by 3–4 US$/500 Sm3CO2 due to the low injection cost of liquid CO2. However, the cheapest way to dispose of the produced gas is to reinject the produced gas directly. The unit cost of the DRM process is only 13.58–15.64 US$/500 Sm3 CO2.
Figure 9c shows the unit energy consumptions of different CCRPs with time. The unit energy consumptions of PSA, MS, and LTF processes decrease quickly in the first 2–3 years and tend to be stable, while the unit energy consumptions of MDEA and DBM processes always remain stable. The order of unit energy consumptions of different CCRPs is MDEA > LTF > MS ≈ PSA > DRM (1143, 721, 342, 328, and 244 MJ/500 Sm3, respectively, after 15 years of injection). A high energy consumption usually means a large amount of additional CO2 emissions and a low effective CO2 capture efficiency; hence, the ranking of CCREs of different CCRPs is DRM > MS ≈ PSA > LTF > MDEA (93.97%, 91.48%, 90.96%, 83.10%, and 74.86%, respectively, 15 years later), as shown in Figure 9d.
For the CO2 capture purity, as shown in Figure 9e, only in the MDEA and PSA processes can it reach 90 mol% in the first 2 years, while the CO2 capture purity of the LTF process is as low as 77.69% at the beginning. After 4 years of production, the CO2 capture purities of different CCRPs become stable with an order of MDEA > LTF > PSA ≈ MS > 90 mol%. For the CO2 capture rate, only a little difference is between different CCRPs because of the high CO2 content in the produced gas, as shown in Figure 9f.
Based on the above analysis, it can be seen that the DRM process is the best way to deal with the produced gas. However, before reinjection, the produced gas should be mixed with the purchased pure CO2 if necessary to meet CO2 purity and injection amount requirements. As shown in Figure 10a, when the produced gas is mixed with the purchased pure CO2 to meet the required CO2 purity of 90 mol%, no more than 8 × 104 Sm3/d of pure CO2 is needed, and with the increase of gas production and decrease of required injection amount, no additional pure CO2 will be needed 10 years later. However, when the produced gas is mixed with pure CO2 according to the required CO2 purity, the total amount of produced gas and pure CO2 is still less than the designed amount. Hence, more purchased pure CO2 is needed, which will make the CO2 content in the mixed gas up to 91–95 mol%, as shown in Figure 10b.
(2) Comparison of CCRPs between the different cases
Besides case D, the other three cases of CO2 flooding were also assessed to study the influence of gas production characteristics on selecting the optimal CCRP. The evaluation indicators of all CCRPs of all cases are summarized in Table 5.
For case A, the order of different CCRPs is MDEA > MS ≈ PSA ≈ LTF > DRM according to the unit costs of CCRPs when the CO2 content in the produced gas has reached stable after several years of production. Due to the stable CO2 content of 65–76 mol% in the produced gas, the CO2 capture purity, unit energy consumption, and CCRE are all kept stable during the project. However, it is not easy to design the DRM process. On the one side, the amount of mixed gas will be much larger than the required amount if the produced gas is mixed with the purchased pure CO2 based on the required CO2 purity. On the other side, the CO2 purity of mixed gas will be lower than 90 mol% during most of the project time if the produced gas is mixed with the purchased pure CO2 based on the required injection amount. For this case, the MS, PSA, or LTF process may be an assistant selection.
For case B, the unit costs of different CCRPs are in the order of MDEA > MS > PSA > LTF > DRM. The CO2 content in the produced gas is 56–88 mol%, and after three years of production, the CO2 content can maintain above 80 mol%. At such a high CO2 content, the unit CO2 capture cost of the LTF process is close to that of MS and PSA processes, while the total unit cost of the LTF process is lower than that of any other capture processes because of the low injection cost of liquid CO2. Besides, the LTF process has the second-high CO2 capture purity, although the unit energy consumption is high and the CCRE is as low as about 80%. This case is similar to case D. The DRM process is the most attractive option, and when the produced gas is mixed with pure CO2 according to the required injection amount, the CO2 content of the mixed gas can be high up to 92–95 mol%.
For case C, the unit costs of different CCRPs have the same order as that of case B. In this case, the injected CO2 will breakthrough in the first year, and the CO2 content in the produced gas is only 20 mol%; only in the fourth year will the CO2 content exceed 80 mol%. Hence, in the early stage of the project, the unit cost of CO2 capture will be very high. For the DRM process, a large amount of pure CO2 should be purchased to mix with the produced gas, which will lead to a high CO2 purity of mixed gas in a range of 95–98 mol%.
By comparing the four cases of CO2 flooding, it can be seen that (1) the DRM process is the best selection, but if the gas production is large and has a low-medium CO2 content, the DRM process may bring new issues such as more blocks are needed for gas injection or the CO2 content of the mixed gas cannot meet the required CO2 purity. (2) The MDEA process can be excluded because of its high cost and energy consumption during most project times. (3) When the CO2 content in the produced gas is above 80 mol%, the LTF process is an attractive option, while when the CO2 content is lower than 80 mol%, the PSA process is better than the MS process. Because of the considering of the probable adjustment of CO2 injection during the project, a more flexible and applicable CCRP is recommended as the following: the DRM process is selected as the main CCRP, and the PSA process is chosen as an assistant option that has a wide range of applicable CO2 content in the produced gas.

5. Conclusions

(1) For the CO2 EOR and storage project in XinJiang oilfield, a technical and economic evaluation model of CCRP was established based on the basic equipment units involved in the process, which can be applicable for any flexibly designed CCRPs. The evaluation indicators such as unit cost, unit energy consumption, CO2 capture efficiency, and CO2 capture purity of each equipment unit and the whole process can be calculated and used as the basis for the optimization of CCRP.
(2) The results of sensitivity evaluation of CCRPs show that with the increase of gas production rate and CO2 content in the produced gas, the unit cost and energy consumption of CCRP will decrease, while the CCRE and CO2 capture purity will increase. The MDEA and LTF processes have large unit energy consumptions, while the PSA process has a large CCRE and a high CO2 capture purity. In terms of the unit cost, the applicable CO2 contents in the produced gas for the MDEA, PSA, MS, and LTF processes are <20–40 mol%, >20–80 mol%, >50 mol%, and >80 mol% respectively, which are consistent with published studies. The DRM process is the most attractive selection because of its simple process, low unit cost, and high CCRE.
(3) According to the designed CO2 flooding schemes in XinJiang oilfield, different CCRPs were assessed. Different CCRPs have different advantages at different stages of the project. For the case of high gas injection and high gas production with a relatively low CO2 content, the DRM process is hard to apply. All or part of the produced gas may need to be purified by PSA, MS, or LTF processes, of which the PSA process has the widest applicable CO2 content range. For the case of high gas injection and low gas production with high CO2 content, the DRM process can be applied by mixing the produced gas with pure CO2 according to the required injection amount. Considering the probable adjustment of the CO2 injection scheme, a flexible and applicable CCRP is recommended to select the DRM process as the main CCRP associated with the PSA process as an assistant option.
(4) In general, the implementation of CCS in the oil field is economically rewarding, and CO2 can be stored permanently and safely. Besides, a large number of CO2 flooding projects around the world have also proved that this is the most feasible commercialization model. Therefore, a reasonable CCRP after enough evaluation can provide a guarantee for the CO2 EOR and storage project of XinJiang Oilfield. Furthermore, the success of the XinJiang oilfield provides a reference for the process optimization and environmental protection indicators of the CCS technology in China.

Author Contributions

Conceptualization, L.Z.; Formal analysis, S.G. and L.Y.; Investigation, Y.H.; Methodology, H.Y.; Project administration, L.Z.; Resources, Z.D.; Software, X.S.; Writing—original draft, S.G. All authors have read and agreed to the published version of the manuscript.

Funding

This research was funded by the National Science and Technology Major Project (2016ZX05056004–003).

Institutional Review Board Statement

Not applicable.

Informed Consent Statement

Not applicable.

Data Availability Statement

The data presented in this study are available.

Acknowledgments

This research is supported by the National Science and Technology Major Project (2016ZX05 056004–003), and partially financed by the General Project of Shandong Natural Science Foundation (ZR2020ME090), the National Natural Science Foundation of China (No. 51974347), and the Basic Research Program Project of Qinghai Province (No. 2020–ZJ–758). We also appreciate the reviewers and editors for their constructive comments to make the paper high quality.

Conflicts of Interest

The authors declare no conflict of interest.

Abbreviations and Nomenclature

Abbreviations
CAChemical absorption
CCRECO2 capture and reinjection efficiency
CCRPCO2 capture and reinjection process
CCSCO2 capture and storage
CCUSCO2 capture, utilization, and storage
CFGRcombustion and flue gas reinjection
DRMdirect reinjection mixed
EORenhanced oil recovery
LTFlow-temperature fractionation
MDEAmethyldiethanolamine
MSmembrane separation
PSApressure swing adsorption
Nomenclature
Csepcapital cost of gas–liquid separator (US$)
Mtrainmass flow rate of disposal gas (t/d)
Cmolcapital cost of molecular sieve (US$)
Ccomptotal capital cost of compressor (US$)
mtrainmass flow rate of CO2 gas in each compressor unit (kg/s)
Ntrainnumber of parallel compressors (dimensionless)
mCO2CO2 mass flow rate (t/d)
Pin–compinlet pressure of compressor (MPa)
Pout–compoutlet pressure of compressor (MPa)
Wcompcompressor power (kW)
Zsaverage compression factor of CO2 at each stage (dimensionless)
Tin–compinlet temperature of compressor (K)
MCO2gasmolar mass of CO2 gas (kg/kmol)
ηcompefficiency of compressor (dimensionless)
ksaverage heat capacity ratio of CO2 at each stage of compressor (dimensionless)
CRoptimal compression ratio (dimensionless)
Nstagenumber of compression stages (dimensionless)
Cpumpcapital cost of booster pump (US$)
Wpumpbooster pump power (kW)
Pout–pumpoutlet pressure of booster pump (MPa)
Pin–pumpinlet pressure of booster pump (MPa)
ρl–CO2density of liquid CO2 (kg/m3)
ηpumpefficiency of booster pump (dimensionless)
WPSA–admass of adsorbent in PSA module (kg)
QPSA–gflow rate of the feed gas in the adsorption tower of PSA module (m3/s)
tPSA–adadsorption time of single bed operation of tower in PSA module (s)
yPSA–CO2CO2 mole fraction of the feed gas in PSA module (dimensionless)
ΔqPSAadsorption capacity in PSA module (kg/kg)
nPSA–bednumber of beds for continuous adsorption in a single tower in PSA module (dimensionless)
HPSAheight of the tower in PSA module (m)
vPSA–ggas flow speed in adsorption tower of PSA module (m/s)
ρPSA–adadsorbent density in PSA module (kg/m3)
DPSAdiameter of the tower in PSA module (m)
nPSA–towernumber of towers in PSA module (dimensionless)
CPSA–towercapital cost of towers in PSA module (US$)
CPSA–pcunit height capital cost of the tower in PSA module (US$/m)
CPSA–adpurchase cost of adsorbent in PSA module (US$)
PPSA–adunit cost of adsorbent in PSA module (US$/kg)
CPSAcapital cost of the PSA module (US$)
WPSApower of the PSA module (kW)
Amfilm area in MS module (m2)
YMS–Fmole fraction of high-speed group (CO2) in feed gas in MS module (dimensionless)
YMS–Rmole fraction of the high-speed group in the nonpenetrating gas in MS module (dimensionless)
YMS–1mole fraction of the high-speed group in the permeation gas in MS module (dimensionless)
QMS–Pflow rate of permeation gas in MS module (kmol/s)
RMS–fweighted average permeation velocity of the high-speed group in MS module (m/s)
PMS–1total pressure on the low-pressure side of the membrane in MS module (bar)
PMS–2total pressure on the high-pressure side of the membrane in MS module (bar)
CMcapital cost of MS device (US$)
Imcost of membrane material in MS device (US$)
Imfcost of membrane frame in MS device (US$)
Kmmembrane material cost of unit film area (US$/m2)
Kmfmembrane frame cost of unit film area (US$/m2)
CMScapital cost of MS module (US$)
WMSpower of MS module (kW)
Chxcapital cost of heat exchanger (US$)
Ahx–pactual heat exchange area in heat exchanger (m2)
Qhxheat flow in heat exchanger (kJ/h)
mhfmass flow rate of hot fluid in heat exchanger (kg/h)
Cpspecific heat capacity of fluid in heat exchanger in heat exchanger (kJ·kg−1·°C−1)
Δthxtemperature change of hot fluid in heat exchanger (°C)
Khcheat transfer coefficient between the hot fluid and the cold fluid in heat exchanger (W·m−2·°C−1)
ΔTmlogarithmic mean temperature changes of heat exchanger (°C)
THIhot fluid temperature at the inlet of the heat exchanger (°C)
THOhot fluid temperature at the outlet of the heat exchanger (°C)
TCIcold fluid temperature at the inlet of the heat exchanger (°C)
TCOcold fluid temperature at the outlet of the heat exchanger (°C)
Whxpower of heat exchanger (kW)
CLTFcapital cost of LTF module (US$)
WLTFpower of LTF module (kW)
DCA–abdiameter of absorption tower in CA module (m)
VCA–abflow rate of feed gas in the absorption tower in CA module (m3/h)
vCA–abgas flow velocity in the adsorption tower in CA module (m/s)
HCA–abcumulative height of absorption towers in CA module (m)
mCA–CO2mass flow rate of CO2 gas in CA module (kg/h)
KGamass transfer coefficient in CA module (kmol·m−3·h−1·atm−1)
YCO2–inabCO2 content of inlet gas in absorption tower (g/m3)
YCO2–outabCO2 content of outlet gas in absorption tower (g/m3)
ACA–tcross–section area of absorption tower in CA module (m2)
∆PCA–mdriving pressure difference in the absorption tower of CA module (atm)
CCA–abcost of unit height tower in CA module (US$/m)
CCA–abtcapital cost of absorption tower in CA module (US$)
DCA–dediameter of the desorption tower in CA module (m)
VCA–deflow rate of feed gas in the desorption tower in CA module (m3/h)
vCA–degas flow velocity in the desorption tower in CA module (m/s)
NCA–ttotal number of theoretical plates in desorption tower in CA module (dimensionless)
CCA–detower cost of a single plate of desorption towers in CA module (US$)
CCA–detcapital cost of desorption tower in CA module (US$)
MMDEArequired circulation amount of MDEA solution (t)
Cspurchase cost of MEDA solution (US$)
Cusunit cost of MEDA solution (US$/t)
CCAcapital cost of CA module (US$)
WCApower of CA module (kW)
O&Mannualannual running cost of CCRP (US$)
Cunitcapital cost of equipment unit (US$)
Mfactorratio of annual maintenance cost to total infrastructure cost (dimensionless)
Wunitpower of equipment unit (kW)
Felecelectricity price (US$/kWh)
Qin–gasgas flow rate at the inlet of equipment unit (Sm3/d)
xin–CO2CO2 content at the inlet of equipment unit (dimensionless)
Qin–CO2pure CO2 gas flow rate at the inlet of equipment unit (Sm3/d)
Qout–gasgas flow rate at the outlet of equipment unit (Sm3/d)
Qout–CO2gasCO2 gas flow rate at the outlet of equipment unit (Sm3/d)
Qout–CH4gasCH4 gas flow rate at the outlet of equipment unit (Sm3/d)
xout–CO2CO2 purity of CO2 gas flow at the outlet of equipment unit (dimensionless)
yout–CH4CH4 purity of CH4 gas flow at the outlet of equipment unit (dimensionless)
Qout–CO2pure CO2 gas flow rate at the outlet of equipment unit (Sm3/d)
Qpower–CO2energy consumption equivalent CO2 emission of equipment unit (Sm3/d)
ηCO2 capture efficiency of the capture module (dimensionless)
Mcoalcoal consumption required for unit power generation (kg/kWh)
ECO2CO2 emissions per unit coal by burning (kg CO2/kg coal)
tuunit time (h)
ρCO2density of CO2 gas (kg/m3)
ClevCO2 capture and reinjection cost per 500 Sm3 CO2 gas (US$/500Sm3)
Ctcatotal annual cost of CCRP (US$)
Cannualannual capital cost by dividing the total capital cost equally over each year of the project duration (US$)
CRFthe discount factor (dimensionless)

References

  1. Ren, S.R.; Li, D.Y.; Zhang, L.; Huang, H. Leakage Pathways and Risk Analysis of Carbon Dioxide in Geological Storage. Acta Pet. Sin. 2014, 35, 591–601, (In Chinese with English abstract). [Google Scholar]
  2. Qin, J.X.; Han, H.S.; Liu, X.L. Application and enlightenment of carbon dioxide flooding in the United States of America. Pet. Explor. Dev. 2015, 42, 209–216. [Google Scholar] [CrossRef]
  3. Sourisseau, K.; Ibrahim, I.; Al-Jabri, A.; Wetzels, G. Surface facilities considerations for the production of a large sour gas resource and the injection of sour and/or acid gas. In Proceedings of the Abu Dhabi International Petroleum Exhibition and Conference, Abu Dhabi, United Arab Emirates, 13–15 October 2000. [Google Scholar]
  4. Zainal, Z.A.; Mahadzir, M.M. Experimental study of hydrodynamic characteristics and CO2 absorption in producer gas using CaO-sand mixture in a bubbling fluidized bed reactor. Int. J. Chem. React. Eng. 2011, 9, 154–156. [Google Scholar]
  5. Adewole, J.K.; Ahmad, A.L. Process modeling and optimization studies of high pressure membrane separation of CO2 from natural gas. Korean J. Chem. Eng. 2016, 33, 2998–3010. [Google Scholar] [CrossRef]
  6. Liu, B.L. Experimental Study of Low-Temperature and Pressure Swing Adsorption Removal Carbon Dioxide Gas from Natural Gas; Dalian University of Technology: Dalian, China, 2015; (In Chinese with English abstract). [Google Scholar]
  7. Torp, T.A.; Brown, K.R. CO2 underground storage costs as experienced at Sleipner and Weyburn. In Proceedings of the 7th International Conference on Greenhouse Gas Control Technologies, Vancouver, BC, Canada, 5 September 2004. [Google Scholar]
  8. Ma, P.F.; Han, B.; Zhang, L.; Xiong, X.Q.; Shen, X.X.; Zhang, X.; Ren, S.R. Disposal scheme of produced gas and CO2 capture for re-injection in CO2 EOR. Chem. Ind. Eng. Prog. 2017, 36, 533–539, (In Chinese with English abstract). [Google Scholar]
  9. Sun, R.Y.; Ma, X.H.; Wang, S.G. CO2 injection technology in Jilin Oilfield. Pet. Plan. Eng. 2013, 24, 1–6, (In Chinese with English abstract). [Google Scholar]
  10. Zhang, L.; Li, X.; Ren, B.; Cui, G.D.; Zhang, Y.; Ren, S.R.; Chen, G.L.; Zhang, H. CO2 storage potential and trapping mechanisms in the H-59 block of Jilin oilfield China. Int. J. Greenh. Gas Control 2016, 49, 267–280. [Google Scholar] [CrossRef]
  11. Zhang, L.; Ren, B.; Huang, H.D.; Li, Y.Z.; Ren, S.R.; Chen, G.L.; Zhang, H. CO2 EOR and storage in Jilin Oilfield China: Monitoring program and preliminary Results. J. Pet. Sci. Eng. 2015, 125, 1–12. [Google Scholar] [CrossRef]
  12. Zhang, L.; Yang, C.H.; Niu, B.L.; Ren, S.R. EOR Principles and Application of CO2 Flooding; Press of China University of Petroleum: Qingdao, China, 2017. (In Chinese) [Google Scholar]
  13. Yu, B.Y.; Zhao, G.P.; An, R.D.; Chen, J.M.; Tan, J.X.; Li, X.Y. Study on China’s carbon emission path under the carbon neutral target. J. Beijing Inst. Technol. (Soc. Sci. Ed.) 2021, 23, 17–24, (In Chinese with English abstract). [Google Scholar]
  14. Kwak, D.H.; Yun, D.; Binns, M.; Yeo, Y.K.; Kin, J.K. Conceptual process design of CO2 recovery plants for enhanced oil recovery applications. Ind. Eng. Chem. Res. 2014, 53, 14385–14396. [Google Scholar] [CrossRef]
  15. Zhou, D.B. EOR Natural Gas CO2 Separation Process Simulation Study; Qingdao University of Science and Technology: Qingdao, China, 2014; (In Chinese with English abstract). [Google Scholar]
  16. Ciferno, J.P.; DiPietro, P.; Tarka, T. An Economic Scoping Study for CO2 Capture Using Aqueous Ammonia; Final Report; National Energy Technology Laboratory, US Department of Energy: Pittsburgh, PA, USA, 2005.
  17. Kleme, J.; Bulatov, I.; Cockerill, T. Techno-economic modeling and cost functions of CO2 capture processes. Comput. Chem. Eng. 2007, 31, 445–455. [Google Scholar] [CrossRef]
  18. Tuinier, M.J.; Hammers, H.P.; van Sint Annaland, M. Techno-economic evaluation of cryogenic CO2 capture—A comparison with absorption and membrane technology. Int. J. Greenh. Gas Control 2011, 5, 1559–1565. [Google Scholar] [CrossRef]
  19. Huang, Y.P.; Rebennack, S.; Zheng, Q.P. Techno-economic analysis and optimization models for carbon capture and storage: A survey. Energy Syst. 2013, 4, 315–353. [Google Scholar] [CrossRef]
  20. Zhang, Z.H. Techno-economic assessment of carbon capture and storage facilities coupled to coal-fired power plants. Energy Environ. 2015, 26, 1069–1080. [Google Scholar] [CrossRef]
  21. Zohrabian, A.; Majoumerd, M.M.; Soltanieh, M.; Sourena, S. Techno-economic evaluation of an integrated hydrogen and power co-generation system with CO2 capture. Int. J. Greenh. Gas Control 2016, 44, 94–103. [Google Scholar] [CrossRef]
  22. Zhai, M.Y.; Lin, Q.G.; Zhong, L.F.; Pi, J.W.; Wang, W.S. Economic assessment of carbon capture and storage combined with utilization of deep saline water. Mod. Chem. Ind. 2016, 36, 8–12, (In Chinese with English abstract). [Google Scholar]
  23. Hu, B.; Zhai, H. The cost of carbon capture and storage for coal-fired power plants in China. Int. J. Greenh. Gas Control 2017, 65, 23–31. [Google Scholar] [CrossRef]
  24. Liu, J.J.; Zhao, D.Y.; Tian, Q.H.; Li, Z.M. Modeling and optimization of the whole process of CO2 capture, transportation, oil displacement and storage. Oil Gas Field Surf. Eng. 2018, 37, 1–5, (In Chinese with English abstract). [Google Scholar]
  25. Decardi-Nelson, B.; Liu, S.; Liu, J.F. Improving flexibility and energy efficiency of post-combustion CO2 capture plants using economic model predictive control. Processes 2018, 6, 135. [Google Scholar] [CrossRef] [Green Version]
  26. Yun, S.; Oh, S.Y.; Kim, J.K. Techno-economic assessment of absorption-based CO2 capture process based on novel solvent for coal-fired power plant. Appl. Energy 2020, 268, 114933. [Google Scholar] [CrossRef]
  27. Gui, X.; Wang, C.W.; Yun, Z.; Zhang, L.; Tang, Z.G. Research progress of pre-combustion CO2 capture. Chem. Ind. Eng. Prog. 2014, 33, 1895–1901, (In Chinese with English abstract). [Google Scholar]
  28. Li, Q.F.; Lu, S.J.; Liu, X.D.; Zhang, J. Experimental research of absorbing carbon dioxide from flue gas by MEA-MDEA mixed amine solutions. Appl. Chem. Ind. 2010, 39, 1127–1131, (In Chinese with English abstract). [Google Scholar]
  29. Ahmad, A.L.; Adewole, J.K.; Leo, C.P.; Ismail, S.; Sultan, A.S.; Olatunji, S.O. Prediction of plasticization pressure of polymeric membranes for CO2 removal from natural gas. J. Membr. Sci. 2015, 480, 39–46. [Google Scholar] [CrossRef]
  30. Algharaib, M.; Al-Soof, N. Economical modeling of CO2 capturing and storage projects. SPE 120815-MS. In Proceedings of the SPE Saudi Arabia Section Technical Symposium, Al-Khobar, Saudi Arabia, 10–12 May 2008. [Google Scholar]
  31. Peters, M.S.; Timmerhaus, K.D.; West, R.E. Plant Design and Economics for Chemical Engineers; McGraw-Hill: New York, NY, USA, 1968. [Google Scholar]
  32. Dong, X.; Han, P.; Yang, Z.; Xie, S.; Zhen, K. Pilot Field Test of Carbon Dioxide Flooding in Daqing Oilfield; Petroleum Industry Press: Beijing, China, 1999. (In Chinese) [Google Scholar]
  33. Zhang, Y. Research on CO2-EOR and Geological Storage in Caoshe Oilfield, Jiangsu; China University of Petroluem: Qingdao, China, 2010; (In Chinese with English abstract). [Google Scholar]
  34. Hendriks, C.; Graus, W.; van Bergen, F. Global Carbon Dioxide Storage Potential and Costs; Ecofys: Utrecht, The Netherlands, 2004. [Google Scholar]
  35. McCollum, D.L. Techno-Economic Models for Carbon Dioxide Compression, Transport, and Storage; University of California: Davis, CA, USA, 2006. [Google Scholar]
  36. GHG IEA. Transmission of CO2 and Energy; IEA Greenhouse Gas R&D Programme, Report PH4/6; IEA: Paris, France, 2002. [Google Scholar]
  37. Han, Y.J.; Wang, S.L.; Zhang, P.Y.; Piao, P.Y. Status and progress of CO2 separation and capture technology. Nat. Gas Ind. 2009, 29, 79–82, (In Chinese with English abstract). [Google Scholar]
  38. Chen, D.Y. Remove Carbon Dioxide by PSA; Nanjing Tech University: Nanjing, China, 2003; (In Chinese with English abstract). [Google Scholar]
  39. Yang, H.Y. Research on Adsorbents for Separation of the CH4/CO2 Mixture; Northeast Agricultural University: Harbin, China, 2013; (In Chinese with English abstract). [Google Scholar]
  40. Meng, D. Structure Design and Stress Analysis of PSA Absorption Tower. Petro-Chem. Equip. 2010, 39, 33–36, (In Chinese with English abstract). [Google Scholar]
  41. Zhou, F. Design of CO2 absorption tower. Guangdong Chem. Ind. 2014, 41, 245–246, (In Chinese with English abstract). [Google Scholar]
  42. Zhao, L.; Menzer, R.; Riensche, E.; Blum, L.; Stolten, D. Concepts and investment cost analyses of multi-stage membrane systems used in post-combustion processes. Energy Procedia 2009, 1, 269–278. [Google Scholar] [CrossRef] [Green Version]
  43. Su, Y.; Hu, L.; Liu, M.S. Gas membrane separation technology and application. Chem. Eng. Oil Gas 2001, 30, 113–116, (In Chinese with English abstract). [Google Scholar]
  44. Shi, M.Z.; Wang, Z.Z. Principle and Design of Heat Exchangers; Southeast University Press: Nanjing, China, 2009. (In Chinese) [Google Scholar]
  45. Peng, Y.X. Coupling of distillation and low temperature stripping—A new output gas recovery technology in CO2 flooding process in oilfields. Reserv. Eval. Dev. 2012, 2, 42–47, (In Chinese with English abstract). [Google Scholar]
  46. Zhang, X.F. Calculation of effective height of chemical absorption packed tower. Chem. Eng. Des. Commun. 1995, 21, 42–46, (In Chinese with English abstract). [Google Scholar]
  47. Liao, H.; Zhao, G.X.; Ma, B.Q. Design of HCl absorber for a 100 kt/a Deacon process. Chem. World 2015, 56, 653–657, (In Chinese with English abstract). [Google Scholar]
  48. Chen, J.; He, G.; Liu, J.; Liu, J. Measurement for the absorption rate of CO2 by aqueous MDEA solution. J. Tsinghua Univ. (Sci. Technol.) 2001, 41, 28–30, (In Chinese with English abstract). [Google Scholar]
  49. Liu, Y.Z.; Shen, H.Y. Carbon Dioxide Emission Reduction Process and Technology--Solvent Absorption Method; Chemical Industry Press: Beijing, China, 2013. (In Chinese) [Google Scholar]
  50. Li, T. Study on Energy-Saving and Optimization Technology of Carbon Dioxide Captured System of Flue Gas in Coal-Fired Power; Qingdao University of Science and Technology: Qingdao, China, 2010; (In Chinese with English abstract). [Google Scholar]
Figure 1. (a) The location of block 530 (b) Well groups selected in the block 530.The block 530 and well groups selected for CO2 EOR and storage pilot project.
Figure 1. (a) The location of block 530 (b) Well groups selected in the block 530.The block 530 and well groups selected for CO2 EOR and storage pilot project.
Energies 14 05076 g001
Figure 2. The CCRPs designed in CO2 EOR and storage project in XinJiang Oilfield. (a) Typical CO2 PSA capture and reinjection process; (b) Direct reinjection process with purchased CO2.
Figure 2. The CCRPs designed in CO2 EOR and storage project in XinJiang Oilfield. (a) Typical CO2 PSA capture and reinjection process; (b) Direct reinjection process with purchased CO2.
Energies 14 05076 g002
Figure 3. Main equipment units involved in the simplified CCRP.
Figure 3. Main equipment units involved in the simplified CCRP.
Energies 14 05076 g003
Figure 4. Variation of CO2 flow through capture module.
Figure 4. Variation of CO2 flow through capture module.
Energies 14 05076 g004
Figure 5. (a) CO2 capture purity, (b) hydrocarbon gas capture purityGas capture purity at different CO2 contents in the feed gas.
Figure 5. (a) CO2 capture purity, (b) hydrocarbon gas capture purityGas capture purity at different CO2 contents in the feed gas.
Energies 14 05076 g005
Figure 6. Calculation results of the evaluation indicators of the CCRPs at different gas production conditions. (a) Unit cost of CO2 capture; (b) Unit cost of CO2 capture and reinjection; (c) Unit energy consumption of CO2 capture; (d) Unit energy consumption of CO2 capture and reinjection; (e) CO2 capture and reinjection efficiency; (f) CO2 capture purity.
Figure 6. Calculation results of the evaluation indicators of the CCRPs at different gas production conditions. (a) Unit cost of CO2 capture; (b) Unit cost of CO2 capture and reinjection; (c) Unit energy consumption of CO2 capture; (d) Unit energy consumption of CO2 capture and reinjection; (e) CO2 capture and reinjection efficiency; (f) CO2 capture purity.
Energies 14 05076 g006
Figure 7. Calculation results of the evaluation indicators of the DRM process. (a) Unit cost; (b) Unit energy consumption; (c) CO2 capture and reinjection efficiency.
Figure 7. Calculation results of the evaluation indicators of the DRM process. (a) Unit cost; (b) Unit energy consumption; (c) CO2 capture and reinjection efficiency.
Energies 14 05076 g007
Figure 8. (a) Gas injection rate, (b) Gas production rate, and (c) CO2 content in produced gas. The predicted gas injection and production in the CO2 EOR and storage project in XinJiang oilfield.
Figure 8. (a) Gas injection rate, (b) Gas production rate, and (c) CO2 content in produced gas. The predicted gas injection and production in the CO2 EOR and storage project in XinJiang oilfield.
Energies 14 05076 g008
Figure 9. The calculated evaluation indicators of different CCRPs based on the predicted production of case D. (a) Unit cost of CO2 capture; (b) Unit cost of CO2 capture and reinjection; (c) Unit energy consumption; (d) CO2 capture and reinjection efficiency (CCRE); (e) CO2 capture purity; (f) CO2 capture rate.
Figure 9. The calculated evaluation indicators of different CCRPs based on the predicted production of case D. (a) Unit cost of CO2 capture; (b) Unit cost of CO2 capture and reinjection; (c) Unit energy consumption; (d) CO2 capture and reinjection efficiency (CCRE); (e) CO2 capture purity; (f) CO2 capture rate.
Energies 14 05076 g009aEnergies 14 05076 g009b
Figure 10. (a) Based on the required CO2 purity. (b) Based on the required injection amount. Two types of produced gas mixed with the purchased pure CO2 in the DRM process of case D.
Figure 10. (a) Based on the required CO2 purity. (b) Based on the required injection amount. Two types of produced gas mixed with the purchased pure CO2 in the DRM process of case D.
Energies 14 05076 g010
Table 1. Main equipment units involved in the five types of CCRPs.
Table 1. Main equipment units involved in the five types of CCRPs.
The Types of CCRPsThe 6 Main Equipment Units
SPAProduced gas (0.5 MPa, 20 1 °C) → gas–liquid separator → low-pressure compressor → molecular sieve → SPA system → high-pressure compressor →reinjected gas (20 MPa, 40 °C)
MSProduced gas (0.5 MPa, 20 °C) → gas–liquid separator → low-pressure compressor → molecular sieve → MS system → high-pressure compressor →reinjected gas (20 MPa, 40 °C)
LTFProduced gas (0.5 MPa, 20 °C) → gas–liquid separator → low-pressure compressor → molecular sieve → LTF system → liquid CO2 storage tank → boost pump→ reinjected gas (20 MPa, −20 °C)
CA-MDEAProduced gas (0.5 MPa, 20 °C) → gas–liquid separator → low-pressure compressor → molecular sieve → CA-MDEA → high-pressure compressor →reinjected gas (20 MPa, 40 °C)
DRMProduced gas (0.5 MPa, 20 °C) → gas–liquid separator → low-pressure compressor → molecular sieve → high-pressure compressor →reinjected gas (20 MPa, 40 °C)
Table 2. CO2 flow variation and CO2 capture efficiency of each equipment unit in CCRP.
Table 2. CO2 flow variation and CO2 capture efficiency of each equipment unit in CCRP.
Equipment UnitsGas Flow at the Outlet, m3/dCO2 Purity at the Outlet, FractionCO2 Flow at the Outlet, m3/dAdditional CO2 Emission, m3CO2 Capture Efficiency, Fraction
Compressor/PumpQout-gas = Qin-gasxout-CO2 = xin-CO2Qout-CO2 = Qout-gas × xout-CO2Qpower-CO2H = (Qout-CO2Qpower-CO2)/Qin-CO2
Carbon Capture ModuleQout-CO2gas
Qout-CH4gas
Qin-gas = Qout-CO2gas + Qout-CH4gas
xout-CO2
yout-CH4
Qin-gas × xin-CO2 = Qout-CO2gas × xout-CO2 + Qout-CH4gas × (1 − yout-CH4)
Qout-CO2 = Qout-CO2gas × xout-CO2Qpower-CO2H = (Qout-CO2 − Qpower-CO2)/Qin-CO2
Table 3. Regression formulas of gas capture purity for different CO2 capture modules.
Table 3. Regression formulas of gas capture purity for different CO2 capture modules.
Gas PurityCapture TypeRegression FormulaCorrelation Coefficient R2
CO2 purity of captured CO2 gasPSAxout-CO2 = 0.036lnxin-CO2 + 0.8002R2 = 0.9952
MSxout-CO2 = 0.094lnxin-CO2 + 0.5420R2 = 0.9734
LTFxout-CO2 = 0.265lnxin-CO2 − 0.2061R2 = 0.9934
MDEAxout-CO2 = 0.9997R2 = 0
Hydrocarbon purity of captured natural gasPSAyout-CH4 = −0.060lnxin-CO2 + 1.1594R2 = 0.9615
MSyout-CH4 = −0.072lnxin-CO2 + 1.1573R2 = 0.8890
LTFyout-CH4 = −0.025lnxin-CO2 + 1.0597R2 = 1
MDEAy = 0.9725R2 = 0
Table 4. Predicted results of four CO2 flooding schemes for CO2 EOR and storage project in XinJiang oilfield.
Table 4. Predicted results of four CO2 flooding schemes for CO2 EOR and storage project in XinJiang oilfield.
SchemeCase ACase BCase CCase D
Total CO2 injection rate, 104 Sm3/d10–145–108–148–15
Total gas production rate, 104 Sm3/d0–100–3.70–4.50–7.8
CO2 content in produced gas, %65–7656–8820–9040–90
Cumulative CO2 injection, 104 t139.9380.83108.22123.93
Cumulative CO2 production, 104 t54.0426.9321.8154.70
Primary CO2 storage efficiency, %61.3866.6879.8555.86
Cumulative oil production, 104 t41.6026.0433.1749.49
Average CO2-oil ratio, t CO2/t oil3.363.103.262.50
EOR, %29.5018.4723.2625.75
No of well group9 injection wells9 injection wells 15 injection wells15 injection wells
Project period, year15151515
Note: primary CO2 storage efficiency refers to the ratio of the amount of stored CO2 (=cumulative CO2 injection—cumulative CO2 production) and the cumulative CO2 injection.
Table 5. Summary of evaluation indicators of all CCRPs of all cases.
Table 5. Summary of evaluation indicators of all CCRPs of all cases.
CO2 Flooding SchemeType of CCRPUnit Cost of Capture, US$/500 Sm3CO2Unit Cost of Capture and Reinjection, US$/500 Sm3CO2Unit Energy Consumption, MJ/500 Sm3CO2CO2 Capture and Reinjection Efficiency, %CO2 Capture Purity, %
Case ASPA21–2530–36358–38687–8995
MDEA31–4139–511148–11547499.97
MS23–3531–45375–40984–8793–95
LTF26–3929–46843–93975–7990–94
DRM7–9 *13–15253–26091–9380–94 **
Case BSPA21–3431–46332–42284–9194–96
MDEA33–5543–671143–116173–7599.97
MS24–4834–60345–45479–9192–96
LTF21–5526–68735–104971–8386–98
DRM9–10 *15–16245–26690–9492–95 **
Case CSPA20–9531–109330–83071–9191–96
MDEA35–23845–941142–125465–7599.97
MS23–16636–180344–88463–9183–96
LTF21–18228–243727–180331–8360–98
DRM8–14 *15–20244–28470–9495–97 **
Case DSPA19–4028–51328–51380–9193–96
MDEA28–5837–691142–118071–7599.97
MS19–6528–77341–57569–9189–96
LTF18–6921–81719–127661–8378–99
DRM8–10 *14–16244–27485–9491–95 **
Note: the data marked by * are the pretreatment costs of the produced gas in the DRM process; the data marked by ** are the CO2 contents of the produced gas after being mixed with the purchased pure CO2 in the DRM process.
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Zhang, L.; Geng, S.; Yang, L.; Hao, Y.; Yang, H.; Dong, Z.; Shi, X. Technical and Economic Evaluation of CO2 Capture and Reinjection Process in the CO2 EOR and Storage Project of Xinjiang Oilfield. Energies 2021, 14, 5076. https://doi.org/10.3390/en14165076

AMA Style

Zhang L, Geng S, Yang L, Hao Y, Yang H, Dong Z, Shi X. Technical and Economic Evaluation of CO2 Capture and Reinjection Process in the CO2 EOR and Storage Project of Xinjiang Oilfield. Energies. 2021; 14(16):5076. https://doi.org/10.3390/en14165076

Chicago/Turabian Style

Zhang, Liang, Songhe Geng, Linchao Yang, Yongmao Hao, Hongbin Yang, Zhengmiao Dong, and Xian Shi. 2021. "Technical and Economic Evaluation of CO2 Capture and Reinjection Process in the CO2 EOR and Storage Project of Xinjiang Oilfield" Energies 14, no. 16: 5076. https://doi.org/10.3390/en14165076

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop