Next Article in Journal
Locked Deduplication of Encrypted Data to Counter Identification Attacks in Cloud Storage Platforms
Next Article in Special Issue
A Case Study on Distributed Energy Resources and Energy-Storage Systems in a Virtual Power Plant Concept: Technical Aspects
Previous Article in Journal
Socio-Economic Opportunities from Miscanthus Cultivation in Marginal Land for Bioenergy
Previous Article in Special Issue
The Application of Hierarchical Clustering to Power Quality Measurements in an Electrical Power Network with Distributed Generation
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Analysis of the Power Supply Restoration Time after Failures in Power Transmission Lines

1
Laboratory of Power Supply and Heat Supply, Federal Scientific Agroengineering Center VIM, 109428 Moscow, Russia
2
Department of Electrical Engineering Fundamentals, Faculty of Electrical Engineering, Wroclaw University of Science and Technology, 50-370 Wroclaw, Poland
3
Department of Electrical Power Engineering, Faculty of Electrical Engineering and Computer Science, VSB-Technical University of Ostrava, 708 00 Ostrava, Czech Republic
4
Faculty of Law, Administration and Economics, University of Wroclaw, 50-145 Wroclaw, Poland
*
Authors to whom correspondence should be addressed.
Energies 2020, 13(11), 2736; https://doi.org/10.3390/en13112736
Submission received: 24 April 2020 / Revised: 25 May 2020 / Accepted: 27 May 2020 / Published: 29 May 2020
(This article belongs to the Special Issue Signal Analysis in Power Systems)

Abstract

:
This paper presents the analysis of power supply restoration time after failures occurring in power lines. It found that the power supply restoration time depends on several constituents, such as the time for obtaining information on failures, the time for information recognition, the time to repair failures, and the time for connection harmonization. All these constituents have been considered more specifically. The main constituents’ results values of the power supply restoration time were analyzed for the electrical networks of regional power supply company “Oreolenergo”, a branch of Interregional Distribution Grid Company (IDGC) of Center. The Delphi method was used for determining the time for obtaining information on failures as well as the time for information recognition. The method of mathematical statistics was used to determine the repair time. The determined power supply restoration time (5.28 h) is similar to statistical values of the examined power supply company (the deviation was equal to 9.9%). The technical means of electrical network automation capable of the reduction of the power supply restoration time have also been found. These means were classified according to the time intervals they shorten.

1. Introduction

Improving power supply efficiency from private homes to large industrial enterprises is an urgent and difficult task for power supply (PS) enterprises. This is because power supply companies often encounter problems such as the remoteness of energy consumers from power distribution points, insufficient capacity margin, depreciation of power supply equipment, and the lack of specialists involved in servicing this equipment. As a result, it leads to the increase in the number of equipment failures and the increase in PS interruptions. In turn, this translates into losses for power supply companies due to the elimination of the failure’s consequences and for consumers due to a disruption of the technological process caused by the power supply outages.
This article deals with the analysis of power supply restoration after power line failures. Thus, the organization of the article is as follows. Section 2 is a literature review of the state of the art with the motivation and contribution of this paper. Section 3 introduces the problem of power supply reliability. It indicates the elements that have an impact on the total time of restoration. In Section 4, the calculation of each element is performed based on real data obtained from a Russian power supply company. Section 5 contains a discussion of the results and propositions for the technical means of automation of electrical networks to reduce the power supply restoration time. Section 6 is the conclusion part.

2. State-of-the-Art Power Supply Restoration Issues

The present research described in the literature concerns the problem of power supply reliability in different areas. The aim of this research is a power supply restoration analysis [1]. Thus, current research trends in the literature are analyzed with regards to restoration issues. The presented literature review is divided into two areas:
  • research based on simulations for both transmission and distribution systems,
  • analysis for real objects obtained from historical data.

2.1. Research Based on Simulations

The present literature is generally based on simulations. The analysis of power supply reliability in point of restoration issues was divided into two parts—distributed and transmission systems.
Distributed grid:
  • The article [2] presents the networked microgrids aided approach to service restoration in a power distribution network. This paper proposes to use a mixed-integer linear approach. The main contribution of the article is to leverage networked microgrids to simplify service restoration. The proposed model was verified using the modified IEEE 123 node distribution test system.
  • The article [3] deals with service restoration for a distribution network. The element under consideration is the uncertainty of restoration time. In the article, a two-stage adaptive algorithm for service restoration was proposed. This algorithm uses the Wasserstein distance metric. It is applied to calculate two restoration times with different probabilities. Then the higher probability is used as the restoration time.
  • The paper [4] describes a multi-stage restoration method. It is applied to an medium voltage (MV) distribution system with distributed generation. The proposed service restoration approach concerns intentionally connection islanding of distributed generators (DGs) with network reconfiguration to maximize restoration of switched-off loads. It is realized by matching islanding schemes. Then the restoration of network connectivity and DGs is realized. Finally, the network reconfiguration as well as load shedding optimization are proposed. This research is based on a Pacific Gas & Electric (PG&E) sixty-nine bus system.
  • The article [5] proposes a heuristic method for distribution network restoration. The proposed algorithm was implemented and tested on the IEEE 33-bus standard network.
  • The article [6] concerns optimal network restoration after faults in a distribution network with distributed generation. The selected method is a meta-heuristic Artificial Bee Colony algorithm. The restoration algorithm and the load flow analysis were simulated using MATPOWER in MATLAB software. That research aimed to minimize out-of-service loads and power losses and improve the voltage profile. The article presents two examples of two single-fault and multi-fault cases. For each example, five different scenarios were studied. The results showed the significant power loss reduction and improvement in minimum voltage.
  • Other papers that concern simulations to increase reliability are based on restoration issues for distributed grids, e.g., static island power supply restoration strategy [7], power restoration method using a genetic algorithm [8], the state-of-the-art fault localization and service restoration [9], robust power supply restoration for self-healing active distribution networks [10], intelligent power supply restoration [11], power restoration strategy [12], and a fast power service restoration method [13].
Transmission grid:
  • The article [14] concerns power system restoration planning. The strategy presented in the paper uses an optimal energizing time needed to sectionalize islands. The method contains the identification of transmission lines that are not adequate to connect to the islands. The article methods consist of a combination of optimization methods: heuristic and discrete. The heuristic one is used to indicate an initial solution which is close to the optimal solution. Then it is input to the discreet method, which is the discrete Artificial Bee Colony approach.
  • The paper [15] is based on a resilience analysis of transmission line restoration. It indicated that transmission line capacitance is based on resilience factors. The proposed ideas were verified in two IEEE tests.
  • The article [16] presents a parallel automated resilience-based approach to restoration. The appliance aims to minimize the influence of the emergency power outages in a power system. The article proposes that during the power restoration process, a black start element is allocated to a little region on an as-needed demand. Then a mixed-integer nonlinear programming approach is indicated. The bi-level programming was used in the proposed solution to such a large-scale optimization model. The application was realized using both 6 and 118 bus IEEE test systems.
  • The article [17] presents a possibility to solve the problem of expansion planning. The article contains the proposition of using multistage stochastic programming to solve this issue. The indicated mixed-integer linear programming proposes the placement of the construction and reinforcement of new transmission lines to assure the high reliability and quick restoration. The presented results are based on the IEEE 30-bus system with assuring to minimalize cost.
  • The article [18] proposes the post-disaster restoration planning model that enables finding an optimal repair and activation schedule for damaged system components. In this model, an aim is to maximize load accommodation capability, as well as to minimalize the make-span of the restoration process. The obtained results increased maintenance efficiency. The IEEE 118 and 30 bus test systems were tested in the study. Moreover, the advantages of using the sequence-dependent repairing period are discussed.
  • Other papers that concern simulation results in transmission systems and reliability are: using interline dynamic voltage restoration [19], a method for the optimization of a power system restoration path [20], a transmission line restoration using an emergency restoration system structure [21], an indication of the maintenance schedule of transmission lines [22], a definition of a restoration strategy in a transmission system during windstorm [23].

2.2. Research Based on Historical Data and Real Objects

The previous subsection includes literature resources from the last three to five years. However, all of them are based on simulations and different models (e.g., IEEE models). The authors indicate that there is a lack of present research of restoration issues based on real data, even if it is only input to further algorithms. This article is devoted to transmission lines restoration time; thus, this part is narrowed down only to transmission grids. Some interesting papers that concerns real object analysis using historical data can be found in the “SCOPUS” data base for key words “restoration” & “transmission lines” from the last three to five years:
  • The article [24] presents a black start case study. However, the article contains simulations which are based on real data from Benghazi North Power Plant. The data were used to validate a black start plan for steady-state and transient operating conditions. The article indicates that the optimum size selection of the black start is defined by the capacity of the biggest motor, transmission line capacitive charging reactance, transformers size, and vector group.
  • The article [25] presents a fault location system. The system is based on synchro phasors measurements. It is used for 345 kV and 161 kV transmission networks at Taiwan Power Company. Additionally, the article presents an evaluation based on historical cases.
  • The paper [26] presents an issue that was connected with noticeable transmission lines failures in India under natural disasters. Data used in the article consisted of historical measurements when real disasters happened. The article discusses emergency restoration system applications. This system uses structure and foundation information, weather-related failure information, weather conditions, structural loading, and damage sizes.
  • The paper [27] is related to the economic impact of climatic events in the USA. It additionally discusses why emergency restoration plans are needed. The second part of the article presents a case study from Oman. It presents emergency restoration procedures to downed transmission lines. Key aspects of emergency restoration procedures are discussed. The article indicates that with the development of materials and techniques, emergency restoration procedures must be periodically reviewed using actual technologies.
  • Other papers that concern using real data in a transmission system and reliability are: an analysis of the empirical probability distribution of transmission line restoration time over 14 years [28], a case study of black starts of transmission lines in Australia [29], the development of a sequential restoration strategy and its empirical verification in a Korean power system [30].

2.3. Motivation and Contribution of the Paper

The number of articles, indicated in previous subsections, that concern simulation in recent years is huge. However, there is a lack of recent analyses realized for real cases although such real case analyses were common in the previous century. However, they are still necessary because the development of the materials and technics has totally changed in different areas. Thus, this article is a case study for the Russian power supply company “Oreolenergo” that concerns the analysis of restoration time in power lines based on analyzing historical data and a survey. In the analyzed regional power supply company “Oreolenergo”, there are no monitoring systems for outages in the considered electrical networks. There is practically no automation equipment, and power lines are made radial. The structuring of the power supply restoration time given in the study makes it possible to consider in more detail all the constituents of the power supply restoration time and to establish the factors affecting it.
It is difficult to assess the real time of power supply restoration, since there is no real data on the time of the power supply outage beginning. The countdown of the power supply restoration time in most cases starts from the moment when the information on a failure is received by the dispatcher of a power supply company. As a result, restoration time is underestimated. Consequently, the damage from the undersupply of electricity is also inaccurate. Therefore, the constituent “time for obtaining information” was introduced into the structure of the power supply restoration time. The value of this constituent was determined by the Delphi method. This method was also used for the determination of the time for recognizing information. The choice of this method is due to the impossibility of evaluating the data on power supply restoration time constituents by other means. The questionnaires used for Delphi were designed specifically for this purpose and were sent to specialists who work in the power supply company “Oreolenergo” and who have at least five years of work experience. The choice of experts was justified by the fact that the dispatchers of the power supply companies receive information from consumers about power supply outages, register the moment of this information receipt, send a repair brigade to search for places of damage and to eliminate the identified damage, and register the corresponding time intervals for repairs and switching on. In most cases of power supply outages, especially in the 0.4 kV electrical network, dispatchers receive information about outages from consumers, since there are no monitoring systems for power supply outages. Nevertheless, they have cases of receiving information about the time of obtaining information, for example, during planned power supply interruptions made by the personnel of power supply companies. In these cases, they can register the time of disconnection and the moment of receipt of the information on the power supply outage from the consumer. Thus, there is the opportunity to analyze the time interval for obtaining information on power supply outages and the experts were competent in estimating time intervals for obtaining and recognizing information. A total of 20 experts responded to the questionnaires. In turn, the repair time was determined by using the method of mathematical statistics, while the time for connection harmonization was determined by using the analysis of literature sources. To summarize the method’s end elements indicated for the restoration time indication, Figure 1 was prepared. Additionally, in the article, the technical means of electrical network automation to reduce the power supply restoration time were also found.

3. Power Supply Reliability

One of the main criteria for power supply efficiency is power supply reliability, which implies the continuous supply of electricity to consumers in accordance with an electricity consumption schedule [31]. In turn, a main indicator of the PS reliability is power supply restoration time [32]. It can include the following constituents: time for obtaining information, time for information recognition, time to repair failures, and time for connection harmonization [33]. That is, the PS restoration time can be determined by Equation (1):
t restor . = t obt . infor . + t rec . infor . + t repair + t harmonize
where
  • t obt . infor . —time to obtain information;
  • t rec . infor . —time to recognize information;
  • t repair —time to repair failures;
  • t harmonize —time to harmonize equipment connection.
Each component of this equation can be further analyzed and contains several more time intervals, each of which ultimately has an impact on the overall power supply restoration time.
A time for obtaining information is denoted as an interval from the beginning of a failure until obtaining information on it by a dispatching service of a PS company [33]. This time includes the following intervals:
t obt . infor . = t infor 1 + t infor 2 + t infor 3
where
  • t infor 1 —time for obtaining information on failures by means of primary information links. This link can be electrical equipment receiving power energy from an electrical network and disconnecting in case of a power failure, a sensing device of an automation system, or network status monitoring (for example, a voltage sensor);
  • t infor 2 —time for obtaining information on failures by means of secondary information links. It can be the compared element of an automation system as well as a monitored network status. The specified time interval can be significantly reduced in the case of the use of automation, since a person (consumer) noticing disconnected equipment has to make sure that this disconnection occurred due to failures;
  • t infor 3 —time for obtaining information on failures by means of third information links. This link can be a dispatcher that receives a network failure signal or an element of a network status monitoring or another automation system making a decision based on received information (for example, a data processing unit, a microprocessor, etc.). This time interval largely depends on the data transmission channel. Thus, a person (consumer) can report a failure by phone, e-mail, or in person to the dispatcher, etc. t infor 3 will be different in each of these cases.
The information recognition time may be described using this equation: [33]
t rec . infor . = t read . infor + t dec + t search + t report
where
  • t read . infor —time required for information message recognition, that concerns failures in an electrical network. This time also depends on the data transmission channel through which the message arrived, the method of data transfer, and the speed of data recognition (who decrypts the message: a person or automatic equipment);
  • t dec —time spent on a decision by a dispatching office. It includes a time to decode information on failure, and it lasts until a place and a failure type are determined by a brigade;
  • t search —time required for a brigade to search the failure (depends on transport type, the remoteness of the failure place, the terrain type, the failure type, and brigade equipment for the search);
  • t report —time required to send information on a location and a failure type by a brigade (depends on the type of data transfer).
The repair time is an interval starting from the preparation of equipment to eliminate a failure up to the harmonization of the repair equipment [33]. This time can be represented as the following equation:
t repair = t repair . prepar + t repair . reach + t repair . switch + t repair . permit + t repair . work + t repair . complet
where
  • t repair . prepar —time required for a repair brigade to depart including the preparation of work permit, equipment, devices, and loading on transport;
  • t repair . reach —time required for a repair brigade to reach a failure location. It depends on the distance to the failure place, the transport type, the landscape, road condition, the season, and the time of day;
  • t repair . switch —time required to switch necessary equipment;
  • t repair . permit —time required to obtain a permit for the work of a repair brigade. It depends on the work complexity as it impacts the preparation time of the workplace, that is, the implementation of technical measures to perform safe work;
  • t repair . work —time required to carry out direct repair work. It depends on brigade staff (quantitative and qualitative ones) and equipment with the appropriate tools and devices, along with the complexity of work;
  • t repair . complet —time required for the completion of work, the cleaning of a workplace, the exit of a repair brigade from a workplace, documenting the completion of work.
The time of the connection harmonization t harmonize can be described using this equation [33]:
t harmonize = t inf . transfer + t pre . connect + t connect + t ensure
where
  • t inf . transfer —time required for information transfer time to a dispatching office the need to connect repaired equipment;
  • t pre . connect —time required to prepare the equipment connection and to document this;
  • t connect —time of equipment connection. It depends on the network diagram, the type of devices used for switching on, the distance from the personnel carrying out the switching up to the switching devices;
  • t ensure —time required to ensure that the equipment was successfully connected.
The literature positions indicate that data on the above time intervals are incomplete or often missed. However, the analysis of these time intervals reveals the potential to realize a reduction of the power supply restoration time that results in the power outages to consumers and the associated failures. Since the diagnostic methods and technical means for obtaining information about failures may be different [34], there are many factors that make it difficult to accurately determine the power supply restoration time and each of its constituents.

4. Results

4.1. Obtaining Information Time

The most correct method of determinization of obtaining information time of failures in electrical networks ( t obt . infor ) is the Delphi method. This method was successfully applied in different researches, e.g., [35,36].
The questionnaire was prepared specifically for this research. It was given to twenty experts working in PS companies (dispatchers). The experts had at least five years employment experience.
This research proposes obtaining information time in 12 intervals. The specialists had to give a score from one to ten for each time interval. The most probable time interval got ten points from experts while the least probable got zero points. In the case that the expert indicates the same time interval probability, they could estimate the time intervals by points. The harmonization degree of the participant of the questionnaire was calculated. For this, a concordance coefficient (Equation (6)) proposed by Kendall was used:
W = 12 × S m 2 × n 3 n , W = 12 × 35.9 × 10 3 20 2 × 12 3 12 = 0.62
where
  • S—the sum of squared differences between the sum of the estimates given by all experts to the i-th time interval ( i = 1 m N i j ) and the arithmetic mean of all the estimates N ¯ ;
  • m—the number of experts surveyed; n is the number of time intervals in the questionnaire;
  • N i j —the score given by the j-th expert to the i-th time interval.
W = 12 × 35.9 × 10 3 20 2 × 12 3 12 = 0.62
The arithmetic mean of all estimates was determined in accordance with the well-known Equation (8):
N ¯ = i = 1 n j = 1 m N i j n N = 172 + 180 + 164 + 135 + 117 + 97 + 71 + 61 + 57 + 41 + 31 + 19 12 = 95.4
The sum of the squares of differences was determined according to Equation (9):
S = i = 1 n ( j = 1 m N i j N ¯ ) 2 S = 5.8 + 7.1 + 4.7 + 1.5 + 0.5 + 0.00256 + 0.6 + 1.2 + 1.5 + 3 + 4.2 + 5.8 × 10 3 = 35.9 × 10 3
Since the time intervals were indicated in the questionnaires, fixed points were chosen for calculating the expectation at each interval. These points corresponded to the middle of the intervals. The mathematical expectation was determined by the following equation:
M t = i = 1 n ( t c i · j = 1 m N i j ) i = 1 n j = 1 m N i j M t = 21.5 + 67.5 + 102.5 + 111.3 + 131.6 + 133.3 + 115.3 + 114.3 + 121.1 + 97.3 + 81.0 + 54.0 1145 = 1.01
where
  • M(t)—the mathematical expectation of the time for obtaining information;
  • tci—the time value of the middle of the i-th interval.
The calculation results are indicated in Table 1.
For clarity, the distribution of expert estimates given to the corresponding time interval is presented in Figure 2.
The mathematical expectation of obtaining information time on failures was 1.01 h with the concordance coefficient of 0.627. In the questionnaires, it was considered that there were no monitoring systems of electric network, i.e., a PS company dispatcher obtained information on failures from the consumers.
This is quite a long time, which can and should be reduced by various means. A proposition to reduce the time may be, e.g., an automatic detection of failures facts and places in electrical networks and unmanned aerial vehicles allowing to monitor the power line state and detect failure places.

4.2. Recognizing Information Time

The present data indicated in the literature that concerns time of recognizing information on failures t rec . infor is not fully explored. However, it is worth noting that this time interval may take 75% of the time of the PS restoration. The Delphi method was also used to determine this time, and there were also 20 experts.
The results of the calculations are summarized in Table 2, the distribution of expert assessments given to this time interval is shown in Figure 3.
The mathematical expectation of a time of recognizing information on failures was indicated as 2.94 h (a concordance coefficient is 0.79).

4.3. Repair Time

This work uses the statistical data of time to repair failures t repair obtained by using the year statistics of a power supply company (“Oreolenergo“) [37]. The used data that concern failures and repair time are summarized in Table 3 and shown in Figure 4.
The values of the mathematical expectation and dispersion of the repair time were determined from this data [5,10,18]. To do this, the sampling mean X B was found out by Equation (11):
X B = 1 n × 1 N i X i × N i X B = 0.25 × 75 + 0.75 × 50 + 1.25 × 29 + 1.75 × 38 + 2.25 × 12 + 2.75 × 3 + 3.25 × 2 + 3.75 × 3 212 = 1
where
  • n —number of failures, n = 212 ;
  • X i i-th repair time for which the calculation is made;
  • N i —frequency of the i-th time value.
Next, the conditional values U i were determined by Equation (12):
U i = X i C h U 1 = 0.25 0.25 0.5 = 0
where
  • C —constant (the repair time with the highest frequency of occurrence), C = 0.25 is for the first time interval;
  • h —scale (the time step h = 0.5 h).
Similarly, other indicators were calculated, and the results are summarized in Table 4.
The conditional sample value U B was determined by Equation (13):
U B = 1 n × 1 N i U i × N i U B = 0 × 75 + 1 × 50 + 2 × 29 + 3 × 38 + 4 × 12 + 5 × 3 + 6 × 2 + 7 × 3 212 = 1.5
The sample value X B through the conditional sample value U B was found by Equation (14):
X B = U B × h + C X B = 1.5 × 0.5 + 0.25 = 1
The value of sample dispersion D B was determined by Equation (15):
D B = 1 n × 1 N i [ X i X B 2 × N i ] D B = 1 212 × 0.25 1 2 × 75 + 0.75 1 2 × 50 + 1.25 1 2 × 29 + 1.75 1 2 × 38 + 2.25 1 2 × 12 + 2.75 1 2 × 3 + 3.25 1 2 × 2 + 3.75 1 2 × 3 = 0.61
Root-mean-square deviation:
δ B = D B δ B = 0.61 = 0.781
The corrected root-mean-square deviation S was found out to obtain a more accurate value of the deviation:
S = n n 1 × δ B S = 212 212 1 × 0.781 = 0.782
The probability of determining the repair time interval was taken to be γ = 0.95 . Therefore, the value for determining the interval is t = 1.96 .
The accuracy of the assessment:
2 F = γ = 0.95 F = 0.475
The estimation deviation:
t × S n = 1.96 × 0.782 212 = 0.105
The boundaries of the confidence interval:
X B t × S n = 1 1.96 × 0.782 212 = 0.895   is   the   lower   interval X B + t × S n = 1 + 1.96 × 0.782 212 = 1.105   is   the   upper   interval
Thus, the time to repair failures was in the interval 1 ± 0.105 h with 95% probability.

4.4. Connection Harmonization Time

The time for the harmonization of the equipment connection t harmonize depends on the applied communication tools, the time for preparing the equipment to be connected and its documentation, the time for equipment connection, and the time needed to ensure that the connection was successful.
The dispatcher must check the possibility of switching on a power line [38]:
  • on records in the operational log and applications;
  • by the telephone book “About the delivery and acceptance of lines”;
  • by the absence of posters on the drives of disconnectors;
  • by interviewing operating personnel of substations and power plants about the absence of working people on the power line equipment which should be switched on.
After that, the command to turn on the equipment is given. In total, the time of connection harmonization can take up to 20 min.

4.5. Analysis Results

Considering the values of time intervals, the PS restoration time was calculated using Equation (1):
t restor . = 1.01 + 2.94 + 1.00 + 0.33 = 5.28   h
The indicated time of power supply restoration based on our analysis is equal to 5.28 h. This duration is significant and can cause considerable material damage to consumers supplied from the electric grid where blackout has occurred especially for those sensitive to process shutdown.

5. Discussion

Annually, the investigated regional power supply company “Oreolenergo“, a branch of IDGC of Center, has an average of 344 power supply outages with a total of 98,495.835 kWh of unsupplied electric power [17]. The total number of power outages includes consumer outages, outages due to damage of overhead lines, cable lines, transformers, equipment of transformer substations, and distribution points. The average power supply restoration time is 5.86 h, which is close to the time obtained based on the performed studies (5.28 h). The deviation is 9.9%. It should be noted that these data on the power supply restoration time are related to failures in power transmission lines, which are the most unreliable element of the power supply systems.
A power supply restoration time of more than 5 h causes significant damage both to consumers and to power supply companies. Opportunities should be sought to shorten this time as much as possible. In most cases, it is difficult, since a noticeable number of power lines especially in rural areas have surpassed their resources and require replacement [39,40]. According to the statistical data of “Oreolenergo” [17], the causes of damage to power lines are shortcomings in maintenance (45%), the influence of natural and weather conditions (33%), the influence of unauthorized persons (15%), other reasons (e.g., birds, animals, etc.) (7%). At the same time, it is indicated that shortcomings in maintenance includes fallen trees and short circuits because of trees touching power line wires caused by untimely cleaning of power line routes, breaks of wires, fallen utility poles, and other causes associated with power line aging and late monitoring of their condition.
The PS restoration time may be reduced by different methods, especially the electrical network automation means. Almost all automation means can reduce the time to perform a particular operation and increase the accuracy of its execution. For example, the time to obtain information and recognize it can be significantly reduced by using a power supply reliability monitoring system or by using means for monitoring the technical condition of an electric network equipment, such as using unmanned aerial vehicles (UAVs) as in the articles [41,42,43,44] or the thesis [45]. Calculations realized in [45] indicated the implementation of the developed power supply reliability monitoring system in the Mtsensky electric grid of the Orel Region, Russian Federation. They showed that the time to obtain information was reduced from 1.01 h to 0.09 h, and the time to recognize information was reduced from 2.30 h to 0.25 h. In [46], UAV tests were described based on the Orelenergo branch of the IDGC of Center, PJSC. They showed that it was possible to achieve a reduction in the time of a PTL round check (the time for recognizing information) from 3.5 h/km to 5…15 min/km, that is, more than 30-fold.
It should be noted that if there are means of sectionalizing and redundancy of power lines such as automatic circuit reclosers (ACR), the time of power supply outages can also be significantly reduced [47,48]. However, in this case, the power supply restoration will be carried out by redundancy means, and the time for this restoration t restor . redund . is determined by the equation
t restor . redund . = t damaged   sec tion   isol . + t backup   power   act .
where t damaged   sec tion   isol . is the time spent on the isolation of the damaged section from intact ones, h; t backup   power   act . is the time spent on backup power actuation, h.
All means of electrical network automation can be classified according to the time intervals that they shorten. This classification is shown in Table 5. Thus, the existing and promising methods and technical means of electrical network automation aim at reducing the specific constituents of the power supply restoration time.

6. Conclusions

The power supply restoration time analysis of power transmission lines shows that it depends on several constituents. The constituents of time restoration analyzed in this study are:
  • time for obtaining information,
  • time for information recognition,
  • time to repair failures,
  • time for connection harmonization.
In this article, the methods of obtaining each of them were proposed and described. The case study calculations were realized for the Russian power supply company “Oreolenergo”. The obtained restoration time was theoretically equal to 5.28 h. This value is equal to the statistical data obtained from the selected power supply company. The result deviation was less than 10%. Additionally, after obtaining the value of PS restoration time, it was proposed how it may be decreased. The proposition of the technical means of electrical network automation was indicated. These means were proposed and ordered in accordance to the time intervals they shorten.
Future research directions will be aimed at numerically estimating the impact of methods and technical means of electrical network automation on the constituents of the power supply restoration time. This will allow evaluating the effectiveness of their introduction by comparing the received values of the power supply restoration time constituents with initial ones and determining the reduction in damage from a lack of electricity supply.

Author Contributions

Conceptualization, A.V. (Alexander Vinogradov); methodology, A.V. (Alexander Vinogradov), and A.V. (Alina Vinogradova); validation, M.J. and T.S.; formal analysis, V.B., M.J., and E.J.; investigation, V.B., A.V. (Alina Vinogradova); resources, A.V. (Alexander Vinogradov); data curation, A.V. (Alexander Vinogradov); writing—original draft preparation, V.B.; writing—review and editing, M.J.; visualization, V.B., A.V. (Alina Vinogradova); supervision, T.S., Z.L., R.G.; project administration, A.V. (Alexander Vinogradov); funding acquisition, Z.L. All authors have read and agree to the published version of the manuscript.

Funding

This research received funding from the Chair of Electrical Engineering Fundamentals (K38W05D02), Wroclaw University of Technology, Wroclaw, Poland.

Conflicts of Interest

The authors declare no conflict of interest.

References

  1. Liu, Y.; Fan, R.; Terzija, V. Power system restoration: A literature review from 2006 to 2016. J. Mod. Power Syst. Clean Energy 2016, 4, 332–341. [Google Scholar] [CrossRef] [Green Version]
  2. Arif, A.; Wang, Z. Service restoration in resilient power distribution systems with networked microgrid. In Proceedings of the 2016 IEEE Power and Energy Society General Meeting (PESGM), Boston, MA, USA, 17–21 July 2016; pp. 1–5. [Google Scholar]
  3. Li, J.; Song, X.; Wang, Y.; Zhang, X.; Tang, W. Service Restoration for Distribution Network Considering the Uncertainty of Restoration Time. In Proceedings of the 2016 3rd International Conference on Systems and Informatics (ICSAI), Shanghai, China, 19–21 November 2016; pp. 188–192. [Google Scholar]
  4. Wang, F.; Chen, C.; Li, C.; Cao, Y.; Li, Y.; Zhou, B.; Dong, X. A Multi-Stage Restoration Method for Medium-Voltage Distribution System with DGs. IEEE Trans. Smart Grid 2017, 8, 2627–2636. [Google Scholar] [CrossRef]
  5. Molaali, M.; Abedi, M. A New Heuristic Method for Distribution Network Restoration and Load Elimination Using Genetic Algorithm. In Proceedings of the 2018 Electrical Power Distribution Conference (EPDC), Tehran, Iran, 9–10 May 2018; pp. 46–51. [Google Scholar]
  6. Gechanga, M.K.; Kaberere, K.K.; Wekesa, C. Optimal power service restoration using artificial bee colony algorithm. Int. J. Sci. Technol. Res. 2019, 8, 1950–1956. [Google Scholar]
  7. Chen, Y.; Yang, P. Bi-level Programming Model for Distribution Generation in Active Distribution Network Considering Static Island Power Supply Restoration Strategy. In Proceedings of the 2019 22nd International Conference on Electrical Machines and Systems (ICEMS), Harbin, China, 11–14 August 2019; pp. 1–6. [Google Scholar]
  8. Fan, Y.; Zi, X.; Jun, L.; Bingbing, L. An integrated power restoration method based on improved genetic algorithm for active distribution network. In Proceedings of the 2017 2nd International Conference on Power and Renewable Energy (ICPRE), Chengdu, China, 20–23 September 2017; pp. 524–528. [Google Scholar]
  9. Mwifunyi, R.J.; Kissaka, M.M.; Mvungi, N.H. Distributed approach in fault localisation and service restoration: State-of-the-Art and future direction. Cogent Eng. 2019, 6. [Google Scholar] [CrossRef]
  10. Yang, Q.; Jiang, L.; Ehsan, A.; Gao, Y.; Guo, S. Robust Power Supply Restoration for Self-Healing Active Distribution Networks Considering the Availability of Distributed Generation. Energies 2018, 11, 210. [Google Scholar] [CrossRef] [Green Version]
  11. Jiang, L.; Yang, Q. Intelligent power supply restoration in power distribution networks with distubuted generation. In Proceedings of the 2016 China International Conference on Electricity Distribution (CICED), Xi’an, China, 10–13 August 2016; pp. 1–6. [Google Scholar]
  12. Haishuang, G.; Liping, Q.; Demin, Y. Research on the Fast Power Restoration Strategy of Distribution Network Based on MAPSO. In Proceedings of the 2017 International Conference on Smart City and Systems Engineering (ICSCSE), Changsha, China, 11–12 November 2017; pp. 175–179. [Google Scholar]
  13. Niu, G.; Zhou, L.; Qu, H.; Xiao, T.; Pei, W.; Qi, Z.; Kong, L. A fast power service restoration method for distribution network with distributed generation. In Proceedings of the 2017 IEEE Transportation Electrification Conference and Expo, Asia-Pacific (ITEC Asia-Pacific), Harbin, China, 7–10 August 2017; pp. 1–6. [Google Scholar]
  14. Abu Talib, D.; Mokhlis, H.; Abu Talip, M.; Naidu, K.; Suyono, H. Power System Restoration Planning Strategy Based on Optimal Energizing Time of Sectionalizing Islands. Energies 2018, 11, 1316. [Google Scholar] [CrossRef] [Green Version]
  15. Khalil, Y.; El-Azab, R.; Abu Adma, M.A.; Elmasry, S. Transmission Lines Restoration Using Resilience Analysis. In Proceedings of the 2018 Twentieth International Middle East Power Systems Conference (MEPCON), Cairo, Egypt, 18–20 December 2018; pp. 249–253. [Google Scholar]
  16. Abbasi, S.; Barati, M.; Lim, G.J. A Parallel Sectionalized Restoration Scheme for Resilient Smart Grid Systems. IEEE Trans. Smart Grid 2019, 10, 1660–1670. [Google Scholar] [CrossRef]
  17. Han, S.; Kim, H.-J.; Lee, D. A Long-Term Evaluation on Transmission Line Expansion Planning with Multistage Stochastic Programming. Energies 2020, 13, 1899. [Google Scholar] [CrossRef] [Green Version]
  18. Yan, J.; Hu, B.; Xie, K.; Tai, H.-M.; Li, W. Post-disaster power system restoration planning considering sequence dependent repairing period. Int. J. Electr. Power Energy Syst. 2020, 117, 105612. [Google Scholar] [CrossRef]
  19. Padmarasan, M.; Babu, R.S. Analysis of Interline Dynamic Voltage Restoration in Transmission Line. In Intelligent Computing in Engineering. Advances in Intelligent Systems and Computing; Springer: Singapore, 2020; pp. 587–595. [Google Scholar]
  20. Kunlong, S.; Jianming, J.; Zongbao, G.; Gongyi, S.; Yue, L. An innovative method for optimization of power system restoration path. In Proceedings of the 2019 Chinese Control and Decision Conference (CCDC), Nanchang, China, 3–5 June 2019; pp. 4225–4230. [Google Scholar]
  21. Prasad, D.; Khan, M.I.; Barua, P.; Agarwal, H. Transmission line restoration using ERS structure. In Proceedings of the 2017 14th IEEE India Council International Conference (INDICON), Roorkee, India, 15–17 December 2017; pp. 1–6. [Google Scholar]
  22. Tian, N.; Dai, J.; Zhu, L.; Wang, Y.; Tan, Z.; Zhong, H.; Liu, B. Corrective short-term transmission maintenance scheduling considering post-contingency restoration. In Proceedings of the 2017 China International Electrical and Energy Conference (CIEEC), Beijing, China, 25–27 October 2017; pp. 699–703. [Google Scholar]
  23. Gao, X.; Chen, Z. Optimal Restoration Strategy to Enhance the Resilience of Transmission System under Windstorms. In Proceedings of the 2020 IEEE Texas Power and Energy Conference (TPEC), College Station, TX, USA, 6–7 February 2020; pp. 1–6. [Google Scholar]
  24. Asheibi, A.; Shuaib, S. A Case Study on Black Start Capability Assessment. In Proceedings of the 2019 International Conference on Electrical Engineering Research & Practice (ICEERP), Sydney, Australia, 24–28 November 2019; pp. 1–5. [Google Scholar]
  25. Lin, T.-C.; Yang, J.-Z.; Yu, C.-S.; Liu, C.-W. Development of a Transmission Network Fault Location Platform Based on Cloud Computing and Synchrophasors. IEEE Trans. Power Deliv. 2020, 35, 84–94. [Google Scholar] [CrossRef]
  26. Tamil Selvan, M.; Malar, K. Challenges faced for installation of emergency restoration system (ERS) in the major natural disaster hit high voltage transmission lines in India. Disaster Adv. 2019, 12, 1–8. [Google Scholar]
  27. Vadivel, K.K. Emergency Restoration of High Voltage Transmission Lines. Open Civ. Eng. J. 2017, 11, 778–785. [Google Scholar] [CrossRef]
  28. Kancherla, S.; Dobson, I. Heavy-Tailed Transmission Line Restoration Times Observed in Utility Data. IEEE Trans. Power Syst. 2018, 33, 1145–1147. [Google Scholar] [CrossRef]
  29. Viawan, F.; Banktavakoli, R. Power System Restoration: Blackstart Studies. In Proceedings of the 2018 Conference on Power Engineering and Renewable Energy (ICPERE), Pittsburgh, PA, USA, 20–24 July 2018; pp. 1–6. [Google Scholar]
  30. Goo, B.; Jung, S.; Hur, J. Development of a Sequential Restoration Strategy Based on the Enhanced Dijkstra Algorithm for Korean Power Systems. Appl. Sci. 2016, 6, 435. [Google Scholar] [CrossRef] [Green Version]
  31. Drouineau, M.; Maïzi, N.; Mazauric, V. Impacts of intermittent sources on the quality of power supply: The key role of reliability indicators. Appl. Energy 2014, 116, 333–343. [Google Scholar] [CrossRef] [Green Version]
  32. Baggini, A. Handbook of Power Quality; John Wiley & Sons: Hoboken, NJ, USA, 2008. [Google Scholar]
  33. Vinogradov, A.; Vasiliev, A.; Bolshev, V.; Semenov, A.; Borodin, M. Time Factor for Determination of Power Supply System Efficiency of Rural Consumers. In Handbook of Research on Renewable Energy and Electric Resources for Sustainable Rural Development; IGI Global: Hershey, PA, USA, 2018; pp. 394–420. ISBN 9781522538677. [Google Scholar]
  34. Vinogradov, A.; Vasiliev, A.; Bolshev, V.; Vinogradova, A.; Kudinova, T.; Sorokin, N.; Hruntovich, N. Methods of Reducing the Power Supply Outage Time of Rural Consumers. In Renewable Energy and Power Supply Challenges for Rural Regions; IGI Global: Hershey, PA, USA, 2019; pp. 370–392. [Google Scholar]
  35. Turoff, M.; Linstone, H.A. The Delphi method-techniques and applications. J. Mark. Res. 2002, 13, 317. [Google Scholar]
  36. Skulmoski, G.J.; Hartman, F.T.; Krahn, J. The Delphi method for graduate research. J. Inf. Technol. Educ. Res. 2007, 6, 1–21. [Google Scholar] [CrossRef]
  37. IDGC of Center. Technical Reports of the Branch of PJSC “IDGC of Center”—“Orelenergo”, 2014–2016; IDGC of Center: Moscow, Russia, 2016. [Google Scholar]
  38. Instruction on the Procedure for Operations during Disconnecting and Connecting 110 kV High-Voltage Power Lines Which are under the Management of a Power Company Dispatcher; PJSC-IDGC of Center: Moscow, Russia, 2013.
  39. Zeng, Y. Introduction to rural power grid problems and solutions. Sci. Technol. Innov. Her. 2013, 7, 138–140. [Google Scholar]
  40. Harish, S.M.; Morgan, G.M.; Subrahmanian, E. When does unreliable grid supply become unacceptable policy? Costs of power supply and outages in rural India. Energy Policy 2014, 68, 158–169. [Google Scholar] [CrossRef]
  41. Jones, D. Power line inspection—A UAV concept. In Proceedings of the IEE Forum on: Autonomous Systems, London, UK, 28 November 2005; Volume 2005, p. 6. [Google Scholar]
  42. Li, Z.; Liu, Y.; Hayward, R.; Zhang, J.; Cai, J. Knowledge-based power line detection for UAV surveillance and inspection systems. In Proceedings of the 2008 23rd International Conference Image and Vision Computing New Zealand, Christchurch, New Zealand, 26–28 November 2008; pp. 1–6. [Google Scholar]
  43. Zhou, G.; Yuan, J.; Yen, I.-L.; Bastani, F. Robust real-time UAV based power line detection and tracking. In Proceedings of the 2016 IEEE International Conference on Image Processing (ICIP), Phoenix, AZ, USA, 25–28 September 2016; pp. 744–748. [Google Scholar]
  44. Chernyshov, V.A.; Semenov, A.E.; Bolshev, V.E.; Belikov, R.P.; Jasinski, M.; Garifullin, M.S. The method of extending drone piloting autonomy when monitoring the technical condition of 6–10 kV overhead power lines. In Proceedings of the E3S Web of Conferences 2019, Kazan, Russia, 18–20 September 2019; Volume 124, p. 02010. [Google Scholar] [CrossRef] [Green Version]
  45. Bolshev, V. Development of Technical Means for Monitoring Power Supply Outages and Voltage Deviation at Inputs of Rural Consumers. Ph.D. Thesis, Federal Scientific Agroengineering Center VIM, Moscow, Russia, 2019. [Google Scholar]
  46. IDGC of Center. Protocol of the Test of an Unmanned Aerial Vehicle for Inspection of Overhead Lines on the Basis of Mtsensky “IDGC of Center”—“Orelehnergo”; IDGC of Center: Moscow, Russia, 2014. [Google Scholar]
  47. Abiri-Jahromi, A.; Fotuhi-Firuzabad, M.; Parvania, M.; Mosleh, M. Optimized Sectionalizing Switch Placement Strategy in Distribution Systems. IEEE Trans. Power Deliv. 2012, 27, 362–370. [Google Scholar] [CrossRef]
  48. Vinogradov, A.; Vinogradova, A.; Bolshev, V.; Psarev, A.I. Sectionalizing and Redundancy of the 0.38 kV Ring Electrical Network. Int. J. Energy Optim. Eng. 2019, 8, 15–38. [Google Scholar] [CrossRef]
Figure 1. The proposed methodology to obtain restoration time for a selected power supply company.
Figure 1. The proposed methodology to obtain restoration time for a selected power supply company.
Energies 13 02736 g001
Figure 2. The histogram that represents the assessment of experts concerning a distribution of the time for obtaining information on failures.
Figure 2. The histogram that represents the assessment of experts concerning a distribution of the time for obtaining information on failures.
Energies 13 02736 g002
Figure 3. The histogram that represents the assessment of experts concerning the distribution of the recognizing information time.
Figure 3. The histogram that represents the assessment of experts concerning the distribution of the recognizing information time.
Energies 13 02736 g003
Figure 4. Number of failures for specific repair time.
Figure 4. Number of failures for specific repair time.
Energies 13 02736 g004
Table 1. The results of the expert survey to determine the time for obtaining information on failures.
Table 1. The results of the expert survey to determine the time for obtaining information on failures.
ExpertsExpert Estimates Given to the i-th Time Interval
Time Intervals, Hours
0.00–0.250.25–0.500.50–0.750.75–1.001.00–1.251.25–1.501.50–1.751.75–2.002.00–2.252.25–2.502.50–2.752.75–3.00
123456789101112
1988784332352
28109655233213
31097864343121
4798765423321
59107843532122
6889675342211
710107564333220
88109655232210
91097864432321
10789654233220
11899756321300
12998675534211
13876754234211
149810765423110
159107886433211
168810676554222
177109866543310
181097756434221
198910655423211
2010108655433111
i = 1 m N i j 17218016413511797716157413119
tci0.1250.3750.6250.8251.1251.3751.6251.8752.1252.3752.6252.875
tci · i = 1 m N i j 21.567.5102.5111.3131.6133.3115.3114.3121.197.381.054.0
i = 1 m N i j N ¯ 76.684.668.639.621.61.6−24.4−34.4−38.4−54.4−64.4−76.4
( i = 1 m N i j N ¯ )25.8 × 1037.1 × 1034.7 × 1031.5 × 1030.5 × 1032.6 × 1030.6 × 1031.2 × 1031.5 × 1033.0 × 1034.2 × 1035.8 × 103
W = 0.627   M(t) = 1.01
Table 2. The results of the survey of experts to determine the time for recognizing information on failures.
Table 2. The results of the survey of experts to determine the time for recognizing information on failures.
ExpertsExpert Estimates Given to the i-th Time Interval
Time Intervals, Hours
0.00–0.500.50–1.001.00–1.501.50–2.002.00–2.502.50–3.003.00–3.503.50–4.004.00–4.504.50–5.005.00–5.505.50–6.00
123456789101112
10013681095210
2113257984321
3012477996232
4112368887411
50012679104220
6123457897530
7014668986320
80024799108511
91155691087422
100233581086310
110144891097411
12002379886310
131146881098321
14113599986222
150023778107400
161335661095530
17023557984421
1811247910107321
190144891097411
20012477996232
i = 1 m N i j 8205579131158184176123673516
tci0.250.751.251.752.252.753.253.754.254.755.255.75
tci · i = 1 m N i j 21568.75138.25294.75434.5598660522.75183.758192
i = 1 m N i j N ¯ −79.8−67.8−32.8−8.843.270.296.288.235.2−20.8−52.8−71.8
( i = 1 m N i j N ¯ )26.4 × 1034.6 × 1031 × 1030.0774 × 1031.9 × 1034.9 × 1039.2 × 1037.8 × 1031.2 × 1030.4 × 1032.8 × 1035.1 × 103
W = 0.79   M(t) = 2.94
Table 3. Number of failures for specific repair time.
Table 3. Number of failures for specific repair time.
Repair time, h.0.00–0.500.50–1.001.00–1.501.50–2.002.00–2.502.50–3.003.00–3.503.50–4.00
Number of failures, pcs.7550293812323
Table 4. Conditional values of the repair time.
Table 4. Conditional values of the repair time.
No interval12345678
U i 01234567
Table 5. Methods and technical means of electrical network automation for reducing the power supply (PS) restoration time.
Table 5. Methods and technical means of electrical network automation for reducing the power supply (PS) restoration time.
Time IntervalMethods and Technical Means of Electrical Network Automation
t obt . infor .
  • Monitoring of the technical condition of electric network equipment;
  • Monitoring of power supply reliability;
  • Telecontrol.
t rec . infor .
  • Monitoring of the technical condition of an electric network equipment;
  • Monitoring of power supply reliability;
  • Monitoring of electric network operation modes;
  • Telecontrol;
  • Means for determining the failure location.
t repair
  • Automation tools (processes digitalization of work authorization of brigades, registration of the beginning and end of work, etc., for example, the “Digital Electrician complex” [15]);
  • Repair work automation.
t harmonize
  • Means for remote communication of the brigade members with the dispatcher and with each other;
  • Monitoring the technical condition of electric network equipment;
  • Monitoring of electric network operation modes;
  • Telecontrol.
t damaged   sec tion   isol .
  • Automatic sectionalizing of power lines;
  • Monitoring the technical condition of electric network equipment;
  • Monitoring of power supply reliability;
  • Telecontrol.
t backup   power   act .
  • Automatic redundancy of power lines and consumers;
  • Monitoring the technical condition of electric network equipment;
  • Monitoring of power supply reliability;
  • Telecontrol.

Share and Cite

MDPI and ACS Style

Vinogradov, A.; Bolshev, V.; Vinogradova, A.; Jasiński, M.; Sikorski, T.; Leonowicz, Z.; Goňo, R.; Jasińska, E. Analysis of the Power Supply Restoration Time after Failures in Power Transmission Lines. Energies 2020, 13, 2736. https://doi.org/10.3390/en13112736

AMA Style

Vinogradov A, Bolshev V, Vinogradova A, Jasiński M, Sikorski T, Leonowicz Z, Goňo R, Jasińska E. Analysis of the Power Supply Restoration Time after Failures in Power Transmission Lines. Energies. 2020; 13(11):2736. https://doi.org/10.3390/en13112736

Chicago/Turabian Style

Vinogradov, Alexander, Vadim Bolshev, Alina Vinogradova, Michał Jasiński, Tomasz Sikorski, Zbigniew Leonowicz, Radomir Goňo, and Elżbieta Jasińska. 2020. "Analysis of the Power Supply Restoration Time after Failures in Power Transmission Lines" Energies 13, no. 11: 2736. https://doi.org/10.3390/en13112736

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop