1. Introduction
Renewable energy sources such as wind power (WP) and photovoltaic power (PVP) are accelerating the replacement of coal, a carbon-intensive fuel. According to the statistics of the Global Wind Energy Commission (GWEC) [
1], the global installed capacity of WP is above 50 GW in 2014–2017. The installed WP capacity of China has accumulated more than 188 GW, ranking first in the world. However, due to the randomness, volatility and intermittent nature of WP, power systems with high penetration wind power face serious “curtailment” problems. In 2017, the quantity of curtailment WP in China was 41.9 billion kWh and the wind curtailment rate was up to 12% [
2]. Wind curtailment problems have seriously hindered the energy production and consumption revolution.
The flexibility of the power system is one of the most factors affecting the large-scale consumption of WP. Currently, there is no uniform standard or definition of power system flexibility (PSF). According to a report issued by the International Energy Agency in 2009 [
3], PSF refers to the rapid response to large power fluctuations on both sides of supply and demand. By adjusting the power generation or load under certain economic cost constraints, the system can quickly respond to foreseeable and unforeseen changes, to maintain the system’s reliability. As increasing levels of WP are integrated in a power system, the flexibility requirements become more severe [
4]. O’Malley et al. believed that the PSF refers to the ability of thermal units to track changes in the net load [
5]. The net load is defined as the residual demand that must be supplied by conventional generation resources after all variable renewable energy generated has been used. To evaluate the PSF, many scholars have proposed corresponding PSF evaluation indicators for different application areas [
4,
5,
6,
7,
8]. The literature [
5] divides the PSF into the upward adjustment flexibility and the downward adjustment flexibility, and a performance evaluation index of the insufficient ramping resource expectation (IRRE) system has been defined. In reference [
6], the influence of network constraints [
9,
10] on the realization of the flexibility of unconstrained factors such as the unit economic dispatch model and transmission resistance plug was analyzed, and the evaluation index defined in the literature in reference [
5,
7] was used to evaluate the PSF.
Besides, instead of using a large amount of historical data to evaluate PSF, dispatch departments are more concerned that the supply of sufficiently flexible resources is available in their generation fleet to enable the reliable operation of the power system under increased WP penetration. In addition to traditional units, demand-side management, energy facilities, interconnections to neighboring power system, and even, renewable energy sources have the potential to contribute significantly to the overall flexibility of a power system. However, under the existing system’s structure and load level, conventional power generation, especially the thermal power unit (TPU), will play a key role in effectively compensating for higher amplitudes and more frequent net load fluctuations [
8,
11,
12,
13]. Thus, it is necessary to quantitatively evaluate the flexibility of the TPU available in the power system. Yasuda [
14] proposed a flexibility chart that provides a glimpse into the potential flexibility resources in a power system. Reference [
15] listed the operating range of each generator and the rate of ramping up and down of each generator to determine the total lifting capacity available per hour in the power system. Literature [
8] considered the operating range, ramping capabilities, start-up and shut-down times, and minimum up and down times characteristics of the generator; and used the analytic hierarchy process (AHP) [
16] to quantitatively evaluate the flexibility resources of the system. However, these documents only considered the technical characteristics of the TPU and did not take into account the economic characteristics of the TPU and only subjectively judged the flexibility of the TPU. They did not consider the objective aspect of the power system.
Recently, many experts and scholars have tried to deal with the unit commitment (UC) problems in a modern power system with WP and the TPU. The UC problem is a highly constrained, large-scale mixed integer nonlinear programming problem [
17]. The development of methods with high speed and high quality has been the focus of important research over the past few decades. The main methods for solving this problem now include prioritization, branching, dynamic programming, and Lagrangian relaxation algorithms, etc. [
17,
18]. Unfortunately, the low degree of WP forecast accuracy poses significant challenges in achieving the dual objective of having a reliable and economically efficient system operation. To address these challenges, advanced scheduling strategies have evolved over the past years, including deterministic and stochastic methods. The WILMAR project [
19] developed a stochastic scheduling tool to examine the impact of the variability of wind in energy markets. In reference [
20], by comparing the deterministic and stochastic methods, the impacts of modeling the uncertainty of wind on different timescales and modeling more of the uncertainty were examined. Based on the traditional UC model, the scenario-based stochastic UC generates multiple deterministic scenarios based on the distribution of uncertain variables to solve the UC problem, but even when advanced scenario reduction techniques are used, the presence of multiple scenarios increases the computational complexity and simulation time [
21,
22,
23]. The uncertain and variable nature of WP in modern power systems raises significant challenges in achieving the dual objective of having a reliable and economically efficient system operation. Considering the uncertainty of WP, reference [
24] employed optimal wind power confidence intervals in a traditional UC model to balance the economic costs and risks of the dispatch plan for the power system with WP integration. In order to reduce the imbalance of electric power supply and demands caused by WP forecast error, chance-constrained dependent chance goal programming was introduced into UC model in reference [
25]. However, these studies neglect the flexibility of the power unit itself which will make the generation companies confused in the electricity bidding market. For example, if two identically-rated capacity units of different generation companies are scheduled to produce different amounts of power, companies that generate less electricity will complain about unfairness without realizing that their units are not flexible.
Based on this, in order to compensate for the more frequent net load fluctuations and make the scheduling plan more transparent, it may be necessary to consider incorporating the flexibility of the TPU into the scheduling of power systems with significant wind penetration. In this paper, under the existing power structure and load level, the economics and flexibility of the system are considered by optimizing the unit commitment and economic dispatching scheme. Compared with existing work, the main contributions of the paper are summarized as follows:
- (1)
Considering both subjective and objective factors, a comprehensive evaluation index system for TPU flexibility is designed which covers the technical and economic characteristics of TPU.
- (2)
A power system optimal scheduling model that considers the flexibility of each unit is proposed. The model takes both the economics and flexibility of the system operation into account which compensates for the greater amount of net load fluctuations and makes the scheduling plan more transparent.
- (3)
The model presented in this article can increase the market competitiveness of flexible units and thus increase the power system flexibility.
The rest of this paper is organized as follows:
Section 2 presents the flexible regulation characteristics of TPU, including technical and economic characteristics. In
Section 3, by using AHP and the entropy method, the TPU flexibility comprehensive evaluation index system is formulated.
Section 4 establishes a power system optimal scheduling model that considers the flexibility of each unit.
Section 5 provides numerical results from case studies using an illustrative 10-unit system, and this paper is concluded in
Section 6.
3. TPU Flexibility Evaluation Index System
The method of multiple indexes was used to analyze the TPU flexibility, because it is closely related with many factors. Composite metrics have been extensively used in diverse fields, such as economic, environmental, and technological performance, and have recently been applied to the power industry [
28]. Reference [
8] used AHP to quantitatively evaluate the flexibility resources of a power system, but did not consider the objective aspect. In this paper, the AHP-entropy method was used to calculate the index weight of TPU flexibility considering both subjective and objective factors. On the one hand, through the subjective judgment of experts by AHP, the knowledge and work experience can be better integrated into the weight coefficient decision. On the other hand, based on the amount of information provided by each indicator of the TPU, the entropy method was used to determine the objective index weight. Then, the comprehensive weight model was established.
3.1. Analytic Hierarchy Process
Saaty [
29] provided a theoretical foundation for the AHP, that is, a decision support tool which can be used to solve complex decision problems by taking into account tangible and intangible aspects. The analytic hierarchy process (AHP) is generally divided into the following four steps:
3.2. Entropy Method
Entropy was originally a term used in thermodynamics, and it is a measure of information in information theory. The entropy method mainly uses observation data provided by the index to avoid the disadvantages of the subjective weighting method. It is a method of objective weighting. The method of determining the weight coefficient is given by using the concept of entropy as follows:
A m × n observation data matrix (uij) was established, and represents the observation data of the j-th index of the evaluation object (i). For indicator j, the greater the difference in uij, the more information that indicator j contains, which means the weighting factor of indicator j is greater. The steps for determining the index weight coefficient by the entropy method are as follows:
Calculate the feature weight of the
i-th evaluated object under the
j-th index:
Calculate the entropy value (
ej) of the
j-th indicator:
Calculate the difference coefficient matrix of the indicator:
Calculate the weight coefficient:
3.3. Construction of the Comprehensive Weighting Model
The AHP mainly reflects the subjective judgment of the evaluator on the flexibility of the TPU, and the entropy method dynamically analyzes the observation data of all units in the dispatching range to make the result more objective. Both methods have their own advantages. The weight coefficients calculated by these two methods are more objective and scientific. The steps for the construction of the comprehensive weighting model are as follows:
This paper uses the commonly used Lagrangian multiplier method for comprehensive empowerment:
where
wj is the calculated comprehensive weight coefficient.
The assembly model used in this paper is a linear “addition” integrated assembly model.
where
Flexi is the comprehensive flexibility evaluation score of TPU
i;
n is the total number of indicators;
xij is the observation value of index
j of TPU
i.