Figure 1.
Typical Hydropower Dam Components for Risk Assessment (CDA, 2011).
Figure 1.
Typical Hydropower Dam Components for Risk Assessment (CDA, 2011).
Figure 2.
A Bowtie Diagram Visualizing Risk Elements and Risk Measures.
Figure 2.
A Bowtie Diagram Visualizing Risk Elements and Risk Measures.
Figure 3.
Influence of controls on different components of the risk pathway.
Figure 3.
Influence of controls on different components of the risk pathway.
Figure 4.
Hierarchy of organizational objectives considered in the case study.
Figure 4.
Hierarchy of organizational objectives considered in the case study.
Figure 5.
Hierarchy of Organization’s Objectives.
Figure 5.
Hierarchy of Organization’s Objectives.
Figure 6.
Illustration of the many-to-many relationships between hazards, risk events, and their impacts on objectives.
Figure 6.
Illustration of the many-to-many relationships between hazards, risk events, and their impacts on objectives.
Figure 7.
Effect of activity and gate durations on likelihood of visible and hidden hazards.
Figure 7.
Effect of activity and gate durations on likelihood of visible and hidden hazards.
Figure 8.
Synthesized likelihoods of unexpected changes in water level and water flow for different activity and location combinations at the case study dam site.
Figure 8.
Synthesized likelihoods of unexpected changes in water level and water flow for different activity and location combinations at the case study dam site.
Figure 9.
Event vulnerability to unexpected water level and flow hazards while performing activities.
Figure 9.
Event vulnerability to unexpected water level and flow hazards while performing activities.
Figure 10.
Event likelihood to due to unexpected change in water level and flow hazards.
Figure 10.
Event likelihood to due to unexpected change in water level and flow hazards.
Figure 11.
Event Likelihoods.
Figure 11.
Event Likelihoods.
Figure 12.
Organization Objectives and their ratio scale priorities.
Figure 12.
Organization Objectives and their ratio scale priorities.
Figure 13.
Consequences of events to objectives.
Figure 13.
Consequences of events to objectives.
Figure 14.
Event impacts on objectives.
Figure 14.
Event impacts on objectives.
Figure 15.
Overall Event Impacts.
Figure 15.
Overall Event Impacts.
Figure 16.
Risk Map showing Event Risks at Damsite. Color contours are for visual guidance only and do not represent risk thresholds or acceptance criteria.
Figure 16.
Risk Map showing Event Risks at Damsite. Color contours are for visual guidance only and do not represent risk thresholds or acceptance criteria.
Figure 17.
Illustrative bowtie showing relative component weights within the risk pathway.
Figure 17.
Illustrative bowtie showing relative component weights within the risk pathway.
Figure 18.
Frequency Distribution of Losses.
Figure 18.
Frequency Distribution of Losses.
Figure 19.
Loss Exceedance Curve.
Figure 19.
Loss Exceedance Curve.
Figure 20.
Risk Heat Maps with Three Selected Boom Controls. Color contours are for visual guidance only and do not represent risk thresholds or acceptance criteria.
Figure 20.
Risk Heat Maps with Three Selected Boom Controls. Color contours are for visual guidance only and do not represent risk thresholds or acceptance criteria.
Figure 21.
Risk Heat Maps with 24/7 Video Surveillance Control. Color contours are for visual guidance only and do not represent risk thresholds or acceptance criteria.
Figure 21.
Risk Heat Maps with 24/7 Video Surveillance Control. Color contours are for visual guidance only and do not represent risk thresholds or acceptance criteria.
Figure 22.
Loss Exceedance Curve with the 24/7 Video Surveillance control.
Figure 22.
Loss Exceedance Curve with the 24/7 Video Surveillance control.
Figure 23.
Risk Maps showing Event Risks after applying controls at Damsite for 10-year timeframe. Color contours are for visual guidance only and do not represent risk thresholds or acceptance criteria.
Figure 23.
Risk Maps showing Event Risks after applying controls at Damsite for 10-year timeframe. Color contours are for visual guidance only and do not represent risk thresholds or acceptance criteria.
Figure 24.
Loss exceedance curve corresponding to a budget level of 50 K.
Figure 24.
Loss exceedance curve corresponding to a budget level of 50 K.
Figure 25.
Efficient Frontier of optimal portfolios of controls.
Figure 25.
Efficient Frontier of optimal portfolios of controls.
Figure 26.
F-N Chart with ALARP Regions for Public Safety Fatalities.
Figure 26.
F-N Chart with ALARP Regions for Public Safety Fatalities.
Table 1.
Representative control functions and targeted components of the risk pathway.
Table 1.
Representative control functions and targeted components of the risk pathway.
| Control Measure | Type | Risk Pathway Target (H-V-C) |
|---|
| Signage | Physical | H-C |
| Safety Booms | Physical | H-C |
| Fencing/Barricades | Physical | H-C |
| Audible or Visual Signaling Devices | Physical/Operational | H-V-C |
| 24/7 Video Surveillance | Operational | V |
| Operational Controls (Procedures) | Operational | V-C |
| Security Patrols | Operational | H-C |
| Public Education and Outreach | Educational | H-C |
| Written Notification to Property Owners | Educational | H-C |
Table 2.
Yearly rates of activity hazards with all likelihoods assumed to occur at least once within a 10-year period.
Table 2.
Yearly rates of activity hazards with all likelihoods assumed to occur at least once within a 10-year period.
| Activity Hazard | Headpond | Spillway | Tailrace | Dam Structures |
|---|
| Boating | 5 | 16 | 18 | - |
| Canoeing | 20 | 8 | 6 | - |
| Swimming | 20 | 6 | 7 | - |
| Portaging | 30 | 15 | 12 | - |
| Fishing | 15 | 28 | 22 | - |
| Accessing Dam | - | - | - | 5 |
Table 3.
Assumptions used in Monte Carlo simulations to estimate likelihoods of being exposed to unexpected change to hydraulic hazards (change in water level or flow) while performing certain activities.
Table 3.
Assumptions used in Monte Carlo simulations to estimate likelihoods of being exposed to unexpected change to hydraulic hazards (change in water level or flow) while performing certain activities.
| Assumptions | Headpond Activity | Operation |
|---|
Swimming/ Wading | Boating | Canoeing | Fishing from Land | Spilling | Generation |
|---|
| Number of recreationists per 10 year (N) | 20 | 5 | 20 | 15 | |
| Timeframe (T) | 10 years |
| Occurrence Period | 7:00 a.m.–8:00 p.m. |
| Occurrence Mean | 12:00 p.m. |
| Std. Dev. Of Occurrence (hours) | 6 | 8 | 8 | 10 | 6 | 6 |
| Mean of Duration of Activity (hours) | 1 | 2 | 2 | 4 | 7 | 7 |
| Std. Dev. Of Duration (hours) | 0.3 | 1 | 1 | 1 | 1 | 1 |
| Distribution Type | NORMAL |
| Likelihood of hazard exposure (L) | 12% | 17% | 17% | 27% | Obtained from MC simulations |
| Annual Likelihood of unexpected change in water flow during activity | 6.58 × 10−2 | 2.33 × 10−2 | 9.32 × 10−2 | 1.64 × 10−2 | |
Table 4.
Likelihood intensity scale used for hazard occurrence assessment.
Table 4.
Likelihood intensity scale used for hazard occurrence assessment.
| Intensity Name | Value (%) | Description |
|---|
| Almost certain | 99.00 | Almost certain to occur |
| Highly likely | 95.00 | Highly likely to occur |
| Very likely | 90.00 | Very likely to occur |
| More than likely | 80.00 | More than likely to occur |
| Likely | 66.67 | Likely to occur |
| Fifty–fifty | 50.00 | Fifty–fifty to occur |
| One in four | 25.00 | One in four to occur |
| Somewhat unlikely (one in ten) | 10.00 | Somewhat unlikely (one in ten) to occur |
| Unlikely (one in twenty) | 5.00 | Unlikely (one in twenty) to occur |
| Highly unlikely | 1.00 | One in a hundred |
| Extremely unlikely | 0.10 | One in a thousand |
| Will never happen | 0.00 | Virtually impossible |
Table 5.
Vulnerability of events to hydraulic hazards and rationale for assigned values.
Table 5.
Vulnerability of events to hydraulic hazards and rationale for assigned values.
| Hazard | Location | Vulnerability of Event to Hazard (%) | Reason/Comment |
|---|
| Unexpected change in water level | Headpond | 5.00 | Very large reservoir with slow and gradual level changes during spilling and generation. Resulting hydraulic conditions are not considered hazardous enough to trigger the event. |
| | Tailrace | 50.00 | Sudden elevation changes and turbulent, aerated flow may cause canoers to lose balance due to hydraulic conditions. |
| | Spillway | 66.67 | Rapid changes in water level can sometimes cause a canoe to capsize. |
| Unexpected change in water flow | Headpond | 25.00 | Very large reservoir with slow and gradual changes in water level during spilling and generation. |
| | Tailrace | 66.67 | Highly turbulent and aerated flow may cause a canoe to sink. |
| | Spillway | 66.67 | Very turbulent and fast flow likely to cause canoe capsizing. |
Table 6.
Rating Scale for Consequences of Events on Objectives.
Table 6.
Rating Scale for Consequences of Events on Objectives.
| Intensity Name | Value | Description |
|---|
| Extreme | 100% | Detrimental impact on organization objective |
| Significant to extreme | 84.03% | Extreme impact on organization objective |
| Significant | 71.36% | Significant impact on organization objective |
| Considerable to significant | 59.84% | Extreme impact on organization objective |
| Considerable | 52.81% | Considerable impact on organization objective |
| Moderate to considerable | 38.23% | Moderate to considerable impact on organization objective |
| Moderate | 23.31% | Moderate impact on organization objective |
| Low to moderate | 14.16% | Low/moderate impact on organization objective |
| Low | 8.76% | Low impact on organization objective |
| Very Low | 5.34% | Very low impact on organization objective |
| Just a tad | 2.60% | Extremely low impact on organization objective |
| Insignificant | 1.16% | Insignificant impact on organization objective |
| None | 0.00% | No impact to the organization objective |
Table 7.
Likelihood, Impact, and Risk of Events as Percentage and Monetary Value.
Table 7.
Likelihood, Impact, and Risk of Events as Percentage and Monetary Value.
| Risk Event | Likelihood | Impact | Risk |
|---|
| Percentage | Monetary | Percentage | Monetary |
|---|
| [09] Falling into water while fishing resulting in fatality | 57.86% | 50.64% | $12.44 M | 29.30% | $7.20 M |
| [05] Unable to surface while swimming resulting in fatality | 18.15% | 46.20% | $11.34 M | 8.39% | $2.10 M |
[03] Loss of control of canoe resulting in fatality | 10.52% | 50.80% | $12.47 M | 5.35% | $1.31 M |
[01] Loss of control of power boat resulting in fatality | 1.70% | 50.06% | $12.29 M | 3.06% | $752 k |
[11] Jumping/Falling from dam resulting in fatality | 0.26% | 33.81% | $8.30 M | 0.09% | $21 k |
| [07] Falling into water while portaging resulting in fatality | 0.12% | 37.32% | $9.16 M | 0.05% | $11 k |
| Total Risk | 46.23% | $11.35 M |
Table 8.
Reported VPF Values for Canadian Jurisdictions.
Table 8.
Reported VPF Values for Canadian Jurisdictions.
| Jurisdiction | VPF Amount (Million) | In Today’s Dollars (Million) |
|---|
| Treasury Board of Canada Secretariat—2007 [27] | $6.11 | $7.573 |
| Transport Canada—1991 [28] | $1.5 | $2.50 |
| Policy Research Initiative—2007 [26] | $3.5–$9.5 | $11.69 |
Table 9.
Taxonomy of control measures, targeted risk-pathway components, and modeled applications.
Table 9.
Taxonomy of control measures, targeted risk-pathway components, and modeled applications.
| Control Name | Risk Pathway Target (H, V, C) | Applications |
|---|
| Headpond Boom | H-C | 14 |
| Headpond Fence | H-C | 10 |
| Headpond Signage | H-C | 10 |
| Tailrace Boom | H-C | 10 |
| Tailrace Fence | H-C | 10 |
| Tailrace Signage | H-C | 10 |
| Spillway Boom | H-C | 10 |
| Spillway Fence | H-C | 10 |
| Spillway Signage | H-C | 10 |
| 24/7 Video Surveillance | V | 81 |
| Audible Danger Signaling Devices | H-C-V | 73 |
| Operational Controls | V-C | 75 |
| Public Education | H-C | 23 |
| Security Patrols | H-C | 53 |
| Dam Structure Fence | H-C | 2 |
Table 10.
Effectiveness of Headpond Boom in Reducing Likelihood of Hazards.
Table 10.
Effectiveness of Headpond Boom in Reducing Likelihood of Hazards.
| Target Hazard | Effectiveness | Comment |
|---|
| Boating Under Power | 0.6 | Reduces the number of powered boats entering the headpond; accounts for boom failures. |
| Floating debris/Power Boating | 0.3 | Reduces debris intrusion into the headpond, lowering risk to boats already inside. |
| Canoeing | 0.4 | Reduces canoer access; less effective than for motorboats due to ease of bypassing by land. |
| Floating debris/Canoeing | 0.3 | Similar rationale as above. |
| Swimming | 0.4 | Reduces swimmer entry; bypass possible from land without fencing. |
| Floating debris/Swimming | 0.1 | Minimal influence; bypass easy without fence. |
| Fishing from land | 0 | No effect on shore-based activity. |
Table 11.
Control portfolio showing cost, number of applications, and stand-alone risk reduction.
Table 11.
Control portfolio showing cost, number of applications, and stand-alone risk reduction.
| Control Name | Cost [k $] | Stand-Alone Risk Reduction [k $] |
|---|
| Headpond Boom | 1000 | 403 |
| Headpond Fence | 200 | 878 |
| Headpond Signage | 5 | 425 |
| Tailrace Boom | 500 | 439 |
| Tailrace Fence | 200 | 695 |
| Tailrace Signage | 5 | 76 |
| Spillway Boom | 500 | 715 |
| Spillway Fence | 100 | 828 |
| Spillway Signage | 1 | 152 |
| 24/7 Video Surveillance | 30 | 9312 |
| Audible Danger Signaling Devices | 50 | 8966 |
| Operational Controls | 10 | 9027 |
| Public Education | 50 | 356 |
| Security Patrols | 100 | 3500 |
| Dam Structure Fence | 50 | 12 |
Table 12.
Cumulative risk reduction and cost for implementation of all controls.
Table 12.
Cumulative risk reduction and cost for implementation of all controls.
| Scenario | Cost (k $) | Risk Reduction (k $) | Residual Risk (% of Baseline) |
|---|
| All Controls Implemented | 2800 | 11,330 | 0.2% |
Table 13.
Risk reduction with three selected boom controls.
Table 13.
Risk reduction with three selected boom controls.
| Scenario | Cost (k $) | Risk Reduction (k $) | Residual Risk (% of Baseline) |
|---|
| Three Booms Implemented | 2000 | 1600 | 85.8% |
Table 14.
Risk reduction with 24/7 video surveillance control.
Table 14.
Risk reduction with 24/7 video surveillance control.
| Scenario | Cost (k $) | Risk Reduction (k $) | Residual Risk (% of Baseline) |
|---|
| 24/7 Video Surveillance | 30 | 9300 | 17% |
Table 15.
Optimum set of controls under a 50 k budget limit.
Table 15.
Optimum set of controls under a 50 k budget limit.
| Scenario | Cost (k $) | Risk Reduction (k $) | Residual Risk (% of Baseline) |
|---|
| Optimized Portfolio (4 Controls) | 50 | 11,000 | 2% |
Table 16.
Risk Reduction and Control Funding under Increasing Budget Scenarios. The downward arrow (↓) denotes reduction in risk.
Table 16.
Risk Reduction and Control Funding under Increasing Budget Scenarios. The downward arrow (↓) denotes reduction in risk.
| Metric | $5 k | $11 k | $15 k | $21 k | $25 k | $41 k | $45 k | $51 k | $55 k | $91 k |
|---|
| Risk ↓ ($M$) | 0.43 | 9.02 | 9.16 | 9.21 | 9.24 | 11.00 | 11.00 | 11.01 | 11.01 | 11.18 |
| Cost ($k$) | 5 | 10 | 15 | 20 | 25 | 40 | 45 | 50 | 55 | 90 |
| Savings ($M$) | 0.43 | 9.02 | 9.14 | 9.18 | 9.21 | 10.95 | 10.95 | 10.95 | 10.95 | 11.09 |
| Leverage | 86:1 | 902:1 | 610:1 | 460:1 | 369:1 | 275:1 | 244:1 | 220:1 | 200:1 | 124:1 |
| Risk (Ctrl) ($M$) | 11 | 2 | 2 | 2 | 2 | 0.3 | 0.2 | 0.2 | 0.2 | 0.1 |
| 5% Exceed. ($M$) | 19 | 15 | 15 | 15 | 15 | | | | | |
| P(L > $12 M) | 68% | 15% | 14% | 14% | 14% | 2% | 2% | 2% | 2% | 0.4% |
| Headpond Boom | | | | | | | | | | |
| Headpond Fence | | | | | | | | | | |
| Headpond Signage | FUNDED | | FUNDED | FUNDED | FUNDED | | FUNDED | FUNDED | FUNDED | |
| Tailrace Boom | | | | | | | | | | |
| Tailrace Fence | | | | | | | | | | |
| Tailrace Signage | | | | | FUNDED | | | | FUNDED | |
| Spillway Boom | | | | | | | | | | |
| Spillway Fence | | | | | | | | | | |
| Spillway Signage | | | | FUNDED | FUNDED | | | FUNDED | FUNDED | |
| 24/7 Video Surveillance | | | | | | FUNDED | FUNDED | FUNDED | FUNDED | FUNDED |
| Audible Danger Signaling Devices | | | | | | | | | | FUNDED |
| Operational Controls | | FUNDED | FUNDED | FUNDED | FUNDED | FUNDED | FUNDED | FUNDED | FUNDED | FUNDED |
| Public Education | | | | | | | | | | |
| Security Patrols | | | | | | | | | | |