Next Article in Journal
5 MW Wind Turbine Annual Energy Production Improvement by Flow Control Devices
Previous Article in Journal
Assessment of Greenhouse Gas (GHG) Emission from Hydropower Reservoirs in Malaysia
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Proceeding Paper

Karst Detection, Prevention and Correction: A Case Study along the Riyadh Metro Line 3 (Saudi Arabia) †

1
IDOM, Avda. Monasterio de El Escorial 4, 28049 Madrid, Spain
2
Department of Geology, University of Oviedo, Jesús Arias de Velasco s/n, 33005 Oviedo, Spain
*
Author to whom correspondence should be addressed.
Presented at the 2nd International Research Conference on Sustainable Energy, Engineering, Materials and Environment (IRCSEEME), Mieres, Spain, 25–27 July 2018.
Proceedings 2018, 2(23), 1429; https://doi.org/10.3390/proceedings2231429
Published: 6 November 2018

Abstract

:
In the framework of the largest urban-transit system ever built from scratch, the Riyadh Metro Project (6 lines totaling 176 km), a comprehensive investigation was carried out for karst detection, prevention and correction. This case study of the Metro Line 3 (41.6 km) seeks to show how the multi-technique geophysical survey (seismic refraction, electrical resistivity and ground penetration radar down to 40–50 m depth) was found to be a successful tool in detecting karst features. Preventive measures included systematic probing drilling to anticipate karst cavities below foundations (653 piers) and tunnel lining evaluation using 2D finite elements. Finally, this paper provides initial guidance of the corrective techniques used for each engineering challenge, such as cavity filling with grouting, geogrid reinforcement, etc.

1. Introduction

Most of the area of Saudi Arabia lies above soluble sedimentary rocks, with a wide variety of karst features reported in numerous areas, constituting one of the most important geohazards in the Kingdom [1,2]. Various authors have reported high potential of karst caves, sinkholes, endokarst and open fractures causing hazard for construction in Riyadh, the capital [3,4,5,6]. In particular, karst was the most significant risk faced throughout the geotechnical design assessment of the Riyadh Metro Project Line 3 (Figure 1).
The Riyadh Metro is the largest urban-transit system ever built from scratch. It is a $23 bn project with a driverless operating system, which comprises 6 lines (176 km), 85 stations (50 underground, 31 elevated and four at-grade), 7 depots and 25 Park & Rides (P&R) with expected completion by the end of 2018. Line 3 is the longest line with 41.6 km, of which 25.7 km are over concrete slab viaducts, 11 km of underground section (including 5.7 km with TBM) and 4.9 km at grade. It includes 22 stations, 2 depots and 5 P&R for users, with a total value of $6 bn and 48 months of expected construction (Figure 2).
This article aims to briefly show how the multi-technique survey used for karst detection enabled us to propose mitigation procedures adapted to the karst structures. Furthermore, it lays out corrective measures which helped achieve reliable, safe and efficient designs and construction works.

2. Methodology

2.1. Detection

An integration of multi-technique geophysical survey was carried out to detect areas with poor engineering properties related to karst features down to 40–50 m depth [7]. This survey included 37.8 km of seismic refraction tomography, conducted with an equipment of 58 geophones of 10 Hz spaced 10 m apart; 39.7 km of electrical resistivity tomography with an instrument of 96 channels using Wenner-Schlumberger configuration; and 39.1 km of ground penetration radar using a system with 100 MHz antenna. On the basis of the results obtained via the geophysical survey, karst presence was confirmed by borehole drilling (with integral logging including measurement of core recovery, Rock Quality Designation, tv images recording, crosshole and downhole tests).

2.2. Prevention

As preventive measures, the ground within the footprint of shallow foundations or beneath base of socketed piles on rock (with a total of 653 viaduct pier foundations) was investigated using probing drilling in anticipation of potential karst cavities below [8]. The drilling was carried out by hydraulic rig using the rotary-percussion method and a minimum diameter of 89 mm to allow for later grouting. The investigation criteria for shallow foundations were based on the size of the footing with 5 to 8 probe holes at the center and corners of each location, which were extended to a depth of twice the footing width. The presence of cavities was identified following a sudden increase of drilling speed. For bored piles socketed in rock, probes were carried out to a depth >3 m below the socket base. In addition, the tunnel lining was evaluated using 2D finite-element software modelled on a circular cavity of 1.5 m diameter to allow of a poor execution of the injections in the back of the ring or due to a complete loss of the injected material.

2.3. Correction

For karst correction, any cavities encountered at rock surface were exposed, cleaned and then filled with concrete to produce a sound footing grade. Based on the results of the preventive investigation at each foundation location, cavities were filled using grout cement. Low injection rates with limited pump-in pressures of 2–5 bar and a water/cement ratio of 0.6 were adopted to maximize grout intake and avoid hydraulic fracturing. This treatment was considered successful when the results obtained from additional cored boreholes carried out 7 days after completion confirmed that the voids were filled. Geogrid reinforcement for pavements and embankments constructed over voids and cavities was also prescribed. Deep foundations on rock were used to circumvent large cavities at site.

3. Results

Following the geophysical and geotechnical investigation, the preventive programme including probing drilling showed the presence of cavities under viaduct foundations, allowing later grouting. In case of karst cavity detection, the number of probeholes was increased around the main holes in order to confirm lateral extension. Finally, cored boreholes were drilled to confirm proper grouting of cavities which also enabled laboratory tests on grouted samples to be carried out (Figure 3).
The evaluation of the cavity in various positions (intersecting the tunnel crown, the sidewall and the invert of the tunnel) confirmed the design of the tunnel lining in terms of geometry and ring reinforcement even for the most stressed section (Figure 4). Long term necessity requires that these cavities must be grouted in order to ensure segmental lining behavior.

4. Conclusions

The geotechnical investigation, prevention and correction methodology carried out along the Riyadh Metro Line 3 was found to be a time and cost-effective tool to minimize the risk involved in construction in karstic terrain. However, this risk cannot be fully addressed and specific measures should be taken when designing infrastructure construction projects in karstic areas. Given the possibility of small karstic cavities (which could remain undetected even after probeholes and geophysical surveys), lower values of bearing capacity should be considered in order to redistribute stresses evenly around cavities. In addition, the bottom of excavations in rock should be thoroughly inspected by an experienced geologist or geotechnical engineer and any weathered material removed before casting. This case study provides initial guidance on techniques to be used in similar contexts.

Funding

This research received no external funding.

Acknowledgments

We thank IDOM Consulting, Engineering, Architecture, S.A.U. for supporting this research and especially all the staff involved in the design of the Line 3. Also, the authors gratefully acknowledge Saudi Arabia’s Riyadh Development Authority (RDA) promoting the Riyadh Metro Project and especially ArRiyadh New Mobility Consortium (ANM) selected to deliver the Package 2—Line 3.

References

  1. Al-Refeai, T.; Al-Ghamdy, D. Geological and geotechnical aspects of Saudi Arabia. Geotech. Geol. Eng. 1994, 12, 253–276. [Google Scholar] [CrossRef]
  2. Amin, A.A.; Bankher, K.A. Karst Hazard Assessment of Eastern Saudi Arabia. Nat. Hazards 1997, 15, 21–30. [Google Scholar] [CrossRef]
  3. Youssef, A.M.; Al-Harbi, H.M.; Gutiérrez, F.; Zabramwi, Y.A.; Bulkhi, A.B.; Zahrani, S.A.; Bahamil, A.M.; Zahrani, A.J.; Otaibi, Z.A.; El-Haddad, B.A. Natural and human-induced sinkhole hazards in Saudi Arabia: Distribution: Distribution, investigation, causes and impacts. Hydrogeol. J. 2016, 24, 625–644. [Google Scholar] [CrossRef]
  4. Abd El-Aal, A. Identification and characterization of near surface cavities in Tuwaiq Mountain Limestone, Riyadh, KSA, “detection and treatment”. Egypt. J. Pet. 2017, 26, 215–223. [Google Scholar] [CrossRef]
  5. Abd El-Aal, A.K. Geomechanical Aspects and Suitability of the Limestone (Sulaiy Limestone Formation) for Foundation Bedrock, Sulaiy Region, Saudi Arabia. J. Geol. Geophys. 2015, 4, 1–5. [Google Scholar]
  6. Abdeltawab, S. Karst Limestone Geohazards in Egypt and Saudi Arabia. Int. J. Geoeng. Case Hist. 2013, 2, 258–269. [Google Scholar]
  7. Cueto, M.; Olona, J.; Fernández-Viejo, G.; Pando, L.; López-Fernández, C. Karst-induced sinkhole detection using an integrated geophysical survey: A case study along the Riyadh Metro Line 3 (Saudi Arabia). Near Surf. Geophys. 2018, 16, 270–281. [Google Scholar] [CrossRef]
  8. Ahmad, S.F. Managing Sinkholes at Project Site, A Saudi Arabian Case History. In Proceedings of the Fifth International Conference on Case Histories in Geotechnical Engineering, New York, NY, USA, 13–17 April 2004; pp. 1–9. [Google Scholar]
Figure 1. Different karst features found during the construction of the Riyadh Metro Line 3: (a) cave in Jubaila Fm. at the West Depot; (b) epikarst in Sulaiy Fm. at an open excavation and (c) endokarst following an interbedded dolomite layer in Jubaila Formation at the western end of Line 3 (RDA-ANM-IDOM).
Figure 1. Different karst features found during the construction of the Riyadh Metro Line 3: (a) cave in Jubaila Fm. at the West Depot; (b) epikarst in Sulaiy Fm. at an open excavation and (c) endokarst following an interbedded dolomite layer in Jubaila Formation at the western end of Line 3 (RDA-ANM-IDOM).
Proceedings 02 01429 g001
Figure 2. Riyadh Metro Project layout showing the different types of sections and stations with different colors depending on their type along the Line 3 (RDA-ANM-IDOM).
Figure 2. Riyadh Metro Project layout showing the different types of sections and stations with different colors depending on their type along the Line 3 (RDA-ANM-IDOM).
Proceedings 02 01429 g002
Figure 3. Probehole drilling and grouting on the footprint of a shallow foundation: (a) hydraulic rig using the rotary-percussion method; (b) probehole record with karst detection from 5.6 to 9.4 m depth; (c) location of 6 probeholes (A to E) on the shallow footing of 6 × 6 m, with red crosses marking the holes with karst where four additional probeholes were drilled to check for lateral extension of the cavity; (d) core box from confirmatory borehole to check the grouting (RDA-ANM-IDOM).
Figure 3. Probehole drilling and grouting on the footprint of a shallow foundation: (a) hydraulic rig using the rotary-percussion method; (b) probehole record with karst detection from 5.6 to 9.4 m depth; (c) location of 6 probeholes (A to E) on the shallow footing of 6 × 6 m, with red crosses marking the holes with karst where four additional probeholes were drilled to check for lateral extension of the cavity; (d) core box from confirmatory borehole to check the grouting (RDA-ANM-IDOM).
Proceedings 02 01429 g003
Figure 4. Tunnel Lining evaluation: (a) Plaxis 2D model; (b,c) structural verification of ring with cavity 1.5 m in terms of bedding moment and axial force (RDA-ANM-IDOM-ROCKSOIL).
Figure 4. Tunnel Lining evaluation: (a) Plaxis 2D model; (b,c) structural verification of ring with cavity 1.5 m in terms of bedding moment and axial force (RDA-ANM-IDOM-ROCKSOIL).
Proceedings 02 01429 g004
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Cueto, M.; De la Puente, P.; López-Fernández, C.; Pando, L.; Arias, D. Karst Detection, Prevention and Correction: A Case Study along the Riyadh Metro Line 3 (Saudi Arabia). Proceedings 2018, 2, 1429. https://doi.org/10.3390/proceedings2231429

AMA Style

Cueto M, De la Puente P, López-Fernández C, Pando L, Arias D. Karst Detection, Prevention and Correction: A Case Study along the Riyadh Metro Line 3 (Saudi Arabia). Proceedings. 2018; 2(23):1429. https://doi.org/10.3390/proceedings2231429

Chicago/Turabian Style

Cueto, Manuel, Pablo De la Puente, Carlos López-Fernández, Luis Pando, and Daniel Arias. 2018. "Karst Detection, Prevention and Correction: A Case Study along the Riyadh Metro Line 3 (Saudi Arabia)" Proceedings 2, no. 23: 1429. https://doi.org/10.3390/proceedings2231429

APA Style

Cueto, M., De la Puente, P., López-Fernández, C., Pando, L., & Arias, D. (2018). Karst Detection, Prevention and Correction: A Case Study along the Riyadh Metro Line 3 (Saudi Arabia). Proceedings, 2(23), 1429. https://doi.org/10.3390/proceedings2231429

Article Metrics

Back to TopTop