Next Article in Journal
Antimicrobial Peptides in Food Systems: Classification, Mechanism, and Industrial Application
Previous Article in Journal
Direct Irradiation Absorption by Nanofluids: A Proposal of Standardization by the Use of the “Solar Wall”
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

External Characteristic Modeling and Cluster Aggregation Optimization for Integrated Energy Systems

1
State Grid Shanghai Electric Power Company, Pudong New Area, Shanghai 200120, China
2
School of Economics and Management, North China Electric Power University, Beijing 102206, China
*
Author to whom correspondence should be addressed.
Processes 2026, 14(3), 526; https://doi.org/10.3390/pr14030526
Submission received: 5 December 2025 / Revised: 26 January 2026 / Accepted: 28 January 2026 / Published: 3 February 2026
(This article belongs to the Section Energy Systems)

Abstract

With the advancement of the dual carbon goals and the rapid increase in the proportion of new energy installations, the power system faces multiple challenges including insufficient flexibility resources, intensified fluctuations in generation and load, and reduced operational safety. Integrated energy systems (IESs), serving as key platforms for integrating diverse energy sources and flexible resources, possess complex internal structures and limited individual regulation capabilities, making direct participation in grid dispatch and market interactions challenging. To achieve large-scale resource coordination and efficient utilization, this paper investigates external characteristic modeling and cluster aggregation optimization methods for IES, proposing a comprehensive technical framework spanning from individual external characteristic identification to cluster-level coordinated control. First, addressing the challenge of unified dispatch for heterogeneous resources within IES, this study proposes an external characteristic modeling method based on operational feasible region projection. It constructs models for the active power output boundary, marginal cost characteristics, and ramping rate of virtual power plants (VPPs), enabling quantitative representation of their overall regulation potential. Second, a cluster aggregation optimization model for integrated energy systems is established, incorporating regional autonomy. This model pursues multiple objectives: cost–benefit matching, maximizing renewable energy absorption rates, and minimizing peak external power purchases. The Gini coefficient and Shapley value method are introduced to ensure fairness and participation willingness among cluster members. Furthermore, an optimization mechanism incorporating key constraints such as cluster scale, grid interaction, and regulation complementarity is designed. The NSGA-II multi-objective genetic algorithm is employed to efficiently solve this high-dimensional nonlinear problem. Finally, simulation validation is conducted on a typical regional energy scenario based on the IEEE-57 node system. Results demonstrate that the proposed method achieves average daily cost savings of approximately 3955 CNY under the optimal aggregation scheme, reduces wind and solar curtailment rates to 5.38%, controls peak external power purchases within 2292 kW, and effectively incentivizes all entities to participate in coordinated regulation through a rational benefit distribution mechanism.

1. Introduction

As the energy structure transformation continues to advance and the low-carbon development of power systems deepens, the role of VPPs as a key vehicle for enhancing energy utilization efficiency and promoting renewable energy integration has become increasingly prominent. Characterized by multi-energy complementarity and efficient coordination, these systems feature complex internal structures and tightly coupled energy flows. Consequently, their direct participation in grid dispatch operations faces numerous challenges, necessitating the development of external characteristic models that can accurately characterize their control capabilities. Furthermore, the limited control capacity of individual IES makes regional-level clustering and coordinated optimization of multiple systems a vital approach to enhancing overall system resilience and operational efficiency. Against this backdrop, accurately characterizing the external operational features of VPPs, establishing cluster aggregation optimization models, and designing equitable and efficient benefit distribution mechanisms have become prominent research focuses and core challenges in the field [1].
While virtual power plants (VPPs) have significantly enhanced the electricity grid, their development still faces numerous challenges. In the field of uncertainty modeling, existing research has primarily employed quantitative methods such as scenario generation, robust optimization, distribution robust optimization, and point estimation. Lin et al. [2] constructed an uncertainty-minimizing operational cost model for cotton field microgrids based on static and dynamic scenarios; Shi et al. [3] established a two-stage stochastic optimization model considering the randomness of hydro, wind, and solar power generation; and Ahmadi et al. [4] addressed wind power uncertainty through scenario trees and developed a stochastic optimization model. To overcome potential optimistic estimation limitations in scenario generation, robust optimization methods have also been employed, such as Zhou et al. [5] who developed a robust optimization model for the uncertainty of prosumer photovoltaic aggregated output, while Erol et al. [6] designed a billing scheme using the Stackelberg game to enhance the robustness of microgrid energy-sharing management. However, these approaches tend to be conservative. Consequently, distributed robust optimization, which combines the advantages of stochastic and robust methods, has gained widespread application: Chen et al. [7] proposed a distributed robust coordinated dispatch method based on the consistent alternating direction of multipliers (ADM) for multi-region integrated energy systems; Li et al. [8] constructed a two-stage distributed robust optimization model based on Wasserstein distance to determine power supply strategies; while [9] introduced this framework into the joint optimization of distribution grids and charging/swapping systems to enhance coordinated dispatch capabilities. Additionally, point estimation methods have been employed for quantifying parameter uncertainties. For instance, Shayegan-Rad et al. [10] addressed multiple uncertain parameters including wind power, electric vehicle behavior, and market prices, while Zamani et al. [11] applied it to modeling uncertainties in electricity prices, power output, and load demand within virtual power plant dispatch.
For scheduling control strategies of various adjustable resources, Tu et al. [12] constructed linear and nonlinear response models and proposed a dynamic economic scheduling strategy incorporating demand-side response. Wang et al. [13] established an interruptible load scheduling model considering user subsidy rates, effectively reducing peak grid loads and system operating costs. Gao et al. [14] constructed a revenue model for controllable load aggregators, comprehensively considering the game relationship between users and aggregators to formulate an optimal compensation pricing strategy for aggregators. Sun et al. [15] reviewed the operational models of foreign aggregators, analyzing the operational mechanisms and dispatch control strategies for multiple types of controllable resources, including controllable loads, energy storage devices, and distributed power sources. Xu et al. [16] proposed a multi-timescale optimization dispatch model accounting for wind power uncertainty and demand response, leveraging demand response to drastically reduce control deviations caused by wind power variability. Do Prado et al. [17] developed a decision model for retail electricity suppliers incorporating short-term demand response to maximize profits in electricity market transactions. Saavedra et al. [18] proposed a flexible load control model based on elastic bands, enabling aggregated responses from large-scale flexible loads. Ryu et al. [19] designed operational strategies for virtual power plants participating in electricity markets, enhancing the flexibility of demand response resources and improving virtual power plant operational revenues. Wang et al. [20] proposed demand response based on real-time electricity prices, maximizing user profits by adjusting total load while alleviating power supply–demand imbalances. Zhang et al. [21] constructed a two-layer model with a single master and multiple slaves to optimize real-time trading strategies for demand-response aggregators. Zare Oskouei et al. [22] proposed a load decomposition algorithm that identifies distinct user electricity consumption behaviors and derives optimal dispatch strategies for demand-response aggregators.
Although existing research has made some progress in modeling external characteristics and cluster aggregation for IES, the following limitations remain: First, when constructing virtual unit models, dynamic cost characteristics and spatiotemporal flexibility are not sufficiently coupled, limiting the accuracy of adjustment potential assessments. Second, multi-objective trade-offs in cluster aggregation lack systematic representation, and insufficient attention is paid to individual execution willingness and benefit distribution mechanisms, affecting model practicality. Third, external feature modeling and cluster aggregation are often treated as independent phases, lacking an integrated optimization framework spanning from individual units to clusters.
To address these gaps, this paper proposes an integrated methodology spanning external feature modeling to cluster aggregation optimization. Section 2 uniformly represents internal system resources as virtual units with power boundaries, marginal costs, and ramp rates to quantify their regulation capabilities; Section 3 constructs a cluster aggregation optimization model considering regional autonomy. Targeting cost–benefit matching, renewable energy integration, and peak external purchase control, it introduces a fair distribution mechanism and employs NSGA-II for solution. Section 4 validates the approach through IEEE-57 node system simulations, demonstrating its effectiveness in reducing average daily costs, minimizing wind and solar curtailment, and controlling peak external electricity purchases. Fair benefit distribution further incentivizes stakeholder participation.

2. Considering the Virtual Energy Storage Integrated Energy System Under High and Low Frequency Decomposition

As an aggregate of multiple heterogeneous internal energy resources, the integrated energy system (IES) features a complex internal structure, making it difficult to directly participate in power grid dispatching. Therefore, it is essential to construct an external characteristic model for the IES, which uniformly equates internal flexible resources to virtual units, thereby quantifying the IES’s overall regulatory potential. The main contents of this model include the following: depicting the active power output boundary of the virtual unit through the projection of the operating feasible region, establishing the marginal cost characteristics of the virtual unit at different output levels, and describing its dynamic response features such as ramping rate. This enables a clear characterization of the IES’s ability to participate in the market or accept dispatching instructions as a whole.
When the IES participates in the market or responds to dispatch instructions as a whole, its internal structure must be taken into account. Considering the feasibility of power decomposition, it can be derived that for a given total output power of the IES p t I E S , the corresponding set of feasible internal flexible resource dispatch schemes is as follows:
p t I E S = P t i F , i F { E S S , C C H P , A C , E B , A P } , t T
where p t I E S represents the flexibility regulation capability of the IES at time t, composed of the regulation capacities of internal multiple resources (kW); E S S denotes distributed energy storage; C C H P represents combined cooling, heating, and power units; A C signifies building air conditioning; E B represents electric boilers; and A P denotes air-source heat pumps. P t i F represents the power of each flexible resource (kW). Meanwhile, regulation resources such as thermal storage, gas boilers, and flexible loads are reflected through the balance of cooling/heating systems and coupled electrical–thermal/cooling devices.
Each flexible resource within the IES is subject to its own operational constraints. The feasible region of each flexible resource’s operation forms a bounded region in the power space. The feasible region of the set of internal flexible resource dispatch schemes for the IES constitutes a high-dimensional space F , as shown in Equation (2):
F : K p t I E S a E min E t = E t 1 + E ( P t i E ) E max   ,   i E { E S S , A C } R k , d o w n i F t P t + t i F P t i F R u p i F t   ,   i F { P V , W , E S S , A C , E B , A P }
where K and a are parameter matrices for the linear operational constraints of flexible resources, corresponding to their technical characteristics; E t and E t 1 represent the energy capacity of distributed storage and building thermal storage at time t and the previous time step, respectively (kWh); E ( P t i E ) denotes the change in energy storage capacity between time t and the previous time step (kWh); and R u p i F and R k , d o w n i F represent the maximum ramp-up and ramp-down rates per unit time for each flexible resource (kW/min). This expression encompasses both linear and nonlinear constraints of various flexibility resources, forming the high-dimensional space F .
Furthermore, the overall output power of the IES can be obtained from the set of internal flexible resource dispatch schemes through power flow calculation. Therefore, a mapping relationship exists between the two. Consequently, the operational feasible region D of the IES is the projection of the feasible region in the high-dimensional space F of the flexible resource which dispatches schemes onto the IES power plane. This section considers only the active-power feasible region. The high-dimensional space F is equivalent to the plane F P , and the operational feasible region D of the IES is equivalent to the active power operational feasible region D P , as shown in Equation (3) and illustrated in Figure 1.
F D , F P D P
The feasible region of the IES’s regulatory potential is generated by reducing the external power purchase load or increasing the external power supply capacity on the basis of the IES’s internal optimal regulatory strategy. Therefore, it is necessary to first solve the optimal operating strategy of the IES and treat it as the system’s baseline load. The optimal operating scheme of the IES has been introduced in Section 3 of this paper, and its solution model is as follows, which will not be repeated here:
min P I E S , t t = 1 T i F C i F , t   ,   i F { P V , W T , E S S , C C H P , E B , G B , A C , A P , T S S , C S S } , t T
where P I E S , t represents the baseline curve of the IES’s electrical energy interaction with the distribution network (kW).
When addressing external regulation demands, the multi-energy resources within the IES will be converted into electrically adjustable resources through power-coupled devices for flexibility regulation. Therefore, this section models the flexibility regulation potential of the IES, solving for the maximum operational feasible region D P of the IES and optimizing the boundaries of the power interaction curve between the IES and the distribution grid.
max / min P I E S , t = E t s u r p l u s ( E t l o a d E t p v E t w t E t e b u y )
E t s u r p l u s = P t e C C H P η e C C H P j U P t j η j P t E S S
where
P I E S , t : Power exchange curve between the IES and the distribution grid at time t (kW).
P t p v , P t w t : Output of PV and wind turbine at time t (kW).
P t e b u y : Electricity purchased from the external grid under optimal system operation cost conditions at time t (kW).
P t s u r p l u s : System net load (kW). Positive values indicate surplus power; negative values indicate power deficit.
η e C C H P : Power generation efficiency of the CCHP unit.
U : Set of electricity-consuming devices within the system (excluding storage devices).
P t j : Output of the j-th electricity-consuming device at time t (kW).
η j : Efficiency of the j-th electricity-consuming device.
P t E S S : Output of the electrical energy storage device at time t (kW). Positive when charging; negative when discharging.
The IES can achieve increases or decreases in electrical load through energy storage charging/discharging and gas–power coupling, possessing bidirectional regulation capability. Therefore, this study treats it as a fixed load plus an independent energy storage unit (a conventional generator capable of negative output) for power flow optimization.
(1) VPU Output Power Boundaries
The upper and lower limits of the power exchange between the IES and the distribution grid are P I E S , t max and P I E S , t min , respectively. Combining these with the baseline P I E S , t from the optimal IES dispatch yields the maximum generation upper limit and maximum consumption upper limit of the IES VPU.
P I E S , t min = P I E S , t max P I E S , t P I E S , t max = P I E S , t min P I E S , t
where P I E S , t min represents the maximum generation power of the VPU in discharge mode at time t (kW), and P I E S , t max represents the maximum consumption power of the VPU in charge mode at time t (kW).
(2) VPU Cost Characteristic Model
Within the VPU’s output boundaries, it is necessary to discuss the cost curve corresponding to different charging/discharging power levels of the VPU. This requires analyzing cost variations under different external electricity purchase constraints based on the operational optimization model. With the objective of minimizing operational cost in the optimization model, and considering regulation demands at different time periods, a load rebound period constraint is added to the original constraints. Combined with Equation (4), the system operational cost C i , t 2 after load increase in a specific period is calculated.
Assuming the increased electrical load in each period does not exceed the maximum regulation potential of a single IES, a linear system load growth coefficient is defined:
r i = i n , i = 1 , 2 , , n
where r i is the load growth coefficient and n is the number of predefined regulation potential levels.
For a single IES, the marginal cost is as follows:
M C t , i = C i , t 2 C 1 E t l o a d 2 E t l o a d = C i , t 2 C 1 f t r i
In the formula,
M C t , i : Marginal cost of the system when load is increased to level at time t (CNY/kW).
C i , t 2 : System operational cost at time t under regulation demand level i (CNY).
C 1 : Optimized system operational cost (CNY).
E t l o a d 2 : Increased system electrical load at time t (kW).
(3) VPU Ramping Rate Characteristics
The VPU ramping rate characteristics include the ramp-up rate and ramp-down rate, representing the maximum increase/decrease in the overall output power of the VPU per unit time relative to the power baseline at that time. That is, when the VPU receives a regulation command at dispatch time t, the maximum increase and decrease in the overall output power at dispatch time  t + 1 are calculated as follows:
P I E S , t u p = ( P I E S , t + 1 P I E S , t )
P I E S , t d o w n = ( P I E S , t P I E S , t + 1 )
P I E S , t u p = P I E S , t + 1 P I E S , t t P I E S , t d o w n = P I E S , t P I E S , t + 1 t
where
P I E S , t + 1 P I E S , t : Ramp-up amount (kW), difference between IES output at t + 1 and baseline at t .
P I E S , t P I E S , t + 1 : Ramp-down amount (kW).
t : Time interval between two dispatch time steps (min).

3. Aggregated Optimization Model for IES Clusters Considering Regional Autonomy

After completing the external characteristic modeling of a single integrated energy system (IES), which uniformly equates its internal multiple resources to a virtual unit with clear output boundaries, cost, and ramping characteristics, this research further focuses on the regional level, constructing an aggregated optimization model for IES clusters considering regional autonomy [23]. The core of this model lies in treating multiple characterized VPPs as dispatchable units for coordinated optimization at a higher level. Aiming to enhance the overall efficiency of the cluster, the model establishes a multi-objective function set including cost–benefit matching degree, maximization of renewable energy consumption rate, and minimization of peak external electricity purchase, while considering key constraints such as cluster scale, VPP dispatch, grid interaction, and resource complementarity. The NSGA-II algorithm is employed to solve this complex multi-objective problem. The solution framework is illustrated in the Figure 2.

3.1. Objective Functions

(1) Cost–Benefit Matching Degree
In IES cluster optimization, the fairness of the “benefit–cost” matching among various entities is a core prerequisite for ensuring the long-term stable operation of the cluster. The Gini coefficient, a classic statistical indicator for measuring distribution inequality, can quantitatively characterize the imbalance degree of the “benefit–cost” differences among multiple entities. This paper constructs an objective function to minimize the Gini coefficient, transforming the fairness requirement into a quantifiable goal, as shown below:
min G = 1 2 n 2 y ¯ i = 1 n j = 1 n ( R i C i ) ( R j C j ) y ¯ = 1 n i = 1 n ( R i C i )
where n is the number of IES entities, R i is the revenue of the i-th IES entity, C i is the cost of the i-th IES entity, and y ¯ is the mean net surplus of all IES entities.
(1) Composition of IES Costs
The cost of an IES entity comprises four parts: energy procurement cost C energy , i , equipment operation and maintenance cost C op , i , auxiliary service cost C aux , i , and grid loss cost C loss , i . The formulas for each component are as follows:
C i = C energy , i + C op , i + C aux , i + C loss , i
C energy , i = t = 1 T P buy , i , t λ elec , t + G buy , i , t λ gas , t + C gen , i , t
where P buy , i , t , G buy , i , t are the electricity and gas purchase amounts of entity i at time t, respectively; λ elec , t , λ gas , t are the electricity and gas market prices at time t, respectively; and C gen , i , t is the power generation cost of distributed generation (e.g., PV, gas turbine) for entity i at time t.
C op , i = k equip Cap k r ( 1 + r ) n ( 1 + r ) n 1 1 T + M op , k , t
where equip is the set of equipment of entity i, Cap k is the installed capacity of equipment k, ris the discount rate, nis the equipment lifespan, and M op , k , t is the maintenance cost of equipment at time t.
C aux , i = t = 1 T P up , i , t λ up , t P dn , i , t λ dn , t
where P up , i , t , P dn , i , t are the upward and downward ancillary service capacities provided by the entity at time t, respectively; λ up , t , λ dn , t are the prices for upward and downward ancillary services at time t, respectively.
C loss , i = t = 1 T P loss , i , t λ elec , t
where P loss , i , t is the grid loss power attributable to entity i at time t, and λ elec , t is the unit price for loss power.
(2) IES Revenue Distribution
Although the aggregation and dispatch optimization model for IES clusters can improve comprehensive resource utilization efficiency from physical and economic perspectives, it does not fully consider the willingness of individual entities to participate, nor does it achieve reasonable benefit distribution among users. Therefore, the Shapley value method from game theory is introduced. It allocates benefits by calculating the average marginal contribution of each member to the participating coalition, reflecting contribution differences, avoiding egalitarianism, and offering good fairness and rationality.
X i ( V ) = S M i W ( S ) · V ( S ) V ( S \ i )
W ( S ) = ( m S ) ! ( S 1 ) ! m !
where
X i ( V ) : Shapley value representing the benefit allocation for individual i in the cooperation.
V : Characteristic function of cooperative, representing the obtained by cooperation among elements.
M i : Set of all subsets containing individual i .
S : Number of elements in subset S .
W ( S ) : Corresponding weighting factor.
m : Total number of elements in the grand coalition.
After calculating the Shapley values of each element with respect to the benefit, the Shapley values of all elements are normalized to obtain the proportion of each element in the total benefit, which is defined as the contribution degree of that element, as shown in Equation (21):
R i = X i / i = 1 m X i
where R i is the benefit allocation result for individual i in the cooperation.
(2) Highest Renewable Energy Consumption Rate
One purpose of optimized aggregation is to promote the consumption of distributed generation. The renewable energy consumption objective for the IES cluster needs to consider both the internal renewable energy consumption within individual IES and the consumption of distributed renewable energy in the distribution network. Therefore, this chapter constructs the following objective function:
max C o n = t = 1 720 | P t I E S + P t g r i d | / [ ( k M Q k I E S + l Z Q l D N E ) h o u r ] P t I E S < 0 ; P t g r i d < 0
C o n : Renewable energy consumption rate of the IES cluster.
P t I E S , P t g r i d : Net load curves of the IES and the IES cluster relative to the distribution grid (kW). Negative indicates surplus generation exported.
Q k I E S : Installed capacity of renewable energy for the k-th IES individual (kW).
Q l D N E : Installed capacity of the l-th distributed renewable energy entity (kW).
h o u r : Monthly utilization hours (h).
(3) Minimum Peak External Electricity Purchase
The aggregation of IES clusters aims to balance internal supply and demand, enhance renewable energy consumption, and reduce pressure on the upper-level grid. This objective is mainly reflected in two aspects: power and energy dependence on the grid. The energy dependence is positively correlated with the renewable energy consumption rate and is not modeled separately here. The power dependence depends on the cluster’s maximum power reserve demand from the upper-level grid, modeled as follows:
min s t a = max P t g r i d
where s t a represents the peak electricity purchase power of the IES cluster from the upper-level grid (kW). In summary, the set of objective functions for optimized aggregation is as follows:
f = min C , max C o n , min s t a
That is, the objective function f represents the optimization goal set for IES cluster aggregation, including minimizing daily average cost, maximizing renewable energy consumption rate, and minimizing peak external electricity purchase.

3.2. Constraints

(1) Cluster Scale Constraints
The primary purpose of IES clusters is to balance the supply and demand of distributed renewable energy and conventional loads through aggregation. Therefore, within a cluster, regional distribution network distributed renewable energy and conventional load entities must exist. IES individuals can be aggregated based on regulation demands and supply-demand needs. Meanwhile, the cluster aggregation scale should not be too small to leverage the advantages of IES individuals in enhancing regional grid security and resilience. Thus, the following cluster scale constraints are established:
k = 1 M X k I E S M min k = 1 M d = 1 V l = 1 Z P k I E S X k I E S + P d l o a d X d l o a d P l D N E X l D N E Q k min X d l o a d = 1 ; X l D N E = 1 ; X k I E S [ 0 , 1 ]
where
X k I E S , X d l o a d , X l D N E : State variables indicating whether the k-th IES individual, d-th load entity, and l-th distributed renewable energy entity in the regional distribution network participate in cluster aggregation (binary 0–1 variables).
Considering the purpose of cluster aggregation is to balance load entities and renewable energy entities, X d l o a d and X l D N E are set to 1.
M min : Minimum number of required resources.
Q k min : Minimum electricity consumption in period k (kWh).
(2) Virtual Power Unit Dispatch Constraints
During the IES cluster aggregation process, the regulation strategies for each IES must adhere to its adjustable upper and lower limits and ramping constraints.
P I E S , t , k min P t , k I E S P I E S , t , k max
P I E S , t , k d o w n P t , k I E S P t 1 , k I E S P I E S , t , k u p
where
P I E S , t , k min , P I E S , t , k max : Minimum and maximum electricity purchase power of the k-th IES at time t (kW).
P I E S , t , k d o w n , P I E S , t , k u p : Downward and upward ramping rates of the k-th IES at time t (kW/min).
(3) Cluster Interaction Constraints with the Upper-level Grid
The IES cluster interacts with the upper-level grid through the distribution transformer, which must satisfy the transformer capacity constraint.
P t g r i d P max
| min P t g r i d | P max r e
where P max and P max r e represent the maximum allowed power of the distribution transformer and the maximum renewable energy reverse power flow acceptable by the upper-level grid (kW), respectively.
(4) Curve Fluctuation Rate Constraint
To reduce the requirement for frequency regulation and ramping reserve resources from the upper-level grid for the IES cluster and improve system operational stability, the fluctuation rate of the curve P t g r i d should not be too high.
P t g r i d P t 1 g r i d A V E ( P t g r i d P t 1 g r i d ) θ max
where θ max is the upper limit of the fluctuation rate.
(5) Regulatory Characteristic Complementarity Constraint
To minimize the impact of uncertain factors on the IES cluster and enhance operational stability, the complementarity of regulatory characteristics among various resources should be fully considered during cluster aggregation. The correlation degree between different types of resources is as follows:
β x y = k = 1 n φ ( k ) 1 + Δ x ( k ) / ξ k Δ k Δ y ( k ) / ξ k Δ k / k = 1 n φ ( k )
where
φ ( k ) : Weighting function constructed based on different complementarity requirements (e.g., for active power, response speed, ramping rate) at different time points.
ξ k , ξ k : Standard deviations of resource sequences x ( k ) and y ( k ) , respectively.
The resource complementarity coefficient between resources x and y is then as follows:
γ x y = 1 β x y
In this paper, the resources participating in the aggregate construction include distributed generation, energy storage devices, and flexible loads. Therefore, the overall complementarity coefficient of the aggregate is defined as the sum of complementarity coefficients between different resource pairs, denoted as γ I E S C A .
To ensure complementarity among multiple resources, the constraint is as follows:
γ I E S C A γ min
where γ min is the lower limit for complementarity.

3.3. Solution Algorithm

The IES cluster aggregation optimization model developed in this study constitutes a typical multi-objective, high-dimensional, nonlinear optimization problem. Its complexity manifests in three primary aspects: First, the solution objectives encompass three distinct dimensions—minimizing the daily average cost, maximizing the renewable energy consumption rate, and minimizing the peak of external electricity purchases. Second, the constraint set is extensive and intricate, including cluster scale constraints, virtual power unit dispatch constraints, grid interaction constraints, curve volatility constraints, and complementary regulation characteristics constraints, collectively defining a highly complex feasible solution space. Finally, the model involves a large number of mixed continuous and discrete decision variables, as well as nonlinear relationships arising from the aggregation of individual IES behaviors, which pose significant challenges to traditional optimization algorithms in terms of direct and efficient solving [24].
To address these characteristics, this paper employs the multi-objective genetic algorithm NSGA-II. Its mechanisms of population-based search, non-dominated sorting, and crowding distance computation enable effective handling of complex constraints and the direct acquisition of a well-distributed Pareto optimal set, thereby elucidating the trade-offs among the three objectives. Key algorithm parameters were calibrated through preliminary experimentation to balance convergence and diversity: a population size of 100 and a maximum of 200 generations govern the search scope; a crossover probability of 0.9 and a mutation probability of 0.1 guide the exploration–exploitation balance. Additionally, a convergence stability criterion (improvement in hypervolume indicator < 0.1% over 100 consecutive generations) ensures solution maturity. The overall solution procedure is illustrated in Figure 3.

4. Case Study

4.1. Parameter Input

This chapter selects a typical scenario in a northern distribution network for an application demonstration. The IES cluster aggregation and scheduling model optimization process involves data range disparity issues. Cluster aggregation calculates monthly coupling relationships between resource entities and comprehensive benefits including economics, renewable energy consumption, and independence for cluster partitioning. Cluster scheduling, based on the aggregation results, performs resource dispatch for 24 h to enhance regional distribution network security and resilience. Therefore, this case study inputs monthly hourly load curves for aggregation optimization. The cluster scheduling simulation will use the first 24 h of the monthly data as the operating day to validate the dispatch optimization model. This case is based on the IEEE-57 node test system, configuring 10 conventional load entities, 24 distributed renewable energy entities, and 10 individual IESs to participate in cluster aggregation. The aggregated IES individuals then participate in cluster dispatch to achieve the goal of enhancing regional distribution network security and resilience. The regional distribution network topology and resource entity distribution are shown in Figure 4. Line capacities, impedances, and other information refer to the IEEE-57 node case data.
The verification is carried out by selecting typical scenarios of the northern distribution network. The access status of entities (new renewable capacity, conventional load, IES) at each node in the IEEE-57 topology is detailed in Appendix A, Table A1. To satisfy monthly renewable energy output simulation and regional power flow calculation, the case inputs typical monthly hourly natural resource data and electrical load data at each node [25], as shown in Figure 5 and Figure 6.
Within the individual IESs in the regional distribution network, the configuration of distributed energy equipment varies due to differences in multi-energy demands at the end-users. This case equips the IESs with commonly used equipment such as renewable energy generators, CCHP, heat pumps, electric boilers, air conditioning, and multiple energy storage devices, but the specific configurations differ among IESs. Detailed configurations are shown in Table A2 and Table A3 of Appendix B. Simultaneously, considering the presence of prosumer entities within the distribution network that primarily consume their own generation and feed excess electricity to the grid, their renewable energy configuration is relatively large and often cannot be fully consumed internally, with most surplus power being balanced by feeding it to the upper grid. Therefore, this case also considers the participation of source-side IES forms (prosumers with large RE capacity) in cluster aggregation, which are equipped with significant renewable energy, storage, and controllable power sources. The cooling, heating, and electrical loads for each IES are shown in Appendix B, Figure A1.
After the IES cluster aggregation, the cluster participates in the market clearing of the upper-level grid as a market entity at the 110 kV node. The external electricity purchase price is based on the spot market trading price. Based on the typical scenario analysis of the spot market price in Section 4, the simulated monthly spot market price is shown in Figure 7. The natural gas price is set at 3 CNY/m3 for calculation.

4.2. IES Cluster Aggregation Optimization Simulation

Based on the integrated energy system (IES) cluster aggregation optimization model, this case conducts aggregation optimization and finds a solution using the multi-objective genetic algorithm, performs a simulation in the MATLAB 2022b environment, and finally generates a multi-objective Pareto solution set as shown in Figure 8.
Considering that different combinations of aggregated entities have a certain impact on the initial average daily cost—specifically, fewer aggregated entities result in lower average daily costs, which is inconsistent with the core objective of aggregation optimization—this study conducts optimization by quantifying the average daily cost savings of the aggregate during the optimization process. The genetic algorithm generates a frontier solution set based on the trade-off among multiple objectives. It can be observed from the Pareto solution set that there exists a mutually exclusive relationship between the average daily cost savings and both the wind–solar curtailment rate and the peak power purchase from the grid. This is because prior to aggregation optimization, each individual integrated energy system (IES) has already implemented optimal regulation of its internal resources, and any external guidance will lead to an increase in its operating costs. To simultaneously reduce the wind–solar curtailment rate of the regional distribution network and the peak power purchase from the upper-level grid, this case adopts the Technique for Order Preference by Similarity to Ideal Solution (TOPSIS) method to select the relatively optimal cluster aggregation results. Equal weights are assigned to the three objectives, and the top ten groups of TOPSIS scores are presented in Table 1, where 0 indicates non-participation in cluster aggregation and 1 indicates participation.
In the optimal aggregation scheme, IES2, IES3, IES4, IES6, and IES7 are aggregated with other conventional load and distributed renewable energy entities to form a cluster participating in coordinated distribution network regulation. Based on the VPU characteristic model calculation method, the static regulation boundaries and cost characteristics of the VPUs are obtained, as shown in Figure 9.
The Figure 10 shows that the adjustable range of each VPU varies across different times of the day, reflecting the consideration of flexibility resource coupling across time scales during the IES cluster aggregation process. Economically, the regulation costs of VPUs IES2, IES3, and IES7 vary significantly across different time periods, but within the same time period, the regulation depth has a minor impact on cost. Although the regulation costs of VPUs IES4 and IES6 also vary across time periods, for periods with high regulation costs, the regulation depth does have a certain impact on the regulation cost. Notably, VPUs IES3, IES6, and IES7 all have periods of low-cost or even zero-cost regulation potential. This is due to the zero-cost regulation capability resulting from the charging/discharging timing of internal storage devices, which provides significant space for cluster scheduling optimization.

4.3. IES Cluster Benefit Distribution Simulation

Regarding benefit distribution, this paper utilizes the Shapley value method to distribute the cost savings. Based on the interaction schemes of each VPU, the benefit distribution results are calculated as shown in Table 2. The periods with high demand for urban power system regulation occur between 0:00–8:00 and 22:00–24:00, particularly at 3:00 and 6:00. Therefore, virtual units with greater regulation potential and lower regulation costs during these periods should be allocated higher revenues.

5. Summary

To address the challenges of insufficient flexibility and renewable energy accommodation in power systems under the dual carbon goals, this paper proposes an external characteristic modeling and cluster aggregation optimization method for integrated energy systems (IES). First, an external characteristic model of virtual power plants (VPPs) is constructed via operational feasible region projection, which quantifies their active power output boundaries, marginal costs, and ramping capabilities, thereby providing a computable modeling basis for solving the unified dispatch of heterogeneous resources. Second, a multi-objective cluster optimization model is established with the objectives of cost–benefit matching, renewable energy accommodation rate improvement, and external power purchase peak minimization. The Gini coefficient and Shapley value methods are introduced to ensure fairness and willingness to participate among entities, and the NSGA-II algorithm is adopted for an efficient solution. Simulations based on the IEEE-57 bus system show that this method can achieve an average daily cost saving of approximately 3955 CNY, reduce the wind and solar curtailment rate to 5.38%, control the external power purchase peak below 2292 kW, and effectively incentivize collaborative participation among entities through rational benefit distribution.
This study still has certain limitations. First, the model relies on typical daily data for optimization and does not consider robustness under medium- and long-term market conditions and extreme weather scenarios. Second, the virtual energy storage model is mainly based on electro-thermal coupling and does not thoroughly cover multi-energy carriers such as hydrogen energy. Third, the scope of cluster aggregation is limited by the scale of the simulation system, and its scalability has not been verified in larger actual power grids. Future research will further expand the multi-time-scale coordinated optimization mechanism, explore the dynamic reconfiguration strategy of clusters under high-proportion renewable energy and multi-type energy storage access, and carry out empirical research combined with actual demonstration projects to improve the engineering applicability and system resilience of the method.

Author Contributions

Conceptualization, Z.D. (Zhenlan Dou), C.Z., Y.W., H.D. and D.M.; Methodology, Z.D. (Zhenlan Dou), Y.W., H.D., C.F. and D.M.; Software, Z.D. (Zhenlan Dou) and C.F.; Validation, Z.D. (Zhenlan Dou), C.Z., H.D. and D.M.; Formal analysis, H.D., Z.D. (Zhenxiang Du) and B.X.; Investigation, Y.W. and Z.D. (Zhenxiang Du); Resources, B.X. and C.F.; Data curation, B.X.; Writing—original draft, Z.D. (Zhenlan Dou), C.Z., Y.W., Z.D. (Zhenxiang Du), B.X., C.F. and D.M.; Writing—review & editing, Z.D. (Zhenlan Dou), Y.W., H.D., Z.D. (Zhenxiang Du), C.F. and D.M.; Project administration, Z.D. (Zhenlan Dou), C.Z. and C.F.; Funding acquisition, Z.D. (Zhenlan Dou). All authors have read and agreed to the published version of the manuscript.

Funding

This research was funded by a science and technology project of State Grid Corporation of China (project number 5400-202417200A-1-1-ZN).

Data Availability Statement

The data presented in this study are available on request from the corresponding author.

Conflicts of Interest

Authors Zhenlan Dou, Chunyan Zhang, Bangpeng Xie and Chaoran Fu were employed by the company State Grid Shanghai Electric Power Company. The remaining authors declare that the research was conducted in the absence of any commercial or financial relationships that could be construed as a potential conflict of interest.

Appendix A

Table A1. Subjects accessed by each node.
Table A1. Subjects accessed by each node.
Node IDNew Energy CapacityLoad Connection StatusStatus of Integrated Energy System Connections
PV (kW)WT (kW)Peak Load (kW)Average Load (kW)
10.000.000.000.00External Power Grid
2368.16258.840.000.00IES2
3446.80144.70587.05250.57IES3
4516.450.000.000.00None
50.00140.400.000.00None
6406.10291.640.000.00IES4
7105.96328.98414.06211.98None
8338.26200.950.000.00IES6
9111.87263.040.000.00IES7
10176.61173.420.000.00None
11126.79112.660.000.00None
12102.8777.980.000.00IES10
13263.510.000.000.00None
140.00330.450.000.00None
15542.99188.05540.98242.37IES1
16205.16189.98633.04233.91None
170.000.000.000.00None
180.0077.770.000.00None
20303.870.000.000.00None
210.00100.080.000.00None
22417.090.000.000.00None
26421.4543.55499.68241.86None
290.000.00491.49214.23None
320.0043.140.000.00None
34428.250.000.000.00None
350.000.00506.39280.97None
410.000.00467.44251.30None
450.000.00518.47218.11None
46314.91216.480.000.00None
48102.90217.910.000.00None
500.000.00443.80194.69None

Appendix B

Table A2. Construction of equipment for energy production and conversion within integrated energy systems.
Table A2. Construction of equipment for energy production and conversion within integrated energy systems.
PV Installed Capacity/kWWT
Installed Capacity/kW
CCHPHeat PumpElectric BoilerGas BoilerAir Conditioning
Installed Capacity/kWEfficiencyInstalled Capacity/kWEfficiencyInstalled Capacity/kWEfficiencyInstalled Capacity/kWEfficiencyInstalled Capacity/kWEfficiency
IES11500010004/3/2400400005003.5
IES22000100010004/3/2100042000.950035003.5
IES3100000 500400005003.5
IES450050012004/3/2002000.95003003.5
IES5200020000 100042000.95008503.5
IES6150050015004/3/24004005000.88003.5
IES7150010005004/3/24004000015003.5
IES815005006006/34004000000
IES9200000 0000005003.5
IES10180000 0000006003.5
Table A3. Construction of multiple energy storage devices within integrated energy systems.
Table A3. Construction of multiple energy storage devices within integrated energy systems.
Energy Storage EquipmentIES1IES2IES3IES4IES5IES6IES7IES8IES9IES10
Energy Storage BatteryPower/kW3005003003005000300300300300
Capacity/kWh1200150012001200200001200120012001200
Initial SOC0.50.50.50.50.500.50.50.50.5
Maximum SOC0.90.90.90.90.900.90.90.90.9
Minimum SOC0.10.10.10.10.100.10.10.10.1
Thermal Storage TankPower/kW300030006008000000
Capacity/kWh1500015000240030000000
Initial SOC0.500.500.50.50000
Maximum SOC0.9500.9500.950.950000
Minimum SOC0.0500.0500.050.050000
Ice Storage TankPower/kW30010003000600050003000
Capacity/kWh1500400015000240002000015000
Initial SOC0.50.50.500.500.500.50
Maximum SOC0.950.950.9500.9500.9500.950
Minimum SOC0.050.050.0500.0500.0500.050
Figure A1. Multiple loads of integrated energy systems at each node.
Figure A1. Multiple loads of integrated energy systems at each node.
Processes 14 00526 g0a1

References

  1. Spora, J.T.P.; Yap, K.K.; Shimizu, Y.; Tadokoro, C.; Vladescu, S.-C. Tribological challenges in hydrogen: Solutions for the future energy transition. Int. J. Hydrogen Energy 2026, 203, 153096. [Google Scholar] [CrossRef]
  2. Lin, Y.; Li, L.; Zhang, J.; Wang, J. A scenario-based stochastic model predictive control approach for microgrid operation at an Australian cotton farm under uncertainties. Int. J. Electr. Power Energy Syst. 2024, 159, 110025. [Google Scholar] [CrossRef]
  3. Shi, Y.; Wang, H.; Li, C.; Negnevitsky, M.; Wang, X. Stochastic optimization of system configurations and operation of hybrid cascade hydro-wind-photovoltaic with battery for uncertain medium-and long-term load growth. Appl. Energy 2024, 364, 123127. [Google Scholar] [CrossRef]
  4. Ahmadi, A.; Nabipour, M.; Mohammadi-Ivatloo, B.; Amani, A.M.; Rho, S.; Piran, M.J. Long-term wind power forecasting using tree-based learning algorithms. IEEE Access 2020, 8, 151511–151522. [Google Scholar] [CrossRef]
  5. Zhou, K.; Guo, J.; Zhou, J. Two-stage credit management for peer-to-peer electricity trading in consortium blockchain. IEEE Trans. Ind. Inform. 2023, 20, 3868–3879. [Google Scholar] [CrossRef]
  6. Erol, Ö.; Filik, Ü.B. A stackelberg game-based dynamic pricing and robust optimization strategy for microgrid operations. Int. J. Electr. Power Energy Syst. 2024, 155, 109574. [Google Scholar] [CrossRef]
  7. Chen, F.; Deng, H.; Chen, Y.; Wang, J.; Jiang, C.; Shao, Z. Distributed robust cooperative scheduling of multi-region integrated energy system considering dynamic characteristic of networks. Int. J. Electr. Power Energy Syst. 2023, 145, 108605. [Google Scholar] [CrossRef]
  8. Li, B.; Zhao, H.; Wang, X.; Zhao, Y.; Zhang, Y.; Lu, H.; Wang, Y. Distributionally robust offering strategy of the aggregator integrating renewable energy generator andenergy storage considering uncertainty and connections between the mid-to long-term and spot electricity markets. Renew. Energy 2022, 201, 400–417. [Google Scholar] [CrossRef]
  9. Zhao, X.; Xu, Q.; Yang, Y.; Zhou, G. Distributed distributionally robust optimization of distribution network incorporating novel battery charging and swapping station. Int. J. Electr. Power Energy Syst. 2024, 155, 109643. [Google Scholar] [CrossRef]
  10. Shayegan-Rad, A.; Badri, A.; Zangeneh, A. Day-ahead scheduling of virtual power plant in joint energy and regulation reserve markets under uncertainties. Energy 2017, 121, 114–125. [Google Scholar] [CrossRef]
  11. Zamani, A.G.; Zakariazadeh, A.; Jadid, S. Day-ahead resource scheduling of a renewable energy based virtual power plant. Appl. Energy 2016, 169, 324–340. [Google Scholar] [CrossRef]
  12. Tu, J.; Zhou, M.; Cui, H.; Li, F. An Equivalent Aggregated Model of Large-Scale Flexible Loads for Load Scheduling. IEEE Access 2019, 7, 143431–143444. [Google Scholar] [CrossRef]
  13. Wang, J.; Zhang, F.; Liu, H.; Ding, J.; Gao, C. Interruptible load scheduling model based on an improved chicken swarm optimization algorithm. CSEE J. Power Energy Syst. 2021, 7, 232–240. [Google Scholar] [CrossRef]
  14. Gao, C.; Li, Q.; Li, H.; Zhai, H.; Zhang, L. Methodology and Operation Mechanism of Demand Response Resources Integration Based on Load Aggregator. Autom. Electr. Power Syst. 2013, 37, 78–86. [Google Scholar] [CrossRef]
  15. Sun, W.; Liu, X.; Xiang, W.; Li, H. Master-Slave Game Based Optimal Pricing Strategy for Load Aggregator in Day-ahead Electricity Market. Autom. Electr. Power Syst. 2021, 45, 159–167. [Google Scholar] [CrossRef]
  16. Xu, H.; Chang, Y.; Zhao, Y.; Wang, F. A new multi-timescale optimal scheduling model considering wind power uncertainty and demand response. Int. J. Electr. Power Energy Syst. 2023, 147, 108832. [Google Scholar] [CrossRef]
  17. Do Prado, J.C.; Qiao, W. A stochastic decision-making model for an electricity retailer with intermittent renewable energy and short-term demand response. IEEE Trans. Smart Grid 2019, 10, 2581–2592. [Google Scholar] [CrossRef]
  18. Saavedra, A.; Negrete-Pincetic, M.; Rodríguez, R.; Salgado, M.; Lorca, Á. Flexible load management using flexibility bands. Appl. Energy 2022, 317, 119077. [Google Scholar] [CrossRef]
  19. Ryu, J.; Kim, J. Virtual Power Plant Operation Strategy under Uncertainty with Demand Response Resources in Electricity Markets. IEEE Access 2022, 10, 62763–62771. [Google Scholar] [CrossRef]
  20. Wang, S.; Bi, S.; Zhang, Y.J.A. Demand response management for profit maximizing energy loads in real-time electricity market. IEEE Trans. Power Syst. 2018, 33, 6387–6396. [Google Scholar] [CrossRef]
  21. Zhang, C.; Wang, Q.; Wang, J.; Pinson, P.; Morales, J.M.; Østergaard, J. Real-time procurement strategies of a proactive distribution company with aggregator-based demand response. IEEE Trans. Smart Grid 2018, 9, 766–776. [Google Scholar] [CrossRef]
  22. Zare Oskouei, M.; Zeinal-Kheiri, S.; Mohammadi-Ivatloo, B.; Abapour, M.; Mehrjerdi, H. Optimal Scheduling of Demand Response Aggregators in Industrial Parks Based on Load Disaggregation Algorithm. IEEE Syst. J. 2022, 16, 945–953. [Google Scholar] [CrossRef]
  23. Naval, N.; Sánchez, R.; Yusta, J.M. A virtual power plant optimal dispatch model with large and small-scale distributed renewable generation. Renew. Energy 2020, 151, 57–69. [Google Scholar] [CrossRef]
  24. Liu, H.; Qiu, J.; Zhao, J. A data-driven scheduling model of virtual power plant using Wasserstein distributionally robust optimization. Int. J. Electr. Power Energy Syst. 2022, 137, 107801. [Google Scholar] [CrossRef]
  25. Liang, H.; Pirouzi, S. Energy management system based on economic Flexi-reliable operation for the smart distribution network including integrated energy system of hydrogen storage and renewable sources. Energy 2024, 293, 130745. [Google Scholar] [CrossRef]
Figure 1. Schematic diagram of the feasible domain of an integrated energy system.
Figure 1. Schematic diagram of the feasible domain of an integrated energy system.
Processes 14 00526 g001
Figure 2. Solution of integrated energy system cluster aggregation optimization.
Figure 2. Solution of integrated energy system cluster aggregation optimization.
Processes 14 00526 g002
Figure 3. Operation optimization solution process of integrated energy system.
Figure 3. Operation optimization solution process of integrated energy system.
Processes 14 00526 g003
Figure 4. IEEE-57 grid topology.
Figure 4. IEEE-57 grid topology.
Processes 14 00526 g004
Figure 5. Natural resources in the area where the new energy unit is located.
Figure 5. Natural resources in the area where the new energy unit is located.
Processes 14 00526 g005
Figure 6. Access to electrical loads at each node.
Figure 6. Access to electrical loads at each node.
Processes 14 00526 g006
Figure 7. Spot market tariff distribution.
Figure 7. Spot market tariff distribution.
Processes 14 00526 g007
Figure 8. Integrated energy system cluster aggregation optimization Pareto solving set.
Figure 8. Integrated energy system cluster aggregation optimization Pareto solving set.
Processes 14 00526 g008
Figure 9. Virtual unit capacity and cost characteristics in clusters.
Figure 9. Virtual unit capacity and cost characteristics in clusters.
Processes 14 00526 g009aProcesses 14 00526 g009b
Figure 10. Comparison of cluster cooperation programs.
Figure 10. Comparison of cluster cooperation programs.
Processes 14 00526 g010aProcesses 14 00526 g010b
Table 1. Multi-objective TOPSIS scoring results based on the TOPSIS approach.
Table 1. Multi-objective TOPSIS scoring results based on the TOPSIS approach.
Cluster Aggregation SolutionAverage Daily Cost Savings/CNYWind and Solar Curtailment RateGrid Power Purchase Peak/kWTOPSIS Score
[0,1,1,1,0,1,1,0,0,0]3955.235.38%2292.580.9517
[1,1,1,1,0,1,1,0,1,0]3952.705.68%2451.410.9410
[1,1,1,1,0,1,0,1,1,1]3948.757.78%2150.790.9334
[1,1,1,0,1,1,1,1,1,1]4035.9210.09%2324.480.9317
[0,1,1,1,0,1,1,0,1,1]3931.639.52%2300.950.9315
[1,1,1,1,1,1,1,0,1,0]4033.8710.08%2334.770.9314
[1,1,1,1,1,1,1,0,0,1]4032.4510.93%2316.520.9313
[1,1,1,0,0,1,1,1,1,1]3937.447.90%2811.470.8906
[1,1,1,0,0,1,1,0,1,1]3924.837.85%2905.160.8881
[1,1,1,1,1,1,0,1,0,1]4002.779.98%3041.980.8576
Table 2. Results of the distribution of benefits from integrated energy system clusters.
Table 2. Results of the distribution of benefits from integrated energy system clusters.
BeneficiaryShapley Value Total Benefit (RMB)Benefit Distribution Ratio Benefit Distribution Result (RMB)
Virtual Unit 266,436.523941.8412.48%491.78
Virtual Unit 266,092.055.19%204.73
Virtual Unit 267,050.925.46%1003.77
Virtual Unit 267,010.0224.60%969.71
Virtual Unit 267,372.5732.26%1271.83
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Dou, Z.; Zhang, C.; Wang, Y.; Dong, H.; Du, Z.; Xie, B.; Fu, C.; Meng, D. External Characteristic Modeling and Cluster Aggregation Optimization for Integrated Energy Systems. Processes 2026, 14, 526. https://doi.org/10.3390/pr14030526

AMA Style

Dou Z, Zhang C, Wang Y, Dong H, Du Z, Xie B, Fu C, Meng D. External Characteristic Modeling and Cluster Aggregation Optimization for Integrated Energy Systems. Processes. 2026; 14(3):526. https://doi.org/10.3390/pr14030526

Chicago/Turabian Style

Dou, Zhenlan, Chunyan Zhang, Yongli Wang, Huanran Dong, Zhenxiang Du, Bangpeng Xie, Chaoran Fu, and Dexin Meng. 2026. "External Characteristic Modeling and Cluster Aggregation Optimization for Integrated Energy Systems" Processes 14, no. 3: 526. https://doi.org/10.3390/pr14030526

APA Style

Dou, Z., Zhang, C., Wang, Y., Dong, H., Du, Z., Xie, B., Fu, C., & Meng, D. (2026). External Characteristic Modeling and Cluster Aggregation Optimization for Integrated Energy Systems. Processes, 14(3), 526. https://doi.org/10.3390/pr14030526

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop