2.2. Evaluating Reliability for Individual Building Assessments
The Quality Rating System method proposed here is analogous to that used in FEMA P-695 (
FEMA P-695 2009, Section 3.4, also known as ATC-63). The individual component uncertainties are represented by their assigned Coefficients of Variation (
β factors). For a building performance prediction Equation (such as for the P-695 collapse fragility, or for here, as the damage ratio) that can be represented as a product of multiple components, the uncertainty contribution due to an individual component can be represented by a random multiplier on the estimated system value. Therefore,
The total uncertainty is the result of a chain of multiplication of the uncertainty of individual components that make up the decision process. These are considered to be independent, random variables are represent subjectively determined values reflecting the uncertainty introduced by the modeling decisions. Each of the these can be considered as successive Bayesian updates (
Fenton and Neil 2019) to the prior calculated value from the risk model of added information considered.
Each uncertainty multiplier is assumed to have a lognormal distribution with mean one and standard deviation
βi. This is consistent with prior practice in FEMA P-695 as the basis of the current Edition of ASCE 7, and
Thiel and Zsutty (
2018). For instance,
βi = 0.1 indicates a roughly ±10% change (
e0.1) of the estimated component value or
βi = 0.2 indicates roughly ±22%, etc. This provides an intuitive understanding why the total
β for the process can be represented as the Root Mean Square (RMS) of component
βi values, see
Section 2.3. An alternative Simple Average approach of a simple linear model is presented in the section for those who are not comfortable with the RMS approach. As will be show shown in
Section 2.3, the comparisons of their results are close except that the RMS is more conservative than the alternate Simple Average approach.
These component
βi factors can be estimated without the need of knowing the mean or median values of the respective underlying components. The final combined index must include uncertainty measures for all the components that impact the reliability of the assessment value or score. This value or score is used for the binary conclusions: The building either meets the criteria of the specific requirements used procedure or does not, or the assessed loss value is too high to proceed with an action. The method of aggregation of the uncertainty indices for all of the components of the building assessment will be discussed in
Section 5. This assessment may in terms of: a PML value
1, an evaluation score from a P-154 assessment, an Earthquake Performance Level (I to VII) in terms of compliance to California Existing Building Code (CEBC) requirements or a deficiency list of demand/capacity ratios for individual elements of the structure from ASCE 41 Tier 3 analysis.
The reliability evaluation process used in this paper is an extension of a procedure used in FEMA P-695 for Quantification of Building Seismic Performance Factors, (
Deierlein et al. 2008). Specifically, the problem involved the prediction of building collapse displacement or fragility due to earthquakes, using the results of non-linear time history analyses of selected examples of prototype building structural systems. The key questions addressed were how to assign quality measures of the factors, used in the calculation of collapse displacement, and how these quality of knowledge measures can be combined to relate to the certainty (reliability) of the results of the collapse displacement estimation process? For a given factor (or component) used in the collapse estimation process, a measure of uncertainty (a
β value: 0 <
β < 1) was assigned corresponding to three qualitative levels of Quality of Description of the factor (High, Medium and Low) and three levels of its assessed Quality of Implementation Characteristics (High, Medium and Low). FEMAP-695 Section 3.4 presents a simple matrix, shown in
Table 1, that provides a single quantitative evaluation of
β based on the paired qualitative assessments of: Quality of Implementation (High, Medium, Low) corresponding to a specific description Quality of Component Description Measure (High, Medium, Low). The lower the
β value, the greater the certainty (reliability) of the result; conversely, the higher the
β value, the lower the certainty (unreliability). The means of assigning the required quality measures shall become clear below that presents 3 × 3 matrices for how the pairs of quality for each of the nine components are assigned. An analytically determined numerical value of
β can be can be expressed as a qualitative linguistic term by use of
Table 2 following the numerical upper and lower bounds for each term in the assignment of the linguistic quantitative term. The
β values of
Table 1 are the same as used in P-695 with the exception that P-695 did not make an assignment of a (Low, Low) value, which we call
Bad and assign a
β = 1.0.
A most important advantage of being able to assign a quantitative uncertainty factor βi for each component i used in an evaluation process (analogous to the FEMA collapse displacement as described above), or for our objective of building loss assessment, is that these quantitative βi values (0 ≤ βi ≤ 1) can be combined in a statistically valid procedure to provide the total uncertainty of the result of the evaluation. This was accomplished as discussed above by assuming that the uncertainties are multiplicative in their impacts, and lognormally distributed with mean one. The multiplicative process of lognormal standard deviations of the individual components to be combined as the standard deviations as the Square Root of the Squares; and it does not need knowledge of the mean. It is essential to note that the combinatory process would be quite subjective if the levels of uncertainties were to be left in Qualitative terms.
For the proposed method of evaluating the uncertainty of an assessed damageability or a related Performance Level, the approach described above for the assignment of qualitative uncertainty expressions by the matrices of Table 3 here and similar tables elsewhere, and the corresponding quantitative
βi factors by
Table 1 and
Table 2 is necessary because building damageability assessments are based on varying degrees of professional knowledge and related judgements. The expression of the likelihood for building response and the corresponding degree of uncertainty is based, primarily, on the experience and qualifications of the assessor and on access to information available concerning the specific characteristics of the building and related seismic risks. For a particular building, detailed engineering analyses and on-site materials testing and investigation (such as ASTM E2026 Level 3 investigations) are usually not feasible. Furthermore, actual seismic performance data for current building types is not sufficient to provide accurate empirical prediction. As a consequence, it is necessary to utilize expert judgmental qualitative values as a major basis for loss assessments. At best, these judgmental values are based on experience and information obtained from building construction documents and/or a building visit when possible.
Table 2 gives a simple qualitative ranking based on qualitative terms
Superior,
Good, Fair, Poor and
Bad and their corresponding (judgmentally assigned) qualitative uncertainty measures (
β values). The number (five) of the qualitative terms of
Table 2 has the benefit of being odd such that there is a subjective middle or neutral representation for judgement heuristics.
Table 1 gives how the
β values can be assigned where two descriptors Quality Measure and Implementation Characteristics, refer to the matrices of
Table 3, rather than one judgmental choice made concerning a particular issue, component or step involved in the assessment process where
Table 2 applies.
For a particular building assessment, the
β values of the
Table 1 should be considered as starting values that may be modestly adjusted if the resulting uncertainty evaluation is clearly between the matrix values for a specific use. For example, the assignment of an interim value of 0.275 if the judgement is that an assessment is better than
Fair and less than
Good, or
0.25 if it is closer to
Good than to
Fair. In addition, note that when a particular evaluation from
Table 2 is not sufficiently reliable for the user/client’s purpose, additional analyses and/or investigation expenditures can serve to reduce the initially high
β value such that an acceptable total reliability can be achieved. In many cases it may not be clear that definitive choices can be made in the
Table 1 assignments. If we designate the probability of the Quality Measure as
Pj for the three Measures
j = H, M and
L and as probability
Qk for the Implementation Characteristics, and
βjk be the corresponding
β value in
Table 1 for row
j and column
k, then the appropriate combined
βi value is determined as:
This simple average approach is used to determine the assigned value since we are in essence interpolating between the β values of the component matrix. For example, if the Quality Measure was assigned as Medium with probability 100% and the Implementation Characteristic High with probability 75%, and to Medium with probability 25%, then the β value would be 0.237; if the same probabilities were assigned to both, then the β value would be 0.153. We recommend that when there is complete uncertainty in the characteristics of a Measure or its Implementation, that Poor or Bad is assigned depending on whether there is insufficient or no information on which to evaluate the characteristics.
It is also important to recognize that
Table 1 essentially provides a quantitative way to define the qualitative terms of performance:
Superior, Good, Fair, Poor and Bad. For many cases decision makers may prefer to express their judgements to their peers in qualitative terms. Similarly, users, particularly for non-technical audiences, may feel more comfortable or effective in using these qualitative terms for the justification of an economic decision rather than quantitative values, which would require more explanation and possibly confusion. Our goal is to use these same terms to describe the reliability/uncertainty of the assessment results.
Table 2 provides guidance on how to assign quantitative
β values according to the pairs of qualitative expressions for component Quality Measure and Implementation Characteristics as obtained from the
Table 3 component matrix evaluations. The
β values, since they are measures of uncertainty, serve to indicate that the higher their value—the lower the reliability. For the specific objective of evaluating the reliability of a building assessment, the following procedure, as developed in the next Sections, will be used:
For each component
i (
i = 1 to 9), under assessment,
Table 3 provides descriptive matrices for corresponding qualitative terms either as a pair of component Quality Measure and Implementation Characteristics description, or a single descriptor used for of the component evaluation,
βi by direct application of the
Table 1 values to the individual matrix locations.
In some cases, there is the quality measure that combines the quality of implementation within its description, then the assignment is direct and the quality assignment is directly given, then use
Table 2 to directly assign the
βi.The resulting
N = 9 quantitative
βi values are combined by the RMS Equation (2) discussed in
Section 2.3 to give
β as the quantitative measure of this aspect of the assessment.
Entering this
β value into
Table 2. provides the corresponding qualitative description.
An important advantage of the quantitative
βi values for each component is that the total uncertainty
β of the assessed damageability and related Performance Level assignment may be evaluated in a mathematically consistent procedure (RMS), as discussed in
Section 2.3. Rationally, it would not be possible express the Total Uncertainty as a combined effect of a set of different qualitative terms, except by assigning the most prevalent value which is not very compelling.
In a single-property loss assessment, an ASTM Level 1 or higher investigation is deemed an engineered study, while Level 0 is considered a desktop study and has no required technical professional input. In practice, it is common that the Portfolio study reports are vague in stating how the individual building’s seismic characteristics were determined, and what the qualifications of the qualifications of the assessor were. The miss-characterization or miss-representation of primary characteristics such as construction type, year built, lateral load resisting system, condition, occupancy, etc., can result in substantial biases in estimated seismic risks. In practice, it is becoming more common that stakeholders engage seismically experienced professionals for the review of these critical inputs before the actual analyses are implemented by the damageability models. The related investigative tasks for specified properties may include:
Review/verify that the construction type assigned to the building is appropriate.
Review/verify that the occupancy type assigned to the building is appropriate.
Review/verify that the year built and year upgraded (if any) assigned is appropriate and the extent of any modification(s) or upgrades is properly considered.
Review/verify that secondary modifiers that are building specific are provided by suitably qualified and experienced engineers and properly represented in the CAT model.
Review/verify that the site seismic hazards have been properly considered, that is confirm that the building is not at a site that is subject to site failure (faulting, liquefaction or landsliding) within the supporting portion of the site.
It is assumed that these technical assessments are completed by an individual(s) that have seismic civil and structural engineer knowledge but are not qualified at the level required by ASTM E2026 to do such studies at Level 1 or higher. The bulleted items level of effort does not qualify as an ASTM Level 1 of Investigation as defined in the ASTM Standards, which typically requires site visits and design drawing reviews as well as the assessor be qualified to ASTM E2026 specified experience and capabilities. To accommodate this important and growing practice in portfolio risk studies, we consider an intermediate Level of Investigation between ASTM Level 0 and Level 1, which can distinguish with more fine detail than the ASTM levels at the low end, by assessing a quality level for the assessment results to help users distinguish the results that can be relied upon from those that cannot. For this purpose, the authors add an ASTM Level 0.5 of Investigation with a corresponding definition that the bulleted items above are followed. This allows some flexibility in the limited ASTM definitions, and the capabilities of the persons assigning the seismic characteristics are given, (
Lee et al. 2021). We propose the definition of this be referred to this level of investigation as a Simi-Engineered Assessment in which the property damageabilities are characterized based on general, not specific, information about the building types, characteristics and site conditions. The purpose of this new defined Level is to reduce the uncertainty in damageability of individual assets by limiting the potential for basic errors in essential inputs, such as misinformation on building year-built, number of stories, occupancy, existing damage to the structural system and its condition, lateral force resistance system type and quality, modifications to the structural system or mischaracterization of construction types. Under the present requirements of ASTM Level 0, the potential for errors and mischaracterizations may be so large that its use may result in unacceptable levels of uncertainty in seismic performance characteristics. Alternatively, the cost of implementation of a Level 1 examination of the plans for the building and observation of its construction characteristics may not be feasible. The proposed Level 0.5 provides a compromise that makes serious errors much less likely.
Table 3 presents a set of proposed evaluation criteria in the form of descriptive matrices for assignment of each of the nine components impacting the assessment of the reliability of the building’s damageability evaluation and/or the resulting assigned Performance Level. These matrices provide qualitative descriptions to characterize the conditions of how the component issue is described and its evaluation is implemented and allow the corresponding quantitative
βi uncertainty value to be found from
Table 1 and the corresponding Qualitative expression from
Table 2. It is emphasized that these descriptions are intended to guide the assignment of the
βi values and that there may be additional characteristics of the process that are important in a particular application. Therefore, it is advised that the value assigned be adjusted, either by revising the Table entries or by adjusting the resulting values by the method of Equation (1), to reflect the value that best describes the professional opinion and experience of the assessor for the circumstance and conditions. As an example, for a FEMA P-154 assessment, if initially a Level 1 assessment for a particular building was used and the outcome was determined to be inadequate, then the performance of a Level 2 investigation can either change or confirm its acceptability rating. The increased Quality due to the use of Level 2 can be used to justify subsequent decisions concerning the building.
2.3. Determination of Reliability/Uncertainty Values for Individual Building Assessments
The determination of the reliability for a specific building’s quality evaluation requires a mathematically defensible (statistically valid) method of combining the individual component uncertainties are combined to reach an aggregated value, or measure of uncertainty, for the specific assessment process. As discussed in the beginning of
Section 2.2 with the use of the model format of FEMA P-695, it is assumed the damage assessment process can be represented as a multiplicative function of the assigned component values [e.g., (ground motion intensity) times (building damageability characteristics) times …] such that the logarithm of the assessed value is in the form of a sum of the logarithms of the components. For the purpose of mathematical tractability and consistent with the level of accuracy in the Qualitative-Quantitative relations in
Table 1 and
Table 2, it will be assumed that the Probability Distribution of the random error in the assigned value for each measure is Log-Normal with a unit mean value and that the assigned
βj is the standard deviation as discussed above, as well as the coefficient of variation since the mean is one. These assumptions allow the determination of the combined uncertainty as a square root of the mean sum of the squares. While we have proposed nine critical components that affect the reliability of an ASCE 41, P-154, ASTM PML evaluation or other applications may consider more or fewer issues. Therefore, we will consider
M issues in the assessment calculations to make the method appropriate for general application.
The evaluation of the combined uncertainty in an assessed value is based on the Probability Rule for the Variance of a Sum of independent random variables being equal to the sum of the individual variances (
2). Given the M values of
for the each of the independent
jth issues, and using the assumption that the
is the standard deviation of the random error in the value of issue
j element, the combined uncertainty
is the root mean sum of the squares (RMS) of the
values as:
In the left expression it is assumed that all of the uncertainty components have equal importance. The expression on the right assumes that the individual issues have differing weights of importance, with
being the assumed weighting factor for the
jth uncertainty source. For the particular objective of this uncertainty procedure that relates qualitative and quantitative descriptions, the division by M in the left- and right-radical is to ensure that the
β value remains between 0 and 1 such that
Table 2 can be used for the qualitative description of this mathematical (quantitative) result. This also achieves the desired result that if all of the
values are the same that the assigned
β is the same as the individual value. The left-side relationship of Equation (2), called RMS here, is interpreted as introducing no bias into the computation since all components are treated equally, and the right-side, called Weighted Average (WA), as introducing a weighting corresponding to the subjective belief in the component’s relative importance to the reliability of the result. Each weighting is an assumption; it is suggested that the right-side Equation be used only if there is a significant difference in the assessed importance of some elements compared to others. This may occur where some of the damageability or loss contributions are less important when compared to others for a particular building.
Equation (2) is the primary mathematical tool used to aggregate uncertainty values ( or similar items) used throughout this paper, although Equation (3) as given below provides a simpler alternative, but not as well based on statistical methods. It is important to note for some evaluations that not all of the components will be important, and those deemed unimportant may be excluded from the computation. Therefore, not all assessments will have nine components of interest. It may also be true that there are other elements that bear on the reliability of the assessment that must be added. We advise that the basis for such additions and/or subtractions be documented in the report.
The purpose of this proposed reliability of assessment method is to provide the user with a qualitative description of the reliability of a given result: specifically, a quantitative
β value is evaluated and then entered into
Table 2 to provide the equivalent qualitative term describing the assessment. In this way we do not have to consider the nuance of meaning of a change, such as 0.01, in the
β value, but instead use a qualitative term to represent the reliability. The basic presumption is that the user of an assessed value is better justified (and more comfortable) to make decisions if
Good or
Superior apply, and reject decision making if the reliability is
Poor or
Bad. The method also serves to identify the specific components and implementations where investment in more information may improve the rating.
Alternative Mean: It could be argued that use of the average (rather than the RMS) of the contributors to be an appropriate way to assess the net reliability of the resulting evaluation, since it does not require assuming that the
β values are surrogates for the standard deviation of the logarithms of the individual component in the analysis, and the aggregation approach does not require independence of the component assigned values. There is a rich literature on the subject of linear models to predict outcomes of complex systems. An improper linear model is one in which the weights are chosen by some non-optimal method to yield a defensible conclusion. The weights may be chosen to be equal, on the basis of intuition of an expert, or at random. Research has found that improper models may have great utility, but it is hard to substantiate in many cases. The linear model cannot replace the expert in deciding such things as what to look for, but it also precisely this knowledge of what to look for in the reaching of the decision that is the special expertise people have. In summary, proper linear models work for that very simple reason. People are good at picking out the right predictor variables and at weighting them in such a way that they have a conditionally monotone relationship with the criterion. People are bad at integrating information from diverse and incomplete sources. Proper linear models are good at such integration when the predictions have a conditional monotone relation to the criterion, (
Dawes 1979). This basic topic is the subject of several volumes of review papers on heuristics and biases that have substantiated this finding in many applications in psychology, medicine and other applications, (
Gilovich et al. 2002). The authors believe that a proper linear model proposed herein is well applied to the problems of seismic assessment reliability determination. The justification would be that this form represents the average or expected error.
We assume two types of simple averages: one is that the weights of the elements are equal, and the other is that an experienced expert in seismic assessment selects them to reflect the relative importance of the individual elements in influencing the decision. In some cases where numerical values are being aggregated, this could be set equal to the replacement cost of the building. This will be called the Simple Average (SA) combination approach, either by a simple average of equally weighted values (left) or weighted values (right). Equation (3) is the primary alternative means to aggregate used throughout this paper but is generally not preferred to Equation (2).
Table 4 provides the
β values for the RMS and the Simple Average alternatives for different assumptions of the
β values. The Table shows the impact of completing a portion of the issues with a common
β value by a better or poorer assessment procedure than the balance, where the
β values are a given level for all but one or two values which are different, termed 1× and 2× in the Table. While the resulting values are comparable for some combinations, the Simple Average yields systematically higher reliability factors (that is lower
β) for all 1× and 2× values. The range of the ratio of the RMS
β values to their simple average range from 1.000 to 1.673 for the 1× comparisons, with the 2× values being in a tighter range of 1.000 to 1.458. We find the RMS approach is consistently the most conservative, and can be better justified on a mathematically basis, if the multiplicative model of components is accepted. The RMS aggregation procedure will be used for the further developments dealing with single building and portfolio assessments. We also note that the Simple Average has standing as a proper linear model that has been substantiated in many binary decision-making processes. Its use is acceptable to the authors, if not preferred.
As seen in
Table 4, changes in having either one or two higher or lower than the principal
β values can alter the model’s reliability index significantly. The clear implication of this table is that accepting less than
Fair component reliability as the basis for the component assessment, makes it very unlikely that the assessment will acquire a
Fair rating or better. In contrast, when
Superior or
Good is the base assessment, one can allow one or two components at a lesser rating and still acquire a
Good or
Fair rating. This behavior may be considered in the formulation of a strategy when it is intended to increase the building assessment’s reliability with the most efficient use of available resources. In addition, the behavior exhibited in the Table provides a direct way to see what would be needed to improve the reliability of the assessment conclusion where there is a concern that the reliability is too low upon which to base a decision. Often the most important link in the assessment procedure concerns whether or not the assessor has access to the structural design drawings, has visited the building to examine its condition and/or has the qualifications to do the assessment. For example, if the assessment does not have any of these afore mentioned attributes, then the rating of Component 3, Basis for Evaluation is likely to be
Poor or
Bad. The raising the Component 3′s rating can dramatically change the
β value from 0.5 or lower to 0.2 or lower. If the base value of assessment is
Good, then the reliability could go from
Fair to
Good or better by this single action. If, in addition, a second attribute is improved, then
Table 4 makes it clear that the impact can be significant. It is important to note that if there is concern about reliability of the assessment and the results will be an essential factor in making fiduciary decisions, it is appropriate to set the criteria for the performer/provider of the assessment to meet the client’s goals before the assessment is commissioned. The purpose is to minimize the possibility of results that are not sufficiently reliable to use for related decision purposes.
2.4. Aggregation of Building Damageability Uncertainties for a Portfolio
In the evaluation of Portfolio uncertainties in
Section 5, it is necessary that a representation be determined for the overall damageability uncertainty for the group of buildings considered. This is represented by a weighted aggregation of the uncertainty values for each of the individual buildings as determined from
Section 2.3. Since it is most common that portfolios consist of buildings having different levels of investigation, it is important that the corresponding
βi differences be reflected in the reliability estimate for the portfolio loss assessment. We will use the building replacement value to provide the weighting for each building. This aggregate for the building evaluation for the portfolio is similar to the weighted version of Equate 1:
where
A is the aggregated damageability uncertainty for the Portfolio,
is the damageability uncertainty for the
ith building in the portfolio of
N buildings and
ci is the replacement cost of the building. The same caution applies to these equations as was discussed in
Section 2.3. The same caution applies to use of these equations as was discussed in
Section 2.3. There is no reason to suppose that a simple average be used here because the value of the
βi is easily defended since these are independent structures and thereby the
βi are independent.
Not surprisingly, when all of the buildings have the same implemented damageability assessment procedure, that is, the
A value for the group is identical to the common
β value for each. For an existing portfolio analysis, the
values are fixed, and the uncertainty index
A is fixed. However, for a portfolio that has yet to be assessed, or for one that is in part to be reassessed, there is an opportunity to make choices that specify the level of investigation for those individual buildings that can significantly impact the
A value. This pre-assessment specification applies as well to the indexes
B and
C to be developed, respectively, in
Section 3 and
Section 4. It should be noted that the Proposed Investigation Level 0.5, as discussed in
Section 2.2, may be particularly useful for those specific buildings that pose a significant element of the loss risk and when a Level 1 assessment is not feasible because of time limits or lack of resources.
2.5. Example Application for Decisions Concerning a Single Building’s Acceptability
A pivotal issue in real estate management of a building may be whether a seismic assessment’s findings are of adequate quality to make a decision of the future use, modification, lease or purchase of a building. We presume that an evaluation prepared has determined whether or not the building is acceptable is based on the client’s purpose for having the assessment completed. Here, the focus is on the quality of the building evaluation and the issue is to decide whether the building is acceptable for occupancy or not based on its seismic evaluation and conformance to an established standard. In the State of California, the usual measure of the assessed seismic performance for a building, new or existing, is the degree to which the building meets the seismic performance requirements of the California Building Code. In California the standard for a state-owned building, including the University of California (UC) and California State University (CSU) Systems, is the degree to which the building meets the seismic performance requirements of the California Existing Building Code. For new buildings this code requirement is an adaptation of ASCE 7, and for existing buildings it is CEBC Section 317 and the following Sections of the 2019 Edition of the California Existing Building Code (CEBC). The issue for decision making is that conformance with Building Code objectives is a binary process: the building either meets or does not meet the criteria. A satisfactory way to express the seriousness of a particular level of non-code acceptability decision is to use a rating scale to express the degree of risk. A satisfactory way of describing the seriousness of a particular assigned level of non-code acceptability is to use a rating scale to express the degree of risk. For this purpose, the California State University System and the University of California have assigned a category method for Earthquake Performance Rating Levels based on CEBC evaluations, see
Table 5.
Generally, a Level IV rated building can be used without limitations, and a newly leased or purchased building must meet the same requirement, (
CSU 2020). In the long term, the CSU and UC policies are to have all of their buildings meet or exceed this Level of seismic performance requirements. However, the objective of achieving a Level IV rating for deficient buildings can be very demanding. In order to provide incentives, the CSU has chosen to accelerate the seismic retrofit work by enforcing the following CEBC requirements:
For existing buildings, any time that a building has proposed work requiring a building permit under the CEBC, that if the work is of the type and/or extent that exceeds stated triggers that require a seismic evaluation, see
Table 6, then the building must be seismically evaluated and if indicated, actions must be taken, within the proposed work, to make the building consistent with CEBC requirements.
It should be noted that the stated triggers for a required CEBC assessment do not necessarily require assessment whenever a modification of the building is proposed that requires a permit. The work must be in excess of the stated trigger limits. In addition, since 1992, in order to achieve due diligence for the life safety performance of all of its facilities, the CSU has performed regular assessments, at all campuses, to determine those buildings in its inventory which pose a significant seismic risk. When such an assessment determines that the vulnerability is too high to accept, then CSU decides on whether the building warrants retrofit as soon as resources become available (listed as Priority I) or be retrofitted whenever any permitted work (no trigger limits) is proposed (listed as Priority 2). These decisions depend on the Ratings of seismic performance indicated in
Table 5. In addition, the CSU has determined that a building identified as posing an unacceptably high life safety risk will either require administrative action to seismically retrofit the building in a short-specified term or cease use of the building.
The above description of the CSU Performance Requirements in terms of Rating values, provides an example of where the proposed Uncertainty and Quality evaluation methodology can be applied. The resulting uncertainty evaluations can be used as guides for risk management decisions governing retrofit of existing buildings, along with the decisions concerning lease or purchase of additional buildings. When a building has been assessed to determine its seismic performance by use of FEMA P-154 or ASCE 41, or other means, an assessment of the uncertainty
A corresponding Quality of the conclusions of should be made by the proposed method.
Table 7 provides an example of how these uncertainty measures could be used to guide decisions. For the case of a
Poor or
Bad Quality evaluation, it is recommended that no decision be made based upon the evaluation, unless the risk is managed by requiring earthquake insurance, with an appropriate deductible. With the prevalent insurance rates, it may be more cost-effective to refuse the investment opportunity rather than incur the cost of a more reliable damageability assessment.