Next Article in Journal
Low-Noise Design of Medium-Range Aircraft for Energy Efficient Aviation
Next Article in Special Issue
Design of a Half-Bridge Current-Source Inverter Topology for Avionic Systems
Previous Article in Journal
Large-Scale CAMUI Type Hybrid Rocket Motor Scaling, Modeling, and Test Results
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Increasing the Efficiency of Aircraft Ground Handling—A Case Study

1
Department of Air Traffic Management, Faculty of Aeronautics, Technical University of Kosice, 040 01 Kosice, Slovakia
2
Department of Aeronautical Engineering, Faculty of Aeronautics, Technical University of Kosice, 040 01 Kosice, Slovakia
3
Faculty of Management, University of Presov, 080 01 Presov, Slovakia
*
Author to whom correspondence should be addressed.
Aerospace 2022, 9(1), 2; https://doi.org/10.3390/aerospace9010002
Submission received: 5 November 2021 / Revised: 16 December 2021 / Accepted: 17 December 2021 / Published: 21 December 2021
(This article belongs to the Special Issue New Trends in Aviation Development 2021-2022)

Abstract

:
This research was focused on increasing the efficiency of aircraft ground handling at the airport. The main goal of the research was to improve the individual processes that are part of the aircraft ground handling in order to speed up this operation, as well as improve the turnaround time between individual flights to enhance the overall throughput of airport stands. The objective of the research was to measure the times of standard airport processes that are part of the aircraft handling, measure the turnaround time between individual flights at the selected airport and increase the efficiency of each process that was measured. After the measurements had been taken, changes were introduced, and the times were measured again. The changes were mainly focused on the following aspects: the position of ground handling equipment before the arrival of the aircraft, the deployment of staff, and the routes taken by ground handling equipment. The measurements were taken during the summer on a fixed stand, with a standard number of employees and with the same type of aircraft. In total, 78 measurements were taken in which 2340 partial times were measured during the entire course of aircraft ground handling before departure to the next destination. After the changes were implemented, the same measurements were taken again to see if the changes that had been implemented could speed up the overall process of the aircraft ground handling. Subsequently, all data were evaluated using statistical methods. All measurements were done at the Košice airport.

Graphical Abstract

1. Introduction

Nowadays, logistics is a dynamically developing discipline. By definition, logistics is an interdisciplinary science that improves the quality of business processes and allows companies to respond to market and customer requirements more quickly [1,2]. The main reason for conducting this research was the need to find new ways to improve quality that meet international standards and reflect the streamlining of services in transport companies. This research was focused on the reduction of the ground handling time and enhancement of the position of aircraft ground handling means [3,4,5].
An important stage in the process of increasing efficiency is the selection of a suitable criterion. In general, the criterion must meet two basic conditions. It must express the real interest of the airport operator and it must also be well quantifiable—time [6,7,8,9]. The aircraft ground handling of one aircraft is the time from on-block to off-block, consisting of several processes where personnel and ground handling equipment are needed [10,11,12,13]. The purpose of speeding up the aircraft ground handling is to provide ground handling to as many airlines as possible and to improve the overall throughput of airport stands [14,15,16]. The time required for the aircraft ground handling is directly dependent on the logistics of the procedural steps which are required [17,18]. A direct factor is the time required for the handling, which depends on the type of aircraft, the number of personnel, as well as resources required for each task, their appropriate order, and the speed of their management within the limits of safety and technical progress [19]. The indirect factors influencing the length of the aircraft ground handling are the number of disembarking passengers, i.e., the amount of their baggage, the weather affecting safety at work, or the condition of the interior of the aircraft after the arrival [20,21,22]. Each aspect of aircraft technical clearance consists of procedures which include operations that can be divided into two categories: fixed and improvable [23,24]. One of the objectives of such research is to test a model that would reduce the time required to obtain all improvisable aspects of aircraft control services as much as possible [25,26]. The model consists of measuring the times of individual operations performed during the individual parts of the aircraft ground handling, as well as the total time of the aircraft’s stay on the ground between flights [27,28,29,30]. The ground control structure is intended to help maintain the required pace. The exchange of information at the operational level in cooperation with decision-making at the airport significantly affects the efficiency of the performance of ground handling tasks. This is accomplished by designing various heuristics for ground handling tasks [31,32,33]. The aircraft ground handling model is a priority for each airport, directly affecting the quality of service, overall capacity, and financial results, and therefore its efficient operation is necessary [34,35,36].
Changes in the process of the aircraft ground handling should focus on the positions of ground handling equipment before the arrival of the aircraft, the deployment of staff, routes of ground handling equipment and others [37,38].

2. Methodology

The overall approach to solving the above problem, which is either inefficient use of the ground handling equipment or long delivery times of the ground handling equipment, was to monitor the ground handling reference values at the airport to reduce the total time the aircraft stayed on the ground. After increasing the efficiency of aircraft ground handling, the time and individual operations was measured and the overall reduction of the time of the aircraft ground handling procedures was monitored. One of the objectives was to measure the values of the time of the total turn of the aircraft and, subsequently, to measure the partial tasks of aircraft ground handling. The research focused on the means needed for the aircraft ground handling, division of employees for individual tasks, location of means, number of means and others. The aim was to work towards the fastest possible turnaround of the aircraft by increasing the efficiency of aircraft ground handling operations. The reason was a possible higher throughput of stands, higher profits, more aircraft movements, etc. The research was carried out at Košice Airport. All of the time data included in the research were obtained by measuring individual aircraft ground handling processes directly at Košice Airport. The entire process of changing the layout of ground handling equipment at Košice Airport was consulted with the management of Košice Airport.
The main objective was to determine the distribution of means used, the total number used for the selected type of aircraft, the number of employees participating in equipping one aircraft and the elaboration of precise actions in the order from the arrival of the aircraft to the stand. After compiling the list of tasks, an aircraft was selected and the time of on-block to the time of off-block was measured. Subsequently, the time of individual subtasks were developed with the help of measurements at the selected airport in the usual procedures. After consultations and evaluations, several solutions were proposed to reduce the time of individual tasks. The measurement process was repeated after the application of the changes, and the sets of values were then statistically compared, and a final evaluation was drawn. The essence was increasing the efficiency of operations with the same number of employees as in the usual procedures of the airport. The main changes were focused on the location and preparation of ground handling equipment before landing the aircraft and rolling on the default stand.

2.1. Acquisition of Input Data

Measurements of the total turn of the aircraft and partial times of the individual aircraft ground handling operations were taken in the selected months of the summer season. The main reason for choosing the summer season is the frequent repetition of the same types of aircraft with the same configuration characteristics. All contained measurements were performed on one type of aircraft of different airlines at a pre-selected fixed stand. The reason for choosing the same stand for all of the measurements is to ensure comparability of the taxi time, the distance from the arrival terminal, the distances of the ground handling means, the distances of the departure terminals and other factors entering the process.
The first part was measuring the total turnaround time of the aircraft at a pre-selected stand. Subsequently, the research focused on measuring the times of each operation performed during the aircraft ground handling. All standard airport procedures were measured. Following the consultations with the management and employees of Košice Airport, procedural changes in the location of resources and procedures were introduced with the same number of employees. After the changes were introduced, the individual times were measured again and the time savings in the procedures were summarized. Košice Airport is a regional airport with one runway with a length of 3100 m. There is also one taxiway, seven fixed stands for aircraft and one terminal building for both departures and arrivals (Table 1).

2.2. Number of Employees and Ground Handling Equipment

For the aforementioned procedures, it was necessary to have a good workforce base and a good technical ability of resources. Under ideal conditions, 21 airport employees were needed with ten means of the ground handling equipment (Table 2).
The ground handling equipment for the aircraft ground handling of the Boeing 737-800:
  • 1x Tractor with GPU,
  • 2x Mobile stairs for boarding and alighting of passengers,
  • 1x Fuel truck with JET-A1,
  • 1x Water truck,
  • 1x Lavatory truck,
  • 1x Special baggage unloading vehicle with built-in belt conveyor,
  • 1x Belt conveyor for baggage loading,
  • 1x Tractor with trolleys for departure baggage,
  • 1x Catering vehicle.
The deployment of the ground handling equipment during ground handling of the aircraft before arrival is shown in the approximate diagram in Figure 1. The location of GHE on arrival was changed to increase the efficiency of the aircraft ground handling, as the positions shown were not effective and valuable time was lost, especially by delivering vehicles to the aircraft. The longest time that was measured in the whole ground handling process was the process of delivery and loading the catering, which came into operation very late in terms of the arrival of the aircraft. The delivery of water and the lavatory truck took more time because they were parked further away in the old airport hangar.

3. Results and Discussion

3.1. Initial Measurement Process

Measurements in standard operation were taken during the summer flight schedule on charter flights. In the initial phase, 26 partial processes were measured with 30 partial times of individual aircraft handling operations. The times that we worked with in the research were measured at Košice Airport (Table 3).
All times listed in the table are average times measured at Košice Airport. All measurements were performed on the same type of aircraft; a Boeing 737-800.

3.2. Measurement Process after Changes Were Applied

After the initial times had been measured, the changes were applied. The first aspect that was changed was the position of selecting the means of ground handling of the aircraft.
It should be noted that not every process and every procedure could be subject to the process of increasing the efficiency. Research was focused on increasing the efficiency of the positions of selected ground handling equipment. After the application of the changes, the processes were measured again under identical conditions (Table 4).

3.3. Statistical Evaluation of Measured Data

After obtaining all of the necessary input data, research proceeded with the statistical evaluation of the measured times of the aircraft ground handling. The first step was to choose the right method of statistical data evaluation. Each operation from the initial phase was assigned to each operation after certain changes were applied and created the corresponding histogram showing times of each operation. Due to fact that there were two variables in the research, the t-test was chosen as a statistical method for the research. Each operation in the aircraft ground handling is interdependent, meaning that if any of the activities are delayed, it will affect the entire process and the total time that the aircraft stays at the airport.
Table 5 shows operations A1–A5 which were:
  • A1—aircraft guidance to stand,
  • A2—aircraft wedging,
  • A3—GPU delivery and connection,
  • A4—approach of the front steps to the aircraft,
  • A5—approach of the rear steps to the aircraft.
The largest time saving was recorded when performing operation A4 where the time saving at the mean value was 0.97 min. The small-time increase was recorded when performing operation A1, where the required time for operation was increased by 0.011 min.
Table 6 shows operations A6–A10, which were:
  • A6—passenger disembarking,
  • A7—delivery of the fuel truck,
  • A8—refueling of the aircraft,
  • A9—arrival of aircraft cleaning staff,
  • A10—aircraft cleaning.
The largest time saving was recorded when performing operation A7 where the time saving at the mean value was 1.14 min. The small-time increase was recorded when performing operation A6, where the required time for the operation was increased by 0.227 min.
Table 7 shows operations A11–A15 which were:
  • A11—delivery of lavatory truck,
  • A12—emptying of the waste tank,
  • A13—delivery of the water truck,
  • A14—filing the aircraft with drinking water,
  • A15—delivery of baggage truck.
The largest time saving was recorded when performing operation A15 where the time saving at the mean value was 1.97 min. The smallest time saved was recorded when performing operation A14, where the required time for the operation was reduced by 0.004 min.
Table 8 shows operations A16–A20, which were:
  • A16—delivery of baggage trolley and belt conveyor,
  • A17—baggage unloading,
  • A18—baggage loading,
  • A19—parking of belt conveyor,
  • A20—parking of special luggage vehicle.
The largest time saving was recorded when performing operation A16 where the time saving at the mean value was 2.08 min. The small-time increase was recorded when performing operation A17, where the required time for the operation was increased by 0.29 min.
Table 9 shows operations A21–A25, which were:
  • A21—delivery of catering truck,
  • A22—catering loading,
  • A23—passenger boarding,
  • A24—preparation of documentation,
  • A25—checking the departure documentation.
The largest time saving was recorded when performing operation A21, where the time saving at the mean value was 4.89 min. The smallest time saved was recorded when performing operation A24, where the required time for the operation was reduced by 0.0085 min.
Table 10 shows operations A26–A30 which were:
  • A26—front steps apposition,
  • A27—rear steps apposition,
  • A28—disconnection and parking of GPU,
  • A29—unwedging of the aircraft,
  • A30—engine start and roll-off.
The largest time saving was recorded when performing operation A27 where the time saving at the mean value was 0.24 min. The smallest time saved was recorded when performing operation A30, where the required time for operation was reduced by 0.01 min.
The GHE layout in Figure 2 shows the more efficient positions of the ground handling equipment with the proposed changes. It is this effective deployment on arrival that has reduced the delivery times and the overall time of the aircraft ground handling of the aircraft after arrival and before take-off. All means were delivered in the immediate vicinity of the aircraft, but it was necessary to maintain safe distances to avoid damage to the aircraft and violation of safety procedures.
The statistical evaluation in the research, statistically significant results were obtained in ten cases from 30 statistical tests performed. In these cases, the goal set by the research was confirmed so that the changes in the processes of the aircraft ground handling have had an impact on the individual times of the aircraft ground handling. In nine cases, the target was confirmed at the set level of significance α = 0.001 (99.99%) and in one case at the level α = 0.05 (95%). Changes in GHE positions as the main goal of increasing the efficiency of aircraft ground handling were made in nine cases, in which a statistically significant result was obtained.
The Table 11 contains the total aircraft ground handling times of selected aircraft in the initial phase before changes were applied and after changes were applied. The results were obtained by summarizing all of the operations of each aircraft in the measurement phases. With 39 aircraft in the initial phase, the total handling time was approximately 910 min (on average, 130 min per group of aircrafts). In the phase after changes were applied, the total handling time for 39 aircraft was approximately 789 min (on average 113 min per group of aircrafts). Subtracting the initial phase time (909.88) from the time after the changes were applied (789.48) equaled 120.40 min, which is approximately a two-hour time saving after applying the changes to increase the efficiency of aircraft ground handling. In one group, a negative value of time was recorded, as the process took approximately 25 min longer after the changes were applied. The times of more efficient operations achieved the expected reduction of time values, but other processes just prolonged the total time. In this case, it is, for example, the passenger disembarking process, which in the case after the changes were applied took longer due to the larger number of passengers on arrival. Another factor was the prolonged cleaning process of the aircraft, for example due to greater pollution of the aircraft, the workload of aircraft cleaning workers and other factors. The process of loading baggage took longer due to the larger number of passengers on departure and other factors that affected the overall time of the aircraft ground handling. Despite this factor, it can be stated that changes in the handling process have led to a reduction in selected partial times.

3.4. Discussion

The main asset of the research was the proposal of process changes in the aircraft ground handling that focused on the position of GHE before the arrival of the aircraft. With simple changes, significant time savings have been achieved, which have led to more efficient process of aircraft ground handling at the selected stand. The applied changes can ensure greater throughput of the stand and the possibility to receive a larger number of aircraft per day, especially in the summer season. The most important finding obtained by this research was that the overall time of aircraft ground handling was reduced by approximately 25 min. These factors will then be reflected in the airport’s revenues (airport charges) with various financial factors, such as the departing passenger tax, fuel sales, landing fee and others. Likewise, with a larger number of aircraft, the prestige and airport statistics will increase in the number of checked aircraft per year and in the number of checked passengers per year. The changes that have been introduced, based on this research, do not only affect the processes but also the overall performance and financial indicators of the airport.
From the point of view of further research in this area, it is possible to consider application of same process of increasing the efficiency of aircraft ground handling on all stands at the airport. Due to the scale of measurements, evaluations, and conclusions, it would be easier to think about creating a certain algorithm, program or mobile application that would work with the obtained/entered data, evaluate them, and apply changes to increase the efficiency of aircraft ground handling within the simulation. Another option that seems simpler is to apply similar changes as we introduced in our case to all sites, as the processes are similar. Subsequently, it is necessary to monitor changes and evaluate their effectiveness. A possible change that already has an impact on airport funding is to consider expanding the ground handling base, which would certainly speed up the overall process of delivering the means from the aircraft and to the aircraft during busier days. As there is a significant difference between the summer and the winter seasons in terms of the number of arrivals and departures, the ideal solution would be to rent selected funds, which are in short supply (e.g., mobile stairs, means of filling water and emptying toilets, etc.). Constants (the same number of employees, the same number of aircraft ground handling equipment, the same stand, and the same type of aircraft) were mainly used in the research to obtain the most accurate and homogeneous results. As research continues, it is possible to focus on multiple inputs of a diverse nature and create research to develop a complex program or application that would work with these values, evaluate them, and then simulate them into outputs.

4. Conclusions

The goal of the research was to increase the efficiency of aircraft ground handling at the selected airport. In the changes in the deployment of selected ground handling equipment, the individual processes were shortened, as well as the total stay of the aircraft at the airport after landing and before take-off. From the results of the research, it can be stated that the goal of the research was achieved.
After measuring the times of individual processes in the initial phase of research and monitoring the possible application of the suitable changes, the changes were introduced into the aircraft ground handling processes of the aircraft and the measurements were repeated under the same conditions. Both measurement processes (before and after changes were applied) provided a sample of measured times (2340), which was statistically evaluated in the research. In the process of statistical evaluation, descriptive statistics were used, which is a method for creating an overview of the obtained data. Subsequently, the research used inductive statistics, which is used to draw conclusions from the measured values by using the t-test. The statistical results were used to verify whether the changes introduced into the processes were statistically significant. Due to the complexity of the aircraft ground handling processes, statistical verification was performed on all processes and not only on processes in which changes were applied.
Overall, it can be stated that in the research and measurement of partial times of specific aircraft ground handling operations, several operations were found where it is possible to achieve significant time savings. The most significant time saving was achieved with the delivery of the catering truck by 4.89 min, mainly due to the large distance of the original position of the catering truck from the stand. Research has also confirmed that certain operations cannot be done faster. An example is guiding the aircraft to a stand where there was no time saved. Thus, it can be concluded that changes made in the ground handling of an aircraft led to a significant reduction in the turnaround time, which was shorter by approximately 25 min.

Author Contributions

Conceptualization, S.S., P.K., M.P., S.M. and Ľ.K.; data curation, S.M. and M.Č.; methodology, S.S., P.K. and Ľ.K.; formal analysis, S.S., P.K., M.P. and S.M.; validation S.M. and M.Č.; supervision, S.S. and P.K.; resources, M.P. and S.M.; writing—original draft preparation, S.M. and M.Č.; writing—review and editing, S.S., P.K., M.P. and Ľ.K. All authors have read and agreed to the published version of the manuscript.

Funding

This article was supported by project New possibilities and Approaches of Optimization within Logistic Processes in the field of Transport and Transport Systems, ITMS code: 313011T567.

Institutional Review Board Statement

Not applicable.

Informed Consent Statement

Not applicable.

Data Availability Statement

Not applicable.

Conflicts of Interest

The authors declare no conflict of interest.

References

  1. Litvaj, I.; Poniščiaková, O.; Stančeková, D.; Drbúl, M. Knowledge processes and their implementation in small transport companies. In Proceedings of the 17th International Conference Transport Means, Kaunas, Lithuania, 24–25 October 2013; pp. 153–156, ISSN 1822296X. [Google Scholar]
  2. Ju, Y.; Wang, A.; Shi, X.; Che, H. Simulation of emergency material transport process. In Proceedings of the 4th International Conference on Wireless Communications, Networking and Mobile Computing, Dalian, China, 12–14 October 2008. [Google Scholar] [CrossRef]
  3. Chovanec, A. Optimization of mainteinance production link. In Transport Means; Publishing House Technologija: Kaunas, Lithuania, 2007; pp. 118–121. ISSN 1822296X. [Google Scholar]
  4. Teplická, K.; Čulková, K.; Manová, E. Using of operation analysis models in selected industrial firm. Acta Montan. Slovaca 2012, 17, 151–157, ISSN 13351788. [Google Scholar]
  5. Nedeliakova, E.; Stefancova, V. Innovative methodology for quality and risk management in logistics processes of transport undertakings. In Proceedings of the 18th International Scientific Conference Business Logistics in Modern Management, Osijek, Croatia, 11–12 October 2018; pp. 41–53. [Google Scholar]
  6. Olszanska, S.; Prokopiuk, I. Balanced scorecard as an effective method for process management in a transport company. Sci. J. Sil. Univ. Technol. Ser. Transp. 2021, 111, 119–128. [Google Scholar] [CrossRef]
  7. Hu, C.; Zhu, W.F. Material handling sequence planning for parallel process. In Proceedings of the 2014 Sixth International Conference on Measuring Technology and Mechatronics Automation, Zhangjiajie, China, 10–11 January 2014; pp. 387–390. [Google Scholar] [CrossRef]
  8. Peceny, L.; Meško, P.; Kampf, R.; Gašparík, J. Optimisation in transport and logistic processes. Transp. Res. Procedia 2020, 44, 15–22. [Google Scholar] [CrossRef]
  9. Poliakova, B.; Semanova, S. The use of transport processes modelling in the freight transport company. In Proceedings of the 21st International Scientific Conference Transport Means, Juodkrantė, Lithuania, 20–22 September 2017; pp. 913–918, ISSN 1822296X. [Google Scholar]
  10. Martin, I.; Alessandra, G. Double-criterion optimalization of distributive system structure. In Proceedings of the International Scientific Conference on Quantitative Methods in Economics (Multiple Criteria Decision Making XVI), Bratislava, Slovakia, 30 May–1 June 2012; pp. 85–91. [Google Scholar]
  11. Szabo, S. Optimization of the parameters of aircraft ground handling by cost function. In Proceedings of the Central European Conference in Finance and Economics (CEFE2017), Herľany, Slovakia, 20–21 September 2017; pp. 733–739, ISBN 978-80-553-2906-2. [Google Scholar]
  12. Mikes, P. Behavioral aspects in optimalization of transport-system. Int. J. Syst. Sci. 1975, 6, 57–66. [Google Scholar] [CrossRef]
  13. Nyulasziova, M.; Palova, D. Implementing a decision support system in the transport process management of a small Slovak transport company. J. Entrep. Manag. Innov. 2020, 16, 75–106. [Google Scholar] [CrossRef] [Green Version]
  14. Koščák, P.; Berežný, Š.; Vajdová, I.; Koblen, I.; Ojciec, M.; Matisková, D.; Puškáš, T. Reducing the negative environmental impact of winter airport maintenance through its model design and simulation. Int. J. Environ. Res. Public Health 2020, 17, 1296. [Google Scholar] [CrossRef] [PubMed] [Green Version]
  15. Abramovic, B.; Nedeliakova, E.; Panak, M.; Šipuš, D. Synergies in logistics processes for railway transport. In Proceedings of the 17th International Scientific Conference Business Logistics in Modern Management, Osijek, Croatia, 12–13 October 2017; pp. 15–28. [Google Scholar] [CrossRef]
  16. Baublys, A. Principles for modelling technological processes in transport terminal. Transport 2009, 24, 5–13. [Google Scholar] [CrossRef]
  17. Pacaiova, H.; Korba, P.; Hovanec, M.; Galanda, J.; Šváb, P.; Lukáč, J. Use of simulation tools for optimization of the time duration of winter maintenance activities at airports. Sustainability 2021, 13, 1095. [Google Scholar] [CrossRef]
  18. Šváb, P.; Korba, P.; Albert, M.; Kolesár, J. Information system to support the management of winter airport maintenance. In Proceedings of the 2019 New Trends in Aviation Development (NTAD) Conference, Chlumec nad Cidlinou, Czech Republic, 26–27 September 2019. [Google Scholar] [CrossRef]
  19. Šváb, P.; Pilát, M.; Kešeľová, M.; Tomanová, K.; Machalová, B. Improving safety with progressive methods to decrease risks during ground handling at the airports. J. Glob. Sci. 2021, 6, 1–12, ISSN 2453-756X. [Google Scholar]
  20. Brezina, D.; Šimák, L.; Hudáková, M.; Masár, M. Comparison of transport problems in process of evacuation. Transp. Res. Procedia 2019, 40, 970–977. [Google Scholar] [CrossRef]
  21. Klyde, D.H.; Magdaleno, R.E.; Reinsberg, J.G. Effect of tire pressure on aircraft ground handling. J. Guid. Control. Dyn. 2003, 26, 558–564. [Google Scholar] [CrossRef]
  22. Camaj, J.; Mašek, J.; Kendra, M. Simulation of the transport centre process by using special tools. Procedia Eng. 2016, 134, 224–230. [Google Scholar] [CrossRef] [Green Version]
  23. Bolek, K.; Kazimierz, L. Development of transport by telematics. In Proceedings of the 19th International Conference on Transport System Telematics, TST 2019, Jaworze, Poland, 27 February–2 March 2019. [Google Scholar] [CrossRef]
  24. Prochazka, P.; Zaskodny, P.; Tarabek, P. Optimalization of the systemic evidence of returnable packaging transport—Analyticalsynthetic model. In Proceedings of the 2007 IEEE International Conference on Service Operations and Logistics, and Informatics, Philadelphia, PA, USA, 27–29 August 2007. [Google Scholar] [CrossRef]
  25. Marasová, D.; Ml, D.M.; Tobisová, A.; Jenčová, E. Baggage Transport Safety System at the Airport. In Proceedings of the 20th International Conference VVaPOL, Vysoké Tatry, Slovakia, 18–21 September 2018; pp. 88–95, ISBN 978-80-553-2742-6. [Google Scholar]
  26. Lawrence, B.; Theodore, C.R.; Johnson, W.; Berger, T. A handling qualities analysis tool for rotorcraft conceptual designs. Aeronaut. J. 2018, 122, 960–987. [Google Scholar] [CrossRef] [Green Version]
  27. Sznajderman, L.; Ramírez-Díaz, G.; Di Bernardi, C.A. Influence of the apron parking stand management policy on aircraft and ground support equipment (gse) gaseous emissions at airports. Aerospace 2021, 8, 87. [Google Scholar] [CrossRef]
  28. Hejtmanek, P. Elementary vehicle handling models. In Proceedings of the 20th International Conference Transport Means, Juodkrantė, Lithuania, 5–7 October 2016; pp. 505–508, ISSN 1822-296X. [Google Scholar]
  29. Authier, M.; Lortie, M.; Gagnon, M. Manual handling techniques: Comparing novices and experts. Int. J. Ind. Ergon. 1996, 17, 419–429. [Google Scholar] [CrossRef]
  30. Horstmeier, T.; de Haan, F. Influence of ground handling on turn round time of new large aircraft. Aircr. Eng. Aerosp. Technol. 2001, 73, 266–271. [Google Scholar] [CrossRef]
  31. Lizbetin, J. Draft of handling equipment for material elements transportation. In Proceedings of the International Conference on Traffic and Transport Engineering, Belgrade, Serbia, 27–28 September 2018; pp. 441–448. [Google Scholar]
  32. Hraskova, D.; Bartošová, V. Process based management in a profile and objectives of the transport company. Adv. Educ. Res. 2014, 61, 109–115, ISSN 04696255. [Google Scholar]
  33. Krzyzewska, I. Problems in the organisation of the transport process on the international market. Sci. J. Sil. Univ. Technol. Ser. Transp. 2021, 112, 113–123. [Google Scholar] [CrossRef]
  34. Drljaca, M.; Sesar, V. Quality factors of transport process. Transp. Res. Procedia 2019, 40, 1030–1036. [Google Scholar] [CrossRef]
  35. Balážiková, M.; Balážiková, M.; Hovanec, M.; Švab, P.; Wysoczańská, B. Estimation of human factor reliability in air operation. In Proceedings of the 2019 New Trends in Aviation Development (NTAD), Chlumec nad Cidlinou, Czech Republic, 26–27 September 2019; pp. 209–213. [Google Scholar] [CrossRef]
  36. Rodchenko, V.V.; Zaichik, L.E.; Yashin, Y.P. Handling qualities criteria for roll control of highly augmented aircraft. J. Guid. Control Dyn. 2003, 26, 928–933. [Google Scholar] [CrossRef]
  37. Tabares, D.A.; Mora-Camino, F.; Drouin, A. A multi-time scale management structure for airport ground handling automation. J. Air Transp. Manag. 2021, 90, 101959. [Google Scholar] [CrossRef]
  38. Schultz, M. Fast aircraft turnaround enabled by reliable passenger boarding. Aerospace 2018, 5, 8. [Google Scholar] [CrossRef] [Green Version]
Figure 1. Deployment of ground handling equipment before changes were applied.
Figure 1. Deployment of ground handling equipment before changes were applied.
Aerospace 09 00002 g001
Figure 2. Deployment of ground handling equipment after changes were applied.
Figure 2. Deployment of ground handling equipment after changes were applied.
Aerospace 09 00002 g002
Table 1. Aircraft ground handling procedures.
Table 1. Aircraft ground handling procedures.
ProcedureTime
Guide the aircraft to the stand
The wedge of the aircraft
Setting up and connecting a GPU
Apposition of stairs
Exit of passengers
Delivery of fuel vehicles
Refueling JET—A1
Arrival of aircraft cleaning staff
Cleaning the interior of the aircraft
Delivery of lavatory truck
Dropping of pallets
Delivery of water truck
Filling the aircraft with drinking water
Delivery of a belt conveyor and a tractor with trolleys for checked baggage
Unloading baggage
Baggage loading
Parking of a belt conveyor and a special baggagevehicle
Catering vehicle delivery
Loading catering
Boarding of passengers
Preparation of departure documentation
Transport and inspection of documents stoving + crew
Parking of stairs
Disconnect and park the GPU
Clearance of the aircraft
Rolling out of the stand
Table 2. Employees needed for aircraft ground handling.
Table 2. Employees needed for aircraft ground handling.
ProcedureNumber of Employees
Guide the aircraft to the stand and wedge the aircraft (also during the departure procedure)1 employee
Setting up and connecting a GPU1 employee
Apposition of stairs2 employees
Exit of passengers and boarding of passengers1 employee
Delivery of fuel vehicle + refueling1 employee
Cleaning the interior of the aircraft4 employees
Parking of lavatory truck + draining of toilets1 employee
Delivery of a drinking water vehicle + filling of the vehicle with drinking water1 employee
Delivery of a belt conveyor and a tractor with trolleys for checked baggage1 employee
Unloading + loading baggage4 employees
Vehicle delivery catering + loading catering2 employees
Preparation of departure documentation2 employees
Table 3. Initial measurements of procedures.
Table 3. Initial measurements of procedures.
ProcedureTime
Guide the aircraft to the stand0:42
The wedge of the aircraft0:23
Setting up and connecting a GPU1:52
Apposition of stairsP: 1:25, Z: 1:20
Exit of passengers3:56
Delivery of fuel vehicles1:42
Refueling JET—A15:53—4253t
Arrival of aircraft cleaning staff1:40
Cleaning the interior of the aircraft13:15
Delivery of toilet vehicles2:30
Dropping of pallets1:52
Delivery of drinking water vehicle2:41
Filling the aircraft with drinking water1:15
Delivery of a belt conveyor and a tractor with trolleys for checked baggage and a special baggage vehicleV = 2:23, PD = 2:15
Unloading baggage9:52
Baggage loading10:21
Parking of a belt conveyor and a special baggage vehiclePD = 0:40, V = 0:48
Catering vehicle delivery8:12
Loading catering12:45
Boarding of passengers12:15
Preparation of departure documentation3:35
Transport and inspection of documents stoving + crew3:24
Parking of stairsP: 0:51, Z 1:25
Disconnect and park the GPU0:53
Clearance of the aircraft0:40
Rolling off the stand + throwing the aircraft engines4:25
P—front stairs, Z—back stairs, V—special vehicle for baggage, PD—conveyor belt for baggage.
Table 4. Measurement of procedures after changes were applied.
Table 4. Measurement of procedures after changes were applied.
ProcedureTime
Guide the aircraft to the stand0:52
The wedge of the aircraft0:36
Setting up and connecting a GPU1:15
Apposition of stairsP: 0:25, Z: 0:58
Exit of passengers7:14
Delivery of fuel vehicles0:17
Refueling JET—A18:16—6436t
Arrival of aircraft cleaning staff0:41
Cleaning the interior of the aircraft19:36
Delivery of toilet vehicles0:35
Dropping of pallets4:46
Delivery of drinking water vehicle0:29
Filling the aircraft with drinking water1:12
Delivery of a belt conveyor and a tractor with trolleys for checked baggage and a special baggage vehicleV = 0:28, PD = 0:41
Unloading baggage13:48
baggage loading21:23
Parking of a belt conveyor and a special baggage vehiclePD = 0:32, V = 0:41
Catering vehicle delivery3:22
Loading catering18:36
Boarding of passengers15:36
Preparation of departure documentation4:18
Transport and inspection of documents stoving + crew5:20
Parking of stairsP: 0:54, Z: 0:52
Disconnect and park the GPU1:12
Clearance of the aircraft0:46
Rolling off the stand + throwing the aircraft engines3:20
P—front stairs, Z—back stairs, V—special vehicle for baggage, PD—conveyor belt for baggage.
Table 5. Statistical evaluation of measured data A1–A5.
Table 5. Statistical evaluation of measured data A1–A5.
OperationNMean Value ± Measurement DeviationMeasurement DeviationMinMaxP
A1 Before780.490000 ± 0.0826640.0878310.360.590.742392
A1 After780.501429 ± 0.076687 0.360.59
A2 Before780.322857 ± 0.0972480.0692130.230.510.536572
A2 After780.340000 ± 0.088318 0.250.51
A3 Before781.330000 ± 0.1634010.2048931.151.520.147937
A3 After781.201429 ± 0.073808 1.151.36
A4 Before781.244286 ± 0.1011360.0730301.151.460.000000
A4 After780.274286 ± 0.092890 0.180.41
A5 Before781.211429 ± 0.0897090.1505391.081.360.000007
A5 After780.395714 ± 0.099139 0.250.58
N—number of aircrafts; P—significance level.
Table 6. Statistical evaluation of measured data A6–A10.
Table 6. Statistical evaluation of measured data A6–A10.
OperationNMean Value ± Measurement DeviationMeasurement DeviationMinMaxP
A6 Before785.457143 ± 1.4227401.5812313.467.140.716990
A6 After785.684286 ± 1.174675 3.467.14
A7 Before781.345714 ± 0.1494270.1246901.151.560.000000
A7 After780.204286 ± 0.053497 0.100.26
A8 Before788.255714 ± 2.2353591.3757145.5311.540.059329
A8 After786.880000 ± 0.944157 5.208.16
A9 Before781.567143 ± 0.4809610.4985221.122.350.000653
A9 After780.350000 ± 0.087750 0.260.51
A10 Before7815.29286 ± 2.8390713.17172612.1819.360.570825
A10 After7816.01143 ± 2.842865 12.1819.36
N—number of aircrafts; P—significance level.
Table 7. Statistical evaluation of measured data A11–A15.
Table 7. Statistical evaluation of measured data A11–A15.
OperationNMean Value ± Measurement DeviationMeasurement DeviationMinMaxP
A11 Before782.298571 ± 0.0949440.1368352.162.460.000000
A11 After780.375714 ± 0.084628 0.300.51
A12 Before782.331429 ± 1.0258401.5978681.364.460.680234
A12 After782.592857 ± 1.017738 1.364.46
A13 Before782.475714 ± 0.3151640.5643832.263.160.000071
A13 After780.420000 ± 0.363822 0.191.23
A14 Before780.877143 ± 0.3423800.3638160.481.180.976147
A14 After780.872857 ± 0.338561 0.481.18
A15 Before782.258571 ± 0.1309490.1553492.102.460.000000
A15 After780.288571 ± 0.065683 0.200.37
N—number of aircrafts; P—significance level.
Table 8. Statistical evaluation of measured data A16–A20.
Table 8. Statistical evaluation of measured data A16–A20.
OperationNMean Value ± Measurement DeviationMeasurement DeviationMinMaxP
A16 Before782.478571 ± 0.4430740.3866952.063.150.000008
A16 After780.398571 ± 0.081328 0.280.52
A17 Before7812.00143 ± 1.7933061.8908419.3613.480.697587
A17 After7812.29286 ± 1.457083 9.3613.48
A18 Before7816.43000 ± 4.6031154.7221679.5621.230.578797
A18 After7817.47714 ± 3.696849 9.5621.23
A19 Before780.374286 ± 0.0562310.0697270.300.460.366890
A19 After780.348571 ± 0.064402 0.250.43
A20 Before780.498571 ± 0.0630950.0428570.420.590.042732
A20 After780.455714 ± 0.072309 0.360.56
N—number of aircrafts; P—significance level.
Table 9. Statistical evaluation of measured data A21–A25.
Table 9. Statistical evaluation of measured data A21–A25.
OperationNMean Value ± Measurement DeviationMeasurement DeviationMinMaxP
A21 Before787.850000 ± 1.6793051.5959685.2310.260.000187
A21 After782.951429 ± 0.460848 2.403.53
A22 Before7815.76286 ± 2.5520762.59645912.2618.360.777567
A22 After7816.05286 ± 2.204561 12.2618.36
A23 Before7813.56857 ± 1.4812883.38021212.0615.510.273432
A23 After7812.02857 ± 3.185631 6.3615.36
A24 Before783.957143 ± 0.6978230.7571093.205.150.977076
A24 After783.948571 ± 0.706834 3.205.15
A25 Before783.748571 ± 0.7200791.1386942.584.580.359293
A25 After784.175714 ± 0.972349 2.585.23
N—number of aircrafts; P—significance level.
Table 10. Statistical evaluation of measured data A26–A30.
Table 10. Statistical evaluation of measured data A26–A30.
OperationNMean Value ± Measurement DeviationMeasurement DeviationMinMaxP
A26 Before780.602857 ± 0.3111650.3522990.431.300.487083
A26 After780.504286 ± 0.061606 0.430.58
A27 Before780.742857 ± 0.4091750.5143420.261.250.248252
A27 After780.494286 ± 0.290623 0.241.12
A28 Before780.774286 ± 0.3068580.5018920.491.130.667253
A28 After780.860000 ± 0.311020 0.491.13
A29 Before780.358571 ± 0.0994030.1023770.150.460.599740
A29 After780.337143 ± 0.104994 0.150.46
A30 Before784.075714 ± 0.9860171.0265382.465.200.977457
A30 After784.064286 ± 0.948698 2.595.20
N—number of aircrafts; P—significance level.
Table 11. Total aircraft ground handling times of selected aircraft groups.
Table 11. Total aircraft ground handling times of selected aircraft groups.
MeasurementsGroup 1Group 2Group 3Group 4Group 5Group 6Group 7
Before (t/min)108.3107.53148.83136.8133.47140.06134.89909.88
After (t/min)80.12132.61117.46109.99119.02112.39117.89789.48
Time saved (t/min)28.18−25.0831.3726.8114.4527.6717.00120.40
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Szabo, S.; Pilát, M.; Makó, S.; Korba, P.; Čičváková, M.; Kmec, Ľ. Increasing the Efficiency of Aircraft Ground Handling—A Case Study. Aerospace 2022, 9, 2. https://doi.org/10.3390/aerospace9010002

AMA Style

Szabo S, Pilát M, Makó S, Korba P, Čičváková M, Kmec Ľ. Increasing the Efficiency of Aircraft Ground Handling—A Case Study. Aerospace. 2022; 9(1):2. https://doi.org/10.3390/aerospace9010002

Chicago/Turabian Style

Szabo, Stanislav, Marek Pilát, Sebastián Makó, Peter Korba, Miroslava Čičváková, and Ľubomír Kmec. 2022. "Increasing the Efficiency of Aircraft Ground Handling—A Case Study" Aerospace 9, no. 1: 2. https://doi.org/10.3390/aerospace9010002

APA Style

Szabo, S., Pilát, M., Makó, S., Korba, P., Čičváková, M., & Kmec, Ľ. (2022). Increasing the Efficiency of Aircraft Ground Handling—A Case Study. Aerospace, 9(1), 2. https://doi.org/10.3390/aerospace9010002

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop