Next Article in Journal
An Overview of Knowledge Graph Reasoning: Key Technologies and Applications
Previous Article in Journal / Special Issue
A Knowledge-Based Battery Controller for IoT Devices
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Optimization of Switch Allocation Problems in Power Distribution Networks

by
Ricardo R. Lângaro
,
Marcelo Teixeira
*,
Richardson Ribeiro
,
Jefferson T. Oliva
and
Marco A. C. Barbosa
Graduate Program in Electrical Engineering, Federal University of Technology-Paraná, Curitiba 80230-901, Brazil
*
Author to whom correspondence should be addressed.
J. Sens. Actuator Netw. 2022, 11(4), 77; https://doi.org/10.3390/jsan11040077
Submission received: 18 October 2022 / Revised: 15 November 2022 / Accepted: 17 November 2022 / Published: 22 November 2022
(This article belongs to the Special Issue Smart Grids: Sensing and Monitoring)

Abstract

:
This paper presents the implementation of the mono-objective Switch Allocation Problem (SAP) optimization model for electric power distribution networks, considering the equivalent interruption duration per consumer unit EIDCU and non-distributed energy END reliability indexes. We use the current summation algorithm to solve the power flow, and we employ an intelligent bee colony algorithm to solve the model. Two network topologies, one with 43 and another with 136 bars, adapted from the literature, are used to illustrate the solution. Results show a significant reduction in the financial cost of planning a power distribution network.

1. Introduction

The current lifestyle of society demonstrates an increasing dependence on energy and, in the current model of power generation systems, a substantial amount of electricity still depends on non-renewable high-carbon sources [1]. In recent years, however, Renewable Energy Sources (RESs) have been integrated into the generation, and distribution matrices, where Photovoltaic (PV), wind, and small hydroelectric plants, for example, have shown to be sustainable alternatives [2]. Furthermore, in the last few years, studies have been adding innovations for different segments of energy systems, such as generation, transmission, and distribution of energy [3,4,5,6]. The need to make these systems more reliable, secure, and efficient has led different areas such as computing, telecommunications, automation, and electrical engineering to develop new solutions [7,8,9,10,11]. The new applications with these areas in electrical infrastructure gave rise to intelligent energy systems, called smart grids [12].
Over several decades, several pioneering research studies on energy optimization problems using intelligent-based methodology were proposed. For instance, Ref. [13] proposes an ant colony optimization algorithm for a minimization problem of energy not supplied during the restoration process. The proposed algorithm is based on a hypercube framework searching for an optimal switching sequence, and the solution provides an effective service restoration strategy that improves system reliability.
A similar approach can also be found in [14], who used an ACO algorithm to minimize the number of switching operations on a network. Ref. [15] used reinforcement learning for optimal reconfiguration that involves selection of the best set of branches to be opened, such that the resulting radial distribution system has the desired performance.
In Ref. [16]), a swarm-based methodology is designed to locate and isolate faults and then decide and implement the switching operations to restore the out-of-service loads.
In Ref. [17], an expert system is developed by utilizing its fast reasoning mechanism and object-oriented features. The feeder component and configuration data are organized in a hierarchy way using the object-oriented programming paradigm. These are just some of the dedicated works in building techniques for energy problems in smart grids.
In the power distribution segment, smart grids include the use of distributed systems, artificial intelligence, and power systems as a way of automating the process of recovering a distribution network in the event of abnormalities (e.g., failures in network devices, excess flow, damages caused by nature or vandalism). These events can cause system failures that lead to blackouts or power supply with lower quality than expected [12,18]. One of the fundamental aspects of a smart grid power distribution network is the system’s ability to identify and recover the network in case of failure. This ability characterizes a self-healing system [19].
Several works have proposed self-healing mechanisms for recovering electrical networks such as [20,21,22,23], just to name a few. Due to the multidisciplinary domain of the problem, some approaches require human specialists from the subareas of computing (distributed systems, programming, and artificial intelligence), telecommunications (transmission and reception of signals), and electrical engineering (energy and electrical systems). This multidisciplinarity makes the proposed solutions highly complex for smart grids due to the diversity of possible approaches to be applied and the sort of problems to handle. For instance, the Switch Allocation Problem (SAP) determines which location, type, and quantity of switches should be installed in a distribution network to increase energy efficiency. For the feasibility of implementing smart electrical grids, the location of the switches is essential, as it increases the possibility of switching on the grid in a future restoration strategy or load reconfiguration. When a grid is optimized for switching plans, it can quickly feed zones without supply or isolate zones with voltage and current disturbances.
Technically, the SAP can be seen as a combinatorial optimization problem [24,25,26]. The approach proposed in [25] deals with a multi-objective SAP model, considering the Average Duration of Interruption (SAIDI) and Average Duration of Failure (SAIFI) indexes of the system in two sectorized networks, addressing not only restoration reliability constraints but also system initial operating point optimization. Other studies address specific problems that help to add more quality to smart grids. For example, Ref. [27] proposes the study of the failure of switches in a sectorized network, usually disregarded by other authors. The optimization in this work is mono-objective, considering the costs of switches and quality indexes SAIDI and SAIFI per consumer.
The approach proposed in this paper is based on the single-objective SAP modeled by [24]. The objective function of our approach are optimizing the network costs by reliability indexes per sector, equivalent interruption duration per consumer unit (EIDCU), and non-distributed energy (END). We use the BackwardForward Sweep method, proposed by [28], to calculate the power flow. Then, we propose a metaheuristic solution Gbest guided Artificial Bee Colony (GABC), raised by [29], and simulate the problem using two networks adapted from the literature [25].
In the following, Section 2 presents the related concepts; Section 3 exposes the proposed resolution, followed by applications in Section 4; and conclusions are presented in Section 5.

2. Problem Formulation

Our proposal is based on two main concepts:
(i)
The network must be conceived as a radial distribution network, i.e., a customer, named load demand, must be redundantly fed by more than one substation (ST) of load. The radial topology provides a way to reconfigure the network by opening/closing some switches and reestablishing the power flow.
(ii)
The network is sectorized in such a way that the normally closed (NC) and normally open (NO) switches segment the clients into separated groups.

2.1. Network Reliability

For the network reliability evaluation, we need to establish some reliability indexes that allow for measuring the efficiency of the network reconfiguration when our methodology is applied.
In this work, we adopted the formulation proposed in [24,30]. Such a formulation establishes two indexes for network evaluation:
(i)
Equivalent interruption duration per consumer unit (EIDCU);
(ii)
The energy not supplied (END).
To calculate EIDCU and END, we first need to calculate the energy load L, Equation (1), the failure rate λ , Equation (2), and the supply time per section U , Equation (3).
Let us consider a network as graph G , i.e., an ordered pair ( V , A ) . Let V ( G ) be the set of vertices modeling the load demands L, and let A ( G ) be the set of edges modeling the switches. Each part of G , delimited by switches, constitutes a sector of S { ( k , l ) S } , where l is normally represented as a failure section, and  k is the target sector for calculations. Each section has its energy load L, failure rate λ , and supply time U , defined as follows:
Energy Load: for the k part
L k = fc i k L i
Failure Rate:
λ l = i V l λ i
In Equation (2), V l is the subset of branches present in the section l S , and λ i is the failure rate of each of the branches i V l . Therefore, the failure rate λ l of a given section l derives from the sum of the failure rates of all its branches, i.e., the average number of failures per year.
Supply Time Fault:
U k = l S λ l · t k l
In Equation (3), λ l models the failure rate in the section l S ; t k l is the expected duration of outage in section k , caused by faults in section l . Determining the restore time t k l depends on the section classification for each fault restoration.
System Average Interruption Duration Index (EIDCU)
EIDCU = l S U l · N l k S N k
In Equation (4), U l represents the total duration of interruptions for each interrupted section l S , considering faults in the section l and all other sectors causing power outages in the sector l ; N l is the number of affected consumers; and N k is the number of consumers on the network. EIDCU expresses the average power outage duration on the grid during one year.
Energy Not Distributed (END)
END = k S U k · L k
In Equation (5), t k is the total duration of outages for each sector k S and L k is the annual average load of the section k S .

2.2. Restoration Time

To solve the Switch Allocation Problem (SAP), we first have to address the Load Restoration in Distribution Systems Problem (PRES). When this problem is solved, the expected interruption duration per sector t k l is obtained.
The network is segmented into sections, the fault l occurs in one section, affecting the sector k in an outage time t k l . Basically, four situations occur:   
t k l = 0 c a s e 1 λ l t l c a s e 2 λ l ( t l + t 2 ) c a s e 3 λ l ( t l + t 2 + t 3 ) c a s e 4
Case 1: when the section k is located downstream from the fault section l , and there is a protection device between them. The sector k is considered not affected.
Case 2: when the section k is located downstream from the fault sector l and there is a sectionalizing switch between them. Opening the switch implies t l . The  k section is considered Resettable.
Case 3: when section k is located upstream from the fault section l , and there is sectionalizing switch between them, as well as a tie switch somewhere upstream from k . Opening the NC key implies t l and closing the NO implies t 2 . The  k sector is considered Transferable.
Case 4: when the sector k is located in sector l ( l k ) or upstream from the fault section l , and there are no switches that can provide load transfer. In such a case, the energy restoration is only possible after the sector l has been repaired, implying t 3 . The sector k and section l are considered Permanently Interrupted.

2.3. Power Flow in Distribution Systems

To establish one of the restrictions in PRES, it is necessary to determine the permanent conditions of the system, i.e., if the grid power is within what is supported by the substation and if the load demands are not overloading the grid at some point. All load variables are calculated for an operating point every time a new solution is considered to ensure these conditions. The method Backward∖Forward Sweep, proposed by [28], is used, an iterative algorithm belonging to the numerical algorithms, which aims to approximate an exact solution by repeated calculations accepting a margin of error, recommended for weakly meshed and radial networks, which present good general performance. The power flow employs a series of calculations to determine the current, voltage, and losses using the data of resistance, reactance, reactive power, and active power. Details of the implementation of this method can be found in [28].

2.4. Mathematical Formulation of the Switch Allocation Problem

The SAP aims to determine the number and the location of the switches to benefit the electrical system by qualifying the system reliability indexes and establishing which ones reduce power losses in the network.
The switch allocation considers the whole network in an operational state with no failures, which benefits the entire network. The SAP is NP-Hard [31] and a multi-criteria problem [24,25].
This work is based in the mathematical formulation of SAP, presented in [24], whose particularity is its time estimate in PRES by considering actual prices applied in the market of electricity distribution. The model also provides conditions to be applied in large-scale networks.
Let us consider a graph G , as an ordered pair ( V ( G ) , A ( G ) ) , where V ( G ) represents a set of vertices, and A ( G ) is a disjoint set of edges. Each edge of G is an unordered pair of vertices, such that the root of the graph is in a ST; i V represents the selection of a vertex modeling a location of a customer i.e., a location of energy demand. Each { ( i , j ) A | i V , j V } corresponds to the selection of a feasible location for switch allocation. Table 1 shows the notation used in the following mathematical formulation.
The decision variables, X i j s and Y i j s , represent the types and locations for sectionalizing switches (NC) and tie switches (NO). These variables are defined as:
X i j s = 1 ,   if   a switch   NC   of   type   s SW   is   allocated   to   the   segment   ( i , j ) A 0 ,   otherwise
Y i j s = 1 , if   a   switch   of   NO   type   s SW   is   allocated   to   the   segment   ( i , j ) A 0 ,   otherwise
The SW set represents the available switches. Next, using the definitions presented in Table 1, the mathematical model for solving the adopted SAP is presented:
( SAP ) (9) m i n i m i z e c e · END ( X , Y ) + ( i , j ) A s SW c s · ( X i j s + Y i j s ) s . t . (10) EIDCU ( X , Y ) z DEC lim z z Z (11) X i j s + Y i j s 1 ( i , j ) A , s SW (12) f i j X i j s + f i j Y i j s F s ( i , j ) A , s SW (13) X i j s , Y i j s { 0 , 1 } ( i , j ) A , s SW (14) f i j 0
Equation (9) represents the objective function to be optimized, with one index being quality and the other cost. Equation (10) is a constraint of the maximum (10) limit for each feeder z. Equation (11) is a binary constraint of the allocation of switches to each edge of the network. Equation (12) is an electrical limitation of the switches where F s is the maximum electrical flow. Equation (13) is a binary constraint on the keys, and Equation (14) is a positive electric flow constraint on the network.
We use the metaheuristic approximate solving algorithm called Artificial Bee Colony (ABC), discussed as follows, to solve this mathematical model.

2.5. Artificial Bee Colony Metaheuristic

The Artificial Bees Colony (ABC) [32] is a metaheuristic that mimics the foraging behavior of a colony of bees. The method consists of conceptually splitting a colony of bees into three groups, named scout, maids, and spectators.
Compared with other swarm algorithms, such as PSO, Ant Colony Optimization, Genetic Algorithm, Simulated Annealing, Tabu Search, etc. [33,34], the ABC pre-divides the number of intelligent agents, respects a sequence of tasks generated by the bees, and limits the location performed by the maids in a relatively low value, explained in [29], as well as being appropriate in problems with continuous search spaces, clustered and constrained search [32,35], the SAP characteristics.

3. Proposed Approach

Algorithm 1 shows the implementation of the proposed approach named GABC (Global Artificial Bee Colony Search). The best solution is initiated by a greedy method, passing through the drawing of neighborhood structures followed by the movement of the sectioning switches and elevation of the type of switches. It also has some mechanisms to avoid stagnation. In spectator bees, a draw between the five most elaborate neighborhood structures is made and passed on to each spectator. In addition, a neighborhood structure is incremented by iterating the best solution.
Algorithm 1: GABC Pseudocode 
Jsan 11 00077 i001
GABC uses both a movement limit l i m and a time limit l i m t i m e . The S { } symbolizes an unfeasible solution, which does not pass when checking its radiality, power flow, or the DEC lim constraints of the feeders.
Random searches are called a total of COL + 1 times, or 2 COL in multiple iterations of three by GABC, Algorithm 1.

4. Experimental Results

Before applying the proposed approach SAP directly to the problem, the power flow was compared with four simulated networks known in the literature: (i) the 10-bar network presented in [36]; (ii) the 33 bars presented [28]; (iii) the 34 bars presented in [37]; and (iv) the 70 bar presented in [38]. The tolerance error of 1 × 10 5 was allowed in these networks. Table 2 shows the comparison between the results obtained by the proposed implementation with the results obtained by MATPOWER.
Results presented in Table 3, Table 4, Table 5 and Table 6 were obtained using an Intel i3 2.40 GHz personal computer with 4 GB of RAM and Windows 7 as the operating system. The algorithms were implemented in MATLAB and supported by the toolbox MATPOWER 7.0. To demonstrate the efficiency of the proposed approach, we use two networks available in [25].
The parameters of the algorithm GABC, Algorithm 1, were set as a colony of 10 bees, 5 employers, and 5 onlookers, with a limit of 6 moves in local searches per iteration and a time limit of 60 s. The scout bees have a constant rate of 86.47%. The algorithm runs until a convergence rate of 10 iterations is achieved.
The electrical parameters used are: V nom = 7.967 kV, I max = 1000 A, S base = 10 MVA. For the resistances, R ij , and reactance X ij of the open switches, minimum values of the reference network 157.54 × 10 6 pu and 0 pu were considered. For the closed switches, the values of 9658.97 × 10 6 pu and 14,179.23 × 10 6 pu were taken. The demand powers P i and Q i were multiplied ten times to increase the currents and adapt to the model used, allowing the optimizer to choose more types of keys.
The ratio between the cost of undistributed power and the cost of switches is 1000:1. Table 3 shows the relationship between the EIDCU for the two feeders after DEC max and DEC min stipulated by the average EIDCU.
In Figure 1, we can see the performance by iteration and by time. It shows the sudden drop in the cost of the network right after the initial heuristic.
Table 4 shows the END separated by the feeder, as well as the total cost of END and the cost of the keys before and after the optimization. The presence of the largest portion of END in feeder 1 is transferred to the second after optimization. In Table 4, we can see the importance of automatic keys in reducing the cost of the objective function. A total of 6 automatic switches are allocated, and 30 manual switches are included for sectioning and switching. The final undistributed energy of the network is 99.09% lower than the initial, showing a decrease of BRL 473,443,261.00. Even reducing the total cost, the greatest weight remains the energy not distributed in the grid. The total cost reduction of the network drops 99.04%, equivalent to BRL 473,219,742.00.
Figure 2 illustrates the optimal setup for 43-bar network. The electrical parameters used are: V nom = 13,800 kV, I max = 1000 A, S base = 20 MVA. For the resistors, R ij , and reactance X ij of the open switches, minimum values of 105.02 × 10 6 pu and 0 pu were considered, while the closed switches considered values of 9321.71 × 10 6 pu and 11,518.86 × 10 6 pu. The demand powers P i and Q i were multiplied three times to increase the currents and adapt to the model used, allowing the optimizer to choose more types of keys.
Table 5 shows the relationship between EIDCU for the two feeders after DEC max and DEC min stipulated by the average EIDCU.
In Figure 3, we can see the performance by iteration and by time. It shows the sudden drop in the cost of the network right after the initial heuristic, represented until the 4th iteration in 57 min, a drop of 79.09% compared to the initial configuration, and in the 10th iteration with 4 h and 44 min, a drop of 90.01% compared to the initial configuration. Between the 61st, in 25 h and 1 min, and the last iteration, there is a drop of less than 1% in the cost of the network. GABC converges on the 99th iteration in 38 h and 47 min showing a total improvement of 96.13% over the initial configuration.
Table 6 shows the portion of END of the feeders, as well as the cost of END and the cost of the keys before and after the optimization. The allocation of automatic keys is predominant in this case, rising from 0 to 71, while manual keys decrease from 28 to 26. The final undistributed energy of the network is 97.35% lower than the initial one, showing a drop of BRL 85,357,177.00. Even reducing the total cost, the greatest weight remains the energy not distributed in the grid. The total cost reduction of the network reduces by 3.87%, equivalent to BRL 84,391,494.00. The optimal setup for 136-bar network which reached such metrics is presented in Figure 4.

5. Conclusions

This paper presented an approach to treat the single objective version of the Switch Allocation Problem (SAP). When our results are compared to alternative solutions in the literature, our model presented more uniform responses for different feeders with a medium EIDCU. Our model produces a uniform duration equivalent to interruption among the feeders, avoiding overloading some of them.
When applying our approach to the two test networks, a considerable reduction in the final cost of the networks was observed. In the 43-bar network, the cost reduction was 99.04%, from BRL 477,814,648.00 to BRL 4,594,906.00. In the network of 136 bars, there was a 96.13% pf reduction in costs, from BRL 87,793,004.00 to BRL 3,401,510.00.
The proposed approach used the bee colony metaheuristic GABC. It is important to emphasize that the algorithm reached promising results. Future works include the execution time of our approach.

Author Contributions

Conceptualization, R.R.L. and M.A.C.B.; methodology, M.A.C.B. and M.T.; software, R.R.L.; validation, R.R.L, M.A.C.B. and R.R.; formal analysis, J.T.O. and M.T.; investigation, R.R.L. and R.R.; resources, R.R.L.; data curation, R.R.; writing—original draft preparation, R.R.L. and M.A.C.B.; writing—review and editing, M.T., R.R. and J.T.O.; visualization, R.R.L. and M.A.C.B.; supervision, M.A.C.B. and M.T.; project administration, M.A.C.B.; funding acquisition, M.T. All authors have read and agreed to the published version of the manuscript.

Funding

This research was funded by the Brazilian National Council of Scientific and Technological Development (CNPq) Grant No. 309946/2020-4, and partially by CAPES (Coordination for the Improvement of Higher Level or Education Personnel), financial code 001, FINEP (Funding Authority for Studies and Projects), and Araucária Foundation.

Institutional Review Board Statement

Not applicable.

Informed Consent Statement

Not applicable.

Data Availability Statement

The data that support the findings of this study are available from the corresponding author upon reasonable request.

Conflicts of Interest

The authors have no conflict of interest to declare.

References

  1. International Energy Agency IEA. World Energy Balances—Overview. 2021. Available online: shorturl.at/noqIT (accessed on 23 September 2022).
  2. Nehrir, M.H.; Wang, C.; Strunz, K.; Aki, H.; Ramakumar, R.; Bing, J.; Miao, Z.; Salameh, Z. A Review of Hybrid Renewable/Alternative Energy Systems for Electric Power Generation: Configurations, Control, and Applications. IEEE Trans. Sustain. Energy 2011, 2, 392–403. [Google Scholar] [CrossRef]
  3. Vardhan, B.S.; Khedkar, M.; Srivastava, I. Effective energy management and cost effective day ahead scheduling for distribution system with dynamic market participants. Sustain. Energy Grids Netw. 2022, 31, 100706. [Google Scholar] [CrossRef]
  4. Alnowibet, K.A.; El-Meligy, M.A. A stochastic programming approach using multiple uncertainty sets for AC robust transmission expansion planning. Sustain. Energy Grids Netw. 2022, 30, 100648. [Google Scholar] [CrossRef]
  5. Baghbanzadeh, D.; Salehi, J.; Gazijahani, F.S.; Shafie-khah, M.; Catalão, J.P. Resilience improvement of multi-microgrid distribution networks using distributed generation. Sustain. Energy Grids Netw. 2021, 27, 100503. [Google Scholar] [CrossRef]
  6. Tavares, I.; Almeida, J.; Soares, J.; Ramos, S.; Vale, Z.; Foroozandeh, Z. Optimizing energy consumption of household appliances using PSO and GWO. In Proceedings of the EPIA Conference on Artificial Intelligence, Lisbon, Portugal, 7–9 September 2021. [Google Scholar]
  7. Mangiatordi, F.; Pallotti, E.; Del Vecchio, P.; Leccese, F. Power consumption scheduling for residential buildings. In Proceedings of the International Conference on Environment and Electrical Engineering, Venice, Italy, 18–25 May 2012. [Google Scholar]
  8. Zidan, A.; Khairalla, M.; Abdrabou, A.M.; Khalifa, T.; Shaban, K.; Abdrabou, A.; El Shatshat, R.; Gaouda, A.M. Fault Detection, Isolation, and Service Restoration in Distribution Systems: State-of-the-Art and Future Trends. IEEE Trans. Smart Grid 2017, 8, 2170–2185. [Google Scholar] [CrossRef]
  9. Maschio, D.M.; Duarte, B.; Lazzaretti, A.E.; Lafay, J.M.S.; Adzkiya, D.; da Costa, J.P.; Teixeira, M. An event-driven approach for resources planning in distributed power generation systems. Int. J. Electr. Power Energy Syst. 2022, 137, 107768. [Google Scholar] [CrossRef]
  10. Simon, D.F.; Teixeira, M.; da Costa, J.P. Availability estimation in photovoltaic generation systems using Timed Petri Net simulation models. Int. J. Electr. Power Energy Syst. 2022, 137, 106897. [Google Scholar] [CrossRef]
  11. Talaat, F.M.; Ali, H.A.; Saraya, M.S.; Saleh, A.I. Effective scheduling algorithm for load balancing in fog environment using CNN and MPSO. Knowl. Inf. Syst. 2022, 64, 773–797. [Google Scholar] [CrossRef]
  12. Hatziargyriou, N.; Asano, H.; Iravani, R.; Marnay, C. Microgrids. IEEE Power Energy Mag. 2007, 5, 78–94. [Google Scholar] [CrossRef]
  13. Lu, Z.; Wen, Y.; Yang, L. An Improved ACO Algorithm for Service Restoration in Power Distribution Systems. In Proceedings of the 2009 Asia-Pacific Power and Energy Engineering Conference, Wuhan, China, 28–31 March 2009; pp. 1–4. [Google Scholar] [CrossRef]
  14. Medeiros, M., Jr.; Lacerda, E. Minimum Number of Switching Operations via Ant Colony Optimization; CIRED: Vienna, Austria, 2007; pp. 21–24. [Google Scholar]
  15. Vlachogiannis, J.; Hatziargyriou, N. Reinforcement learning for reactive power control. IEEE Trans. Power Syst. 2004, 19, 1317–1325. [Google Scholar] [CrossRef]
  16. Zidan, A.; El-Saadany, E.F. Network reconfiguration in balanced and unbalanced distribution systems with variable load demand for loss reduction and service restoration. In Proceedings of the 2012 IEEE Power and Energy Society General Meeting, San Diego, CA, USA, 22–26 July 2012; pp. 1–8. [Google Scholar]
  17. Tsai, M.S. Development of an Object-Oriented Service Restoration Expert System With Load Variations. IEEE Trans. Power Syst. 2008, 23, 219–225. [Google Scholar] [CrossRef]
  18. Wang, Y.; Xu, Y.; He, J.; Liu, C.C.; Schneider, K.P.; Hong, M.; Ton, D.T. Coordinating Multiple Sources for Service Restoration to Enhance Resilience of Distribution Systems. IEEE Trans. Smart Grid 2019, 10, 5781–5793. [Google Scholar] [CrossRef] [Green Version]
  19. Zidan, A.; El-Saadany, E.F. A Cooperative Multiagent Framework for Self-Healing Mechanisms in Distribution Systems. IEEE Trans. Smart Grid 2012, 3, 1525–1539. [Google Scholar] [CrossRef]
  20. Luo, Y.; Lu, C.; Zhu, L.; Song, J. Graph Convolutional Network-Based Interpretable Machine Learning Scheme in Smart Grids. IEEE Trans. Autom. Sci. Eng. 2021, 1–12. [Google Scholar] [CrossRef]
  21. Aboutalebi, M.; Setayesh Nazar, M.; Shafie-khah, M.; Catalão, J.P. Optimal scheduling of self-healing distribution systems considering distributed energy resource capacity withholding strategies. Int. J. Electr. Power Energy Syst. 2022, 136, 107662. [Google Scholar] [CrossRef]
  22. Shirazi, E.; Jadid, S. A multiagent design for self-healing in electric power distribution systems. Electr. Power Syst. Res. 2019, 171, 230–239. [Google Scholar] [CrossRef]
  23. Ribeiro, R.; Enembreck, F.; Guisi, D.M.; Casanova, D.; Teixeira, M.; de Souza, F.A.; Borges, A.P. An Advanced Software Tool to Simulate Service Restoration Problems: A case study on Power Distribution Systems. Procedia Comput. Sci. 2017, 108, 675–684. [Google Scholar] [CrossRef]
  24. Assis, L.; Federico Vizcaino Gonzalez, J.; Usberti, F.; Lyra, C.; Cavellucci, C.; Von Zuben, F. Switch Allocation Problems in Power Distribution Systems. Power Syst. IEEE Trans. 2015, 30, 246–253. [Google Scholar] [CrossRef]
  25. López Amézquita, J.C. Alocação ótima de Chaves de Interconexão nas Redes de Distribuição de Energia Elétrica. Master’s Thesis, Universidade Estadual Paulista (UNESP), São Paulo, Brazil, 2015. [Google Scholar]
  26. Benavides, A.; Machado, M.; Costa, A.; Ritt, M.; Buriol, L.; Garcia, V.; França, P. A Comparison of Tabu Search and GRASP for the Switch Allocation Problem; Sociedade Brasileira de Pesquisa Operacional (SOBRAPO): Porto Seguro, Brazil, 2009; p. 12. [Google Scholar]
  27. Farajollahi, M.; Fotuhi-Firuzabad, M.; Safdarian, A. Sectionalizing Switch Placement in Distribution Networks Considering Switch Failure. IEEE Trans. Smart Grid 2019, 10, 1080–1082. [Google Scholar] [CrossRef]
  28. Baran, M.E.; Wu, F.F. Network reconfiguration in distribution systems for loss reduction and load balancing. IEEE Trans. Power Deliv. 1989, 4, 1401–1407. [Google Scholar] [CrossRef]
  29. Akay, B.; Karaboga, D. A survey on the applications of artificial bee colony in signal, image, and video processing. Signal Image Video Process. 2015, 9, 24. [Google Scholar] [CrossRef]
  30. Epifanio, G.; de Assis, L.S.; Usberti, F.L.; González, J.F. Genetic Algorithm for Sectionalizer Switches Allocation in Distribution System with Distributed Generation. In Proceedings of the LI Simpósio Brasileiro de Pesquisa Operacional; Galoá; Limeira, São Paulo, Brasil, 2019. [Google Scholar]
  31. Sanjoy, D.; Christos, H.; Papadimitriou, U.V.V. Algorithms; McGraw Hill Education Pvt. Ltd.: Chennai, India, 2008; p. 320. [Google Scholar]
  32. Karaboga, D.; Gorkemli, B.; Ozturk, C.; Karaboga, N. A comprehensive survey: Artificial bee colony (ABC) algorithm and applications. Artif. Intell. Rev. 2012, 42, 21–57. [Google Scholar] [CrossRef]
  33. Gendreau, M.; Potvin, J.Y. (Eds.) Handbook of Metaheuristics, 2nd ed.; Springer: Berlin/Heidelberg, Germany, 2010. [Google Scholar]
  34. Poli, R.; Kennedy, J.; Blackwell, T. Particle Swarm Optimization. Swarm Intell. 2007, 1, 33–57. [Google Scholar] [CrossRef]
  35. Akay, B.; Karaboga, D.; Görkemli, B.; Kaya, E. A survey on the Artificial Bee Colony algorithm variants for binary, integer and mixed integer programming problems. Appl. Soft Comput. 2021, 106, 107351. [Google Scholar] [CrossRef]
  36. Grainger, J.J.; Lee, S. Capacity Release by Shunt Capacitor Placement on Distribution Feeders: A New Voltage-Dependent Model. IEEE Trans. Power Appar. Syst. 1982, PAS-101, 1236–1244. [Google Scholar] [CrossRef]
  37. Chis, M.; Salama, M.M.A.; Jayaram, S. Capacitor placement in distribution systems using heuristic search strategies. IEE Proc. Gener. Transm. Distrib. 1997, 144, 225–230. [Google Scholar] [CrossRef]
  38. Baran, M.E.; Wu, F.F. Optimal capacitor placement on radial distribution systems. IEEE Trans. Power Deliv. 1989, 4, 725–734. [Google Scholar] [CrossRef]
Figure 1. Performance of the GABC for 43 nodes.
Figure 1. Performance of the GABC for 43 nodes.
Jsan 11 00077 g001
Figure 2. Optimal of the 43-bar network.
Figure 2. Optimal of the 43-bar network.
Jsan 11 00077 g002
Figure 3. Performance of the GABC for the 136 nodes.
Figure 3. Performance of the GABC for the 136 nodes.
Jsan 11 00077 g003
Figure 4. Optimal of the 136-bar network.
Figure 4. Optimal of the 136-bar network.
Jsan 11 00077 g004
Table 1. Mathematical model notation.
Table 1. Mathematical model notation.
c e Energy Cost ( B R L )
c s Cost of the Switch type s SW ( B R L )
f i j Current Power flow on branch ( i , j ) A ( A )
F s Maximum Power flow of switch type s ( A )
SW Set of switch types
X Set of decision variables in sectionalizing switches NC
Y Set of decision variables in tie switches NO
DEC lim Maximum value allowed for the EIDCU ( h r s / c o n s . / y e a r )
END ( X , Y ) END expected in allocation ( K W h )
EIDCU ( X , Y ) EIDCU expected in allocation ( h r s / c o n s . / y e a r )
Table 2. Results of the 33-bar network.
Table 2. Results of the 33-bar network.
PropertyImplementedMatpower
Active power loss (kW)       202,676202,677
Reactive power lost (kvar)       135,140135,141
Active p. generated (kW)       3,918,0003,917,680
Reactive p. generated (kvar)       2,435,0002,435,140
Total active load (MW)       37153715
Total reactive load (Mvar)       23002300
Time (s)       0.0500.051
Iterations       58
Table 3. EIDCU of the 43-bar network.
Table 3. EIDCU of the 43-bar network.
FeederMinimumLimitMaximum
1287819,48836,099
43267013,89125,112
Table 4. Key information and costs for the 43-bar network.
Table 4. Key information and costs for the 43-bar network.
SwitchEND (BRL/year)Cost (BRL)
InitialEndFeederInitialEnd InitialEnd
Manual9301428,341,662254,027END477,773,7914,330,530
Automatic06249,432,1294,076,503Switch40,857264,376
Total936Total477,773,7914,330,530Total477,814,6484,594,906
Table 5. EIDCU of the 136-bar network.
Table 5. EIDCU of the 136-bar network.
FeederMinimumLimitMaximum
1517844216,368
137416673313,050
Table 6. Key information and costs for the 136 bars.
Table 6. Key information and costs for the 136 bars.
SwitchEND (BRL/year)Cost (BRL)
InitialEndFeederInitialEndTypeInitialEnd
Manuals2826168,989,562574,971END87,677,6562,320,479
Automatics07113718,688,0941,745,508Switch115,3481,081,031
Total2897Total87,677,6562,320,479Total87,793,0043,401,510
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Lângaro, R.R.; Teixeira, M.; Ribeiro, R.; Oliva, J.T.; Barbosa, M.A.C. Optimization of Switch Allocation Problems in Power Distribution Networks. J. Sens. Actuator Netw. 2022, 11, 77. https://doi.org/10.3390/jsan11040077

AMA Style

Lângaro RR, Teixeira M, Ribeiro R, Oliva JT, Barbosa MAC. Optimization of Switch Allocation Problems in Power Distribution Networks. Journal of Sensor and Actuator Networks. 2022; 11(4):77. https://doi.org/10.3390/jsan11040077

Chicago/Turabian Style

Lângaro, Ricardo R., Marcelo Teixeira, Richardson Ribeiro, Jefferson T. Oliva, and Marco A. C. Barbosa. 2022. "Optimization of Switch Allocation Problems in Power Distribution Networks" Journal of Sensor and Actuator Networks 11, no. 4: 77. https://doi.org/10.3390/jsan11040077

APA Style

Lângaro, R. R., Teixeira, M., Ribeiro, R., Oliva, J. T., & Barbosa, M. A. C. (2022). Optimization of Switch Allocation Problems in Power Distribution Networks. Journal of Sensor and Actuator Networks, 11(4), 77. https://doi.org/10.3390/jsan11040077

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop