1. Introduction
Black-start restoration after a large-scale blackout is an extremely complex control and decision-making problem in power systems. Black start refers to the process by which, after a complete outage caused by system faults, the power system is restored without support from external systems. In this process, generating units with self-starting capability are first started and then used to energize units without self-starting capability, thereby gradually expanding the restoration area until the entire system is recovered [
1]. Conventional black-start resources mainly rely on hydropower units, gas turbine units, and other traditional power sources. Although these resources have favorable startup performance and high operational reliability, their availability is constrained by resource conditions, geographical location, and network topology [
2]. In inland areas or regions with insufficient water resources, if no suitable local black-start source is available, regional grid restoration usually depends on external power support, and the restoration process may be restricted by transmission paths and system operating conditions. Therefore, exploiting rapidly dispatchable distributed support resources within a region is of great significance for improving the restoration resilience of power grids [
3,
4,
5].
In recent years, the number of electric vehicles (EVs) has continued to increase, and centralized EV charging stations have been rapidly deployed near urban load centers. Compared with conventional black-start resources, charging stations are characterized by wide spatial distribution and fast response capability, which enables faster load restoration after a large-scale blackout. Meanwhile, with the development of battery energy storage, bidirectional charging and discharging, and power electronic conversion technologies, EVs have gradually acquired the characteristics of distributed power sources. Therefore, centralized EV charging stations can be incorporated into black-start resources to provide a new support approach for power system restoration.
Existing studies have mainly focused on EV participation in peak shaving, frequency regulation, demand response, and optimal dispatch of charging stations. Some studies have also incorporated charging stations as restoration resources into network reconfiguration optimization. In ref. [
6], an energy-reserve coordinated operation model between EV charging stations and distribution networks was established, demonstrating that centralized charging stations can participate in reserve regulation and economic dispatch of distribution networks. Based on measured data from an office site, ref. [
7] compared several charging strategies and showed that optimized charging management can significantly reduce operating costs, thereby reflecting the dispatchable potential of EV loads. In terms of frequency support, ref. [
8] proposed a frequency regulation strategy for EV aggregators under limited data collection. Reference [
9] further considered the uncertainty of V2G charger connections and investigated a dispatch method for aggregated V2G resources to provide fast frequency response. A hierarchical frequency regulation strategy for EV clusters considering demand charging load optimization was proposed in [
10]. In ref. [
11], an autonomous V2G ancillary service framework was designed to enable onboard batteries to participate in primary frequency regulation and distribution-side voltage regulation. For microgrid scenarios, ref. [
12] analyzed the impact of V2G integration on peak shaving and frequency regulation, while ref. [
13] indicated that V2G can be applied to peak shaving, renewable energy accommodation, and frequency regulation. In addition, a limited number of studies have begun to investigate the application of V2G in outage restoration. Reference [
14] proposed a three-stage black-start restoration strategy based on centralized EV charging stations and verified the feasibility of charging station participation in power system restoration. In ref. [
15], the uncertain restoration capability of E-taxi discharging stations was incorporated into a distribution network reconfiguration and emergency power vehicle dispatch model, indicating that mobile EV resources can participate in post-disaster load restoration. Reference [
16] developed a power supply restoration strategy for distribution networks under typhoon disasters by considering the coordinated dispatchable potential of V2G clusters and mobile energy storage.
Meanwhile, secondary frequency and voltage regulation have also received increasing attention in islanded microgrids. In ref. [
17], a distributed secondary coordination strategy was proposed to constrain frequency and voltage within prescribed operating boundaries under disturbances. Reference [
18] developed an exact-time convergent secondary control method for frequency and voltage restoration while considering active- and reactive-power allocation. In ref. [
19], a dynamic event-triggered secondary control strategy was proposed to achieve frequency and voltage restoration and optimal power allocation in islanded AC microgrids. However, these studies mainly focus on secondary regulation and power coordination under normal islanded operation, while the transient restoration process involving sequential auxiliary-motor startup and rapid source–load imbalance during black start has received limited attention.
The above studies indicate that V2G clusters have established a technical foundation for participating in power system operation and outage restoration as flexible active-power regulation resources. However, most existing works focus on planning and dispatch, network reconfiguration, and post-disaster load restoration, while insufficient attention has been paid to the electromagnetic transient process of V2G participation in black start. In practical black-start processes, plant auxiliary equipment is commonly dominated by induction motor loads. Their startup can cause short-duration power surges and bus-voltage fluctuations, which further affect the frequency stability of the islanded system [
20]. Therefore, it is necessary to investigate the transient startup process of plant auxiliary motors when V2G clusters participate in black start.
For a black-start scheme in which V2G participates in a diesel-generator-formed islanded network, further investigation is needed into how the respective advantages of the diesel generator and V2G can be exploited, how their coordinated control can be designed during the sequential startup of auxiliaries, and how the transient stability of the black-start system can be improved.
To address the above research gaps, this paper proposes a coordinated black-start control method for a diesel generator–V2G system with V2G-assisted frequency support. The main contributions of this study are summarized as follows:
(1) An integrated black-start source assessment and capacity-configuration framework is developed. The dynamically available power and energy of the V2G cluster are evaluated by considering vehicle connection status, post-outage disconnection behavior, SOC, and converter-capacity constraints. On this basis, the diesel-generator capacity is verified considering both the steady-state auxiliary-load demand and the transient impact of direct-on-line motor startup, thereby coordinating the available V2G resources with the grid-forming diesel-generator capacity.
(2) A coordinated control strategy is developed for the grid-forming diesel generator and grid-following V2G cluster during sequential auxiliary-load restoration. The diesel generator establishes the islanded voltage and frequency references and improves their recovery through secondary frequency and voltage correction, while the V2G cluster provides fast active-power support through primary frequency regulation and inertia-based frequency control. Through their complementary roles, the two types of sources jointly enable islanded grid formation, steady-state power supply, and transient frequency support during black start.
(3) The proposed method is validated using a detailed electromagnetic transient model of the auxiliary-power system of a biomass CHP plant. Mixed auxiliary motors with both direct-on-line and variable-frequency starting characteristics are considered, and comparative cases are designed to separately evaluate the effects of the improved diesel-generator control, V2G primary frequency regulation, and inertia-based frequency control on the frequency and voltage dynamics during sequential auxiliary startup.
3. Simulation Results and Discussion
3.1. Simulation System and Case Setup
To numerically verify the general method presented in
Section 2, a diesel generator–V2G coordinated black-start electromagnetic transient model was developed in PSCAD/EMTDC (version 5.0.2, Manitoba Hydro International Ltd., Winnipeg, MB, Canada) based on the actual auxiliary-power system of a biomass CHP plant located in an eastern province of China. The system topology, voltage levels, major equipment ratings, auxiliary-load operating powers, starting modes, and cold-start sequence were determined from plant design documents, equipment records, and actual operating information. The plant identity is not disclosed for confidentiality reasons.
This system was selected as the validation case because its two-level 10 kV/0.4 kV auxiliary network contains both direct-on-line and variable-frequency-driven motor loads, thereby representing the main types of source–load disturbances encountered during staged auxiliary-power restoration. It therefore provides a practical engineering scenario for evaluating the coordinated response of the grid-forming diesel generator and the grid-following V2G cluster during black start.
Although the numerical parameters adopted in this study are specific to the investigated plant, the proposed coordination framework can be extended to other islanded auxiliary-power microgrids with similar grid-forming and grid-following source structures. For systems with different voltage levels, source capacities, network impedances, or load compositions, the capacity configuration and control parameters should be recalculated according to the corresponding engineering conditions.
Full-scale field validation was not conducted because deliberate islanding and staged energization of the actual auxiliary-power system are constrained by plant operational and safety requirements.
The system includes a diesel generator, a V2G cluster, and the auxiliary loads of a biomass CHP plant. The diesel generator is represented by a classical synchronous-machine model and is equipped with an IEEE Type 1 excitation system and a DEGOV governor. The V2G cluster consists of four independently controlled subclusters, each connected to the 10 kV auxiliary bus through a 0.4 MVA step-up transformer. The main forced-draft fan, booster fan, and electric feedwater pump are connected to the 10 kV auxiliary bus, while the auxiliary cooling-water pump, fuel conveyor, and condensate pump are connected to the 0.4 kV auxiliary bus through a 10/0.4 kV auxiliary transformer. The simulation-system topology is shown in
Figure 5.
According to the cold-start process of the biomass CHP plant, the plant auxiliaries are started in the following order: auxiliary cooling-water pump, main forced-draft fan, booster fan, fuel conveyor, condensate pump, and electric feedwater pump. To represent their actual starting characteristics, the auxiliary cooling-water pump and fuel conveyor on the 0.4 kV side are started directly across the line, each with an operating power of 144 kW; their rotor inertia time constants are 1.25 s and 1.00 s, respectively. The main forced-draft fan, booster fan, and electric feedwater pump on the 10 kV side, together with the condensate pump on the 0.4 kV side, are started using variable-frequency soft starting. Their rated powers are 847, 610, 553, and 189 kW, respectively; their operating powers are set to 80, 260, 77, and 16 kW; and their rotor inertia time constants are 3.00, 3.00, 1.50, and 2.00 s, respectively. The equipment ratings, operating-power settings, starting modes, and motor inertia parameters used in the simulation were taken from the corresponding plant equipment data and operating records.
The total simulation duration is 120 s. During the initial stage, the diesel generator establishes the voltage and frequency of the islanded system. To reduce the transient impact caused by simultaneous V2G connections, the four V2G subclusters are connected in two batches: the first batch at 5 s and the second batch at 10 s. After grid connection, the V2G cluster tracks the base active-power command corresponding to each auxiliary-restoration stage and provides primary frequency regulation and inertia-based frequency support during frequency disturbances. Beginning at 15 s, the plant auxiliaries are connected sequentially at 15 s intervals according to the predefined order to simulate staged load restoration during black start.
The 120 s simulation horizon is selected as an electrical-transient observation window rather than the actual duration of the complete plant black-start process. The 15 s interval between successive auxiliary startups is used to separate the individual transient responses and facilitate comparison of the control performance, while the final startup at 90 s is followed by a 30 s observation period to evaluate the post-disturbance recovery of the system.
3.2. Capacity Configuration of the Black-Start Sources
Unless otherwise stated, the plant-side electrical and load parameters are obtained from the actual plant data described in
Section 3.1, whereas the V2G available capacity, energy reserve, and diesel-generator capacity are calculated using Equations (1)–(6) based on the specified operating conditions.
For the representative case, the total number of EVs in the considered microgrid area is set to 50. The vehicle plug-in probability at the onset of the outage, the post-outage cumulative disconnection ratio, and the local PLL synchronization success coefficient are set to 0.70, 0.20, and 0.90, respectively. Substitution into Equation (1) gives an expected available fleet size of 25.2 EVs. For the subsequent electromagnetic transient simulation, an integer resource level of 25 EVs is adopted, which is slightly conservative relative to the expected value. Accordingly, the stochastic availability assessment is used to determine the representative V2G resource level, while the subsequent EMT simulation evaluates the dynamic black-start performance under this resource configuration. The rated power of each bidirectional EV converter is 20 kW, and the initial cluster SOC is above the minimum safe discharge limit. Equation (2) therefore gives an available V2G active-power capacity of 0.50 MW. Considering the 0.72 MW steady-state active-power demand of the auxiliary-power system, the V2G cluster is scheduled to supply 0.40 MW in steady state, while the remaining 0.32 MW is supplied by the diesel generator. Accordingly, 0.10 MW of upward regulation margin is reserved for primary frequency regulation and inertia-based frequency control.
The energy capacity of the V2G cluster is verified according to the sustained energy-supply requirement during black-start restoration. The rated battery energy of each EV is 60 kWh; therefore, 25 effective vehicles correspond to a total rated cluster battery energy of 1.50 MWh. The initial equivalent SOC of the cluster is 0.70, and the minimum safe discharge SOC is 0.30, yielding an available discharge energy of 0.60 MWh. Using a continuous V2G supply at 0.40 MW for 1 h as a representative verification case, the required output energy is 0.40 MWh, leaving an energy margin of 0.20 MWh. Therefore, the sustained energy-supply requirement is satisfied.
As the grid-forming source, the diesel generator must satisfy both the steady-state apparent-power demand after all auxiliaries have been connected and the transient voltage-support requirement during the startup of the largest direct-on-line auxiliary. For capacity verification, the steady-state active and reactive loads are taken as 0.72 MW and 0.25 Mvar, respectively. With the V2G cluster supplying 0.40 MW of steady-state active power, the diesel generator supplies 0.32 MW of active power, corresponding to a steady-state apparent-power requirement of 0.406 MVA. The largest direct-on-line auxiliary on the 0.4 kV side has an operating power of 144 kW. According to the starting characteristics of the induction-motor model used in the simulation, its starting current is approximately four times the rated current, corresponding to a transient apparent-power impact of 0.53 MVA. Taking the diesel-generator subtransient reactance as 0.14 p.u., the maximum allowable voltage dip of the 10 kV auxiliary bus as 0.10 p.u., and the pre-start diesel-generator apparent power as 0.31 MVA, Equation (6) gives a minimum required diesel-generator capacity of 1.052 MVA. A 1.4 MVA diesel generator is therefore selected as the grid-forming source, providing a capacity margin of 33.1% above the calculated minimum requirement. The main control parameters of the black-start sources are listed in
Table 1.
The control parameters in
Table 1 are design and tuning parameters used for the proposed controllers rather than plant equipment ratings; the droop coefficients are determined from the adopted droop characteristics, while the remaining controller parameters are selected through controller tuning under the studied operating conditions.
3.3. Startup Characteristics of Mixed Auxiliary-Motor Loads
To analyze the influence of different starting methods on the black-start dynamic process, the electric feedwater pump is selected as a representative large-capacity auxiliary, and two comparison cases are established: direct-on-line starting at grid frequency and variable-frequency soft starting. These cases are used only to compare the current characteristics of the two starting methods; in the actual black-start restoration sequence, the electric feedwater pump is started using the variable-frequency method. The stator current responses under the two starting methods are shown in
Figure 6.
As shown in
Figure 6, during direct-on-line starting, the stator current rises sharply when the motor is connected, with a peak exceeding 100 A, and the high-current interval lasts for about 5 s. In contrast, with variable-frequency soft starting, the converter gradually increases the output voltage and frequency according to the prescribed V/f relationship, limiting the starting-current peak to 15 A and producing a much smoother current response. Compared with direct-on-line starting, variable-frequency soft starting therefore substantially reduces both the magnitude and abruptness of the starting current, thereby mitigating the transient impact of large-capacity auxiliaries on the black-start system.
To characterize the normal starting behavior of the plant auxiliaries,
Figure 7 shows the active power, reactive power, and total feeder current as the auxiliaries are connected according to the predefined sequence.
As shown in
Figure 7, the system active load increases in a stepwise manner as the plant auxiliaries are connected, with short-duration power variations during the acceleration of variable-frequency-started motors. After all auxiliaries are connected, the steady-state active and reactive powers are 0.72 MW and 0.25 Mvar, respectively, and the total feeder current settles at 46 A. The steady-state active power differs from the predefined total operating-power demand of 0.721 MW by less than 1%, indicating good consistency between the specified load demand and the simulated steady-state response. During the two direct-on-line startup events at t = 15 s and t = 60 s, the reactive-power peaks reach 0.47 Mvar and 0.58 Mvar, respectively, while the corresponding feeder currents rise to 29 A and 52 A. In contrast, the variable-frequency-started auxiliaries exhibit smoother reactive-power and current variations during startup. These quantitative results indicate that the two starting modes produce distinctly different transient load characteristics, with direct-on-line starting causing more abrupt reactive-power and current changes and therefore a stronger instantaneous impact on the auxiliary-power system.
3.4. Analysis of Coordinated Diesel Generator–V2G Black-Start Results
To verify the dynamic support performance of the proposed diesel generator–V2G coordinated control strategy during black start, this section analyzes the system frequency, diesel-generator output power, V2G-cluster output power, and bus-voltage responses. The black-start transient responses are shown in
Figure 8.
Figure 8a–d show the system frequency, diesel-generator active power, total V2G-cluster active power, and cumulative V2G output energy, respectively. After an auxiliary is connected, the diesel generator cannot immediately compensate for the active-power deficit during the initial startup period because of delays in the governor and fuel system. The V2G cluster rapidly adjusts its active-power output according to the frequency deviation and the rate of change in frequency, suppressing frequency fluctuations caused by the source–load imbalance. The diesel generator then gradually assumes the newly added load and re-establishes power balance. During the entire restoration process, the minimum and maximum system frequencies are 49.75 Hz and 50.23 Hz, corresponding to deviations of −0.50% and +0.46% from the nominal frequency of 50 Hz, respectively. After all auxiliaries are connected, the active-power outputs of the diesel generator and the V2G cluster stabilize at 0.32 MW and 0.40 MW, respectively, which is consistent with the predefined power allocation. During the 120 s transient restoration process, the cumulative V2G output energy reaches 0.0075 MWh, corresponding to only 1.25% of the available 0.60 MWh, which is consistent with the preceding sustained energy-supply verification.
Figure 8e–g show the 10 kV auxiliary-bus voltage, the 0.4 kV bus voltage, and the diesel-generator reactive-power output, respectively. When the two direct-on-line auxiliaries are connected at t = 15 s and t = 60 s, the reactive-power demand and starting current increase rapidly, causing short-duration voltage dips at both voltage levels. The minimum voltages of the 10 kV and 0.4 kV buses are 0.988 p.u. and 0.955 p.u., corresponding to maximum voltage dips of 1.2% and 4.5% from their nominal values, respectively. Through excitation control and secondary voltage correction, the diesel generator rapidly increases its reactive-power output; the reactive-power peaks during the two direct-on-line startup events reach 0.47 Mvar and 0.58 Mvar, respectively. After the disturbances subside, the voltages at both bus levels recover to values close to their rated levels. These results show that the adopted diesel-generator grid-forming and voltage-regulation strategy can mitigate the voltage impact associated with the transient reactive-power demand of direct-on-line auxiliary startup and support bus-voltage recovery throughout the black-start process.
To further quantify the contributions of the individual control components to black-start dynamic performance, three comparison cases are established while keeping the auxiliary startup sequence and system parameters unchanged: (i) diesel-generator-only black start with conventional droop control; (ii) diesel-generator-only black start with the improved droop control proposed in this paper; and (iii) coordinated black start in which the diesel generator uses the proposed control while V2G participates only in primary frequency regulation.
Figure 9a,b compare the first two cases to verify the effect of the improved diesel-generator control.
Figure 9c,d then compare diesel-generator-only operation, V2G primary frequency regulation, and the complete coordinated control while keeping the diesel-generator control unchanged, thereby evaluating the effects of V2G primary frequency regulation and inertia-based frequency control on the system frequency dynamics.
Figure 9a,b show the system-frequency and 10 kV bus-voltage responses under different diesel-generator control strategies. Under conventional droop control, the system frequency varies between 49.5 and 50.9 Hz, with a peak-to-valley range of 1.40 Hz. With the improved droop control, the frequency variation is reduced to 49.6–50.6 Hz, and the peak-to-valley range calculated from the simulated response decreases to 0.95 Hz, corresponding to a reduction of 32.1%. In addition, the frequency deviation following successive load disturbances is gradually eliminated. For the voltage response, taking the direct-on-line auxiliary startup at t = 60 s as an example, the minimum 10 kV bus voltage increases from 0.985 p.u. under conventional droop control to 0.989 p.u. under the improved control. After the disturbance, the voltage settles at 0.995 p.u. under conventional droop control, whereas the improved control restores it close to the nominal value of 1.0 p.u. This indicates that the secondary frequency and voltage correction not only reduces frequency fluctuations during black start but also substantially mitigates the steady-state frequency and voltage deviations inherent in conventional droop control, thereby improving the restoration performance of the diesel generator during islanded operation.
Figure 9c,d further show the system-frequency and V2G-cluster active-power responses under different V2G support modes. The frequency peak-to-valley ranges under diesel-generator-only operation, V2G primary frequency regulation only, and the complete coordinated control are 0.95 Hz, 0.74 Hz, and 0.48 Hz, respectively. Relative to diesel-generator-only operation, introducing V2G primary frequency regulation reduces the frequency-fluctuation range by 22.1%. Adding inertia-based frequency control further reduces the range by 35.1% relative to primary frequency regulation alone and by 49.5% relative to diesel-generator-only operation. As shown in
Figure 9d, during the load disturbances near 35 s and 55 s, the peak transient V2G power increments under the proposed control reach 0.21 MW and 0.30 MW, respectively, which are 0.05 MW and 0.06 MW higher than those obtained with primary frequency regulation alone. These results demonstrate that inertia-based frequency control provides faster active-power support during the initial stage of a disturbance by responding to the rate of change in frequency. Both V2G control modes eventually settle at 0.40 MW, indicating that the inertia-based frequency control primarily improves transient frequency-support capability without altering the steady-state V2G power allocation.