A Test System for Transmission Expansion Planning Studies
Abstract
:1. Introduction
- Technical gap 1: In TEP studies, it is essential to conduct assessments under both normal operating conditions and all single contingencies. Therefore, the base system used in TEP studies must demonstrate robustness and reliability under both conditions. However, as previously mentioned, existing test systems have significant limitations: they adhere to technical requirements solely under normal operating conditions, lacking their validation under all single contingency conditions. This raises uncertainty about whether these systems meet requirements across all single contingencies. The reliability concerns escalate with the outcomes of TEP, and winning scenarios cannot be achieved when utilizing a base test system that has not been evaluated under all single contingencies for TEP studies.
- Technical gap 2: In the cases mentioned above, it is essential to verify whether the chosen base test system satisfies the requirements under all single contingencies. If it cannot satisfy the requirements, necessary adjustments should be made to the base test system before utilizing it for TEP studies. However, this poses a challenge, especially for large-scale test systems, as first we need to check the test system for all single contingencies. It should not be too difficult since there are many papers and open-source and commercial software programs that can do n − 1 (and even n − 2) contingency analysis quickly. The challenge is when the test system cannot meet requirements under a single contingency. Resolving the problem of ensuring a test system meets operational requirements under both normal and all single contingencies lacks a straightforward solution. Exploring various alternatives—like adding new lines, modifying generations or loads, adjusting shunt compensators, and so on—requires a trial-and-error process. It is essential to acknowledge that a modification to resolving an issue in a particular single contingency may lead to violations in other contingencies, different loading conditions, or even in normal operation. Therefore, every modification necessitates a comprehensive load flow analysis under both normal and all single contingencies. This task is exhaustive, particularly within a large network, without a guaranteed solution. Even if successful, different researchers may obtain various mitigations to address an identical violation for one of the single contingencies. This results in different, but not the same, test systems.
- Contributions: The main objective of this paper is to address the issues, difficulties, and technical gaps highlighted above by introducing a new test system specifically for TEP studies, operating at a transmission voltage level of 500 kV. In our previous effort and very challenging task, we developed a test system that meets the requirements under peak load, for normal conditions, and for all single contingencies [29]. However, there was still an issue: the test system was under one loading condition, peak load, while TEP studies are needed for different loading conditions. This paper deals with this challenge, and the test system introduced within satisfies the requirements for voltage drop and line loading limits under both normal and all single contingency conditions. This applies to two distinct loading conditions: peak load and dominant load (representing 60% of peak load). The paper provides comprehensive details regarding the new test system, along with power flow analysis results under normal conditions and the most critical single contingency for two different loading scenarios.
2. Information on the Test System
2.1. Power Network Topology
2.2. Transmission Line Configuration
2.3. Generation Units and Load Data
3. Power Flow Formulation
3.1. Normal Operating Condition
3.2. Single Contingency Conditions
4. Power Flow Result and Analysis
4.1. Peak Load: Normal Condition
4.2. Peak Load: Single Contingency Conditions
4.3. Dominant Load: Normal Condition
4.4. Dominant Load: Single Contingencies
5. Case Studies for TEP Using the Test System
- Case I: Connecting a new power plant to the network
- Case II: Addition of a generation unit and a load
6. Conclusions
Author Contributions
Funding
Data Availability Statement
Conflicts of Interest
References
- Western Assessment of Resource Adequacy, WECC. 2022. Available online: https://www.wecc.org/Reliability/2022WesternAssessment%20of%20Resource%20Adequacy.pdf (accessed on 20 December 2023).
- Heeter, J.S.; Speer, B.K.; Glick, M.B. International Best Practices for Implementing and Designing Renewable Portfolio Standard (RPS) Policies (NREL/TP-6A20-72798); National Renewable Energy Lab. (NREL): Golden, CO, USA, 2019; p. 1507986. [Google Scholar]
- Gautam, D.; Vittal, V.; Harbour, T. Impact of Increased Penetration of DFIG-Based Wind Turbine Generators on Transient and Small Signal Stability of Power Systems. IEEE Trans. Power Syst. 2009, 24, 1426–1434. [Google Scholar] [CrossRef]
- Nwaigwe, K.N.; Mutabilwa, P.; Dintwa, E. An Overview of Solar Power (PV Systems) Integration into Electricity Grids. Mater. Sci. Energy Technol. 2019, 2, 629–633. [Google Scholar] [CrossRef]
- Mehrtash, M.; Hobbs, B.F.; Cao, Y. A Large-Scale Test System for Transmission Expansion Planning with AC Networks Model. In Proceedings of the IEEE Texas Power & Energy Conference (TPEC), College Station, TX, USA, 28 February–1 March 2022; pp. 1–5. [Google Scholar]
- Conejo, A.J.; Baringo Morales, L.; Kazempour, S.J.; Siddiqui, A.S. Investment in Electricity Generation and Transmission; Springer International Publishing: Cham, Switzerland, 2016. [Google Scholar]
- Quintero, J.; Zhang, H.; Chakhchoukh, Y.; Vittal, V.; Heydt, G.T. Next Generation Transmission Expansion Planning Framework: Models, Tools, and Educational Opportunities. IEEE Trans. Power Syst. 2014, 29, 1911–1918. [Google Scholar] [CrossRef]
- Haffner, S.; Monticelli, A.; Garcia, A.; Mantovani, J.; Romero, R. Branch and Bound Algorithm for Transmission System Expansion Planning Using a Transportation Model. IEE Proc. Gener. Trans. Distrib. 2000, 147, 149. [Google Scholar] [CrossRef]
- Meneses, M.; Nascimento, E.; Macedo, L.H.; Romero, R. Transmission Network Expansion Planning Considering Line Switching. IEEE Access 2020, 8, 115148–115158. [Google Scholar] [CrossRef]
- Mutlu, S.; Şenyiğit, E. Literature Review of Transmission Expansion Planning Problem Test Systems: Detailed Analysis of IEEE-24. Electr. Power Syst. Res. 2021, 201, 107543. [Google Scholar] [CrossRef]
- Zhuo, Z.; Zhang, N.; Yang, J.; Kang, C.; Smith, C.; O’Malley, M.J.; Kroposki, B. Transmission Expansion Planning Test System for AC/DC Hybrid Grid with High Variable Renewable Energy Penetration. IEEE Trans. Power Syst. 2020, 35, 2597–2608. [Google Scholar] [CrossRef]
- Dechamps, C.; Jamoulle, E. Interactive Computer Program for Planning the Expansion of Meshed Transmission Networks. Int. J. Electr. Power Energy Syst. 1980, 2, 103–108. [Google Scholar] [CrossRef]
- Romero, R.; Monticelli, A.; Garcia, A.; Haffner, S. Test Systems and Mathematical Models for Transmission Network Expansion Planning. IEE Proc. Gener. Trans. Distrib. 2002, 149, 27–36. [Google Scholar] [CrossRef]
- Rahmani, M. Study of New Mathematical Models for Transmission Expansion Planning Problem. Ph.D. Dissertation, Ilha Solteira UNESP, São Paulo, Brazil, 2013. [Google Scholar]
- Sierra, J.E.; Giraldo, E.A.; Lopez-Lezama, J.M. Weighting Transmission Loading Relief Nodal Indexes for the Optimal Allocation of Distributed Generation in Power Systems. Contemp. Eng. Sci. 2018, 11, 2601–2611. [Google Scholar] [CrossRef]
- Pena, I.; Martinez-Anido, C.B.; Hodge, B.-M. An Extended IEEE 118-Bus Test System with High Renewable Penetration. IEEE Trans. Power Syst. 2018, 33, 281–289. [Google Scholar] [CrossRef]
- Xu, Q.; Hobbs, B.F. Value of Model Enhancements: Quantifying the Benefit of Improved Transmission Planning Models. IET Gener. Trans. Distrib. 2019, 13, 2836–2845. [Google Scholar] [CrossRef]
- Electric Grid Test Cases. Available online: https://electricgrids.engr.tamu.edu/electric-grid-test-cases/ (accessed on 25 July 2023).
- Probability Methods Subcommittee IEEE Reliability Test System. IEEE Trans. Power Appar. Syst. 1979, 98, 2047–2054.
- Grigg, C.; Wong, P.; Albrecht, P.; Allan, R.; Bhavaraju, M.; Billinton, R.; Chen, Q.; Fong, C.; Haddad, S.; Kuruganty, S.; et al. The IEEE Reliability Test System-1996. A Report Prepared by the Reliability Test System Task Force of the Application of Probability Methods Subcommittee. IEEE Trans. Power Syst. 1999, 14, 1010–1020. [Google Scholar] [CrossRef]
- Allan, R.N.; Billinton, R.; Sjarief, I.; Goel, L.; So, K.S. A Reliability Test System for Educational Purposes-Basic Distribution System Data and Results. IEEE Trans. Power Syst. 1991, 6, 813–820. [Google Scholar] [CrossRef]
- Leite Da Silva, A.M.; Cassula, A.M.; Billinton, R.; Manso, L.A.F. Integrated Reliability Evaluation of Generation, Transmission and Distribution Systems. IEE Proc. Gener. Trans. Distrib. 2002, 149, 1–6. [Google Scholar] [CrossRef]
- Akhavein, A.; Porkar, B. A Composite Generation and Transmission Reliability Test System for Research Purposes. Renew. Sustain. Energy Rev. 2017, 75, 331–337. [Google Scholar] [CrossRef]
- Barrows, C.; Bloom, A.; Ehlen, A.; Ikäheimo, J.; Jorgenson, J.; Krishnamurthy, D.; Lau, J.; McBennett, B.; O’Connell, M.; Preston, E.; et al. The IEEE Reliability Test System: A Proposed 2019 Update. IEEE Trans. Power Syst. 2020, 35, 119–127. [Google Scholar] [CrossRef]
- Zou, K.; Agalgaonkar, A.P.; Muttaqi, K.M.; Perera, S. Distribution System Planning with Incorporating DG Reactive Capability and System Uncertainties. IEEE Trans. Sustain. Energy 2012, 3, 112–123. [Google Scholar] [CrossRef]
- Wu, Y.-K.; Lee, C.-Y.; Liu, L.-C.; Tsai, S.-H. Study of Reconfiguration for the Distribution System with Distributed Generators. IEEE Trans. Power Deliv. 2010, 25, 1678–1685. [Google Scholar] [CrossRef]
- Lotero, R.C.; Contreras, J. Distribution System Planning with Reliability. IEEE Trans. Power Deliv. 2011, 26, 2552–2562. [Google Scholar] [CrossRef]
- Lin, Z.; Hu, Z.; Song, Y. Distribution Network Expansion Planning Considering N-1 Criterion. IEEE Trans. Power Syst. 2019, 34, 2476–2478. [Google Scholar] [CrossRef]
- Dhamala, B.; Ghassemi, M. A Test System for Transmission Expansion Planning Studies Meeting the Operation Requirements Under Normal Condition as Well as All Single Contingencies. In Proceedings of the North American Power Symposium (NAPS), Asheville, NC, USA, 15–17 October 2023; pp. 1–5. [Google Scholar]
- Wei-Gang, H. Study on Conductor Configuration of 500 kV Chang-Fang Compact Line. IEEE Trans. Power Deliv. 2003, 18, 1002–1008. [Google Scholar] [CrossRef]
- Birchfield, A.B.; Gegner, K.M.; Xu, T.; Shetye, K.S.; Overbye, T.J. Statistical Considerations in the Creation of Realistic Synthetic Power Grids for Geomagnetic Disturbance Studies. IEEE Trans. Power Syst. 2017, 32, 1502–1510. [Google Scholar] [CrossRef]
Line | Length (km) | Line | Length (km) |
---|---|---|---|
1–2 | 512.90 | 7–12 | 300.00 |
1–4 | 474.19 | 8–11 | 349.09 |
1–7 | 370.91 | 9–10 | 447.27 |
2–3 | 485.45 | 9–15 | 398.18 |
2–5 | 294.55 | 10–14 | 392.73 |
3–6 | 349.55 | 11–13 | 261.29 |
4–8 | 416.13 | 12–14 | 348.38 |
5–6 | 519.00 | 12–16 | 406.45 |
5–7 | 435.48 | 13–16 | 490.91 |
5–10 | 376.36 | 14–17 | 403.64 |
6–9 | 316.36 | 15–17 | 502.70 |
7–11 | 387.09 |
Conductor and Bundle Information | Line Parameters | ||
---|---|---|---|
Type | 4 Macaw | Rsistance | 0.0228 |
The outside diameter of the conductor (inches) | 1.055 | Inductance (mH/km) | 0.878 |
Subconductor spacing(m) | 0.45 | Capacitor (nF/km) | 12.975 |
Bus (Type) | |V| (p.u.) | (MW) | (Mvar) | (Mvar) |
---|---|---|---|---|
Bus 3 (PV) | 1.04 | 3300 | −990 | 1980 |
Bus 6 (PV) | 1.04 | 3400 | −1020 | 2040 |
Bus 8 (PV) | 1.05 | 3600 | −1080 | 2160 |
Bus 10 (PV) | 1.03 | 3300 | −990 | 1980 |
Bus 12 (PV) | 1.05 | 3600 | −1080 | 2160 |
Bus 13 (PV) | 1.05 | 3500 | −1050 | 2100 |
Bus 15 (PV) | 1.00 | 2800 | −840 | 1680 |
Bus | Load | Fixed Shunt | |
---|---|---|---|
(MW) | (Mvar) | ||
Bus 2 | 1750.00 | 847.56 | 100 Mvar Reactor |
Bus 3 | 1600.00 | 774.92 | - |
Bus 4 | 1760.00 | 852.41 | - |
Bus 5 | 1500.00 | 731.33 | - |
Bus 6 | 1600.00 | 774.92 | - |
Bus 7 | 1860.00 | 900.88 | 100 Mvar Capacitor |
Bus 8 | 1600.00 | 774.92 | - |
Bus 9 | 1800.00 | 871.78 | 250 Mvar Capacitor |
Bus 10 | 1600.00 | 774.92 | - |
Bus 11 | 1850.00 | 896.00 | 250 Mvar Capacitor |
Bus 12 | 1600.00 | 774.92 | - |
Bus 13 | 1700.00 | 823.35 | - |
Bus 14 | 2100.00 | 1017.07 | - |
Bus 15 | 1700.00 | 823.35 | - |
Bus 16 | 1750.00 | 847.56 | - |
Bus 17 | 1050.00 | 508.54 | 300 Mvar Reactor |
Bus # | Voltage | Generation | ||
---|---|---|---|---|
(deg.) | Pg (MW) | Qg (Mvar) | ||
1 | 1.050 | 0.00 | 3645.46 | −1454.12 |
2 | 1.050 | −16.05 | 0.0 | 0.0 |
3 | 1.040 | 6.93 | 3300.0 | 47.86 |
4 | 1.050 | −16.90 | 0.0 | 0.0 |
5 | 1.050 | −24.88 | 0.0 | 0.0 |
6 | 1.040 | −1.99 | 3400.0 | 99.33 |
7 | 1.046 | −22.34 | 0.0 | 0.0 |
8 | 1.050 | −5.91 | 3600.0 | −105.07 |
9 | 1.026 | −19.38 | 0.0 | 0.0 |
10 | 1.030 | −14.59 | 3300.0 | −297.31 |
11 | 1.038 | −20.99 | 0.0 | 0.0 |
12 | 1.050 | −17.65 | 3600.0 | −387.79 |
13 | 1.050 | −8.32 | 3500.0 | 154.92 |
14 | 1.050 | −30.84 | 0.0 | 0.0 |
15 | 1.000 | −14.89 | 2800.0 | −159.61 |
16 | 1.050 | −27.17 | 0.0 | 0.0 |
17 | 1.050 | −32.51 | 0.0 | 0.0 |
Line Outage | Lowest Voltage | The Highest Line Loading | ||
---|---|---|---|---|
Bus # | % Loading | Line | ||
1–2 (1 line) | 0.937 | 2 | 39.8% | 1–7 |
1–4 (1 line) | 0.908 | 4 | 39.6% | 1–7 |
1–7 (1 line) | 0.957 | 7 | 54.7% | 1–7 |
2–3 (1 line) | 0.908 | 2 | 43.5% | 2–3 |
2–5 | 0.942 | 5 | 40.2% | 1–7 |
3–6 | 1.000 | 15 | 38.2% | 1–7 |
4–8 (1 line) | 0.921 | 4 | 34.4% | 1–7 |
5–6 | 0.900 | 5 | 37.2% | 1–7 |
5–7 | 0.949 | 5 | 34.7% | 1–7 |
5–10 | 0.901 | 5 | 35.4% | 1–7 |
6–9 (1 line) | 0.908 | 9 | 56.6% | 6–9 |
7–11 | 0.988 | 7 | 36.0% | 1–7 |
7–12 | 0.985 | 7 | 37.0% | 1–7 |
8–11 (1 line) | 0.948 | 11 | 44.2% | 8–11 |
9–10 | 0.953 | 9 | 36.0% | 1–7 |
9–15 | 0.991 | 9 | 35.9% | 1–7 |
10–14 (1 line) | 0.979 | 14 | 38.2% | 10–14 |
11–13 | 0.959 | 11 | 35.5% | 13–16 |
12–14 (1 line) | 0.970 | 14 | 39.1% | 12–16 |
12–16 (1 line) | 0.923 | 16 | 35.4% | 1–7 |
13–16 (1 line) | 0.900 | 16 | 37.1% | 13–16 |
14–17 (1 line) | 0.941 | 17 | 36.2% | 1–7 |
15–17 (1 line) | 0.900 | 17 | 36.2% | 1–7 |
Bus | Load | Fixed Shunt Reactor | |
---|---|---|---|
(MW) | (Mvar) | ||
Bus 2 | 1050.00 | 508.54 | 500 Mvar |
Bus 3 | 960.00 | 464.95 | - |
Bus 4 | 1056.00 | 511.44 | 200 Mvar |
Bus 5 | 900.00 | 435.89 | 400 Mvar |
Bus 6 | 960.00 | 464.95 | - |
Bus 7 | 1116.00 | 540.50 | 150 Mvar |
Bus 8 | 960.00 | 464.95 | 100 Mvar |
Bus 9 | 1080.00 | 523.07 | - |
Bus 10 | 960.00 | 464.95 | 250 Mvar |
Bus 11 | 1110.00 | 537.60 | - |
Bus 12 | 960.00 | 464.95 | 500 Mvar |
Bus 13 | 1020.00 | 494.01 | - |
Bus 14 | 1260.00 | 610.25 | 300 Mvar |
Bus 15 | 1020.00 | 494.01 | 100 Mvar |
Bus 16 | 1050.00 | 508.54 | 200 Mvar |
Bus 17 | 630.00 | 305.12 | 600 Mvar |
Bus # | Voltage | Generation | ||
---|---|---|---|---|
(deg.) | Pg (MW) | Qg (Mvar) | ||
1 | 1.000 | 0.00 | 2120.30 | −1970.84 |
2 | 1.032 | −9.90 | 0.0 | 0.0 |
3 | 1.000 | 4.77 | 1980.0 | −398.05 |
4 | 1.041 | −10.58 | 0.0 | 0.0 |
5 | 1.026 | −15.27 | 0.0 | 0.0 |
6 | 1.000 | −0.82 | 2040.0 | −570.53 |
7 | 1.040 | −13.81 | 0.0 | 0.0 |
8 | 1.000 | −3.30 | 2160.0 | −620.27 |
9 | 1.032 | −11.67 | 0.0 | 0.0 |
10 | 1.000 | −8.61 | 1980.0 | −546.31 |
11 | 1.025 | −12.89 | 0.0 | 0.0 |
12 | 1.000 | −10.39 | 2160.0 | −610.56 |
13 | 1.000 | −4.60 | 2100.0 | −444.45 |
14 | 1.047 | −18.73 | 0.0 | 0.0 |
15 | 1.000 | −8.99 | 1680.0 | −457.01 |
16 | 1.043 | −16.57 | 0.0 | 0.0 |
17 | 1.048 | −19.65 | 0.0 | 0.0 |
Line Outage | Lowest Voltage | The Highest Line Loading | ||
---|---|---|---|---|
Bus # | % Loading | Line | ||
1–2 (1 line) | 0.971 | 2 | 25.3% | 1–7 |
1–4 (1 line) | 0.972 | 4 | 25.4% | 1–7 |
1–7 (1 line) | 1.000 | PV Buses | 32.2% | 1–7 |
2–3 (1 line) | 0.967 | 2 | 27.5% | 2–3 |
2–5 | 0.965 | 5 | 25.4% | 1–7 |
3–6 | 1.000 | PV Buses | 24.9% | 1–7 |
4–8 (1 line) | 0.982 | 4 | 23.0% | 1–7 |
5–6 | 0.950 | 5 | 23.7% | 1–7 |
5–7 | 0.953 | 5 | 22.0% | 1–7 |
5–10 | 0.963 | 5 | 23.1% | 1–7 |
6–9 (1 line) | 0.993 | 9 | 33.0% | 6–9 |
7–11 | 0.980 | 7 | 22.8% | 1–7 |
7–12 | 1.000 | PV Buses | 23.9% | 1–7 |
8–11 (1 line) | 0.986 | 11 | 26.3% | 8–11 |
9–10 | 0.987 | 9 | 23.9% | 1–7 |
9–15 | 0.992 | 9 | 23.8% | 1–7 |
10–14 (1 line) | 1.000 | PV Buses | 24.8% | 10–14 |
11–13 | 1.000 | PV Buses | 25.4% | 13–16 |
12–14 (1 line) | 1.000 | PV Buses | 24.7% | 12–16 |
12–16 (1 line) | 0.986 | 16 | 23.8% | 1–7 |
13–16 (1 line) | 0.970 | 16 | 23.7% | 13–16 |
14–17 (1 line) | 0.964 | 17 | 23.9% | 1–7 |
15–17 (1 line) | 0.960 | 17 | 24.1% | 1–7 |
Peak Loading Condition | |||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Bus | 5 | 9 | 11 | 14 | 16 | 17 | 18 | ||||||
Mvar | 100 (Cap.) | 350 (Cap.) | 350 (Cap.) | 100 (Cap.) | 250 | 300 | 300 | ||||||
Dominant Loading Condition | |||||||||||||
Bus | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 10 | 12 | 14 | 16 | 17 | 18 |
Mvar | 450 | - | 150 | 300 | 50 | 150 | 100 | 250 | 450 | 300 | 300 | 600 | 300 |
Peak Loading Condition | ||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Bus | 5 | 7 | 9 | 11 | 14 | 16 | 17 | 18 | 18 | |||||
Mvar | 50 (Cap.) | 100 (Cap.) | 350 (Cap.) | 350 (Cap.) | 100 (Cap.) | 250 | 300 | 300 | 300 (Cap.) | |||||
Dominant Loading Condition | ||||||||||||||
Bus | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 10 | 12 | 14 | 16 | 17 | 18 | 19 |
Mvar | 450 | 150 | 150 | 300 | 500 | 150 | 100 | 250 | 450 | 300 | 300 | 600 | 300 | 300 (Cap.) |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2024 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
Dhamala, B.; Ghassemi, M. A Test System for Transmission Expansion Planning Studies. Electronics 2024, 13, 664. https://doi.org/10.3390/electronics13030664
Dhamala B, Ghassemi M. A Test System for Transmission Expansion Planning Studies. Electronics. 2024; 13(3):664. https://doi.org/10.3390/electronics13030664
Chicago/Turabian StyleDhamala, Bhuban, and Mona Ghassemi. 2024. "A Test System for Transmission Expansion Planning Studies" Electronics 13, no. 3: 664. https://doi.org/10.3390/electronics13030664
APA StyleDhamala, B., & Ghassemi, M. (2024). A Test System for Transmission Expansion Planning Studies. Electronics, 13(3), 664. https://doi.org/10.3390/electronics13030664