Joint Optimization of Berth and Shore Power Allocation Considering Vessel Priority Under the Dual Carbon Goals
Abstract
1. Introduction
1.1. Literature Review
1.2. The Contributions of This Paper
2. Problem Description and Model Formulations
2.1. Problem Description
2.2. Model Formulations
2.2.1. Model Assumption Conditions
- (1)
- Waterway conditions are assumed to consistently satisfy navigation requirements, ensuring that all vessels can safely access and depart from the terminal.
- (2)
- The vessels’ arrival time is known due to ships’ time table, and the influence of weather, accidents and other interference on the vessels are not into consideration.
- (3)
- All berths and shore power systems are assumed to be initially idle, ensuring a well-defined initial system state and avoiding the complexity associated with pre-existing allocations.
- (4)
- The shore power connection time is assumed to be negligible compared to the vessel berthing and handling time.
2.2.2. Model Parameters and Definitions
2.2.3. Mathematical Model
3. Solution Method
| Algorithm 1: Pseudo-code for the improved ALNS-II algorithm |
| 1 Input: Model parameters, maximum iteration count , initial temperature , cooling rate destruction ratio 2 Output: Pareto archive 𝒜 (set of non-dominated solutions), best compromise solution 3 Initialization: 4 Generate initial solution S0 using heuristic rules S ← S0, T ← T0 5 Initialize Pareto archive 𝒜 ← {S0} 6 Initialize destruction operator weights ← [0.25, 0.25, 0.25, 0.25] 7 Initialize repair operator weights ← [0.33, 0.33, 0.34] 8 Initialize operator scores ← 0, ← 0 9 Initialize operator usage counters ← 0, ← 0 10 Main Loop: 11 for k = 1 to do 12 Select destruction operator d ∈ Ω− based on weights 13 Select repair operator r ∈ Ω+ based on weights 14 ← + 1, ← + 1 15 S’ ← Apply destruction operator d to S (remove ξ·|I| vessels) 16 S’ ← Apply repair operator r to reconstruct S’ 17 Compute objective values F1(S’) and F2(S’) using Equations (5) and (6) 18 //Multi-Objective Acceptance Criterion 19 if S’ dominates S (i.e., F1(S’) ≤ F1(S) and F2(S’) ≤ F2(S), with at least one strict inequality) then 20 S ← S’ 21 Update operator scores ← + 30, ← + 30 22 else if S’ is not dominated by S then 23 Δmin ← min {F1 (S’) − F1(S), F2(S’) − F2(S)} 24 if exp (−Δmin/T) > random (0,1) then 25 S ← S’ 26 Update operator scores ← + 15, ← + 15 27 else 28 Update operator scores ← + 5, ← + 5 29 end if 30 end if 31 //Pareto Archive Update 32 if S’ is not dominated by any solution in 𝒜 then 33 Add S’ to 𝒜 34 Remove from 𝒜 any solution dominated by S’ 35 end if 36 //Adaptive Weight Update 37 Update destruction operator weights ← (1 − r) + r () 38 Update repair operator weights ← (1 − r) + r (/) 39 T ← αT 40 end for 41 Return: Pareto archive 𝒜 and best compromise solution (closest to origin) |
3.1. Initial Solution Generation
3.2. Design of Destruction and Repair Operators
3.3. Adaptive Mechanism
3.4. Acceptance Criteria and Termination Conditions
3.5. Multi-Objective Handling Strategy
3.6. Comparison with Classical ALNS
4. Numerical Experiments
4.1. Experiment Settings
4.2. Results and Analysis of Numerical Examples
4.3. Algorithm Performance
4.3.1. Algorithm Effectiveness Analysis
4.3.2. Algorithm Comparisons
4.4. Sensitivity Analysis
4.4.1. Impact of Electricity Pricing Mechanisms
4.4.2. Impact of New Energy Vessel Proportions
4.4.3. Impact of Vessel Costs
4.4.4. Impact of Carbon Tax Pricing Mechanisms
5. Discussion
6. Conclusions
Author Contributions
Funding
Data Availability Statement
Conflicts of Interest
References
- Yu, H.; Huang, M.; He, J.; Tan, C. The clustering strategy for stacks allocation in automated container terminals. Marit. Policy Manag. 2023, 50, 1102–1117. [Google Scholar] [CrossRef]
- Imai, A.; Nishimura, E.; Papadimitriou, S. Berth allocation with service priority. Transp. Res. Part B Methodol. 2003, 37, 437–457. [Google Scholar] [CrossRef]
- Lin, X.; Pu, X.; Bai, X. On the efficiency impacts of berthing priority provision. Transp. Sci. 2024, 58, 578–596. [Google Scholar] [CrossRef]
- Gao, Y.; Zhen, L.; Lu, H.; Xu, X. Ship Scheduling for Taicang Port. Inf. J. Appl. Anal. 2025, 55, 484–505. [Google Scholar] [CrossRef]
- Ganji, F.; Gholami, S. Minimizing fuel emission by optimizing ship scheduling considering priorities and release times. Int. J. Environ. Sci. Technol. 2024, 21, 135–152. [Google Scholar] [CrossRef]
- Yıldırım, M.S.; Aydın, M.M.; Gökkuş, Ü. Simulation optimization of the berth allocation in a container terminal with flexible vessel priority management. Marit. Policy Manag. 2020, 47, 833–848. [Google Scholar] [CrossRef]
- Chen, X.; Yan, R.; Wu, S.; Liu, Z.; Mo, H.; Wang, S. A fleet deployment model to minimise the covering time of maritime rescue missions. Marit. Policy Manag. 2023, 50, 724–749. [Google Scholar] [CrossRef]
- Lu, H.; Lu, X. Joint optimization of berths and quay cranes considering carbon emissions: A case study of a container terminal in China. J. Mar. Sci. Eng. 2025, 13, 148. [Google Scholar] [CrossRef]
- Ursavas, E. Priority control of berth allocation problem in container terminals. Ann. Oper. Res. 2022, 317, 805–824. [Google Scholar] [CrossRef]
- Jiang, S.; Liu, L.; Peng, P.; Xu, M.; Yan, R. Prediction of vessel arrival time to port: A review of current studies. Marit. Policy Manag. 2025, 53, 301–326. [Google Scholar] [CrossRef]
- Wang, Z.; Cheng, J.; Hu, H. A proactive-reactive-based approach for continuous berth allocation and quay crane assignment problems with hybrid uncertainty. J. Mar. Sci. Eng. 2024, 12, 182. [Google Scholar] [CrossRef]
- Zhen, L.; Wang, W.; Lin, S. Analytical comparison on two incentive policies for shore power equipped ships in berthing activities. Transp. Res. Part E Logist. Transp. Rev. 2022, 161, 102686. [Google Scholar] [CrossRef]
- Song, Z.; Tang, W.; Zhao, R.; Zhang, G. Implications of government subsidies on ship companies’ shore power usage strategies in port. Transp. Res. Part E Logist. Transp. Rev. 2022, 165, 102840. [Google Scholar] [CrossRef]
- Peng, Y.; Li, X.; Wang, W.; Wei, Z.; Bing, X.; Song, X. A method for determining the allocation strategy of on-shore power supply from a green container terminal perspective. Ocean Coast. Manag. 2019, 167, 158–175. [Google Scholar] [CrossRef]
- Zhang, Z.; Zhu, Y.; Zhu, J.; Huang, D.; Yin, C.; Li, J. Collaborative optimization of shore power and berth allocation based on economic, environmental, and operational efficiency. J. Mar. Sci. Eng. 2025, 13, 776. [Google Scholar] [CrossRef]
- Wang, T.; Du, Y.; Fang, D.; Li, Z. Berth allocation and quay crane assignment for the trade-off between service efficiency and operating cost considering carbon emission taxation. Transp. Sci. 2020, 54, 1307–1331. [Google Scholar] [CrossRef]
- Rodrigues, F.; Agra, A. Berth allocation and quay crane assignment/scheduling problem under uncertainty: A survey. Eur. J. Oper. Res. 2022, 303, 501–524. [Google Scholar] [CrossRef]
- Zhen, L.; Zhuge, D.; Wang, S.; Wang, K. Integrated berth and yard space allocation under uncertainty. Transp. Res. Part B Methodol. 2022, 162, 1–27. [Google Scholar] [CrossRef]
- Guo, L.; Zheng, J.; Du, J.; Du, J.; Gao, Z.; Fagerholt, K. Integrated planning of berth allocation, quay crane assignment and yard assignment in multiple cooperative terminals. Transp. Res. Part E Logist. Transp. Rev. 2024, 183, 103456. [Google Scholar] [CrossRef]
- Zhang, Y.; Liang, C.; Shi, J.; Lim, G.; Wu, Y. Optimal port microgrid scheduling incorporating onshore power supply and berth allocation under uncertainty. Appl. Energy 2022, 313, 118856. [Google Scholar] [CrossRef]
- Wang, Z.; Hu, H.; Zhen, L. Berth and quay cranes allocation problem with on-shore power supply assignment in container terminals. Comput. Ind. Eng. 2024, 188, 109910. [Google Scholar] [CrossRef]
- Parise, G.; Parise, L.; Malerba, A.; Pepe, F.M.; Honorati, A.; Chavdarian, P.B. Comprehensive peak-shaving solutions for port cranes. IEEE Trans. Ind. Appl. 2016, 53, 1799–1806. [Google Scholar] [CrossRef]
- van Duin, J.H.R.; Geerlings, H.; Verbraeck, A.; Nafde, T. Cooling down: A simulation approach to reduce energy peaks of reefers at terminals. J. Clean. Prod. 2018, 193, 72–86. [Google Scholar] [CrossRef]
- Iris, Ç.; Lam, J.S.L. Optimal energy management and operations planning in seaports with smart grid while harnessing renewable energy under uncertainty. Omega 2021, 103, 102445. [Google Scholar] [CrossRef]
- Yu, J.; Voß, S.; Song, X. Multi-objective optimization of daily use of shore side electricity integrated with quayside operation. J. Clean. Prod. 2022, 351, 131406. [Google Scholar] [CrossRef]
- Dai, H.; Ma, J.; Yang, Y.; Sun, J.; Dai, Y. A bi-layer model for berth allocation problem based on proactive-reactive strategy. Comput. Ind. Eng. 2023, 179, 109200. [Google Scholar] [CrossRef]









| Paper | Berth Allocation | Shore Power Allocation | TOU Pricing | Objective | Solution Method |
|---|---|---|---|---|---|
| [4] Gao et al. (2025) | ✓ | Minimize ships’ total stay time | GUROBI + ALNS | ||
| [5] Ganji et al. (2024) | ✓ | Minimize ship pollutant emissions | GAMS(38.2) + Simulation | ||
| [19] Guo et al. (2024) | ✓ | ✓ | Minimize total port operating cost | CPLEX + ALNS | |
| [20] Zhang et al. (2022) | ✓ | ✓ | Minimize ship berthing cost and microgrid operation cost | CPLEX + Heuristic Algorithm | |
| [21] Wang et al. (2024) | ✓ | ✓ | Minimize port operation cost, energy consumption, and total crane emissions | Adaptive Immune Clonal Selection Algorithm | |
| [25] Yu et al. (2022) | ✓ | ✓ | ✓ | Minimize shore power usage cost, berthing delay, and carbon emissions | Meta-Heuristic Algorithm |
| This paper | ✓ | ✓ | ✓ | Minimizing the total economic costs of vessels and environmental tax costs from pollutant emissions | ALNS Algorithm |
| Set | Description |
|---|---|
| The set of vessels during the planning period, } | |
| The set of discretized continuous berths, } | |
| Set of operational periods t within the planning period, T } | |
| Set of pollutants, P ,,,} | |
| Set of vessel types, V } 1 = Electric vessels, 2 = Fuel vessels, 3 = Methane vessels | |
| Set of shore power equipment, E } | |
| Electricity period, K , where = peak period, = flat period, = valley period | |
| Parameters | |
| Vessel type , V | |
| Cargo handling capacity of vessel (tons) | |
| Length of vessel (m) | |
| Engine power of vessel (kW) | |
| Arrival time of vessel (hours) | |
| Duration of berthing and cargo handling operations for Vessel (hours) | |
| Estimated departure time of vessel (hours) | |
| Diesel price ($/liter) | |
| Peak Electricity Rate ($/kWh) | |
| Flat electricity rate ($/kWh) | |
| Valley electricity rate ($/kWh) | |
| Delay Cost for Vessel ($/hour) | |
| Waiting cost for vessel at anchorage ($/hour) | |
| Pollutant unit emission tax ($/kg) | |
| Maximum power supply distance of shore power equipment (m) | |
| Distance from shore power equipment to berth (m) | |
| Ship auxiliary machinery load factor | |
| Ship auxiliary machinery diesel consumption rate (liters/kWh) | |
| Pollutant emission factor (kg/L) | |
| Minimum shore power supply capacity (kW) | |
| Maximum shore power supply capacity (kW) | |
| Total shoreline length (m) | |
| Sufficiently large positive number | |
| Minimum safety distance for methanol vessels (m) | |
| Selection of methanol vessel refueling sites | |
| Charging time required for electric vessel (hours) | |
| Fueling time required for methanol vessel (hours) | |
| Remaining energy capacity of vessel upon arrival at port (%) | |
| Priority time window (hours), set to 1 h | |
| Auxiliary Variables | |
| Binary, equal to 1 if berthing areas of ships and do not overlap; else 0 | |
| Binary, equal to 1 if the berthing time windows of vessels and j do not overlap; else 0 | |
| Binary, equal to 1 if vessel is prioritized over vessel for berthing; else 0 | |
| Binary, equal to 1 if the arrival time difference between new energy vessel i and fuel-powered vessel j is within ; else 0 | |
| Decision Variables | |
| Binary, equal to 1 if Ship docked at berth b at time t; else 0 | |
| Binary, equal to 1 if Ship uses shore power equipment ; else 0 | |
| Binary, equal to 1 if Ship uses shore power during berthing; else 0 | |
| Actual berthing time for vessel | |
| Vessel Actual Departure Time | |
| Duration of Ship’s Electricity Consumption During Peak Pricing Period | |
| Duration of electricity consumption by vessel during flat periods | |
| Duration of electricity consumption by vessel during valley pricing periods | |
| Start time of charging for the electric vessel | |
| Start time of the methanol vessels fuel replenishment | |
| Aspect | Classical ALNS | Proposed ALNS-II |
|---|---|---|
| Objective | Single-objective | Bi-objective (Pareto-based) |
| Acceptance criterion | Simulated annealing based on single objective improvement | Pareto dominance check + non-dominated acceptance probability |
| Pareto archive | Not maintained | External archive stores all non-dominated solutions; updated after each iteration |
| Destruction operators | Random, worst-cost (general purpose) | Random, worst-cost, correlation disruption, time-slot disruption |
| Correlation disruption | _ | Destroys vessels with overlapping berthing times: |
| Time-slot disruption | _ | Destroys vessels berthing during peak tariff periods |
| Repair operators | Greedy (general purpose) | Greedy, regret-based, random |
| Regret-based repair | _ | Prioritizes vessels with higher regret |
| Adaptive weight update | Based on single objective improvement scores | Based on multi-objective scores |
| Operator weights | Adjust according to the historical scores dynamically | The same mechanism, but the scores are derived from multi-objective scoring |
| Time Period | Electricity Price/($/kWh) | Time Period |
|---|---|---|
| Peak Period | 1.15 | 9:00 AM–12:00 PM, 7:00 PM–10:00 PM |
| Flat Period | 0.55 | 8:00 AM–9:00 AM, 12:00 PM–7:00 PM, 10:00 PM–12:00 AM |
| Valley Period | 0.37 | 0:00 AM–8:00 AM |
| Vessel ID | Length /m | Vessel Type | Arrival Time | Estimated Departure Time | Loading/ Unloading Time (h) | Delay Cost ($) | Waiting Cost ($) | Loading/ Unloading Volume (TEU) | Energy Reserve (%) | Charging Time (h) | Refueling Time (h) |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 123 | Fuel | 08:18 | 19:00 | 10 | 89.13 | 44.57 | 900 | 35 | 0 | 0 |
| 2 | 119 | Electric | 08:45 | 17:00 | 8 | 86.23 | 43.12 | 730 | 34 | 9 | 0 |
| 3 | 113 | Methanol | 08:58 | 18:00 | 8 | 81.88 | 40.94 | 780 | 27 | 0 | 8.6 |
| 4 | 115 | Fuel | 11:14 | 21:30 | 9 | 83.33 | 41.67 | 880 | 26 | 0 | 0 |
| 5 | 95 | Electric | 16:35 | 22:40 | 6 | 68.84 | 34.42 | 580 | 35 | 5 | 0 |
| 6 | 105 | Methanol | 19:55 | 4:55 | 7 | 76.09 | 38.04 | 620 | 38 | 0 | 8 |
| 7 | 106 | Fuel | 20:27 | 06:00 | 8 | 76.81 | 38.41 | 860 | 22 | 0 | 0 |
| 8 | 89 | Electric | 20:34 | 03:00 | 5 | 64.79 | 32.25 | 450 | 23 | 6 | 0 |
| 9 | 93 | Methanol | 21:00 | 05:00 | 6 | 67.39 | 33.70 | 540 | 31 | 0 | 5 |
| 10 | 138 | Fuel | 22:10 | 10:40 | 12 | 100.00 | 50.00 | 950 | 26 | 0 | 0 |
| 11 | 96 | Electric | 21:35 | 6:00 | 8 | 69.57 | 34.78 | 750 | 37 | 8.5 | 0 |
| 12 | 95 | Methanol | 23:48 | 8:30 | 8 | 68.84 | 34.42 | 720 | 36 | 0 | 8 |
| Emitted Pollutants | |||||
|---|---|---|---|---|---|
| Emission Factor | 0.308 | 0.00002 | 0.0468 | 0.0014 | 0.0014 |
| Symbol | Description | Minimum | Maximum | Optimal Value |
|---|---|---|---|---|
| η | Maximum Iterations | 500 | 5000 | 1000 |
| T | Initial temperature (simulated annealing) | 1000 | 100,000 | 50,000 |
| α | Temperature cooling rate | 0.90 | 0.999 | 0.995 |
| ρ | Failure rate parameter | 0.1 | 0.3 | 0.2 |
| New Optimal Solution Reward Weight | 20 | 50 | 30 | |
| Better Solution Reward Weight | 10 | 30 | 15 | |
| Acceptable Solution Reward Weight | 1 | 10 | 5 | |
| P | Acceptance Probability Parameter | 0.15 | 0.25 | 0.2 |
| Random Destruction of Initial Weights | 0.1 | 0.4 | 0.25 | |
| Correlated initial weight perturbation | 0.1 | 0.4 | 0.25 | |
| Initial weight for the time period damage | 0.1 | 0.4 | 0.25 | |
| Worst-case disruption initial weight | 0.1 | 0.4 | 0.25 | |
| Greedy Repair Initial Weight | 0.2 | 0.6 | 0.33 | |
| Regret value correction initial weight | 0.2 | 0.6 | 0.33 | |
| Randomly restore initial weight | 0.2 | 0.6 | 0.33 |
| Vessel Decision Scenario | Affected Vessel | Shore Power Usage Cost ($) | Vessel Delay Cost ($) | Vessel Waiting Cost ($) | Total Economic Cost ($) |
|---|---|---|---|---|---|
| Scenario A | Methanol Vessel 6 | 5635.62 | 1118.75 | 0 | 6753.37 |
| Fuel Vessel 5 | 0 | 1584.23 | 1336.36 | 2920.59 | |
| Scenario B | Methanol Vessel 6 | 1312.41 | 936.57 | 1058.41 | 3306.39 |
| Fuel Vessel 5 | 0 | 1007.56 | 0 | 1007.76 | |
| Scenario C | Electric Vessel 7 | 5228.45 | 1204.13 | 0 | 6432.58 |
| Fuel Vessel 2 | 2668.31 | 1356.73 | 1376.62 | 5400.56 | |
| Scenario D | Electric Vessel 7 | 1296.34 | 1372.42 | 1248.13 | 3916.49 |
| Fuel Vessel 2 | 3107.56 | 1145.61 | 0 | 4252.17 |
| Objective Function Value | FCFS Baseline | Proposed Model | Improvement |
|---|---|---|---|
| Total Economic Cost ($) | 225,438.52 | 183,245.76 | 23.03% |
| Environmental Tax Cost ($) | 62,723.15 | 51,648.23 | 21.44% |
| INS | Total Economic Cost ($) | Environmental Tax Cost ($) | ||||||
|---|---|---|---|---|---|---|---|---|
| GUROBI | ALNS-II | GAP (%) | GUROBI Running Time (s) | GUROBI | ALNS-II | ALNS-II Running Time (s) | GAP (%) | |
| B4_S18_P4 | 186,382.52 | 186,382.52 | 0.00% | 219 | 52,453.95 | 52,453.95 | 10 | 0.00% |
| B4_S21_P4 | 195,218.93 | 195,218.93 | 0.00% | 288 | 53,690.21 | 53,690.36 | 13 | 0.00% |
| B4_S24_P4 | 197,892.31 | 198,255.45 | 0.18% | 174 | 55,218.75 | 55,418.23 | 15 | 0.36% |
| B4_S27_P4 | 204,126.13 | 205,079.53 | 0.47% | 440 | 57,640.36 | 57,880.27 | 19 | 0.42% |
| B4_S30_P4 | 210,653.83 | 211,424.63 | 0.37% | 356 | 58,482.42 | 58,693.42 | 23 | 0.36% |
| B4_S33_P4 | 221,989.54 | 223,493.52 | 0.68% | 691 | 59,690.96 | 60,038.46 | 27 | 0.58% |
| B5_S36_P5 | 232,914.76 | 234,712.63 | 0.77% | 157 | 62,694.25 | 63,067.46 | 29 | 0.60% |
| B5_S39_P5 | 236,782.49 | 239,186.36 | 1.02% | 1215 | 65,603.46 | 66,211.48 | 48 | 0.93% |
| B5_S42_P5 | 246,317.56 | 248,562.59 | 0.91% | 2624 | 67,723.52 | 68,302.51 | 61 | 0.85% |
| B5_S45_P5 | 249,932.43 | 253,028.18 | 1.24% | 2072 | 71,994.21 | 72,920.36 | 78 | 1.29% |
| B5_S48_P5 | 256,684.82 | 258,329.64 | 0.64% | 6258 | 73,684.05 | 74,315.34 | 98 | 0.86% |
| B5_S51_P5 | 289,066.48 | 290,217.34 | 0.40% | 1980 | 74,824.15 | 75,214.66 | 103 | 0.52% |
| B5_S54_P5 | 297,926.35 | 299,371.56 | 0.49% | 3634 | 75,573.48 | 76,122.52 | 120 | 0.73% |
| B6_S57_P6 | 307,025.62 | 309,937.71 | 0.95% | 2079 | 76,917.36 | 77,939.03 | 146 | 1.33% |
| B6_S60_P6 | — | 315,292.83 | 1.15% † | 10,800 | — | 78,243.68 | 167 | 1.52% † |
| B6_S63_P6 | — | 329,980.45 | 1.32% † | 10,800 | — | 81,437.81 | 182 | 1.78% † |
| B6_S66_P6 | — | 332,965.61 | 1.08% † | 10,800 | — | 82,269.45 | 196 | 1.45% † |
| B6_S69_P6 | — | 349,950.32 | 1.21% † | 10,800 | — | 86,479.07 | 217 | 1.60% † |
| B6_S72_P6 | — | 351,314.96 | 0.94% † | 10,800 | — | 88,974.86 | 228 | 1.27% † |
| B6_S75_P6 | — | 382,919.37 | 1.45% † | 10,800 | — | 89,381.46 | 242 | 1.93% † |
| Floating Scheme | TOU Pricing Adjustment Strategy | Electricity Price/[($·(kWh))] | Peak-Valley Price Differential |
|---|---|---|---|
| 1 | Peak Electricity Price Reduced by 30% | Peak: 0.81, flat: 0.69, Valley: 0.36 | 2.25:1 |
| Valley electricity rates increased by 30% | |||
| 2 | Peak electricity rates reduced by 20% | Peak: 0.92, flat: 0.69, Valley: 0.34 | 2.71:1 |
| Valley electricity rates increased by 20% | |||
| 3 | Peak electricity rates reduced by 10% | Peak: 1.04, flat: 0.69, Valley: 0.31 | 3.35:1 |
| Valley electricity rates increased by 10% | |||
| 4 | Electricity rates unchanged | Peak: 1.15, flat: 0.69, Valley: 0.28 | 4.11:1 |
| 5 | Peak electricity rates increased by 10% | Peak: 1.27, flat: 0.69, Valley: 0.25 | 5.08:1 |
| Valley electricity rates reduced by 10% | |||
| 6 | Peak electricity rates increased by 20% | Peak: 1.38, flat: 0.69, Valley: 0.22 | 6.27:1 |
| Valley electricity rates reduced by 20% | |||
| 7 | Peak electricity rates increased by 30% | Peak: 1.50, flat: 0.69, Valley: 0.20 | 7.50:1 |
| Valley electricity rates reduced by 30% |
| Example | New Energy Vessels Ratio (%) | Ship Time Cost ($) | Energy Consumption Cost ($) | Total Ship Economics Cost ($) | Pollutant Emissions Environmental Tax Cost ($) |
|---|---|---|---|---|---|
| 1 | 10 | 101,169.26 | 85,213.46 | 188,373.28 | 65,829.35 |
| 2 | 20 | 101,713.46 | 90,487.15 | 195,394.36 | 64,921.48 |
| 3 | 30 | 102,167.44 | 95,642.78 | 197,356.24 | 62,793.62 |
| 4 | 30 | 102,373.15 | 100,328.91 | 202,496.35 | 61,836.63 |
| 5 | 50 | 102,784.76 | 105,791.23 | 208,164.38 | 59,374.45 |
| 6 | 60 | 102,913.76 | 110,255.37 | 211,424.63 | 58,693.42 |
| 7 | 70 | 103,159.82 | 115,638.49 | 218,423.25 | 57,104.55 |
| 8 | 80 | 103,272.52 | 120,472.56 | 223,386.32 | 56,280.35 |
| 9 | 90 | 104,907.21 | 125,186.84 | 228,459.36 | 54,391.24 |
| Cost Item | Baseline ($) | Waiting Cost Increased by 50% | Difference from Benchmark Difference/% | Delay Cost Increased by 50% | Compared to Baseline Difference/% |
|---|---|---|---|---|---|
| Total Economic Cost per Vessel ($) | 177,061.75 | 23,826.48 | 34.77% | 189,256.65 | 6.89% |
| Environmental Tax Cost Pollutant Emission ($) | 48,089.70 | 56,483.50 | 17.46% | 50,997.30 | 6.05% |
| Vessel Time Cost ($) | 108,386.65 | 125,233.43 | 15.54% | 112,761.35 | 4.04% |
| Ship Energy Consumption Cost ($) | 68,675.10 | 83,393.05 | 21.46% | 71,495.30 | 4.11% |
| Metric | Single-Rate Tax | Tiered Tax |
|---|---|---|
| Total Pollutant emissions volume (kg) | 23,580.13 | 18,920.04 |
| Vessels using shore power (ID) | 2,3,6,7,10,11 | 1,2,4,7,8,9,10,12 |
| Shore power cost ($) | 5635.62 | 31,731.52 |
| Pollutant emission environmental tax cost ($) | 62,723.15 | 50,617.58 |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2026 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license.
Share and Cite
Zhang, Y.; Wang, W.; Lu, H. Joint Optimization of Berth and Shore Power Allocation Considering Vessel Priority Under the Dual Carbon Goals. J. Mar. Sci. Eng. 2026, 14, 688. https://doi.org/10.3390/jmse14070688
Zhang Y, Wang W, Lu H. Joint Optimization of Berth and Shore Power Allocation Considering Vessel Priority Under the Dual Carbon Goals. Journal of Marine Science and Engineering. 2026; 14(7):688. https://doi.org/10.3390/jmse14070688
Chicago/Turabian StyleZhang, Yongfeng, Wenya Wang, and Houjun Lu. 2026. "Joint Optimization of Berth and Shore Power Allocation Considering Vessel Priority Under the Dual Carbon Goals" Journal of Marine Science and Engineering 14, no. 7: 688. https://doi.org/10.3390/jmse14070688
APA StyleZhang, Y., Wang, W., & Lu, H. (2026). Joint Optimization of Berth and Shore Power Allocation Considering Vessel Priority Under the Dual Carbon Goals. Journal of Marine Science and Engineering, 14(7), 688. https://doi.org/10.3390/jmse14070688

