1. Introduction
Offshore wind energy is expected to play a central role in the global energy transition, with floating offshore wind enabling deployment in deep-water regions where bottom-fixed solutions are not feasible. Global offshore wind capacity has expanded rapidly in recent years, reaching more than 68 GW of installed capacity by 2023 and exceeding 80 GW by 2024, with continued strong growth expected toward 2030. Despite this progress, floating offshore wind remains at an early stage of commercial deployment, with global installed capacity still below 300 MW, highlighting the gap between technological potential and large-scale deployment [
1,
2].
The installation phase represents one of the most critical contributors to project cost and schedule risk. Industry and technical economic studies indicate that installation and commissioning activities account for approximately 10 to 20% of total project CAPEX, with vessel day rates and offshore operation duration representing the dominant cost drivers [
3]. Recent cost assessments further show that floating offshore wind systems remain significantly more expensive than bottom-fixed systems, with total capital costs typically ranging between 5000 and 8000 USD/kW depending on project configuration and site conditions. Although the levelised cost of offshore wind energy has decreased by more than 40% over the past decade, cost reductions for floating wind remain limited due to installation complexity and immature supply chains [
4]. Consequently, improving installation logistics is widely recognised as a key pathway toward reducing the levelized cost of energy for floating offshore wind projects.
A substantial body of research has been devoted to offshore wind installation logistics and planning. Poulsen and Hasager [
5] demonstrated that improved logistics strategies can reduce installation costs through optimised vessel utilisation. Kaiser and Snyder [
6] developed cost estimation approaches for offshore wind installation, while Thomsen [
7] provided detailed descriptions of installation processes and logistical constraints. Simulation and optimisation-based approaches have further advanced installation planning, including decision support systems developed by Lange et al. [
8] and optimisation frameworks proposed by Ait-Alla et al. [
9]. Discrete-event simulation methods have also been applied to evaluate installation timelines and identify logistical bottlenecks under realistic operating conditions [
10,
11,
12]. More recent studies have extended these approaches to floating offshore wind systems. Díaz and Guedes Soares [
13] reviewed the state of offshore wind technology and highlighted the increasing importance of logistics for floating wind deployment. In subsequent work, Díaz and Guedes Soares [
14] demonstrated that installation duration is highly sensitive to vessel configuration, transport distance, and logistics strategy. Complementary studies by Vis and Ursavas [
15] and Maples et al. [
16] emphasised the importance of supply chain design and pre-assembly strategies in improving installation efficiency.
More recently, Ivanov and Ma [
17] investigated floater assembly and turbine integration strategies for large floating offshore wind turbines, highlighting the importance of port infrastructure, crane capacity, storage arrangements, and assembly location in determining the feasibility and cost-effectiveness of floating wind deployment.
Environmental conditions play a decisive role in offshore installation performance. Weather downtime (WDT) is a key factor governing installation schedules, as offshore operations are constrained by limits on wave height, wave period, wave heading, wind speed, and vessel motions. Previous studies have shown that weather-related delays can account for approximately 20–40% of total installation time, depending on site conditions and operation type [
10,
17]. Barlow et al. [
18,
19] demonstrated the sensitivity of installation duration to weather variability, while subsequent studies further confirmed the importance of incorporating environmental effects into logistics simulations. Weather window analysis remains a fundamental tool for evaluating offshore operability, as highlighted by Martins et al. [
20], who showed that accurate metocean representation is essential for reliable prediction of offshore operations. Recent studies on floating offshore wind maintenance operations have similarly demonstrated that vessel dynamics, wave conditions, and floating-to-floating interaction effects can significantly constrain offshore lifting and component handling activities [
21].
More recent research has advanced the representation of weather-dependent operability through the incorporation of probabilistic weather windows and forecast uncertainty into offshore operational planning. In particular, environmental variability has been shown to strongly influence installation scheduling, operational risk, and downtime, especially for activities constrained by strict motion limits and environmental thresholds [
22,
23,
24].
In parallel, offshore engineering research has established methodologies for assessing operational limits in weather-restricted marine operations. Clauss and Riekert [
25] defined motion-based criteria for offshore lifting operations, while Cozijn et al. [
26] investigated hydrodynamic responses during offshore installation activities. More recent work using spectral wave analysis has demonstrated the importance of accurately capturing environmental loading for assessing structural response and operational limits in offshore operations [
27]. Industry standards, such as DNV-RP-C205 [
28], further define environmental loading and operational criteria, which directly influence installation planning and operability assessment.
Floating offshore wind installations introduce additional challenges compared to bottom-fixed systems, particularly due to the dynamic response of floating structures and the increased complexity of marine operations [
29]. Recent review studies further highlight that installation logistics, vessel operations, and environmental constraints remain key challenges for large-scale deployment of floating wind farms [
30]. Current installation practices are largely based on towing pre-assembled or partially assembled floating structures to offshore sites, followed by hook-up and commissioning operations. Recent studies on FOWT wet-towing operations have further highlighted the importance of towing dynamics, tugboat–floater interaction, forward-speed effects, and environmental loading in assessing the feasibility and safety of towing-based deployment strategies [
31,
32]. This approach has been successfully implemented in projects such as Hywind Scotland and Hywind Tampen [
33,
34], as well as semi-submersible concepts such as the WindFloat projects, which have demonstrated alternative installation and deployment strategies [
35]. However, these approaches remain highly sensitive to weather conditions and dependent on suitable assembly locations and offshore operations. These constraints become increasingly significant for large-scale deployment and serial installation of floating wind turbines.
To improve installation efficiency, alternative installation concepts have been proposed. Jiang et al. [
36] investigated innovative installation vessel concepts and demonstrated their potential to improve operational stability and reduce offshore lifting requirements. Broader assessments of offshore wind installation have shown that installation strategy has a direct influence on project duration and overall efficiency [
37]. In this context, Hassan and Guedes Soares [
38,
39] introduced the Nordic Wind concept, which enables onshore assembly of wind turbines and reduces reliance on weather-sensitive offshore lifting operations through a motion-compensated transfer system. Additional studies have shown that improvements in installation strategy can significantly reduce installation time and enhance overall project performance [
40,
41,
42].
Despite these developments, important gaps remain in the literature. Existing studies primarily address offshore wind installation from isolated perspectives, including logistics optimisation, vessel design, or the assessment of individual installation concepts. However, there is a lack of studies that systematically compare fundamentally different installation methodologies under consistent logistical, operational, and environmental assumptions. In particular, the influence of installation philosophy, such as towing-based strategies versus integrated installation concepts, on key performance indicators remains insufficiently understood.
Furthermore, while weather downtime (WDT) is widely recognised as a critical factor governing offshore operations, its role is often treated as an external constraint rather than a primary metric for comparing installation strategies. As a result, the relationship between installation methodology, weather-dependent operability, and overall installation duration has not been comprehensively quantified for floating offshore wind applications.
This limitation is particularly significant given that weather-related delays can account for a substantial portion of total installation time. In addition, although installation cost is known to be strongly influenced by vessel spread and offshore operation duration, there is limited work that explicitly links logistics efficiency and operability performance to quantifiable cost implications. In particular, the potential cost benefits associated with reducing offshore activities, minimising weather exposure, and enabling alternative installation sequences remain insufficiently assessed in the context of floating wind deployment.
In addition to installation efficiency, installation philosophy may also influence future operation and maintenance (O&M) strategies for floating offshore wind systems. Existing studies have highlighted the importance of tow-to-port and in situ maintenance approaches, weather-dependent accessibility, and vessel logistics in determining lifecycle operability and maintenance performance of floating offshore wind farms [
41]. Although maintenance operations are outside the scope of the present study, the relationship between installation methodology and lifecycle maintenance strategy represents an important direction for future research. To address these gaps, the present study develops a simulation-based logistics framework to evaluate the impact of a novel installation method (Nordic Wind) as an alternative to conventional towing-based approaches. The proposed framework enables a direct and consistent comparison between installation methodologies by incorporating detailed logistics sequences, vessel operations, and environmental constraints. Unlike multi-criteria decision-making approaches, which typically rank alternatives using weighted evaluation criteria, the proposed methodology is based on a simulation-driven operational framework that explicitly models installation sequences, vessel activities, and weather-dependent operability to quantify installation performance metrics. The analysis explicitly quantifies weather downtime, total installation duration, and associated logistical performance across multiple case study locations. By comparing a novel installation methodology with current industry practice, this study provides new insights into how installation strategy can influence project duration, weather exposure, and ultimately the potential for cost reduction in floating offshore wind projects.
2. Installation Methodology
The installation of floating offshore wind turbines presents unique challenges due to the scale of components, reliance on marine operations, and sensitivity to environmental conditions. Current industry practices and emerging concepts differ significantly in how installation activities are distributed between onshore, nearshore, and offshore environments. In this study, the term installation method refers to the physical process by which the wind turbine and floating foundation are assembled, transported, and installed offshore. By contrast, logistics strategy refers to the sequencing, coordination, and resource allocation associated with the installation campaign, including vessel utilisation, port activities, transport cycles, and weather-dependent waiting periods. The Nordic Wind concept affects both aspects: it modifies the physical installation process through offshore float-over turbine integration and changes the logistics strategy by decoupling turbine assembly from the installation of the floating foundation. To assess the combined influence of installation method and logistics strategy on project performance, this study considers two distinct approaches:
The conventional towing-based installation method, which represents the current floating wind practice.
The Nordic Wind installation method, which introduces a float-over installation concept for offshore turbine integration.
2.1. Conventional Floating Wind Installation Method
Existing floating offshore wind projects, including Hywind, WindFloat, and Kincardine, are primarily based on onshore or nearshore assembly followed by towing operations, rather than offshore installation in the traditional sense. The overall installation sequence associated with conventional floating wind deployment is illustrated in
Figure 1, highlighting the key stages from fabrication and assembly to towing, hook-up, and commissioning.
In these projects, the floating substructure is first constructed and prepared, after which the wind turbine generator (WTG) is assembled using onshore cranes or, where suitable sheltered-water conditions and supporting infrastructure are available, integrated in protected coastal areas before offshore deployment. For semi-submersible concepts such as WindFloat, turbine integration is typically completed at quayside or in protected areas before the fully assembled unit is towed to the offshore site using anchor handling vessels [
43]. Existing floating wind projects have also demonstrated both in situ and tow-to-port maintenance approaches depending on operational requirements, environmental conditions, and available infrastructure.
For spar-based concepts such as Hywind, the installation process involves additional steps, including upending the floating structure using ballasting operations in deep water. In Hywind Scotland, turbine integration was performed using a heavy-lift vessel offshore, whereas in Hywind Tampen, this operation was shifted to nearshore locations using a high-capacity onshore crane. Due to the significant draft of the spar substructure, a barge was installed at the quayside to provide sufficient water depth during turbine integration, as shown in
Figure 2. Furthermore, the required crane capacity is not widely available and introduces additional logistical challenges, including large-scale transportation, assembly, and pre-assembly operations involving hundreds of components. In both cases, however, the fully assembled turbine foundation system is subsequently towed to the offshore site, where final hook-up and commissioning are carried out.
Therefore, the defining characteristics of the conventional installation method are the prior assembly of the WTG, transportation of the complete unit by towing, and a limited offshore installation scope primarily restricted to hook-up and commissioning activities. Despite avoiding full offshore assembly, this method presents several challenges, including the requirement for suitable deep-water assembly locations, constraints on installation sequencing and scalability, dependence on long-distance towing operations, and limited availability of high-capacity towing vessels. These factors contribute to increased installation duration and logistical complexity, particularly for large-scale deployment scenarios.
2.2. Nordic Wind Installation Method
The Nordic Wind installation method introduces an alternative approach to floating wind turbine deployment by combining onshore turbine assembly with offshore float-over installation onto a pre-installed floating foundation. In this concept, the wind turbine generator (WTG) is fully assembled onshore, independently of the floating foundation fabrication and installation schedule. The complete turbine assembly is subsequently loaded onto a dedicated installation vessel equipped with motion-compensated gripper and transfer systems.
In contrast to conventional towing-based approaches, where the turbine and foundation are integrated prior to transportation, the floating foundation in the Nordic Wind method is installed offshore separately. The installation vessel then transports the fully assembled WTG to the offshore site, where installation is performed through a controlled float-over operation. This configuration removes the need for offshore heavy-lift crane operations during turbine installation. The installation sequence is illustrated in
Figure 3 and can be summarised as follows:
Onshore full assembly of the WTG;
Loadout of the WTG onto the installation vessel;
Transportation to the offshore site;
Positioning of the installation vessel relative to the floating foundation;
Connection using a motion-compensated gripper system;
Float-over transfer and mating of the WTG onto the spar foundation.
The main distinguishing characteristics of the Nordic Wind method can be summarised as follows:
Separation of turbine and foundation installation processes;
Offshore integration of a fully assembled WTG;
Use of a motion-compensated gripper system for controlled connection;
Elimination of offshore heavy-lift crane dependency during installation.
Overall, the Nordic Wind method represents an alternative installation configuration that shifts the integration phase offshore, under controlled motion conditions, while maintaining flexibility in the sequencing of construction and installation activities. At present, the Nordic Wind method remains a conceptual installation approach that has not yet been commercially demonstrated at full scale; accordingly, its performance is evaluated in this study using a simulation-based logistics framework. Several enabling technologies required for the proposed approach, including motion-compensated handling systems, dynamic positioning vessels, and offshore float-over operations, are already established within the offshore oil and gas sector; however, their integrated application to floating wind turbine installation remains at a pre-commercial stage.
3. Case Study and Simulation Framework
To evaluate the implications of the installation methodologies described in
Section 2, a case study-based simulation approach is adopted. The objective is to assess the performance of both conventional and Nordic Wind installation strategies under realistic project conditions, considering logistics, environmental constraints, and operational limitations. The analysis builds upon previous work addressing the dynamic behaviour of the Nordic Wind installation method and the definition of motion-based operational limits.
In the present study, these aspects are incorporated within a logistics simulation framework to enable the evaluation of installation duration, weather downtime, and operational sequencing across multiple project scenarios. The following subsections describe the case study definition, including site characteristics, environmental data, and vessel assumptions, as well as the simulation framework used to model installation activities.
3.1. Case Study Definition
The objective is to enable a consistent comparison between the conventional towing-based installation method and the Nordic Wind installation concept under equivalent logistical and environmental conditions. The case study considers a floating wind farm comprising multiple WTGs installed on spar-type floating foundations.
The selection of a spar-based configuration is motivated by its relevance to existing commercial-scale floating wind projects and its sensitivity to installation constraints related to draft, stability, and offshore operations.
The main project parameters, including turbine rating, number of units, water depth, and key logistical assumptions, are summarised in
Table 1. These parameters are selected to be representative of current commercial-scale floating wind developments and are applied consistently across all simulation scenarios.
3.2. Environmental Conditions
A set of geographical locations is considered to capture a range of environmental conditions relevant to floating offshore wind deployment. The selected locations, shown in
Figure 4, represent different wave climates and operational environments, allowing for the assessment of installation performance under varying metocean conditions. The environmental conditions are incorporated into the analysis through the use of hindcast metocean datasets representing the selected case study locations.
The metocean dataset consists of 35 years of hourly hindcast time series. For each case study location, environmental parameters are extracted at the nearest available offshore data point and include the variables required for the operability assessment, namely wind speed, significant wave height Hs, peak wave period Tp, wind speed Vw, and current, where applicable. The use of a multi-decadal hourly hindcast dataset provides a consistent basis for evaluating weather windows, weather downtime, and seasonal operability across all selected locations. These time series are used directly in the discrete-event simulation to determine whether the environmental conditions at each time step satisfy the operational limits defined for each installation activity.
Wave-heading effects are not recalculated explicitly at each time step within the logistics simulation. Instead, their influence is incorporated through the response-based operational limits adopted from the preceding dynamic analysis study. In that analysis, allowable installation conditions were derived by considering the response of the installation system under different wave headings and defining operability envelopes in terms of allowable Hs-Tp combinations for the critical installation phases. Therefore, the present simulation applies these Hs-Tp-based limits to determine activity feasibility and weather downtime, with the influence of wave heading already embedded in the adopted operational criteria.
Rather than relying on simplified environmental parameters, the analysis adopts a time-dependent approach in which installation activities are evaluated continuously against predefined operational limits. Weather downtime is therefore quantified based on periods during which environmental conditions exceed the allowable limits for specific installation operations. The environmental parameters are thus used to evaluate weather-dependent operability and quantify weather downtime during installation operations.
3.3. Marshalling Port Selection
In addition to environmental inputs, logistical parameters related to marshalling port selection are explicitly defined, as they represent a key factor influencing installation efficiency. Port selection is based on criteria including proximity to the wind farm, available water depth, quay capacity, and infrastructure suitability for assembly and loadout operations. These parameters directly affect transportation time, vessel utilisation, and installation sequencing.
To ensure a consistent and unbiased comparison between installation methodologies, the same marshalling port is assumed for both the conventional and Nordic Wind installation approaches in this study. This assumption allows the analysis to isolate the impact of installation methodology on logistics performance and weather downtime, without introducing additional variability associated with port selection.
For conventional installation methods, port selection is typically constrained by the requirement for deep-water access and heavy-lift capabilities to support the integration of the floating foundation and turbine. In contrast, the Nordic Wind installation method offers greater flexibility in port selection, as turbine assembly is decoupled from the floating foundation and can be performed independently of foundation availability. The distance between the selected port and the installation site is incorporated as a key input parameter in the simulation model. This distance directly influences transportation duration and contributes to the overall installation timeline.
The representative marshalling port-to-site transit distances adopted for each case study are reported in
Table 1 and are used to calculate transit durations for towing and installation vessel operations. For the conventional towing method, a loaded tow-out speed of 3 knots is adopted for the fully assembled floating turbine system, while a return transit speed of 10 knots is assumed for the towing vessel or AHTS when returning without tow. For the Nordic Wind method, a representative transit speed of 10 knots is adopted for the dedicated installation vessel for both loaded and return transits. These assumptions are applied consistently across all case studies to provide a transparent and comparable basis for estimating transit-related installation time.
3.4. Simulation Model
The installation process is modelled using a time-series-based discrete event simulation (DES) framework, in which the overall installation campaign is represented as a sequence of discrete time-dependent activities. This approach follows established practice for weather downtime and operability assessment, where installation operations are evaluated against time-varying environmental conditions derived from hindcast datasets.
The simulation is driven by met-ocean time series corresponding to the selected case study locations, with environmental conditions defined at discrete time intervals Δt. At each time step t, the feasibility of executing a given installation activity is evaluated by comparing the environmental conditions with pre-defined operational limits.
An activity is considered feasible when the environmental constraints are satisfied, which can be expressed as:
where
f(
t) is a binary feasibility function,
Ec(
t) represents the time-dependent environmental conditions, and
Elimit defines the operational limits for the considered activity.
The progress of installation activities is governed by this feasibility condition. When
f(
t) = 1, the activity proceeds and contributes to active operational time. When
f(
t) = 0, the activity is temporarily halted, and the corresponding time increment is recorded as weather downtime. The total weather downtime is therefore expressed as
while the active operational time is defined as
and the total installation duration is therefore given by
In the DES implementation, each installation methodology is represented as an ordered sequence of activities:
where each activity
ai is assigned a required execution duration
di and a set of limiting environmental criteria
Li. At each simulation time step
Δt, the environmental state vector
E(
t), including the relevant metocean parameters for the active activity, is compared with the corresponding operational limits
Li. The feasibility of activity a
i is therefore defined as:
where
indicates that the activity can proceed and
indicates that the activity is weather-restricted. The accumulated progress of each activity is updated as:
where
is the accumulated execution time of activity a
i. Once
≥
di, the activity is considered completed, and the simulation advances to the next activity in the predefined installation sequence. This procedure is repeated until all activities required for the installation campaign are completed.
The continuity classification assigned to each activity determines how weather interruptions are treated in the simulation. For interruptible activities, accumulated progress is retained when environmental limits are exceeded, and the activity resumes from the same progress state once suitable conditions return. For continuous activities, the specified duration represents the minimum uninterrupted weather window required for safe execution. If environmental limits are exceeded before the activity is completed, the activity is considered interrupted and must restart when a new suitable weather window becomes available. This distinction is applied to reflect the practical difference between operations that can be paused, such as port-side preparation or assembly activities, and marine operations that require continuous execution, such as towing, offshore hook-up, transit, or mating operations.
For each installation methodology, the process is defined as a sequence of events including loadout, transportation, positioning, connection and installation operations. The base duration for each activity is defined using representative engineering values derived from published offshore installation studies, reported marine operations practices and information from commercial-scale floating wind deployment. The effective execution time is determined by the availability of suitable weather conditions. In practice, these durations and limiting operational criteria can vary significantly depending on turbine rating, floater configuration, vessel capabilities, and site-specific environmental conditions, all of which influence offshore operability, handling complexity, and allowable weather limits. The full definition of activities, durations, and corresponding limiting environmental criteria adopted in this study is summarised in
Table 2. The installation sequence differs between the two methods considered. In the conventional towing-based method, the floating structure is assembled and towed from the marshalling port to the offshore site, followed by hook-up and commissioning operations. In contrast, the Nordic Wind method decouples turbine and foundation installation, where the floating foundation is installed separately, and the WTG is transported and installed offshore using a float-over operation.
Vessel configuration and fleet composition are defined for each installation method. The conventional method typically requires multiple tug vessels to perform towing operations, whereas the Nordic Wind method relies on a dedicated installation vessel equipped with a motion compensation system. Vessel speeds, operational capacities, and availability are assumed constant throughout the simulation.
The operational limits adopted in
Table 2 are based on motion-based criteria derived from the dynamic analysis presented in Hassan and Guedes Soares [
44], where allowable environmental conditions were established for key installation phases of floating spar wind turbine installation. These limits are applied consistently within the simulation framework to evaluate activity feasibility under time-varying environmental conditions.
To ensure consistent and unbiased comparison, identical environmental conditions, port location, and project configuration are applied to both installation methods. Consequently, differences in installation performance are attributed solely to the installation methodology and associated operational sequences. The simulation is repeated for all selected case study locations and scenarios. The resulting output includes total installation duration, weather downtime, vessel utilisation, and transportation time. These outputs form the basis for the costs assessment and comparative analysis presented in the following sections.
6. Conclusions
This study evaluates two installation methodologies for floating offshore wind turbines: the conventional towing-based approach and the Nordic Wind installation concept. A simulation-based logistics framework was developed to evaluate installation performance under realistic environmental conditions, explicitly accounting for weather downtime, operational constraints, and vessel utilisation. The analysis was applied across four case study projects (A to D), representing different scales and metocean environments.
The results demonstrate that installation performance is strongly governed by the interaction between environmental conditions, project scale, and installation methodology. Across all projects, both methods exhibit sensitivity to weather conditions, with installation duration increasing from favourable (P20) to more severe (P90) scenarios. This reflects the inherent dependence of offshore installation activities on metocean limits and available weather windows.
For Projects A–C, which represent mild to moderate environmental conditions and increasing project scale, the Nordic Wind method consistently achieves shorter installation durations compared to the conventional towing approach. This behaviour is primarily attributed to reduced offshore exposure and more efficient utilisation of favourable weather windows. As project scale increases, these advantages become more pronounced, highlighting the importance of installation efficiency for large-scale developments.
Project D represents a more challenging installation environment, characterised by long-period swell conditions that introduce additional constraints during critical offshore operations such as connection and mating. Under these conditions, both methods experience increased installation durations and greater variability. The Nordic Wind method shows higher sensitivity to these environmental constraints; however, it maintains shorter overall campaign durations across all scenarios, demonstrating that reduced offshore exposure remains a key advantage even in more demanding environments.
The cost assessment confirms that installation duration is the dominant driver of total installation cost. For Projects A to C, the Nordic Wind method consistently results in lower total installation costs due to reduced campaign durations.
In Project D, the cost difference between the two methods decreases under more severe weather scenarios, reflecting the increased sensitivity of offshore operations to environmental conditions. Nevertheless, the Nordic Wind method remains competitive across all evaluated scenarios. Overall, the results highlight a fundamental trade-off between operational efficiency and environmental sensitivity. The Nordic Wind method improves installation efficiency by reducing offshore exposure, while the conventional towing approach provides more stable operability across a wider range of conditions. The selection of the installation strategy should therefore consider both project characteristics and environmental conditions.
Future work should extend the present framework to include the full installation logistics chain and expand the cost assessment to account for full wind farm development elements, such as subsea cables and supporting infrastructure, which would enable a more comprehensive evaluation of project-level economics.