Next Article in Journal
Energy-Aware Integrated Scheduling for Quay Crane and IGV in Automated Container Terminal
Next Article in Special Issue
Transient Tests for Checking the Trieste Subsea Pipeline: Diving into Fault Detection
Previous Article in Journal
Optimizing Multi-Vessel Collision Avoidance Decision Making for Autonomous Surface Vessels: A COLREGs-Compliant Deep Reinforcement Learning Approach
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Transient Tests for Checking the Trieste Subsea Pipeline: Toward Field Tests

1
Department of Civil and Environmental Engineering, The University of Perugia, 06125 Perugia, Italy
2
AcegasApsAmga SpA, 35128 Padova, Italy
3
Umbria Regional Forestry Agency, 06036 Perugia, Italy
*
Author to whom correspondence should be addressed.
J. Mar. Sci. Eng. 2024, 12(3), 374; https://doi.org/10.3390/jmse12030374
Submission received: 8 January 2024 / Revised: 18 February 2024 / Accepted: 19 February 2024 / Published: 22 February 2024
(This article belongs to the Special Issue Underwater Pipe System Fault Detection)

Abstract

:
Subsea pipelines are vital arteries transporting oil, gas, and water over long distances and play a critical role in the global resource supply chain. However, they are the most vulnerable to damage from both human-made and natural causes and are characterized by inherent inaccessibility. As a result, routine inspection and monitoring technologies, both reliable and at the lowest possible cost, are needed to ensure their longevity. To fill this need, the use of transient-test-based techniques is proposed. In this first paper of a set of two companion papers, attention is focused on the selection of the appropriate maneuver that generates pressure waves and then on the planned steps—i.e., the sequence of actions—functional to the execution of the transient tests in the best flow conditions for effective fault detection. A brief review of the available fault detection technologies with their limitations is also offered. Finally, the performance of the proposed procedure is evaluated mainly in terms of the stability of the pressure regime prior to the execution of the transient test.

1. Introduction

Subsea pipelines (SPs) are vital arteries, transporting oil, gas, and water over long distances and playing a critical role in the global resource supply chain. However, they are the most vulnerable to damage from both human-made and natural causes [1,2,3]. Critical issues arise early during the manufacturing stage: in the case of metallic pipes, for example, welding is a complicated process. After the laying process, when bending stresses can cause fractures, SPs are subjected to the external hydrostatic pressure, which can crush the pipe, especially if it is not yet under pressure. Successively, the corrosive environment significantly reduces fatigue strength in dry air conditions [4,5]. Moreover, the low temperature of the seabed and the heat of the transported fluid exert opposing stresses on the pipe material: global contraction and local expansion, respectively. In addition, debris from the topside, ship anchors, and fishing gear—the latter especially in shallow water—can endanger the SPs. In the case of SPs, the problem of the inaccessibility of ground transmission mains is exacerbated. As a result, reliable routine inspection and monitoring technologies are needed to ensure a long service life [6]. Recently, to realize efficient remote control and monitoring, downtime prediction, and risk reduction, the digital twin has been discussed as a powerful technology [7].
Smart pigging, acoustic monitoring, remotely operated vehicles, and diving are the current cornerstones of SP inspection, all of which are characterized by high costs and some limitations [8]. In [9], a comprehensive review of in-pipe robots from different perspectives is provided. In particular, attention is focused on their ability in terms of self-localizing, mapping the pipelines, moving into them, and assessingth pipe conditions. Smart pigging uses intelligent devices called pressure inspection gauges (pigs) that travel through the pipeline, collecting data on wall thickness, corrosion, and other potential anomalies (e.g., [10]). This in-line inspection method is highly regarded for its accuracy and ability to provide comprehensive health assessments without disrupting pipeline operations (e.g., [11,12,13,14,15,16]). However, it can be limited by its reduced maneuverability and the types of anomalies that are not always detectable from inside the pipe, such as external wall deterioration. Acoustic monitoring is based on the propagation of sound waves through the pipeline material to detect leaks or structural weaknesses. The acoustic signatures are analyzed to determine the location and severity of any irregularities detected, allowing timely intervention. However, it can fail to pinpoint the exact location of a leak or distinguish between different types of acoustic signatures in noisy subsea environments (e.g., [17,18]). Remotely operated vehicles equipped with cameras and sensors provide versatile platforms for visual inspection and intervention in deep water environments, but their effectiveness is often hampered by underwater currents and visibility issues. Diving operations offer unique human judgement but are constrained by depth limitations, potential health risks to divers, underwater currents, and visibility issues. Figure 1 shows a typical example of the environment around an SP and the external condition of its outer surface; it gives an idea of the difficulty experienced by divers in investigating the condition of SPs.
The limitations of the above technologies, which affect their performance and applicability, as well as their high cost, underscore the need for continued innovation in SP diagnostics to provide a more comprehensive, cost-effective, and safer solution for the industry. It is clear that any new technology must first be demonstrated on a simple pipe in a controlled laboratory environment, possibly after preliminary numerical simulations, and then applied to real SPs. This is the case for transient-test-based techniques, (TTBTs) which, after numerical experiments, have been tested in the laboratory (e.g., [19,20,21,22,23,24,25,26,27]), and then refined in real pipe systems (e.g., [28,29,30,31,32]). These techniques require the generation of sharp but small-amplitude pressure waves. The basic concept of the TTBTs depends on the dynamics of transient phenomena in pressurized flows. In particular, the inserted pressure waves propagate along the pipeline and interact with any existing anomalies such as leaks, extended blockages, and wall deteriorations. This interaction results in a distinct feature in the pressure signal (the pressure time history): a leak reflects a negative pressure wave; a discrete blockage (e.g., a partially closed in-line valve) reflects a positive pressure wave; an extended partial blockage and wall deterioration give rise to “positive bell” and “negative bell” shape features, respectively (e.g., [20,21,24,33,34,35,36,37,38,39,40,41,42,43,44]). However, the application of these techniques to long SPs represents an uncharted area of research. The Trieste SP offers an ideal scenario to fill this gap. In fact, the effectiveness of TTBTs in pipeline fault detection can be compromised by the presence of branches and junctions, which attenuate pressure wave propagation—a critical component for the detection mechanism. The Trieste SP, which will be described in the following in more detail, characterized by a considerable length, large diameter, and the absence of branches, enables a more direct and uninterrupted propagation of pressure waves, making it an exemplary model for assessing the feasibility and reliability of TTBTs in similar large-scale applications.
To successfully implement TTBTs for the diagnosis of real SPs, it is essential to address two issues. The first involves selecting the most appropriate maneuver to generate pressure waves. The second issue involves establishing a preparatory procedure tailored to the investigated system and the operational constraints. This preparation phase must take into account the specific characteristics of the pipeline under investigation, its boundary conditions, and any restrictions imposed by the water company to minimiae service interruptions. Factors such as the layout of the system, the positioning of valves and sensors, and the operational conditions of the pipeline must be taken into account to generate meaningful diagnostic data. In addition, the correct application of TTBTs requires a precise setup to ensure that the transient phenomena can be accurately induced and measured. From this perspective, the transient test must be preceded by a stabilization phase to ensure that the system reaches a reliable steady state. This step is essential to prevent the superposition of “ad hoc” generated pressure waves on pre-existing pressure fluctuations, which could compromise the reliability of subsequent pressure signal analyses [45]. Establishing such baseline conditions is essential for accurately interpreting wave reflections and distinguishing between the transient response of a fault-free system and further pressure waves due to faults. In other words, as with many operations, the preparation phase greatly influences the successive analysis of the pressure signals and then the outcome of the fault detection procedure.
To illustrate in detail the results of the executed field tests and the crucial preparatory phase of the tailored approach followed, a set of two companion papers has been prepared. This first paper focuses on the operations performed before the transient tests, while the second presents and discusses the results of the fault detection procedure. Accordingly, in this paper, a brief overview of the SP investigated is given first. Then, the choice of the maneuver type is explained, and the experimental procedure breakdown is described, indicating all of its steps. Finally, some considerations about the preparatory phase are offered from the management point of view.

2. Materials and Methods

In the first subsection, the characteristics of the Trieste SP are presented; in the second subsection, the preliminary survey is described; in the third subsection, the hydraulic characterization of the device used for generating the pressure waves is provided; finally, in the fourth subsection, the field procedure breakdown—i.e., all the maneuvers to be carried out—is described.

2.1. An Overview of the Trieste Water Supply System

Trieste, a city on the border between Italy and Slovenia, draws its water from 13 wells in San Pier D’Isonzo (Figure 2). Once extracted from the deep karst strata, the water is conveyed through a main pipeline to the Randaccio pumping station—the heart of Trieste’s water supply system—where it also undergoes treatment processes.
From the Randaccio pumping station, the treated water is conveyed to the city of Trieste via a dual-pipe system managed by AcegasApsAmga SpA (Hera Group). This dual system ensures a continuous water supply and provides a backup in the event of a problem with one of the pipelines. In particular, there is a 900 mm diameter steel pipeline, almost a century old, that runs under the coastal road to Trieste. The Sistiana piezometric tower along this pipeline ensures constant pressure, facilitating efficient water delivery. Two needle valves have recently been installed on this pipeline to optimize the water supply system through automatic pressure adjustment. Successively, in response to the increased water demand in Trieste, an SP was built in 1970, designed by G. Pistilli, one of the most talented Italian SP designers of the second half of the twentieth century (Figure 3). It was constructed of layered steel, bituminous cast, and concrete, reinforced with two electro-welded meshes; the internal diameter, D, is equal to 1297 mm. The SP operates at about 7–8 bar pressure under typical functioning conditions. The overland section of the SP extends a total of 680 m, connecting the Randaccio pumping station to the Petrinia piezometric tower. In addition, the pipeline extends for a further 1687 m, connecting the Petrinia piezometric tower to the VP in-line valve near the quarry in Villaggio del Pescatore, a very small settlement. In the immediate vicinity of Villaggio del Pescatore, several connections are active: (i) a branch to the Villaggio del Pescatore District Metered Area (DMA) via a DN100 iron pipe, (ii) a DN100 HDPE service line supplying a hotel, and (iii) two DN350 and DN150 iron pipe branches. Downstream of VP, the pipeline submerges for 17,935 m and connects VP to the in-line valve VM at Molo 0 of Porto Franco Vecchio. Just upstream of the VM, the device used for generating the transients is installed, as discussed in the third subsection. The pipeline emerges briefly before joining the existing supply lines near Viale Miramare.

2.2. A Preliminary First Survey Evaluating the System Response to Maneuvers

The initial phase of the field procedure involves executing a preliminary survey to evaluate the system’s response to maneuvers performed, for example, by existing devices, such as valves and pumps, in exploratory tests. Despite the potentially time-intensive nature of this preliminary phase, it is fundamentally crucial for two main reasons: it allows the exploration of the possibility of executing reliable transient tests with the existing devices, and it facilitates the comprehension of the system’s transient response, enabling the design of optimally tailored tests. As demonstrated in previous research [46], certain transients have been identified as unsuitable for fault detection due to the nature of the resulting pressure waves. Specifically, two maneuvers were conducted using existing infrastructure: pump switching off and closure of the VM valve. The pump switching off led to a gradual decrease in pressure. The effectiveness of these transients for fault detection was compromised by several factors. Firstly, the location of the Petrinia piezometric tower, positioned between the point of pressure wave insertion and the system, acted as a filter. The mass of water in the tower introduced significant inertia, affecting the transmission of pressure waves. Secondly, the slow nature of the pump deactivation, due to its inertia, resulted in pressure waves that were too gradual for effective fault detection. Additionally, the VM valve’s large diameter prevented rapid closure. Despite an initial partial closure to reduce flow, the final manual closure of the valve was too slow to produce detectable reflected pressure waves in the signal, rendering the transient ineffective for identifying faults.
Even if alternative methods for generating pressure waves must be sought, this phase is pivotal in allowing the real-time observation of the system’s response to transients, surpassing the predictive capabilities of numerical modeling. It is important to note that relying solely on numerical modeling for analyzing transient responses may be inadequate due to the complexity of modeling certain factors accurately, such as unsteady friction and particularly the authentic behavior of boundary conditions. The latter factor is critical for understanding the transient response and is difficult to predict without empirical evidence. Therefore, such a preliminary survey is instrumental in monitoring and understanding the behavior of these complex factors. Accordingly, a second survey, as discussed below, was designed.

2.3. Hydraulic Characterization of the Maneuver Valve

In order to insert small, sharp pressure wave into the system (a prerequisite for the safe and successful implementation of TTBTs for anomaly detection), a special device must be used, as discussed in the previous subsection. For this, among the proposed devices, the portable pressure wave maker (PPWM) [45] and a small-diameter side discharge valve (SDV), which have been extensively tested in real pipe systems, are suitable. For the sake of brevity, an SDV with a nominal diameter of DN32 was installed immediately upstream of the VM valve. A first action in the second survey design was the hydraulic characterization of such a valve. Specifically, steady-state tests were carried out at the Water Engineering Laboratory (WEL) of the University of Perugia, Italy (Figure 4a). Specifically, the valve was equipped with a protractor, used to measure the opening degree, and a pressure transducer was installed immediately upstream of the SDV to measure the head loss across it (MATLAB R2022b codes were used to process the acquired data and generate plots.). In fact, as the valve discharges into the atmosphere, the measure of the upstream pressure directly allows the determination of the local head loss.
Tests have been executed by varying the opening degree and then the discharge, so that the SDV flow-rate curve was obtained using the orifice (Torricelli’s) equation:
A E ( δ ) = Q 2 g ζ ( δ )
in which A E (m2) is the valve effective area, Q (m3/s) is the discharge; δ is the relative opening degree (with δ = 1 (0) if the SDV is fully open (closed)), ζ (m) is the local head loss across the valve, and g is the acceleration due to gravity (9.806 m/s2). Experimental data are shown in Figure 4b, and, given their trend, the following fitting function was obtained:
A E ( δ ) = 4.15 10 6 e 5.532 δ
Equations (1) and (2) are essential for evaluating the pressure wave generated by maneuvering the SDV. Precisely, by assuming frictionless transients and an instantaneous total closure maneuver, the inserted pressure wave, Δ H , can be evaluated through the Allievi–Joukowski formula, combined with the previously mentioned orifice equation [47]:
Δ H = a A E ( δ ) 2 g ( H M , 0 z M ) g A
where H is the piezometric head, a is the pressure wave speed (m/s), z is the elevation, and the subscripts M and 0 indicate the measurement section and steady-state conditions preceding the transient event, respectively.
To accurately characterize the behavior of the SDV in unsteady-state conditions, transient tests were conducted by quickly closing the SDV. Figure 5 shows the dimensionless pressure signal, h = ( H H M , 0 ) / ( Δ H ) , acquired immediately upstream of the SDV, during a transient test. From such a pressure signal, the maneuver duration, τ S D V , is assumed as the time interval between the instant when the pressure signal deviates from steady-state conditions (i.e., the transient starts) and the instant when the overpressure is fully accomplished. Specifically, it is equal to about 0.03 s, indicating that the maneuver is fast. It is worth noting that the SDV’s relative opening degree in such a test was equal to about 0.22. Values larger than this were not tested to avoid the generation of large overpressures in the laboratory setup. Instead, in the field tests, larger values of δ , and then of τ S D V , are expected, since the SDV is to be connected to a large-diameter pipe and then not-too-large overpressures are a concern. Nevertheless, the small value of τ S D V obtained in the laboratory transient test in Figure 5 ensures that the maneuver performed with this valve in the SP will be sufficiently fast.
For the Trieste SP, consistent with the water supply monitoring, the value of H M , 0 can be set at 70 m. Accordingly, in Figure 6, the values of Δ H for different δ and a values are reported. The selection of the a values, ranging from 900 to 1300 m/s, is based on the mechanical and geometrical characteristics of the SP.
Figure 6 confirms that Δ H does not exceed 3.73 m, which is well within the maximum overpressure threshold of the examined SP. Accordingly, the transients generated for fault detection by closing the SDV are safe for the SP.

2.4. Field Procedure Breakdown

To diagnose the considered SP as part of an articulated pipe system, a sophisticated procedure is implemented for the effective use of TTBTs. Pressure signals, H, are acquired by piezoresistive transducers (Figure 7c). These transducers operate at a frequency of 1000 Hz and are located at two measurement sections: section P, immediately downstream of the VP valve (Figure 7a), and section M (Figure 7b), immediately upstream of the VM valve. Importantly, within the TTBTs, there is no need to measure the discharge during the tests. The selected measurement sections are close to the submerged part of the SP and are easily accessible. It should be noted that there are no accessible sections in the approximately 18 km submerged section of the SP. Furthermore, the water utility company carries out daily operations of turning on and off pumps at the Randaccio pumping station in response to water demand. In particular, these operations are not considered dangerous for the SP due to the presence of two piezometric towers that mitigate the water hammer effects. Accordingly, the planned operations are as follows:
0.
At t 0 : initiate pressure monitoring at sections P and M;
1.
At t 1 : pump 8 switching off at the Randaccio pumping station;
2.
At t 2 : pump 9 switching off at the Randaccio pumping station;
3.
At t 3 : closure of the VM, with a maneuver duration, τ V M ;
4.
At t 4 : opening of the SDV;
5.
At t 5 : closure of the SDV (the transient test), with a maneuver duration, τ S D V ;
6.
At t 6 : opening of the VM;
7.
At t 7 : pump 9 switching on at the Randaccio pumping station;
8.
At t 8 : pump 8 switching on at the Randaccio pumping station;
9.
At t 9 : end of the pressure monitoring and field procedure.
The actions in steps #1 and #2 are essential to reduce both pressure and discharge, thereby increasing the safety of subsequent transients. It is important to emphasize that the water needs, including the potential leakage and demand of the Villaggio del Pescatore DMA, are provided by the Petrinia piezometric tower. For the same reasons, it was decided not to close the VP valve. In addition, steps #1 and #2 were carried out independently to avoid unnecessary and excessive excitation of the SP.
Closing the VM (step #3) is an infrequent practice for the Trieste water company’s technicians, usually reserved for addressing maintenance issues (e.g., repairing leaks). For example, in the last eight years, this valve has only been operated once to repair a leak between the VM and the city of Trieste. Throughout this procedure, the maneuver was performed manually, with great care and a large value of the closure duration, τ V M (≃18 min), ensuring minimal pressure variations to prioritize the safety of the SP.
In step #4, the SDV is opened gradually until the desired opening degree is achieved. Once steady-state conditions are established, it is quickly ( τ S D V ≃ 0.3 s) and fully closed in step #5. As discussed in detail in the companion paper [48], this maneuver ensures the generation of a small and then absolutely safe pressure wave.
Steps #6 to #9 are critical to returning the SP to its original operating conditions prior to the start of the survey. Specifically, in step #6, the VM valve is slowly reopened, re-establishing the original connection to the Trieste distribution system without placing undue stress on the infrastructure. During steps #7 and #8, the two pumps at the Randaccio pumping station are activated to smoothly return the SP to its normal operating state.
Pressure monitoring is then completed (step #9), confirming that the SP has returned to its pretest operating condition.

3. Transient Response of the Subsea Pipeline (SP) to the Field Procedure (Second Survey)

In this section, the Trieste SP response to transients generated during the second survey is described, and some remarks on the field test procedure are highlighted.

3.1. Transient Response of Maneuvers Indicated in Section 2.4

In Figure 8, the pressure signals recorded at sections P and M are presented. The figure highlights the mentioned instances of time when the operational steps were implemented. To enhance clarity, these instances are also listed in Table 1. Specifically, the acquisition started at t 0 = 0. Step #1, occurring at t 1 = 702 s, which caused a pressure drop in section P, which was then observed in section M. Step #2, occurring at t 2 = 1704 s, triggered a pressure increase in both sections, which was then followed by a gradual decrease. Step #3 was initiated at t 3 = 3130 s, when the effects of step #2 had not fully dissipated. This strategic timing was chosen to address the shift in the flow direction, aiming to counteract and mitigate the consequences of this change effectively.
Just because of this flow direction change, the VM closure in step #3 resulted in a pressure drop in section M, accompanied by a prolonged period of oscillations, which finally dampened after about 40 min due to the local flow reversal. Step #3 had a less pronounced effect on section P, with its pressure damping out more quickly.
The scheduling of successive timings adhered to a specific guideline. Precisely, for the considered transient, the attenuation of pressure peaks had to be managed to ensure they were reduced to less than 4% of the initial pressure variation [49]. This approach guarantees that the effects of the previous transient have adequately dissipated, thereby preventing the overlap of distinct transient phenomena and their associated impacts. To elucidate this strategy and visually support the decision-making process for proceeding with the next phase of the operation, Figure 9a presents a detailed view of the pressure signal acquired at section M, as shown in Figure 8, during the closure of the VM, considered as an example. The peaks of this pressure signal, H p e a k s , is evaluated and then normalized with respect to the maximum difference observed between any two successive peaks, m a x Δ H p e a k s :
Δ h p e a k s = | H p e a k s m a x ( Δ H p e a k s ) |
The time history of the resulting dimensionless peak variation is illustrated in Figure 9b. In this figure, a threshold is set where, if Δ h p e a k s falls below 4%—indicated by a red dashed line—it signals the readiness for initiating the subsequent step.
At t 4 =10,021 s, step #4 was executed, producing effects similar to those of step #3 in both measurement sections. This is because the maneuver in step #4 was an SDV opening with almost hydro-static conditions as a pre-transient regime. Specifically, in section M, this SDV opening caused a maximum pressure variation of about 0.94 m, whereas in section P, the variation was only about 0.52 m.
During step #5, performed at t 5 = 13,360 s, which, as mentioned above, is relevant within TTBTs, a small initial pressure rise of 0.58 m in section M and 0.40 m in section P was observed, followed by the damping of pressure oscillations.
At step #6 ( t 6 = 16,189 s), the VM was gradually reopened, resulting in a pressure increase throughout the pipeline. Similarly, in steps #7 and #8, corresponding to t 7 = 17,313 s and t 8 = 17,931 s, respectively, the two pumps at the Randaccio pumping station were switched on, both maneuvers resulting in a pressure increase.
As the pressure in both sections M and P returned to values comparable to those at t 0 , the acquisition was terminated at step #9 ( t 9 = 18,996 s).

3.2. Effect of Not Ideal Timing

To verify the establishment of “quasi” steady-state conditions, the pressure signal acquired at section M 180 s prior to t 5 is depicted in Figure 10a. This visualization is pivotal in demonstrating the achievement of a pressure peak variation of less than the critical threshold of 4% of the maximum variation. In fact, the corresponding frequency response function shown in Figure 10b (blue line) clearly indicates the absence of significant pressure fluctuations. On the contrary, if a time sequence and maneuvers other than the scheduled ones are performed, the quality of the pre-transient conditions is much worse. For example, the closure of the VP after step t 3 leads to much worse pre-transient conditions in the first survey. In fact, these are characterized by more pronounced pressure fluctuations (red line in Figure 10) in the frequency spectrum. In particular, there is a notable peak at a frequency ω = 0.0167, which corresponds to the natural period of the system, given a pressure wave speed of about 1100 m/s, a typical value for metallic pipes. In other words, isolating the SP before performing the transient tests does not improve the quality of the pre-transient pressure regime. The results of the two different pre-transient procedures, summarized in Figure 10, clearly show that the determination of the precise timing of the operational steps, as well as the sequence and type of maneuvers, are crucial, as they allow the avoidance of the potential amplification of the pressure oscillations. In other words, the choice of inappropriate intervals and/or maneuvers could result in the amplification–or failure to damp–of pressure waves. This means that the pre-transient conditions in the first survey are far from the desired steady state.

4. Conclusions

This paper, the first of a series of two companion papers, addresses challenges associated with inspecting subsea pipelines (SPs), with a specific focus on the Trieste SP managed by AcegasApsAmga SpA. Such infrastructure plays a key role in the water supply of the important city of Trieste, located on the Italy–Slovenia border. Special attention is given to the use of transient-test-based techniques (TTBTs) for fault detection. The application of this technology to SPs represents an uncharted area of research. The Trieste SP offers an ideal scenario to fill this gap. Characterized by a considerable length (about 18 km), a large diameter (≃1.3 m), and notably, the absence of branches, it enables a more direct and uninterrupted propagation of pressure waves, making it an exemplary model for assessing the feasibility and reliability of TTBTs in similar large-scale applications. Given the novel application of TTBTs, a detailed exposition of the test background and procedural design—with all the actions considered in the preparation phase prior to the transient tests—was provided. In this respect, the choice of the maneuver generating the pressure waves and tests for the hydraulic characterization of the maneuver valve were discussed first. Subsequently, the steps—i.e., the sequence of actions—for carrying out the field tests were proposed. The performance of the sequence was evaluated in terms of the steadiness of the flow conditions preceding the maneuver that generates the transient. Specifically, a specific guideline was established for the scheduling of successive steps through pressure signal monitoring. Precisely, for the considered transient, when the pressure peaks reduce to less than 4% of the initial pressure variation, the successive step can be carried out. For the considered transient, this method ensures the almost complete dissipation of the effects from any preceding transient, effectively eliminating the possibility of overlapping transient phenomena and their resultant impacts. This methodology not only applies to the current study but also offers a framework that could be adapted for other configurations and field-testing scenarios. In addition, the planned steps ensure that the TTBTs are viable within the operational realities of SP management. The companion paper [48] describes the results of the fault detection procedure in detail.

Author Contributions

Conceptualization, S.M., C.C., B.B., L.T. and A.R.; methodology, S.M., C.C., B.B., L.T. and A.R.; software, S.M., C.C. and B.B.; validation, S.M., C.C., B.B., L.T., A.R. and M.C.; formal analysis, S.M., C.C., B.B., L.T., A.R. and M.C.; investigation, S.M., C.C., B.B., L.T., A.R. and M.C.; resources, S.M., C.C. and B.B.; data curation, S.M., C.C., B.B., L.T., A.R. and M.C.; writing—original draft preparation, S.M., C.C. and B.B.; writing—review and editing, S.M., C.C., B.B., L.T., A.R. and M.C.; project administration, S.M., C.C. and B.B.; funding acquisition, S.M., C.C. and B.B. All authors have read and agreed to the published version of the manuscript.

Funding

This research was funded by the University of Perugia Fondo di ricerca di Ateneo-edizioni 2021 e 2022 and the Ministry of University and Research (MUR) under the Project of Relevant Interest PRIN2022-“Hybrid Transient-machine learning approach for ANomaly DEtection and classification in water transmission Mains (TANDEM)” (CUP: J53D23002110006).

Data Availability Statement

Experimental pressure signals are available upon request.

Acknowledgments

This research was carried out within a joint project between the Department of Civil and Environmental Engineering (DICA) of the University of Perugia and AcegasApsAmga SpA, Padova, Italy. The assistance of Filomena Maietta, C. Del Principe of DICA, and the technicians of AcegasApsAmga SpA during the field activity is highly appreciated.

Conflicts of Interest

Lorenzo Tirello and Andrea Rubin were employed by AcegasApsAmga SpA. The remaining authors declare that the research was conducted in the absence of any commercial or financial relationships that could be construed as a potential conflict of interest.

References

  1. Kawsar, M.R.; Youssef, S.A.; Faisal, M.; Kumar, A.; Seo, J.K.; Paik, J.K. Assessment of dropped object risk on corroded subsea pipeline. Ocean. Eng. 2015, 106, 329–340. [Google Scholar] [CrossRef]
  2. Ho, M.; El-Borgh, S.; Patil, D.; Song, G. Inspection and monitoring systems subsea pipelines: A review paper. Struct. Health Monit. 2020, 19, 606–645. [Google Scholar] [CrossRef]
  3. Reda, A.; Amaechi, C.V.; Diaz Jimenez, L.F.; Sultan, I.A.; Rawlinson, A. Guideline for the Decommissioning/Abandonment of Subsea Pipelines. J. Mar. Sci. Eng. 2023, 12, 8. [Google Scholar] [CrossRef]
  4. Guo, Y.; Shao, Y.; Gao, X.; Li, T.; Zhong, Y.; Luo, X. Corrosion fatigue crack growth of serviced API 5L X56 submarine pipeline. Ocean. Eng. 2022, 256, 111502. [Google Scholar] [CrossRef]
  5. Kakaie, A.; Guedes Soares, C.; Ariffin, A.K.; Punurai, W. Fatigue reliability analysis of submarine pipelines using the Bayesian approach. J. Mar. Sci. Eng. 2023, 11, 580. [Google Scholar] [CrossRef]
  6. Reda, A.; Shahin, M.A.; Sultan, I.A.; Amaechi, C.V.; McKee, K.K. Necessity and suitability of in-line inspection for corrosion resistant alloy (CRA) clad pipelines. Ships Offshore Struct. 2023, 18, 1360–1366. [Google Scholar] [CrossRef]
  7. Chen, B.Q.; Videiro, P.M.; Soares, C.G. Opportunities and challenges to develop digital twins for subsea pipelines. J. Mar. Sci. Eng. 2022, 10, 739. [Google Scholar] [CrossRef]
  8. Amaechi, C.V.; Hosie, G.; Reda, A. Review on subsea pipeline integrity management: An operator’s perspective. Energies 2022, 16, 98. [Google Scholar] [CrossRef]
  9. Kazeminasab, S.; Sadeghi, N.; Janfaza, V.; Razavi, M.; Ziyadidegan, S.; Banks, M.K. Localization, mapping, navigation, and inspection methods in in-pipe robots: A review. IEEE Access 2021, 9, 162035–162058. [Google Scholar] [CrossRef]
  10. Chen, H.; Zhang, X.; Li, J. Ultra low frequency electromagnetic wave localization and application to pipeline robot. In Proceedings of the 2006 IEEE/RSJ International Conference on Intelligent Robots and Systems, Beijing, China, 9–15 October 2006; pp. 1201–1205. [Google Scholar]
  11. Davidson, R. An Introduction to Pipeline Pigging; Gulf Publishing: Houston, TX, USA, 2002; p. 92. [Google Scholar]
  12. Wang, Z.; Cao, Q.; Luan, N.; L Zhang, L. Damping in transient pressurised flow. Ind. Robot. 2010, 145, 04019034. [Google Scholar]
  13. Brockhaus, S.; Ginten, M.; Klein, S.; Teckert, M.; Stawicki, O.; Oevermann, D.; Meyer, S.; Storey, D. In-line inspection (ILI) methods for detecting corrosion in underground pipelines. In Underground Pipeline Corrosion; Elsevier: Amsterdam, The Netherlands, 2014; pp. 255–285. [Google Scholar]
  14. Ma, Q.; Tian, G.; Zeng, Y.; Li, R.; Song, H.; Wang, Z.; Gao, B.; Zeng, K. Pipeline in-line inspection method, instrumentation and data management. Sensors 2021, 21, 3862. [Google Scholar] [CrossRef]
  15. Dobmann, G.; Barbian, O.; Willems, H. State of the art of in-line nondestructive weld inspection of pipelines by ultrasonics. Russ. J. Nondestruct. Test. 2007, 43, 755–761. [Google Scholar] [CrossRef]
  16. Parlak, B.O.; Yavasoglu, H.A. A comprehensive analysis of in-line inspection tools and technologies for steel oil and gas pipelines. Sustainability 2023, 15, 2783. [Google Scholar] [CrossRef]
  17. Cawley, P.; Lowe, M.; Alleyne, D.; Pavlakovic, B.; Wilcox, P. Practical long range guided wave testing: Applications to pipes and rail. Mater. Eval. 2003, 61, 66–74. [Google Scholar]
  18. Gazis, D.C. Three-dimensional investigation of the propagation of waves in hollow circular cylinders. 1. Analytical foundation. J. Acoust. Soc. Am. 1959, 31, 568573. [Google Scholar] [CrossRef]
  19. Brunone, B. A transient test-based technique for leak detection in outfall pipes. J. Water Resour. Plan. Manag. 1999, 125, 302–306. [Google Scholar] [CrossRef]
  20. Wang, X.; Waqar, M.; Yan, H.; Louati, M.; Ghidaoui, M.S.; Lee, P.J.; Meniconi, S.; Brunone, B.; Karney, B. Pipeline leak localization using matched-field processing incorporating prior information of modeling error. Mech. Syst. Signal Process. 2020, 143, 106849. [Google Scholar] [CrossRef]
  21. Liou, C. Pipeline leak detection by impulse response extraction. J. Fluids Eng. 1998, 120, 833–838. [Google Scholar] [CrossRef]
  22. Alexander, J.; Lee, P.; Davidson, M.; Li, Z.; Murch, R.; Duan, H.; Meniconi, S.; Brunone, B. Experimental investigation of the interaction of fluid transients with an in-line air pocket. J. Hydraul. Eng. 2020, 146, 04019067. [Google Scholar] [CrossRef]
  23. Mohapatra, P.; Chaudhry, M.; Kassem, A.; Moloo, J. Detection of partial blockage in single pipelines. J. Hydraul. Eng. 2006, 132, 200–206. [Google Scholar] [CrossRef]
  24. Taghvaei, M.; Beck, S.B.M.; Boxall, J.B. Leak detection in pipes using induced water hammer pulses and cepstrum analysis. Int. J. Comadem 2010, 13, 19–25. [Google Scholar]
  25. Bohorquez, J.; Lambert, M.F.; Alexander, B.; Simpson, A.R.; Abbott, D. Stochastic resonance enhancement for leak detection in pipelines using fluid transients and convolutional neural networks. J. Water Resour. Plan. Manag. 2022, 148, 04022001. [Google Scholar] [CrossRef]
  26. Zhang, C.; Lambert, M.F.; Gong, J.; Zecchin, A.C.; Simpson, A.R.; Stephens, M.L. Bayesian inverse transient analysis for pipeline condition assessment: Parameter estimation and uncertainty quantification. Water Resour. Manag. 2020, 34, 2807–2820. [Google Scholar] [CrossRef]
  27. Zeng, W.; Zecchin, A.C.; Cazzolato, B.S.; Simpson, A.R.; Gong, J.; Lambert, M.F. Extremely sensitive anomaly detection in pipe networks using a higher-order paired-impulse response function with a correlator. J. Water Resour. Plan. Manag. 2021, 147, 04021068. [Google Scholar] [CrossRef]
  28. Meniconi, S.; Brunone, B.; Frisinghelli, M. On the role of minor branches, energy dissipation, and small defects in the transient response of transmission mains. Water 2018, 10, 187. [Google Scholar] [CrossRef]
  29. Meniconi, S.; Capponi, C.; Frisinghelli, M.; Brunone, B. Leak detection in a real transmission main through transient tests: Deeds and misdeeds. Water Resour. Res. 2021, 57, e2020WR027838. [Google Scholar] [CrossRef]
  30. Gong, J.; Stephens, M.L.; Lambert, M.F.; Zecchin, A.C.; Simpson, A.R. Pressure surge suppression using a metallic-plastic-metallic pipe configuration. J. Hydraul. Eng. 2018, 144, 04018025. [Google Scholar] [CrossRef]
  31. Stephens, M.L.; Lambert, M.F.; Simpson, A.R.; Vitkovsky, J. Calibrating the water-hammer response of a field pipe network by using a mechanical damping model. J. Hydraul. Eng. 2011, 137, 1225–1237. [Google Scholar] [CrossRef]
  32. Gong, J.; Lambert, M.; Zecchin, A.; Simpson, A.; Arbon, N.; Kim, Y.i. Field study on non-invasive and non-destructive condition assessment for asbestos cement pipelines by time-domain fluid transient analysis. Struct. Health Monit. 2016, 15, 113–124. [Google Scholar] [CrossRef]
  33. Covas, D.; Ramos, H. Case studies of leak detection and location in water pipe systems by inverse transient analysis. J. Water Resour. Plan. Manag. 2010, 136, 248–257. [Google Scholar] [CrossRef]
  34. Shucksmith, J.D.; Boxall, J.B.; Staszewski, W.J.; Seth, A.; Beck, S.B.M. Onsite leak location in a pipe network by cepstrum analysis of pressure transients. J. Am. Water Work. Assoc. 2012, 104, E457–E465. [Google Scholar] [CrossRef]
  35. Ghazali, M.; Staszewski, W.; Shucksmith, J.; Boxall, J.; Beck, S. Instantaneous phase and frequency for the detection of leaks and features in a pipeline system. Struct. Health Monit. 2011, 10, 351–360. [Google Scholar] [CrossRef]
  36. Sun, J.; Wang, R.; Duan, H.F. Multiple-fault detection in water pipelines using transient-based time-frequency analysis. J. Hydroinformatics 2016, 18, 975–989. [Google Scholar] [CrossRef]
  37. Xu, X.; Karney, B. An overview of transient fault detection techniques. In Modeling and Monitoring of Pipelines and Networks; Springer: Berlin/Heidelberg, Germany, 2017; pp. 13–37. [Google Scholar]
  38. Wang, X.J.; Lambert, M.F.; Simpson, A.R. Detection and location of a partial blockage in a pipeline using damping of fluid transients. J. Water Resour. Plan. Manag. 2005, 131, 244–249. [Google Scholar] [CrossRef]
  39. Mpesha, W.; Gassman, S.L.; Chaudhry, M.H. Leak detection in pipes by frequency response method. J. Hydraul. Eng. 2001, 127, 134–147. [Google Scholar] [CrossRef]
  40. Lee, P.J.; Vítkovskỳ, J.P.; Lambert, M.F.; Simpson, A.R.; Liggett, J.A. Frequency domain analysis for detecting pipeline leaks. J. Hydraul. Eng. 2005, 131, 596–604. [Google Scholar] [CrossRef]
  41. Sattar, A.M.; Chaudhry, M.H.; Kassem, A.A. Partial blockage detection in pipelines by frequency response method. J. Hydraul. Eng. 2008, 134, 76–89. [Google Scholar] [CrossRef]
  42. Duan, H.F.; Lee, P.J.; Kashima, A.; Lu, J.; Ghidaoui, M.S.; Tung, Y.K. Extended blockage detection in pipes using the system frequency response: Analytical analysis and experimental verification. J. Hydraul. Eng. 2013, 139, 763–771. [Google Scholar] [CrossRef]
  43. Gong, J.; Simpson, A.; Lambert, M.F.; Zecchin, A.C.; Kim, Y.I.; Tijsseling, A.A. Detection of distributed deterioration in single pipes using transient reflections. J. Pipeline Syst. Eng. Pract. 2013, 4, 32–40. [Google Scholar] [CrossRef]
  44. Che, T.C.; Duan, H.F.; Lee, P.J. Transient wave-based methods for anomaly detection in fluid pipes: A review. Mech. Syst. Signal Process. 2021, 160, 107874. [Google Scholar] [CrossRef]
  45. Brunone, B.; Capponi, C.; Meniconi, S. Design criteria and performance analysis of a smart portable device for leak detection in water transmission mains. Measurement 2021, 183, 109844. [Google Scholar] [CrossRef]
  46. Meniconi, S.; Rubin, A.; Tirello, L.; Capponi, C.; Cifrodelli, M.; Lucato, P.; Brunone, B. Checking procedure of the Trieste (Italy) subsea pipeline by transient tests. Preliminary results. Proceedings 2020, 48, 2. [Google Scholar]
  47. Wylie, E.; Streeter, V. Fluid Transients in Systems; Prentice-Hall Inc.: Upper Saddle River, NJ, USA, 1993; p. 463. [Google Scholar]
  48. Meniconi, S.; Brunone, B.; Tirello, L.; Rubin, A.; Cifrodelli, M.; Capponi, C. Transient Tests for Checking the Trieste Subsea Pipeline: Diving into Fault Detection. J. Mar. Sci. Eng. 2024, 12, 391. [Google Scholar] [CrossRef]
  49. Agarwal, A.; Lang, J. Foundations of Analog and Digital Electronic Circuits; Elsevier: Amsterdam, The Netherlands, 2005. [Google Scholar]
Figure 1. Typical example of the environment around a subsea pipeline (SP) and the condition of its outer surface (the SP is illuminated by the divers’ powerful torches).
Figure 1. Typical example of the environment around a subsea pipeline (SP) and the condition of its outer surface (the SP is illuminated by the divers’ powerful torches).
Jmse 12 00374 g001
Figure 2. The Trieste water supply system managed by AcegasApsAmga SpA (Hera Group).
Figure 2. The Trieste water supply system managed by AcegasApsAmga SpA (Hera Group).
Jmse 12 00374 g002
Figure 3. Sketch of the Trieste subsea pipeline (SP).
Figure 3. Sketch of the Trieste subsea pipeline (SP).
Jmse 12 00374 g003
Figure 4. Hydraulic characterization of the side discharge valve (SDV): (a) the experimental set-up at the Water Engineering Laboratory (WEL) of the University of Perugia, Italy, and (b) the SDV flow-rate curve.
Figure 4. Hydraulic characterization of the side discharge valve (SDV): (a) the experimental set-up at the Water Engineering Laboratory (WEL) of the University of Perugia, Italy, and (b) the SDV flow-rate curve.
Jmse 12 00374 g004
Figure 5. Transient test carried out at the Water Engineering Laboratory. The time-history of the dimensionless pressure signal, h, is shown, highlighting the evaluation of the maneuver duration, τ S D V , which is about 0.03 s.
Figure 5. Transient test carried out at the Water Engineering Laboratory. The time-history of the dimensionless pressure signal, h, is shown, highlighting the evaluation of the maneuver duration, τ S D V , which is about 0.03 s.
Jmse 12 00374 g005
Figure 6. Inserted pressure wave, Δ H , vs. SDV relative opening degree, δ , and pressure wave speed, a.
Figure 6. Inserted pressure wave, Δ H , vs. SDV relative opening degree, δ , and pressure wave speed, a.
Jmse 12 00374 g006
Figure 7. Characteristics of the measurement sections: (a) VP and measurement section P; (b) VM and measurement section M; (c) typical equipment for pressure measurement.
Figure 7. Characteristics of the measurement sections: (a) VP and measurement section P; (b) VM and measurement section M; (c) typical equipment for pressure measurement.
Jmse 12 00374 g007
Figure 8. Pressure signals at sections P and M acquired during the scheduled survey (Table 1).
Figure 8. Pressure signals at sections P and M acquired during the scheduled survey (Table 1).
Jmse 12 00374 g008
Figure 9. Analysis of the system’s transient response: (a) pressure signal at M, acquired during the VM closing; and (b) dimensionless pressure variation, Δ h p e a k s .
Figure 9. Analysis of the system’s transient response: (a) pressure signal at M, acquired during the VM closing; and (b) dimensionless pressure variation, Δ h p e a k s .
Jmse 12 00374 g009
Figure 10. Pressure signals, H, in section M, acquired during the scheduled and extemporaneous surveys: (a) time-domain analysis and (b) frequency-domain analysis.
Figure 10. Pressure signals, H, in section M, acquired during the scheduled and extemporaneous surveys: (a) time-domain analysis and (b) frequency-domain analysis.
Jmse 12 00374 g010
Table 1. Steps timing of the scheduled survey.
Table 1. Steps timing of the scheduled survey.
Steps TimeTiming (s)Operation
t 0 0Pressure monitoring start
t 1 702Pump 8 switching off
t 2 1704Pump 9 switching off
t 3 3130VM closure
t 4 10,021SDV opening
t 5 13,360SDV closure (transient test)
t 6 16,189VM opening
t 7 17,313Pump 9 switching on
t 8 17,931Pump 8 switching on
t 9 18,996Pressure monitoring end
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Meniconi, S.; Brunone, B.; Tirello, L.; Rubin, A.; Cifrodelli, M.; Capponi, C. Transient Tests for Checking the Trieste Subsea Pipeline: Toward Field Tests. J. Mar. Sci. Eng. 2024, 12, 374. https://doi.org/10.3390/jmse12030374

AMA Style

Meniconi S, Brunone B, Tirello L, Rubin A, Cifrodelli M, Capponi C. Transient Tests for Checking the Trieste Subsea Pipeline: Toward Field Tests. Journal of Marine Science and Engineering. 2024; 12(3):374. https://doi.org/10.3390/jmse12030374

Chicago/Turabian Style

Meniconi, Silvia, Bruno Brunone, Lorenzo Tirello, Andrea Rubin, Marco Cifrodelli, and Caterina Capponi. 2024. "Transient Tests for Checking the Trieste Subsea Pipeline: Toward Field Tests" Journal of Marine Science and Engineering 12, no. 3: 374. https://doi.org/10.3390/jmse12030374

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop