Next Article in Journal
Recognition of Stages of Endogenous Fire Outbreak and Development in Coal Mines
Previous Article in Journal
Deep Learning Model Ensemble Applied to Modulus Back-Calculation of Old Cement Concrete Rubblized Overlay Asphalt Pavement
Previous Article in Special Issue
Image Augmentation Approaches for Building Dimension Estimation in Street View Images Using Object Detection and Instance Segmentation Based on Deep Learning
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

A Preliminary Study on the Comparative Schedule Analysis of Traditional and Advanced Work Packaging Plans for Nuclear Power Plant Construction

Department of Nuclear Power Plant Engineering, KEPCO International Nuclear Graduate School (KINGS), 658-91 Haemaji-ro, Seosaeng-myeon, Ulju-gun, Ulsan 45014, Republic of Korea
*
Author to whom correspondence should be addressed.
Appl. Sci. 2025, 15(20), 11113; https://doi.org/10.3390/app152011113
Submission received: 21 September 2025 / Revised: 11 October 2025 / Accepted: 13 October 2025 / Published: 16 October 2025

Abstract

The construction of nuclear power plants (NPPs) involves complex and long-duration projects where schedule delays critically affect project performance. To overcome this challenge, Advanced Work Packaging (AWP) has emerged as a promising alternative approach. It offers a more integrated and structured way to plan and execute projects, aiming to improve efficiency and reduce the risk of delays. To evaluate the potential benefits, this preliminary study developed and compared a traditional phase-based schedule and two AWP-based schedules. Delay simulations and productivity adjustments were conducted to analyze schedule resilience and mitigation performance. The results show that AWP-based schedules enhance traceability, expand work package granularity, and improve recovery against engineering delays through structured segmentation and Workface Planning (WFP). These findings quantitatively demonstrate the potential of AWP to improve scheduling efficiency not only in NPP projects but also mega construction projects while also identifying gaps in maturity, boundary definition, and integration practices that must be addressed for broader adoption.

1. Introduction

The construction of nuclear power plants (NPPs) entails large-scale, complex projects with long durations and high regulatory and safety requirements. Schedule delays in such projects often lead to significant cost overruns and stakeholder risks [1]. In the nuclear domain, these delays are especially consequential because of safety and regulatory interfaces and often cascade into severe cost overruns and extended completion times [2]. Empirical rankings identify policy changes and approval delays as dominant schedule risks, reinforcing the need for policy frameworks that prioritize design maturity and a stable, predictable safety-regulatory regime with explicit construction-readiness requirements [3,4]. Accordingly, an effective management system ensuring documentation, configuration control, and lifecycle traceability becomes a prerequisite for disciplined schedule control [5].
Advanced Work Packaging (AWP) has emerged as a structured project execution methodology that improves schedule predictability, cost efficiency, and quality through well-defined work packaging and the alignment of engineering, procurement, and construction (EPC) processes [1,6,7,8,9,10,11,12,13]. International adoption of AWP is expanding across industrial sectors (e.g., oil & gas, petrochemical, infrastructure) [9,10,11,12] and owners have begun to require bidders to incorporate AWP principles into project planning [9].
Most prior AWP research has focused on explaining concepts, pros and cons, it has rarely provided explicit schedule logic or practical comparisons with traditional practices. This study aims to clearly demonstrate the differences between AWP and traditional project management methods, specifically within the context of a nuclear power plant construction project. The research focuses on two main objectives. First, it identifies the specific changes required in the WBS, deliverables, and activities when transforming traditional schedules into an AWP-based approach. Second, it compares this AWP-based method to current Korean traditional NPP practices to pinpoint the practical advantages and disadvantages of its adoption. Ultimately, this study offers a clear, scheduling-level comparison to illustrate how AWP can practically change project planning and control, and frames this comparison in terms of schedule resilience—the ability of plans to absorb engineering delays and recover execution feasibility [14,15]. The novelty of this work lies in being the first preliminary attempt to systematically apply AWP concepts to nuclear power plant scheduling. By developing both traditional and AWP-based schedules on a common Nuclear Island model, the study provides an intuitive apples-to-apples comparison, contributing methodological insights and practical evidence to guide future adoption of AWP in the nuclear domain.

2. Background: AWP Application for NPP Construction

2.1. Previous AWP Application Research

AWP is a structured execution framework that aligns EPC through clearly defined package types and workface planning. Its core components are well established in the literature: Construction Work Areas (CWAs), Path of Construction (POC), Engineering/Procurement/Construction Work Packages (EWP/PWP/CWP), Installation Work Packages (IWP), and Workface Planning (WFP) [13]. In practice, early definition of the POC and constraint-free release of IWPs are repeatedly highlighted as mechanisms that improve schedule predictability and field productivity [13,16,17].
Across industrial sectors such as oil and gas, petrochemical, infrastructure, empirical and case-based studies report that AWP adoption is associated with productivity gains, reductions in total installed cost, and improved schedule reliability and safety performance, with benefits traced to disciplined work packaging, earlier engineering readiness, and clearer inter-package interfaces [10,11,12,13,16,17]. Methodological work has also proposed decision frameworks to evaluate AWP’s costs and benefits by structuring both direct costs and indirect/intangible benefits for investment decisions [18].
Scope extensions have been studied to connect AWP with commissioning and startup. For example, package schemas and handover criteria have been proposed to bridge IWP-level field completion to system-based commissioning activities, thereby reducing late rework and improving startup readiness [19]. On the information side, researchers emphasize bridging the engineering and construction 3D so that package boundaries, sequencing, and constraints are consistently represented across design and construction environments; poor alignment has been linked to rework and schedule slippage [20].
Implementation studies and reviews consistently surface enablers and barriers: organizational maturity and training, data/model standards, system interoperability, governance and roles/responsibilities, and stakeholder alignment. Sectoral surveys and literature syntheses report that ambiguity in implementation plans, capability gaps, and fragmented systems are recurring inhibitors that must be addressed for AWP to deliver the intended outcomes [21,22,23,24,25].
In summary, prior research indicates that (i) package-based execution with proactive constraint removal tends to improve schedule and cost performance, (ii) early POC definition and model/data alignment are necessary preconditions, and (iii) organizational readiness largely determines realized benefits [10,11,12,13,16,18,19,20,21,22,23]. However, there weren’t much research showing the detailed schedule logic and work package information.

2.2. Considerations for AWP Application in NPP Construction

NPP projects face tighter regulatory, quality, and documentation requirements than most industrial projects; they also feature system-centric testing and turnover, long-lead procurement, and complex interfaces. Translating AWP into this environment calls for the following considerations, which draw on both international megaproject insights and Korean NPP practice.
(1)
Alignment with licensing hold points and regulatory milestones.
NPP schedules are highly sensitive to front-end definition and external approvals. POC and CWP boundaries should be established to coincide with licensing hold points and inspection gates so that release of EWPs, CWPs and IWPs is feasible within the regulatory timeline [1]. In practice, policy frameworks should prioritize design maturity and regulatory stability with explicit construction-readiness requirements and a stable, predictable safety-regulatory regime, directly addressing approval-driven schedule risk [3]. Such approval delays are repeatedly ranked among top schedule drivers in empirical assessments [4].
(2)
Mapping to QA/QC and document/procedure control.
Korean NPP delivery relies on mature process and procedure management (standardized workflows, controlled documentation, rigorous revision/approval cycles). AWP packages must therefore be mapped to existing QA records and procedure hierarchies so that package completion criteria and evidence (drawings, specifications, inspection/test records) are auditable within the current quality system [26]. An effective management system—ensuring documentation, configuration control, and lifecycle traceability—is essential and AWP packaging should be embedded within the project’s safety/quality/regulatory interfaces [5].
(3)
Bridging phase-driven WBS and CWA-driven AWP.
Domestic practice commonly uses phase (EPC) and discipline-driven WBS with CPM and EVMS (WBS–Control Account–cost/schedule integration). Because AWP organizes scope by CWA, a direct 1:1 mapping gap exists. Clear WBS to CWA/package mapping rules (e.g., WBS code extensions, cross-walk tables) and redefined progress/cost roll-ups are needed to preserve EVMS integrity while introducing EWPs/PWPs/CWPs [27]. Recent Korean reviews of AWP for NPPs reach similar conclusions and recommend early decisions on package boundaries and coding to avoid late rework in controls and reporting [24,28].
(4)
Engineering–construction data/model consistency.
EWP deliverables (drawings, MTOs, specifications) and CWP/IWP readiness attributes (materials, access, safety, quality checks) should live in compatible data models to prevent interface gaps. Research urges a structured bridge between engineering and construction models so that package metadata, sequencing, and constraints are consistent and machine-readable across tools [20]. Consistent information and records reduce rework from errors and late design changes, which are frequently observed delay factors in NPP projects [2,28].
(5)
Commissioning interface (system-based turnover).
Because NPP turnover is system centric, commissioning packages and handover criteria (e.g., completeness, QA records, punch status) should be explicitly linked to CWP/IWP completion states. The AWP literature proposes package schemas and governance to tie construction work faces to system-level commissioning workflows [19,28,29].
To apply AWP to nuclear projects, management plans must span the full delivery lifecycle, from early definition to final commissioning, and should incorporate the considerations outlined above. Using the PMBOK process framework as a guide [30], this study concentrates on early-phase foundations because they set constraints for all later work and can be evaluated with available project data. Accordingly, the research scope focuses on defining the WBS and developing the schedule that is traceably linked to that WBS, which together act as prerequisite enablers for integrating engineering, procurement, and construction in an AWP context [24,27].

3. Methods: Research Framework and Model Set Up

This study implements a comparative schedule analysis comprising model configuration, development of a traditional phase-based and two AWP-based (AWP-M1, AWP-M2) schedule, parameter adoption (productivity uplift and workface-planning), and delay–recovery simulations. Figure 1 details the procedure for the comparative schedule analysis. Productivity is applied as literature-based assumptions, while explicit resource and spatial constraints are not modeled in this comparison.

3.1. Model Configuration

A scaled-down hypothetical model of the Nuclear Island (NI), comprising the Reactor Containment Building (RCB) and the Auxiliary Building (AB), was configured as the project scope. This was selected because it captures the dominant critical path of the NPP schedule and is tightly coupled with startup milestones and Final Safety Analysis Report (FSAR) interfaces; accordingly, much prior work focuses on compressing this path. In addition, construction practices within the NI & AB already employ segmentation concepts equivalent to CWAs and the POC, which enables consistent area-based breakdown and sequencing in this study. CWAs were defined for each major zone, and the POC was established according to logical sequencing (Figure 2).
The geometric reference followed Shin-Kori Units 3 and 4 Final Safety Analysis Report (FSAR), Chapter 1: General Plant Information [31]. To isolate schedule-structure effects, the model was intentionally simplified. Only structural boundaries and construction zones were represented, while detailed equipment layouts, piping systems, and functional rooms such as the Main Control Room (MCR) were omitted. For the AB, functional elements that are typically concentrated in specific zones in practice were assumed to be uniformly distributed across CWAs to minimize modeling bias and support analysis of AWP-based WBS and schedule structures. Accordingly, to assume a model that permits the uniform application of simplified, standardized durations to unit activities in the schedules developed in this study, dimensional scaling was applied to derive realistic activity durations; key dimensions and scaling ratios are summarized in Table 1.

3.2. Traditional Schedule Development

3.2.1. WBS Creation

Figure A1 presents the traditional WBS developed based on typical Korean NPP practices [24]. The structure supported the study objectives by enabling comparison with AWP-based WBS models and by providing a foundation for schedule development. It followed a discipline-driven, phase-based hierarchy segmented into EPC phases and was optimized for progress measurement and cost management, consistent with Korean NPP practice. Unlike AWP-based WBS structures, it was not explicitly aligned with CWAs or the POC and primarily functioned as a performance-tracking structure rather than a field-execution guide.
Work packages in this study were defined at Level 4 of the WBS:
  • Engineering Functional Breakdown Structure (FBS) items representing discipline-specific drawings, specifications, and calculations.
  • Procurement packages (PO, Purchase order) representing major material and equipment supply.
  • Construction package (CP) activity types representing grouped site work activities. The selected Level 4 items used for modeling are listed in Appendix A.4 Scheduling Assumptions.
These selections enabled clear mapping across engineering, procurement, and construction sequences, supported realistic activity-duration estimation, and established a structured basis for comparative analysis between the traditional baseline and AWP-based schedules. Details on how these deliverables informed schedule logic and activity durations are presented in the following subsection.

3.2.2. Schedule Development

Define Activities
Based on the selected Level-4 work packages, activities and associated deliverables were defined together with their relationships to maintain a consistent structure across EPC phases and to identify standard sequences per WBS item. Engineering activities modeled drawings and documents as Preliminary Issue (PI) followed by Construction Issue (CI), and specifications were issued for Invitation to Tender (ITT). Procurement sequences comprised ITT; bidder selection/purchase-order award/vendor data submission (ITT/PO/VD); review and approval (R&A); and fabrication and site delivery (Fab). Construction execution was organized by physical segmentation (area, level, and type of work). Representative relationships are illustrated in Figure A7 and Figure A8.
Sequence Activities
To ensure comparability between the traditional and AWP-based approaches, detailed activity relationships were simplified and standardized. Initial sequences derived from Korean NPP cases (Figure A7) were refined into a standard sequence model (Figure A8), aligning engineering, procurement, and construction phases across disciplines and providing a practical baseline for comparative analysis. A 30-day lead time was applied between completion of engineering/procurement activities and the start of the corresponding construction tasks to reflect preparation and readiness requirements. A relationship-mapping table (* Part of the numbers are replaced with “X” for confidentiality. Table A6, Table A7 and Table A8) identified logical linkages among engineering (FBS), procurement (PO), and construction (CP) activity types.
Estimate Activity Durations
Activity durations were determined based on the following: (i) reference values from Korean NPP project schedules; (ii) adjustments reflecting the scaling factors of the hypothetical model (Table 1); and (iii) the simplified activity flow (Figure A8).
  • Engineering activities: PI (3 months), CI (2 months), and specification issue for ITT (2 months).
  • Procurement activities: ITT/PO/VD (2 months), R&A (1 month), and fabrication & site delivery (1–12 months depending on material or equipment type).
  • Construction activities: durations were assigned according to area, level, or type of work, and adjusted for scaling ratios, reflecting typical field productivity in Korean NPP projects.
This standardized approach ensured comparability between the traditional baseline and AWP-based schedules.
Development Schedule
The traditional baseline schedule was developed using a CPM methodology in Microsoft Excel and Primavera P6. Logical networks were constructed for each Level-4 WBS element and linked according to Figure A8 and * Part of the numbers are replaced with “X” for confidentiality.
Table A6, Table A7 and Table A8 to reflect typical NPP construction flows. Before import into P6, an Excel Gantt chart was prepared and reviewed to validate linkages, confirm EPC sequencing, and resolve inconsistencies. After validation, activity sequences and durations were imported into P6 to generate the baseline traditional project schedule.

3.3. AWP-Based Schedule Development

3.3.1. WBS Creation

WBS Structure
The AWP-based WBS was configured with reference to established AWP WBS frameworks [24] and aligned with CWA segmentation to support the development of EWPs, PWPs, and CWPs (Figure A2). The activity-development process followed the traditional baseline and was further refined into a CWA-based organization to reflect AWP principles.
Define Work Packages
Four alternative packaging schemes were developed from the defined WBS (Figure A3, Figure A4, Figure A5 and Figure A6) to test how traditional engineering and procurement processes could be structured into AWP-compatible units (Table 2). The four alternatives are characterized as follows:
  • Method 1 (AWP-M1): Engineering by functional deliverable (FBS); procurement by equipment type.
  • Method 2 (AWP-M2): Engineering by discipline; procurement by equipment type.
  • Method 3 (AWP-M3): Engineering by discipline and by issue phase (PI/CI); procurement by discipline and by procurement phase.
  • Method 4 (AWP-M4): Engineering and procurement by discipline.
Based on applicability to CWA-based scheduling, corroborated by the assessment criteria and scores in Appendix A.1, methods 1 and 2 were selected for detailed schedule development. The rationale for selection and their comparative performance are reported in Section 4.

3.3.2. Schedule Development

Define Activities
The activity structure followed the same framework and standard relationships as the traditional baseline (Figure A8). Activities were then subdivided by CWA under the AWP-based WBS, enabling independent planning and tracking by work area and ensuring alignment among EWPs, PWPs, and CWPs while preserving comparability.
Sequence Activities
Sequencing was derived by partitioning the traditional activity flows by CWA and applying the POC. Although traditional Korean NPP schedules did not explicitly use the terms “CWA” and “POC,” equivalent concepts are partly embedded in segmentation practices (e.g., design areas, construction joints/sequences). In this study, the same CWA segmentation and POC was applied to both the traditional and AWP-based schedules for construction.
Estimate Activity Durations
Activity durations were adopted from the traditional baseline to ensure consistency. The same 30-day lead time was applied between engineering/procurement completion and the start of corresponding construction activities. This approach isolates structural effects of work packaging and sequencing.
Development Schedule
AWP-based schedules were developed directly in Primavera P6 using the CWA-based WBS and activity definitions. Common project milestones were maintained across models to enable direct comparison of schedule performance and characteristics.

3.4. Schedule Impact Adoption

3.4.1. Construction Productivity Effect

A 25% construction-productivity improvement factor was applied to AWP-M1 and AWP-M2 to evaluate the potential benefits of AWP-based delivery. Prior studies [7,9,10] report field-productivity gains of 20–25%, attributed to improved workface planning (reduced idle time). Accordingly, durations of construction activities in Primavera P6 were reduced by 25% in the AWP-based schedules to isolate AWP-driven productivity effects. In this preliminary scenario, the 25% uplift is used as a representative value synthesized from industry case studies [9] and is not a trade-specific estimate. The purpose is to provide an intuitive, reproducible comparison of schedule behavior between traditional and AWP configurations without over-fitting to sparse or non-public domestic datasets.
In addition, to reflect the AWP practice that Engineering Work Packages are issued at least 90 days before field execution, a 90-day finish-to-start lag was inserted between IEWP and the start of corresponding construction; the same minimum lead time was enforced between completion of procurement and construction start. This lead-time setting ensured engineering completion preceded construction with sufficient margin for IWP development, improving sequencing control and compliance with workface-planning protocols.
Together, these modifications enabled a structured comparison between the traditional baseline and the AWP-based models under uplifted productivity assumptions and explicit readiness constraints.

3.4.2. Workface Planning Effect

In field operations, the workface planner verified information completeness for IWPs and monitored whether planned construction could proceed as scheduled. When information was incomplete or constraints remained near a planned start, the planner flexibly adjusted sequencing using a prepared backlog of IWPs to prevent delays.
Assuming that construction began only after information completeness was ensured, a delay scenario was designed and implemented to examine the schedule impact of engineering delays and to evaluate AWP-based WFP mitigation (In the simplified baseline schedule, procurement activities were placed explicitly between engineering deliverables and construction tasks (Figure A8). Any procurement delay therefore propagates deterministically to site installation. For this reason, the simulation scope was limited to engineering delays, as their downstream impact inherently included procurement slippage.). The procedure (Figure 3) comprised the following steps.
  • Selection of delay-causing engineering activities. As summarized in Table A9, delay drivers were selected from the Traditional, AWP-M1, and AWP-M2 schedules by choosing, for each discipline, the earliest drawing-related engineering activity that could affect downstream construction. Multi-discipline deliverables with broad successor impacts were excluded to enable clear attribution of WFP effects. Target structures were grouped as RCB and AB; for the AB, a conservative choice selected the earliest engineering activity in CWA2 to ensure a direct, measurable impact on subsequent construction.
  • Insertion of delaying dummy activity. A Delaying Dummy Activity was inserted as a predecessor to the selected construction tasks to represent upstream engineering delay.
  • Increment of dummy duration. The dummy duration was increased in monthly steps using.
N = n + a × i
where
  • Initial delay: n = 0;
  • Increment step: a = 30 days;
  • Iteration step: i = i + 1;
  • Maximum delay duration: N ≤ 360 days.
4.
Schedule delay analysis. For each increment, the schedule was recalculated in Primavera P6, reflecting resulting changes in milestone dates.
5.
Evaluation of milestone impacts. Shifts were confirmed for First Concrete, Set Reactor Vessel (RV), and Construction Finish.
6.
WFP mitigation scenarios. Two scenarios were applied independently to isolate individual effects:
  • Scenario ①—Lead-time reduction by construction readiness. Consistent with CII IR 272-2 guidance [7], IWPs were assumed to be prepared 3 months (2 months development and 1 month of lead time) in advance. Upon detecting delay, up to 30 days of this 3-month window were repurposed as schedule float without compromising readiness.
  • Scenario ②—Risk-driven re-sequencing via backlog utilization. Successor activities were re-sequenced to maintain workflow continuity, allowing non-impacted areas to proceed in parallel using pre-issued backlogs; the logic is summarized in Table A10.
  • Initially, Scenario ① was intended to run with concurrent re-sequencing; however, extensive successor dependencies around the delayed engineering tasks made practical re-sequencing infeasible. Consequently, Scenario ② was executed separately by substituting the delayed engineering activity with its IEWP counterpart, enabling a distinct assessment of the re-sequencing strategy and clearer attribution of milestone recovery.
7.
Schedule update and recording. After each schedule delay/mitigation analysis, the schedule was updated and milestone impacts were recorded.
8.
Iteration and termination. Steps 3–7 were repeated for all increments until N = 360 days, at which point the simulation terminated.

3.5. Comparative Analysis

This section presents a comparative analysis of the traditional baseline and the two AWP-based schedules (AWP-M1 and AWP-M2). The objective was to evaluate, in a controlled manner, how differences in work packaging, WBS structure, activity sequencing, assumed productivity uplift, and WFP mitigation affected schedule performance and resilience under engineering-delay conditions. To ensure consistency, all models shared the same overall project scope and milestones, top-level WBS hierarchy, activity taxonomy, and base sequencing rules. The analysis evaluated (i) WBS structure—level of detail, hierarchy alignment, and integration with CWA and POC; (ii) activity and deliverable breakdown—counts, types, and package distribution; (iii) schedule durations—overall and by phase; (iv) sensitivity to engineering delays—shifts in construction finish; and (v) mitigation performance under delay scenarios—effects of WFP actions and recovery patterns relative to the traditional model. The quantitative results in Section 4 demonstrate the schedule impacts of AWP-based methods, outline advantages and limitations of each approach, and indicate their applicability to Korean NPP project environments.

4. Results: Illustrative Application and Discussion

4.1. Traditional Schedule Development

4.1.1. WBS Creation

The traditional WBS was developed in line with typical Korean NPP practices [24]. The structure supported the study objectives by enabling comparison with AWP-based WBS models and by providing a basis for schedule development. It followed a discipline-driven, phase-based hierarchy segmented into EPC phases and was optimized for progress measurement and cost management. For consistency across phases, activities were grouped by discipline using an Organizational Breakdown Structure (OBS), even though actual projects often distinguish engineering functions from contract packaging (e.g., NSSS vs. BOP, or construction by package vs. by discipline).
The WBS and corresponding activities were first assembled in excel to reflect major deliverables (e.g., reinforcing steel bars, structural drawings) and included attribute fields to enable direct import into Primavera P6. A summary of the total number of activities and deliverables by WBS level is provided in Table 3 (details in Table A11).

4.1.2. Schedule Development

An Excel Gantt chart was prepared from the relationship mapping in * Part of the numbers are replaced with “X” for confidentiality.
Table A6, Table A7 and Table A8 to verify activity linkages prior to development in Primavera P6. After validation, the activities and relationships were imported into P6 to generate the traditional schedule; the resulting critical activities are shown in Figure A12. Key project milestones are summarized in Table 4, yielding a total project duration of approximately 42 months from start to finish across engineering, procurement, and construction phases. The quantity and types of logic relationships applied in the P6 schedule are summarized in Table 5, with a total of 589 predecessor–successor links.

4.2. AWP-Based Schedule Development

4.2.1. WBS Creation

WBS Structure
In developing the AWP-based WBS, Figure A2 was referred to as the foundational guideline. As shown in Figure 4, the hierarchical structure was reorganized to align with the AWP framework, emphasizing physical construction zones (CWAs), work packaging logic, and clear alignment with the EWPs, PWPs, and CWPs.
In contrast to the traditional schedule, where the breakdown was driven by functional disciplines or contract packages, the AWP-based WBS was configured as follows:
  • Level 1: Project;
  • Level 2: CWA;
  • Level 3: Phase (Engineering, Procurement, Construction);
  • Level 4: Discipline (OBS);
  • Level 5: Work Package;
  • Level 6: FBS, Equipment type, Construction type.
This configuration maintained compatibility with project-management practice while aligning with AWP. Selecting CWA at Level 2 reflected the central role of physical workface zones in defining IWPs and CWPs. Clear phase delineation at level 3 enabled distinct control of engineering, procurement, and construction workflows. An OBS-based level 4 was applied uniformly to harmonize the hierarchy across phases and to improve responsibility clarity and traceability. Although real projects often group procurement by NSSS vs. BOP or organize construction by package/subcontractor, such contract-driven groupings were intentionally avoided here to enhance consistency and comparability across WBS levels. In addition, whereas traditional schedules typically use POs as the primary procurement unit, the AWP WBS decomposed these elements under each CWA; consequently, PWPs should be regrouped and redefined in line with procurement/contracting strategies that reflect this breakdown.
Define Work Packages
To establish an effective AWP packaging framework, four alternatives were evaluated with an assessment matrix (Appendix A.1) against six criteria—Scope Definition, WBS Compatibility, Schedule Unit, Compatibility with Schedule Hierarchy, Constructability, and Progress Measurement—for both EWP and PWP.
  • Method 1 (AWP-M1). Scored 4–5 across all criteria and was the only scheme to receive a 5 for both “EWP as a Schedule Unit” and “Progress Measurement by EWP.” The FBS-based EWP boundary forms self-contained schedule units with minimal cross-coupling, and its deliverable register enables direct, auditable progress measurement. Equipment-type PWPs nest cleanly under CWA/CWP and align with procurement/fabrication streams, sustaining constructability with routine materials planning and measurable progress.
  • Method 2 (AWP-M2). Also scored 4–5 across all criteria and was the only scheme to receive a 5 for “EWP Compatibility with Schedule Hierarchy.” Discipline-based EWPs map directly to the OBS layer within the WBS, slotting into the schedule hierarchy with supplemental links. PWPs are defined the same as in Method 1.
  • Method 3 (AWP-M3). Predominantly 3–4. The EWP scored 3 on “Scope Definition, Schedule Unit, and Compatibility with Schedule Hierarchy” because splitting by issue phase (PI/CI) divides a single discipline’s scope over time, creating relationship logics for overlapping activities of phase functions of work, and an expanding number of packages as phases increase. The PWP likewise scored 3 on the same items (and associated constructability/progress implications) since discipline-plus-procurement-phase coupling conflicts with PO lifecycles (composition and process), demands supplementary activity relationships and field-requested-date plans, and require management plans per equipment-level traceability.
  • Method 4 (AWP-M4). Ranged 3–5. The EWP have same scores with method 2, but the PWP scored 3 on “Schedule Unit, Constructability, and Progress Measurement” because discipline-based PWPs conflicts with PO lifecycles (composition), demands supplementary activity relationships and field-requested-date plans, and require management plans per equipment-level traceability.
A recurring concern with PWPs was granularity. Decomposition by CWA/CWP further multiplies the amount of PWPs; moreover, site logistics and field-requested dates make pure WP-level materials control burdensome without sub-WP checks. Accordingly, in this study, we retain PWP grouping for WBS/control purposes but do not introduce separate “PWP issuance” activities; procurement is anchored in the schedule by fabrication and delivery nodes that already tie to engineering readiness and field need dates. Considering the above results and the scores in Table 6, Methods 1 and 2 were advanced to detailed schedule development, while Methods 3 and 4 were excluded due to phase-split inefficiencies (M3) and discipline-based PWP control/logistics drawbacks (M4).
AWP Method 1 (AWP-M1)
The WBS and corresponding activities for AWP-M1 were first developed in Excel to reflect major deliverables (e.g., reinforcing steel bars, structural drawings) and included attribute fields for direct import into Primavera P6. Table 7 (details in Table A12) summarizes activity quantities by WBS level, including IEWP and ENG-IF items (definitions provided in Section 4.2.2). The AWP-M1 WBS was then implemented in P6 following the standard logical structure in Figure A3.
Table 7. AWP-M1-Summary of activity and deliverable quantities by WBS.
Table 7. AWP-M1-Summary of activity and deliverable quantities by WBS.
WBS LevelQuantity (Activities/IEWP/ENG-IF)ENG
Deliverable
Lev.2
CWA
Lev.3
Phase
Lev.4
OBS
Lev.5
WP
AE/BOPNSSS/RCBCommonTotal
Milestone/Dummy--33-
0ENG468 (7/1/0)11 (7/4/0)3 (2/1/0)22 (16/6/0)16
PRO2233-6-
CON111--1-
Sum9121432916
1ENG531-93 (48/31/14)-93 (48/31/14)276
PRO510-30-30-
CON58-46-46-
Sum49-169-169276
2, 3, 4, 5 eachENG52476 (38/24/14)--76 (38/24/14)162
PRO5721--21-
CON5525--25-
Sum36122--122162
Total2025001836689940
AWP Method 2 (AWP-M2)
The WBS and activities for AWP-M2 were likewise developed in Excel with import attributes for Primavera P6. In contrast to AWP-M1, AWP-M2 bundled multiple deliverables into fewer work packages, reducing package counts and simplifying coordination, while it may increase the complexity of tracking individual deliverable readiness or constraint resolution due to the higher level of aggregation within each package. This approach reflects field practice in which engineering drawings are often issued and reviewed in batches by area or system.
Table 8 presents the quantitative summary for AWP-M2 (including IEWP and ENG-IF counts; Section 4.2.2), showing reductions in both activities and packages relative to AWP-M1—primarily due to integration of CWP-related engineering work. The resulting AWP-M2 WBS was configured in P6 based on the logical structure in Figure A4.
Table 8. AWP-M2-Summary of activity and deliverable quantities by WBS.
Table 8. AWP-M2-Summary of activity and deliverable quantities by WBS.
WBS LevelQuantity (Activities/IEWP/ENG-IF)ENG
Deliverable
Lev.2
CWA
Lev.3
Phase
Lev.4
OBS
Lev.5
WP
AE/BOPNSSS/RCBCommonTotal
Milestone/Dummy--33-
0ENG468 (1/1/0)11 (7/4/0)3 (2/1/0)22 (16/6/0)16
PRO2233-6-
CON111--1-
Sum9121432916
1ENG524-86 (48/24/14)-86 (48/24/14)276
PRO510-30-30-
CON58-46-46-
Sum42-162-162276
2, 3, 4, 5 eachENG51668 (38/16/14)--68 (38/16/14)162
PRO5721--21-
CON5525--25-
Sum28114--114162
Total1634681766650940

4.2.2. Schedule Development

The AWP-based schedules were developed using the same foundational logic and standardized sequences as the traditional baseline. Sequencing and activity relationships followed the workflows in Figure A3 and Figure A4 and the logic map in Table A6, Table A7 and Table A8. All activities were defined during WBS development in Section 4.2.1.
However, two critical implementation considerations unique to AWP were identified and incorporated during scheduling:
Management of Duplicate Engineering Deliverables
In procurement planning, overlapping information across multiple PWPs (due to CWP breakdowns) is generally manageable—particularly for physical items such as tags and bulk materials, which remain consistent and identifiable.
However, in engineering, the same deliverables (e.g., drawings, specifications) may be required by multiple CWPs within a single CWA. As the number of CWPs increases or their scopes narrow, the same engineering deliverable can become logically assigned to several different CWPs. In AWP, these are treated as separate entities and assigned different codes. While this is acceptable in a database-driven management system, it introduces complexity when developing and managing the schedule in tools like Primavera P6, which require clear logic relationships.
To address this, Start Interface (SI) and Finish Interface (FI) activities—collectively referred to as ENG-IF—were introduced. These act as centralized control points for shared deliverables across CWPs. Each CWP that references a shared deliverable establishes logical relationships to these ENG-IF activities:
  • SI captures the earliest start among all referencing activities.
  • FI captures the latest finish among them.
This ensured that predecessor/successor logic, especially for fabrication and fieldwork, depended on the global start/finish of the shared deliverable rather than on any single instance. The configuration is illustrated in Figure A9, and Figure A10 shows how a delay to one EWP shifts the global FI and downstream successors.
Issuance of Engineering Work Packages (IEWP)
In traditional EPC scheduling, engineering, procurement, and construction activities are often managed independently and interface dates are exchanged via designated interface activities. These interface activities are often contractually fixed and rigid.
To align with AWP principles, IEWP activities were introduced to replace interface activities between engineering and construction. These represent the final issuance of engineering deliverables required for CWP-level field execution and serve as the formal control points between design and construction.
While interface activities may still be relevant between engineering and procurement (e.g., for vendor data or specification transfer), the engineering-to-construction relationship is now captured via these IEWP activities.
Procurement activities, in this study, were not further decomposed into physical PWPs. Although PWP-level scheduling could be considered, it was deemed unnecessary since fabrication activities already serve as effective scheduling anchors with direct logical links to engineering deliverables. Thus, schedule management remains both simplified and meaningful.
All construction deliverables required by a CWP are logically connected to their corresponding IEWP activities, ensuring visibility into readiness and schedule integration. Figure A11 shows the added IEWP activity and relationship within EWP16.
Following the application of the WBS and logic development principles described above, the scheduling results for AWP-M1 and AWP-M2 were compiled and summarized. These outcomes include the total quantity of activities, work packages, and engineering deliverables generated, as well as the quantity and types of logical relationships developed in Primavera P6.
Table 7 and Table 8 present the quantitative outcomes of activity and deliverable generation for AWP-M1 and AWP-M2, respectively. AWP-M1 resulted in a total of 202 work packages, 689 activities including IEWPs and ENG-IF nodes, and 940 engineering deliverables. AWP-M2 generated 163 work packages, 650 activities including IEWPs and ENG-IF nodes, and 940 engineering deliverables.
Logical relationship mappings used in P6 are summarized in Table 9 and Table 10. AWP-M1 included 1079 relationships and AWP-M2 slightly reduced the total to 1055, primarily due to a decreased number of IEWP to CON dependencies.
Developed Schedule
The final AWP schedules critical path activities are visualized in Figure A13 and Figure A14. AWP-M1 shows more IEWP activities and relationships due to finer packaging granularity, whereas AWP-M2 applies more aggregated packaging with fewer work packages and slightly simpler paths. Both AWP schedules maintained the same key milestone dates as the traditional model (Table 4).

4.3. Schedule Impact Adoption

4.3.1. Construction Productivity Effect

Applying a 25% construction-productivity uplift to AWP-M1 and AWP-M2 advanced the Construction Finish by 120 days. To comply with AWP practice that EWPs are issued at least 90 days before field execution, a 90-day IEWP → CWP finish-to-start lag was enforced; this offset part of the gain, yielding a net improvement of 60 days versus the baseline. This resulted from a 120-day reduction achieved by the 25% productivity uplift, partly offset by a 60-day increase associated with the readiness lag for IWP development under AWP practice, yielding a net saving of 60 days. The resulting dates and variances are summarized in Table 11.

4.3.2. Workface Planning Effect

Delay Impact Results in Traditional Schedule
In the Traditional model, the insertion of 360-day delays into eight discipline-specific engineering activities resulted in milestone deferrals ranging from 0 to 270 days, depending on the degree of float and the criticality of each path. As summarized in Table 12, civil I, electric (E), and piping (P) deliverables in both RCB and AB areas exhibited the largest impact. The delay by I&C (J) deliverable did not influence the finish date because of the free float.
Scenario ①: Schedule Recovery by Backlog Float Utilization (AWP-M1, M2)
To simulate AWP-based mitigation (Scenario ①), a 30-day float derived from the standard IWP preparation buffer was applied to each delayed engineering deliverable. The results for AWP-M1 and AWP-M2 are presented in Table 13, showing consistent delay reductions of 30 days in most activities where mitigation was applicable. Activities with sufficient float (J159PI) showed no delay regardless of the scenario.
Scenario ②: Schedule Recovery by Re-Sequencing of IEWPs Successor Activities (AWP-M1, M2)
Table 14 presents the results of schedule delay and mitigation outcomes for delayed IEWP activities in the AWP-M1 model. The scenario assumes a 360-day engineering delay, with risk-driven re-sequencing applied to assess potential schedule recovery.
I-EWP16, I-EWP24, I-EWP46, and I-EWP52 cases exhibited no schedule impact despite being delayed, due to the presence of sufficient free float within the schedule. These IEWPs were preconfigured with generous float periods, enabling delay absorption without affecting downstream activities.
I-EWP10 and I-EWP27, both located in the RCB zone, experienced delays of 186 days and 34 days, respectively. However, no schedule recovery was achieved through re-sequencing. This is attributable to the absence of alternative activities within the same work type and time window in adjacent CWAs. Due to their location within the critical structural scope of the Reactor Containment Building, schedule flexibility was highly constrained.
In contrast, I-EWP41 and I-EWP57, associated with the Auxiliary Building (AB), CWA2, demonstrated substantial recovery potential. I-EWP41 initially delayed by 124 days achieved a recovery of 23 days, while I-EWP57, initially delayed by 170 days, recovered 74 days. These outcomes were made possible by the availability of identical work types across adjacent CWAs (CWA3, 4, and 5), allowing for effective re-sequencing and float absorption through parallel activity adjustments.
Table 15 presents the results of schedule delay and mitigation outcomes for delayed IEWP activities in the AWP-M2 model with the same scenario assumptions.
I-EWP13, I-EWP21, I-EWP35, and I-EWP40 cases exhibited no schedule impact despite being delayed, due to the presence of sufficient free float within the schedule. These IEWPs were preconfigured with generous float periods, enabling delay absorption without affecting downstream activities.
I-EWP9 and I-EWP25, both located in the RCB zone, experienced delays of 247 days and 185 days, respectively. However, no schedule recovery was achieved through re-sequencing. This is attributable to the absence of alternative activities within the same work type and time window in adjacent CWAs. Due to their location within the critical structural scope of the Reactor Containment Building, schedule flexibility was highly constrained.
In contrast, I-EWP31 and I-EWP44, associated with the Auxiliary Building (AB), CWA2, demonstrated substantial recovery potential. I-EWP31 initially delayed by 185 days, recovered 74 days, resulting in a net delay of 111 days. I-EWP44 initially delayed by 231 days, recovered 74 days, resulting in a net delay of 157 days. These outcomes were made possible by the availability of identical work types across adjacent CWAs (CWA3, 4, and 5), allowing for effective re-sequencing and float absorption through parallel activity adjustments.

4.4. Comparative Analysis

4.4.1. WBS Structure and Work Package Configuration

As summarized in Table 16, the Traditional schedule model adopts a WBS that reflects the characteristics of each EPC phase. At Level 2 and below, classification criteria varied by phase—e.g., contract packages in procurement, functional disciplines in engineering, or construction packages and types in field execution. This approach offers operational efficiency for each domain but lacks consistency across the entire schedule. Consequently, cross-phase reporting often requires manual aggregation or selective filtering, which introduces complexity in project controls.
In contrast, both AWP-M1 and AWP-M2 adopt a standardized and hierarchical WBS structure aligned with AWP principles. This configuration ensures consistent traceability and management across all scopes. The adoption of CWAs at Level 2 reflects the physical segmentation of the construction site, and identical breakdown logic is applied throughout the EPC domains and are further grouped by discipline, equipment type, or construction type depending on the phase.
However, such standardized structure can lead to increased fragmentation. Elements previously consolidated in the traditional schedule (e.g., common engineering or procurement tasks) may be split across multiple CWAs, increasing the number of work packages and deliverables to manage. Additionally, the uniform structure may require additional customization when applied to projects with unique organizational or contract-specific requirements.

4.4.2. Schedule Composition and Activity Volume

A quantitative comparison of schedule components across the Traditional, AWP-M1, and AWP-M2 models is provided in Table 17. Notable differences are observed in the number of activities, deliverables, and structural nodes required to support each scheduling approach.
In the engineering domain, AWP schedules demonstrate a significant increase in the number of activities. For AE/BOP engineering, the number of activities in both AWP-M1 and AWP-M2 increased by a factor of 6.63 compared to the Traditional model. This surge is attributed to the following:
  • The segmentation of engineering deliverables by CWA;
  • The replication of identical design activities across multiple CWPs;
  • The introduction of Issuance Engineering Work Package (IEWP) and ENG-IF nodes to coordinate shared deliverables across CWPs.
In the NSSS/RCB domain, the activity count increased by a factor of 1.77, primarily due to the redistribution of previously “common” activities into specific CWAs. This shift enables more localized tracking but increases the total volume of tasks.
AWP introduces 133 (M1) and 94 (M2) IEWP activities, which are not present in the Traditional schedule. These elements enhance schedule control by tracking the readiness of EWP sets instead of relying solely on individual engineering tasks.
The AWP models also eliminate the use of traditional interface activities—98 in engineering, 59 in procurement, and 124 in construction—through the adoption of an integrated schedule. This results in more transparent dependencies but requires a higher number of direct relationships between domain-specific activities.
Procurement activities increased significantly, from 33 activities (9 + 24) in the Traditional schedule to 120 activities in both AWP-M1 and AWP-M2, representing approximately a fourfold increase. This increase reflects the redistribution of materials previously grouped under common scopes into individual CWAs.
In construction, the increase in activity volume was relatively modest (about 13%) in the AE/BOP domain and negligible for NSSS/RCB. This reflects the fact that Traditional construction plans already accounted for zonal execution strategies. The additional activity count in AWP reflects further breakdown by physical area (CWA), such as by level or building.
Overall, the total number of activities increased from 517 in the Traditional schedule to 686 (AWP-M1) and 647 (AWP-M2). The number of engineering deliverables increased from 269 to 940, with 202 and 163 work packages, respectively, for AWP-M1 and M2—compared to only 48 in the Traditional model.

4.4.3. Schedule Logic and Relationship Density

Table 18 summarizes the schedule logic relationships embedded within the Traditional, AWP-M1, and AWP-M2 schedules. AWP implementation led to a significant increase in logical connectivity, especially in engineering and procurement activities, due to more granular structuring and the introduction of intermediate coordination nodes.
  • Engineering-to-Engineering Relationships:
In the Traditional schedule, there were 102 engineering-to-engineering relationships. With AWP, this figure rose to 550—an increase of 5.39 times—due to the following factors:
  • Segmentation of engineering deliverables by CWA;
  • Introduction of ENG-IF (Engineering Interface) activities to coordinate replicated deliverables across CWPs;
  • Addition of IEWP (Issuance of Engineering Work Package) activities that structure the design completion status per EWP.
  • Engineering-to-Procurement Relationships:
The Traditional schedule contained 22 engineering-to-procurement relationships, which were implemented via interface activities. These interface activities exist on both the engineering and procurement side of the schedule, so the actual number of logical connections between engineering and procurement activities can be interpreted as approximately 11.
In contrast, AWP explicitly models 40 engineering-to-procurement relationships based on material groupings and CWA alignment. This is nearly four times higher than the actual interdependency count in the Traditional schedule, highlighting the granularity introduced by AWP.
  • Engineering-to-Construction Relationships:
Similarly, the Traditional schedule includes 174 connections between engineering and construction. However, about 87 of these represent mirrored interface activities on each side, meaning that only half reflect true logical dependencies.
AWP replaces interface activities with IEWPs nodes, which serve as centralized coordination points. AWP-M1 and M2 shows 96 and 70 IEWP → CON relationships, respectively, which is similar in magnitude to the relationships in the Traditional schedule but offers better modularity and traceability.
  • Procurement-to-Procurement Relationships:
Procurement-to-procurement dependencies increased from 22 to 80, a 3.64× rise, due to the breakdown of bulk material activities by CWA.
  • Procurement-to-Construction Relationships:
Procurement-to-construction relationships decreased from 74 (Traditional) to 40 (AWP). Again, if half of Traditional connections are interpreted as mirrored interfaces, then the effective connection count is 37—roughly equivalent to AWP’s explicit 40 dependencies.
  • Construction-to-Construction Relationships:
Construction-to-construction links increased modestly from 193 to 214 in AWP models (1.11×), mainly due to the further segmentation of previously common or building-wide activities into CWA-specific tasks.
This increase in the number of relationships does not merely indicate added complexity, but rather reflects a more detailed and structured planning approach enabled by AWP. The rise in relationship volume demonstrates improved modeling of dependencies between tasks at the work package level. These enhanced linkages support better workface readiness, enable modularized execution, and establish clearer handover structures. Consequently, they contribute to improved schedule reliability and greater alignment between planning and field execution.

4.4.4. Delay Simulation and Mitigation Effectiveness

To quantitatively assess the schedule-level benefits of applying the AWP framework, construction productivity and workface planning adjustments were introduced into the baseline schedules.
Table 19 presents the comparison between the traditional schedule and the AWP-applied schedule under the assumption of a 25% improvement in construction productivity and the implementation of a 90-day lead time requirement for engineering deliverables prior to field execution. This adjustment was applied to both AWP-M1 and AWP-M2 schedules, and the resulting project finish dates were compared against the traditional baseline schedule.
This result demonstrates that, even with the imposition of a 90-day buffer requirement before CWP execution, the 25% productivity gain led to a net schedule improvement of 60 days. This highlights AWP’s potential to accelerate overall project completion when workface planning is systematically implemented in conjunction with construction zone alignment and early deliverable readiness.
In scenario ①, a 360-day delay was introduced individually to selected engineering activities across disciplines. These delays were applied directly to the designated activities and not at the IEWP level. In the traditional schedule, the critical path initially ran through RCB-related construction activities and remained unchanged even after the delays—the impacted activities extended the overall duration without shifting the path logic.
However, in both AWP-M1 and AWP-M2 schedules, where the initial critical path also passed through RCB-related construction, the same delays led to a shift in the critical path toward the delayed activities located in CWA2. This shift was observed as shown in Table 20:
  • 320C118PI, 320E145PI, and 320P193PI: The delays caused the critical path to move from RCB-related construction to activities in CWA2.
  • In the case of 310E145PI, while the traditional schedule had a direct link from engineering to overall construction, the AWP schedules restructured the sequence such that engineering delay propagated through procurement and construction, particularly through the cable tray activity chain in CWA2.
Other activities like 310J159PI and 320J159PI showed no delay impact and stayed outside the critical path in all scenarios.
When the lead time was reduced—allowing for a 30-day float within the IEWP preparation buffer—all delay-impacted scenarios showed a corresponding 30-day recovery. This demonstrated that the AWP framework’s segmentation and buffering capability can absorb localized delays when managed appropriately, offering resilience against schedule disruptions.
In Scenario ②, the same set of discipline-specific activities used in Scenario ① were restructured and grouped into EWPs, with the corresponding 360-day delays applied at the I-EWP. This scenario aimed to test whether the AWP structure’s logical segmentation and re-sequencing flexibility could mitigate delays more effectively under a centralized delay input.
The results, summarized in Table 21, revealed the following patterns:
  • RCB-zone delays (I-EWP10, I-EWP27):
    These elements, associated with single-zone execution in the RCB, showed no recovery after re-sequencing, as there were no alternative packages or CWAs with the same work types scheduled earlier or in parallel. The lack of flexibility in spatial and temporal overlap restricted mitigation.
  • CWA2-zone delays (I-EWP41, I-EWP57 in M1; I-EWP31, I-EWP44 in M2):
    These were able to make significant delay mitigation through re-sequencing.
    For instance, 23 days to 74 days reduction after re-sequencing.
    This was possible due to the availability of follow-up CWAs (e.g., CWA3, CWA4, CWA5) with similar work scopes that allowed flexible scheduling.
  • Non-impacted or high-float activities (I-EWP16, 24, 46, 52 for M1; I-EWP13, 21, 35, 40 for M2):
    These showed no schedule impact due to adequate float or already being outside the critical path.
Overall, Scenario ② demonstrated that the AWP structure’s segmentation by CWAs and the flexibility of I-EWPs support delay mitigation through workface-level re-sequencing, particularly in areas with overlapping or sequential work packages.
These findings highlight the importance of spatial redundancy and float buffering in AWP planning, especially for disciplines executed across multiple CWAs.

5. Discussion

  • The results indicate that AWP-based configurations exhibit higher schedule resilience than traditional CPM logic, particularly through robustness against early engineering delays and rapidity of recovery via IWP re-sequencing [14,15].
  • The assumption of a 25% construction-productivity uplift is a simplification. It was adopted as a literature-based scenario value to enable transparent comparison and does not represent trade- or site-specific measurements. Future studies should calibrate differentiated uplifts (e.g., concrete, rebar, MEI) using validated field data or formal meta-analysis.
  • Procurement effects were represented deterministically through their intermediate placement between engineering and construction, rather than through stochastic risk distributions. This simplification may understate uncertainty, and probabilistic procurement-risk modeling should be considered in future work.
  • The hypothetical model represents 22–28% of referenced plant volume. While the structure was derived from standardized FSAR data to preserve plausibility, no sensitivity runs were performed. As the study’s purpose was comparative, not predictive, results should be interpreted as relative responses. The model was physically simplified and scaled down to serve the needs of a preliminary study, which included treating the RCB as a single construction zone. Accordingly, future research should validate zone-level segmentation against complete, real NPP project schedules where data are accessible.
  • The reported 60-day net improvement is a deterministic result derived from fixed scenario logic. Because no probabilistic sampling was conducted, no confidence interval or p-value can be provided. This value should therefore be interpreted as illustrative of structural schedule effects, not as a statistically validated result. Future research should apply stochastic risk analysis to test the statistical robustness of such improvements.
  • Commissioning and regulatory gates were not included due to scope and confidentiality. However, research is emerging on how AWP may be applied in commissioning, particularly on reconciling physical packages used in construction with system-level packages required for system turnover. This represents a future extension of the current study.
  • While this study concentrated on schedule-level impacts, the adoption of AWP also requires procedural, administrative, and system changes across design, procurement, and project management processes. These adjustments inevitably involve additional time and cost, which were not analyzed here. ROI should therefore not be inferred from schedule benefits alone. Future research should extend the analysis to include these broader dimensions, so that cost–benefit trade-offs are evaluated in a comprehensive manner.
  • The weighting applied in Table A2 was developed by the first and corresponding author, both with 10–20 years of project management experience, and then informally cross-checked with a small group of senior practitioners. Because direct AWP implementation experience in nuclear projects is not yet available, no inter-rater reliability testing was possible. This is recognized as a limitation, and future work should validate such weighting through structured expert panels and reliability methods.
  • This study applied deterministic, step-wise delays in order to compare schedule-structure responses under controlled conditions. The use of standardized nuclear project schedule data made deterministic testing more suitable than probabilistic sampling. While this approach was appropriate for a preliminary comparison, it does not provide delay distributions or confidence intervals. Future studies should apply stochastic methods such as Monte Carlo or PERT to complement the findings and validate statistical robustness.
  • NPP schedules are highly sensitive to external uncertainties, including policy changes, regulatory approval processes, and supply chain disruptions. These factors were not quantified in this study, as the analysis focused on deterministic, comparative scenarios to illustrate AWP-specific effects. Nonetheless, such uncertainties exert significant influence on actual project performance. Future studies should extend the analysis to incorporate probabilistic schedule risk assessments (e.g., Monte Carlo approaches), so that the impact of policy, regulatory, and supply chain risks can be evaluated in a more comprehensive manner.
  • As authors’ best knowledge, no published nuclear power project has reported full-scale application of AWP. International references remain at the level of conceptual proposals or emerging contractual requirements rather than validated case studies. In several recent projects, owners have signaled an interest in incorporating AWP principles into execution planning. Against this backdrop, the present work is positioned as a preliminary study to provide a first step toward evaluating the potential of AWP in nuclear construction.

6. Conclusions, Limitations, and Recommendations

6.1. Conclusions

This study investigated the application of Advanced Work Packaging (AWP) to nuclear power plant (NPP) construction scheduling, contrasting it with the Korean traditional practices. Key conclusions are as follows:
  • In evaluating four packaging schemes against six criteria (scope definition, WBS compatibility, schedule-unit suitability, fit with schedule hierarchy, constructability, and progress measurement), Methods 1 and 2 consistently scored 4–5 and were advanced. Method 1 uniquely earned top marks for “EWP as a Schedule Unit” and “Progress Measurement by EWP,” because FBS-based EWPs are self-contained and auditable and pair cleanly with equipment-type PWPs. Method 2 uniquely earned top marks for “EWP Compatibility with Schedule Hierarchy,” as discipline-based EWPs map directly to the OBS within the WBS. By contrast, Methods 3–4 were not advanced: both exhibit PWP configurations that conflict with PO lifecycles (composition and process), demand supplementary activity relationships and field-requested-date plans, and require management plans at equipment-level traceability; in addition, Method 3’s procurement-phase split introduces temporal overlap that further fragments schedule units and progress measurement.
  • WBS Structure and Work Packaging: Traditional WBS structures varied by EPC phase (contract-based, discipline-based, package-based, etc.), creating challenges for integrated management and reporting. By contrast, the AWP-based WBS consistently followed: Project → CWA → Phase (E/P/C) → Discipline (OBS) → WP. This structure expanded work packages from 48 (traditional) to 202 (AWP-M1) and 163 (AWP-M2), with engineering deliverables standardized at 940. The increase is explained by CWA-level scoping that replicates discipline deliverables by area; this improves area-based traceability and reporting but raises management complexity due to package proliferation.
  • Schedule Activities and Relationships: AWP schedules significantly expanded activities compared to the traditional baseline.
    Engineering (AE/BOP) increased 6.6×, and NSSS/RCB about 1.8×, due to CWA segmentation and replicated activities.
    Procurement activities increased almost 4× (33 → 120) as previously common items were allocated to CWAs.
    Construction activities showed minor increases since traditional schedules already applied area-based planning.
    Relationships expanded substantially: ENG–ENG links increased 5.4×, and ENG–PRO nearly 2×. Traditional interface activities (281) disappeared, replaced by IEWP and ENG-IF logic, providing stronger integration across phases.
  • Schedule Impacts: Applying a 25% construction productivity improvement shortened durations by about 120 days, while the 90-day lag for EWP issuance included 60 days of readiness for IWP development, which offset part of the gains. The net outcome was a 60-day earlier project completion compared to the traditional baseline.
  • Delay Simulation and Mitigation: In Scenario ① (360-day engineering delays), the traditional critical path remained in RCB-related construction, while AWP shifted the critical path toward delayed activities in CWA2, demonstrating segmentation-driven responsiveness. In Scenario ② (re-sequencing), substantial recovery was observed in successive CWAs (e.g., I-EWP41 mitigated 23 days, I-EWP57 recovered 74 days). These results confirm that AWP’s zonal structure enables localized delay absorption when alternative workfaces exist. Recovery concentrated in the AB because spatial redundancy across adjacent CWAs enabled parallel advancement of similar work types, whereas the RCB’s contiguous, critical structural scope offered few viable substitutes.
  • These conclusions should be interpreted with caution, as they are derived from a simplified, scaled model of the Nuclear Island, applied under generalized productivity and lead-time assumptions, with delays treated deterministically. While sufficient for a preliminary study, these boundaries limit direct generalization to full-scale NPP projects.

6.2. Limitations

  • Simplified Modeling Assumptions: The schedules developed in this study relied on a simplified standard work logic and assumptions rather than fully reflecting the detailed complexities of an actual project. For example, construction productivity was adjusted uniformly by 25%, and 90-day engineering/procurement lead time were modeled in a generalized manner. Such simplifications limit the direct applicability of the results to real projects, where variability and uncertainty are more pronounced. Furthermore, the AWP-based WBS was structured around CWAs, EWPs, PWPs, and CWPs in accordance with industry guidelines. However, not all possible variations of work package configurations were considered. For instance, procurement strategies were simplified by excluding detailed vendor-specific practices and fabrication steps that could significantly influence the applicability.
  • Limited Risk Coverage: The delay simulations were designed around selected engineering activities across disciplines. While effective for comparative analysis, they did not incorporate the broader range of risks that typically affect nuclear projects, such as regulatory reviews, vendor-related delays, or site-specific conditions. The mitigation effects observed should therefore be interpreted within this limited scope.
  • Re-Sequencing Assumptions: In this study, Scenario ② re-sequencing was applied only to AWP schedules, under the assumption that such adjustments are uniquely aligned with WFP practices. However, in reality, similar resequencing and adjustments are also carried out in traditional project execution once construction readiness allows. This limitation may have led to an overestimation of the differential benefit attributed solely to AWP.

6.3. Recommendations for Future Research

  • Detailed Schedule Development: Current industry practice using Level 3 IPS (Integrated Project Schedule) or CPS (Critical Path Schedule) provides activity relationships but lacks the level of granularity required for accurate critical path analysis. Future research should develop model-based detailed schedules in which CWAs, POCs and IWPs are explicitly linked to 4D/5D BIM objects, enabling higher-precision critical path monitoring, quantity-driven progress validation, and automated look-ahead generation.
  • Stakeholder Engagement at Project Initiation: Successful AWP implementation requires active involvement of procurement and construction stakeholders from the project outset. Future research should investigate contractual and procedural approaches that move away from the traditional reliance on fixed interface activities, enabling earlier alignment of deliverables and responsibilities.
  • FOAK (For first of a kind) Considerations: Adopting AWP in FOAK settings requires rethinking how engineering deliverables, procurement packages, and construction packages are defined. Packages should be BIM-addressable from the start of the project (e.g., derive the Path of Construction from the model; tie fabrication lots to model assemblies). Future work should also assess the practical and business impacts on EPC delivery—such as data governance, change control, and traceability.

6.4. Contributions of the Study

This research contributes to both academia and industry in the following ways:
  • Applying the AWP Project Definition Assessment Tool to a Korean nuclear EPC context, identifying current alignment and gaps.
  • Demonstrating a practical methodology for constructing AWP-based schedules and comparing them against traditional schedules using Primavera P6.
  • Quantitatively analyzing differences in work packages, deliverables, activities, and relationships, clarifying the impacts of AWP adoption.
  • Testing delay simulation scenarios, showing how AWP segmentation and re-sequencing provide resilience to schedule disruptions.
  • Offering practical recommendations on WBS standardization, tool integration, risk-driven planning, and FOAK implications, bridging theoretical research with industrial application.
Ultimately, this study shows that adopting AWP in NPP construction schedules can enhance consistency, traceability, and resilience, while also highlighting the challenges and research directions needed for successful implementation.

Author Contributions

Conceptualization, D.C. and W.J.; methodology, D.C.; software, D.C.; validation, W.J.; formal analysis, D.C.; investigation, D.C. and W.J.; resources, D.C. and W.J.; data curation, D.C.; writing—original draft preparation, D.C.; writing—review and editing, D.C. and W.J.; visualization, D.C.; supervision, W.J.; project administration, W.J.; funding acquisition, W.J. All authors have read and agreed to the published version of the manuscript.

Funding

This research was supported by the 2025 Research Fund of the KEPCO International Nuclear Graduate School (KINGS), the Republic of Korea and by the Korea Agency for Infrastructure Technology Advancement (KAIA) grant funded by the Ministry of Land, Infrastructure and Transport (Grant No. RS-2025-02220317).

Data Availability Statement

The original contributions presented in the study are included in the article. Further inquiries can be directed to the corresponding authors.

Conflicts of Interest

The authors declare no conflicts of interest.

Abbreviations

ABAuxiliary Building
AWPAdvanced Work Packaging
AWP-M1Advanced Work Packaging Method 1
AWP-M2Advanced Work Packaging Method 2
BIMBuilding Information Modeling
CIConstruction Issue
CIIConstruction Industry Institute
COAAConstruction Owners Association of Alberta
CPConstruction Package
CPMCritical Path Method
CWAConstruction Work Area
CWPConstruction Work Package
EPCEngineering, Procurement, and Construction
EWPEngineering Work Package
FBSFunctional Breakdown Structure
FSARFinal Safety Analysis Report
IEWPIssuance of Engineering Work Package
ITTInvitation to Tender
IWPInstallation Work Package
NPPNuclear Power Plant
OBSOrganizational Breakdown Structure
PBSPhysical Breakdown Structure
PIPreliminary Issue
POPurchase Order
POCPath of Construction
PWPProcurement Work Package
R&AReview & Approval
RCBReactor Containment Building
RVReactor Vessel
VDVendor Data
WBSWork Breakdown Structure
WFPWorkface Planning

Appendix A

Appendix A.1. Work Breakdown Structures

Figure A1. Structure of the traditional WBS.
Figure A1. Structure of the traditional WBS.
Applsci 15 11113 g0a1
Figure A2. WBS example of AWP-based NPP project WBS.
Figure A2. WBS example of AWP-based NPP project WBS.
Applsci 15 11113 g0a2

Appendix A.2. Work Packaging Alternatives

Figure A3. Work Packaging Method 1.
Figure A3. Work Packaging Method 1.
Applsci 15 11113 g0a3
Figure A4. Work Packaging Method 2.
Figure A4. Work Packaging Method 2.
Applsci 15 11113 g0a4
Figure A5. Work Packaging Method 3.
Figure A5. Work Packaging Method 3.
Applsci 15 11113 g0a5
Figure A6. Work Packaging Method 4.
Figure A6. Work Packaging Method 4.
Applsci 15 11113 g0a6

Appendix A.3. Advanced Work Packaging (AWP) Assessment Criteria

The assessment criteria for selecting the optimal EWP and PWP structuring method were established by synthesizing proven industry guidelines and research literature (Key references: [7,11,13,16,23]). Selected criterions were weighted by importance, and each packaging method was scored on a 0–5 scale.
Table A1. Advanced Work packaging assessment criteria.
Table A1. Advanced Work packaging assessment criteria.
No.CriteriaDescriptionImportanceWeight
(%)
Scoring Criteria
Planning 805: Fully Compliant; The criterion is fully met. The implementation is highly effective, and aligns perfectly with best practices.

4: Largely Compliant; The criterion is largely met. While minor improvements may be needed, the implementation is generally effective and well-established.

3: Partially Compliant; The criterion is partially met. The application presents significant gaps certain areas.

2: Minimally Compliant; The criterion is minimally met. Minor efforts have been made, but the actual application level is very low.

1: Not Compliant (Concept Acknowledged); The concept of the evaluation criterion is known, but there is no structured or concrete effort to apply it.

0: Not Addressed; There is no awareness of this criterion, and no attempt has been made to apply it.

N/A: Not applicable for this assessment
1Scope Definition of EWPThe package is defined by a specific scope of work and has clear boundaries, leaving no room for scope disputes.Medium8
2Scope Definition of PWPThe package is defined by a specific scope of work and has clear boundaries, leaving no room for scope disputes.Medium8
3WBS Compatibility of EWPEWP structure is compatible with the project’s WBS hierarchy.Medium8
4WBS Compatibility of PWPPWP structure is compatible with the project’s WBS hierarchy.Medium8
5EWP as a Schedule UnitEWP structure is suitable as a unit within the schedule.Low6
6PWP as a Schedule UnitPWP structure is suitable as a unit within the schedule.Low6
7EWP Compatibility with Schedule HierarchyThe EWP schedule is structured at an appropriate level and aligns with the schedule hierarchy.Medium8
8PWP Compatibility with Schedule HierarchyThe PWP schedule is structured at an appropriate level and aligns with the schedule hierarchy.Medium8
9Constructability of EWPEWPs align with and support the construction sequence defined in the POC.High10
10Constructability of PWPPWPs align with and support the construction sequence defined in the POC.High10
11Support for IWPs by EWPEWP’s information is detailed enough to be easily broken down into IWPs, the smallest unit of field work.N/A-
12Support for IWPs by PWPPWP’s material list accurately tracks items needed for an IWP and clearly indicates how they should be distributed to the field.N/A-
13Completeness of Engineering Information in EWPEWP includes all necessary and up-to-date information for work execution, such as drawings, specifications, and vendor drawings.N/A-
14Procurement Readiness of PWPPWP is structured to ensure all necessary materials are planned for procurement, have a delivery schedule, and are confirmed to be on-site when needed.N/A-
15Level of Detail of EWPEWP drawings include detailed dimensions, installation methods, and material information that can be easily understood by a craft worker.N/A-
16Level of Detail of PWPPWP’s material distribution plan clearly specifies which IWP each material should be delivered to.N/A-
Execution -
17Prerequisite CompletionAll prerequisite tasks are complete before the work in the package can begin.N/A-
18Material and Equipment ReadinessAll materials, equipment, tools, and personnel required for the package are available at the job site.N/A-
19Field ProductivityAbility of the CWP structure to reduce idle time for workers and improve direct work productivityN/A-
20Rework MinimizationPrevent rework caused by incomplete or inaccurate information.N/A-
21EWP Operational ComplexityIntuitiveness and ease of management for EWP structuresN/A-
22PWP Operational ComplexityIntuitiveness and ease of management for PWP structuresN/A-
Monitoring/Control 20
23Progress Measurement by EWPEWP progress measured based on quantitative completion criteria, with the results linked to the higher-level schedule to ensure overall project visibility and ease of management.High10
24Progress Measurement by PWPPWP progress measured based on quantitative completion criteria, with the results linked to the higher-level schedule to ensure overall project visibility and ease of management.High10
25Controllability of EWPEWP controllable to ensure stable project execution by systematically managing and responding to changes, constraints, and potential risks.N/A-
26Controllability of PWPPWP controllable to ensure stable project execution by systematically managing and responding to changes, constraints, and potential risks.N/A-
Methods 1 and 2 achieved the highest applicability scores (93.6%, 92.0%), confirming suitability for further schedule development steps.
Table A2. Advanced work packaging assessment matrix.
Table A2. Advanced work packaging assessment matrix.
No.CriteriaMethod 1Method 2Method 3Method 4
ScoreRationaleScoreRationaleScoreRationaleScoreRationale
1Scope Definition of EWP5Discipline/function-based packaging; sub-discipline and function specific range of work.5Discipline-based packaging; discipline specific range of work.3Discipline/phase-based packaging; discipline specific range of work; may require overlapping phases of work5Discipline-based packaging; discipline specific range of work.
2Scope Definition of PWP5Type-based packaging5Type-based packaging3Discipline (Multi-material type)/phase-based packaging; compatibility with PO & process needed.4Discipline (Multi-material type)-based packaging; compatibility with PO needed.
3WBS Compatibility of EWP5Aligns with WBS hierarchy.5Aligns with WBS hierarchy.4Can align with WBS hierarchy; but duplicated functions required5Aligns with WBS hierarchy.
4WBS Compatibility of PWP5Aligns with WBS hierarchy.5Aligns with WBS hierarchy.4Can align with WBS hierarchy; but duplicated types required5Aligns with WBS hierarchy.
5EWP as a Schedule Unit5Compliant as an independent schedule unit; may require supplementary activity relationships.4Compliant as an independent schedule unit; but require supplementary activity relationships.3Compliant as an independent schedule unit; but require supplementary activity relationships and overlapping for phased functions.4Compliant as an independent schedule unit; but require supplementary activity relationships.
6PWP as a Schedule Unit4Compliant as an independent schedule unit; may require supplementary activity/relationship; require a separate plan for field-requested dates4Compliant as an independent schedule unit; may require supplementary activity/relationship; require a separate plan for field-requested dates3Compliant as an independent schedule unit; require supplementary activity/relationship; require a separate plan for field-requested dates; overlap in phased procurement; require compatibility with PO.3Compliant as an independent schedule unit; require supplementary activity/relationship; require a separate plan for field-requested dates; require compatibility with PO.
7EWP Compatibility with Schedule Hierarchy4Appropriate and align with WBS hierarchy; but may generate an extensive number of work packages5Appropriate and align with WBS hierarchy.3Appropriate and align with WBS hierarchy; but may generate an extensive number of work packages as the phases increase5Appropriate and align with WBS hierarchy.
8PWP Compatibility with Schedule Hierarchy4Appropriate and align with WBS hierarchy; but may have extensive number of work packages4Appropriate and align with WBS hierarchy; but may have extensive number of work packages3Appropriate and align with WBS hierarchy; but may generate an extensive number of work packages as the phases increase; require compatibility with PO.4Appropriate and align with WBS hierarchy; require compatibility with PO.
9Constructability of EWP5Align with and support the POC5Align with and support the POC5Align with and support the POC5Align with and support the POC
10Constructability of PWP4Align with and support the POC; however, a separate material delivery management plan is needed to prevent a large amount of inventory from being stored on-site for a long period.4Align with and support the POC; however, a separate material delivery management plan is needed to prevent a large amount of inventory from being stored on-site for a long period.3Align with and support the POC; separate material delivery management plan is needed to prevent a large amount of inventory from being stored on-site for a long period; require compatibility with PO.3Align with and support the POC; separate material delivery management plan is needed to prevent a large amount of inventory from being stored on-site for a long period; require compatibility with PO.
11Progress Measurement by EWP5Measurable.4Measurable; but require separate plan to track specific tasks4Measurable; but require separate plan to track specific tasks4Measurable; but require separate plan to track specific tasks
12Progress Measurement by PWP5Measurable.5Measurable.3Measurable; but require separate plan to track specific tasks; require compatibility with PO.3Measurable; but require separate plan to track specific tasks; require compatibility with PO.
Score total
/Converted Score
56/93.6%55/92%41/69.2%50/83.2%

Appendix A.4. Scheduling Assumptions

Table A3. Selected engineering FBS for the model.
Table A3. Selected engineering FBS for the model.
DisciplineFBS No. *Description
All/Common4XXSystem design criteria
C1XXStructural drawing
1XXLiner plate drawing
1XXStructure detail drawing
2XXSpecification-reinforcing steel bar
2XXSpecification-containment liner plates
2XXSpecification-ready mixed concrete
3XXStructural analysis
3XXLiner plate calculation
E1XXSingle line diagram
1XXCable tray drawing
1XXConduit plan drawing
2XXSpecification-cables
2XXSpecification-cable trays and fittings
J1XXC&ID
1XXInstrument location drawing
2XXSpecification-instruments
M1XXP&ID
2XXSpecification-pumps
2XXSpecification-crane
NSSSSpecification-nsss equipment
1XXP&ID
P1XXPiping support drawing
1XXGeneral arrangement drawing
1XXPiping iso drawing
2XXSpecification-piping
2XXSpecification-valves
3XXPiping stress analysis
* All FBS numbers are replaced with “X” for confidentiality.
Table A4. Selected PO for the model.
Table A4. Selected PO for the model.
PO *Description
CXXXReinforcing steel bar
CXXXReady mixed concrete
CXXXContainment liner plates
MXXXPumps
MXXXHoists & cranes
NSSSNSSS equipment
PXXXValves
PXXXPiping
JXXXInstruments
EXXXCable trays and fittings
EXXXCables
* All PO numbers are replaced with “X” for confidentiality.
Table A5. Selected CP and activity type for the model.
Table A5. Selected CP and activity type for the model.
CP *DescriptionActivity Type *Description
CP-AXMajor building and
Related structure
AXBasemat & slab
AXWall & column
AXSteel liner plate
CP-PXPiping workPXPipe & support
CP-EXCable trayEXCable tray & support
CP-EXCabling and terminationEXCabling & termination
CP-JXInstrument and
Control installation
JXInstrument and
Control installation
* Part of the numbers are replaced with “X” for confidentiality.
Table A6. Engineering (FBS)-to-Procurement (PO) relationships.
Table A6. Engineering (FBS)-to-Procurement (PO) relationships.
BLDGSys.PredecessorSuccessor *
RCBABOBSFBS *DESCRIPTIONCXXXCXXXCXXXMXXXMXXXNSSSPXXXPXXXJXXXEXXXEXXX
OO PXXXGENERAL ARRANGEMENT DRAWINGO OOOOOOOOO
OOOAllXXXSYSTEM DESIGN CRITERIA
XOOMXXXP&ID O OOO
OXONXXXP&ID O O
OO PXXXPIPING STRESS ANALYSIS
OO PXXXPIPING ISO DRAWING O OOOO
OO PXXXPIPING SUPPORT DRAWING OO
OO CXXXSTRUCTURAL ANALYSIS
OO CXXXSTRUCTURAL DRAWINGO OOO
OO CXXXSTRUCTURE DETAIL DRAWINGO OOO
OX CXXXLINER PLATE CALCULATION
OX CXXXLINER PLATE DRAWING O
OOOEXXXSINGLE LINE DIAGRAM OO
OO EXXXCABLE TRAY DRAWING OO
OO EXXXCONDUIT PLAN DRAWING OO
OOOJXXXC&ID O
OO JXXXINSTRUMENT LOCATION DRAWING O
OO CXXXSPECIFICATION-REINFORCING STEEL BARO
OO CXXXSPECIFICATION-READY MIXED CONCRETE O
OX CXXXSPECIFICATION-CONTAINMENT LINER PLATES O
XO MXXXSPECIFICATION-PUMPS O
OX MXXXSPECIFICATION-CRANE O
OX MXXXSPECIFICATION-NSSS EQUIPMENT O
XO PXXXSPECIFICATION-VALVES O
OO PXXXSPECIFICATION-PIPING O
OO JXXXSPECIFICATION-INSTRUMENTS O
OO EXXXSPECIFICATION-CABLE TRAYS AND FITTINGS O
OO EXXXSPECIFICATION-CABLES O
* Part of the numbers are replaced with “X” for confidentiality.
Table A7. Engineering (FBS)-to-Construction (CP/type) relationships.
Table A7. Engineering (FBS)-to-Construction (CP/type) relationships.
BLDGSys.PredecessorSuccessor *
RCBABOBSFBS *DescriptionCXCXSXPXEXEXEXJXMXMX
OO PXXXGENERAL ARRANGEMENT DRAWING
OOOAllXXXSYSTEM DESIGN CRITERIA
XOOMXXXP&ID
OXONXXXP&ID
OO PXXXPIPING STRESS ANALYSIS
OO PXXXPIPING ISO DRAWING O OO
OO PXXXPIPING SUPPORT DRAWING O OO
OO CXXXSTRUCTURAL ANALYSIS
OO CXXXSTRUCTURAL DRAWINGOO
OO CXXXSTRUCTURE DETAIL DRAWINGOO
OX CXXXLINER PLATE CALCULATION
OX CXXXLINER PLATE DRAWINGOOO
OOOEXXXSINGLE LINE DIAGRAM
OO EXXXCABLE TRAY DRAWING OO O O
OO EXXXCONDUIT PLAN DRAWINGO OO
OOOJXXXC&ID
OO JXXXINSTRUMENT LOCATION DRAWING O
OO CXXXSPECIFICATION-REINFORCING STEEL BAROO
OO CXXXSPECIFICATION-READY MIXED CONCRETEOO
OX CXXXSPECIFICATION-CONTAINMENT LINER PLATES O
XO MXXXSPECIFICATION-PUMPS O
OX MXXXSPECIFICATION-CRANE O
OX MNSSSSPECIFICATION-NSSS EQUIPMENT O
XO PXXXSPECIFICATION-VALVES O
OO PXXXSPECIFICATION-PIPING O
OO JXXXSPECIFICATION-INSTRUMENTS O
OO EXXXSPECIFICATION-CABLE TRAYS AND FITTINGS OO
OO EXXXSPECIFICATION-CABLES O
* Part of the numbers are replaced with “X” for confidentiality.
Table A8. Procurement (PO)-to-Construction (CP/type) relationships.
Table A8. Procurement (PO)-to-Construction (CP/type) relationships.
BLDGSys.PredecessorSuccessor *
RCBABOBSFBS *DESCRIPTIONCXCXSXPXEXEXEXJXMXMX
OO CXXXSPECIFICATION-REINFORCING STEEL BAROO
OO CXXXSPECIFICATION-READY MIXED CONCRETEOO
OX CXXXSPECIFICATION-CONTAINMENT LINER PLATES O
XO MXXXSPECIFICATION-PUMPS O
OX MXXXSPECIFICATION-CRANE O
OX MNSSSSPECIFICATION-NSSS EQUIPMENT O
XO PXXXSPECIFICATION-VALVES O
OO PXXXSPECIFICATION-PIPING O
OO JXXXSPECIFICATION-INSTRUMENTS O
OO EXXXSPECIFICATION-CABLE TRAYS AND FITTINGS OO
OO EXXXSPECIFICATION-CABLES O
* Part of the numbers are replaced with “X” for confidentiality.
Figure A7. Example of traditional NPP activity relationships.
Figure A7. Example of traditional NPP activity relationships.
Applsci 15 11113 g0a7
Figure A8. Simplified traditional NPP activity relationships.
Figure A8. Simplified traditional NPP activity relationships.
Applsci 15 11113 g0a8
Figure A9. Start/Finish Interface activities.
Figure A9. Start/Finish Interface activities.
Applsci 15 11113 g0a9
Figure A10. Start/Finish Interface activities when delayed.
Figure A10. Start/Finish Interface activities when delayed.
Applsci 15 11113 g0a10
Figure A11. Adoption of EWP Issuance.
Figure A11. Adoption of EWP Issuance.
Applsci 15 11113 g0a11
Table A9. Delay causing engineering activities for each schedule *.
Table A9. Delay causing engineering activities for each schedule *.
CWADiscFBSActivity ID
TraditionalAWP-M1AWP-M2
ABAB
1: RCBC1XX3XXC1XXPICWP01-EWP10-3XX1C1XXPII-EWP 10CWP01-EWP9-3XX1C1XXPII-EWP 9
E1XX3XXE1XXPICWP03-EWP16-3XX1E1XXPII-EWP 16CWP03-EWP13-3XX1E1XXPII-EWP 13
J1XX3XX1XXPICWP06-EWP24-3XX1J1XXPII-EWP 24CWP06-EWP21-3XX1J1XXPII-EWP 21
P1XX3XXP1XXPICWP07-EWP27-3XX1P1XXPII-EWP 27CWP03-EWP25-3XX1P1XXPII-EWP 25
2: ABC1XX3XXC1XXPICWP09-EWP41-3XX2C1XXPII-EWP 41CWP09-EWP31-3XX2C1XXPII-EWP 31
E1XX3XXE1XXPICWP00-EWP46-3XX2E1XXPII-EWP 46CWP00-EWP35-3XX2E1XXPII-EWP 35
J1XX3XXJ1XXPICWP12-EWP52-3XX2J1XXPII-EWP 52CWP12-EWP40-3XX2J1XXPII-EWP 40
P1XX3XXP1XXPICWP10-EWP57-3XX2P1XXPII-EWP 57CWP10-EWP44-3XX2P1XXPII-EWP 44
* Part of the numbers are replaced with “X” for confidentiality.
Table A10. Re-sequencing steps.
Table A10. Re-sequencing steps.
StepsRelationships
BaselineApplsci 15 11113 i001
Activities A → B → C follow a standard Finish-to-Start (FS) logic.
Delay OccurrenceApplsci 15 11113 i002
A delay in activity A causes a shift in B and C.
Re-SequencingApplsci 15 11113 i003
While activity A is delayed, activity B is advanced independently by resequencing the relationship, reducing the cumulative schedule impact.

Appendix A.5. Scheduled Artifacts

Figure A12. P6—Critical path of Traditional.
Figure A12. P6—Critical path of Traditional.
Applsci 15 11113 g0a12
Figure A13. P6—Critical path of AWP-M1.
Figure A13. P6—Critical path of AWP-M1.
Applsci 15 11113 g0a13
Figure A14. P6—Critical path of AWP-M2.
Figure A14. P6—Critical path of AWP-M2.
Applsci 15 11113 g0a14
Table A11. Traditional—Activity and deliverable quantities by WBS.
Table A11. Traditional—Activity and deliverable quantities by WBS.
WBS LevelQuantity of ActivitiesENG
Deliverable
Lev.2Lev.3Lev.4 AmountAE/BOPNSSS/RCBCommonInterfaceTotal
Milestone/Dummy--3-3-
ENGC85102425991
E5444162852
J344131229
M5241202786
P677217337
X1220044
Sum2824311098163269
PROC3-361726-
E2--61117-
J1--347-
M3-631322-
P2--61420-
Sum1109245992-
CONC(A)33623-50109-
E2176-2144-
J141-49-
M21611-2451-
P1165-2546-
Sum989460124259-
416481138637281517269
Table A12. AWP-M1-Activity and deliverable quantities by WBS.
Table A12. AWP-M1-Activity and deliverable quantities by WBS.
WBS LevelQuantity (Activities/IEWP/ENG-IF)ENG
Deliverable
Lev.2
CWA
Lev.3
Phase
Lev.4
OBS
Lev.5
WP
AE/BOPNSSS/RCBCommonTotal
Milestone/Dummy--33-
0ENGE22 (1/1/0)-3 (2/1/0)5 (3/2/0)3
J12 (2/0/0)3 (2/1/0)-5 (4/1/0)4
M22 (2/0/0)5 (3/2/0)-7 (5/2/0)5
X12 (2/0/0)3 (2/1/0)-5 (4/1/0)4
Sum68 (7/1/0)11 (7/4/0)3 (2/1/0)22 (16/6/0)16
PROE13--3-
M1-3-3-
Sum233-6-
CONE11--1-
Sum11--1-
Sum9121432916
1ENGC8-20 (12/8/-)-20 (12/8/-)66
E9-33 (16/9/8)-33 (16/9/8)100
J2-5 (3/2/-)-5 (3/2/-)15
M2-4 (2/2/-)-4 (2/2/-)93
P10-31 (15/10/6)-31 (15/10/6)2
Sum31-93 (48/31/14)-93 (48/31/14)276
PROC3-9-9-
E2-6-6-
J1-3-3-
M2-6-6-
P2-6-6-
Sum10-30-30-
CONA2-23-23-
E2-6-6-
J1-1-1-
M2-11-11-
P1-5-5-
Sum8-46-46-
Sum49-169-169276
2ENGC512 (7/5/-)--12 (7/5/-)27
E831 (15/8/8)--31 (15/8/8)71
J25 (3/2/-)--5 (3/2/-)11
M12 (1/1/-)--2 (1/1/-)52
P826 (12/8/6)--26 (12/8/6)1
Sum2476 (38/24/14)--76 (38/24/14)162
PROC26--6-
E13--3-
J13--3-
M13--3-
P26--6-
Sum721--21-
CONA19--9-
E14--4-
J14--4-
M14--4-
P14--4-
Sum525--25-
Sum36122--122162
3Same as CWA 2
Sum36122--122162
4Same as CWA 2
Sum36122--122162
5Same as CWA 2
Sum36122--122162
Total2025001836689940
Table A13. AWP-M2-Activity and deliverable quantities by WBS.
Table A13. AWP-M2-Activity and deliverable quantities by WBS.
WBS LevelQuantity (Activities/IEWP/ENG-IF)ENG
Deliverable
Lev.2
CWA
Lev.3
Phase
Lev.4
OBS
Lev.5
WP
AE/BOPNSSS/RCBCommonTotal
Milestone/Dummy--33-
0ENGE22 (1/1/0)-3 (2/1/0)5 (3/2/0)3
J123
(2/1/0)
-5 (4/1/0)4
M225
(3/2/0)
-7 (5/2/0)5
X123 (2/1/0)-5 (4/1/0)4
Sum68 (1/1/0)11 (7/4/0)3 (2/1/0)22 (16/6/0)16
PROE13--3-
M1-3-3-
Sum233-6-
CONE11--1-
Sum11--1-
Sum9121432916
1ENGC5-17 (12/5/0)-17 (12/5/0)66
E9-33 (16/9/8)-33 (16/9/8)100
J2-5 (3/2/0)-5 (3/2/0)15
M2-4 (2/2/0)-4 (2/2/0)93
P6-27 (15/6/6)-27 (15/6/6)2
Sum24-86
(48/24/14)
-86
(48/24/14)
276
PROC3-9-9-
E2-6-6-
J1-3-3-
M2-6-6-
P2-6-6-
Sum10-30-30-
CONA2-23-23-
E2-6-6-
J1-1-1-
M2-11-11-
P1-5-5-
Sum8-46-46-
Sum42-162-162276
2ENGC18 (7/1/0)--8 (7/1/0)27
E831 (15/8/8)--31 (15/8/8)71
J14 (3/1/0)--4 (3/1/0)11
M12 (1/1/0)--2 (1/1/0)52
P523 (12/5/6)--23 (12/5/6)1
Sum1668
(38/16/14)
--68
(38/16/14)
162
PROC26--6-
E13--3-
J13--3-
M13--3-
P26--6-
Sum721--21-
CONA19--9-
E14--4-
J14--4-
M14--4-
P14--4-
Sum525--25-
Sum28114--114162
3Same as CWA 2
Sum28114--114162
4Same as CWA 2
Sum28114--114162
5Same as CWA 2
Sum28114--114162
Total1634681766650940
Table A14. Schedule relationship comparison.
Table A14. Schedule relationship comparison.
Predecessor ⇒ SuccessorTraditional
Schedule (A)
AWP-M1 (B)AWP-M2 (C)
BB-AB/ACC-AC/A
ENG
⇒ ENG
ENG ⇒ ENG102144421.41144421.41
ENG ⇒ ENG-IF-123123-123123-
ENG ⇒ IEWP-136136-136136-
ENG-IF ⇒ ENG-123123-123123-
ENG-IF ⇒ ENG-IF-2424-2424-
Sum1025504485.395504485.39
ENG
⇒ PRO
ENG ⇒ PRO2240181.8240181.82
Sum2240181.8240181.82
ENG
⇒ CON
ENG ⇒ CON174-−174--−174-
IEWP ⇒ CON-9696-7070-
ENG-IF ⇒ CON-5757-5757-
Sum174153−210.88127−470.73
PRO
⇒ PRO
PRO ⇒ PRO2280583.6480583.64
Sum2280583.6480583.64
PRO
⇒ CON
PRO ⇒ CON7440−340.5440−340.54
Sum7440−340.5440−340.54
CON
⇒ CON
CON ⇒ CON193214211.11214211.11
Sum193214211.11214211.11
Total58910794901.8310534641.79

References

  1. Locatelli, G. Why Are Megaprojects, Including Nuclear Power Plants, Delivered Overbudget and Late? Reasons and Remedies; MIT-ANP-TR-172; Massachusetts Institute of Technology: Cambridge, MA, USA, 2018; pp. 5–21. [Google Scholar]
  2. Alsharif, S.; Karatas, A. A Framework for Identifying Causal Factors of Delay in Nuclear Power Plant Projects. Procedia Eng. 2016, 145, 1486–1487. [Google Scholar] [CrossRef]
  3. OECD Nuclear Energy Agency (NEA). Unlocking Reductions in the Construction Costs of Nuclear: A Practical Guide for Stakeholders; NEA No. 7530; OECD Publishing: Paris, France, 2020; p. 17. [Google Scholar]
  4. Hossen, M.M.; Kang, S.; Kim, J. Construction Schedule Delay Risk Assessment by Using Combined AHP-RII Methodology for an International Project. Nucl. Eng. Technol. 2015, 47, 376–378. [Google Scholar] [CrossRef]
  5. International Atomic Energy Agency (IAEA). Management of Nuclear Power Plant Projects; IAEA Nuclear Energy Series No. NG-T-1.6; IAEA: Vienna, Austria, 2020; pp. 75–108. [Google Scholar]
  6. CII/COAA. IR 272-2 Version 3.1 Vol.1: Advanced Work Packaging—Design Through Workface Execution; CII: Austin, TX, USA, 2013; pp. 1–5. [Google Scholar]
  7. CII/COAA. IR 272-2 Version 3.1 Vol.2: Advanced Work Packaging Implementation Guidance; CII: Austin, TX, USA, 2013; pp. 1–7, 81–83. [Google Scholar]
  8. CII/COAA. IR 272-2 Version 3.1 Vol.3: Advanced Work Packaging Implementation Case Studies and Expert Interviews; CII: Austin, TX, USA, 2013; pp. 1, 5–6. [Google Scholar]
  9. CII/COAA. IR 319-2: Validating Advanced Work Packaging as a Best Practice—A Game Changer; CII: Austin, TX, USA, 2015; pp. 15–18, 22–23. [Google Scholar]
  10. CII/COAA. RR 272-12: Advanced Work Packaging—From Project Definition through Site Execution; CII: Austin, TX, USA, 2013; pp. 9–35. [Google Scholar]
  11. CII/COAA. RR 319-11: Transforming the Industry—Advanced Work Packaging as a Standard (Best) Practice; CII: Austin, TX, USA, 2015; pp. 11–14. [Google Scholar]
  12. CII/COAA. RS 319-1: Making the Case for Advanced Work Packaging as a Standard (Best) Practice; CII: Austin, TX, USA, 2015; pp. 7–15. [Google Scholar]
  13. Hamdi, O. Advanced Work Packaging: Guide for Life Cycle Implementation; BookBaby: Pennsauken, NJ, USA, 2022; pp. 4–9. [Google Scholar]
  14. Huang, Z.-K.; Zeng, N.-C.; Zhang, D.-M.; Argyroudis, S.; Mitoulis, S.-A. Resilience Models for Tunnels Recovery After Earthquakes. Engineering 2025, in press. [CrossRef]
  15. Bruneau, M.; Chang, S.E.; Eguchi, R.T.; Lee, G.C.; O’Rourke, T.D.; Reinhorn, A.M.; Masanobu, S.; Kathleen, T.; William, A.W.; von Winterfeldt, D.; et al. A framework to quantitatively assess and enhance the seismic resilience of communities. Earthq. Spectra 2003, 19, 733–752. [Google Scholar] [CrossRef]
  16. Construction Industry Institute (CII). AWP Execution Planning Guide for Projects and Organizations. 2023. Available online: https://www.construction-institute.org/ (accessed on 17 June 2025).
  17. Hamdi, O. Advanced Work Packaging from Project Definition Through Site Execution: Driving Successful Implementation of Workface Planning. Master’s Thesis, University of Alberta, Edmonton, AB, Canada, 2013. Abstract. pp. 253–261. [Google Scholar]
  18. Halala, M.; Fayek, A.R. A Framework to Assess the Costs and Benefits of Advanced Work Packaging in Industrial Construction. Can. J. Civ. Eng. 2019, 46, 226–228. [Google Scholar]
  19. O’Connor, J.T.; Leite, F.; Ma, J.W. Expanding Advanced Work Packaging to Include Commissioning and Startup for Industrial Projects. Constr. Innov. 2022, 22, 939–960. [Google Scholar] [CrossRef]
  20. Guerra, B.C.; Leite, F. Bridging the Gap between Engineering and Construction 3D Models in Support of Advanced Work Packaging. J. Leg. Aff. Disput. Resolut. Eng. Constr. (ASCE) 2020, 12, 04520029. [Google Scholar] [CrossRef]
  21. Musarat, M.A.; Faisal, I.; Siddiq, M.Z.; Altaf, A.; Shah, F.; Zhou, Y.; Zhang, X. Advanced Work Packaging (AWP) Implementation and Challenges in the Malaysian Oil and Gas Sector. Sustainability 2024, 16, 1265. [Google Scholar] [CrossRef]
  22. Rebai, A.; Fakhfakh, N.; Ghedamsi, N. Barriers to Adopting Advanced Work Packaging (AWP) in Construction. Buildings 2024, 14, 1032. [Google Scholar] [CrossRef]
  23. Construction Owners Association of Alberta (COAA). EWP Readiness Playbook; COAA: Edmonton, AB, Canada, 2019; Available online: https://www.coaa.ab.ca/library/awp-ewp-readiness-playbook/ (accessed on 17 June 2025).
  24. Choo, D.; Jung, W. Advanced Work Package Application for Nuclear Construction Project: Review on the Work Breakdown Structure. In Proceedings of the Korean Nuclear Society (KNS) Spring Meeting, Jeju, Republic of Korea, 22–23 May 2025. [Google Scholar]
  25. Rebai, S.; Hamdi, O.; Lafhaj, Z.; Ouchala, H.; AlBalkhy, W. Comparative Analysis of AWP and IPD Methods: Strengths, Challenges, and Opportunities. Buildings 2025, 15, 2893. [Google Scholar] [CrossRef]
  26. Kim, S.; Choi, H.; Won, S.; Lim, B.; Son, H.; Lee, K.; Shin, I.; Yang, M.; Yang, J. Nuclear Power Plant Business Process Modeling and Procedure Management Method. Republic of Korea Patent KR 10-2015-0001923, 7 January 2015. pp. 3–4. [Google Scholar]
  27. Moon, B. A Study on the Application of EVMS to Nuclear PowerPlant Construction Project. Master’s Thesis, Soongsil University, Seoul, Republic of Korea, 2009; pp. 30–48, 73–74. [Google Scholar]
  28. Demetracopoulou, V.; Faust, K.I.; O’Brien, W.J. Benefits and Conditions for Successful Implementation of Advanced Work Packaging in Front-End Planning and Design. J. Leg. Aff. Disput. Resolut. Eng. Constr. 2025, 17, 04525055. [Google Scholar] [CrossRef]
  29. COAA/CII. Scalable Advanced Work Packaging Report (COP-SWP-PBP-01-2019-v1); COAA/CII: Edmonton, AB, USA; Austin, TX, USA, 2019. [Google Scholar]
  30. Project Management Institute (PMI). A Guide to the Project Management Body of Knowledge (PMBOK Guide), 7th ed.; PMI: Newtown Square, PA, USA, 2021.
  31. Korea Hydro & Nuclear Power Co., Ltd. (KHNP). Shin-Kori Units 3 and 4 Final Safety Analysis Report (FSAR), Chapter 1: General Plant Information, Revision 7; KHNP: Seoul, Republic of Korea, 2023. [Google Scholar]
Figure 1. Process for the comparative schedule analysis.
Figure 1. Process for the comparative schedule analysis.
Applsci 15 11113 g001
Figure 2. Hypothetical model of the nuclear island (sectional elevation and CWA1–5 area plan with POC).
Figure 2. Hypothetical model of the nuclear island (sectional elevation and CWA1–5 area plan with POC).
Applsci 15 11113 g002
Figure 3. Delay and mitigation analysis flowchart.
Figure 3. Delay and mitigation analysis flowchart.
Applsci 15 11113 g003
Figure 4. Modified AWP-WBS.
Figure 4. Modified AWP-WBS.
Applsci 15 11113 g004
Table 1. Dimensional assumptions for the hypothetical model.
Table 1. Dimensional assumptions for the hypothetical model.
ComponentParameterAPR1400 Reference *AWP Model *Scaling Ratio (%)
RCBRadius (r)0.00 m0.00 m65.22%
Area (A)0.00 m20.00 m243.06%
Height (S.L.)0.00 m0.00 m49.18%
Height (Dome)0.00 m0.00 m54.22%
Dome Volume0.00 m30.00 m328.26%
Total Volume (V)0.00 m30.00 m322.71%
ABWidth0.00 m0.00 m67.31%
Depth0.00 m0.00 m82.35%
Area (A)0.00 m20.00 m255.32%
Height0.00 m0.00 m43.48%
Total Volume (V)0.00 m30.00 m325.13%
* All dimensional values are replaced with “0” for confidentiality.
Table 2. Structural comparison of methods 1 to 4.
Table 2. Structural comparison of methods 1 to 4.
FeatureMethod 1Method 2Method 3Method 4
EWP groupingFBS
(horizontal)
Discipline
(horizontal + vertical)
Disc. + Phase (PI/CI)
(vertical)
Discipline
(horizontal + vertical)
PWP groupingEquipment type
(horizontal)
Equipment type
(horizontal)
Equipment by phase
(vertical)
Discipline
(horizontal + vertical)
Table 3. Traditional—Summary of activity and deliverable quantities by WBS.
Table 3. Traditional—Summary of activity and deliverable quantities by WBS.
WBS LevelQuantity of ActivitiesENG
Deliverable
Lev.2Lev.3Lev.4AE/BOPNSSS/RCBCommonInterfaceTotal
Milestone/Dummy--3-3-
ENG62824311098163269
PRO51109245992-
CON5989460124259-
416481138637281517269
Table 4. Key project milestones.
Table 4. Key project milestones.
MilestoneScheduled DateFrom Project Start
Project Start (D)2026.01.01D + 0 month
First Concrete2027.11.05D + 22 month
Set Reactor Vessel (RV)2028.12.09D + 35 month
Construction Completion2029.06.11D + 42 month
Table 5. Traditional-P6 relationships.
Table 5. Traditional-P6 relationships.
Predecessor–SuccessorRelationship TypeAmount
Milestone ⇒ CONFS2
ENG ⇒ ENGFS102
ENG ⇒ PROFS22
ENG ⇒ CONFS174
PRO ⇒ PROFS22
PRO ⇒ CONFS74
CON ⇒ CONSS8
FS178
FF7
589
Table 6. Score summary of the packaging assessment matrix.
Table 6. Score summary of the packaging assessment matrix.
MethodTotal ScoreConverted Score
Method 156/6093.6%
Method 255/6092.0%
Method 341/6069.2%
Method 450/6083.2%
Table 9. AWP-M1-P6 relationships.
Table 9. AWP-M1-P6 relationships.
Predecessor–SuccessorRelationship TypeAmount
Milestone ⇒ CONFS2
ENG ⇒ ENGFS144
ENG ⇒ IEWPFS136
ENG ⇒ ENG-IFFS123
ENG ⇒ PROFS40
IEWP ⇒ CONFS96
ENG-IF ⇒ ENGFS123
ENG-IF ⇒ ENG-IFFS24
ENG-IF ⇒ CONFS57
PRO ⇒ PROFS80
PRO ⇒ CONFS40
CON ⇒ CONSS8
FS187
FF19
1079
Table 10. AWP-M2-P6 relationships.
Table 10. AWP-M2-P6 relationships.
Predecessor–SuccessorRelationship TypeAmount
Milestone ⇒ CONFS2
ENG ⇒ ENGFS144
ENG ⇒ IEWPFS136
ENG ⇒ ENG-IFFS123
ENG ⇒ PROFS40
IEWP ⇒ CONFS70
ENG-IF ⇒ ENGFS123
ENG-IF ⇒ ENG-IFFS24
ENG-IF ⇒ CONFS57
PRO ⇒ PROFS80
PRO ⇒ CONFS40
CON ⇒ CONSS8
FS187
FF19
1053
Table 11. Schedule Outcomes under Construction Productivity Adjustment.
Table 11. Schedule Outcomes under Construction Productivity Adjustment.
ScenarioFinish DateSchedule VarianceRemarks
Baseline Schedule
(No Adjustment) (ⓐ)
11 June 2029±0 daysAWP-M1, M2 schedule without AWP improvements
25% Productivity Improvement Applied (ⓑ)11 February 2029−120 days
(ⓑ − ⓐ)
Reflects 25% reduction in CWP durations
ⓑ + 90 day Lag for IEWPto CWP Sequencing (ⓒ)12 April 2029−60 days
(ⓒ − ⓐ)
Accounts for AWP workface planning requirement
Table 12. Traditional schedule engineering activity delay results.
Table 12. Traditional schedule engineering activity delay results.
Delay ActivityFinish Date (A)Variance (A-Baseline)
310C118PI8 March 2030270 days
310E145PI6 January 2030209 days
310J159PI11 June 20290 days
310P193PI8 March 2030270 days
320C118PI1 December 2029173 days
320E145PI30 November 2029172 days
320J159PI11 June 20290 days
320P193PI1 December 2029173 days
Table 13. AWP-M1, M2 schedule engineering activity delay/mitigation scenario results.
Table 13. AWP-M1, M2 schedule engineering activity delay/mitigation scenario results.
Delay Activity360-Day Delay30-Day Backlog
AWP-M1AWP-M2Finish Date
(A)
Variance
(A-Baseline)
Finish Date
(B)
Variance
(B-A)
CWP01-EWP10-3101C118PICWP01-EWP9-3101C118PI7 January 20302708 December 2029−30
CWP03-EWP16-3101E145PICWP03-EWP13-3101E145PI20 November 202922221 October 2029−30
CWP06-EWP24-3101J159PICWP06-EWP21-3101J159PI12 April 2029012 April 20290
CWP07-EWP27-3101P186PICWP03-EWP25-3101P193PI7 January 20302708 December 2029−30
CWP09-EWP41-3202C118PICWP09-EWP31-3202C118PI15 November 202921716 October 2029−30
CWP00-EWP46-3202E145PICWP00-EWP35-3202E145PI29 December 202926129 November 2029−30
CWP12-EWP52-3202J159PICWP12-EWP40-3202J159PI12 April 2029012 April 20290
CWP10-EWP57-3202P193PICWP10-EWP44-3202P193PI15 November 202921716 October 2029−30
Table 14. AWP-M1 schedule I-EWP activity delay/mitigation scenario results.
Table 14. AWP-M1 schedule I-EWP activity delay/mitigation scenario results.
AWP-M1360-Day DelayRe-Sequencing
Delay ActivityFinish DateVariance
(A-Baseline)
Finish Date
(B)
Variance
(B-Baseline)
Variance
(B-A)
I-EWP1015 October 202918615 October 20291860
I-EWP1612 April 2029012 April 202900
I-EWP2412 April 2029012 April 202900
I-EWP2716 May 20293416 May 2029340
I-EWP4114 August 202912422 July 20290−23
I-EWP4612 April 2029012 April 202900
I-EWP5212 April 2029012 April 202900
I-EWP5714 February 203017017 July 202996−74
Table 15. AWP-M2 schedule I-EWP activity delay/mitigation scenario results.
Table 15. AWP-M2 schedule I-EWP activity delay/mitigation scenario results.
AWP-M2360-Day DelayRe-Sequencing
Delay ActivityFinish DateVariance
(A-Baseline)
Finish Date
(B)
Variance
(B-Baseline)
Variance
(B-A)
I-EWP915 December 202924715 December 20292470
I-EWP1312 April 2029012 April 202900
I-EWP2112 April 2029012 April 202900
I-EWP2514 October 202918514 October 20291850
I-EWP3114 October 20291851 August 2029111−74
I-EWP3512 April 2029012 April 202900
I-EWP4012 April 2029012 April 202900
I-EWP4429 November 202923116 September 2029157−74
Table 16. Structural comparison of WBS & WPs.
Table 16. Structural comparison of WBS & WPs.
AttributeTraditional Schedule *AWP-M1AWP-M2Remark
WBS (or WP) Levels455* Varies on project and purpose
WBS Level definition1-Project
2-Phase(EPC)
3-Disc/CP
4-FBS/PO/Type
1-Project
2-CWA
3-Phase(EPC)
4-Discipline
5-WP
1-Project
2-CWA
3-Phase(EPC)
4-Discipline
5-WP
WP groupingFunction
-ENG: FBS
-PRO: PO
-CON: CP
CWA + Function
-ENG: FBS
-PRO: Equip. type
-CON: Con. type
CWA + Function
-ENG: Disc.
-PRO: Equip. type
-CON: Con. type
WPs48202163* Lowest WBS level
ENG deliverables269940940
* In the traditional schedule attribute, values may vary depending on the project characteristics.
Table 17. Schedule activity quantity comparison summary.
Table 17. Schedule activity quantity comparison summary.
AttributeTraditional Schedule (A)AWP-M1 (B)AWP-M2 (C)
BB-AB/ACC-AC/A
ENGAE/BOP241591356.631591356.63
NSSS/RCB3155241.7755241.77
Common102−80.202−80.2
Interface/IEWP/ENG-IF982031052.07164661.67
Sum1634192562.573802172.33
PROAE/BOP-8787-8787-
NSSS/RCB933243.6733243.67
Common24-−24--−24-
Interface59-−59--−59-
Sum92120281.30120281.30
CONAE/BOP89101121.13101121.13
NSSS/RCB4646-1.0046-1.00
Common-------
Interface124-−124--−124
Sum259147−1120.57147−1120.57
Sum5176861691.336471301.25
Table 18. Schedule relationship comparison summary.
Table 18. Schedule relationship comparison summary.
Predecessor ⇒ SuccessorTraditional
Schedule (A)
AWP-M1 (B)AWP-M2 (C)
BB-AB/ACC-AC/A
ENG ⇒ ENG1025504485.395504485.39
ENG ⇒ PRO2240181.8240181.82
ENG ⇒ CON174153−210.88127−470.73
PRO ⇒ PRO2280583.6480583.64
PRO ⇒ CON7440−340.5440−340.54
CON ⇒ CON193214211.11214211.11
Total58910794901.8310534641.79
Table 19. Comparison due to construction productivity adjustment.
Table 19. Comparison due to construction productivity adjustment.
ScheduleFinish DateSchedule Variance
Traditional11 June 2029
AWP applied
(25% productivity + 90-day lag)
12 April 2029ⓐ—60 days
Table 20. 360-day delay and Scenario ① mitigation result comparison summary.
Table 20. 360-day delay and Scenario ① mitigation result comparison summary.
Delay ActivityVariance on 360-Day DelayB, C
30-Day Backlog
Traditional
(A)
AWP-M1
(B)
AWP-M2
(C)
A-Base
(ⓐ)
B,C-Base
(ⓑ)
ⓑ − ⓐCritical Path
Changes on ⓑ
310C118PICWP01-EWP10-3101C118PICWP01-EWP9-3101C118PI2702700-−30
310E145PICWP03-EWP16-3101E145PICWP03-EWP13-3101E145PI20922213Overall Construction → Cable Tray−30
310J159PICWP06-EWP24-3101J159PICWP06-EWP21-3101J159PI000-0
310P193PICWP07-EWP27-3101P186PICWP03-EWP25-3101P193PI2702700-−30
320C118PICWP09-EWP41-3202C118PICWP09-EWP31-3202C118PI17321744RCB → CWA2−30
320E145PICWP00-EWP46-3202E145PICWP00-EWP35-3202E145PI17226189RCB → CWA2
Activity(E3) Duration difference
−30
320J159PICWP12-EWP52-3202J159PICWP12-EWP40-3202J159PI000-0
320P193PICWP10-EWP57-3202P193PICWP10-EWP44-3202P193PI17321744RCB → CWA2−30
Table 21. Scenario ② mitigation result comparison summary.
Table 21. Scenario ② mitigation result comparison summary.
Delay ActivityVariance on 360-Day Delay Finish DateVariance on Post Re-Sequencing
Delay Finish Date (Mitigated Dates)
AWP-M1 (A)AWP-M2 (B)A-BaselineB-BaselineA-BaselineB-Baseline
I-EWP10I-EWP9186247186 (0)247 (0)
I-EWP16I-EWP130000
I-EWP24I-EWP210000
I-EWP27I-EWP253418500
I-EWP41I-EWP31124185101 (−23)111 (−74)
I-EWP46I-EWP350000
I-EWP52I-EWP400000
I-EWP57I-EWP4417023196 (−74)157 (−74)
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Choo, D.; Jung, W. A Preliminary Study on the Comparative Schedule Analysis of Traditional and Advanced Work Packaging Plans for Nuclear Power Plant Construction. Appl. Sci. 2025, 15, 11113. https://doi.org/10.3390/app152011113

AMA Style

Choo D, Jung W. A Preliminary Study on the Comparative Schedule Analysis of Traditional and Advanced Work Packaging Plans for Nuclear Power Plant Construction. Applied Sciences. 2025; 15(20):11113. https://doi.org/10.3390/app152011113

Chicago/Turabian Style

Choo, Dongwoo, and Wooyong Jung. 2025. "A Preliminary Study on the Comparative Schedule Analysis of Traditional and Advanced Work Packaging Plans for Nuclear Power Plant Construction" Applied Sciences 15, no. 20: 11113. https://doi.org/10.3390/app152011113

APA Style

Choo, D., & Jung, W. (2025). A Preliminary Study on the Comparative Schedule Analysis of Traditional and Advanced Work Packaging Plans for Nuclear Power Plant Construction. Applied Sciences, 15(20), 11113. https://doi.org/10.3390/app152011113

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop