Next Article in Journal
Studies and Rejection of Intercrystal Crosstalk on FPGA in a High-Energy Photon-Counting System
Previous Article in Journal
Analysis of Aspirin and Dipyridamole in a Modern Pharmaceutical Formulation-Drug Release Study and Permeability Assessment
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Study on the Ground Pressure Manifestation Patterns of Roof Cutting and Pressure Relief

College of Mining Engineering, Taiyuan University of Technology, Taiyuan 030024, China
*
Author to whom correspondence should be addressed.
Appl. Sci. 2025, 15(11), 6049; https://doi.org/10.3390/app15116049
Submission received: 10 April 2025 / Revised: 22 May 2025 / Accepted: 23 May 2025 / Published: 28 May 2025

Abstract

Pillarless mining technology is of great significance for improving coal recovery rates, but the intense mining-induced stress disturbances on gob-side entries often lead to surrounding rock instability. In this study, we focused on the ground control challenges in the headgate of Panel 81308 at Huayang Mine No. 2. Comprehensive monitoring of roof–floor convergence, rib deformation, and support resistance revealed the gob-side entry retaining deformation mechanisms with roof-cutting pressure relief; the results show that this retaining deformation exhibits the following three phases of characteristics: the rapid, decelerated, and stable stages. The average roof–floor convergence (607 mm) was significantly greater than the average rib deformation (170 mm), with floor heave accounting for 72.6% of total convergence. The coal pillar side showed dominant deformation in rib movements. The mining influence zones can be divided, based on their distances behind the working face, into strong disturbance zones (0–88 m), weak disturbance zones (88–142 m), and stabilized zones (>178 m). The cable bolt support system demonstrated advanced response characteristics. Compared with conventional gob-side entry retaining, the roof-cutting pressure relief technique altered stress transmission paths, significantly reduced roof load transfer efficiency, and effectively controlled roadway convergence, providing technical guidance for safe production in both this panel and mines with similar geological conditions.

1. Introduction

With the increasing demand for coal resources, and the gradual deepening of coal mining depths, traditional mining methods are facing several challenges, including resource wastage, tight mining face succession, and the need for improved roadway safety performance. Gob-side entry retaining (GER) technology enables pillarless mining, providing significant improvements in coal recovery rates, alleviating succession pressure, and reducing roadway excavation volumes. However, GER technology remains constrained by complex strata pressure, roof–floor collapse, floor heave, and rib spalling during the entry retaining process. In summary, conducting further research on strata behavior laws and surrounding rock control for GER technology has become an emerging trend. Many scholars have conducted in-depth studies on strata behavior laws in roof-cutting pressure relief working faces and achieved a series of important research outcomes [1,2,3,4,5].
Jiang et al. [6,7] proposed a directional roof-cutting coordinated pressure relief control method, revealing its mechanism of roadway stabilization through reducing working face stress, surrounding rock stress, and roof–floor deformation. Yang et al. [8,9,10] developed a presplit blasting roof-cutting pressure relief method for adjacent roadways based on the short cantilever beam theory; through intercepting advanced mining stress transmission paths, it achieved surrounding rock stress environment regulation, reducing hydraulic support resistance peaks by 24.9% and decreasing roadway roof–floor and rib deformations by 34.9–50.1%. Zhu et al. [11,12] introduced a dense pressure relief hole roof weakening coordinated control method, and engineering tests demonstrated its capability to replace conventional blasting techniques, achieving safe and efficient pressure relief for roadway protection, thereby establishing a “mechanical regulation-pressure relief roadway protection”-coordinated technical system. Gong et al. [13] established a deep/shallow hole coordinated presplit blasting parameter system; through advanced slot cutting, grouting reinforcement, and flexible gangue blocking, they achieved coordinated surrounding rock control. Field measurements showed fracture development rates of 85%/90% for deep/shallow holes, respectively, with roof subsidence reduced by 46.3%, forming a “directional slotting-structure reconstruction-active roadway protection” hard roof control system that breaks through conventional strong support concepts. Habib et al. [14,15] investigated soundless cracking demolition agent (SCDA) chemical expansion rock-breaking technology; through borehole optimization and uniaxial auxiliary loading experiments, they revealed that increasing the borehole diameter reduces the hard rock fracture time to 7 h, with an optimal diameter-spacing ratio of 12.8–14.6, establishing a “chemical-mechanical” coordinated rock-breaking system that provides green mining solutions without detonation and with low vibration. Dmytro et al. [16,17,18] innovatively developed an underground gangue in situ backfilling and coal gangue quality-controlled coordinated mining process, reducing raw coal ash content to 15.2% while increasing the energy equivalent by 7.4% (9.6 TJ); they created a coal quality–energy dynamic prediction algorithm, breaking through traditional process limitations in energy efficiency/coal quality coordinated optimization. Wang et al. [19,20,21,22,23,24] conducted theoretical calculations and numerical simulations based on deep-hole blasting roof-cutting pressure relief principles and technologies; the results showed significant reduction in the surrounding rock deformation of retained roadways after roof cutting, verifying the effectiveness of advanced deep-hole presplit blasting technology in improving the surrounding rock deformation of gob-side entry retaining in thick coal seams with soft floors. Liu et al. [25,26,27] addressed the challenge of generating initial stress fields with principal stresses, oblique to boundaries, in FLAC3D models; they proposed determining boundary stress directions using elastic theory combined with the Mohr’s circle pole and force equilibrium methods, employing quasi-stress boundary control to generate initial stress fields, and verification showed high consistency between model principal stress values/directions and actual conditions, confirming the method’s effectiveness and providing technical references for similar projects. Liu et al. [28,29,30] developed a hydraulic fracturing vertical roof-cutting technology based on additional tensile stress roof bending regulation; using mechanical models to precisely locate maximum additional horizontal tensile stress zones for fracturing implementation, they achieved vertical slot cutting and coordinated control of the hard roof and surrounding rock, establishing a “mechanical criterion-fracturing positioning-roof cutting pressure relief” technical system.
Currently, pillarless mining technology has established a relatively comprehensive technical system in thin-coal-seam mining and has been successfully implemented in multiple mining areas. However, practical applications and research under medium–thick- and thick-coal-seam conditions remain insufficient. Therefore, we conducted field observations of roadway roof subsidence, floor heave, rib convergence, and working face hydraulic support loading in this study, in order to analyze the strata behavior characteristics of gob-side entry retaining with presplit blasting roof-cutting pressure relief in the headgate of Panel 81308 at Huayang Mine No. 2. The findings provide theoretical support for a support design of gob-side entry retaining in mines with similar geological conditions.

2. Project Overview

2.1. Engineering Background

The mining engineering plan of Panel 81308 in Huayang Mine No. 2 is shown in Figure 1. The panel is located in the 13th mining district of coal seam #8 at level 470, with panel elevation ranging from 487 to 541 m, surface elevation between 846 and 1063 m, and burial depth varying from 305 to 576 m. The panel has a strike length of 1460 m and a dip length of 240 m, covering a total area of 350,400 m2. The proposed mining method employs strike longwall retreat with comprehensive mechanization, with extraction following the coal seam strike direction. The coal seam dip angle ranges from 1° to 8°, averaging 4°, and the seam demonstrates stable development.

2.2. Roadway Support Method

The headgate of Panel 81308 employs a rectangular cross-section with an excavated width of 5.2 m and height of 3.6 m, providing a clear width of 5.0 m and a height of 3.4 m, developed along the coal seam roof. Figure 2 shows both the original and reinforced support schemes for the retained roadway. The original support system consists of cable bolts, combined with steel straps and metal wire mesh. The reinforced support system uses four rows of high-strength cable bolts (Φ21.8 mm × 11.2 m). The first row is installed 0.9 m from the rib and 0.4 m from the cutting slot, with 0.8 m spacing; the second row is arranged 1.2 m from the first row, with 0.8 m spacing; the third row is placed 1.6 m from the second row, with 1.6 m spacing; and the fourth row is positioned 1.4 m from the third row, with 1.6 m spacing in a staggered arrangement relative to the third row.

2.3. Roof Cutting Technical Parameters

Based on the engineering background of roof-cutting pressure relief automatic roadway formation pillarless mining technology, the current application of pillarless roof cutting in gob-side entry retaining has its critical success factors lying in the advanced roof-cutting technique and its effectiveness. Panel 81308 of Huayang Mine No. 2 employs directional drilling and blasting for advanced roof-cutting operations, with a vertical borehole depth of 1275 mm and a dip angle of 15°. Specific parameters are shown in Table 1.

2.4. Ground Pressure-Monitoring Scheme for Gob-Side Entry Retaining with Roof Cutting

After implementing the pillarless mining technology of gob-side entry retaining with roof cutting and pressure relief, in order to facilitate the formulation of subsequent mining measures for Panel 81308, it was necessary to monitor the stress conditions and deformation of the roadway and working face. The surrounding KJ1100 coal mine rock dynamic monitoring system for gob-side entry retaining (excavation) was adopted; this system consists of a central station computer, a KZG18 intrinsically safe mine signal converter, a GMY500 intrinsically safe mine bolt (cable) stress transmitter, a GUD2000 intrinsically safe mine displacement sensor, and other equipment. The monitoring system flowchart is shown in Figure 3. The main working principle is as follows: the data collected from each sensor are transmitted to the central station computer through the signal converter, and the central computer performs information storage and analysis. The system monitors parameters such as the working resistance of powered supports and the shrinkage of powered support legs in real time; these data are used to evaluate the rationality of support parameters in the working face and roadway, as well as to study the movement laws of the roof strata.
In this section, we detail the monitoring scheme designs for both the roadway and working face. The specific arrangements are described below.
For the retained roadway section of the headgate of Panel 81308, starting from 68 m behind the setup room to the stopping line, one monitoring station was installed every 50 m. Each station consisted of one roof separation monitor and one constant-resistance cable bolt stress monitor. The system collected data every 30 min. The monitoring equipment is shown in Figure 4.
Within working face 81308, one pressure-monitoring point was installed every 30 m, totaling seven pressure-monitoring points. The system collected data every 30 min. The layout schematic of the monitoring stations and points is shown in Figure 5.

3. Simulation Study on Roof-Cutting Effectiveness

In this study, based on the roof–floor rock mass structural characteristics of Panel 81308 and the pillarless roof-cutting gob-side entry retaining (GER) design, we established a numerical model (200 m × 10 m × 30 m) using FLAC3D5.0 simulation software. Given the average burial depth of 440 m for coal seam #8 in Panel 81308 of Mine No. 2, and assuming an average overburden density of 2500 kg/m3, the calculated vertical stress is approximately 11 MPa. Thus, an 11 MPa vertical stress (downward) and a 5 MPa horizontal stress were applied to the model’s upper boundary to simulate in situ strata stress conditions. The model consists of seven vertically stratified layers. The constructed model is shown in Figure 6.
For the simulation, we employed the Mohr–Coulomb failure criterion for rock mass assignment and the Mohr–Coulomb slip model for joint characterization; this combination accurately reflects geomechanical failure mechanisms, enabling reliable simulation of rock mass failure and joint slip behavior. Physico-mechanical parameters of coal–rock masses were determined through uniaxial compression tests, Brazilian splitting tests, and subsequent calibration, with the finalized mechanical parameters presented in Table 2.
The simulation results, depicted in Figure 7, show that, without roof-cutting measures, the peak residual stress in the solid coal rib reached 19.8 MPa, with a cumulative vertical displacement of 26.5 mm. After implementing roof-cutting pressure relief, the peak residual stress reduced to 14.5 MPa, with the corresponding roof subsidence decreasing to 18.6 mm, demonstrating 26.8% stress concentration reduction and 29.8% deformation control improvement. The simulation verifies that roof cutting achieves the mechanical effects of stress redistribution and energy dissipation through reconstructing roof stress transmission paths. The fundamental mechanisms for reducing stress concentration and roof subsidence through deep-hole blasting roof cutting include the following:
(1)
Severing mechanical continuity between goaf and roadway roof beams, thereby reducing pressure on GER support structures;
(2)
Promoting timely goaf caving and effective waste rock filling, transferring overburden loads to collapsed strata to relieve GER support pressure;
(3)
Minimizing roof beam rotation angles (typically <15°) after cutting in the headgate of Panel 81308, thus reducing the predefined deformation of GER roof beams;
(4)
Creating artificial weak zones to control roof fracture locations.

4. Ground Pressure Monitoring Data Analysis

4.1. Analysis of Surrounding Rock Displacement Evolution

The ground pressure monitoring stations in the headgate of Panel 81308 were categorized into three groups (advance, central, and rear monitoring sections). Average values from each station group were calculated to plot the characteristic surrounding rock deformation patterns versus distance from the working face, as shown in Figure 8.
Analysis of Figure 7 and Table 3 reveals the following:
(1)
The average total roof-to-floor deformation measures 607 mm, including 443 mm (73%) of floor heave. Rib deformation averages 170 mm, predominantly occurring at the pillar side. Both roof–floor and rib deformations exhibit similar evolutionary patterns: rapid initial growth, followed by gradual stabilization. The roof–floor deformation rate significantly exceeds the rib deformation rate, with floor heave dominating roof subsidence, and pillar-side deformation being primary in rib convergence.
(2)
Maximum roof–floor convergence occurs within 0–88 m behind the face (primary deformation zone), decreasing through 88–142 m, and stabilizing beyond 178 m. The initial deformation mechanism is governed by composite roof structure movement, while later-stage deformation manifests as progressive settlement from goaf fracture zone compaction. Pillarless roof-cut roadways demonstrate “wide disturbance range and prolonged residual deformation” characteristics under mining-induced stresses.

4.2. Cable Bolt Load Analysis

The load-monitoring data of roof cable bolts in the retained roadway section were collected, with the average load curve plotted in Figure 9. Monitoring results indicate that cable bolt stress begins to significantly increase approximately 30 m ahead of the face due to front abutment pressure. The stress stabilizes at about 185 m behind the face, indicating that the rock surrounding the roadway reaches relative stability.
Load analysis reveals that intense deformation occurs within 0–70 m behind the face (caving zone influence area). High-strength cable bolts in this zone provide active support, effectively controlling roof deformation and ensuring stability.

4.3. Roof Separation Analysis

Field monitoring data indicate that the roof separation development process can be divided into the three following characteristic zones: the initial development stage, within 15 m ahead of the working face; the core development area, extending from 15 m ahead to 85 m behind the working face; and the zone beyond 85 m behind the face to the stress stabilization boundary, where the roof exhibits composite beam-type integral rotational subsidence, reaching a maximum separation of 27.8 mm. Monitoring results demonstrate that, when the lag distance exceeds 140 m, the separation deformation stabilizes, with the final separation magnitude maintaining at approximately 39.6 mm, as shown in Figure 10.

4.4. Working Face Pressure Variation

Based on the hydraulic support load-monitoring data from Panel 81308 (as shown in Figure 11), the roof-cutting pressure-relief technology demonstrates significant stress regulation effects: the measured load curves of the cutting-side supports show a 12.7–18.4% reduction in peak bearing capacity compared to under untreated conditions, indicating that the roof-cutting blasting technique has achieved the expected results.

5. Field Application Effectiveness

Post-blasting borehole inspection (Figure 12) reveals well-developed fracture networks near the borehole collar in roof-cutting holes. The external roof-cutting measures play decisive roles in gob-side entry retaining. Field practice at Panel 81308 confirms that this technology successfully interrupts roof stress transmission, effectively ensuring entry stability. The field application results are shown in Figure 13.

6. Conclusions

(1)
The surrounding rock deformation in roof cutting for pressure relief in gob-side entry retaining exhibits the following three-phase evolution: ① the strong disturbance phase (0–88 m behind face), dominated by composite roof structure destabilization, showing peak deformation rates; ② the weak disturbance phase (88–142 m), controlled by goaf waste rock compaction, with decaying deformation rates; ③ and the stabilization phase (>178 m), in which stress redistribution is completed, maintaining deformation rates below 0.5 mm/m. Floor heave constitutes 72% of roof–floor convergence, with pillar-side deformation being primary in rib movements.
(2)
Front abutment pressure induces significant cable bolt load increase, starting 30 m ahead of the face. The intense deformation zone spans 0–70 m behind the face (caving influence area), with stress stabilization occurring at ~185 m behind it, revealing asynchronous evolution between support systems and the surrounding rock deformation.
(3)
Numerical modeling and field monitoring jointly validate the mechanical optimization mechanism. Artificially created weak planes from pre-splitting blasting effectively intercept the stress transmission between the roadway and goaf rooves, inducing “voussoir beam-waste rock” composite structures in overlying strata and achieving effective deformation control that meets safe production requirements.

Author Contributions

Conceptualization, B.H.; methodology, T.L.; software, C.S.; validation, R.Z.; writing—original draft preparation, R.Z.; writing—review and editing, B.H.; funding acquisition, B.H. All authors have read and agreed to the published version of the manuscript.

Funding

This research received no external funding.

Institutional Review Board Statement

Not applicable.

Informed Consent Statement

Not applicable.

Data Availability Statement

The data presented in this study are available on request from the corresponding author.

Conflicts of Interest

The authors declare no conflicts of interest.

References

  1. Hua, X.Z.; Li, C.; Li, X.; Guo, Y.J.; Qi, Y.B.; Chen, D.H. Current situation of gob-side entry retaining and suggestions forits improvement in China. Coal Sci. Technol. 2023, 51, 128–145. [Google Scholar] [CrossRef]
  2. Wang, J.C. Introduction to Theory and Technology of Scientific Coal Mining. Shanxi Coal 2023, 43, 5–7. [Google Scholar]
  3. Xie, S.R.; Wu, Y.Y.; Guo, F.F.; Zou, H.; Chen, D.D.; Zhang, X.; Ma, X.; Liu, R.P.; Wu, C.W. Application of Pre-Splitting and Roof-Cutting Control Technology in Coal Mining: A Review of Technology. Energies 2022, 15, 6489. [Google Scholar] [CrossRef]
  4. Tian, C.; Liu, Y.J.; Lou, H.Z.; Jia, T.G. Stability Control of a Roadway Surrounding Rock during the Cutting and Pressure Relief of a Coal-Bearing Roof at a Shallow Mining Depth. Geofluids 2022, 2022, 5308530. [Google Scholar] [CrossRef]
  5. Deng, Z.; Ma, C.; Xia, Z.; Ma, Q.; Lu, Z. Influence of ore-drawing port position on ore-rock flow characteristics in ore pass and lateral pressure on ore pass wall. Sci. Rep. 2024, 14, 21202. [Google Scholar] [CrossRef]
  6. Jiang, Z.H.; Jiang, B.; Wang, Q.; Xue, H.J.; Ma, Y.K. Model test research and application on control method of cooperative pressure relief by directional roof cutting for roadways with strong dynamic pressure. Environ. Earth Sci. 2023, 82, 434. [Google Scholar] [CrossRef]
  7. Zhang, S.Z.; Ren, C.N.; Gao, X.Y.; Gao, Y.S.; Nie, L.Y.; Li, S.D.; Jiang, M.L. Stability and Control of Surrounding Rock of a Trapezoidal Roadway Retained with Hard Roof Cutting. Appl. Sci. 2025, 15, 348. [Google Scholar] [CrossRef]
  8. Yang, X.J.; Hu, C.W.; He, M.C.; Wang, H.H.; Zhou, Y.B.; Liu, X.Y.; Zhen, E.Z.; Ma, X.G. Study on Presplitting Blasting the Roof Strata of Adjacent Roadway to Control Roadway Deformation. Shock Vib. 2019, 2019, 3174898. [Google Scholar] [CrossRef]
  9. Guo, Z.B.; Wang, H.H.; Ma, Z.M.; Wang, P.F.; Kuai, X.H.; Zhang, X.Z. Research on the Transmission of Stresses by Roof Cutting near Gob Rocks. Energies 2021, 14, 1237. [Google Scholar] [CrossRef]
  10. Yue, X.Z.; Tu, M.; Li, Y.F.; Chang, G.F.; Li, C. Stability and Cementation of the Surrounding Rock in Roof-Cutting and Pressure-Relief Entry under Mining Influence. Energies 2022, 15, 951. [Google Scholar] [CrossRef]
  11. Zhu, Z.; Du, M.Q.; Xi, C.H.; Yuan, H.P.; He, W.S. Mechanics Principle and Implementation Technology of Surrounding Rock Pressure Release in Gob-Side Entry Retaining by Roof Cutting. Processes 2022, 10, 2629. [Google Scholar] [CrossRef]
  12. Lang, D.; Chen, S.M.; Yuan, H.P.; Yu, J.D.; Yu, Y.; Luo, S.H.; Hu, B.S.; Xie, P.S. Study of Reasonable Roof Cutting Parameters of Dense-Drilling Roof Cutting and Pressure Relief Self-Forming Roadway in Non-Pillar Mining. Appl. Sci. 2025, 15, 2685. [Google Scholar] [CrossRef]
  13. Gong, S.; Tan, Y.; Liu, Y.P.; Zhu, D.; Yu, Y. Application of Presplitting Blasting Technology in Surrounding Rock Control of Gob-Side Entry Retaining with Hard Roof: A Case Study. Adv. Mater. Sci. Eng. 2021, 653–663, 1318975. [Google Scholar] [CrossRef]
  14. Habib, K.M.; Vennes, I.; Mitri, H. Laboratory investigation into the use of soundless chemical demolitions agents for the breakage of hard rock. Int. J. Coal Sci. Technol. 2022, 9, 70. [Google Scholar] [CrossRef]
  15. Sakhno, I.; Sakhno, S. Directional fracturing of rock by soundless chemical demolition agents. Heliyon 2024, 10, e26068. [Google Scholar] [CrossRef]
  16. Malashkevych, D.; Petlovanyi, M.; Sai, K.; Zubko, S. Research into the coal quality with a new selective mining technology of the waste rock accumulation in the mined-out area. Min. Miner. Depos. 2022, 16, 103–114. [Google Scholar] [CrossRef]
  17. Kostecki, T.; Spearing, A.J.S. Influence of backfill on coal pillar strength and floor bearing capacity in weak floor conditions in the Illinois Basin. Int. J. Rock Mech. Min. Sci. 2015, 76, 55–67. [Google Scholar] [CrossRef]
  18. Bai, Y.L. Research on the Underground Pressure Behavior Laws of Reserving Space forLane along the Tunnel by Self—Filling with Breakage Wastes. Met. Mine 2011, 6, 63–66. [Google Scholar]
  19. Wang, Y.J.; Zhang, C.; Xu, Z.J. Research on Surrounding Rock Control Technology of Deep-Hole Blasting ang Roof Cutting Gob-Side Entry Retaining in Thick Coal Seam. Min. Res. Dev. 2023, 43, 103–111. [Google Scholar] [CrossRef]
  20. Tang, J.X.; Wang, X.; Yuan, F.; Kong, L.R.; Li, W.; Li, S.; Lu, S.J.; Lin, Y. Rock pressure distribution law of roadway based on displacement back analysis method. Saf. Coal Mines 2023, 54, 128–134. [Google Scholar] [CrossRef]
  21. Li, Y.J.; Wang, Y.H.; Yang, Y.H.; Gai, Q.K.; Zhang, X.X.; Gao, Y.B. Research and application of non pillar mining technology for cutting roof and retaining roadway in Rongkang Coal Mine. China Min. Mag. 2023, 32, 288–294. [Google Scholar]
  22. Shi, Z.W.; Gao, H.T.; Qi, W.M.; Deng, Q.P.; Liu, W.J.; Zhang, D.L. Analysis on Deformation Evolution of Surrounding Rock in Gob-sideEntry Retaining by Roof Cutting. Coal Technol. 2022, 41, 33–36. [Google Scholar] [CrossRef]
  23. Shang, R.L.; Huang, B.; Yang, F.Y.; Song, Y.W.; Li, J.F.; Li, Z.L. Study on Mine Pressure Behaviors of Gob—Side Entry Retaining Working Face in Zhongxing Mine. Coal Eng. 2015, 47, 74–77. [Google Scholar]
  24. He, D.S.; Liu, D.L.; Zhang, Y. Non—pillar mining technology of medium thick seam with roof cutting andpressure released retained gateway and complex roof. Coal Sci. Technol. 2018, 46, 126–132. [Google Scholar] [CrossRef]
  25. Liu, J.Y.; Bian, T.; Ji, Z. Initial stress field generation based on FLAC3D by considering obliqueintersection between measured principal stress andcomputation model boundary. China Min. Mag. 2024, 33, 163–169. [Google Scholar]
  26. Qiu, Y.L.; Hu, X.Y.; Wang, Z.; Wang, Z.J. Automatic FLAC3D Mesh Generation Based on Advancing-Frontal Method. In Proceedings of the International Conference on Civil Engineering and Building Materials (CEBM), Kunming, China, 29–31 July 2011; pp. 1862–1866. [Google Scholar]
  27. Zhao, B.Y.; Liu, D.Y.; Zheng, Y.R.; Dong, Q. Secondary Development and Slope Application Discussion of the Non-Linear Visco-Elastic Plastic Creep Model in Flac3D Software. Disaster Adv. 2012, 5, 1231–1236. [Google Scholar]
  28. Liu, J.W.; Liu, C.Y.; Yao, Q.L.; Si, G.Y. The position of hydraulic fracturing to initiate vertical fractures in hard hanging roof for stress relief. Int. J. Rock Mech. Min. Sci. 2020, 132, 104328. [Google Scholar] [CrossRef]
  29. Yang, S.; Li, X.H.; Wang, J.; Yang, S.H.; Shen, Z.; Xu, G.Z. Study on Pressure Relief Technology of High-Pressure Water Jet of Residual Coal Pillar in Overlying Goaf in Close Seam Mining. Shock Vib. 2022, 2022, 7842921. [Google Scholar] [CrossRef]
  30. Wu, L.Z.; Huang, B.; Li, Y.Z.; Xie, B.; Lin, R. Analysis of the propagation path for hydraulic fracture intersecting natural fracture. In Proceedings of the International Conference on Energy, Environmental & Sustainable Ecosystem Development (EESED), Kunming, China, 21–23 August 2015. [Google Scholar]
Figure 1. Mining layout plan of coal seam #8 in Panel 81308.
Figure 1. Mining layout plan of coal seam #8 in Panel 81308.
Applsci 15 06049 g001
Figure 2. Original and reinforced support systems for the retained roadway.
Figure 2. Original and reinforced support systems for the retained roadway.
Applsci 15 06049 g002
Figure 3. Monitoring system flowchart.
Figure 3. Monitoring system flowchart.
Applsci 15 06049 g003
Figure 4. Monitoring equipment diagram.
Figure 4. Monitoring equipment diagram.
Applsci 15 06049 g004
Figure 5. Layout of ground pressure monitoring stations in Panel 81308.
Figure 5. Layout of ground pressure monitoring stations in Panel 81308.
Applsci 15 06049 g005
Figure 6. Numerical simulation base model.
Figure 6. Numerical simulation base model.
Applsci 15 06049 g006
Figure 7. Comparison of roof-cutting vs. conventional conditions in the headgate of Panel 81308.
Figure 7. Comparison of roof-cutting vs. conventional conditions in the headgate of Panel 81308.
Applsci 15 06049 g007aApplsci 15 06049 g007b
Figure 8. Characteristics of surrounding rock deformation vs. distance from working face in retained roadway.
Figure 8. Characteristics of surrounding rock deformation vs. distance from working face in retained roadway.
Applsci 15 06049 g008aApplsci 15 06049 g008b
Figure 9. Cable bolt stress-monitoring curves in the headgate of Panel 81308.
Figure 9. Cable bolt stress-monitoring curves in the headgate of Panel 81308.
Applsci 15 06049 g009
Figure 10. Roof separation monitoring curves in the headgate of Panel 81308.
Figure 10. Roof separation monitoring curves in the headgate of Panel 81308.
Applsci 15 06049 g010
Figure 11. Three-dimensional visualization of hydraulic support pressure variation at working face.
Figure 11. Three-dimensional visualization of hydraulic support pressure variation at working face.
Applsci 15 06049 g011
Figure 12. Borehole imaging results.
Figure 12. Borehole imaging results.
Applsci 15 06049 g012
Figure 13. Field application results of gob-side entry retaining.
Figure 13. Field application results of gob-side entry retaining.
Applsci 15 06049 g013
Table 1. Design parameters of advanced roof pre-splitting drilling and blasting.
Table 1. Design parameters of advanced roof pre-splitting drilling and blasting.
ParameterValueRemarks and Explanations
Borehole position200–500 mmDistance from mining rib to cutting seam holes in the headgate of Panel 81308: 200–500 mm
Cutting seam dip angle15°Angle between borehole and vertical direction
Borehole inclined length13 mInclined length of cutting seam holes
Borehole diameter50 mm
Energy-gathering tubeBTC35-1 500Outer diameter: 42 mm; inner diameter: 36.5 mm; charge diameter: Φ35 mm; single section: 1.5 m
Emulsion explosiveGrade IIISpecification: Φ35 × 200 mm; single cartridge weight: 200 ± 10 g
Borehole spacing500 mmDetermined based on field test results
Charge structure5 + 4 + 4 + 3 + 2 + 1Single hole uses six energy-gathering tubes; stemming length: 4.0 m; 19 cartridges per hole
Maximum simultaneous detonation holes15 piecesPost-blast gas concentration < 0.5%; CO concentration < 0.0024% (24 ppm)
Table 2. Rock mass mechanical parameters for numerical calculation.
Table 2. Rock mass mechanical parameters for numerical calculation.
Stratum NameThickness (m)Density (kg/m3)Tensile Strength (MPa)Friction Angle (°)Cohesion (MPa)Elastic Modulus (GPa)Poisson’s Ratio
Overburden Strata6.0025004.9045.503.808.500.20
Fine-grained Sandstone5.5026307.3742.923.1114.940.21
Sandy Mudstone4.3725904.7440.032.9412.120.23
Mudstone3.4725702.7139.352.322.450.26
Coal Seam #83.5014502.0736.871.742.220.25
Fine-grained Sandstone3.1926308.3441.343.5114.640.22
Sandy Mudstone3.9725904.5639.952.8411.290.24
Table 3. Surrounding rock deformation data at monitoring stations in retained roadway.
Table 3. Surrounding rock deformation data at monitoring stations in retained roadway.
Monitoring Station NameRoof–Floor Convergence (mm)Floor Heave (mm)Rib-to-Rib Convergence (mm)
Advance
monitoring section
640460200
Central monitoring section58039070
Rear monitoring section600480240
Average607443170
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Zheng, R.; Hao, B.; Shi, C.; Li, T. Study on the Ground Pressure Manifestation Patterns of Roof Cutting and Pressure Relief. Appl. Sci. 2025, 15, 6049. https://doi.org/10.3390/app15116049

AMA Style

Zheng R, Hao B, Shi C, Li T. Study on the Ground Pressure Manifestation Patterns of Roof Cutting and Pressure Relief. Applied Sciences. 2025; 15(11):6049. https://doi.org/10.3390/app15116049

Chicago/Turabian Style

Zheng, Runhu, Bingyuan Hao, Chaoyao Shi, and Tongxi Li. 2025. "Study on the Ground Pressure Manifestation Patterns of Roof Cutting and Pressure Relief" Applied Sciences 15, no. 11: 6049. https://doi.org/10.3390/app15116049

APA Style

Zheng, R., Hao, B., Shi, C., & Li, T. (2025). Study on the Ground Pressure Manifestation Patterns of Roof Cutting and Pressure Relief. Applied Sciences, 15(11), 6049. https://doi.org/10.3390/app15116049

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop