Next Article in Journal
Habitat Destruction and Restoration in Relation to Extinction and Survival of Species in Competitive Communities
Next Article in Special Issue
Finite Element Parametric Analysis of High-Strength Eccentrically Braced Steel Frame with Variable-Cross-Section Replaceable Link
Previous Article in Journal
Anthraquinone Rhein Exhibits Antibacterial Activity against Staphylococcus aureus
Previous Article in Special Issue
Dimensional Reduction-Based Moment Model for Probabilistic Slope Stability Analysis
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Safety Risk Assessment of Highway Bridge Construction Based on Cloud Entropy Power Method

1
School of Water Conservancy Engineering, Zhengzhou University, Zhengzhou 450001, China
2
Henan Jiaotou Jiaozheng Expressway Co., Ltd., Zhengzhou 450016, China
*
Author to whom correspondence should be addressed.
Appl. Sci. 2022, 12(17), 8692; https://doi.org/10.3390/app12178692
Submission received: 4 August 2022 / Revised: 22 August 2022 / Accepted: 28 August 2022 / Published: 30 August 2022

Abstract

:
(1) In recent years, with China’s increasing investment in the transportation industry, the construction of highways and bridges has flourished, bringing great convenience to people’s lives. At the same time, there are many uncertain factors in the process of bridge construction, being prone to construction risks. In order to meet the requirements of sustainable development, it is necessary to accurately evaluate the safety risk level of bridge construction. Therefore, it is necessary to establish a new scientific safety risk evaluation system for highway bridge construction. (2) Methods. Based on the relevant standards and specifications, this paper establishes a highway bridge construction safety risk evaluation index system, and then uses the cloud entropy weight method to objectively weight each risk index, using cloud model theory to conduct a risk assessment, and through the cloud model images directly determine the overall risk level of bridge construction, and the level of risk indicators. (3) Results. Applying this method to the construction safety risk assessment of a particular bridge, the overall construction risk level of the bridge is obtained as “level 4”, and the risk levels of the four first-level indicators are also all “level 4”. (4) Conclusions. The cloud entropy weight method proposed in this paper and the traditional AHP-Extenics method are applied to a bridge construction safety risk evaluation, and the evaluation results obtained are consistent. However, this paper uses the cloud model to improve the entropy weight method in order to calculate the weights, which fully reflects the objectivity of the assignment. The cloud model is used for evaluation, and the risk level of indicators can be determined visually with images.

1. Introduction

There are approximately 832,500 highway bridges in China, with a total of 52,256,200 linear meters, and highway bridges have become an important part of the national infrastructure. As the link between highways, bridges are interdependent. Bridge construction is an important and high-risk branch of the transportation construction industry [1]. In particular, the construction of large bridges often faces complex social and natural environments. The environment, coupled with the characteristics of the bridge itself, such as a long construction period, complex structural system, relatively high construction technology, and complex external connections, lead to a series of uncertain factors in the bridge construction process, resulting in construction safety risk, which in turn affects the sustainability of the bridge construction process [2]. During the bridge construction period, risk usually consists of two aspects: one is the size of the possibility of risk occurrence, i.e., risk probability, and the other is the size of the severity of the loss caused by the risk occurrence, also called risk loss. If the risks are not effectively managed and controlled during the bridge construction process, it will not only hinder the progress and cause delays in construction, but even lead to serious economic losses and casualties, which will have a negative impact on the transportation construction industry and society as a whole [3]. To date, several domestic bridge construction accidents have occurred, such as the sudden collapse of the bridge erection machine for Jiashao Bridge in the prefabricated box girder assembly, and the collapse of Jinshan Bridge in Enshi City, Hubei Province during the pouring process, among others [4]. There are many reasons for these events, involving various aspects such as design, construction, and environmental factors, but in general, the main reasons are the lack of awareness of construction safety risks by construction enterprises, and the lack of risk awareness of a considerable number of construction practitioners [5]. In view of the current research on the safety risk assessment of highway and bridge construction, most studies focus on qualitative or quantitative analysis, which is easily limited to research on the direct risk factors of bridge construction accidents, and lacks in-depth analysis of the nature and mechanism of risk. Bridges are affected by the social and natural environment, construction personnel and management, construction technology, materials and equipment and other factors during construction. These uncertain factors greatly increase the difficulty of construction control. Therefore, it is necessary to establish a more complete and scientific index system for highway and bridge construction safety evaluation; this would reasonably evaluate the safety risk level of highway and bridge construction, reflect the results of risk evaluations in an intuitive way, and make it possible to take corresponding control measures for risk factors in a timely manner, in order to ensure the absolute safety of bridge construction.
At present, scholars at home and abroad have conducted a great deal of research on the safety risk assessment of highway bridge construction, and established many bridge construction safety risk assessment models. In order to accurately and effectively control the construction risk of highway bridges, Yichen Li et al. [6] proposed a method based on network analysis (ANP) and two-dimensional risk assessment methods for cloud models. Seyedmehdi Mortazavi et al. [7] conducted a questionnaire survey on the severity of construction risk indicators among experts and technicians, prioritized risk factors according to the survey results, conducted a quantitative analysis of construction risks on actual bridge projects through Monte Carlo simulation, and determined the impact on bridges of the most critical risk factors for construction safety. Gholamreza Abdollahzadeh [8] used fault tree and event tree analysis methods to evaluate the construction risk of bridge engineering, in order to determine the main causes of fault occurrence and the potential consequences of risk occurrence. Li et al. [9] improved the traditional AHP method and established an entropy-based analytic hierarchy process model, used to evaluate and analyze the risk factors in the bridge construction process. Curra et al. [10] proposed a HYRISK model for bridge scour risk assessment, which was used to determine bridge scour risk probability and consequential loss size, based on the data in the National Bridge Inventory (NBI); the model was successfully used to assess bridge scour in New York State. Yuxin Liu [11] proposed a PC cable-stayed bridge construction based on the fuzzy hierarchical identification method, the F-A-M risk probability assessment method, and the loss equivalent assessment method, using the construction characteristics of the PC cable-stayed bridge. Nieto-Morote [12] proposed a risk assessment method based on the analytic hierarchy process (AHP)-fuzzy set theory using the uncertain factors existing in the bridge construction process. The risk factors were scored and weighted, and then the algorithm was used to deal with the inconsistency in the fuzzy preference relationship in terms of fuzzy judgment. The method was successfully applied to the risk assessment of a bridge project under construction. In order to solve the problems of uncertainty and ambiguity affecting the accuracy of the evaluation results in the safety risk evaluation of bridge construction, Weijun Yang et al. [13] realized qualitative evaluation and quantitative conversion; they proposed a bridge construction safety risk assessment method based on cloud model theory, provided cloud-based evaluation indicators and cloud scale construction methods, and adopted the improved cloud index method to evaluate bridge construction safety risks. Hitoshi Furuta [14] developed a bridge construction risk fuzzy assessment expert system by combining genetic algorithms and neural networks. Considering the difficulties of obtaining expert knowledge on field bridges, the combined method of GA-NN can more accurately evaluate the risk source level. Jianbo Yuan et al. [15] used the network analysis method to establish a road bridge construction safety risk evaluation model and combined it with the fuzzy comprehensive evaluation method to evaluate the safety risk level of road bridge construction. In the actual assessment process, the existing bridge construction safety risk assessment methods have certain disadvantages, such as an incomplete index system, index weights not matching with the actual engineering, and the assessment results being relatively rough. Therefore, based on the summary of the existing assessment methods, this paper innovatively proposes a highway bridge construction safety risk assessment method based on the cloud entropy weight method.
In this paper, based on the “Analysis of Construction Safety Risk Assessment System and Guidelines for Highway Bridges and Tunnels” [16], the main risk factors during bridge construction are identified from four perspectives: the literature research method, accident causation theory analysis, accident statistical analysis, and construction method analysis. A highway bridge construction safety risk evaluation index system is established, and then the improved cloud entropy weight method is used to objectively assign each risk. The evaluation indexes are then objectively assigned with the traditional weighting method, which fully avoids the subjective arbitrariness of experts’ scoring, and makes the calculated weights reflect both the subjective intention of decision makers and the objective properties of data. Finally, by calculating the evaluation cloud of each risk evaluation index, the standard cloud and the comprehensive cloud digital features can be obtained, and then a comprehensive cloud map and standard cloud map can be generated by the cloud forward generator for visual comparison. Then, the cloud forward generator generates a comprehensive cloud map for visual comparison with the standard cloud map, and calculates the closeness N between the comprehensive cloud and the standard cloud to determine the overall risk of highway bridge construction safety and the evaluation level of the primary risk index. In this paper, this method was applied to a bridge construction safety risk assessment; the overall bridge construction safety risk level was four, and the evaluation levels of the four level 1 risk indicators were all also four. In order to verify the scientificity and effectiveness of the method, this paper also combines the AHP-Extenics method to conduct a comparative study on the construction safety risk evaluation of this bridge. The results of the study are consistent with the evaluation results of the cloud entropy weight method used in this paper, which shows that the method is reasonable.
The research flow of this paper is shown in Figure 1.

2. Selection of Evaluation Indicators

The construction safety risk assessment of highway bridges is a very complex issue. There are many factors affecting the construction safety of bridges, and the interaction between these factors is very complex. Therefore, the accurate and reasonable identification of the risk factors in the bridge construction process, and the systematic and scientific construction of the highway bridge construction safety risk evaluation index system, will directly affect the accuracy of the evaluation results.
This article refers to “Highway Bridge and Tunnel Construction Safety Risk Assessment System and Guidelines Analysis” to establish a bridge construction safety risk level classification standard, and the bridge risk is divided into five levels, X = X 1 , X 2 , X 3 , X 4 , X 5 = level   1 , level   2 , level   3 , level   4 , level   5 ; the higher the level, the worse the corresponding bridge safety status, as shown in Table 1.
In this paper, the main risk factors during bridge construction are identified from four perspectives: the literature research method, accident cause theoretical analysis, accident statistical analysis, and construction method analysis [17]. The sources of risk for highway and bridge construction are decomposed into personnel risk, material and equipment risk, construction environment risk, and construction technology risk. Then, through the theoretical analysis of accident causes, accident statistical analysis, and construction method analysis, the relevant risk indicators of personnel risk, material equipment risk, construction environment risk, and construction technology risk are obtained; the important risk factors in these four aspects are determined, and a safety risk assessment index system is established for highway bridge construction, as shown in Figure 2. In addition, economic contract issues, material and equipment transportation, inadequate safety measures, illegal construction operations, the construction monitoring situation, construction site conditions, and other risk factors can adversely affect bridge construction. Due to the relatively small importance of these factors, and the quantification of their weights being complex and error-prone, this paper does not consider them when establishing the bridge construction risk evaluation index system. Sufficient attention still needs to be paid to the bridge construction process, in order to minimize the level of bridge construction risk as much as possible.

3. Evaluation Method

3.1. Cloud Model Theory

3.1.1. Definition of Cloud Model

The cloud model is a transformation model between qualitative concepts and quantitative measures proposed by academician Deyi Li based on traditional fuzzy set theory and probability statistics, which can reveal the intrinsic correlation between the randomness and fuzziness of things themselves. This model is used to study uncertainty and has been applied in river health evaluation, IoT system performance assessment, bridge, and tunnel durability assessment, etc. [17]. At present, the distribution forms of cloud theory that have been developed include triangular clouds, rectangular clouds, trapezoidal clouds, and normal clouds, among which the normal cloud model is widely used due to its unique mathematical properties and universality [18].
Definition of a normal cloud: let U be a theoretical domain, C be a qualitative concept of U with quantitative values xU, and x be a random realization of C if it satisfies x ~ N(Ex, En2), where En2 ~ N(En, He2), and x satisfies a certain law for the determinacy μ ( x ) of C [19]:
μ ( x ) = e [ ( x E x ) 2 2 ( E n ) 2 ]
where Ex is the expected value, En is the entropy value, and He is the super-entropy value.

3.1.2. Numerical Characteristics of Cloud Model

The cloud model uses the three numerical characteristics of expectation Ex, entropy En, and super-entropy He to comprehensively express a concept of uncertainty [20]:
(1)
Expectation Ex: The mathematical expectation value of the distribution of cloud drops in the domain space, i.e., the value of the domain corresponding to the shape of the center area under the affiliated cloud coverage. The cloud drops belonging to this value are located at the highest point of the cloud map, and the affiliation degree is 1. Expectation Ex is the centralized embodiment of the qualitative concept of things; the closer to the expectation point, the more intensive the aggregation of cloud drops, and the higher the recognition of the index.
(2)
Entropy En: The category of the value of the domain U that the concept can accept, i.e., the measure of the fuzziness of the qualitative concept. Entropy is an important feature used in the cloud model to measure the probability and vagueness of qualitative concepts, reflecting their uncertainty; the larger the entropy value, the more vague the concept is.
(3)
Super-entropy He: The uncertainty measure of entropy, i.e., the entropy of entropy, closely related to the randomness and vagueness of the entropy concept, and used to describe the uncertainty of the concept granularity, reflecting the discrete degree of cloud drops.
The schematic diagram of the cloud model digital features is shown in Figure 3.
The cloud model realizes the transformation of qualitative and quantitative uncertainty, and the transformation result is a random number with a stable tendency, which is not a simple superposition of ambiguity and randomness. Different from traditional probability theory and fuzzy theory, the cloud model fully reflects uncertainty in describing things, weakens human subjectivity, and makes the evaluation results more objective, accurate, and rich [21].

3.1.3. Cloud Model Generator

The cloud model generator realizes the interconversion between qualitative concepts and quantitative representations as the core part of cloud model uncertainty reasoning, which is the basis for realizing cloud model control [22]. The cloud model generator takes mainly two forms: the forward cloud model generator and inverse cloud model generator [23]. The forward cloud generator carries out mapping from the qualitative to quantitative, generating cloud drops from three numerical features of the cloud model (Ex, En, and He), and the inverse cloud generator is a model for realizing uncertainty conversion between quantitative values and qualitative language [24], which efficiently converts a certain amount of precise data into concepts, expressed in proper qualitative language values (Ex, En, and He) [25]. The operations of the cloud model generator are shown schematically in Figure 4.

3.2. Entropy Method

The entropy weight method is an objective weighting method that determines the weight of decision indicators according to the amount of information contained in each indicator value [26]. Generally, if the entropy corresponding to the index value is smaller, it indicates that the degree of variation of the index value, the impact on the comprehensive evaluation, and the weight value are all greater; otherwise, the weight value is smaller.
There are m evaluation objects, denoted as M = M 1 , M 2 , , M m , n evaluation indicators, denoted as N = N 1 , N 2 , , N n , and the value of evaluation object M i on evaluation indicator N j , denoted as r i j i = 1 , 2 , , m ; j = 1 , 2 , , n . The original data matrix R is formed by r i j , where r i j is the evaluation value of the ith object under jth evaluation indicators.
The steps for calculating the weights of each evaluation index using the entropy weighting method are as follows [27]:
(1)
Data standardization
The difference in the dimensional units of the evaluation indicators will affect the evaluation results during the calculation process. Therefore, it is necessary to perform dimensionless processing on the original data and obtain the dimensionless matrix B = b i j m × n .
For the benefit-type index with a more favorable value, the dimensionless processing expression is:
b i j = r i j min j ( r i j ) max j ( r i j ) min j ( r i j )
For the cost index, for which the smaller the value, the more favorable it is, the dimensionless processing expression is:
b i j = max j ( r i j ) r i j max j ( r i j ) min j ( r i j )
where max j ( r i j ) is the maximum value of r i j under the jth evaluation index, and max j ( r i j ) is the minimum value of r i j under the jth evaluation index.
(2)
Calculating the proportion of the ith evaluation object under the jth indicator
p i j = b i j i = 1 m b i j
(3)
Calculating the entropy value of the jth indicator
e j = k i = 1 m p i j ln p i j
K = 1 ln m
The greater the difference in a certain index in the evaluation system, the smaller e j ; the smaller the difference, the greater e j . If e j = 1, this means that the index i has no influence on the evaluation system at this time.
(4)
Calculating the difference coefficient of the information entropy of the jth indicator
d j = 1 e j
(5)
Determining the weight of each evaluation indicator
γ j = d j j = 1 n d j

3.3. Cloud Entropy Weight Calculation Model

The cloud model uses three parameters, Ex, En, and He, to describe the magnitude, oscillation degree and dispersion degree of the values, with essentially the same idea as the entropy concept, but the data connotation is richer and more consistent with the actual distribution [28]. In this paper, we adopt the cloud model and improve it with reference to the entropy method for the variability of indicators, and obtain the improved model for calculating the indicator weights. The subjective judgments of experts are processed into key representative parameters representing uncertainty by the cloud model, and then the improved calculation model obtains a weight distribution that reflects the importance of risk factors as scientifically as possible, through the organic combination of subjective and objective measures [29].
With m experts and n evaluation metrics, the formula for calculating the numerical eigenvalue of the cloud model for the jth evaluation metric is obtained according to the cloud model inverse generator formula, as follows [30]:
E x j = x j ¯ = 1 m i = 1 m x i j
E n j = π 2 × 1 m i = 1 m x i j E x j
H e j = 1 m 1 i = 1 m ( x i j E x j ) 2 E n j 2
where i = 1 , 2 , , m ; j = 1 , 2 , , n , E x j , E n j , H e j are the expected value, entropy value, and super-entropy value of the jth indicator, respectively.
The traditional weight calculation method is used to solve the jth evaluation index weight β j as shown in Equation (12).
β j = E x j j = 1 n E x j   ( j = 1 , 2 , , n )
As can be seen from Equation (12), although the traditional weight calculation method is easy to use, it does not make full use of the entropy change in the cloud model and cannot guarantee the comprehensiveness and objectivity of the results. Based on this finding, we propose an improved entropy weighting method to replace this traditional weighting calculation method.
The cloud entropy weighting method is used to solve the jth evaluation index weight ω j , with the following formula [31]:
ω j = E x j ln ( 1 + E n j ) + 1 1 j = 1 n E x j ln ( 1 + E n j ) + 1   ( En j 0 ) E x j j = 1 n E x j   ( En j = 0 )

3.4. Comprehensive Evaluation Model Based on Cloud Theory

The safety risk assessment of bridge construction is a complex system affected by multi-level factors, and the evaluation subject has strong ambiguity and randomness [32]. In this paper, the cloud model theory is used to evaluate the construction safety risk of a bridge. This risk evaluation model is established on the basis of the bridge construction safety risk evaluation index system. The cloud model is used to improve the weight calculation method in order to calculate and evaluate the weight of each risk evaluation index. The standard and evaluation data are converted into cloud models, and the digital features of the standard cloud, evaluation cloud, and comprehensive cloud are obtained. The forward cloud generator is used to generate and compare the comprehensive cloud map and the standard cloud map, and the closeness between the two maps is calculated. The safety risk level of the bridge construction is comprehensively determined.

3.4.1. Standard Cloud Cm

The standard cloud Cm is a cloud model generated by the evaluation criteria. In the evaluation of bridge construction safety risk, the evaluation criteria are the criteria for the evaluation indexes to judge the severity level of the evaluation target, which can generally be qualitatively expressed in language, or quantitatively expressed in segmental scores. The normal cloud model is used to calculate the standard cloud, and the steps are as follows: the evaluation criteria scores are normalized to obtain the effective theoretical domains U = [ X min , X max ] , X min and X max , which indicate the normalized upper and lower limits of the scores belonging to the evaluation levels, respectively, and the corresponding risk levels can be expressed by the cloud numerical characteristic values [33]. The standard cloud Cm is calculated by normalizing the score intervals of the values of different risk levels, Cm as shown in Equation (14).
E x m = ( X max i + X min i ) / 2 E n m = ( X max i X min i ) / 2.355 H e m = k E n m
In the formula, X min i and X max i represent the upper and lower limit values, respectively, of the score interval corresponding to the risk level i, and k is the coefficient, which is adjusted according to the fuzzy degree of the concept, being generally taken as 0.1.

3.4.2. Evaluation Cloud Cn

Evaluation cloud Cn is a cloud model generated from evaluation data. Each quantitative and qualitative evaluation index is scored according to the evaluation judgment criteria, and the data are quantitatively transformed so that the form of the scored values of both indexes is consistent. The raw evaluation data are passed through the cloud inverse generator to generate the numerical characteristics of the evaluation cloud Cn under this criterion; see Equation (15) [34].
E x n = 1 n i = 1 n x i E n n = 1 n π 2 i = 1 n x i E x n H e n = S 2 + E n n 2
In the formula, x i is the scoring data of the ith expert; S is the standard deviation of the scoring data; E x n is the expected value of the expert scoring; E n n is the expert scoring entropy value; and H e n is the expert scoring super-entropy value.

3.4.3. Integrated Cloud C

Comprehensive cloud C is a parent cloud with deeper meaning obtained by the comprehensive calculation of similar sub-clouds, and its essence is the improvement of concepts [35]. The numerical features of the comprehensive cloud C are obtained by combining the evaluation cloud Cn with the index weight through the fuzzy operator; see Equation (16).
E x = i = 1 m ( E x i × ω i ) E n = i = 1 m ( E n i 2 × ω i ) H e = i = 1 m ( H e i × ω i )  
In the formula, E x i , E n i , and H e i are the evaluation cloud expectation value, entropy value, and super-entropy value of the first index, respectively.

3.4.4. Proximity N

According to the digital features of the calculated comprehensive risk cloud and the standard risk cloud, there is similarity between the generated comprehensive cloud map and the standard cloud map, which may cause a certain visual error in the judgment of the risk evaluation level. Therefore, in order to determine the risk level more accurately, the degree of closeness is used to calculate the degree of closeness between the comprehensive risk cloud and the standard cloud. The greater the degree of closeness, the closer the evaluation result is to the standard risk level.
N = 1 ( E x E x m ) 2
In the formula, N is the closeness of the risk level, E x is the expected value of the comprehensive cloud, and E x m is the expected value of the standard cloud.

4. Project Example Analysis

4.1. Project Overview

A highway bridge spans the first-level tributary of the Yangtze River; the width of the river is approximately 300 m, the water level is level 3, and the water level changes greatly with the season. The bridge site is designed on a circular curve with R = 2500 m. The bridge adopts simple support first, and then continuous. The main bridge structure is a 90 m + 170 m + 90 m variable-section prestressed concrete continuous steel box girder, and the approach bridge is a 30 m T-type simply supported girder bridge.
The geological structure of the area where the bridge is located is stable, and there is no fault structure. After investigation, it was found to be mainly composed of sandstone and siltstone. The bridge section contains soil slopes, mainly composed of gravel and clay. It is easily loosened due to the influence of the river water level, and there are certain hidden risks. The bridge site is located in an area of subtropical monsoon climate, and is affected by the corresponding climatic and environmental conditions. The bridge spans rivers and roads and covers a long distance. The terrain is more dangerous, and risk is likely to occur. The bridge construction does not adopt new technology, with the construction technology being relatively mature. The foundation adopts water drilling platform technology, and the upper structure adopts hanging basket construction.

4.2. Risk Weight Calculation Based on Cloud Entropy Weight Method

Based on the entropy weight method and the need for the accuracy and validity of cloud model generation [35], 10 experts were invited to score the risk indicators based on two principles: risk probability magnitude and risk loss magnitude. The scoring results are shown in Table 2.
After processing the expert scoring results in the above table through the cloud model inverse generator, the expected score E x j , the discrete degree E n j , and the random degree H e j of each risk factor are obtained according to Equations (9)–(11). Then, according to Equation (12), weight β j can be calculated by the traditional weight calculation method, and the improved weight ω j obtained by using the improved entropy weight Equation (13). The results are shown in Table 3.
The analysis of Table 3 shows that the expected value of each risk index has a good distribution, and the interval difference is more obvious; the entropy value and the super-entropy value represent the dispersion degree of the expert opinions. The risk weight value obtained by the weight calculation method is generally 6% to 9%, and the weight value distribution is relatively even. Such a result is not conducive to the distinction of primary and secondary weights, and is not conducive to the judgment of factor importance.
The improved weights of each risk index are sorted from small to large, as shown in Figure 5.
As can be seen from the above figure:
(1)
The ranking of the importance of indicators has not changed much after the improvement, and basically maintains the trend of the original expected value ranking, which fully reflects the opinions of experts.
(2)
The weight distribution is readjusted by the difference in the scoring results, which shows that the improved model makes fuller use of the scoring data results and more effectively reflects the objective scoring situation.
(3)
After the improvement, the difference in the weight distribution becomes larger, and the weight after the improvement is generally between 5% and 11%. The weight range between the top and bottom indicators nearly doubles, which can avoid the problem of averaging weight values.
In summary, the traditional weight calculation method using Equation (12) only uses the expected value Ex in the cloud model for calculation, without making full use of the variation in entropy in the cloud model, and cannot guarantee the objectivity of the results. If the expected values Ex of all indicators are not very different, the calculated weight value will tend to be averaged and cannot objectively reflect the actual situation. However, in fact, the entropy En of each indicator varies greatly. Based on this finding, this paper proposes an improved entropy weighting method of the cloud model shown in Equation (13) to replace this traditional weighting method, which can effectively avoid the problem of averaging the weights of evaluation indicators.

4.3. Risk Assessment Analysis

4.3.1. Determination of Standard Cloud

In this paper, the cloud model is used to evaluate the safety risk of bridge construction. In order to facilitate the expert judgment and scoring, a unified judgment criterion is used. This paper refers to the “Guidelines for Safety Risk Assessment of Highway Bridge and Tunnel Engineering Construction”, and combines the construction site safety specifications and expert opinions. The construction safety risk is divided into five levels according to the possibility and severity of the risk, and is described in qualitative language: extremely low, low, moderate, high, and extremely high.
From the risk level classification standard in Table 1, the standard cloud digital characteristics are calculated by Equation (14), and the standard risk cloud map is generated by the forward cloud generator. The digital characteristics are shown in Table 4, and the standard cloud map is shown in Figure 6.

4.3.2. Determination of Safety Risk Assessment Level in Bridge Construction

In this paper, 10 experts were invited to score the risk indicators. The scoring results are shown in Table 2. According to Equation (15) and the weight determined by the abovementioned cloud entropy weight method, to determine the evaluation cloud digital features, the comprehensive cloud digital features are obtained using Equation (16), and the calculation results are shown in Table 5.
From the weights of the first-level indicators and the comprehensive cloud digital features, the target layer comprehensive cloud digital features can be further calculated. From Equation (16), the target layer comprehensive cloud digital features are (72.166, 15.958, 4.050).
The digital features of the first-level index integrated cloud and the target layer integrated cloud calculated above are used to generate a comprehensive cloud map through the cloud forward generator, which is compared with the standard cloud map to determine the risk level of the target layer and the first-level index. The comparison chart with the standard cloud is shown in Figure 7, Figure 8, Figure 9, Figure 10 and Figure 11.
Due to the similarity between the comprehensive risk cloud and the standard risk cloud, and that fact that one-dimensional graphics can cause visual errors, only the risk level can be determined initially. Therefore, this paper introduces the closeness degree to accurately determine the construction risk level of the bridge; for the calculation result of the closeness degree, see Table 6.
From Figure 7, Figure 8, Figure 9 and Figure 10 it can be seen that the risk level of personnel risk B1 is between level 3 and level 4, being closer to level 4, and the degree of closeness between the B1 comprehensive cloud and level 4 standard cloud is the largest, with a value of 0.305. The risk level of material equipment risk B2 is close to level 4, and the closeness of the B2 comprehensive cloud and level 4 standard cloud is the largest, with a value of 1.440. The risk level of construction environment risk B3 is between level 4 and level 5, being closer to level 4, and the degree of closeness between the B3 comprehensive cloud and level 4 standard cloud is the largest, with a value of 0.137. The risk level of construction technology risk B4 is between level 4 and level 5, being closer to level 4, and the B4 comprehensive cloud is closer to level 4. The closeness of the level 4 standard cloud is the largest, with a value of 0.242. Therefore, the risk levels of the four first-level indicators are all four, and the risk levels are ranked as follows: construction environment risk B3 > construction technology risk B4 > material and equipment risk B2 > personnel risk B1.
According to the comparison chart of the comprehensive cloud and the evaluation cloud of bridge construction safety risk in Figure 11, the overall construction safety risk level of the bridge is between level 4 and level 5, which is very close to the center expectation of level 4, between 61 and 80. The bridge construction safety risk comprehensive cloud has the highest similarity with the four-level standard cloud, so it can be determined that the bridge construction safety risk level is four. Therefore, the formulation of the corresponding control measures during construction shall focus on the abovementioned higher-level safety risk factors.
In conclusion, the entropy weight method in conjunction with cloud model theory has been well tested in the actual safety risk assessment of bridge construction, which reflects the accuracy and applicability of the method, providing a new method for highway bridge construction safety risk assessment.

4.4. Comparative Study

In order to illustrate the rationality and scientificity of the method, this paper uses the AHP-Extenics method to perform a comparative study.

4.4.1. Analytic Hierarchy Process (AHP)

The AHP method is a subjective weighting analysis method that solves problems in which it is difficult to accurately recognize the relative importance of multiple targets. By measuring the relative importance of each target, the weighting can be reasonably quantified, and the weight value can be used to effectively compare the relative importance of each target [36]. The calculation steps of the AHP to determine the weight of the evaluation index are as follows:

Constructing a Judgment Matrix

After stratifying each evaluation index, the relative importance of each index at the same level is compared, and assigned by the method of pairwise comparison to determine the relative importance of each index at the lower level compared with the index at the upper level, so as to obtain the weight of each evaluation index. If a certain layer has n evaluation indicators, the judgment matrix can be constructed as shown in Equation (19) [37].
A = ( a i j ) n × n = a 11 a 1 n a n 1 a n n
where i = 1, 2, , n; j = 1, 2, , n; a i j indicates the judgment result of the comparative importance of two evaluation indicators i and j in criterion A. In this paper, the expert scoring method is used to determine the original data based on the 1–9 scale method [38] to compare the evaluation indicators, which can quantify the relative importance between the two factors. The values and importance relationships are shown in Table 7, values 2, 4, 6, and 8 indicate that the relative factor importance is between two adjacent levels.

Calculating the Weight of the Evaluation Index

The eigenvector β corresponding to the maximum eigenvalue λ max is calculated according to the judgment matrix A obtained by the pairwise comparison of the evaluation indicators; then, the calculation problem of the evaluation index weight is transformed into the problem of solving the eigenvector β of the judgment matrix A. The equation is as follows:
A α = λ max α
In this paper, the square root method is used to calculate the weight, and the specific calculation steps are as follows [39]:
Step 1: Each row of the judgment matrix A is multiplied to obtain u i ; see Equation (20).
u i = j = 1 n a i j , i = 1 ,   2 ,     n
Step 2: u i is squared n times separately to obtain u i ; see Equation (21).
u i = u i n
Step 3: u i is regularized to obtain the feature vector α i ; see Equation (22).
α i = u i i = 1 n u i
Step 4: The maximum characteristic root λ max of the judgment matrix A is calculated; see Equation (23).
λ max = i = 1 n ( A α ) i n α i

Consistency Test

In order to verify the rationality of the above weight calculation, it is necessary to perform a consistency check on the judgment matrix A; the specific steps are as follows [40]:
Step 1: The consistency index C . I . is calculated; see Equation (24).
C . I . = λ max n n 1
where n is the order of judgment matrix A; λmax is the maximum characteristic root of judgment matrix A.
Step 2: The consistency ratio C . R . is calculated; see Equation (25).
C . R . = C . I . R . I .
where R.I. is the average random consistency index, which can be determined by checking Table 8 [41].
According to the consistency test standard, when the consistency ratio C.R. < 0.10, it means that the constructed judgment matrix satisfies the consistency test; otherwise, it is necessary for the experts to re-score and construct a new judgment matrix until the test is satisfied.

4.4.2. Extenics Theory

Extenics theory is a new discipline founded by Cai Wen and other scholars from the Guangdong University of Technology. It uses formal models to study the possibility of things expanding and the laws and methods of innovation, and is widely used in multi-objectives. The comprehensive judgment problem is mainly divided into matter-element theory, extension set theory, and extension logic. Among them, matter-element theory has great advantages in solving the uncertainty and ambiguity of things. Matter-element theory mainly includes the following three parts: the determination of the classical domain and section domain, the determination of the matter-element to be evaluated, and the calculation of the correlation degree of the evaluation index [42].
Let the risk assessment research of highway bridge construction be matter-element R, under which there are m evaluation indexes, and at the same time, each evaluation index u i is divided into n evaluation levels; then, the evaluation index set U = u 1 , u 2 , , u m and the evaluation level set V = v 1 , v 2 , , v n .
(1)
The object element classical domain is denoted as:
R j = ( V j , u i , x i j ) = V j , u 1 , x 1 j u 2 x 2 j u m x m j = V j , u 1 a 1 j , b 1 j u 2 a 2 j , b 2 j u m a m j , b m j
where V j —the jth ( j = 1 ,   2 ,   ,   n ) level of the evaluation object; u i —the ith ( i = 1 ,   2 ,   ,   m ) evaluation index of the evaluation object; x i j —the value of the corresponding u i index when the evaluation object belongs to the jth level; a i j , b i j —the value range when the evaluation object i belongs to the jth evaluation level, that is, the classical domain; a i j is the lower limit of the value of the ith index u i ; and b i j is the upper limit of the value of the ith index u i .
The nodal domain of the object element is expressed as:
R P = [ P , u i , x i P ] = P , u 1 , x 1 P u 2 x 2 P u m x m P = V j , u 1 , a 1 P , b 1 P u 2 a 2 P , b 2 P u m a m P , b m P
where P —the whole of the evaluation level; x i p = a i p , b i p —the range of all values of evaluation index u i , i.e., the section field; a i p is the minimum value of the lower limit of the ith evaluation index u i in all evaluation levels; and b i p is the maximum value of the upper limit of the ith index u i in all evaluation levels [43].
(2)
Determination of the elements to be evaluated
R W = W u 1 x 1 u 2 x 2 u n x n
where W—an object to be evaluated; and x i W for the evaluation of the value range of index u i , the specific index data of the object to be evaluated.
(3)
Calculation of the correlation of the evaluation index
The correlation degree of the construction safety risk level j of the highway and bridge to be evaluated is as follows:
ρ ( x i , x i j ) = x i a i j + b i j 2 b i j a i j 2
ρ ( x i , x i p ) = x i a i p + b i p 2 b i p a i p 2
K j ( x i ) = ρ ( x i , x i j ) ρ ( x i , x i p ) ρ ( x i , x i j )
where K j ( x i ) —the correlation degree of the object to be evaluated when the evaluation level is j.
(4)
Determining the safety risk assessment level of highway bridge construction
Combined with the weight coefficients of each index, and the calculated correlation function value synthesized to obtain the evaluation object’s level of correlation shown in Equation (32), if K max = K j , then the evaluation object belongs to level j.
K j ( W ) = i = 1 n α i K j ( x i )
where α i is the weight value of evaluation index u i ; the larger α i is, the greater the degree of influence of the evaluation index on the evaluation object.

4.4.3. Risk Indicator Weight Calculation

According to the highway and bridge construction safety risk evaluation index system presented in Figure 1, the 1–9 scale method is used to construct the judgment matrix of each level index, and the weight of the highway bridge construction safety risk evaluation index is calculated. The judgment matrices and their weight assignments of the target layer A–B and the criterion layers B1–C, B2–C, and B3–C are listed in Table 9, Table 10, Table 11, Table 12 and Table 13, respectively.
From the calculation results in Table 8, Table 9, Table 10, Table 11 and Table 12, it can be seen that in the safety risk assessment analysis of highway bridge construction, the index weight of the target layer A–B is W A B = 0.195 , 0.231 , 0.426 , 0.148 T , and the index weight of the criterion layer B–C is W B C = (0.195, 0.231, 0.426, 0.148, 0.528, 0.140, 0.333, 0.272, 0.362, 0.255, 0.111, 0.493, 0.196, 0.311, 0.667, 0.333)T. The consistency test indexes of each layer judgment matrix C.R. < 0.1 all meet the consistency requirements. On this basis, the comprehensive weight of each risk index is calculated and then sorted, and the overall ranking of the road and bridge construction safety risk assessment index levels can be obtained. The results are listed in Table 14.
It can be seen from Table 13 that among the safety risk evaluation indicators of highway bridge construction, the type of risk that has the greatest impact on highway bridge construction safety is construction material error C5, followed by temporary structure safety C4, climatic and environmental conditions C9, and material and equipment stacking C6.

4.4.4. Comprehensive Evaluation of AHP-Extenics

In this paper, referring to the “Analysis of Safety Risk Assessment System and Guidelines for Highway Bridge and Tunnel Engineering Construction”, combined with construction site safety regulations and expert opinions, the safety risk of bridge construction is divided into five levels: level 1 (0–20), level 2 (21–40), level 3 (41–60), level 4 (61–80) and level 5 (81–100). From this, it is determined that the construction safety risk level U= {X1, X2, X3, X4, X5} = {level 1, level 2, level 3, level 4, level 5}.
This paper invited 10 experts to score the risk indicators. The scoring results are shown in Table 2. In order to avoid the influence of the subjectivity of experts’ scoring on the evaluation results, this paper takes the expected value of each expert’s score for a certain index to calculate the relevance of the index. The classic domain and section domain in the safety risk evaluation index of highway bridge construction are shown in Table 15, and the expected value of the expert scoring of each evaluation index is shown in Table 16.
From Equations (30)–(32), the correlation degree of the safety risk evaluation index for the construction of highway bridges to be evaluated can be obtained. The calculation results are as follows:
K j ( x i ) = 0.620 0.493 0.240 0.462 0.255 0.448 0.263 0.105 0.087 0.354 0.643 0.523 0.285 0.430 0.231 0.678 0.570 0.355 0.290 0.184 0.738 0.650 0.475 0.050 0.045 0.604 0.472 0.208 0.355 0.270 0.445 0.260 0.110 0.090 0.355 0.691 0.588 0.383 0.235 0.160 0.843 0.790 0.685 0.370 1.423 0.975 0.955 0.744 1.524 0.939 0.713 0.617 0.425 0.150 0.115 0.638 0.517 0.275 0.450 0.237
The subjective weight values of each secondary index calculated by the AHP are WB1–C = (0.528,0.140,0.333), WB2–C = (0.272,0.362,0.255,0.111), WB3–C = (0.493, 0.196, 0.311), and WB4–C = (0.667, 0.333). According to Equation (32), the comprehensive correlation degree of the criterion layer for the evaluation level j of the highway bridge construction safety risk can be calculated as:
K j ( B 1 ) = ( 0.603 , 0.471 , 0.207 , 0.374 , 0.261 ) K j ( B 2 ) = ( 0.655 , 0.539 , 0.309 , 0.177 , 0.174 ) K j ( B 3 ) = ( 0.809 , 0.742 , 0.554 , 0.043 , 0.092 ) K j ( B 4 ) = ( 0.688 , 0.583 , 0.375 , 0.250 , 0.156 )
The weight value of the first-level index obtained by the above AHP is WA–B = (0.195, 0.231, 0.426, 0.148). Similarly, according to Equation (32), the safety risk of the highway and bridge construction can be calculated to obtain the target of the evaluation level j. The comprehensive correlation degree of the layer is:
K j ( A ) = ( 0.715 , 0.619 , 0.403 , 0.032 , 0.153 )
According to the principle of maximum membership, the risk levels of the four first-level indicators of the criterion layer are personnel risk B1 (level 4), material and equipment risk B2 (level 4), construction environment risk B3 (level 4), and construction technology risk B4 (level 4); the overall construction safety risk level of the bridge is also level 4.
In this study, two different methods were used to evaluate the safety risk of bridge construction. The evaluation results are consistent, and the evaluation grades are all four. In the controlled study, the traditional AHP method was used to calculate the weights. Due to the variable level of the experts, it is difficult to ensure the scientificity and accuracy of the weights. In this paper, the cloud model was used to improve the entropy weight method to objectively weight each risk evaluation index, and the subjective judgment of experts was processed into the key representative parameters of uncertainty through the cloud model. The subjective and objective weight distribution, through the organic combination of subjective and objective measures, reflects the importance of each risk factor as scientifically as possible. The cloud map was compared with the standard cloud map, and the closeness of the comprehensive cloud and the standard cloud was calculated to comprehensively determine the risk level of the target layer and the first-level indicators. The evaluation results obtained are consistent with the results determined by AHP-Extenics. Through comparative research, the rationality of the method proposed in this paper is highlighted.

5. Conclusions

Highway bridge construction risk evaluation is an important part of bridge construction, and it is therefore of great significance to propose a scientific and effective highway bridge construction risk evaluation method for the construction safety and normal use of bridges. In this paper, with reference to the literature, we use the cloud entropy power method to evaluate the construction risk of a bridge, and the main conclusions are as follows:
(1)
Referring to the relevant standards and specifications, this paper decomposes the highway bridge construction risk sources into four first-level risk indicators—personnel risk, material and equipment risk, construction environment risk, and construction technology risk—and selects personnel quality, organizational completeness, construction management strength, temporary structure safety, construction material error, material and equipment stacking, machinery failure, geological conditions, climatic and environmental conditions, and natural disasters. Then, the cloud entropy weight method was used to objectively assign weight to each risk indicator, and was compared to the traditional weighting method.
(2)
To determine the evaluation level of highway bridge construction risk factors, the evaluation criteria and evaluation data were transformed into a cloud model, and the forward cloud generator was used to generate and compare a comprehensive cloud map and a standard cloud map. Then, the closeness N between the two maps was calculated to comprehensively determine the bridge construction safety risk levels as follows: personnel risk B1 (level 4), material and equipment risk B2 (level 4), construction environment risk B3 (level 4), construction technology risk B4 (level 4), and overall construction safety risk (level 4). The method proposed here was also combined with the AHP-Extenics method to perform a comparative study, and the assessment results are consistent, which proves that the cloud entropy weight method can be used in the evaluation of highway bridge construction risks with certain scientific validity.
(3)
This paper evaluates the construction risk of highway bridges. Since there are many risk factors affecting bridge construction safety, this paper only selects four primary risk indicators and twelve secondary risk indicators that are more common and have a greater impact on construction safety. There are shortcomings in many aspects, such as the number and importance of the evaluation indicators selected. Therefore, it is necessary to conduct more in-depth exploration and research on the risk assessment of highway bridge construction, in order to move forward in the direction of sustainable development.

Author Contributions

Conceptualization, J.Z. and J.F.; Data curation, Q.L. and J.F.; Investigation, Q.L.; Methodology, J.Z.; Resources, Q.L. and J.Z.; Software, Q.L. and J.F.; Supervision, J.Z.; Validation, Q.L.; Visualization, J.F.; Writing—original draft, Q.L. and J.F.; Writing—review and editing, J.Z. All authors have read and agreed to the published version of the manuscript.

Funding

This research received no external funding.

Institutional Review Board Statement

Not applicable.

Informed Consent Statement

Not applicable.

Conflicts of Interest

The authors declare no conflict of interest.

References

  1. O’Reilly, G.J.; Monteiro, R. On the efficient risk assessment of bridge structures. In Proceedings of the 7th ECCOMAS Thematic Conference on Computational Methods in Structural Dynamics and Earthquake Engineering, Crete, Greece, 24–26 June 2019; pp. 473–483. [Google Scholar]
  2. Cho, T.; Kim, T.S. Probabilistic risk assessment for the construction phases of a bridge construction based on finite element analysis. Finite Elem. Anal. Des. 2008, 44, 383–400. [Google Scholar] [CrossRef]
  3. Agarwal, A.; Sharma, V.; Shukla, V.; Yadav, B.P.; Singh, R. IoT-and NDT-based bridge risk assessment and identification. In Advances in Fire and Process Safety; Springer: Singapore, 2018; pp. 301–310. [Google Scholar]
  4. Wang, L. Research on Safety Risk Assessment and Control of Bridge Construction in Mountainous Areas; Hubei University of Technology: Wuhan, China, 2018. [Google Scholar]
  5. Ongkowijoyo, C.S.; Gurmu, A.; Andi, A. Investigating risk of bridge construction project: Exploring Suramadu strait-crossing cable-stayed bridge in Indonesia. Int. J. Disaster Resil. Built Environ. 2021, 12, 127–142. [Google Scholar] [CrossRef]
  6. Li, Y.C.; Feng, Z.R.; Wang, X.J. Risk assessment of highway bridge construction based on ANP two-dimensional cloud model. J. Wuhan Univ. Technol. 2019, 41, 73–79. [Google Scholar]
  7. Mortazavi, S.; Kheyroddin, A.; Naderpour, H. Risk evaluation and prioritization in bridge construction projects using system dynamics approach. Pract. Period. Struct. Des. Constr. 2020, 25, 04020015. [Google Scholar] [CrossRef]
  8. Abdollahzadeh, G.; Rastgoo, S. Risk assessment in bridge construction projects using fault tree and event tree analysis methods based on fuzzy logic. ASME J. Risk Uncertain. Part B 2015, 1, 031006. [Google Scholar] [CrossRef]
  9. Li, Q.; Zhou, H.; Ma, Q.; Lu, L. Evaluation of Serviceability of Canal Lining Based on AHP–Simple Correlation Function Method–Cloud Model: A Case Study in Henan Province, China. Sustainability 2021, 13, 12314. [Google Scholar] [CrossRef]
  10. Curra, J.; Omidvar, M.; Horine, B. A GIS-Based Platform for Bridge Scour Risk Assessment Using the HYRISK Mode. In Proceedings of the Geo-Congress 2019: Soil Erosion, Underground Engineering, and Risk Assessment, Philadelphia, PA, USA, 24–27 March 2019; American Society of Civil Engineers: Reston, VA, USA, 2019; pp. 11–19. [Google Scholar]
  11. Liu, Y.X. Research on Risk Analysis of Pc Cable-Stayed Bridge During Construction Period; Chang’an University: Chang’an, China, 2013. [Google Scholar]
  12. Nieto-Morote, A.; Ruz-Vila, F. A fuzzy approach to construction project risk assessment. Int. J. Proj. Manag. 2011, 29, 220–231. [Google Scholar] [CrossRef]
  13. Yang, W.J.; Wang, P. Research on bridge construction risk assessment method based on cloud scale and the most unfavorable state. Zhongwai Highw. 2013, 33, 89–93. [Google Scholar]
  14. Furuta, H.; He, J.; Watanabe, E. A fuzzy expert system for damage assessment using genetic algorithms and neural networks. Comput.-Aided Civ. Infrastruct. Eng. 1996, 11, 37–45. [Google Scholar] [CrossRef]
  15. Yuan, J.B.; Cui, G.; Fu, Q.S.; Yu, W.M. Research on safety risk assessment of highway bridge construction based on network analysis method. Sci. Technol. Prog. Countermeas. 2014, 31, 96–100. [Google Scholar]
  16. Analysis of Safety Risk Assessment System and Guidelines for Highway Bridge and Tunnel Engineering Construction; People’s Communications Publishing House, Engineering Quality Supervision Bureau of the Ministry of Transport: Beijing, China, 2011.
  17. Choudhry, R.M.; Aslam, M.A.; Hinze, J.W.; Arain, F.M. Cost and schedule risk analysis of bridge construction in Pakistan: Establishing risk guidelines. J. Constr. Eng. Manag. 2014, 140, 04014020. [Google Scholar] [CrossRef]
  18. Lu, Z.; Wei, C.; Liu, M.; Deng, X. Risk Assessment Method for Cable System Construction of Long-Span Suspension Bridge Based on Cloud Model. Adv. Civ. Eng. 2019, 2019, 5720637. [Google Scholar] [CrossRef]
  19. Ahn, S.; Kim, T.; Kim, J.M. Sustainable risk assessment through the analysis of financial losses from third-party damage in bridge construction. Sustainability 2020, 12, 3435. [Google Scholar] [CrossRef] [Green Version]
  20. Li, Y.C. Research on Safety Risk Assessment Method of Cable-Stayed Bridge Construction Based on Cloud Model; Wuhan University of Technology: Wuhan, China, 2020. [Google Scholar]
  21. Li, W. Evaluation of China’s Dam Break Risk Consequences Based on Cloud Model and Improved Variable Fuzzy Set; Zhengzhou University: Zhengzhou, China, 2019. [Google Scholar]
  22. Choudhry, R.M. Risk Analysis Related to Cost and Schedule for a Bridge Construction Project. In Perspectives on Risk, Assessment and Management Paradigms; IntechOpen: London, UK, 2019. [Google Scholar]
  23. Li, X.; Ran, Y.; Zhang, G.; He, Y. A failure mode and risk assessment method based on cloud model. J. Intell. Manuf. 2020, 31, 1339–1352. [Google Scholar] [CrossRef]
  24. Wang, J.C.; Zhang, F. Risk assessment of deep foundation pit construction based on entropy weight two-dimensional cloud model. J. Saf. Environ. 2018, 18, 849–853. [Google Scholar]
  25. Wang, J.W.; Hu, D.; Wu, H.; Wang, M.Y.; Liu, D.H. Safety risk assessment of shield construction of small-diameter deep drainage tunnels. Chin. J. Saf. Sci. 2020, 30, 113–120. [Google Scholar]
  26. Vaid, S.K.; Vaid, G.; Kaur, S.; Kumar, R.; Sidhu, M.S. Application of multi-criteria decision-making theory with VIKOR-WASPAS-Entropy methods: A case study of silent Genset. Mater. Today: Proc. 2022, 50, 2416–2423. [Google Scholar] [CrossRef]
  27. Delgado, A.; Romero, I. Environmental conflict analysis using an integrated grey clustering and entropy-weight method: A case study of a mining project in Peru. Environ. Model. Softw. 2016, 77, 108–121. [Google Scholar] [CrossRef]
  28. Zhang, P.; Zhong, S.; Zhu, R.; Jiao, M.J. Evaluation of the technical status of stone arch bridges based on entropy weight method-cloud model. J. Zhengzhou Univ. (Eng. Ed.) 2022, 43, 69–75. [Google Scholar]
  29. Andrić, J.M.; Lu, D.G. Risk assessment of bridges under multiple hazards in operation period. Saf. Sci. 2016, 83, 80–92. [Google Scholar] [CrossRef]
  30. Gu, X.B.; Wu, S.T.; Ji, X.J.; Zhu, Y.H. The Risk Assessment of Debris Flow Hazards in Banshanmen Gully Based on the Entropy Weight-Normal Cloud Method. Adv. Civ. Eng. 2021, 2021, 8841310. [Google Scholar] [CrossRef]
  31. Mangalathu, S.; Soleimani, F.; Jeon, J.S. Bridge classes for regional seismic risk assessment: Improving HAZUS models. Eng. Struct. 2017, 148, 755–766. [Google Scholar] [CrossRef]
  32. Tian, Y.F.; Chen, L.J.; Huang, L.W.; Mou, J.M. Featured risk evaluation of nautical navigational environment using a risk cloud model. J. Mar. Eng. Technol. 2020, 19, 115–129. [Google Scholar] [CrossRef]
  33. Wang, K.Y.; Yang, C.F. Application of AHP-DEA in risk assessment of bridge construction. J. Hebei Univ. Technol. 2014, 43, 102–106. [Google Scholar]
  34. Li, Q.; Zhou, H.D.; Zhang, H. Durability evaluation of highway tunnel lining structure based on matter element extension-simple correlation function method-cloud model: A case study. Math. Biosci. Eng. 2021, 18, 4027–4054. [Google Scholar] [CrossRef]
  35. Decò, A.; Frangopol, D.M. Risk assessment of highway bridges under multiple hazards. J. Risk Res. 2011, 14, 1057–1089. [Google Scholar] [CrossRef]
  36. Nurani, A.I.; Pramudyaningrum, A.T.; Fadhila, S.R.; Sangadji, S.; Hartono, W. Analytical hierarchy process (AHP), fuzzy AHP, and TOPSIS for determining bridge maintenance priority scale in Banjarsari, Surakarta. Int. J. Sci. Appl. Sci. Conf. Ser. 2017, 2, 60. [Google Scholar] [CrossRef] [Green Version]
  37. Yang, Y.; Peng, J.; Cai, C.S.; Zhang, J. Improved Interval Evidence Theory-Based Fuzzy AHP Approach for Comprehensive Condition Assessment of Long-Span PSC Continuous Box-Girder Bridges. J. Bridge Eng. 2019, 24, 04019113. [Google Scholar] [CrossRef]
  38. Hummel, J.M.; Bridges, J.F.; IJzerman, M.J. Group decision making with the analytic hierarchy process in benefit-risk assessment: A tutorial. Patient-Patient-Cent. Outcomes Res. 2014, 7, 129–140. [Google Scholar] [CrossRef]
  39. Farkas, A. The use of the AHP in civil engineering projects. In Proceedings of the 8th International Conference on Management, Enterprise and Benchmarking, MEB, Budapest, Hungary, 4 June 2010; pp. 4–5. [Google Scholar]
  40. Chai, J.C.; Wan, Y.L. Analysis on the increase of pier height index in highway bridge construction safety risk assessment system. Highway 2018, 63, 166–172. [Google Scholar]
  41. Ikpong, A.; Chandra, A.; Bagchi, A. Alternative to AHP approach to criteria weight estimation in highway bridge management. Can. J. Civ. Eng. 2021, 48, 1181–1191. [Google Scholar] [CrossRef]
  42. Li, T.; Huang, Y.E.; Xiang, J.; Liu, H.W.; Jiang, H. Durability assessment of cross-sea tied arch bridges based on fuzzy extension sets. J. Cent. South Univ. (Nat. Sci. Ed.) 2021, 52, 2470–2479. [Google Scholar]
  43. Pei, X.W.; Li, H.M.; Li, W.L.; Meng, H.; Li, X. Hazard evaluation of bridge inspection operations based on entropy and matter-element extension. Chin. J. Saf. Sci. 2019, 29, 42–48. [Google Scholar]
Figure 1. Flow chart of the study.
Figure 1. Flow chart of the study.
Applsci 12 08692 g001
Figure 2. Highway bridge construction safety risk evaluation index system.
Figure 2. Highway bridge construction safety risk evaluation index system.
Applsci 12 08692 g002
Figure 3. Schematic diagram of the digital features of the cloud model.
Figure 3. Schematic diagram of the digital features of the cloud model.
Applsci 12 08692 g003
Figure 4. Cloud generator operation schematic.
Figure 4. Cloud generator operation schematic.
Applsci 12 08692 g004
Figure 5. Risk indicator weighting chart.
Figure 5. Risk indicator weighting chart.
Applsci 12 08692 g005
Figure 6. Standard cloud map.
Figure 6. Standard cloud map.
Applsci 12 08692 g006
Figure 7. People risk integrated cloud versus standard cloud.
Figure 7. People risk integrated cloud versus standard cloud.
Applsci 12 08692 g007
Figure 8. Material and equipment risk integrated cloud vs. standard cloud.
Figure 8. Material and equipment risk integrated cloud vs. standard cloud.
Applsci 12 08692 g008
Figure 9. Construction environmental risk integrated cloud vs. standard cloud.
Figure 9. Construction environmental risk integrated cloud vs. standard cloud.
Applsci 12 08692 g009
Figure 10. Construction technology risk integrated cloud vs. standard cloud.
Figure 10. Construction technology risk integrated cloud vs. standard cloud.
Applsci 12 08692 g010
Figure 11. Comparison of bridge construction safety risk integrated cloud and evaluation cloud.
Figure 11. Comparison of bridge construction safety risk integrated cloud and evaluation cloud.
Applsci 12 08692 g011
Table 1. Bridge safety state level classification.
Table 1. Bridge safety state level classification.
Risk LevelLevel 1Level 2Level 3Level 4Level 5
Security situationextremely lowLowmediumhighextremely high
Table 2. Risk indicator scoring results.
Table 2. Risk indicator scoring results.
Risk Indicator12345678910
C1 Personnel quality78806555854368787272
C2 Organizational completeness67704280522360483086
C3 Construction management strength70906589756086406079
C4 Temporary structure safety86845694726758887265
C5 Construction material error65855095967370929074
C6 Material equipment stacking63754079605563868478
C7 Mechanical failure30723280702656704575
C8 Geological conditions85707895946865605880
C9 Climatic environmental conditions758590979680809010081
C10 Natural disasters76593559755681308279
C11 Rationality of the design75928865706065709095
C12 Process maturity60759080556052687595
Table 3. Objective weighting of risk indicators.
Table 3. Objective weighting of risk indicators.
Risk Indicator E x j E x n H e ω j β j
C1 Personnel quality69.60010.1521.7910.0910.082
C2 Organizational completeness55.80023.0116.2430.0590.066
C3 Construction management strength71.40015.8921.7340.0830.084
C4 Temporary structure safety74.20014.4385.0150.0880.088
C5 Construction material error79.00015.6294.2460.0920.093
C6 Material equipment stacking68.30013.5733.0080.0830.081
C7 Mechanical failure55.60024.8784.2120.0580.066
C8 Geological conditions75.30015.4285.1330.0880.089
C9 Climatic environmental conditions87.40010.2022.6000.1140.103
C10 Natural disasters63.20021.0316.5300.0690.075
C11 Rationality of the design77.00014.2885.9560.0920.091
C12 Process maturity71.00015.0403.6170.0840.084
Table 4. Risk evaluation criteria and standard cloud digital features.
Table 4. Risk evaluation criteria and standard cloud digital features.
Risk LevelLevel 1Level 2Level 3Level 4Level 5
Security situationvery lowlowmiddlehighvery high
Risk consequencesIgnorablesmallgeneralseriousessential
Score 0 20 21 40 41 60 61 80 81 100
Cloud digital features 10 , 8.49 , 0.85 30 , 8.49 , 0.85 50 , 8.49 , 0.85 70 , 8.49 , 0.85 90 , 8.49 , 0.85
Table 5. Weights and cloud numerical feature results.
Table 5. Weights and cloud numerical feature results.
First-Level
Indicator
WeightsCloud Digital FeaturesSecondary IndicatorsWeightsCloud Digital Features
B10.233(66.725, 16.277, 2.905)C10.091(69.60, 10.15, 1.79)
C20.059(55.80, 23.01, 6.24)
C30.083(71.40, 15.89, 1.73)
B20.321(70.695, 16.935, 4.133)C40.088(74.20, 14.44, 5.02)
C50.092(79.00, 15.63, 4.25)
C60.083(68.30, 13.57, 3.01)
C70.058(55.60, 24.88, 4.21)
B30.271(77.317, 15.282, 4.423)C80.088(75.30, 15.43, 5.13)
C90.114(87.40, 10.20, 2.60)
C100.069(63.20, 21.03, 6.53)
B40.176(74.141, 14.651, 4.841)C110.092(77.00, 14.29, 5.96)
C120.084(71.00, 15.04, 3.62)
Table 6. Proximity calculation results.
Table 6. Proximity calculation results.
Risk LevelRisk Indicator
B1B2B3B4A
Level 10.0180.0160.0150.0160.016
Level 20.0270.0250.0210.0230.024
Level 30.0600.0480.0370.0410.045
Level 40.3051.4400.1370.2420.462
Level 50.0430.0520.0790.0630.056
Table 7. Relationship between numerical value and importance.
Table 7. Relationship between numerical value and importance.
Numerical ValueImportance
1Equal importance
3Moderate importance of one over another
5Essential or strong importance
7Very strong importance
9Extreme importance
Table 8. Average random consistency index, R.I.
Table 8. Average random consistency index, R.I.
n12345678910
R.I.000.520.891.121.261.361.411.461.49
Table 9. A–B judgment matrix and weight assignment.
Table 9. A–B judgment matrix and weight assignment.
AB1B2B3B4WiConsistency Check
B1110.510.195λmax: 4.0458
B2110.520.231
B322130.426C.R. = 0.0172 < 0.1
B410.50.33310.148
Table 10. B1–C judgment matrix and weight assignment.
Table 10. B1–C judgment matrix and weight assignment.
B1C1C2C3WiConsistency Check
C11320.528λmax: 3.0536
C20.33310.3330.140C.R. = 0.0516 < 0.1
C30.5310.333
Table 11. B2–C judgment matrix and weight assignment.
Table 11. B2–C judgment matrix and weight assignment.
B2C4C5C6C7WiConsistency Check
C411120.272λmax: 4.0813
C511230.362
C610.5130.255C.R. = 0.0304 < 0.1
C70.50.3330.33310.111
Table 12. B3–C judgment matrix and weight assignment.
Table 12. B3–C judgment matrix and weight assignment.
B3C8C9C10WiConsistency Check
C81220.493λmax: 3.0536
C90.510.50.196C.R. = 0.0516 < 0.1
C100.5210.311
Table 13. B4–C judgment matrix and weight assignment.
Table 13. B4–C judgment matrix and weight assignment.
B4C11C12WiConsistency Check
C11120.667λmax: 2.0000
C120.510.333C.R. = 0 < 0.1
Table 14. Total hierarchical ranking of highway bridge construction safety risk evaluation indexes.
Table 14. Total hierarchical ranking of highway bridge construction safety risk evaluation indexes.
Target LayerFirst-Level IndicatorPrimary WeightSecondary IndicatorSecondary WeightComprehensive WeightRank
AB10.195C10.5280.1035
C20.1400.02712
C30.3330.0658
B20.231C40.2720.1162
C50.3620.1541
C60.2550.1094
C70.1110.04710
B30.426C80.4930.0727
C90.1960.1143
C100.3110.04511
B40.148C110.6670.0996
C120.3330.0509
Table 15. Classical and sectional domains in the construction safety risk evaluation index.
Table 15. Classical and sectional domains in the construction safety risk evaluation index.
Evaluation IndicatorsClassic DomainSectional Domain
X 1 X 2 X 3 X 4 X 5
C1~C12 0 , 20 20 , 40 40 , 60 60 , 80 80 , 100 0 , 100
Table 16. Expert scoring expectations for each evaluation index.
Table 16. Expert scoring expectations for each evaluation index.
Evaluation
Indicators
C1C2C3C4C5C6C7C8C9C10C11C12
Scoring
expectations
69.655.871.474.27968.355.675.387.463.27771
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Li, Q.; Zhou, J.; Feng, J. Safety Risk Assessment of Highway Bridge Construction Based on Cloud Entropy Power Method. Appl. Sci. 2022, 12, 8692. https://doi.org/10.3390/app12178692

AMA Style

Li Q, Zhou J, Feng J. Safety Risk Assessment of Highway Bridge Construction Based on Cloud Entropy Power Method. Applied Sciences. 2022; 12(17):8692. https://doi.org/10.3390/app12178692

Chicago/Turabian Style

Li, Qingfu, Jianpeng Zhou, and Jinghe Feng. 2022. "Safety Risk Assessment of Highway Bridge Construction Based on Cloud Entropy Power Method" Applied Sciences 12, no. 17: 8692. https://doi.org/10.3390/app12178692

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop