Next Article in Journal
Foreword to the Special Issue on Terahertz Nondestructive Testing
Next Article in Special Issue
Experimental Study on Electrical Resistivity Characteristics of Saturated Sand Mixes with Bentonite Slurry
Previous Article in Journal
Smart Cooperative Energy Supply Strategy to Increase Reliability in Residential Stand-Alone Photovoltaic Systems
Previous Article in Special Issue
Review on Early Warning Methods for Rockbursts in Tunnel Engineering Based on Microseismic Monitoring
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Dynamic Risk Assessment of Ultra-Shallow-Buried and Large-Span Double-Arch Tunnel Construction

1
College of Civil Engineering, Tongji University, Shanghai 200092, China
2
Key Laboratory of Geotechnical and Underground Engineering of Ministry of Education, Tongji University, Shanghai 200092, China
3
Xiamen Road and Bridge Construction Group Co., Ltd., Xiamen 361026, China
*
Author to whom correspondence should be addressed.
Appl. Sci. 2021, 11(24), 11721; https://doi.org/10.3390/app112411721
Submission received: 12 November 2021 / Revised: 5 December 2021 / Accepted: 8 December 2021 / Published: 10 December 2021
(This article belongs to the Special Issue Tunneling and Underground Engineering: From Theories to Practices)

Abstract

:
Ultra-shallow-buried and large-span double-arch tunnels face complex risks during construction. The risk sources are hidden, complicated, and diverse. The dynamic risk assessment problem cannot be solved satisfactorily by using the static method as an insufficient amount of research has been conducted. The land part of the Xiamen Haicang double-arch tunnel was selected as the background for the dynamic risk assessment of ultra-shallow-buried and large-span double-arch tunnel construction. The construction process was divided into five stages: pre-construction preparation; ground and surrounding rock reinforcement; pilot tunnel excavation; and the single-and the double-tunnel excavations of the main tunnel. Through consultation with tunnel experts, six first-level and thirty second-level risk evaluation indexes were proposed. The benchmark weight of the dynamic risk assessment index was determined by using the analytic hierarchy process. The weight of the risk evaluation index was revised according to the monitoring data and the construction stage. The fuzzy evaluation matrix of the construction risk membership degree was obtained by using the fuzzy comprehensive assessment method, and the calculation results were analyzed using the subsection assignment method. Control measures were suggested according to the risk assessment results. The risk assessment result of the double tunnel excavation stage of the main tunnel was level II, and the risk level was the highest among the five construction stages. The risk assessment result of the ground and surrounding rock reinforcement stage was level IV, and the risk level was the lowest. The dynamic construction safety risk assessment based on the fuzzy comprehensive assessment method is more timely, accurate, and reasonable than the traditional assessment method. The method can be adopted in similar engineering projects.

1. Introduction

The construction of urban underground projects is increasing with the rapid development of urbanization. In recent years, the urban underground transportation system represented by the urban subway and highway networks has developed rapidly [1]. Double-arch tunnels have been widely used in urban underground transportation due to their small footprint, beautiful cross-section shape, and relatively small impact on the surrounding environment [2]. A double-arch tunnel uses a partition wall to connect two adjacent tunnels. This tunnel is characterized by a large excavation span, multiple construction procedures, and complex supporting structures [3]. Double-arch tunnels face various types of risks during the construction process, and these risks gradually develop to be hidden, complicated, and diversified [4,5]. In areas with complex geological conditions, tunnel excavation can easily lead to landslides, water inrush, rock burst, and other accidents [6,7,8], resulting in casualties and economic losses, all of which can subsequently affect the construction schedules. Risk assessment helps identify the risks related to tunnel construction, provides a reference for decision-makers to make appropriate preparations before construction, and reduces the project risks [9]. Therefore, a clear grasp of the potential risk factors is necessary at all times during the construction process, and countermeasures must be determined in advance according to the risk level.
Risk assessment calculates the degree of influence of each factor on the assessment results [10] and is a tool designed to support decision-making in all aspects, from the beginning to the end of the process [11]. Tunnel risk assessment was first proposed by Einstein [12,13]. Subsequently, many studies [14,15,16] were conducted on tunnel risk assessment, and the concept and method of tunnel risk assessment were proposed. Kuang et al. [17] analyzed the risk sources of the Xuefengshan No. 1 deep-buried tunnel and identified the main risk of tunnel construction and those in the construction process. Li et al. [18] selected twelve influencing factors from the aspects of karst hydrogeology, engineering geological conditions, and construction factors as the comprehensive risk evaluation index of karst tunnels and established a comprehensive risk evaluation index system of tunnel collapse, the large deformation of surrounding rocks, water inrush, and mud inrush. Zhang et al. [19] took the collapse risk assessment of mountain tunnels as an example and proposed a collapse risk assessment method on the basis of case-based reasoning, advanced geological prediction, and rough set theory. In recent years the soil steel structure, due to its fast assembly speed, low construction cost, continuous construction, and sustainable development, has been more extensively used in the construction of bridge, culvert and tunnel [20]. The research on the safety of the soil steel bridge, culvert and tunnel has gradually attracted the attention of scholars [21]. Maleska et al. [22,23] successively studied the durability of the soil steel bridge under rock burst and the performance of the steel soil tunnel under a seismic load. Flener′s research [24] shows that the backfilling process, covering depth and sealing depth of the soil steel culvert are important factors that affect the performance of the box culvert. Common risk assessment methods include fault tree analysis, the analytic hierarchy process (AHP), fuzzy comprehensive assessment, grey clustering, and neural network. Hong et al. [25] adopted the event tree analysis method to consider the probability of accidents during construction, studied tunnel construction risks, and put forward countermeasures. Hyun et al. [26] analyzed the risk of adverse events, which may occur during the construction of a shield tunneling machine, using the AHP method and systematically assessed the overall risk level of the shield tunneling machine. Lyu et al. [27] studied the flood risk of a metro system by using the AHP and then proposed an improved trapezoidal fuzzy AHP (FAHP) to evaluate the risk related to the ground subsidence of the infrastructure in Shanghai [28]. The consistency requirements of the comparison matrix in the AHP are difficult to meet. Li et al. [29] analyzed the reasons for the inconsistency and proposed an improved AHP (IAHP), which they applied to subway construction risk identification. Chu et al. [30] selected twelve factors affecting water inrush for the evaluation index system and used the fuzzy comprehensive assessment method to evaluate the water inrush risk of a karst tunnel. Balta et al. [31] proposed a tunnel boring machine project delay risk assessment method based on Bayesian neural network. Kodu et al. [32] proposed a methodology for evaluating the important factor for the fire design of bridges. That proposed important factor was similar to those used to evaluate the wind and snow loads of buildings. Enrico et al. [33] determined important factors by comprehensively considering the concepts of hazard, exposure, and vulnerability. With the progress of society and the increasing complexity of engineering projects, the single assessment method often fails to obtain accurate assessment results. Consequently, risk assessment methods that combine two or more qualitative or quantitative analysis methods have gradually become popular. Deng et al. [34] used the historical data of fifty tunnels and combined the fuzzy method with a neural network to establish a tunnel risk assessment model, which they then applied to the risk assessment of the Tiefodian tunnel. Wang et al. [35] proposed a risk assessment model for coal mine flood emergency logistics by combining the AHP with a neural network. Zhang et al. [36] used the AHP method and fuzzy decision-making to evaluate the collapse risk of ridge tunnels. Lyu et al. [37] combined the interval FAHP with fuzzy cluster analysis to assess the flood risk of a subway system in a sinking environment. Lyu et al. combined the triangular fuzzy number (TFN) and the AHP into a geographic information system to assess the submergence risk of the Shenzhen subway system [38] and applied it to the evaluation of geological disasters [39].
Tunnel construction risk assessment is divided into static and dynamic risk assessments. Static risk analysis mainly focuses on the preliminary stage of the project, supporting a project feasibility study, the selection of construction methods, and the preparation of the project budget. In the construction process, the risks are evaluated and can change, and therefore the assessment results obtained by these models are often different from the actual situation. Therefore, the dynamic risk assessment of construction sites is necessary. Huseby [40] systematically introduced the principle of the dynamic risk analysis model based on the impact graph and DynRisk models of the Monte Carlo principle. At present, an increasing number of scholars are studying dynamic evaluation and have gradually studied dynamic methods after initially proposing the concept of dynamic evaluation. Currently, various methods can be used for specific and operable dynamic evaluation, and the dynamics are mainly achieved through four aspects: introduction of time and assignment of weight [41]; dynamic adjustment of the risk evaluation index system [42]; dynamic adjustment of the weights of risk evaluation indicators [43]; and division of the evaluation process into stages [44]. Wang et al. [45,46] established a dynamic collapse risk assessment method on the basis of the attributed comprehensive assessment model and evaluated the tunnel before excavation, after excavation, and before support. Wang et al. [47] proposed a dynamic risk assessment method based on a Bayesian network in view of the shortcomings of the risk assessment of deeply buried tunnels. Wu et al. [48] established a dynamic risk assessment system, including pre- and post-evaluation models, by using the attribute recognition model and performed risk analysis on sections in tunnels with a high risk of water inrush.
Few studies have been conducted on the dynamic evaluation of urban underground engineering and fewer on the dynamic evaluation of urban shallow-buried and large-span double-arch tunnels. The construction of ultra-shallow-buried and large-span double-arch tunnels is large scale and has high construction risks, and the construction process is divided into several stages. As the construction progresses, the construction environment and geological conditions of the project constantly change. Given these dynamic external factors, the risk factors vary at different construction stages, and the risk also changes and develops dynamically. To comprehensively evaluate the risks during the construction of an ultra-shallow-buried and large-span double-arch tunnel, a dynamic risk assessment of the construction of such tunnel was conducted. As such, the ultra-shallow-buried and large-span double-arch tunnel in the land part of the Xiamen Haicang undersea tunnel in China use selected. The construction process was divided into five stages. On the basis of the traditional fuzzy comprehensive evaluation method, the weights were adjusted according to the construction stage, and the risk dynamic evaluation model was finally constructed. The dynamic risk assessment method can be used as a reference for similar tunnels.

2. Engineering Background

The ultra-shallow-buried and large-span double-arch tunnel of the land part of the Xiamen Haicang Tunnel is located in Huli District, Xiamen City, Fujian Province, China. The entrance of the double-arch tunnel is at the No. 4 working well on the north slope of Xinghu Road. The exit of the tunnel is at the No. 5 working well near the east exit of the Furongyuan underground parking lot on the south side of Xinghu Road. The starting and ending mileages are BK17 + 825 and BK17 + 982, respectively, and the total length is 157 m. The double-arch tunnel underpasses through Xinghu Road, and is a two-way, six-lane urban expressway. The main road of Xinghu Road is crowded with heavy vehicles. Under the road surface, various municipal pipelines, such as water supply, drainage, and power cables, are buried within 2.5 m below the ground and approximately 1.8 m to 3.0 m above the top of the tunnel. Many buildings exist around the tunnel, and the shortest distance from the underground garage of Furongyuan is only approximately 30 m. In the construction range of the underground double-arch tunnel, the surrounding rock is mainly quaternary hybrid fill, silty clay and fully and strongly weathered bedrocks. The roof at the tunnel entrance is in the miscellaneous fill and silty clay layer, and the other main bodies of the tunnel are mainly buried in completely or strongly weathered rocks or residual soil. Figure 1 presents the longitudinal section of the double-arch tunnel. The buried depth of the tunnel is relatively shallow, and the effective pressure arched area cannot form after excavation. Furthermore, the strength of the surrounding rock is low, and its self-stability is poor. Therefore, the stability of the surrounding rock and sidewall of the vault during construction should be a concern. The stability of the rock and soil in the tunnel construction area is poor, and the construction risk is high.
The tunnel is excavated by using three pilot tunnels and the three-bench reserved core soil method. Before excavation, the ground and the surrounding rock are strengthened. The main construction in this stage includes reinforcements, such as ground grouting reinforcement, grouting reinforcement of the rock surrounding the tunnel, concrete mixing pile reinforcement at the entrance, pipe shed construction at the entrance, and advanced support structure construction, and the excavation of the guide and main tunnels. The sequence during pilot tunnel excavation is as follows: the middle; left; and right pilot tunnels. The spacing between the advanced and following pilot tunnels is 20 m. The partition wall is constructed after the excavation of pilot tunnels. Through the analysis of the above construction methods and procedures, the entire construction process can be divided into five stages. The five stages are as follows: the initial stage/preparation stage before construction; Stage 1, ground and surrounding rock reinforcement stage; Stage 2, pilot tunnel excavation stage; Stage 3, main tunnel excavation stage (single tunnel excavation); Stage 4, main tunnel excavation stage (double tunnel excavation).

3. Dynamic Risk Evaluation Index Construction

The risk assessment process of the construction process of shallow-buried and large-span double-arch tunnel is as follows: (1) The construction risks of urban ultra-shallow-buried and large-span double-arch tunnels are identified using two aspects, risk type identification and risk factor identification, and the risk evaluation index suitable for shallow-buried and large-span double-arch tunnel is then proposed; (2) According to the actual working conditions on site and expert opinion, the primary and secondary risk evaluation indexes are weighed up and determined by using the AHP. The weights of risk evaluation indicators are revised according to changes in the monitoring data and construction status; (3) Determine the quantitative value of the membership degree of the construction dynamic risk evaluation index according to expert opinion, and then use the membership degree function to ensure the fuzzy evaluation matrix is composed of these indexes in each stage; (4) According to the weight and membership degree of the second-level risk evaluation index in each construction stage, fuzzy calculation is carried out to obtain the first-level comprehensive evaluation matrix. According to the weight of first-level risk evaluation index and first-level comprehensive evaluation matrix, the second-level comprehensive evaluation matrix is obtained by fuzzy calculation; (5) A quantitative analysis of fuzzy comprehensive evaluation results is conducted.
The establishment of a risk evaluation index system is an important link to risk assessment. The rationality of the index system directly affects the reliability of risk assessment results. The selection of risk evaluation indexes is based on the following criteria: objective; scientific; systematic; comprehensive; easy to quantify; and reflect the research content. The risk evaluation index is determined on the basis of the risk identification results, the risk types, and the risk factors. Risk identification can be divided into risk type identification and risk factor identification. According to the main risk types and risk factors, dynamic construction risk evaluation indexes suitable for urban ultra-shallow large-span double-arch tunnels can be further determined. The construction risk types of urban shallow-buried and concealed double-arch tunnels are divided into tunnel collapse, water and sand penetration, mechanical injury, surrounding environment damage, structural damage, electric shock, fire, explosion, poisoning, and suffocation. According to the key characteristics of the design and construction of urban shallow-buried large-span tunnels [49] and the opinions of tunnel experts, the main risk factors in the construction of urban ultra-shallow buried large-span double-arch tunnels include the engineering geology and hydrogeology, the surrounding construction environment, the overall engineering design, the engineering construction technology, and the engineering construction management. To help risk assessors with indicator weighting, risk classification, and other tasks in the follow-up work, the risk evaluation indexes should be divided into several levels according to a certain logic, which are generally called first-level indexes, second-level indexes, and so on. According to existing research [7,18,49] and the opinions of tunnel experts, the first-level index (Ui) in the construction risk evaluation system of urban shallow-buried large-span double-arch tunnels was divided into six aspects: engineering geology and hydrogeology; surrounding construction environment; overall engineering design; engineering construction technology; engineering construction management; and monitoring measurement data. Given that monitoring measurement data should be obtained in the construction stage, this indicator is only used during construction, and only the first five indexes need to be used in the preparation stage before construction. Then, the first-level indexes were divided into the corresponding second-level indexes (Uij), which are the j-th second-level indexes of the i-th first-level index. Finally, an urban shallow-buried large-span double-arch tunnel construction dynamic risk evaluation index system composed of six first-level indexes and thirty second-level indexes was established, as shown in Figure 2.

4. Construction Dynamic Risk Evaluation Index Weight

4.1. Benchmark Weight Determination

According to the existing risk assessment hierarchical system, the commonly used and effective AHP method is used to determine the weight of the indexes. The AHP is a systematic analysis method that combines qualitative and quantitative analyses. The AHP hierarchizes the problem, decomposes it into different components, and combines them in hierarchical clusters according to their mutual influence and affiliation. A judgment matrix is formed by comparing the relative importance of the indexes at each level. The relative importance of each index is quantified using a certain digital scale, which is called the judgment scale, between two indexes. The most commonly used judgment standard would use the numbers 1–9 to represent the relative importance of the indexes, that is, one represents equal importance, and nine represents extreme importance [50]. The degree of importance increases with the digital value, and the criteria are listed in Table 1.
The importance of each evaluation index at the same level is compared in pairs in order to construct a judgment matrix. Assuming n factors U1, U2, …, Un in a level, scale aij with a value of 1–9 is used to reflect the relative importance of the comparison between Ui and Uj, and an n-th order judgment matrix is obtained, as shown in Equation (1).
A = [ a 11   a 1 n                 a n 1   a n n ]
The maximum eigenvalue (λmax) and eigenvector (W) of the judgment matrix are obtained, and the eigenvector is normalized to obtain the relative weight of the risk indexes at the same level. Then, the consistency test is carried out to determine the logical rationality of the judgment matrix. The random consistency ratio (CR) is used to check the consistency of the judgment matrix. When CR is less than 0.1, the requirement is met.
C R = C I R I ,
where RI is the average random consistency index value of the judgment matrix, as shown in Table 2. CI is the consistency index, which can be calculated by Equation (3).
C I = λ max n n 1 .
Ten experienced tunnel design, geological exploration, and tunnel construction experts were selected in order to form an evaluation team. Through the table comparison method [51], the experts scored the importance of each level of risk factors. According to the experts’ replies, a judgment matrix was constructed. According to the AHP method, the relative weights of the first- and second-level risk evaluation indexes were calculated, and the results are shown in Table 3 and Table 4.

4.2. Base Weight Correction

During construction, the pairwise judgment relationship of the risk evaluation indexes at the same level may change. To ensure the accuracy of the construction risk assessment results, the benchmark weights should be corrected according to the construction stage. According to reference [49] and relevant specifications and expert opinions, the construction stage of each risk assessment index was quantified. The classification standard for the change in construction stage of each index can be based on the reference value of the risk evaluation index classification standard, as shown in Table 5.
After scoring the risk evaluation index according to the construction state, a vector was obtained and normalized to obtain the weight correction vector X (x1, x2, …, xi). xi is the normalized value of the construction state of the risk evaluation index. The benchmark weight can be modified according to Equation (4).
Y i ( X ) = y i x i 1 2 i = 1 m y i x i 1 2 ,
where Yi(X) is the weight correction value of each risk assessment index, and yi is the initial weight value.
According to monitoring data and the changes in the construction at each stage, the benchmark weights of the risk assessment indicators were adjusted, as shown in Table 6.

5. Fuzzy Comprehensive Assessment

The fuzzy comprehensive assessment method is a comprehensive assessment method based on fuzzy mathematics. The basic principle of the comprehensive assessment method is to quantitatively analyze and comprehensively evaluate the risk factors that have unclear boundaries and are difficult to quantify according to the membership theory of fuzzy mathematics; that is, using fuzzy mathematics to make an overall assessment of the things or objects restricted by many factors. Using this method, the assessment set of a group of risk evaluation indexes was determined first. Then, the weight of each index and their membership degree were determined to obtain the fuzzy evaluation matrix. Finally, the weight vector and the fuzzy evaluation matrix were used in the fuzzy operation and normalization processing to obtain the fuzzy comprehensive assessment results.

5.1. Determine Comment Set

According to the principle of the fuzzy comprehensive assessment method, the comment set of the risk evaluation index must be determined before calculating the membership degree. The risk evaluation index comment set is a description of the risk grade and severity and a form of risk quantification. According to the actual construction risks of urban shallow-buried large-span double-arch tunnels, the risk assessment indexes can be divided into five levels: safe; relatively safe; generally safe; relatively dangerous; and dangerous. Figure 3 shows the risk comment level and the corresponding quantitative interval of the urban shallow-buried large-span double-arch tunnel construction process.

5.2. Determine the Fuzzy Evaluation Matrix

Referring to the research results of other experts and scholars [49], the trapezoidal function was used to determine the membership degree in the urban shallow-buried large-span double-arch tunnel. Equations (5)–(9) are the membership function relationships of the method.
u 1 ( x ) = { 0 x 2.5 2.5 x 1.5 x 2.5 1 x < 1.5 ,
u 2 ( x ) = { 0 x < 1.5 x 1.5 1.5 x < 2.5 1 2.5 x < 3.5 4.5 x 3.5 x < 4.5 0 x 4.5 ,
u 3 ( x ) = { 0 x < 3.5 x 3.5 3.5 x < 4.5 1 4.5 x < 5.5 6.5 x 5.5 x < 6.5 0 x 6.5 ,
u 4 ( x ) = { 0 x < 5.5 x 5.5 5.5 x < 6.5 1 6.5 x < 7.5 8.5 x 7.5 x < 8.5 0 x 8.5 ,
u 5 ( x ) = { 1 x 8.5 x 7.5 7.5 x < 8.5 0 x 7.5 ,
According to the risk assessment index classification standard and quantification interval and the actual situation of each construction stage of the project, the expert survey method was used to evaluate the quantitative value of the membership degree of the risk evaluation indexes in the pre-construction preparation stage and each construction stage.
The quantitative value of the membership degree of the risk evaluation indexes obtained according to the experts’ replies are shown in Figure 4.
The obtained standard of risk assessment index membership degree was substituted into the trapezoidal membership function formula for calculation, and the fuzzy evaluation matrix composed of these indexes was obtained at each construction stage, as shown in Table 7.

5.3. Results and Analysis of Fuzzy Comprehensive Assessment

The dynamic risk evaluation model for the construction of the urban shallow-buried large-span double-arch tunnel can be expressed by Equation (10):
[ B ] t = [ w ] t [ B 1 B 2 B 5 ] = [ w ] t { [ w 1 w 2 w 5 ] [ D 1 D 2 D 5 ] } ,
where [ w i ] t is the weight vector of the second-level risk evaluation index at t, and [ D i ] t is the fuzzy evaluation matrix of the second-level risk evaluation index at t. [ w ] t is the weight vector of the first-level risk evaluation index at t, [ B i ] t is the fuzzy evaluation matrix of the first-level risk evaluation index at t, and [ B ] t is the second-level comprehensive evaluation matrix at t. [ B i ] t and [ B ] t reflect the result of the fuzzy comprehensive assessment. ○ is the fuzzy composition operator, and the operations of the fuzzy composition operator can be divided into three categories: taking the larger; taking the smaller; and weighted average.
[ B ] t is the final calculation result of the fuzzy comprehensive assessment method, and its essence is still a fuzzy vector. The result should be clarified in order to analyze the risk evaluation and level. The commonly used methods are the maximum membership, median, and subsection assignment methods.
The calculated results of the fuzzy comprehensive assessment can be obtained by the fuzzy synthesis of the dynamic weights of the risk evaluation indexes and the fuzzy evaluation matrix. Among them, the fuzzy synthesis operator adopts the weighted average operator, which can comprehensively consider the effects of various factors. After the calculation, the subsection assignment method, which can comprehensively consider the calculation results of each risk level, is used to verify the calculation results.

5.3.1. First-Level Fuzzy Comprehensive Assessment

The weighted average operator was used to synthesize the obtained dynamic weight of the second-level risk evaluation index and the fuzzy evaluation matrix to obtain the first-level evaluation matrix at each stage, as shown in Table 8.

5.3.2. Second-Level Fuzzy Comprehensive Assessment

According to the weight of the first-level risk evaluation index and the first-level evaluation matrix of each stage, the evaluation matrix composed of the second-level comprehensive evaluation vectors of each stage can be obtained by fuzzy calculation, as shown in Table 9.
The calculation results were analyzed using the subsection assignment method. The risk evaluation level was divided into five grades: safe; relatively safe; generally safe; relatively dangerous; and dangerous. As such, a certain quantitative score was given to each level, as shown in Figure 5. The risk level was divided into five levels according to the range where the score was calculated, as shown in Figure 6.
As shown in Figure 6, when Q ≤ 3, the risk level was class V, indicating a very low level of risk and a negligible acceptance degree at this stage, where risk treatment measures were unnecessary. When 3 ≤ Q < 5, the risk level was IV, indicating low risk and a tolerable acceptance level at this stage. The risks should be monitored at all times for all the monitoring indicators specified, however risk treatment measures were still unnecessary. When 5 ≤ Q < 7, the risk level was III, indicating that the risk evaluation conclusion at this stage was a medium/acceptable risk, and the risk occurrence probability and risk loss were high, yet within the controllable range. This level of risk must be given attention, and necessary risk treatment measures should be taken while strengthening the monitoring. When 7 ≤ Q < 9, the risk level was II. This kind of risk is major and is not expected to occur. The probability of risk occurrence was high, and the risk loss was large, requiring great attention. When Q ≥ 9, the risk level was I, which is unacceptable. The risk occurrence probability was greater than that of the level II risk, and the loss was unacceptable. A series of measures must be taken in advance to avoid its occurrence or further deterioration.
If the assessment result is at level I risk, the construction shall be stopped immediately, and comprehensive rectification shall be carried out to reduce the risk assessment level. Through the assignment calculation, the pre-construction preparation stage of the shallow-buried large-span double-arch tunnel and the risk evaluation score (Q) of each stage during the construction process were finally obtained. Then, the risk evaluation and risk acceptance levels of each stage can be obtained by referring to Figure 6. The specific results are shown in Figure 7.
The risk evaluation result in the initial stage was level III, indicating that the tunnel construction project was generally at a medium risk level, and the formulation of perfect risk prevention policies and risk treatment measures was therefore necessary, and the monitoring items required by the specification (such as ground settlement, pipeline deformation, vault settlement, surrounding rock pressure, and anchor rod axial force) required monitoring. The risk evaluation result of stage 1 (ground and surrounding rock reinforcement) was level IV. The risk at this stage was low, requiring no risk treatment measures. The risk evaluation results of stage 2 (pilot tunnel excavation) and stage 3 (main tunnel single tunnel excavation) were both level III. During the construction process, attention must be given to the changes in monitoring data to avoid risks in a timely manner. The risk evaluation result of stage 4 (main tunnel double tunnel excavation) was level II, and the risk level was relatively high. The risk at this stage must be given great attention. The monitoring encrypted the monitoring control points, improved the monitoring frequency, and reduced the risk by strengthening management and risk treatment measures.
The risk assessment result of the traditional static fuzzy comprehensive assessment method for this project was level III. The risk prevention policies and risk treatment measures formulated according to level III risk during construction undoubtedly caused the waste of social resources in the ground and surrounding rock reinforcement stage and led to insufficient risk prevention awareness and protection measures in the main tunnel double tunnel excavation stage. The dynamic construction safety risk assessment based on the fuzzy comprehensive assessment method is more timely, accurate, and reasonable than the traditional assessment method. Dynamic construction safety risk assessment can accurately grasp the potential risks in each construction stage, reduce the occurrence of safety accidents in the construction process, and save social resources.

6. Risk Control of Shallow Buried Large-Span Double-Arch Tunnel

According to the construction risk assessment results, the construction risk was high in the main tunnel excavation and pilot tunnel excavation stages. Therefore, reasonable, effective, and feasible measures should be taken to reduce the probability of risk occurrence and the loss caused by risk. The corresponding risk control measures include engineering geology and hydrogeology, surrounding environment, engineering design scheme, and engineering construction and management.
For the construction risks of shallow-buried large-span double-arch tunnels caused by engineering geology and hydrogeological conditions, the following risk control measures can be taken: (i) Strengthening of the advanced geological prediction. During construction, the geological conditions in front of the tunnel excavation face shall be explored by flat drilling, geophysical exploration, and other methods, and corresponding preventive and treatment measures shall be taken according to the detection results, as shown in Figure 8; (ii) Strengthening of the advance support measures. The advance long pipe shed shall be erected at the portal, as shown in Figure 9. During tunnel excavation, the advanced long pipe shed and small conduit shall be simultaneously constructed to ensure the stability of the surrounding rock near the tunnel excavation surface and prevent collapse accidents; (iii) Strengthening the ground reinforcement. To control the nearby ground settlement deformation caused by tunnel construction and the structural deformation caused by the vehicle load on the underground tunnel, the subgrade slope in the Xinghu section above the tunnel excavation area is reinforced by grouting; (iv) Strengthening the monitoring and the measurement. During tunnel excavation, the monitoring and measurement of the ground, vault, groundwater level, surrounding pipelines, soil pressure, and support structure shall be strengthened, and the measured data shall be fed back to the construction and design in a timely manner to adjust the construction method, the construction process, the support structure type, and the design parameters; (v) Full-section curtain grouting is considered as reinforcement for the fault fracture zone. A fault fracture zone exists at BK17 + 890~BK17 + 930 in the underground excavation section of the project. The rock mass strength is lower than the surrounding rock mass, and the stability is poor. When the tunnel is excavated to this section, groundwater leakage and tunnel collapse may occur. Full-section curtain grouting reinforcement technology is used to send the prepared cement grout to the rock mass in front of the excavation through the grouting borehole laid in advance. After the slurry is diffused and solidified, the physical and mechanical properties of the surrounding rock can be improved, as shown in Figure 10.
To ensure that the construction of shallow tunnels can be carried out safely and smoothly, under the premise of the continued normal use of the surrounding buildings, expressways, and underground pipelines, the following measures can be taken for risk control: (i) Detailed underground pipeline protection measures and an emergency treatment plan should be formulated before tunnel construction, and sufficient anti-collapse and anti-leakage materials should be prepared to ensure that small leakage or collapse events can be handled in a timely manner to prevent worse accidents; (ii) Before construction, preventive measures must be taken with regard to the surrounding buildings and monitoring schemes during the construction period shall be formulated, and the settlement and deformation of surrounding buildings shall be investigated and monitored in a timely manner during construction; (iii) The subgrade slope surface and slope toe within the influence range of tunnel construction shall be reinforced by surface vertical grouting in advance, and the measures of transverse grouting reinforcement shall be adopted within the main traffic lane.
The reliability of the engineering design scheme determines whether the project can be carried out smoothly. In terms of the engineering design scheme, the following risk control measures can be taken: (i) Tunnel location selection, linear design, cross-section design, and support structure design should be carried out in strict accordance with the highway tunnel design specifications; (ii) Independent design schemes should be specially written for the important and difficult parts of the project, such as the ground surface reinforcement design plan, three-pilot-tunnel excavation and support design plan, and partition wall force optimization plan; (iii) Experts in highway tunnels must be organized to review the design scheme and drawings. In the field implementation process, dynamic analysis of data must be carried out in combination with results monitoring, and the design scheme should be modified and improved in real time according to the data analysis results to realize dynamic design.
In terms of project construction and management, relevant measures can be taken to strengthen the quality management, the organization management, and the safety management. The specific measures are as follows: (i) During construction, the excavation step distance shall be strictly controlled to approximately 2 m to prevent over excavation and under excavation. The distance between the upper steps of the three pilot tunnels should be kept at 20 m, and the distance between the steps of the left and right main tunnels should be kept at 30 m; (ii) After excavation, spray-anchor support should be carried out on time to reduce the stress release time of the surrounding rock and prevent the excessive deformation of the surrounding rock. After excavating the entire section, the invert and the secondary lining structure shall be constructed on time to make the supporting structure close into a ring as soon as possible; (iii) During tunnel excavation and supporting structure construction, the monitoring and measurement of the tunnel vault, clearance convergence, surrounding rock pressure, and supporting structure stress must be strengthened; (iv) The professional skills and quality construction training system of construction personnel must be improved.
During the construction period, all monitoring items ran normally, and no abnormal phenomenon or safety accidents occurred in the monitoring data. During the entire construction period of the shallow-buried tunnel, the driving conditions on Xinghu Road and the production and life of residents in the surrounding communities were unaffected. Finally, the project was successfully completed and accepted by the experts and relevant departments. The results show that the risk assessment methods used in this paper, the risk assessment results obtained, and the risk control measures proposed are reasonable and effective.

7. Conclusions

The main problem that faced this study was to overcome the deficiency of static risk assessment in an ultra-shallow-buried large-span double-arch tunnel. Xiamen Haicang double-arch tunnel was selected as an example, and the dynamic risk assessment was investigated for the ultra-shallow-buried large-span double-arch tunnel construction. Firstly, the construction process was divided into five stages, and the dynamic risk evaluation index system was established. Then the benchmark weight of the dynamic risk evaluation index was determined by AHP, and the weight of risk evaluation index was modified according to the construction stage. The risk evaluation indexes of the different construction stages were determined differently, and the weights of the risk evaluation indexes at the same level were changed during the construction process. The changes in weights affected the risk assessment results. Finally, the fuzzy comprehensive evaluation method was adopted to evaluate the risk of each stage, and the risk control measures were suggested. Therefore, the following conclusions can be drawn:
(1) Dividing the construction into different stages for risk evaluation according to the construction process and the key construction nodes improved the accuracy, timeliness, and rationality of the dynamic evaluation results;
(2) The risk assessment result of the main tunnel double tunnel excavation stage was level II, and the risk level was high. The risk assessment result of the ground and surrounding rock reinforcement stage was level IV, and the risk in this stage was low. The risk assessment results of the other stages were level III, and the risk was medium;
(3) In the pre-construction preparation stage, comprehensive risk prevention policies and risk treatment measures should be formulated, and the monitoring of the items required by the specification during the project must be strengthened. No risk treatment measures were needed at the surface and surrounding rock reinforcement stage. During the construction of pilot tunnel and single tunnel excavation stages of the main tunnel, attention should be given to the changes in monitoring data. Great attention must be given to the risk in the excavation stage of the double tunnels of the main tunnel;
(4) The dynamic construction safety risk assessment based on the fuzzy comprehensive assessment method is more timely, accurate, and reasonable than the traditional assessment method. Dynamic risk assessment can promptly discover and prevent hidden dangers in the construction of shallow-buried tunnels.
Summarizing the research performed above, it can be concluded that the dynamic risk assessment of the Xiamen Haicang tunnel objectively reflected the dynamic risks. However, the dynamic risk identification of an ultra-shallow-buried and large-span double-arch tunnel construction maybe complex and uncertain. The influencing factors are normally determined by the experience of experts. The dynamic assessment currently depends on quantitative work. In the future, random field theory and probability method can be introduced to describe the risks, quantitative methods including artificial intelligence (AI), big data, digital technology, and AI monitoring can be involved in the dynamic assessment to identify the number of risk factors and improve the accuracy of risk assessment.

Author Contributions

J.W., Z.W. and A.C. carried out the main research task and wrote the manuscript. J.W. proposed the original idea and contributed to the revision of the obtained results and of the whole manuscript. Z.S., X.L. (Xiao Lin), L.S. performed utilization on-site. W.L., X.L. (Xiaotian Liu), H.L., Y.S. and Y.L. performed the investigation. All authors have read and agreed to the published version of the manuscript.

Funding

This research was funded by the Shanghai Municipal Science and Technology Project (18DZ1201301; 19DZ1200900); Xiamen Road and Bridge Group (XM2017-TZ0151; XM2017-TZ0117); the project of Key Laboratory of Impact and Safety Engineering (Ningbo University), Ministry of Education (CJ202101); Shanghai Municipal Science and Technology Major Project (2021SHZDZX0100) and the Fundamental Research Funds for the Central Universities; Key Laboratory of Land Subsidence Monitoring and Prevention, Ministry of Natural Resources of the People’s Republic of China (No. KLLSMP202101); Suzhou Rail Transit Line 1 Co. Ltd. (SURT01YJ1S10002); China Railway 15 Bureau Group Co. Ltd. (CR15CG-XLDYH7-2019-GC01); the National Natural Science Foundation of China (grant No. 41907230).

Data Availability Statement

The data presented in this study are available on request from the corresponding author.

Conflicts of Interest

The authors declare no conflict of interest.

References

  1. Cui, J.Q.; Nelson, J.D. Underground transport: An overview. Tunn. Undergr. Space Technol. 2019, 87, 122–126. [Google Scholar] [CrossRef]
  2. Hamidreza, V.; Fatemeh, M.; Amir, R. Modified dynamic stress concentration factor for twin tunnels using a novel approach of FEM-scattering. Tunn. Undergr. Space Technol. 2017, 70, 30–41. [Google Scholar] [CrossRef]
  3. Wang, H.N.; Zeng, G.S.; Sutilt, S.; Jiang, M.G.; Wu, L. Analytical solutions of stresses and displacements for deeply buried twin tunnels in viscoelastic rock. Int. J. Rock Meck. Min. 2017, 93, 13–29. [Google Scholar] [CrossRef]
  4. Kim, Y.G. Application of risk analysis and assessment in tunnel design. Int. J. JCRM 2014, 5, 11–18. [Google Scholar] [CrossRef]
  5. Moradi, M.R.; Farsangi, M.A.E. Application of the risk matrix method for geotechnical risk analysis and prediction of the advance rate in rock TBM tunneling. Rock Mech. Rock Eng. 2014, 47, 1951–1960. [Google Scholar] [CrossRef]
  6. Shin, H.S.; Kwon, Y.C.; Jung, Y.S.; Bae, G.J.; Kim, Y.G. Methodology for quantitative hazard assessment for tunnel collapses based on case histories in Korea. Int. J. Rock Mech. Min. Sci. 2009, 46, 1072–1087. [Google Scholar] [CrossRef]
  7. Li, S.C.; Wu, J.; Xu, Z.H.; Li, L.P. Unascertained measure model of water and mud inrush risk evaluation in karst tunnels and its engineering application. KSCE J. Civ. Eng. 2016, 21, 1170–1182. [Google Scholar] [CrossRef]
  8. Li, N.; Feng, X.; Jimenez, R. Predicting rock burst hazard with incomplete data using Bayesian networks. Tunn. Undergr. Space Technol. 2017, 61, 61–70. [Google Scholar] [CrossRef]
  9. Evbuomwan, P.O.; Yu, D.M. Theoretical and practical risk assessment method in tunneling. Adv. Mater. Res. 2011, 255–260, 3953–3957. [Google Scholar] [CrossRef]
  10. Zhu, K.Y. Fuzzy analytic hierarchy process: Fallacy of the popular methods. Eur. J. Oper. Res. 2014, 236, 209–217. [Google Scholar] [CrossRef]
  11. Rundmo, T.; Nordfjærn, T.; Iversen, H.H.; Oltedal, S.; Jørgensen, S.H. The role of risk perception and other risk-related judgements in transportation mode use. Saf. Sci. 2011, 49, 226–235. [Google Scholar] [CrossRef]
  12. Einstein, H.H.; Labreche, D.A.; Markow, M.J.; Baecher, G.B. Decision analysis applied to rock tunnel exploration. Eng. Geol. 1978, 12, 143–161. [Google Scholar] [CrossRef]
  13. Einstein, H.H. Risk and risk analysis in rock engineering. Tunn. Undergr. Space Technol. 1996, 11, 141–155. [Google Scholar] [CrossRef]
  14. Sturk, R.; Olsson, L.; Johansson, J. Risk and decision analysis for large underground projects, as applied to Stoekholm Ring Road tunnels. Tunn. Undergr. Space Technol. 1996, 11, 157–164. [Google Scholar] [CrossRef]
  15. Reilly, J.J. The management process for complex underground and tunneling projects. Tunn. Undergr. Space Technol. 2000, 15, 31–44. [Google Scholar] [CrossRef]
  16. Choi, H.H.; Cho, H.N.; Seo, J.W. Risk assessment methodology for underground construction projects. J. Constr. Eng. Undergr. Manag. 2004, 130, 258–272. [Google Scholar] [CrossRef]
  17. Kuang, X.; Yi, D.Q.; Wang, C.L. Study on construction risk assessment method of deep buried tunnels. Appl. Mech. Mater. 2013, 405–408, 1305–1308. [Google Scholar] [CrossRef]
  18. Li, S.C.; Wu, J. A multi-factor comprehensive risk assessment method of karst tunnels and its engineering application. Bull. Eng. Geol. Environ. 2019, 78, 1761–1776. [Google Scholar] [CrossRef]
  19. Zhang, G.H.; Jiao, Y.Y.; Chen, L.B.; Wang, H.; Li, S.C. Analytical model for assessing collapse risk during mountain tunnel construction. Can. Geotechnol. J. 2016, 53, 326–342. [Google Scholar] [CrossRef]
  20. Embaby, K.; Naggar, M.H.; Sharnouby, M. Response evaluation of large-span ultradeep soilsteel bridges to truck loading. Int. J. Geomech. 2021, 21, 04021186. [Google Scholar] [CrossRef]
  21. Amer, W.; Lars, P.; Raid, K. FEM simulation of a full-scale loading-to-failure test of a corrugated steel culvert. Steel Compos. St. 2018, 27, 217–227. [Google Scholar] [CrossRef]
  22. Maleska, T.; Beben, D. The effect of mine induced tremors on seismic response of soil-steel bridges. MATEC Web Conf. 2018, 174, 04002. [Google Scholar] [CrossRef]
  23. Maleska, T.; Beben, D.; Nowacka, J. Seismic vulnerability of a soil-steel composite tunnel—Norway Tolpinrud Railway Tunnel Case Study. Tunn. Undergr. Space Technol. 2021, 110, 103808. [Google Scholar] [CrossRef]
  24. Flener, E.B. Soil-Steel Interaction of Long-Span Box Culverts—Performance during Backfilling. J. Geotech. Geoenviron. Eng. 2010, 136, 823–832. [Google Scholar] [CrossRef]
  25. Hong, E.S.; Lee, I.M.; Shin, H.S.; Nam, S.W.; Kong, J.S. Quantitative risk evaluation based on event tree analysis technique: Application to the design of shield TBM. Tunn. Undergr. Space Technol. 2009, 24, 269–277. [Google Scholar] [CrossRef]
  26. Hyun, K.C.; Min, S.; Choi, H.; Park, J.; Lee, I.M. Risk analysis using fault-tree analysis (FTA) and analytic hierarchy process (AHP) applicable to shield TBM tunnels. Tunn. Undergr. Space Technol. 2015, 49, 121–129. [Google Scholar] [CrossRef]
  27. Lyu, H.M.; Sun, W.J.; Shen, S.L.; Arulrajah, A. Flood risk assessment in metro systems of mega-cities using a GIS-based modeling approach. Sci. Total Environ. 2018, 626, 1012–1025. [Google Scholar] [CrossRef]
  28. Lyu, H.M.; Shen, S.L.; Zhou, A.; Yang, J. Risk assessment of mega-city infrastructures related to land subsidence using improved trapezoidal FAHP. Sci. Total Environ. 2019, 717, 135310. [Google Scholar] [CrossRef] [PubMed]
  29. Li, F.W.; Phoon, K.K.; Du, X.L.; Zhang, M.J. Improved AHP Method and Its Application in Risk Identification. J. Constr. Eng. Manag. 2013, 139, 312–320. [Google Scholar] [CrossRef] [Green Version]
  30. Chu, H.; Xu, G.; Yasufuku, N.; Yu, Z.; Liu, P.; Wang, J. Risk assessment of water inrush in karst tunnels based on two-class fuzzy comprehensive evaluation method. Arab. J. Geosci. 2017, 10, 179. [Google Scholar] [CrossRef]
  31. Balta, G.; Dikmen, I.; Birgonul, M.T. Bayesian network based decision support for predicting and mitigating delay risk in TBM tunnel projects. Autom. Constr. 2021, 129, 103819. [Google Scholar] [CrossRef]
  32. Kodur, V.K.R.; Naser, M.Z. Importance factor for design of bridges against fire hazard. Eng. Struct. 2013, 54, 207–220. [Google Scholar] [CrossRef]
  33. Zacchei, E.; Molina, J.L. Introducing importance factors (IFs) to estimate a dam’s risk of collapse produced by seismic processes. Int. J. Disast. Risk 2021, 60, 102311. [Google Scholar] [CrossRef]
  34. Deng, X.; Xu, T.; Wang, R. Risk Evaluation Model of Highway Tunnel Portal Construction Based on BP Fuzzy Neural Network. Comput. Intel. Neurosci. 2018, 2018, 8547313. [Google Scholar] [CrossRef] [Green Version]
  35. Wang, J.; Zhong, H.; Feng, L. A model of coal mine water disaster emergency logistics risk assessment based on AHP and BP neural network. In Future Communication, Computing, Control and Management; Springer: Berlin, Germany, 2012; pp. 535–542. [Google Scholar]
  36. Zhang, C.; Wu, S.; Wu, J. Study on risk assessment model of collapse during construction of mountain tunnel and its application. J. Saf. Sci. Technol. 2019, 15, 128–134. [Google Scholar] [CrossRef]
  37. Lyu, H.M.; Shen, S.L.; Zhou, A.N.; Zhou, W.H. Flood risk assessment of metro systems in a subsiding environment using the interval FAHP-FCA approach. Sustain. Cities Soc. 2019, 50, 101682. [Google Scholar] [CrossRef]
  38. Lyu, H.M.; Zhou, W.H.; Shen, S.L.; Zhou, A.N. Inundation risk assessment of metro system using AHP and TFN-AHP in Shenzhen. Sustain. Cities Soc. 2020, 56, 102103. [Google Scholar] [CrossRef]
  39. Zheng, Q.; Lyu, H.M.; Zhou, A.; Shen, S.L. Risk assessment of geohazards along Cheng-Kun railway using fuzzy AHP incorporated into GIS. Geomat. Nat. Haz. Risk. 2021, 12, 1508–1531. [Google Scholar] [CrossRef]
  40. Huseby, A.B.; Skogen, S. Dynamic risk analysis: The DynRisk concept. Int. J. Proj. Manag. 1992, 10, 160–164. [Google Scholar] [CrossRef]
  41. Yi, P.T.; Zhou, Y.; Guo, Y.J.; Li, W.W. A dynamic comprehensive evaluation method embodying development tendency. Oper. Res. Manag. Sci. 2016, 25, 175–180. [Google Scholar] [CrossRef]
  42. Hu, P.; Liu, S.H.; Wang, D.G.; He, R.Y. Dynamic risk assessment for natural gas pipelines based on variable weights comprehensive theory. China Saf. Sci. J. 2012, 22, 82–88. [Google Scholar] [CrossRef]
  43. Li, Y.C.; Xue, Y.D.; Li, Y.J. A new construction risk assessment method based on dynamic weight. Chin. J. Under Sp. Eng. 2017, 13, 209–215. [Google Scholar]
  44. Zhao, H.; Wang, X.Q. Research on dynamic financing risk evaluation system of large-scale infrastructure projects. J. Beijing Inst. Technol. (Soc. Sci. Ed.) 2017, 19, 83–90. [Google Scholar] [CrossRef]
  45. Wang, S.; Li, L.P.; Shi, S.S.; Cheng, S.; Hu, H.J.; Wen, T. Dynamic risk assessment method of collapse in mountain tunnels and application. Geotechnol. Geol. Eng. 2020, 38, 2913–2916. [Google Scholar] [CrossRef]
  46. Wang, S.; Li, L.P.; Cheng, S.; Hu, H.J.; Gao, S. Dynamic risk assessment method of tunnel collapse based on attribute interval assessment model and application. Pol. J. Environ. Soc. 2020, 29, 3853–3864. [Google Scholar] [CrossRef]
  47. Wang, Y.; Su, J.; Zhang, S.; Guo, S.; Zhang, P.; Du, M. A dynamic risk assessment method for deep-buried tunnels based on a bayesian network. Geofluids 2020, 2020, 8848860. [Google Scholar] [CrossRef]
  48. Wu, B.; Chen, H.B.; Huang, W.; Meng, G.W. Dynamic Evaluation Method of the EW-AHP Attribute Identification Model for the Tunnel Gushing Water Disaster under Interval Conditions and Applications. Math. Probl. Eng. 2021, 2021, 6661609. [Google Scholar] [CrossRef]
  49. Zheng, J.F. Research on Construction Risk Assessment of Urban Shallow-Buried Large Span Underground Excavation Engineering; Beijing Jiaotong University: Beijing, China, 2020. [Google Scholar] [CrossRef]
  50. Cheng, Y.; Liu, Z.B.; Liu, S.Y.; Cai, G.J.; Tong, L.Y. Risk recognition of construction of large-span and shallow buried-highway tunnels based on analytic hierarchy process. Chin. J. Geotech. Eng. 2011, 33 (Suppl. 1), 198–202. [Google Scholar]
  51. Lyu, H.M.; Sun, W.J.; Shen, S.L.; Zhou, A.N. Risk Assessment Using a New Consulting Process in Fuzzy AHP. J. Constr. Eng. Manag. 2020, 146, 04019112. [Google Scholar] [CrossRef]
Figure 1. Longitudinal view of the double-arch tunnel.
Figure 1. Longitudinal view of the double-arch tunnel.
Applsci 11 11721 g001
Figure 2. Risk evaluation index system of urban shallow-buried large-span double-arch tunnel construction.
Figure 2. Risk evaluation index system of urban shallow-buried large-span double-arch tunnel construction.
Applsci 11 11721 g002
Figure 3. Risk comment level and the corresponding quantitative interval.
Figure 3. Risk comment level and the corresponding quantitative interval.
Applsci 11 11721 g003
Figure 4. The quantitative value of risk evaluation indexes membership degree at each stage: (a) Initial stage; (b) Stage 1; (c) Stage 2; (d) Stage 3; (e) Stage 4.
Figure 4. The quantitative value of risk evaluation indexes membership degree at each stage: (a) Initial stage; (b) Stage 1; (c) Stage 2; (d) Stage 3; (e) Stage 4.
Applsci 11 11721 g004aApplsci 11 11721 g004b
Figure 5. Relationship between evaluation level and quantitative score.
Figure 5. Relationship between evaluation level and quantitative score.
Applsci 11 11721 g005
Figure 6. Risk level and calculated score.
Figure 6. Risk level and calculated score.
Applsci 11 11721 g006
Figure 7. Dynamic risk evaluation results of each stage.
Figure 7. Dynamic risk evaluation results of each stage.
Applsci 11 11721 g007
Figure 8. Advance geological prediction by drilling method.
Figure 8. Advance geological prediction by drilling method.
Applsci 11 11721 g008
Figure 9. Advance long pipe shed.
Figure 9. Advance long pipe shed.
Applsci 11 11721 g009
Figure 10. Full section curtain grouting.
Figure 10. Full section curtain grouting.
Applsci 11 11721 g010
Table 1. Relative comparison scale.
Table 1. Relative comparison scale.
Digital ScaleDefinition
1Ui is as important as Uj
3Ui is slightly more important than Uj
5Ui is obviously more important than Uj
7Ui is more important than Uj
9Ui is extremely important than Uj
2, 4, 6, 8Take the median value between the two adjacent degrees of the above comparison
Table 2. Average random consistency index RI.
Table 2. Average random consistency index RI.
Matrix Order2345678910
RI00.580.901.121.241.321.411.461.49
Table 3. Weight calculation of first-level risk evaluation indexes.
Table 3. Weight calculation of first-level risk evaluation indexes.
StageFirst-Level IndexesFirst-Level IndexesCICRWeight
U1U2U3U4U5U6
Preparation stage before constructionEngineering geology and hydrogeology U112125 0.01350.01210.32
Surrounding construction environment U2½11/212 0.15
Overall engineering design U312114 0.27
Engineering construction technology U4½1113 0.19
Engineering construction management U51/51/21/41/31 0.07
Construction stageEngineering geology and hydrogeology U11212510.0110.00890.24
Surrounding construction environment U2½11/2121/20.12
Overall engineering design U31211410.21
Engineering construction technology U4½11131/20.14
Engineering construction management U51/51/21/41/311/50.05
Monitoring measurement data U61212510.24
Table 4. Weight of second-level evaluation indexes.
Table 4. Weight of second-level evaluation indexes.
First-Level IndexesSecond-Level IndexesSecond-Level IndexesCICRWeight
Ui1Ui2Ui3Ui4Ui5Ui6
Engineering geology and hydrogeology U1Rock mass strength U1112542 0.00450.0040.40
Deformation modulus U12½1321 0.21
Weathering degree U131/51/3111/3 0.08
Groundwater condition U14¼1/2111/2 0.10
Bad geological conditions U15½1321 0.21
Surrounding construction environment U2Surrounding buildings U211234 0.01030.01150.47
Underground pipeline U22½123 0.28
Urban road grade U231/31/211 0.14
Climatic conditions U24¼1/311 0.11
Overall engineering design U3Tunnel section size U311211330.01090.00880.24
Tunnel depth U32½1½1/2220.13
Design method rationality U331211230.23
Reasonable load value U341211230.23
Structural importance U351/31/2½1/2110.09
New technology application U361/31/21/31/3110.08
Engineering construction technology U4Construction method rationality U41121/322 0.00460.00410.20
Rationality of construction procedure U42½1¼11 0.11
Construction quality U4334145 0.48
Monitoring and measurement U44½1¼11 0.11
Skill level of workers U45½11/511 0.10
Engineering construction management U5Construction organization management level U5111/2223 0.01230.01100.24
Safety education and training U5221344 0.42
Emergency management U53½1/3112 0.14
Equipment material protection U54½1/4111 0.11
Construction environment U551/31/4½11 0.09
Monitoring measurement data U6Ground subsidence U6111/2134 0.00960.00860.24
Vault settlement U6221245 0.40
Pipeline settlement U6311/2123 0.20
Bolt axial force U641/31/4½11 0.09
Surrounding rock pressure U65¼1/51/311 0.07
Table 5. The reference value of risk evaluation index classification standard.
Table 5. The reference value of risk evaluation index classification standard.
Second-Level IndexesRisk Level and Scoring Range
I (90~100)II (80~90)III (70~80)IV (60~70)V (0~60)
Rock mass strength U11>6030~6015~305~15<5
Deformation modulus U12>5030~5010~305~10<5
Weathering degree U13UnweatheredBreezeModerately weatheredStrong weatheredCompletely weathered
Groundwater condition U14No waterLess waterModerately waterMore waterAbundant water
Bad geological conditions U15No bad geologyLess bad geologyPoor geology existsMore bad geologyAbundant bad geology
Surrounding buildings U21No surrounding buildingsSecondary buildingsBuildings of general importanceImportant buildingKey protected buildings
Underground pipeline U22No pipelineLess pipelineMore pipelinesDense pipelinePipeline must be relocated
Urban road grade U23Branch roadSecondary trunk roadTrunk roadExpresswayMultiple roads and complex routes
Climatic conditions U24GoodBetterGenerallyPoorVery bad
Tunnel section size U31<1010~3030~5050~100>100
Tunnel depth U32>3022~3015~228~15<8
Design method rationality U33ReasonableBasically reasonableGeneral reasonablePoorUnreasonable
Reasonable load value U34ReasonableBasically reasonableGeneral reasonablePoorUnreasonable
Structural importance U35UnimportantBasically importantGeneral importantMore importantVery important
New technology application U36No new technologyFew new technologiesGeneral new technologiesMore new technologiesMany new technologies
Construction method rationality U41ReasonableBasically reasonableGeneral reasonablePoorUnreasonable
Rationality of construction procedure U42ReasonableBasically reasonableGeneral reasonablePoorUnreasonable
Construction quality U43Superior to design standardsMeet design standardsGeneral qualityBelow qualitySeriously unqualified quality
Monitoring and measurement U44Strictly follow the specificationsMore perfectionGeneral perfectionImperfectNone Monitored measurement
Skill level of workers U45Perfect arrangement of technical staffThe arrangement of technical staff is relatively completeEquipped with basic technical staffLack of key technical staffSevere shortage of technical staff
Construction organization management level U51No omissionsCan better complete the construction contentCan basically complete the construction contentPoorVery bad
Safety education and training U52Adequate trainingMore trainingGeneral trainingLess trainingNo training
Emergency management U53Perfect emergency planRelatively completeGeneral perfectionIncomplete emergency planNo contingency plan
Equipment material protection U54New equipmentRelatively new equipmentNew equipment but poor maintenanceEquipment is new and maintenance is not timelySerious aging of equipment
Construction environment U55No impact on construction safetyRelatively goodGenerallyPoorVery bad
Ground subsidence U61S1 ≤ 0.6 U10.6 U1 < S1 ≤ 0.7 U10.7 U1 < S1 ≤ 0.8 U10.8 U1 < S1 ≤ 0.9 U1S1 ≥ 0.9 U1
Vault settlement U62S2 ≤ 0.6 U20.6 U < 2S2 ≤ 0.7 U20.7 U2 < S2 ≤ 0.8 U20.8 U2 < S2 ≤ 0.9 U2S2 ≥ 0.9 U2
Pipeline settlement U63S3 ≤ 0.6 U30.6 U < 3S3 ≤ 0.7 U30.7 U3 < S3 ≤ 0.8 U30.8 U3 < S3 ≤ 0.9 U3S3 ≥ 0.9 U3
Bolt axial force U64n ≤ 0.6 U40.6 U4 < n ≤ 0.7 U40.7 U4 < n ≤ 0.8 U40.8 U4 < n ≤ 0.9 U4n ≥ 0.9 U4
Surrounding rock pressure U65p ≤ 0.6 U50.6 U5 < p ≤ 0.7 U50.7 U5 < p ≤ 0.8 U50.8 U5 < p ≤ 0.9 U5p ≥ 0.9 U5
Note: S1, S2, and S3, respectively, represent the monitoring values of the ground, vault, and pipeline settlements. U1, U2, and U3, respectively, represent the control values of the ground, vault, and pipeline settlements. n and p, respectively, represent the monitoring values of the bolt axial force and the surrounding rock pressure. U4 and U5, respectively, represent the allowable values of bolt axial force and surrounding rock pressure.
Table 6. The dynamic weight of each stage.
Table 6. The dynamic weight of each stage.
Second-Level IndexesThe Dynamic Weight of Each Stage
Initial StageStage 1Stage 2Stage 3Stage 4
Rock mass strength U110.400.380.30 0.36 0.24
Deformation modulus U120.210.230.19 0.24 0.16
Weathering degree U130.080.100.12 0.12 0.12
Groundwater condition U140.100.08 0.09 0.17 0.08
Bad geological conditions U150.210.210.30 0.11 0.40
Surrounding buildings U210.470.38 0.35 0.40 0.36
Underground pipeline U220.280.26 0.28 0.27 0.26
Urban road grade U230.140.21 0.23 0.20 0.18
Climatic conditions U240.110.15 0.14 0.13 0.20
Tunnel section size U310.240.25 0.25 0.21 0.38
Tunnel depth U320.130.16 0.18 0.25 0.26
Design method rationality U330.230.20 0.19 0.17 0.10
Reasonable load value U340.230.18 0.18 0.17 0.10
Structural importance U350.090.09 0.08 0.10 0.08
New technology application U360.080.12 0.12 0.10 0.08
Construction method rationality U410.200.20 0.21 0.22 0.22
Rationality of construction procedure U420.110.11 0.15 0.16 0.16
Construction quality U430.480.46 0.38 0.36 0.38
Monitoring and measurement U440.110.11 0.12 0.12 0.11
Skill level of workers U450.100.12 0.14 0.14 0.13
Construction organization management level U510.240.25 0.24 0.24 0.24
Safety education and training U520.420.35 0.38 0.38 0.39
Emergency management U530.140.16 0.16 0.15 0.15
Equipment material protection U540.110.12 0.10 0.12 0.12
Construction environment U550.090.12 0.12 0.11 0.10
Ground subsidence U61 0.50 0.25 0.24 0.25
Vault settlement U62 0.00 0.36 0.31 0.31
Pipeline settlement U63 0.50 0.18 0.20 0.19
Bolt axial force U64 0.00 0.12 0.15 0.15
Surrounding rock pressure U65 0.00 0.09 0.10 0.10
Table 7. Fuzzy evaluation matrix of risk evaluation index in each construction stage.
Table 7. Fuzzy evaluation matrix of risk evaluation index in each construction stage.
Second-Level IndexesConstruction Stage
Initial StageStage 1Stage 2Stage 3Stage 4
1234512345123451234512345
U1100010000.20.800000.70.30001000001
U1200010000100000.50.5000100000.50.5
U130001000010000010000.60.400001
U1400100000.30.70000.70.3000100000.50.50
U1500010001000000.50.5000.80.200000.70.3
U2100010001000000.70.30000.70.300001
U2200010000.30.700000.50.5000100000.50.5
U230000.50.5001000000.30.70000.30.700.80.200
U2400010000.30.7000010000.30.7000.80.200
U310000.50.5000.30.700000.30.7000100000.90.1
U3200010001000000.40.60000.50.5000.70.30
U330100001000010000100000100
U3401000010000100001000000.80.20
U350000.80.2000100000.20.80001000.50.300
U3600100010000010000100000.80.20
U41010000.20.8000010000100001000
U42001000.10.900000.30.70000.20.80000.30.700
U4301000000.50.50010000100000.50.500
U440010000100000.90.10000.30.7000100
U450100000.50.500010000100000.90.100
U5100.40.6000010000.30.70000.90.10000.50.500
U520.10.900000.50.5000100000.90.10000001
U5300100001000100000.20.80000001
U540100000.80.200010000100000001
U550100001000010000.30.70000000.30.7
U61 01000000100010000010
U62 10000000100010000100
U63 01000000100010000100
U64 10000000.20.800001000010
U65 1000000100000.50.50000.50.50
Table 8. First-level evaluation matrix.
Table 8. First-level evaluation matrix.
StageRisk Evaluation IndexesAssessment Results
12345
Initial stageEngineering geology and hydrogeology U10.000.000.100.900.00
Surrounding construction environment U20.000.000.000.930.07
Overall engineering design U30.000.460.080.320.14
Engineering construction technology U40.000.780.220.000.00
Engineering construction management U50.040.670.290.000.00
Stage 1Engineering geology and hydrogeology U10.00 0.00 0.31 0.69 0.00
Surrounding construction environment U20.00 0.00 0.71 0.29 0.00
Overall engineering design U30.00 0.50 0.23 0.27 0.00
Engineering construction technology U40.05 0.32 0.40 0.23 0.00
Engineering construction management U50.00 0.39 0.61 0.00 0.00
Monitoring measurement data U60.00 1.00 0.00 0.00 0.00
Stage 2Engineering geology and hydrogeology U10.00 0.00 0.06 0.48 0.46
Surrounding construction environment U20.00 0.00 0.00 0.59 0.41
Overall engineering design U30.00 0.37 0.12 0.16 0.35
Engineering construction technology U40.00 0.78 0.21 0.01 0.00
Engineering construction management U50.00 0.83 0.17 0.00 0.00
Monitoring measurement data U60.00 0.00 0.11 0.89 0.00
Stage 3Engineering geology and hydrogeology U10.00 0.00 0.26 0.69 0.05
Surrounding construction environment U20.00 0.00 0.04 0.70 0.26
Overall engineering design U30.00 0.34 0.10 0.44 0.12
Engineering construction technology U40.00 0.75 0.16 0.09 0.00
Engineering construction management U50.03 0.79 0.18 0.00 0.00
Monitoring measurement data U60.00 0.00 0.80 0.20 0.00
Stage 4Engineering geology and hydrogeology U10.00 0.00 0.04 0.12 0.84
Surrounding construction environment U20.00 0.00 0.00 0.50 0.50
Overall engineering design U30.00 0.15 0.10 0.23 0.52
Engineering construction technology U40.00 0.32 0.55 0.05 0.00
Engineering construction management U50.00 0.42 0.58 0.00 0.00
Monitoring measurement data U60.00 0.00 0.00 0.15 0.86
Table 9. Risk assessment results of each stage.
Table 9. Risk assessment results of each stage.
StageAssessment Results
12345
Initial stage0.010.320.120.510.05
Stage 10.010.410.290.290.00
Stage 20.000.230.110.440.23
Stage 30.000.220.310.400.07
Stage 40.000.100.140.180.58
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Wang, J.; Cao, A.; Wu, Z.; Sun, Z.; Lin, X.; Sun, L.; Liu, W.; Liu, X.; Li, H.; Sun, Y.; et al. Dynamic Risk Assessment of Ultra-Shallow-Buried and Large-Span Double-Arch Tunnel Construction. Appl. Sci. 2021, 11, 11721. https://doi.org/10.3390/app112411721

AMA Style

Wang J, Cao A, Wu Z, Sun Z, Lin X, Sun L, Liu W, Liu X, Li H, Sun Y, et al. Dynamic Risk Assessment of Ultra-Shallow-Buried and Large-Span Double-Arch Tunnel Construction. Applied Sciences. 2021; 11(24):11721. https://doi.org/10.3390/app112411721

Chicago/Turabian Style

Wang, Jianxiu, Ansheng Cao, Zhao Wu, Zhipeng Sun, Xiao Lin, Lei Sun, Wuji Liu, Xiaotian Liu, Huboqiang Li, Yuanwei Sun, and et al. 2021. "Dynamic Risk Assessment of Ultra-Shallow-Buried and Large-Span Double-Arch Tunnel Construction" Applied Sciences 11, no. 24: 11721. https://doi.org/10.3390/app112411721

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop