Critical Delaying Factors: Public Sector Building Projects in Gilgit-Baltistan, Pakistan

1
Faculty of Management and Economics, Dalian University of Technology, Dalian 116024, China
2
Department of Business Management, Karakoram International University, Gilgit-Baltistan 15100, Pakistan
3
Department of Management Science, The Islamia University of Bahawalpur, Bahawalpur 63100, Pakistan
4
Department of Infrastructure Engineering, Dalian University of Technology, Dalian 116024, China
*
Authors to whom correspondence should be addressed.
Received: 20 November 2017 / Revised: 25 December 2017 / Accepted: 2 January 2018 / Published: 3 January 2018
Full-Text   |   PDF [231 KB, uploaded 3 January 2018]

Abstract

Project delays are a large and prevalent problem in the Gilgit-Baltistan construction industry, and delays can distinctly affect project duration, budget, and also community needs. The purpose of this study is to highlight and rank delaying factors in the Annual Development Programme public sector building infrastructure projects and examine them through a relative importance index. A total of 52 delaying factors were identified through a detailed literature review and categorized into eight major groups, and a pilot study with 16 experienced construction experts was conducted. A questionnaire survey was conducted to collect the importance of each factor from public construction experts. In total, 102 respondents participated in the survey. The study determined that difficulties in financing projects by contractors, delays in progress payments, dispute on land usage, improper project feasibility studies, award project to the lowest bid price, extreme weather conditions, inadequate contractor experience, and insufficient data collection and survey before design were among the top eight critical delaying factors. In addition, Spearman’s rank correlation tests revealed that there was no difference in perception between owners and contractors. A comparison of the top five delay factors was done with eight preferred construction industries in Asia to validate the results of this study. The findings are likely to be a solid contribution to the Gilgit-Baltistan construction industry in mitigating future construction delays. View Full-Text
Keywords: critical delaying factors; public sector; building infrastructure projects; Gilgit-Baltistan; Pakistan critical delaying factors; public sector; building infrastructure projects; Gilgit-Baltistan; Pakistan
This is an open access article distributed under the Creative Commons Attribution License which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited (CC BY 4.0).
SciFeed

Share & Cite This Article

MDPI and ACS Style

Hussain, S.; Zhu, F.; Ali, Z.; Aslam, H.D.; Hussain, A. Critical Delaying Factors: Public Sector Building Projects in Gilgit-Baltistan, Pakistan. Buildings 2018, 8, 6.

Show more citation formats Show less citations formats

Note that from the first issue of 2016, MDPI journals use article numbers instead of page numbers. See further details here.

Related Articles

Article Metrics

Article Access Statistics

1

Comments

[Return to top]
Buildings EISSN 2075-5309 Published by MDPI AG, Basel, Switzerland RSS E-Mail Table of Contents Alert
Back to Top