Next Article in Journal
Research and Prospects of Airtightness of Biological Laboratory Enclosures: Influencing Factors and Evaluation Methods
Previous Article in Journal
Prediction of Urban Construction Land Carbon Effects (UCLCE) Using BP Neural Network Model: A Case Study of Changxing, Zhejiang Province, China
Previous Article in Special Issue
Computer Vision-Based Safety Monitoring of Mobile Scaffolding Integrating Depth Sensors
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Systematic Methodology for Estimating the Social Dimension of Construction Projects—Assessing Health and Safety Risks Based on Project Budget Analysis

by
María D. Alba-Rodríguez
1,*,
Valeriano Lucas-Ruiz
2 and
Madelyn Marrero
2
1
Design Engineering Department, Higher Polytechnic School, University of Seville, C/Virgen de África, 7, 41011 Seville, Spain
2
Department of Architectural Constructions II, School of Building Engineering, University of Seville, Av. Reina Mercedes 4, 41012 Seville, Spain
*
Author to whom correspondence should be addressed.
Buildings 2025, 15(13), 2313; https://doi.org/10.3390/buildings15132313
Submission received: 21 May 2025 / Revised: 26 June 2025 / Accepted: 28 June 2025 / Published: 1 July 2025

Abstract

One of the major challenges in the construction sector involves achieving sustainability in all three of its dimensions: economic, social, and environmental. Economic and environmental assessments have already been unified, but social indicators are still excluded. In this line, it is important for a rapid introduction of sustainability indicators that the evaluations of its three dimensions are carried out simultaneously and without adding new training or a large workload to the project. In this work, it is proposed to use the definition of tasks in construction cost databases. These, due to their long tradition in the sector, have a clear definition of the contours of the problem and the inventory of resources. Therefore, based on this inventory that does not leave any unaccounted element, the evaluation of the social dimension is proposed through the use of the work units of the databases as an element of occupational risk assessment. The project cost and risk assessment are performed simultaneously in the construction of a social housing project in Andalusia, Spain. The costs of prevention measures represent 5% of the work units’ costs and reduce the risk indicator by 65%.

1. Introduction

One important aspect of construction project sustainability is related to its social impact, and Health and Safety (H&S) risk indicators can be of importance since the sector is characterised by high accident and mortality rates on the work site. Two strategies can be defined to reduce the number of accidents and/or their severity: first, reduce the risks by means of prevention; and once the event occurs, reduce its impact through protection, following the model defined by Hollnagel [1]. Regarding prevention, in a review of the causes of construction accidents in Norway [2], 176 major accidents were studied, whereby it was found that immediate management and supervision and planning and risk control at different levels were of great importance, thereby underlining the need for risks to be addressed at various levels and by different actors in construction projects.
A study conducted in Korea [3] suggests classifying causes of accidents into direct and indirect groups. Direct causes are the difficulty of the work, the characteristics of the building, the urgency to finish the project, and the unsatisfactory response to unforeseen situations on the construction site. Indirect causes are also important, such as safety culture, atmosphere, leadership, and management policies.
The direct aspects can be addressed by prevention through design (PtD). Addressing and minimising safety risks in construction from the initial phase of a project has generated interest in research since it was identified that 42% of fatality cases are related to the design [4]. But designers tend to avoid making decisions related to H&S, leaving it up to contractors during the construction phase.
In the United Kingdom, where PtD is integrated in their regulation, interviews were conducted with people from the sector who show changes in attitudes towards worker safety, in identifying who can have a positive impact, as well as better communication, knowledge transfer, and innovation in design [5]. Also in Australia, legislation includes PtD, and designers have responsibility for H&S issues of construction projects; therefore, H&S decisions are made early in the project development process [6]. In Spain, policies make it mandatory to comply with minimum H&S requirements for construction works. The obligation to prepare a H&S study on the work is established, in which it is necessary to plan the execution of the work, not only considering the occupational risks existing in the execution project, but also the inclusion of a budget [7]. However, despite being a legislative requirement in Spain, it has not permeated the attitude of those involved in the sector, in addition to the responsibility for prevention being delegated to those involved in the execution phase and removed from the design and planning phase.
In this line, the present work, in a novel way, proposes a methodology for the control and definition of risks from a systematised perspective, linked to the economic and environmental control of the project. The structure that integrates the construction cost databases, which are of extended use in the sector, has enabled the simultaneous evaluation of two dimensions of sustainability: economic and environmental [8,9]. In the present work, a link to the third dimension or social aspects is proposed through risk assessment and its reduction. Specifically, by focusing on the design and/or planning phase, a model is developed that analyses occupational risks in residential building construction. Therefore, the objective is to evaluate the prevention of occupational risks in the design and/or planning phase based on the budget and to define the necessary measures to minimise them. A new indicator is proposed for the evaluation of such risks.

1.1. Risk Identification Tools

The first step to reduce risks and hazards in the construction site is to identify them. For that, many tools have been introduced internationally. In the early 1990s, the Safety, Health, and Environmental Checklist for Contractors (Veiligheid gezondheid en milieu Checklist Aannemers), known as the VCA, was introduced in the Netherlands [10]. The VCA was employed in the training and certification of contractors in order to allow them to perform maintenance work and construction activities on construction sites of the chemical and oil industries. The mandatory certificate aimed to ensure an acceptable level of safety. Its introduction resulted in a drastic decrease in the number of accidents reported. Risk analysis and control measures form a strong combination in this model.
Another proposal for the evaluation and control of risks involves the construction toolbox safety index [11]. These authors present the design of a framework and protocol for risk management in the construction industry as a “toolbox”. This has a comprehensive and systematic approach for the evaluation and control of occupational risks. A qualitative risk assessment was generated, which determines a “band” of risk for a given project [12]. A total of 150 worksites were evaluated, and the Construction Site Risk Assessment Tool (CONSRAT) was developed. They propose the concept of “site risk”, which is defined as the risk associated with the entire work that is generated from the various elements that individually affect the risk, since there may be potential risk synergies that can only be captured if the whole construction site constitutes the unit of analysis. But these solutions fall short and have limits that can intervene from the beginning in the conception of the project or project design, so that a notable change can occur in the sector.

1.2. Prevention Through Design

Some researchers have addressed the risks arising from innovations in building designs to make them environmentally sustainable. The authors of [13] defined a risk identification and assessment method that assesses risk in the Leadership in Energy and Environmental Design rating system (LEED). In the same line, the authors of [14] identified the safety impact of sustainable building design, where the injury rate is 9% higher than in non-LEED buildings, and similar design implications are explored by the authors of [15].
Designers, when they are aware of the risks on the construction site, are willing to address them during the design phase [16]. Tools have been developed to provide risk mitigation advice, recommend design alternatives, or facilitate site planning processes, but the designer’s lack of knowledge of construction processes and limited availability to tools that help assess risk are barriers to implementing PtD [17]. Traditional PtD tools consist of risk assessment matrices, design guides, and database suggestions of lessons learned [18]. For example, the authors of [19] define a risk assessment method that helps designers assess the safety of residential building designs.
However, automation and many technological improvements, which have led to greater safety in other industries, have not had the same impact on the construction sector [10]. Therefore, other authors propose the use of Building Information Modelling (BIM) in the development of quantitative risk analysis to better support safety management [20]. Advances in BIM provide an opportunity to integrate computerisation and automation into risk prevention. Melzner et al. (2013) [21] and Qi et al. (2014) [22] developed BIM-based PtD verification tools to identify fall hazards and provide design alternatives through the case study of a three-story building. Zhang et al. (2013) [23] created a BIM-based tool that supports ontology-based automated occupational risk analysis in a case study of a masonry project. Yuan et al. (2019) [24] programmed a Revit plugin that helps designers verify security risks through a case study of a six-story building. Nnaji et al. (2023) [25] are also working on a BIM-based risk assessment approach that is integrated with a construction breakdown structure and site planning using a case study of a three-storey concrete building. Cortés-Pérez et al. (2020) [26] have developed a BIM-based method that integrates the Spanish H&S regulations in order to assess risks and to generate H&S plans.
Other authors propose the use of Building Information Modelling (BIM) in the development of quantitative risk analysis to better support safety management [20]. For example, risk libraries associated with construction scenarios allow threats to be automatically linked to BIM objects, following PtD approaches [27]. Advances in BIM provide an opportunity to integrate computerisation and automation into risk prevention [26] and have developed a BIM-based method that integrates the Spanish H&S regulations in order to assess risks and to generate H&S plans. Furthermore, works such as [28] propose the integration of Work Breakdown Structures (WBS) and Risk Breakdown Structures (RBS), stored in knowledge bases and linked with parametric BIM methods and risk repositories to facilitate visualisation and decision-making. The WBS and RBS structures are developed separately and then connected by rules; they are not from a single classification structure.
But what can really drive a change in BIM is a previous step: standardisation in the definition of the elements that generate risk and their link to BIM models. For this reason, it is necessary to continue developing a unification in the measurement of risk and implementation of prevention measures that facilitate decision-making by architects, engineers, and builders in order to make the work site a safer environment, avoiding overlaps or unassessed risks. To this end, the breaking down of systems of construction work, which are already widely used in cost control, planning, or environmental assessment, can serve as a link for the integration of prevention from design. The problem boundaries already set in the construction cost definition or life cycle analysis can be useful to define risk assessment.
In this work, a more structural integration is proposed from an already-in-place classification of construction cost databases, which facilitates automation, scalability, and logical coherence for risk management in BIM environments. In our model, a single code stores all the information (costs, environmental, and social impacts), and the procedures are structured from the same hierarchy, sharing a single tree. It is the work unit or unit cost that has all the information stored.

2. Materials and Methods

A systematised methodology linked to economic control is proposed, which allows the control and definition of construction risks. The main source of information is the project budget, which contains information on the working hours of the staff and the type of work they perform. This information is used to define the work procedures and make it possible to be able to develop the social indicator. For better understanding, Figure 1 outlines the flow chart of the various stages of the methodology:
  • Project data: Analysis and identification of the different work units contained in the project budget. These work units provide information on worker hours and the type of work they perform (Figure 1).
  • Procedures of work units: The definition of the work procedures associated with the work units contained in the budget.
  • Risk assessment: For the assessment of accident risks, the holistic model proposed by Marrero et al. (2024) [29] is employed. This assessment provides the initial risk level of the work procedures, before incorporating corrective measures. Once the corrective measures are applied, the risk assessment is conducted again. (Figure 1).
  • Prevention Indicator (IP): The qualitative and quantitative evaluation conducted on the risks identified in their initial state and in their final state, after the application of the corrective measures, allows the development of the prevention indicator, which provides two results in parallel (Figure 1):
    • Risk reduction: This indicates the reduction in the level of risk that has been achieved with the incorporation of the corrective measures applied.
    • Cost (EUR): The determination of the economic cost of the corrective measures applied to achieve the reduction in the level of risk.
The methodology establishes a relationship between risk reduction and the cost increase due to implementation.
Figure 1. Methodological flowchart.
Figure 1. Methodological flowchart.
Buildings 15 02313 g001
In the second part of Figure 1, the conceptual prototype for BIM integration is developed for the transfer of generated data and how it should be managed within the BIM environment. The first step will be to adapt the information contained in the cost database (bc3 format in Spain) files to the structure of the open IFC4 format and make it comply with the ISO 16739-1.2020 standard [30]. Initially, the attributes and properties necessary to incorporate non-native parameters related to the assessment of social sustainability will be identified, linking them to elements and resources of the BIM model, enabling their integration with the data associated with the external database. The created information structure will need to be tested to ensure its functionality and the efficiency of the developed workflow. Based on the previous conceptualisation, the information from the risk indicator file will be imported into a local database (SQL Server, MySQL, among others), allowing for efficient data organisation and query. In addition, IFC parameters will be linked to the BIM model to store calculation results for the elements. As a final stage, an interactive representation of the model with colour scales locates the elements that generate the greatest social impacts. This functionality will allow users to make more efficient decisions to improve the project’s social sustainability.
As for the boundaries of the system, it should be noted that this study is limited to collective and individual protection measures and the delimitation of spaces, including compliance with Spanish law (Ley_31/95, 1999) regarding the organisational and ergonomic activities necessary to prevent and/or minimise risks. The remaining H&S measures (hygiene and signalling of premises or training of workers) are not covered in this study because they cannot be linked to direct work units. It should be borne in mind that work equipment, especially machines, tools, provisional installations, and auxiliary means, must comply with the provisions of Royal Decree 1215 of 1997 [31], which establishes the minimum H&S requirements for the use by workers of work equipment, as well as the rest of the mandatory standards associated with the equipment.

2.1. Classification of Construction Work

As a first step of the methodology, the contours of the problem are defined. To this end, the construction cost databases and their systematic classification of the work units are employed. This makes it possible to identify and define jobs, tasks, and their risks in projects. Construction cost databases are widely used in the construction sector [9], which enables, for example, the economic and environmental control of projects [32], which can be conducted throughout their life cycle [33]. Among the Spanish systems are ITEC in Catalonia [32], CYPE in Alicante [34], the Construction Cost Base of the Community of Madrid [35], PRECIOCENTRO [36], and the Andalusian Construction Cost Database (ACCD) in Andalusia [37]. Over 30 years ago, an agreement was reached in Spain regarding a common language and a simple and standardised format, called bc3 exchange format [38].
This research is based on the systematic classification of the ACCD [37]. Its management and classification system of work units is flexible and adaptable (an example is given in Figure 2A), which allows the incorporation of new work units with their indicators for the generation of models easily understood by technicians. The cost structure is created by virtue of a hierarchy that, starting from the lowest level, grows by joining the lower costs to form costs of a more complex nature. There are three large groups of costs, which, ordered from the lowest to the highest complexity, would be the following: basic costs distributed largely according to the three natures of machinery, labour, and materials; auxiliary costs formed by the union of these basic costs with the quantities appropriate to their typology and function, but which contain insufficient entities to be considered units of completed work, such as mortar or a masonry crew; and unit costs, which are formed by the union of basic costs and/or auxiliary costs (see Figure 2A). Each cost is identified with an alphanumeric code that enables an enormous number of combinations since it comprises twenty-six characters in the alphabetic blocks and ten in the numeric blocks. This leads to shorter codes with a great coding capacity. The letters, if carefully chosen, can provide additional intuitive information.
All costs are expressed as a unit of measurement with a measurement criterion, adjusted to the uses and tendencies of execution. The concepts described above together constitute the epigraph of a unit cost, resulting in all costs having an epigraph, which is different for each element of the system. The work units are organised in an ascending structure of sections, groups, subchapters, and chapters (Figure 2A).

2.2. Standardisation and Classification of Working Procedures

The procedures necessary for the work execution are defined for each work unit. At this point, it is essential to generate a codification of the procedures for their standardisation within the database. Each worker intervenes in one or more parts of the work unit that will be defined in the procedure codification. In the present work, an extension of the classification initiated at the unit cost level is proposed for the definition of the work procedures for work units in the ACCD.
The codification can be seen in Figure 2B. The first two alphabetic characters are “pr” corresponding to a procedure type of code. In second place, two alphabetic symbols identify the type of job. In the present work, 13 different trades have been defined, for which their codes are Al (mason), Am (insulation fixer), At (roofing tiler), El (electrician), En (formwork), Es (plaster board placer), Fe (rebar worker), Fo (plumber), Ho (concrete mixer), Im (water-proofer), Om (machine operator), So (ceramic tiler), and Ye (plasterer). The coding is completed with the corresponding work unit code in the ACCD, followed by five blocks of alphanumeric characters. In the coding example in Figure 2B, the procedure code would be prOm02PMM001, where “pr” indicates that it corresponds to a procedure code; “Om” means that the procedure’s occupation is Machine Operator. From here, the code identifies the work unit to which it belongs within the ACCD, where the numerical value “02” indicates that it corresponds to the Land Conditioning chapter of the project, the letter (P) belongs to the Wells subchapter, and (MM) belongs to the By Mechanical Means group. And finally, the numerical value “001” indicates that it is in the first procedure of the series (Figure 2B).
For a better understanding, in addition to a detailed summary of equations and calculation methodology presented in Figure 3, each stage of the methodology is developed through an example: (1) project data, (2) procedures of work units, (3) risk assessment and (4) prevention indicator (Ip): risk reduction and cost (EUR).

2.3. Project Data

These work units provide information on worker hours and the type of activity they perform (Figure 3). For a better understanding, the methodology is described through an example: unit cost 02PMMM00002, which corresponds to the excavation of one cubic metre of hole for the foundation, in soil of medium consistency, using mechanical means at a maximum depth of 4 m (see Table 1). In its decomposition, the necessary labour is described, from which the jobs involved are derived. These jobs are then analysed, and their corresponding procedures are defined.

2.4. Procedures of Work Units

The workstations involved in the work unit are analysed, and their corresponding procedures are defined. There are two jobs associated with the unit cost shown in the example (see Table 1): mason (Al) and machine operator (Om) (backhoe operator). The tasks to be executed have a starting and ending state with specific conditions. A total of 92 procedures are defined in the case study of a multifamily building construction.

2.5. Risk Assessment

The risk levels of the procedures in the most unfavourable situation are considered, which implies that collective or individual protection is not used, that the spaces have not been delimited, and organisational measures related to H&S are not taking place. The safety and ergonomic risks associated with the worst scenario are analysed (Table 1).
Once the risks have been defined, they are evaluated. First, the deficiencies that exist in the workplace are established. Then, it is necessary to define the probability that an accident may occur as well as the magnitude of the consequences of the accident. The NTP-330 method assesses occupational safety risks, and REBA assesses ergonomic risks. NTP 330 enables the level of the risks of the speciality of Safety at Work to be estimated [39]. In order to make this estimate, the first step is to identify the deficiencies that exist in the workplace. The probability that an accident may occur is included in the probability level (PL), which includes the deficiency level (DL) and the exposure level (EL). In order to calculate DL, the risk factor and to what degree it can cause an accident are determined. Four levels are contemplated: very deficient (MD-10), deficient (D-6), improvable (M-2), and acceptable (A-0). The EL calculates the frequency of exposure to the risk and is also classified into four levels of exposure, and their score are continuous (EC-4), frequent (EF-3), occasional (EO-2), and sporadic (EE-1). The probability level is expressed as the product of these two levels: PL = DL × EL. The PL is categorised as extremely high (MA) (between 40 and 24), high (A) (between 20 and 10), medium (M) (between 8 and 6), and low (B) (between 4 and 2). Another indicator that forms part of the calculation is the consequence level (CL), which has four levels and considers both physical and material damage as fatal or catastrophic (M-100), very serious (MG-60), serious (G-25), and mild (L-10). The risk level (RL) results from RL = PL × CL. Risk levels range from Level I (between 4000 and 6000) for critical situations in need of urgent correction to Level II (between 500 and 150) for situations requiring correction and control measures, Level III (between 120 and 40) for areas of possible improvement of the situation if possible, and Level IV (value 20) to indicate that no intervention is necessary (see Figure 3).
The second method employed is REBA (Rapid Entire Body Assessment), which enables Ergonomics and Psychosociology risks from work-related bodily disorders to be estimated. The method enables the analysis of the positions taken by the upper limbs of the body (arm, forearm, wrist), trunk, neck, and legs. In order to develop the method, its authors, supported by a team of ergonomists, physiotherapists, occupational therapists, and nurses, assessed around 600 working postures [40]. Work tasks with variations in load and movements were analysed. This study was carried out by applying several previously developed methods, such as the Niosh equation [41], the Effort Perception Scale [42], the OWAS method [43], the BPD [44], and the RULA method [45]. To this end, REBA evaluates the risk of static and dynamic postures adopted by arm, forearm, and wrist (group A) and by trunk, neck, and legs (group B) [46]. The score of group A begins with the position of the trunk, depending on the degree of flexion–extension, and it is scored from 1 to 4. The neck is scored from 1 to 2 depending on the degree of flexion–extension of the neck from two positions. Both trunk and neck add a point (+1) if there is also torsion or lateral inclination. Thirdly, the leg position score is 1 if there is bilateral support and 2 if the support is unilateral, light, or of an unstable posture. The leg score is increased by one point (+1) if there is knee flexion between 30° and 60° (except when sitting) and by two points (+2) if said flexion is greater than 60°. With these scores, a matrix scores group A (between 1 and 9), to which we must add a last score depending on the load handled during the maintenance of the posture: a load less than 5 kg (0), between 1 and 10 kg (1), or greater than 10 kg (2). The score is increased by one point (+1) if a quick or abrupt installation of the load is required. The score of group B begins with the position of the arms, which depends on the degree of flexion–extension, and this is scored from 1 to 4. A point (+1) is added if there is also abduction or rotation, another point (+1) is added if there is a shoulder lift, and a point (−1) is subtracted if there is support or posture in favour of gravity. The forearms, depending on the degree of flexion, are scored from 1 to 2. The wrists are scored from 1 to 2 depending on the degree of flexion–extension. The wrist score is increased by one point (+1) if there is torsion or lateral deviation. With these scores, a matrix generates the score of group B (between 1 and 9) and adds a last score depending on the quality of the grip: good grip (0), regular (+1), bad (+2), and unacceptable (+3). After obtaining the scores of groups A and B, the score is obtained in the matrix, which defines the risk level (RL) (between 1 and 12). To this score, a point (+1) must be added in the following situations: if one or more parts of the body remain static, if there are repetitive movements, and if important postural changes are made. Finally, with this score, the level of risk is defined in the following ranges: 1 point (negligible), between 2 and 3 (low), between 4 and 7 (medium), between 8 and 10 (high), and between 11 and 15 (extremely high) (see Table 2).
Table 2 shows an example of how the initial risk assessment is carried out using both methods of the prAl02PMM001 procedure: bottom and side profiling. The risk indicator is calculated for an excavation of 333.59 m3, which determines LE, that is, the frequency with which the operator is subjected to risk. To obtain the values for the levels of risk for safety at work and ergonomics, the NTP-330 method and the REBA method have been applied, respectively. The tables and matrices necessary to obtain partial values for obtaining the risk levels can be consulted in the official documents published for the application of both methods [39,46]. In order to add the results of the risk levels (RL) of the NTP-330 method (uses Roman numerals from I to IV) and the REBA (uses numbers), it is necessary to generate a numerical equivalence to the risk levels of the NTP-330. I to IV correspond to the values 4 to 1, respectively. This makes both methods work in a range that goes from 1 to 4. Also, additional tables are employed that are in the annexe example, Table A2.
Once the initial risk assessment has been carried out, preventative measures are taken to eliminate or minimise risks in the initial assessment. These are classified according to the factors they influence: technical, organisational, or environmental (Table 3). The risk assessment of the procedure is subsequently conducted by considering the measures adopted (see Table 4).

2.6. Prevention Indicator (Ip)

The prevention indicator (Figure 3) is obtained from the quantitative assessment of the risks identified in their initial and final state, or before and after the incorporation of corrective measures. The prevention indicator (Ip) shows how the risk level has been reduced (Figure 3), where Ei is the sum of the initial risk assessment, both for occupational safety and ergonomic risk, and Em is the sum of the risk assessment of the final situation (with the corrective measures incorporated) (Figure 3, definition of the equation legend: prevention indicator). With the data provided by the indicator, it is possible to determine the reduction in risk levels that has been achieved with the incorporation of the corrective measures applied, as well as the economic cost (EUR) of the corrective measures applied to achieve the reduction in the risk level.
The results of the risk assessment of the initial situation are Ei = 11 (see Table 2). Once the preventative measures are adopted, the improved situation is Em = 4 (see Table 4), which represents a 67% reduction.
H&S costs can be determined indirectly in the same way as the jobs for each work procedure. According to the structure of the ACCD, the direct costs for the adoption of the measures of each work unit are assigned by adding the costs of all its procedures. In the total construction budget, all prevention-related costs are grouped within Chapter 19 of Prevention and safety activities (for example, the unit cost of the worker’s helmet is measured in euros per helmet unit).
The classification of the ACCD (see Figure 2A) can be employed for an AI-driven methodology. The codes’ numbers and letters can be employed for the definition of the construction tasks and the risk evaluation, as shown in Figure 2B. A tree has been added to show a possible expansion of the present work (see Figure 4). Some work units of the ACCD are used to illustrate how the same procedure could be associated with others, specifically, procedure PrOm02PMM001. The excavation of a hole for the foundation footings can be associated with the units listed in Figure 4, since these are excavations in which only the type or consistency of the soil varies. Once the database is completed, artificial intelligence can be applied to identify patterns, as in [47], or predictive models in time series can be used, as in [48].
The developed model offers innovative potential for visualising, anticipating, and managing risks more effectively and comprehensively, especially in the design and planning phases. However, it does not replace a management system such as that proposed by ISO 45001 [49], which establishes the organisational, regulatory, and procedural requirements for a solid preventive culture. The developed model is intended to be used as a technical support tool within an ISO 45001 system, integrating advanced visualisation with structured organisational management.

3. Case Study

The case study consists of the construction of a housing project representative of the most commonly built typologies in Spain. Housing construction accounts for 85% of all new construction, of which four-story multi-family buildings comprise 32% [50]. The case study building is located on a rectangular plot of 200 m2. The floor area is 625 m2, built on three floors above ground level, and with an installation area on the roof. It contains a total of 6 dwellings (two per floor). The foundation is of reinforced concrete footings, and the structure combines a sanitary slab on the ground floor, pillars of 30 × 30 cm, and a bidirectional slab on other floors. The exterior enclosure is formed by a brick wall, one foot in thickness. The interior divisions between houses are executed with one-foot ceramic bricks of the same characteristics as the exterior enclosure, and the interior partitions between rooms of the houses are 4 cm thick performed with ceramic bricks. As for the coatings, the floors are terrazzo tiles of 40 × 40 cm with medium-grain marble, the ceilings are trimmed and plastered, except in the kitchens and bathrooms, whose ceilings have plasterboard suspended from metal elements. Likewise, the walls are trimmed and plastered, except in kitchens and bathrooms, which are tiled with 15 × 30 cm glazed ceramic tiles. In the exterior, the walls are finished with a monolayer coating. The concrete slab roof is flat and non-passable, and consists of a top layer of mortar, modified bitumen membrane, a steam diffuser layer, an extruded polystyrene insulation panel, anti-puncture polypropylene fabric, and a 5 cm thick protection layer with rolled aggregate.
For simplification, some construction units have been excluded from the analysis, such as in Chapter 08. Installations only include electrical, water supply, and drainage installations. Chapters that are completely excluded are Chapter 11, which refers to the work conducted outside the building, such as gardening, pavements, roads, and play areas; Chapter 12, Quality assurance; Chapter 17, Waste management; and Chapter 19, Safety. And overhead costs and taxes are not part of the total budget. Finally, the project is formed by 58 unit costs or work units, which need the definition of 92 procedures. All the preventative measures taken in the case study are summarised per chapter in Appendix A (Appendix A.1. Table A1). The present work consists of a first step, where only this list of work units has been evaluated so far. Those were chosen because they are representative of the main activities in a dwelling construction project, as set out in previous points. The most representative project in the region is a multifamily housing with three floors [9,29,50].

4. Results and Discussion

The project’s original risk level, previous to any safety measure, and the improved risk level are calculated for the 92 procedures identified in the project. Appendix A (Appendix A.1, Table A2) summarises the risk reduction per work unit of the project. Table 5 shows the costs per floor area of the construction chapters and the reduction in the risk indicator. In order to indicate which work units are more important, a range in colours is established with red for the elements that are three times the standard deviation away from the mean, two times is dark green, and one time is bright yellow (see Table A3).
Another strong aspect of the present methodology is that it automatically includes H&S-related costs. Once risk assessment can be integrated into work breakdown systems, related costs are also part of the analysis, which becomes an additional tool to control prevention measures being included in projects. Ahn et al. (2021) [3] suggest that in order to ensure that occupational H&S measures are properly implemented, their needs should be included in the construction project budget since their implementation is not free, and that this can be achieved by making it a permanent feature in the project’s budget. They also identified that the management cost of H&S is commonly determined as a percentage of the total budget. Subsequently, when the H&S management plan is established onsite, which corresponds to the requirements and regulations in the country, the cost of management is usually higher than in the first estimate. These researchers have found that the cost estimation methods of H&S measures fail to reflect the characteristics of the project. In Malaysia, where accident and injury statistics in the construction industry were among the highest compared to other sectors, insufficient economic resources are allocated to H&S management, ranging from 0.15% to 1.08%, with an average of 0.41% [51]. Feng (2013) [52] proposes that H&S measures, such as staffing, equipment and safety facilities, mandatory training, internal safety training, safety inspections and meetings, safety incentives and promotions, and safety innovation, all be included in the cost estimate. The total proportion of investment in safety ranged from 1.62% to 3%. Gurcanli et al. (2015) [53] examined blueprints, quantity surveying, etc., of 25 specific buildings in Istanbul and established the ratio between safety cost and total construction cost to be 1.9%. In Spain, Ibarrondo-Dávila et al. (2015) [54] developed and implemented a model to analyse and control the safety costs applied to two construction projects; in this case, the percentages were higher, at 2% and 4.5%. In the present analysis, the cost increase is 5.12%, close to the other study in Spain.
The risk level of the project is reduced by 65%. The structures chapter stands out with the greatest reduction of 75%, followed by the masonry and roof chapters, with 69% each (see Figure 5). Since these are the chapters that present a considerable risk of falling from a height, the protection and preventative measures achieve a substantial reduction. These major risks coincide with those found in Spain by Camino-Lopez [55], where scaffolding, ladders, and cranes—elements used in the construction of structures, masonry, and roofs— caused most accidents.
At the level of unit costs, the greatest risk reduction is 80%, in 05FUA00005, corresponding to the incorporation of a concrete slab with self-resistant beams. This work unit has four procedures, of which the following stand out: PrAl05FUA002, which affects the mason during the placement of the beams and vaults; and prFe05FUA003, which affects the rebar placer during the placement of the concrete reinforcements, both with a risk reduction of 83% (Figure 6). This quantitative analysis enables the level of risk of the project to be related to the investment made to reduce the risk (Figure 7). It can be observed that in Chapter 02 Earthworks, the values of investment and risk reduction are very close in the graph (Figure 7). Since the measures adopted have not entailed a high cost, nor have a high-risk reduction, the chapter also has a low risk level. In the case of Chapter 05 Structures, there is a high initial risk level due to the possibility of falling from a height. In this case, we can observe how the investment in protection measures is the highest of all chapters, but it also has a significant risk reduction achieved (Figure 7).
At a qualitative level, the proposed model enables the analysis to be conducted in the design phase of the risks to which workers are exposed according to their job. And at the same time, it is possible to obtain a quantitative assessment of the risk through the indicator for all the work units included in the project chapters. This allows the substitution of work units that generate an important level of risk during the project design phase. Table 6 shows two examples of work in which changing the construction element for an alternative solution (in bold in Table 6) reduces risks. Specifically, it is reduced by 6% in the case of changing the reticular slab by a concrete slab with self-resistant beams, the operator is prevented from repeatedly subjecting himself to the risk associated with removing the coffers. Another element is reduced by 86% by changing the brick enclosure from one that needs a single layer coating to an enclosure made of exposed brick, since the work unit for the execution of the single layer is directly eliminated and, therefore, the risks. In addition, the model makes it possible to check whether the protective measures included in the H&S budget correspond to the risks of its construction units. By studying several projects, the influential factors and cost can be optimised in order to achieve maximum safety, as in [56].
The main weakness of the present methodology is that it fails to consider any training of the workers (mandatory in Spanish legislation) since they are not connected to individual work units, and neither does this methodology take the preventative culture on the worksite into consideration since its effects need an independent model in order to assess its impact on H&S. Other aspects that have been excluded from this model and should be added in future work include monitoring, individual characteristics of the site condition, such as attitude/motivation, age/experience, and contractor size or rate of subcontracting, which are also influential on the safety level [2]. Similarly, other aspects that should be included are unsafe behaviours and accidents, such as safety climate/culture, information, and project management [57]. Furthermore, accidents are usually multicausal, resulting from a combination of overlapping factors [58]. Other authors have identified that the effect of basic safety investments on performance differs across different projects. The implication of their findings is that greater protection and a safer environment do not always produce better safety performance without improved safety culture [52].
Even though, as said in the discussion, there are elements that are missing in the analysis, the main focus of the work is to improve the H&S from the design stage by adding information to the already existing packages of information contained in the project work units, i.e., cost and environmental impacts, in order to improve from early stages of the project, the H&S assessment in parallel to other indicators. Because the work units are the vector of information, they can only contain part of the information related to H&S in the construction site, then not all the risks and their interconnection are represented. But the present work can be included as part of the information in a broader analysis.
Another aspect yet to be included is the evaluation of the opportunity cost of the investments in safety aimed at mitigating and preventing those serious accidents that can lead to financial losses and deaths [59], and the evaluation of the optimisation of such investments [56,60].

5. Conclusions

The social impact assessment of construction projects is the sustainability dimension less addressed. The present work shows that it is possible to define a methodology that can be implemented as part of construction cost databases, which are generic and commonly used. The proposed methodology allows the automation of the analysis of occupational risk prevention in the project phase. To this end, based on the information held in the project budget, which follows the structure of a cost database, the work procedures are established for all work units that are part of the project. These procedures are accompanied by their risk assessment and the measures necessary for the minimisation of their risk. Although it is impossible to eliminate every risk of the work procedures, the necessary measures in each group of tasks can clearly be defined.
At a qualitative level, it can be concluded that the model enables the automation of the analysis of the risks to which the workforce is exposed to be analysed according to their tasks, while, at the same time, calculates a quantitative assessment of the risk. Furthermore, it can be verified whether the protective measures incorporated in H&S budgets correspond to the risks of its construction units. The database of procedures, risks, and measures can evolve in a structured way with the evaluation of new projects.
The proposed quantitative analysis includes the study of the level of risk of a specific project, and the valuation of the economic investment necessary for the elimination or minimisation of such risk.
The methodology proposed that each time a new work unit is defined it can be accompanied in an automated manner by the risk assessment and the minimum prevention and protection measures, this will constitute an information package that can be attached to the economic and environmental assessments by employing a unified structure. The model can help companies define work procedures and conduct initial risk assessments in order to both complete their occupational risk prevention plans and correctly plan operator training courses.
It has been deduced that an automated construction procedures database is necessary that includes all the costs of the Andalusia Construction Cost Database so that every activity defined in the budget can be evaluated in terms of risk. This database can also be supplemented with procedures for diverse types of buildings. Procedures can also be managed by using BIM and by linking them to BIM objects of work units, and via their corresponding procedures and risks.
As future lines of research concerning the work undertaken herein, in order to help managers make better decisions about H&S investments, by getting a better idea of how effective certain budget allocations will be at lowering risks, decision trees and random forests can be used to predict campaign ROI, as in the work by Hayadi and Emary (2024) [61]. Also, Advance modelling techniques could potentially be used to create future models that combine budget data with elements that affect real on-site H&S resilience as in the work by Hery and Widjaja, A. E. (2024) [62]. The work methodology can also be combined with time-based patterns in H&S incident reports or construction site paperwork, like Buchdadi and Al-Rawahna (2025) [63] conducted for crime patterns, which could show important risk trend and patterns in H&S incident reports or construction site paperwork, like in Dewi, D. A., and Kurniawan, T. B. (2025) [64].

Author Contributions

Conceptualization, V.L.-R., M.M. and M.D.A.-R.; methodology, V.L.-R.; validation, V.L.-R. and M.D.A.-R.; investigation, V.L.-R. and M.D.A.-R.; resources, M.M. and M.D.A.-R.; data curation, M.D.A.-R.; writing—original draft preparation, M.M.; writing—review and editing, M.M. and M.D.A.-R.; visualization, V.L.-R., M.M. and M.D.A.-R.; supervision, V.L.-R. and M.M.; project administration, M.M. All authors have read and agreed to the published version of the manuscript.

Funding

This publication is the result of the research carried out in the research project (US.20-10): “Holistic model for the evaluation of the sustainability of the life cycle of social housing in Andalusia”. This project was funded within the 2020 call for grants for the development of research projects in the areas of housing, rehabilitation, and architecture by “the Junta de Andalucía, through the Ministry of Development, Infrastructure and Territory Planning”.

Data Availability Statement

The raw data supporting the conclusions of this article will be made available by the authors upon request.

Conflicts of Interest

The authors declare no conflicts of interest.

Appendix A

Appendix A.1

Table A1. Prevention measures applied in the case study. Catalogued per work chapter and per typology.
Table A1. Prevention measures applied in the case study. Catalogued per work chapter and per typology.
Prevention Measures per ChapterPrevention Measures per Type
02. Earthworks06. MasonryCollective protection
-
Non-slip safety boots
-
Placement of nets in façade openings
-
Free-edge guardrail
-
Non-slip safety boots
-
Placement of nets in façade openings
-
Railing on forged formwork
-
Safety helmet
-
Nets in enclosure voids
-
Railing on sloping slab formwork
-
Reflective vest
-
Work area delimitation
-
Railing on slab
-
Dorsal-lumbar girdles
-
Non-slip safety boots
-
Railing on inclined slab
-
Safety gloves
-
Helmet
-
Horizontal forged hollow railings
-
Perimeter dimensioning
-
Dorsal-lumbar girdle
-
Placement of railings on the edge of excavation
-
Delimitation of passage zones
-
Protective glasses
-
Placement of nets in façade openings
-
Safety gloves
-
Placement of rebar protection mushroom caps
-
Dust mask
-
Extinguisher
-
Under-forged nets
-
Nets in façade openings
-
Marquee
03. Foundation07. RoofsIndividual Protection
-
Placement of rebar protection mushroom caps
-
Extinguisher
-
Noise damper
-
Non-slip safety boots
-
Marquee
-
Safety harness
-
Wellies and safety boots
-
Safety harness
-
Non-slip safety boots
-
Safety helmet
-
Non-slip safety boots
-
Wellies
-
Reflective vest
-
Helmet
-
Wellies and safety boots
-
Dorsal-lumbar girdles
-
Reflective vest
-
Safety boots
-
Protective glasses
-
Safety gloves
-
Safety helmet
-
Safety gloves
-
Thermal gloves
-
Reflective vest
-
Perimeter dimensioning
-
Lifeline
-
Dorsal-lumbar girdle
-
Apron
-
Protective glasses
-
Knee pads
-
Safety gloves
-
Lower zone delimitation
-
Thermal gloves
-
Risk area signage
-
Lifeline
04. Sewerage system08. Installations
-
Apron
-
Placement of railings on the edge of excavation
-
Placement of nets in façade openings
-
Dust mask
-
Non-slip safety boots
-
Noise damper
-
Masks
-
Helmet
-
Non-slip safety boots
-
Knee pads
-
Dorsal-lumbar girdle
-
Helmet
-
Protective glasses
-
Protective glasses
-
Safety gloves
-
Safety gloves
-
Dust mask
-
Dust mask
-
Excavation bounding
-
Knee pads
-
Perimeter dimensioning of utility access hole
-
Delimitation of the work area
05. Structures09. InsulationSignalling and delimitation of spaces
-
Placement of rebar protection mushroom caps
-
Placement of nets in façade openings
-
Excavation bounding
-
Railing on forged formwork
-
Safety boots
-
Perimeter dimensioning of utility access hole
-
Railing on sloping slab formwork
-
Helmet
-
Dimensioning of work area in slab
-
Railing on slab
-
Reflective vest
-
Lower zone delimitation
-
Railing on inclined slab
-
Protective glasses
-
Perimeter dimensioning of the work area
-
Horizontal forged hollow railings
-
Safety gloves
-
Delimitation of passage zones
-
Under-forged nets
-
Masks
-
Risk area signage
-
Safety harness
-
Knee pads
-
Non-slip safety boots
-
Zone bounding
-
Wellies
10. Coatings
-
Wellies and safety boots
-
Free-edge guardrail
-
Helmet
-
Nets in façade openings
-
Safety helmet
-
Non-slip safety boots
-
Reflective vest
-
Safety boots
-
Dorsal-lumbar girdle
-
Helmet
-
Protective glasses
-
Reflective vest
-
Safety gloves
-
Dorsal-lumbar girdle
-
Lifeline
-
Protective glasses
-
Work area delimitation
-
Safety gloves
-
Dimensioning of work area in slab
-
Masks
-
Perimeter dimensioning
-
Knee pads
-
Delimitation of passage zones
-
Zone bounding
-
Lower zone delimitation
Table A2. Example calculation of the safety costs of the work unit 02PMM00012.
Table A2. Example calculation of the safety costs of the work unit 02PMM00012.
Work Units Budget
Procedure Quantity
(Unit)
Unit Cost (EUR/Unit)Cost
(EUR)
Chapter 02, Earthworks
Excavation, in shafts, with mechanical means up to 4 m and loading by truck
02PMM00012Digging in wells and loading by truck
PrOm02PMM001Backhoe excavation
Situation corrected
Technical factor
MachinesBackhoe loader 0.00
Auxiliary means
Installations
Collective protections
Personal protectionsSafety helmet1.001.691.69
Reflective vest1.002.772.77
Non-slip safety boots1.0027.7927.79
Signage and delimitation of spacesPerimeter shoulder50.001.7587.50
Delimit passage areas20.001.7535.00
Organizational factorCleaning of the pits 0.00
5 min breaks every 30 min 0.00
Environmental factor
prAl02PMM001Profiling of bottoms and sides
Situation corrected
Technical factor
Machines
Auxiliary meansLadder 0.00
Installations
Collective protections
Personal protectionsSafety helmet1.001.691.69
Reflective vest1.002.772.77
Non-slip and safety boots1.0027.7927.79
Safety gloves1.004.154.15
Lumbar girdle1.0011.9911.99
Signage and delimitation of spacesDelimit passage areas 0.00
Perimeter shoulder 0.00
Organizational factorCleaning of the pits 0.00
5 min breaks every 30 min 0.00
Environmental factor
Total cost of earthmoving prevention measuresTotal cost corrected situation203.14
Table A3. Calculation of risk reduction per procedure: (Al (mason), Am (insulation fixer), At (tiler), El (electrician), En (formwork), Es (plaster board placer), Fe (rebar worker), Fo (plumber), Ho (concrete mixer), Im (water-proofer), Om (machine operator), So (tiler), and Ye (plasterer). Information per work unit, chapter, and for the total project.
Table A3. Calculation of risk reduction per procedure: (Al (mason), Am (insulation fixer), At (tiler), El (electrician), En (formwork), Es (plaster board placer), Fe (rebar worker), Fo (plumber), Ho (concrete mixer), Im (water-proofer), Om (machine operator), So (tiler), and Ye (plasterer). Information per work unit, chapter, and for the total project.
CHAPTERACCD Unit CodeCode of ProceduresIp% Risk Reduction
UnitInitial RiskFinal RiskBy ProceduresBy Work UnitBy ChapterTotal
02 Earthworks
Digging foundation pads02PMM00012prOm02PMM0014151575%67%67%65%
prAl02PMM00111464%
03 Foundation
Concrete slab03ACC00010prFe03ACC00123961%61%61%
03HAZ00002prHo03HAZ00117665%65%
Contour beams 05HAC00010prFe05HAC002261062%62%
03ERM00001prEn03ERM00114750%50%
05HHJ00003prHo05HHJ00217853%53%
04 Sewer system
Buried sewer system04EAS00002prAl04EAS001114182627%37%37%
prAl04EAS002191047%
prAl04EAS00311827%
04EAP90002prAl04EAP001134082338%43%
prAl04EAP00217759%
prAl04EAP00310820%
04ECP90007prAl04ECP001144651764%63%
prAl04ECP00218761%
prAl04ECP00314564%
05 Structure
Self-resilient slab05FUA00005prAl05FUA002188731783%80%75%
prEn05FUA00225676%
prFe05FUA00324483%
prHo05FUA00320480%
Pillars05HAC00015prFe05HAC00318667%67%
05HET00001prEn05HET00123674%74%
05HHP00103prHo05HHP00116475%75%
05HED00051prEn05HED00123674%74%
Waffle slab05FBB00007prEn05FBB002266271873%71%
prFe05FBB00220670%
prHo05FBB00216569%
Inclined slab05HEM00101prEn05HEM00226773%73%
05HAC00015prFe05HAC00220670%70%
05HHL00103prHo05HHL00216475%75%
05HED00001prEn05HED00219574%74%
06 Masonry work
Enclosure06LPM00001prAl06LPM00115567%67%69%
06LPM00004prAl06LPM00213562%62%
Partitions06DSS00001prAl06DSS00117476%76%
07 Roof
Flat roof06LPM00001prAl06LPM00117665%65%69%
07HNF00021prAl07HNF001106541160%68%
prIm07HNF00217476%
prAl07HNF00310370%
prAl07HNF00410070%
prAl07HNF00510070%
prAl07HNF0068050%
10CEE00001prAl10CEE00111645%45%
07HNE00001prAl07HNE001184431083%77%
prIm07HNE00216475%
prAl07HNE00310370%
08 Installations
Electricity Installation08ECC00001prAl08ECC001162781479%48%66%
prEl08ECC00111645%
08EDD00004prAl08EDD001172881479%50%
prEl08EDD00111645%
08ELL00001prAl08ELL001152571279%52%
prEl08ELL00110550%
08ETT00003prAl08ETT00115250079%52%
prEl08ETT00110050%
8EWW00040prAl08EWW00112185779%61%
prEl08EWW0016267%
08EID00007prEl08EID0015260%60%
08EIM00102prEl08EIM0015260%60%
Water Installation08FAC00204prFo08FAC00111373%73%
08FAC00410prFo08FAC00211303973%70%
prAl08FAC00119668%
08FDP00022 prFo08FDP00112313875%74%
prAl08FDP00119574%
08FDP00050prFo08FDP00212313875%74%
prAl08FDP00219574%
08FDP00091prFo08FDP00312313875%74%
prAl08FDP00319574%
08FFP90300prFo08FFP001133351162%67%
prAl08FFP00120670%
08FFP90320prFo08FFP002133351162%67%
prAl08FFP00220670%
08FFP90830prFo08FFP003153551167%69%
prAl08FFP00320670%
08FGN00103prFo08FGN00112375%75%
08FSW00101prFo08FSW00111273673%78%
prAl08FSW00116381%
08FTC00651prFo08FTC001133251162%66%
prAl08FTC00119668%
08FVL00003prFo08FVL00112375%75%
08FVW00002prFo08FVW00112375%75%
09 Insulation
Insulation09TPP90220 prAl09TPP0013250142356%54%54%
prAm09TPP00218950%
Finishes
Trimming and plastering walls10CGG00006prYe10CGG00215940%40%58%
Tiling10AAE00023prAt10AAE002291452%52%
Ceramic flooring10SCS00003prSo10SCS00119763%63%
Terrazzo flooring 10STS00001prSo10STS00119763%63%
Plaster ceiling10TET00005prEs10TET00118856%56%
Trimming and plastering walls10CGG00005prYe10CGG00115940%40%
Tiles of staircase10PNP00001prSo10PNP00116569%69%
10PNZ00001prSo10PNZ00116569%69%
Monolayer10CWW00006prAl10CWW00115567%67%
10CWW00012prAl10CWW00215567%67%
10CWW00021prAl10CWW00315567%67%

References

  1. Hollnagel, E. Risk + Barriers = Safety? Saf. Sci. 2008, 46, 221–229. [Google Scholar] [CrossRef]
  2. Winge, S.; Albrechtsen, E.; Arnesen, J. A Comparative Analysis of Safety Management and Safety Performance in Twelve Construction Projects. J. Saf. Res. 2019, 71, 139–152. [Google Scholar] [CrossRef] [PubMed]
  3. Ahn, H.; Son, S.; Park, K.; Kim, S. Cost Assessment Model for Sustainable Health and Safety Management of High-Rise Residential Buildings in Korea. J. Asian Archit. Build. Eng. 2021, 21, 689–700. [Google Scholar] [CrossRef]
  4. Gambatese, J.A.; Behm, M.; Rajendran, S. Design’s Role in Construction Accident Causality and Prevention: Perspectives from an Expert Panel. Saf. Sci. 2008, 46, 675–691. [Google Scholar] [CrossRef]
  5. Gambatese, J.; Gibb, A.; Bust, P.; Behm, M. Expanding prevention through design (PTD) in practice: Innovation, change, and a path forward. J. Constr. Proj. Manag. Innov. 2017, 7, 1995–2006. Available online: https://hdl.handle.net/10520/EJC-c23fb9e63 (accessed on 22 February 2025).
  6. Jin, Z.; Gambatese, J.; Karakhan, A.; Nnaji, C. Analysis of Prevention through Design Studies in Construction: A Subject Review. J. Saf. Res. 2023, 84, 138–154. [Google Scholar] [CrossRef]
  7. BOE.Es-BOE-A-1997-22614; RD_1627/97 Real Decreto 1627/1997, de 24 de Octubre, Por El Que Se Establecen Disposiciones Mínimas de Seguridad y de Salud En Las Obras de Construcción. Ministerio de la Presidencia: Madrid, Spain, 1997.
  8. Ruiz-Pérez, M.R.; Alba-Rodríguez, M.D.; Marrero, M. Evaluation of Water Footprint of Urban Renewal Projects. Case Study in Seville, Andalusia. Water Res. 2022, 221, 118715. [Google Scholar] [CrossRef]
  9. Freire-Guerrero, A.; Alba-Rodríguez, M.D.; Marrero, M. A Budget for the Ecological Footprint of Buildings Is Possible: A Case Study Using the Dwelling Construction Cost Database of Andalusia. Sustain. Cities Soc. 2019, 51, 101737. [Google Scholar] [CrossRef]
  10. Swuste, P.; Frijters, A.; Guldenmund, F. Is It Possible to Influence Safety in the Building Sector?: A Literature Review Extending from 1980 until the Present. Saf. Sci. 2012, 50, 1333–1343. [Google Scholar] [CrossRef]
  11. Zalk, D.M.; Spee, T.; Gillen, M.; Lentz, T.J.; Garrod, A.; Evans, P.; Swuste, P. Review of Qualitative Approaches for the Construction Industry: Designing a Risk Management Toolbox. Saf. Health Work 2011, 2, 105–121. [Google Scholar] [CrossRef]
  12. Forteza, F.J.; Sesé, A.; Carretero-Gómez, J.M. CONSRAT. Construction Sites Risk Assessment Tool. Saf. Sci. 2016, 89, 338–354. [Google Scholar] [CrossRef]
  13. Karakhan, A.A.; Gambatese, J.A. Identification, Quantification, and Classification of Potential Safety Risk for Sustainable Construction in the United States. J. Constr. Eng. Manag. 2017, 143, 04017018. [Google Scholar] [CrossRef]
  14. Dewlaney, K.S.; Hallowell, M.R.; Fortunato, B.R. Safety Risk Quantification for High Performance Sustainable Building Construction. J. Constr. Eng. Manag. 2012, 138, 964–971. [Google Scholar] [CrossRef]
  15. Fortunato, B.R., III; Hallowell, M.; Behm, M.; Hallowell, M.R.; Dewlaney, K. Identification of Safety Risks for High-Performance Sustainable Construction Projects. J. Constr. Eng. Manag. 2012, 138, 499–508. [Google Scholar] [CrossRef]
  16. Bong, S.; Rameezdeen, R.; Zuo, J.; Li, R.Y.M.; Ye, G. The Designer’s Role in Workplace Health and Safety in the Construction Industry: Post-Harmonized Regulations in South Australia. Int. J. Constr. Manag. 2015, 15, 276–287. [Google Scholar] [CrossRef]
  17. Dharmapalan, V.; Gambatese, J.A.; Fradella, J.; Moghaddam Vahed, A. Quantification and Assessment of Safety Risk in the Design of Multistory Buildings. J. Constr. Eng. Manag. 2015, 141, 04014090. [Google Scholar] [CrossRef]
  18. Osburn, L.; Lee, H.W.; Gambatese, J.A. Formal Prevention through Design Process and Implementation for Mechanical, Electrical, and Plumbing Worker Safety. J. Manag. Eng. 2022, 38, 05022011. [Google Scholar] [CrossRef]
  19. Gangolells, M.; Casals, M.; Forcada, N.; Roca, X.; Fuertes, A. Mitigating Construction Safety Risks Using Prevention through Design. J. Saf. Res. 2010, 41, 107–122. [Google Scholar] [CrossRef]
  20. Fargnoli, M.; Lombardi, M. Building Information Modelling (BIM) to Enhance Occupational Safety in Construction Activities: Research Trends Emerging from One Decade of Studies. Buildings 2020, 10, 98. [Google Scholar] [CrossRef]
  21. Melzner, J.; Zhang, S.; Teizer, J.; Bargstädt, H.-J.; Ju¨, J.; Melzner, J.; Bargsta¨dt, H.-J.; Bargsta¨dt, B. A Case Study on Automated Safety Compliance Checking to Assist Fall Protection Design and Planning in Building Information Models. Taylor Fr. 2013, 31, 661–674. [Google Scholar] [CrossRef]
  22. Qi, J.; Issa, R.R.A.; Olbina, S.; Hinze, J. Use of Building Information Modeling in Design to Prevent Construction Worker Falls. J. Comput. Civ. Eng. 2014, 28, A4014008. [Google Scholar] [CrossRef]
  23. Zhang, S.; Teizer, J.; Lee, J.K.; Eastman, C.M.; Venugopal, M. Building Information Modeling (BIM) and Safety: Automatic Safety Checking of Construction Models and Schedules. Autom. Constr. 2013, 29, 183–195. [Google Scholar] [CrossRef]
  24. Yuan, J.; Li, X.; Xiahou, X.; Tymvios, N.; Zhou, Z.; Li, Q. Accident Prevention through Design (PtD): Integration of Building Information Modeling and PtD Knowledge Base. Autom. Constr. 2019, 102, 86–104. [Google Scholar] [CrossRef]
  25. Nnaji, C.; Gambatese, J.; Karakhan, A.; Osei-Kyei, R. Development and Application of Safety Technology Adoption Decision-Making Tool. J. Constr. Eng. Manag. 2020, 146, 04020028. [Google Scholar] [CrossRef]
  26. Cortés-Pérez, J.P.; Cortés-Pérez, A.; Prieto-Muriel, P. BIM-Integrated Management of Occupational Hazards in Building Construction and Maintenance. Autom. Constr. 2020, 113, 103115. [Google Scholar] [CrossRef]
  27. Collinge, W.H.; Farghaly, K.; Mosleh, M.H.; Manu, P.; Cheung, C.M.; Osorio-Sandoval, C.A. BIM-Based Construction Safety Risk Library. Autom. Constr. 2022, 141, 104391. [Google Scholar] [CrossRef]
  28. Zou, Y. BIM and Knowledge Based Risk Management System; University of Liverpool: Liverpool, UK, 2017. [Google Scholar]
  29. Marrero, M.; Rivero-Camacho, C.; Martínez-Rocamora, A.; Alba-Rodríguez, D.; Lucas-Ruiz, V. Holistic Assessment of the Economic, Environmental, and Social Impact of Building Construction. Application to Housing Construction in Andalusia. J. Clean. Prod. 2024, 434, 140170. [Google Scholar] [CrossRef]
  30. UNE-EN ISO 16739-1:2020; Intercambio de Datos En La Industria de Construcción y En La Gestión de Inmuebles Mediante IFC (Industry Foundation Classes). Parte 1: Esquema de Datos (ISO 16739-1:2018) (Ratificada Por La Asociación Española de Normalización En Abril de 2020). Asociación Española de Normalización: Madrid, Spain. Available online: https://www.une.org/encuentra-tu-norma/busca-tu-norma/norma?c=N0063503 (accessed on 2 February 2025).
  31. RD_2015/97 Royal Decree 1215/1997, of July 18, Which Establishes the Minimum Health and Safety Provisions for the Use of Work Equipment by Workers. Available online: https://www.boe.es/buscar/act.php?id=BOE-A-1997-17824 (accessed on 12 March 2023).
  32. BEDEC Construction Cost Bases; Institute of Construction Technology of Catalonia ITeC: Barcelona, Spain. Available online: https://itec.es/servicios/bedec/ (accessed on 4 March 2019).
  33. Rivero-Camacho, C.; Marrero, M. Water Footprint of the Life Cycle of Buildings: Case Study in Andalusia, Spain. In Advances of Footprint Family for Sustainable Energy and Industrial Systems; Green Energy and Technology; Springer: Cham, Switzerland, 2022; pp. 135–165. [Google Scholar] [CrossRef]
  34. CYPE. CYPE Arquitectura, Ingeniería y Construcción. Available online: https://www.cype.es/ (accessed on 12 March 2023).
  35. BPCM Base de Precios de La Construcción, Madrid. Available online: https://www.comunidad.madrid/servicios/vivienda/base-datos-construccion (accessed on 20 November 2023).
  36. PRECIOCENTRO Generador de Precios Descompuestos. Available online: https://preciocentro.com/ (accessed on 12 March 2023).
  37. ACCD Ministry of Development and Housing/Housing and Rehabilitation/Andalusian Construction Cost Database. Available online: https://www.juntadeandalucia.es/organismos/fomentoarticulaciondelterritorioyvivienda/areas/vivienda-rehabilitacion/planes-instrumentos/paginas/vivienda-bcca.html (accessed on 30 April 2025).
  38. FIEBDC Formato de Intercambio Estándar de Bases de Datos de Construcción. Available online: https://www.fiebdc.es/ (accessed on 12 March 2023).
  39. NTP-330 NTP 330; Simplified Accident Risk Assessment System. National Institute of Safety and Hygiene at Work: Madrid, Spain. Available online: https://www.sesst.org/wp-content/uploads/2020/11/ntp_330.pdf (accessed on 30 April 2025).
  40. Hignett, S.; McAtamney, L. Rapid Entire Body Assessment (REBA). Appl. Ergon. 2000, 31, 201–205. [Google Scholar] [CrossRef]
  41. Waters, T.R.; Putz-Anderson, V.; Garg, A.; Fine, L.J. Revised NIOSH Equation for the Design and Evaluation of Manual Lifting Tasks. Ergonomics 1993, 36, 749–776. [Google Scholar] [CrossRef]
  42. Borg, G.; Ljunggren, G.; Ceci, R. The Increase of Perceived Exertion, Aches and Pain in the Legs, Heart Rate and Blood Lactate during Exercise on a Bicycle Ergometer. Eur. J. Appl. Physiol. Occup. Physiol. 1985, 54, 343–349. [Google Scholar] [CrossRef]
  43. Karhu, O.; Kansi, P.; Kuorinka, I. Correcting Working Postures in Industry: A Practical Method for Analysis. Appl. Ergon. 1977, 8, 199–201. [Google Scholar] [CrossRef]
  44. Corlett, E.N.; Bishop, R.P. A Technique for Assessing Postural Discomfort. Ergonomics 1976, 19, 175–182. [Google Scholar] [CrossRef] [PubMed]
  45. McAtamney, L.; Nigel Corlett, E. RULA: A Survey Method for the Investigation of Work-Related Upper Limb Disorders. Appl. Ergon. 1993, 24, 91–99. [Google Scholar] [CrossRef] [PubMed]
  46. REBA NTP 601; Método REBA (Rapid Entire Body Assessment). National Institute of Safety and Hygiene at Work: Madrid, Spain. Available online: https://www.insst.es/documentacion/colecciones-tecnicas/ntp-notas-tecnicas-de-prevencion/17-serie-ntp-numeros-576-a-610-ano-2003/ntp-601-evaluacion-de-las-condiciones-de-trabajo-carga-postural.-metodo-reba-rapid-entire-body-assessment-. (accessed on 30 April 2025).
  47. Sangsawang, T.; Yang, L. Predicting Student Achievement Using Socioeconomic and School-Level Factors. Artif. Intell. Learn. 2025, 1, 20–34. [Google Scholar] [CrossRef]
  48. Ghaffar, S.A.; Setiawan, W.C.; Ghaffar, S.A.; Setiawan, W.C. Metaverse Dynamics: Predictive Modeling of Roblox Stock Prices Using Time Series Analysis and Machine Learning. Int. J. Res. Metaverse 2024, 1, 77–93. [Google Scholar] [CrossRef]
  49. ISO_45001:2018 ISO 45001:2018(En); Occupational Health and Safety Management Systems—Requirements with Guidance for Use. International Organization for Standardization: Geneva, Switzerland. Available online: https://www.iso.org/obp/ui/#iso:std:iso:45001:ed-1:v1:en (accessed on 12 June 2025).
  50. González-Vallejo, P.; Solís-Guzmán, J.; Llácer, R.; Marrero, M. La Construcción de Edificios Residenciales En España En El Período 2007-2010 y Su Impacto Según El Indicador Huella Ecológica. Inf. Constr. 2015, 67, e111. [Google Scholar] [CrossRef]
  51. Hamid, A.; Singh, B. Cost of Compliance with Health and Safety Management System among Contractor in Construction Industry. In Proceedings of the National Seminar on Civil Engineering Research, Johor Bahru, Malaysia, 14–15 April 2014; Universiti Teknologi Malaysia, Ed.; Universiti Teknologi Malaysia: Johor Bahru, Malaysia, 2014; pp. 14–15. [Google Scholar]
  52. Feng, Y. Effects of Safety Investments on Safety Performance of Building Projects. Saf. Sci. 2013, 59, 28–45. [Google Scholar] [CrossRef]
  53. Gurcanli, G.E.; Bilir, S.; Sevim, M. Activity Based Risk Assessment and Safety Cost Estimation for Residential Building Construction Projects. Saf. Sci. 2015, 80, 1–12. [Google Scholar] [CrossRef]
  54. Ibarrondo-Dávila, M.P.; López-Alonso, M.; Rubio-Gámez, M.C. Managerial Accounting for Safety Management. The Case of a Spanish Construction Company. Saf. Sci. 2015, 79, 116–125. [Google Scholar] [CrossRef]
  55. Camino López, M.A.; Ritzel, D.O.; Fontaneda, I.; González Alcantara, O.J. Construction Industry Accidents in Spain. J. Saf. Res. 2008, 39, 497–507. [Google Scholar] [CrossRef]
  56. Ketabi, A.B.; Heravi, G. Developing a Framework for Evaluating Construction Project Safety Levels and Optimal Cost Allocation to Safety Influential Factors. Eng. Constr. Archit. Manag. 2022, 29, 643–668. [Google Scholar] [CrossRef]
  57. Khosravi, Y.; Asilian-Mahabadi, H.; Hajizadeh, E.; Hassanzadeh-Rangi, N.; Bastani, H.; Behzadan, A.H. Factors Influencing Unsafe Behaviors and Accidents on Construction Sites: A Review. Taylor Fr. 2014, 20, 111–125. [Google Scholar] [CrossRef] [PubMed]
  58. Haslam, R.; Hide, S.; Atkinson, S.; Pavitt, T.; Gibb, A. Causal Factors in Construction Accidents; Health and Safety Executive: London, UK, 2003. [Google Scholar]
  59. Talarico, L.; Reniers, G. Risk-Informed Decision Making of Safety Investments by Using the Disproportion Factor. Process Saf. Environ. Prot. 2016, 100, 117–130. [Google Scholar] [CrossRef]
  60. Ma, Y.; Zhao, Q.; Xi, M. Decision-Makings in Safety Investment: An Opportunity Cost Perspective. Saf. Sci. 2016, 83, 31–39. [Google Scholar] [CrossRef]
  61. Hayadi, B.H.; El Emary, I.M.M. Predicting Campaign ROI Using Decision Trees and Random Forests in Digital Marketing. J. Digit. Mark. Digit. Curr. 2024, 1, 1–20. [Google Scholar] [CrossRef]
  62. Hery; Widjaja, A.E. Predictive Modeling of Blockchain Stability Using Machine Learning to Enhance Network Resilience. J. Curr. Res. Blockchain 2024, 1, 124–138. [Google Scholar] [CrossRef]
  63. Buchdadi, A.D.; Al, A.S.M.; Dharmawan Buchdadi, A.; Salamh, A.; Al-Rawahna, M. Temporal Crime Pattern Analysis Using Seasonal Decomposition and K-Means Clustering. J. Cyber Law 2025, 1, 65–87. [Google Scholar] [CrossRef]
  64. Dewi, D.A.; Kurniawan, T.B. Exploring Financial Trends through Topic Modeling and Time-Series Analysis: A Clustering Approach Using Latent Dirichlet Allocation (LDA) on Twitter Data. J. Digit. Soc. 2025, 1, 91–108. [Google Scholar] [CrossRef]
Figure 2. (A) Systematic classification ACCD. Example: 02PMM00012. Excavation of footings in soil of medium consistency, (B) schematic of the procedures coding. Example: prOm02PMM001. Digging a hole for the foundation concrete pad.
Figure 2. (A) Systematic classification ACCD. Example: 02PMM00012. Excavation of footings in soil of medium consistency, (B) schematic of the procedures coding. Example: prOm02PMM001. Digging a hole for the foundation concrete pad.
Buildings 15 02313 g002
Figure 3. Summary of equations and calculation methodology for the prevention indicator.
Figure 3. Summary of equations and calculation methodology for the prevention indicator.
Buildings 15 02313 g003
Figure 4. Work units with coding starting with 02PMM can adhere to one common procedure: pr0m02PMM001.
Figure 4. Work units with coding starting with 02PMM can adhere to one common procedure: pr0m02PMM001.
Buildings 15 02313 g004
Figure 5. Risk reduction percentage by chapters.
Figure 5. Risk reduction percentage by chapters.
Buildings 15 02313 g005
Figure 6. Risk reduction at unit cost level.
Figure 6. Risk reduction at unit cost level.
Buildings 15 02313 g006
Figure 7. Relation between percentage of risk reduction and cost of the measure.
Figure 7. Relation between percentage of risk reduction and cost of the measure.
Buildings 15 02313 g007
Table 1. Example of methodological development.
Table 1. Example of methodological development.
Project Data. Definition of Unit Cost
02PMM00002m3
Excavation of holes in earth of medium consistency conducted with mechanical means up to a maximum depth of 4 m, including extraction at the edges and profiling of bottom and sides.
Measured volume in natural profile.
CodeConceptQuantityCostCost
TP00100h SPECIAL LABOURER 0.12018.902.27
ME00400h BACKHOE0.13034.984.55
Direct costs6.82
10.62% Indirect costs0.72
Procedures of work units
CodeProcedure
prAl02PMM001Profiling of bottom and sides
prOm02PMM001Hole digging with backhoe
Division of the procedure into tasks/subtasks
prAl02PMM001Profiling of bottom and sides
Starting situation
-
The hole has been dug by the backhoe machine and the earth has been transported.
-
The machine is located near the hole.
Description of Level 1. Tasks and subtasks
1. Checking the depth in the hole.
1.1. By means of a tape measure and as a reference set a pike that delimits the foundation concrete pad: it must be verified that the measurement is correct.
2. Hand profiling of the hole.
2.1. The slopes of the hole must be outlined by hand with a shovel to avoid any debris that could damage it. The earth at the edge of the excavation is shovelled.
Final situation
-
Holes for foundation concrete pads are completed.
-
Earth collected at the edge of excavation.
Identification of procedure risks (example of a procedure)
prAl02PMM001Profiling of bottom and sides
Occupational safety risk
Risk identification:
  • Risk of falling by the operator who is checking the excavation, caused by the detachment of the walls of the hole.
  • Risk of pushing the officer who is checking the excavation into the hole with the excavator shovel due to lack of control or machine operator error.
Ergonomics risk
Risk identification:
3.
Risk of injury to the lower back from strained postures and repetitive movements when outlining the walls of the hole.
Table 2. Example of initial risk assessment.
Table 2. Example of initial risk assessment.
02PMM00002m3
CodeProcedure
prAl02PMM001Profiling of bottom and sides
Safety at work Risk numberProbability (P)Consequence (C)PXCInitial assessmentErgonomicsRisk numberInitial assessment
1241002400I43A-33
2241002400I4
Σ safety hazards at work8Σ ergonomic risks3
Final summary11
Table 3. Example of preventative measures taken.
Table 3. Example of preventative measures taken.
02PMM00002m3
CodeProcedure
prAl02PMM001Profiling of bottom and sides
Corrected situation
Technical factor Auxiliary means
-
Ladder
Personal protection
-
Safety helmet
-
Reflective vest
-
Non-slip safety boots
-
Safety gloves
-
Lumbar dorsum girdles
Collective protection---
Signalling and delimitation of spaces
-
Delimitation of passage zone
-
Perimeter dimensioning
Organisational factor
-
Cleaning of the faces of the hole excavated
-
5 min break every 30 min
Environmental factor
-
Running the task at more suitable temperatures
Table 4. Example of risk assessment of the improved situation.
Table 4. Example of risk assessment of the improved situation.
02PMM00002m3
CodeProcedure
prAl02PMM001Profiling of bottom and sides
Improved situation
Safety at work RiskCorrected assessmentErgonomicsRiskCorrected assessment
1IV13M-22
2IV1
Σ safety hazards at work2Σ ergonomic risks 2
Final summary4
Table 5. Costs per m2 of floor area and the risk reduction per chapter.
Table 5. Costs per m2 of floor area and the risk reduction per chapter.
Cost (EUR/m2)Risk Indicator (Ip/m2)Cost per Risk (EUR/Ip)
(EUR/Reduction)
ChaptersInitialCorrectedInitialCorrected
02. Earthworks0.530.860.0240.0080.03
03. Foundation11.5712.480.0780.030.03
04. Sewer system7.898.60.0660.0420.05
05. Structures83.0296.060.4960.1260.06
06. Masonry71.4372.880.0720.0220.05
07. Roof20.5921.340.2190.0690.01
08. Installations59.4660.550.7410.2530
09. Insulation27.7828.010.080.0370.01
10. Finishes105.86107.250.3790.1580.01
Total388.14408.022.1550.7460.24
Increased cost/decreased risk in the project per m2
Total(EUR/m2)%Total(Ip/m2)%
Cost increase19.895.12Ip reduction1.4165.4
Table 6. Alternative constructive solutions (in bold).
Table 6. Alternative constructive solutions (in bold).
CodeUnitConceptQCost
(EUR)
H&S Risks
05FBB00037m2Reticular slabs with recoverable coffers594.2826,534.6066
05FUA00005m2Concrete slab with self-resistant beams594.2832,822.0862
% improvement impact−19%+6%
10CWW00006 + 06LPM00001m2Single layer coating with aggregates on brick +
wall of small drills bricks
656.23523,197.9190
621.422,208.8415
06LPM00002m2Wall of small drills bricks with exposed face656.23531,715.8015
% improvement impact−30%−86%
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Alba-Rodríguez, M.D.; Lucas-Ruiz, V.; Marrero, M. Systematic Methodology for Estimating the Social Dimension of Construction Projects—Assessing Health and Safety Risks Based on Project Budget Analysis. Buildings 2025, 15, 2313. https://doi.org/10.3390/buildings15132313

AMA Style

Alba-Rodríguez MD, Lucas-Ruiz V, Marrero M. Systematic Methodology for Estimating the Social Dimension of Construction Projects—Assessing Health and Safety Risks Based on Project Budget Analysis. Buildings. 2025; 15(13):2313. https://doi.org/10.3390/buildings15132313

Chicago/Turabian Style

Alba-Rodríguez, María D., Valeriano Lucas-Ruiz, and Madelyn Marrero. 2025. "Systematic Methodology for Estimating the Social Dimension of Construction Projects—Assessing Health and Safety Risks Based on Project Budget Analysis" Buildings 15, no. 13: 2313. https://doi.org/10.3390/buildings15132313

APA Style

Alba-Rodríguez, M. D., Lucas-Ruiz, V., & Marrero, M. (2025). Systematic Methodology for Estimating the Social Dimension of Construction Projects—Assessing Health and Safety Risks Based on Project Budget Analysis. Buildings, 15(13), 2313. https://doi.org/10.3390/buildings15132313

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop