1. Introduction
The lower reaches of the Yellow River can be classified into three distinct morphological segments: the braided reach (from Baihe to Gaocun), the transitional reach (from Gaocun to Aishan), and the meandering reach (from Aishan to Lijin). In some of the wandering sections, a phenomenon known as a “secondary suspended river” has developed, characterized by a channel bed that is higher than the adjacent floodplain, which in turn lies above the surrounding ground level. Furthermore, the operation of the Xiaolangdi Reservoir has exacerbated the imbalance between water and sediment transport in the lower Yellow River [
1,
2]. The historical flood risk is characterized by high frequency (historically, two breaches every three years and one course change every century), large peak discharges (32,000 m
3/s in 1761, 36,000 m
3/s in 1843, 22,300 m
3/s in 1958, etc.), prominent overbank flood risk (overbank flooding may occur when the discharge exceeds 4600 m
3/s, and “small flood with high risk” units account for nearly 40% of the floodplain area), and a significant change in return period after engineering regulation (the design peak discharge decreased by about 43% after the operation of the Xiaolangdi Reservoir, and the flood of 22,000 m
3/s has been raised from a 60-year event to nearly a millennium event) [
3,
4]. The floodplain areas serve not only as crucial regions for flood detention and sediment deposition but also as important spaces for local livelihood and production activities [
5]. The total floodplain area in the lower Yellow River reaches approximately 3154 km
2, accounting for about 65% of the entire lower reach [
6]. With the increasing frequency of extreme hydrological events, the flood risk to residents in these regions is becoming increasingly severe.
Although the standardization and reinforcement of embankments in 2002 have largely mitigated the risk of overtopping and breaching, the structural integrity of these dikes remains untested by major floods [
7]. Moreover, in braided reaches, unstable river regimes and complex water–sediment conditions increase the likelihood of dike failure even under moderate flooding [
8]. Once overbank flow occurs, the lateral slope of the floodplain directs water toward the embankments, and topographical depressions at the dike to promote the development of flanking flow along the embankment—a phenomenon that poses a significant threat to levee safety [
9]. In this context, ecological protective forests established on the riverside of embankments can serve as a nature-based solution to reduce near-bank flow velocity and mitigate flanking erosion. However, the optimal configuration of such forests for enhancing sediment deposition and flow reduction along the lower Yellow River embankments remains poorly understood, representing a critical research gap that this study aims to address.
Ecological protective forests constitute a specialized vegetation system established on the waterside of river embankments, functioning both as wave dissipation structures and sources of emergency materials. As an integral component of flood control infrastructure, they provide an effective defensive line against flooding [
10] and concurrently act as a green ecological barrier [
11,
12]. The efficacy of wave dissipation is primarily determined by several factors, including forest width, spatial arrangement, stand density, tree bio-mechanical type, and bank slope [
13]. Research indicates that, for a given density, an equilateral triangular arrangement yields superior wave attenuation, and rigid plant species outperform flexible ones in this regard [
14]. No unified perspective exists, however, on the optimal scale for planting such forests to enhance sediment deposition near the embankment toe along the lower Yellow River. Among the suitable tree species, willow, pagoda tree, and ash tree, willow has been identified as the most effective [
7].
Vegetation affects water flow mainly through the mechanism of hydraulic resistance. This resistance is commonly parameterized using established coefficients, including the Manning’s roughness coefficient, the drag coefficient, and the Darcy–Weisbach friction factor [
15,
16,
17]. Key vegetation properties including density, stem diameter, flexibility, and arrangement govern flow structure [
18,
19,
20]. Studies on flexible turf show that flow resistance peaks and then declines with increasing density [
21,
22]. Hydraulic resistance on vegetated slopes correlates positively with the Reynolds number, with submerged and emergent vegetation respectively reducing and enhancing Reynolds shear stress [
23,
24]. Flow through vegetation produces an S-shaped vertical velocity profile, divisible into three layers: the inner plant area, the plant canopy, and the upper non-vegetated zone. The canopy layer exhibits the strongest velocity fluctuations, while the upper zone maintains a logarithmic distribution [
25,
26]. Overall, vegetation increases energy dissipation, particularly at the canopy top, and induces energy transfer from non-vegetated to vegetated areas [
27].
Vegetation significantly influences sediment transport dynamics. At low plant densities, the effect on sediment settling velocity is minimal. However, once vegetation density exceeds a certain threshold, a further increase leads to a notable reduction in the settling velocity. Additionally, under the same plant density, fine-stemmed vegetation tends to enhance sediment deposition more effectively than thick-stemmed plants due to its stronger adsorptive capacity [
28]. A critical vegetation density threshold has been identified: below this value, turbulence intensity increases with vegetation density, promoting sediment re-suspension; above it, turbulence intensity declines as density rises, thereby facilitating the deposition of suspended sediment [
29]. Moreover, vegetation can reduce the bed-load transport rate and modify the morphology of bed-form features such as sand waves [
30,
31]. Conversely, some studies suggest that vegetation may inhibit sediment deposition. For instance, vegetation has been observed to reduce sediment settling velocity, making sediment more prone to suspension compared to non-vegetation conditions [
32]. Flow interactions with plant stems can also induce local scouring around vegetation due to wake turbulence [
33]. As vegetation density increases, the average turbulence intensity between stems rises, which may further enhance sediment suspension.
Although extensive research has established the hydraulic principles of vegetated flows (e.g., drag, S-shaped velocity profiles, and density-dependent deposition), these studies have mostly focused on fully submerged, emergent, or idealized vegetation patches in low-sediment environments. Few have addressed the specific context of the lower Yellow River, characterized by (i) hyper-concentrated sediment loads [
34], (ii) overbank flow parallel to embankments rather than perpendicular to channel banks, and (iii) conical-canopy protective forests. Consequently, it remains unclear how different planting geometries (row spacing, plant spacing, and staggered vs. aligned arrangements) affect flow velocity reduction and sediment deposition under semi- and fully submerged conditions in such a unique setting. This study systematically compares four arrangements (A1–A4) under 24 scenarios. The new, transferable insight is that the row-to-plant spacing ratio (rather than absolute density alone) governs deposition efficiency in embankment-parallel flows. These findings provide design guidelines for nature-based embankment protection along sediment-laden rivers.
2. Materials and Methods
2.1. Study Area
The study area is the reach of the lower Yellow River in China between Huayuankou and Gaocun, which represents a typical wandering river segment, as shown in
Figure 1. This region lies within the North China Plain, covering an area of approximately 1695 km
2, with geographical coordinates ranging from 113°35′ E to 115°10′ E and 34°50′ N to 35°30′ N. The terrain exhibits a general trend of higher elevation in the west and lower elevation in the east. The climate is classified as a temperate monsoon type. The geomorphic types of the river channel are functionally classified into main river channels, floodplains, training and protection structures, productive embankments, roads, and farmland. The distance between the main embankments on both banks generally ranges from 5 km to 10 km, with the widest section reaching up to 24 km. The longitudinal slope of the river channel varies between approximately 2.65‱ and 1.72‱. The study area contains numerous floodplains, including fourteen floodplain zones such as Huayuankou, Changyuan, Yuanyang, and Dongming. Among these, the Yuanyang and Changyuan floodplains each cover an area exceeding 300 km
2, while the Fengqiu Backwater Area, WeiTan, and Dongming floodplain areas all have areas greater than 100 km
2.
2.2. Similarity Criterion of Experiment
Experiment focuses on the evolution of sediment-laden flow within the ecological protective forest area along the lower Yellow River embankment, including the hydrodynamic behavior of the flow and the mechanisms of sediment erosion and deposition. To accurately represent these processes, the experimental design must satisfy both hydrodynamic and sediment movement similarity criteria. Since the primary force governing flow movement is gravity, the Froude similarity criterion should be applied. Additionally, due to the presence of sediment, similarity in flow turbulence resistance must also be considered. Key similarity criteria for sediment transport include: bed load movement, suspended sediment transport, vertical distribution of sediment concentration, sediment-carrying capacity of the flow, and riverbed erosion and deposition patterns.
The following similarity criteria should be adhered to in the experimental design:
Similarity Criterion of Gravity:
Similarity Criterion of Flow Resistance:
Similarity Criterion of Stream Sediment Transport:
Similarity Criteria of Sediment Suspension:
Similarity Criteria of Sediment Incipient Motion:
Time Similarity Criteria of Water Flow Movement:
Similarity Criteria of Riverbed Erosion and Deposition:
where
λL is horizontal scale;
λH is vertical scale;
λV is average velocity scale of water flow;
λn is roughness scale;
λJ is gradient scale;
λs is sediment concentration scale of water flow;
λs* is sediment-carrying capacity scale of water flow;
λω is sediment settling velocity scale;
λVc is sediment incipient velocity scale;
λt1 is experimental water flow duration scale;
λt2 is river bed deformation time scale;
λγ0 is experimental dry bulk density scale of suspended sediment; and
m is coefficient, commonly taken as 0.5 in Yellow River channel model experiments.
Based on field observations of the morphological characteristics of the ecological protective forests along the lower Yellow River, and in consideration of laboratory constraints and established scaling practices, the geometric scales for this generalized flume experiment were determined as
λL =
λH = 80. Other relevant scales were subsequently derived in accordance with the previously stated similarity criteria. The specific scaling ratios used in the experiment are provided in
Table 1.
In addition to the similarity criteria outlined above, the experimental design should also adhere to the following constraints.
(1) Limitation of subcritical flow and supercritical flow
supercritical flow:
where
Fr is Froude number;
v is cross-sectional mean velocity;
g is gravity; and
h is mean water depth.
(2) Laminar and turbulent flow restriction conditions
Natural flow exhibits two distinct regimes: laminar flow and turbulent flow, each with fundamentally different characteristics. Since the Reynolds number of natural flow typically exceeds the critical value, it is generally in a turbulent state. Therefore, the experimental flow should also be maintained in the turbulent regime, ensuring that the Reynolds number remains greater than the critical Reynolds number.
(3) Limitation of resistance square area
Natural water flow, particularly during flood seasons, typically falls within the resistance square area—a state of fully developed turbulence. Therefore, the experimental flow must also be in a fully turbulent regime, which requires the Reynolds number in the model to exceed the critical range of 1000 to 2000.
(4) Limitation of surface tension
Due to the cohesive forces between water molecules, surface tension develops at the interface with other media. To ensure that the experimental flow is not unduly influenced by surface tension effects, a minimum water depth of 1.5 cm must be maintained.
2.3. Experimental Arrangement
2.3.1. Experimental Flume
The experiment was conducted in the Hydraulics and River Regulation Laboratory at North China University of Water Resources and Electric Power. A scaled physical model of the flume was constructed according to the predetermined geometric scale, with the specific configuration adapted to the available site conditions, as illustrated in
Figure 2.
The experimental system consists of three integrated components: a sediment–water mixing system, a water supply system, and a flume system. The main flume, constructed with smooth-surfaced plexiglass sidewalls and a high-density PVC rectangular base, measures 10 m in length, 1.0 m in width, and 0.35 m in height. Longitudinally, the flume was divided into five functional sections: the forebay, the front transition region, the experimental region, the rear transition region, and the withdrawal region. The forebay, situated between the inlet and the flow-stabilizing device, has dimensions of 1.0 m × 1.0 m × 0.2 m (L × W × H). Its primary function is to temporarily store and regulate the sediment-laden water delivered from the mixing tank via the supply system before it enters the experimental area.
A 20 cm long flow-stabilizing device was installed downstream of the forebay. This device was constructed from multiple PVC pipes, each with a diameter of 2 cm. During fabrication, the pipes were cut into 20 cm segments, arranged in tangential contact, and securely bonded using high-strength adhesive to form a compact honeycomb-structured bundle measuring 20 cm in both length and height. The primary function of this device is to dampen flow fluctuations and stabilize incoming currents. Water entering the forebay from the supply pipeline typically exhibits high turbulence intensity and complex flow behavior. The honeycomb configuration effectively dissipates these disturbances, promoting a more uniform flow profile essential for accurate hydraulic measurements in the experimental area. Inflow to the flume was regulated by an adjustable inlet valve, while a tailgate at the downstream end controlled the water level throughout the experiments.
2.3.2. Ecological Protective Forest Arrangement
The ecological protective forest model was positioned 4.00–5.40 m downstream from the steady flow device, covering a length of 1.40 m and a width of 0.35 m. Depending on the spacing configuration, the model consisted of 10 rows in the transverse (
x) direction and 20 rows along the streamwise (
y) direction. Four distinct arrangement patterns were implemented, as illustrated in
Figure 3:
Arrangement A1: The ecological protective forest models are arranged in 5 transverse rows, with uniform center-to-center spacing of 7 cm in both transverse and longitudinal directions.
Arrangement A2: Derived from A1 by removing all even-numbered rows along the longitudinal direction. This results in alternating transverse center spacings of 7 cm and 14 cm, and longitudinal spacings of 7 cm and 14 cm.
Arrangement A3: Derived from A1 by removing even-numbered rows in the transverse direction, yielding a transverse center spacing of 14 cm and a longitudinal spacing of 7 cm.
Arrangement A4: Derived from A1 by removing even-numbered rows along the longitudinal direction, resulting in a transverse center spacing of 7 cm and a longitudinal spacing of 14 cm.
The layout of measurement sections for flow velocity and sediment concentration is illustrated in
Figure 3. Four cross-sections (CS1–CS4) were established along the streamwise direction (
y-axis) within the protective forest area. CS1 is situated upstream of the leading edge of the forest; CS2 and CS3 are located inside the forest, with CS2 at one-third and CS3 at two-thirds of the total forest length; CS4 is positioned downstream of the trailing edge.
The ecological protective forest model was generalized based on typical tree species identified in the Dongming Beach area. Field investigations at Dongming Beach indicate that the dominant species used in these ecological protective forests are
Fraxinus chinensis and
Sophora japonica. Accordingly, the model trees were designed at experimental scale using morphological parameters representative of these species, which is shown in
Figure 4, with a vertical height of 12 cm, a maximum crown width of 7 cm horizontally, and a trunk diameter of approximately 4 mm. It is necessary to clarify that real tree species are simplified into rigid geometric models. To some extent, the omission of flexibility, porosity variation, branch motion, and seasonal foliage strongly limits ecological realism. This simplification requires further quantitative framing. Specifically, willow which was identified as the most effective species in Zhang et al. [
7] is highly flexible. Under high-flow conditions, flexible vegetation reconfigure such as bend and streamline in response to flow drag, which reduces their frontal area and drag coefficient relative to rigid vegetation of the same size [
35,
36,
37]. Luhar and Nepf [
37,
38] proposed the concept of “effective length” (
le) to quantify this drag reduction, showing that flexible blades generate substantially lower drag than rigid blades at high Cauchy numbers (Ca ≫ 1). Chapman et al. [
39] experimentally compared rigid and flexible cylindrical obstructions of identical size and found that flexibility significantly reduces measured drag forces. In the context of the present study, this implies that our rigid model trees likely overestimate flow resistance and, consequently, the sediment deposition promotion effect under submerged or high-velocity conditions. Lower velocities and partially submerged conditions may reduce this bias, but the direction of error is consistently towards overestimation of deposition enhancement.
Figure 4 illustrates the experimental zone configuration and measurement point locations under varying submergence conditions. The flume was divided into three regions: Region I extends from the right edge of the forest to the right flume wall; Region II corresponds to the forested area; and Region III spans from the left forest edge to the left embankment, featuring a triangular cross-section. In each measurement section, three points were arranged along the transverse direction (
x-axis) at normalized positions of
b/
B = 0.15, 0.37, and 0.65, where b denotes the distance from the point to the right flume wall and B represents the bottom width of the flume. Define submergence degree as the ratio of water depth (
H0) to the height of the protective forest model (
H). Two submergence degrees were set as 0.5 and 1.0. Along the vertical direction (
z-axis), three measurement points were set at each transverse location. For a submergence degree of 0.5, the vertical locations of measurement points were
Z/
H0 = 0.167, 0.5, and 0.833; for a submergence degree of 1.0, the locations of measurement points were
Z/
H0 = 0.083, 0.5, and 0.917, where
Z is the height above the flume bed and
H0 is the water depth.
2.3.3. Selection of Sediment
The sediment in the lower Yellow River consists predominantly of fine suspended particles, making it difficult to source suitable experimental sediment that strictly conforms to the scaled size requirements. In line with previous research and in consideration of the experimental objectives, natural sediment collected from the lower Yellow River was used in this study. The particle size distribution of the natural sediment was determined using a BT-9300ST laser particle size analyzer (Bettersize Instruments Ltd., Dandong, China). The gradation curve is presented in
Figure 5, and the median particle size (
d50) was measured as 0.0255 mm. It should be noted that natural sediment was used because ideal scaled sediment was unavailable. While understandable, this creates scaling inconsistency.
2.4. Experimental Scenario
Considering the combination of water and sediment in natural rivers, three characteristic water–sediment combinations were adopted: low flow with low sediment (
Q = 5 L/s,
S = 5 kg/m
3), high flow with low sediment (
Q = 10 L/s,
S = 5 kg/m
3), and high flow with high sediment (
Q = 10 L/s,
S = 10 kg/m
3). Under varying inflow and sediment conditions, a total of 24 experimental scenarios were conducted, as summarized in
Table 2.
Table 2 lists the key physical parameters for each experiment, including vegetation arrangement, water depth, submergence degree, discharge, sediment concentration, vertical vegetation density, and horizontal vegetation density. In all scenarios, the water depth is greater than 1.5 cm, satisfying the surface tension requirement.
The vertical vegetation density,
ρv, is defined as the ratio of the total longitudinal projected area,
Ah, of all vegetation elements on the flume cross-section to the cross-sectional flow area,
A1, measured at the center of the vegetation region. That is:
The horizontal vegetation density,
ρL, is defined as the ratio of the total projected area
AL of all vegetation elements on the riverbed to the total bed area
A2 within the protective forest region, expressed as:
Based on the experimental design and layout described previously, preliminary pretests were first carried out in order to detect any possible problems such as water leakage. Refinements were made to address issues observed during the pretests before formal experiments were conducted. The experimental procedure consisted of two main phases: pre-experimental preparation and experimental execution. The specific operational steps for each scenario were as follows:
(1) Preparation of Sediment-Laden Flow in the Mixing Tank
According to the target sediment concentration specified in the experimental design, a predetermined volume of clear water was added to the mixing tank, followed by a measured quantity of sediment. The mixing system was then activated and run for a sufficient period to achieve a homogeneous sediment–water mixture. Sediment concentration was verified using a pycnometer and an electronic balance. If the measured concentration was lower than the design value, additional sediment was added and mixed thoroughly before re-measurement. Conversely, if the concentration exceeded the target, clear water was added incrementally until the desired concentration was attained.
(2) Arrangement of the Ecological Protective Forest
To secure the model trees, a PVC board pre-drilled with holes was fixed to the flume bed. Following the experimental layout plan, tree models were inserted into the holes and firmly fastened to prevent displacement under flow conditions.
(3) Flume filling and Flow conditioning
The sediment–water mixing system was restarted and operated until homogeneity was re-achieved. Sediment concentration was checked again to confirm it met the experimental requirements. The water supply pump was then started to fill the flume gradually. Discharge was regulated via a control valve until the target flow rate was reached. The tailgate at the downstream end was adjusted to maintain a constant water depth along the flume.
(4) Experimental observation and Data Collection
Once steady flow conditions were established, velocity was measured using an electromagnetic current meter (Nanjing Huanyang Automation Co., Ltd., Nanjing, China), and sediment concentration samples were collected with a pycnometer. A camera was used to document flow patterns and related phenomena. After one hour of test duration, sediment deposition thickness within the experimental reach was measured with a calibrated scale.
(5) Post-Experiment Cleanup
After completing the measurements, accumulated sediment was thoroughly flushed from the flume using clean water. Measuring instruments were re-positioned and re-calibrated as necessary before starting the next experimental run.
2.5. Experimental Measuring Instrument
Discharge, flow velocity, water level, and sediment concentration were measured using an electromagnetic flowmeter (Nanjing Huanyang Automation Co., Ltd., Nanjing, China), an electromagnetic current meter, a ruler, a pycnometer, and an electronic balance, respectively, with a water pump serving as the water supply equipment. The inflow to the flume was measured using an integrated digital electromagnetic flowmeter (Model HY-LDG, Nanjing Huanyang Automation Co., Ltd. (Nanjing, China); see
Figure 6a). Flow velocity in the experimental area was measured using a laboratory electromagnetic current meter (Model LS-606, Nanjing Huanyang Automation Co., Ltd., Nanjing, China; see
Figure 6b,c). The water supply system employed a single-phase submersible electric pump (Model: QDX55-2-2.2, Changzhou Wanhe Electromechanical Co., Ltd., Changzhou, China). Key specifications include a power rating of 2.2 kW, supply voltage of 220 V, operating frequency of 50 Hz, pump head of 5 m, rotational speed of 2860 r/min, rated discharge capacity of 55 m
3/h, and outlet diameter of 100 mm.
A ruler with an accuracy of 1 mm was used for length measurements. The ruler was affixed to both the three-dimensional measuring frame and the side of the glass flume using double-sided adhesive tape to control the displacement of measuring instruments and monitor water depth. Sediment concentration was determined using twelve 50 mL pycnometers, numbered #1 to #12, as shown in
Figure 6d. Prior to measurement, each pycnometer was calibrated by filling it with clear water and repeatedly weighing it on an electronic balance; the average value from multiple calibrations was taken as the calibration constant. During sediment concentration measurement, each pycnometer was filled with sediment-laden water and weighed. The net mass of suspended sediment was obtained by subtracting the calibration constant from the total weight. Sediment concentration was then calculated by dividing this net mass by the volume of the pycnometer. An electronic balance (Model JA2003, Shanghai Sunny Hengping Scientific Instrument Co., Ltd. (Shanghai, China); maximum capacity 200 g, measurement accuracy ±0.001 g) was used for all mass measurements, as illustrated in
Figure 6e.
4. Discussion
4.1. Key Factor Controlling Deposition Efficiency
Based on experimental observations, the submergence process of the ecological protective forest can be divided into three distinct stages: trunk submergence stage, canopy submergence stage, and post-submergence stable stage. Based on the spatial distribution of mean velocity components, we infer the existence of complex flow patterns that may include trunk-scale turbulence and secondary circulation. These inferences are consistent with earlier vegetated-flow studies [
2,
15,
16,
25], but are not directly verified by turbulence measurements in the present experiment. Vegetation can slow down the flow velocity of water, a finding consistent with the research results of Khadami et al. [
15]; Sediqi et al. [
16]; and Xu et al. [
17]. Vertical velocities in Regions I and III generally followed a logarithmic profile, and Region II exhibited a distinct velocity minimum within the canopy layer. In terms of sediment retention performance, arrangement A1 yielded the optimal deposition results, followed by A2 and A4, while A3 demonstrated the least effectiveness. Comparative analysis revealed that increased density of ecological protective forests generally enhances deposition thickness which agrees with the study of Sediqi et al. [
16].
Horizontal vegetation density
ρL emerged as a governing factor influencing deposition efficiency, as quantitatively detailed in
Table 4. Under identical horizontal vegetation density conditions, higher vertical vegetation density
ρv consistently improved sediment retention capacity. The comparative relationship between the longitudinal and transverse spacing of trees determines the location of sediment deposition. An arrangement where the longitudinal spacing exceeds the transverse spacing can effectively promote sediment deposition.
Additionally, we provide a qualitative comparison between our laboratory findings and available field observations from the lower Yellow River floodplain sites (Yuanyang, Changyuan, and Dongming), as cited in Ref. [
7] and related surveys. Field observations at Dongming Beach indicate that sediment deposition is consistently thicker immediately upstream of existing protective forest patches than within or downstream. This matches our laboratory findings (
Figure 8 and
Figure 9), where the highest deposition occurred at CS1 (upstream of the forest leading edge) for all four arrangements. In the field, denser vegetation patches (naturally regenerated willow stands) show visibly greater sediment accumulation around trunks and along the toe of the embankment compared to sparser stands. Our A1 arrangement (highest vegetation density) consistently produced the greatest deposition thickness, confirming this monotonic relationship. Although high-resolution transect data are limited, concentration profiles measured at Yuanyang floodplain during moderate overbank events show a decreasing trend from the floodplain entrance towards the embankment toe, consistent with the longitudinal decay we quantified in
Section 3.3.2 (
Figure 12).
4.2. Further Discussion on Flow Incidence Angle
The experiments reported in this study were conducted exclusively under embankment-parallel flow conditions. As justified in
Section 3.2, this configuration is hydrologically representative because floodplain inundation events in the lower Yellow River ultimately stabilize into prolonged flow parallel to the embankments. However, overbank flows initially often impinge obliquely on dike toes, and it is under such oblique or transverse incidence that flanking erosion can be most damaging. Therefore, it is important to discuss qualitatively how the ranking of arrangements (A1 > A2 > A4 > A3) might change under non-parallel flow conditions.
Under oblique or transverse flow incidence, the effective spacing between trees in the streamwise direction is no longer the original longitudinal (ly) or transverse (lx) spacing as defined in the flume coordinate system. Instead, the flow encounters a combination of both spacings depending on the incidence angle. For arrangement A1 (square grid, lx = ly = 7 cm), the geometry is isotropic: the frontal area presented to the flow is insensitive to incidence angle. Arrangement A3 (row spacing 14 cm in the transverse direction, 7 cm in the streamwise direction) and arrangement A4 (7 cm transverse, 14 cm streamwise) are highly anisotropic. Under oblique flow, A3 and A4 may behave more similarly because the effective spacings in the flow direction converge. In contrast, arrangement A2 (alternating wide and narrow spacings in both directions) may create local flow acceleration and deceleration patterns that are sensitive to incidence angle. The relative superiority of A1 is likely to be robust. The ranking between A3 and A4 may become less distinct or even reverse under highly oblique or transverse flow, because their anisotropic spacing geometries exchange roles as the flow direction changes. A2 may experience a more complex response, potentially reducing its deposition effectiveness relative to A1, because alternating wide and narrow gaps could cause flow channeling under oblique incidence.
Thus, while the present results provide a clear ranking for embankment-parallel flow, the practical recommendation for field implementation (A1 with a row-to-plant spacing ratio of 1.0) should be considered robust only for the dominant flow direction parallel to the embankment. For sites where oblique or transverse overbank flows are frequent and erosive, additional experimental or numerical studies are needed to evaluate the performance of anisotropic arrangements (A2, A3, A4) under varying incidence angles. The present study therefore serves as a baseline, and future work should extend the investigation to oblique flow conditions.
4.3. Limitations
We selected a geometric scale to establish a flume experiment by scaling down the natural river channel and ecological protective forests accordingly. To better align the experimental conditions with natural flow characteristics, additional similarity criteria were considered, such as gravitational similarity, flow resistance similarity, and sediment movement similarity. It should be noted that due to the sediment particle size in the lower Yellow River being less than 1 mm, it was impossible to scale down the sediment according to the corresponding ratio. Therefore, natural sand (with a measured median diameter
d50 = 0.0255 mm) was used in the experiment. This resulted in dissimilarities between the experimentally measured flow velocity and sediment deposition thickness and those under natural conditions, making it impossible to directly scale the experimental data to represent natural river parameters. Given the complex nature of sediment-related issues in rivers, obtaining precise quantitative data is challenging, a limitation also observed in previous studies [
40,
41,
42,
43,
44]. This represents a constraint of the present study. Nevertheless, the regular patterns observed in the experiment can still provide scientific reference for disaster mitigation and flood control in the lower Yellow River.
(1) Direction of bias
Using unscaled natural fines (instead of lighter or coarser scaled sediment) likely leads to an underestimation of the deposition-promotion percentages reported in this study. The present fine sediment remains suspended longer, requiring greater flow deceleration to settle. Consequently, the measured promotion percentages (e.g., 6.8–20.6% for arrangement A1) are conservative lower-bound estimates. Conversely, the velocity reduction caused by vegetation is less affected by sediment scaling, because it is governed primarily by geometric and hydraulic similarity (Froude and Reynolds constraints), which were satisfied.
(2) Robustness of data
The relative ordering of sediment deposition effectiveness (A1 > A2 > A4 > A3) is robust and can be confidently transferred to prototype conditions. This ranking is governed by the row-to-plant spacing ratio and the resulting flow-blocking geometry, which are correctly represented even with unscaled sediment because all arrangements experienced the same sediment-scaling bias. In contrast, the absolute percentage values should be treated as qualitative indicators of relative performance rather than precise design numbers for the prototype Yellow River. The magnitudes are influenced by the unscaled sediment and should not be directly extrapolated without site-specific calibration.
(3) Guidance for transfer to prototype conditions
Advised to use the reported percentages only for comparative ranking among arrangements (A1 > A2 > A4 > A3) and for understanding the influence of submergence degree and spacing ratio. For quantitative design of ecological protective forests along the lower Yellow River embankments, the following conservative approach is recommended: (i) adopt the relative performance order to select arrangement A1 as the preferred layout; (ii) apply the measured promotion percentages as a lower-bound estimate; (iii) perform field validation or numerical modeling (e.g., using a calibrated vegetation drag model) to obtain site-specific deposition rates, because the absolute values cannot be obtained by simple geometric scaling of the flume data. The key transferable insight is that maximum horizontal vegetation density ρL and a row-to-plant spacing ratio of 1.0 (arrangement A1) maximizes deposition efficiency, not the specific percentage numbers.
Additionally, this study reports only mean velocity components measured with an electromagnetic current meter. No measurements of fluctuating velocities were obtained, such as Reynolds stresses, turbulent kinetic energy, or eddy frequencies. Therefore, interpretations involving wake turbulence, vortex shedding, or secondary circulation are qualitative inferences drawn from the existing literature rather than direct experimental evidence. Future work should employ advanced instrumentation (e.g., Acoustic Doppler Velocimeter, Particle Image Velocimetry) to directly quantify turbulence dynamics in ecological protective forests. Furthermore, this study does not consider non-rigid vegetation or the combined effects of waves and currents. As discussed in
Section 2.3.2, the use of rigid vegetation models instead of flexible ones introduces a systematic bias. Based on the literature on flexible vegetation reconfiguration [
37,
38,
39], rigid models overestimate drag forces by an amount that depends on flow velocity, vegetation stiffness, and submergence degree. Under fully submerged conditions with high flow velocities, the overestimation can be substantial. Consequently, the sediment deposition promotion percentages reported in this study (e.g., 6.8–20.6% for arrangement A1) likely represent upper-bound estimates for the performance of actual flexible protective forests under similar flow conditions. Future research should introduce a flexible vegetation model to verify the generalizability of the current research.
4.4. Practical Implications for Embankment Management
The present experiments demonstrate that arrangement A1 is the most effective among the four tested configurations for promoting sediment deposition under embankment-parallel flow conditions. However, translating this laboratory ranking into operational design choices for the Yellow River Conservancy Commission requires consideration of several practical constraints.
Arrangement A1 has the highest stem density per unit area. In many reaches of the lower Yellow River, the space between the embankment toe and the edge of the floodplain is limited by existing infrastructure such as roads, drainage ditches, and agricultural fields. Where land width is narrow, A1 may be physically impossible to implement at full scale. In such cases, A2 or A4 (which retain the same transverse spacing but reduce longitudinal density) could serve as practical compromises, acknowledging that they provide lower deposition enhancement (A2 and A4 gave 5.4% and 5.4% promotion under semi-submerged conditions vs. 7.6% for A1).
A1 requires approximately twice as many trees per hectare as A3 or A4, and roughly 1.5 times as many as A2 (depending on the exact removal pattern). For long embankment sections (hundreds of kilometers), the additional cost of seedlings, labor for planting, and subsequent maintenance (pruning, disease control, flood-damage replacement) is non-negligible. A cost-effectiveness analysis, balancing deposition benefit against planting density, would be needed before large-scale adoption.
A1 approximates a monoculture-like, high-density plantation. Continuous dense stands of a single tree species (e.g., willow or ash) may reduce habitat heterogeneity compared to patchier arrangements (A2 or A3) or mixed-species designs. While biodiversity was not an endpoint of this study, river managers are increasingly required to consider ecological co-benefits. A mosaic of A1 patches in high-priority erosion zones interspersed with lower-density A2 or A4 patches elsewhere might balance hydraulic performance with habitat diversity.
Dense forests reduce flow velocity effectively, which is desirable for deposition but may also back up floodwaters upstream, potentially increasing water levels and levee overtopping risk elsewhere. During extreme floods, rigid dense arrangements (A1) are more likely to trap woody debris, agricultural waste, or ice, which can further obstruct flow and cause local scour around accumulated material. The present experiments did not include debris or extreme flood conditions; therefore, the ranking A1 > A2 > A4 > A3 should be considered valid for ordinary overbank flows but not automatically extrapolated to design-flood conditions without additional study.
In summary, while arrangement A1 offers the highest deposition-promotion potential, its practical superiority must be weighed against land availability, cost, biodiversity, and extreme-flow conveyance. The most resilient solution for the lower Yellow River embankments is likely a context-dependent, multi-arrangement strategy rather than a single, uniform layout.
5. Conclusions
Based on field investigations of ecological protective forests in the lower Yellow River, an experimental flume was designed following similarity principles, with forest models constructed to represent typical morphological characteristics. A series of experiments was conducted under varied water–sediment conditions and abnormal flow scenarios. The flow-reducing and promoting sediment deposition effects of different arrangements, hydrological combinations, and submergence states were systematically analyzed. For the optimal arrangement pattern, detailed flow velocity and sediment concentration distributions were examined. Based on these findings, we discuss practical implementation considerations for the Yellow River Conservancy Commission. The main findings are summarized as follows:
(1) For high flow with low-sediment conditions with embankment-parallel flow, the average sediment deposition promotion rates for arrangements A1 to A4 were 7.6%, 5.4%, 4.7%, and 5.4%, respectively, under semi-submerged conditions. At full submerged state, the corresponding values increased to 11.38%, 10.85%, 8.60%, and 10.34%. Sediment promoted deposition efficiency increases with vegetation density and A1 providing the strongest promotion of deposition. For a given density, configurations with greater concentration in the transverse (x) direction yield superior deposition performance. Arrangement A1 is recommended as the priority layout for actual embankment engineering projects, with a maximum horizontal vegetation density ρL and a row-to-plant spacing ratio of 1.0.
(2) The flow-reducing effect of riverside ecological protective forests typically ranges between 5% and 75%, with particularly significant velocity reduction (up to 75%) observed at the relative depth Z/H0 = 0.5 under full submergence. Vertically, the streamwise velocity profile in semi-submerged forests (H0/H = 0.5) maintains a similar J-shaped distribution, while full submergence (H0/H = 1.0) produces a distinct velocity minimum near the canopy base.
(3) Across all experimental scenarios and regardless of submergence condition, the ecological protective forest area consistently exhibited a characteristic vertical sediment distribution: minimum concentrations near the water surface and maximum concentrations near the bed. At full submergence (H0/H = 1.0), the vertical gradients of both surface and mid-depth sediment concentration profiles were notably steeper than those observed at semi-submerged state (H0/H = 0.5), indicating significant canopy-induced modification of sediment distribution patterns in the water column. Furthermore, a clear longitudinal attenuation in sediment concentration was observed along the flow path through the forested area.