Stability Analysis of Cofferdam with Double-Wall Steel Sheet Piles under Wave Action from Storm Surges
Abstract
:1. Introduction
2. Experimental Details
2.1. Test Apparatus
2.2. Test Model and Materials
2.3. Monitoring System and Construction of the Model Cofferdam
- (1)
- The seabed and cofferdam outline were marked on a glass wall, followed by the layered construction of the seabed using quartz sand, each layer 10 cm thick. Piezometers were buried in the seabed according to the locations shown in Figure 3.
- (2)
- The two rows of steel sheet piles were installed with soil pressure sensors and optic fiber sensors (see Figure 3b) in the reserved notch, ensuring a depth inside the seabed of 30 cm. Two U-shaped rubber sealing strips were installed between the piles and the glass wall to prevent boundary seepage.
- (3)
- Four steel tie rods connecting two rows of steel sheet piles were installed (see Figure 3c). The optic fiber stress sensors were set on the middle of two tie rods to measure the tensile stress.
- (4)
- The space between the two rows of steel sheet piles was filled with quartz sand of the designed density until the cofferdam height reached 60 cm.
- (5)
- Five high-speed cameras were installed with full side view (the full seabed), local side view (the full cofferdam), top view, offshore side view, and landside view. The monitoring equipment was commissioned.
2.4. Test Procedure
- (1)
- The offshore side was filled to water depth (D) of 65 cm in 15 min followed by waiting for 30 min until the seepage flow reached a steady state with a steady phreatic line.
- (2)
- A sine wave was generated with wave height (HW) of 4 cm and period of 2 s for 15 min. Then, the wave-generating machine was turned off for 2–5 min until the water level basically became steady. This stage was called Stage 1.
- (3)
- Water was added to keep D of 65 cm and replace water lost due to seepage and wave overflow. A sine wave was generated with HW of 8 cm and period of 2 s for 12.5 min. Then, the wave-generating machine was turned off for 2–5 min until the water level basically became steady. This stage was called Stage 2.
- (4)
- Water was added to keep D at 65 cm. A sine wave with HW of 12 cm and period of 2 s was generated for 10 min. Then, the wave-generating machine was turned off for 7 min until the water level basically became steady. This stage was called Stage 3.
- (5)
- Water was added to the offshore side with D of 73 cm in 6 min followed by waiting for 1–2 min until the water level became steady. A sine wave was generated with HW of 4 cm and the period of 2 s in 10 min. Then, the wave-generating machine was turned off for 2–5 min until the water level basically became steady. This stage was called Stage 4.
- (6)
- Water was added to maintain a D of 73 cm. Water waves with HW of 8 cm and period of 2 s were generated until the cofferdam failed. This stage was called Stage 5.
3. Test Results and Analysis
3.1. Stage 0 (before the Wave-Generating Stage, D = 0~65 cm)
3.2. Stage 1 (D = 65 cm, HW = 4 cm)
3.3. Stage 2 (D = 65 cm, HW = 8 cm)
3.4. Stage 3 (D = 65 cm, HW = 12 cm)
3.5. Stage 4 (D = 73 cm, HW = 4 cm)
3.6. Stage 5 (D = 73 cm, HW = 8 cm)
3.7. Deformation during Failure of the DSSP Cofferdam
4. Numerical Simulation of the Dynamic Behavior of the DSSP in the Presence of Waves
4.1. Methodology
4.1.1. Introduction to Simulia Xflow
4.1.2. Introduction to Plaxis Software
4.1.3. Wave Functions in the Five Tests
4.1.4. Simulation Procedure
- (1)
- A numerical model consistent with the tank model test was established via Xflow software and wave surface equations were inputted as boundary conditions corresponding to different wave heights and water depths, as shown in Table 3, to obtain the time records of the force at the fluid–solid boundary.
- (2)
- The DSSP cofferdam model was built according to the parameters of the materials of the seabed, sand infill, steel sheep piles, and tie rods, as shown in Figure 16. The time records of the forces from the water and waves on the seaside pile with six segments (5 cm for each). The definitions of material parameters for backfill, steel sheet piles, tie rods, etc., in the numerical model are provided in Table 4, Table 5 and Table 6.
- (3)
- The dynamic simulation of the DSSP cofferdam under wave action was conducted to obtain the force and deformation of the cofferdam structure in the five stages introduced in the model test. The erosion was simulated by removing the corresponding finite element mesh in the cofferdam model.
4.2. Displacement of the Cofferdam
4.3. The Stress of the Cofferdam
5. Discussion
5.1. Comparisons of the Dynamic Behavior of the Cofferdam with Difference Methods
5.2. Deformation of the DSSP Cofferdam in Tests and Simulation
5.3. Behavior of the DSSP Cofferdam with Reinforced Measures in Different Seabeds
- (1)
- The seabeds close to both seaside and landside sheet piles were covered with geotextile bags filled with coarse sands to prevent soil erosion.
- (2)
- The height of the seaside sheet pile was increased 10 cm to reduce wave overflow.
- (3)
- The top of the cofferdam between the two piles was covered with clay packed with plastic bags to prevent soil erosion and water infiltration.
- (4)
- The junctions between the sheet piles and the glass walls were covered with clay for waterproofing.
5.4. Limitations
- (1)
- The influence of wave period was not investigated in this study due to the workload. The wave height is varied from 4 cm to 12 cm, while the period is constant at 2 s. This is not an appropriate setting for natural waves. The effect of the wave period will be studied in the future work.
- (2)
- The effect of increased pressure due to wave breaking is pointed out in both laboratory tests and numerical simulation, but the characteristics of wave breaking are not quantitatively studied due to the complex mechanisms. Additionally, the importance of erosion in the failure process is mentioned, and the similarities of Shields number and shear velocity were not examined, especially the dynamic erosion due to wave action.
- (3)
- The numerical analysis method used in this study is not truly a coupled method of CFD and FEM, and the mesh for erosion was removed manually. In addition, since the topographic change is expected to be affected by the reduction of soil strength due to liquefaction, the dynamic behavior of the pile model also needs to be discussed in the future.
6. Conclusions
- (1)
- The waves caused erosion and deposition in the seaside seabed, forming a slope inclined in the seaward direction. The angle of the slope increased with the wave height, decreasing the water depth close to the seaside pile. The tall waves and shallow water depth made the waves break, significantly increasing the dynamic wave pressure toward the seaside pile and the overflow volume.
- (2)
- The static water pressure caused the stress of the seaside pile to increase in the middle part. Small waves increased the stress in the bottom part of the seaside pile and continuous unrecoverable plastic deformation in the seabed soils. The breaking waves dramatically increased the stress and displacement of the seaside pile due to the large dynamic pressure. The erosion of the landside seabed made the stress and deformation of the landside pile the largest. The stresses on the tie rods depended on the relative displacement of the two piles, which showed that the effect of the tie rods maintained the DSSP cofferdam as a whole structure.
- (3)
- Despite the waterproof DSSP, the seepage from the high water head made the landside slope slide. The dynamic wave pressure accelerated the seepage and caused excess pore water pressure. The higher the wave was, the larger the excess pore water pressure. The overlap of the traveling and the reflected waves increased the excess pore water pressure in the area close to the seaside pile due to the taller overlapped wave and higher wave frequency.
- (4)
- The DSSP cofferdam failed under the combined action of the dynamic wave pressure and the erosion of the landside seabed and sand infill between the two piles. The dynamic wave pressure caused large deformation of the piles, leading to leakage between the glass wall and the piles. The leakage and overflow of the breaking waves resulted in significant erosion of the landside seabed and the sand infill, greatly weakening the support of the seabed. The dynamic wave pressure then pushed the DSSP cofferdam to failure.
- (5)
- The results of the simulation with the combined methods of CFD and FEM had trends that were similar to those of the measurement results in the tests. Compared to the quasi-static method and pseudo-dynamic method, the results of the simulation via the present method were much closer to the experimental measurements because the simulation included the dynamic wave pressure increase caused by breaking waves.
- (6)
- According to the deformation–leakage–erosion–tilting continuous failure mechanisms of the DSSP cofferdam, four reinforced measures were taken to reduce the wave overflow, leakage, and soil erosion. The reinforced DSSP cofferdam not only endured the maximal wave load in the tests but also stayed stable in even larger wave load. Meanwhile, the DSSP cofferdam in a clay interlayer seabed should have a higher wave wall due to large settlement caused by the soft clay.
Author Contributions
Funding
Data Availability Statement
Conflicts of Interest
References
- Gönnert, G.; Gerkensmeier, B. A multi-method approach to develop extreme storm surge events to strengthen the resilience of highly vulnerable coastal areas. Coast. Eng. J. 2015, 57, 1540002. [Google Scholar] [CrossRef]
- Wahl, T.C.; Mudersbach, J. Statistical assessment of storm surge scenarios within integrated risk analyses. Coast. Eng. J. 2015, 57, 1540003. [Google Scholar] [CrossRef]
- Streicher, M.; Kortenhaus, A.; Marinov, K.; Hirt, M.; Hughes, S.; Hofland, B.; Schüttrumpf, H. Classification of bore patterns induced by storm waves overtopping a dike crest and their impact types on dike mounted vertical walls—A large-scale model study. Coast. Eng. J. 2019, 61, 321–339. [Google Scholar] [CrossRef]
- Toyoda, M.; Fukui, N.; Miyashita, T.; Shimura, T.; Mori, N. Uncertainty of storm surge forecast using integrated atmospheric and storm surge model: A case study on Typhoon Haishen 2020. Coast. Eng. J. 2022, 64, 135–150. [Google Scholar] [CrossRef]
- Gui, M.W.; Han, K.K. An investigation on a failed double-wall cofferdam during construction. Eng. Fail. Anal. 2009, 16, 421–432. [Google Scholar] [CrossRef]
- Furuichi, H.; Hara, T.; Tani, M.; Nishi, T.; Otsushi, K.; Toda, K. Study on reinforcement method of dykes by steel sheet-pile against earthquake and tsunami disasters. Soil Eng. J. 2015, 10, 583–594. (In Japanese) [Google Scholar]
- Cheng, X.S.; Zheng, G.; Diao, Y.; Huang, T.M.; Deng, C.H.; Lei, Y.W.; Zhou, H.Z. Study of the progressive collapse mechanism of excavations retained by cantilever contiguous piles. Eng. Fail. Anal. 2017, 71, 72–89. [Google Scholar] [CrossRef]
- Wang, K.Z.; Gao, Y.H.; Jin, Z.H.; Zhou, X.; Chen, L.H.; Zhang, C. Research on stability of steep bank slope and reserved thin-walled rock cofferdam during excavation of intake foundation pit. Eng. Fail. Anal. 2022, 141, 106659. [Google Scholar] [CrossRef]
- Yi, F.; Su, J.; Zheng, G.; Cheng, X.S.; Zhang, J.T.; Lei, Y.W. Overturning progressive collapse mechanism and control methods of excavations retained by cantilever piles. Eng. Fail. Anal. 2022, 140, 106591. [Google Scholar] [CrossRef]
- Kimura, M.; Inazumi, S.; Too, J.K.A.; Isobe, K.; Mitsuda, Y.; Nishiyama, Y. Development and application of H-joint steel pipe sheet piles in construction of foundations for structures. Soils Found. 2007, 47, 237–251. [Google Scholar] [CrossRef]
- Mawer, R.W.; Byfield, M.P. Reduced modulus action in U-section steel sheet pile retaining walls. J. Geotech. Geoenviron. Eng. 2010, 136, 439–444. [Google Scholar] [CrossRef]
- Inazumi, S.; Kimura, M.; Kakuda, T.; Kobayashi, M. Water cut-off performance of H-jointed steel pipe sheet piles with HH joints attaching water-swelling materials. Soils Found. 2011, 51, 1019–1035. [Google Scholar] [CrossRef]
- Wang, J.F.; Xiang, H.W.; Yan, J.G. Numerical simulation of steel sheet pile support structures in foundation pit excavation. International Journal of Geomechanics. Int. J. Geomech. 2019, 19, 05019002. [Google Scholar] [CrossRef]
- Osthoff, D.; Grabe, J. Deformational behaviour of steel sheet piles during jacking. Comput. Geotech. 2018, 101, 1–10. [Google Scholar] [CrossRef]
- Kang; Zhu, B.; Lin, P.; Ju, J.; Zhang, J.; Zhang, D. Experimental and numerical study of wave-current interactions with a dumbbell-shaped bridge cofferdam. Ocean Eng. 2020, 210, 107433. [Google Scholar] [CrossRef]
- Ohori, K.; Takahashi, K.; Kawai, Y.; Shiota, K. Static analysis model for double sheet-pile wall structures. J. Geotech. Eng. ASCE 1988, 114, 810–825. [Google Scholar] [CrossRef]
- Khan, M.R.A.; Takemura, J.; Kusakabe, O. Centrifuge model tests on behavior of double sheet pile wall cofferdam on clay. Int. J. Phys. Model. Geotech. Model. Geotech. 2006, 6, 1–23. [Google Scholar] [CrossRef]
- Hou, Y.M.; Wang, J.H.; Gu, Q.Y. Deformation performance of double steel sheet piles cofferdam. J. Shanghai Jiaotong Univ. 2009, 43, 1577–1580. [Google Scholar]
- Mitobe, Y.; Adityawan, M.B.; Roh, M.; Tanaka, H.; Otsushi, K.; Kurosawa, T. Experimental study on embankment reinforcement by steel sheet pile structure against tsunami overflow. Coast. Eng. J. 2016, 58, 1640018-1–1640018-18. [Google Scholar] [CrossRef]
- Zhu, Y.; Gu, Q.Y.; Jiang, J.; Peng, M. Reliability analysis for overall stability of large-span double-row steel sheet-piled dock cofferdam based on Bayesian method. Rock Soil Mech. 2016, 37, 609–615. (In Chinese) [Google Scholar]
- Fujiwara, K.; Taenaka, S.; Otsushi, K.; Yashima, A.; Sawada, K.; Ogawa, T.; Takeda, K. Study on levee reinforcement using double sheet-piles with partition walls. Jpn. Geotech. Soc. Spec. Publ. 2017, 5, 11–15. [Google Scholar]
- Xue, R.Z.; Bie, S.A.; Guo, L.L.; Zhang, P.L. Stability analysis for cofferdams of pile wall frame structures. KSCE J. Civ. Eng. 2019, 23, 4010–4021. [Google Scholar] [CrossRef]
- Peng, M.; Li, Z.; Zhu, Y.; Zhang, J.L. Stability analysis of double-row steel sheet pile cofferdam with sandy and cohesive foundation under surge wave action. Geo-Risk 2023 Dev. Reliab. Risk Resil. 2023, 346, 195–203. [Google Scholar]
- Boltzmann, L. Weitere studien über das wärmegleichgewicht unter gasmolekülen. In Kinetische Theorie II; Springer: Berlin/Heidelberg, Germany, 1970. [Google Scholar]
- JTS 145-2015; Code of Hydrology for Harbour and Waterway. Ministry of Transport of the People’s Republic of China: Beijing, China, 2022.
Description | Value |
---|---|
Sand (%) | 100 |
Specific gravity | 2.4 |
Maximum dry density (kg/m3) | 1444 |
Minimum dry density (kg/m3) | 1240 |
Average dry density (kg/m3) | 1403 |
Soil friction angle at average density | 30.5° |
Stage | Water Depth, D (cm) | Wave Height, H (cm) | Period, T (s) | Wave Length, L (cm) |
---|---|---|---|---|
1 | 65 | 4 | 2 | 450 |
2 | 65 | 8 | 2 | 450 |
3 | 65 | 12 | 2 | 450 |
4 | 73 | 4 | 2 | 470 |
5 | 73 | 8 | 2 | 470 |
Test No. | Function Type | Function of the Wave |
---|---|---|
1 | WSF | |
VPF | ||
2 | WSF | |
VPF | ||
3 | WSF | |
VPF | ||
4 | WSF | |
VPF | ||
5 | WSF | |
VPF |
Test Condition | Relative Compactness of Backfill Sand (Dr) | Cofferdam Width S (cm) | Tie Rod Height (cm) | γ (kN/m3) | Eref (MPa) | ν | C (kPa) | Φ (°) |
---|---|---|---|---|---|---|---|---|
Standard condition | 0.80 | 20.00 | 4.00 | 16.00 | 25.00 | 0.30 | 2.50 | 30.10 |
Material | Material Type | EA (1 × 106 kN/m) | EI (kN·m2/m) | Thickness d (mm) | Unit Weight w (kN·m/m) |
---|---|---|---|---|---|
Steel plates | Linear elasticity | 1.14 | 2.38 | 5.00 | 78.00 |
Material | Material Type | EA (1 × 102 kN) | Interval L (cm) |
---|---|---|---|
Galvanized iron wire | Linear elasticity | 3.00 | 8.00 |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2024 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
Zhu, Y.; Bi, J.; Xing, H.; Peng, M.; Huang, Y.; Wang, K.; Pan, X. Stability Analysis of Cofferdam with Double-Wall Steel Sheet Piles under Wave Action from Storm Surges. Water 2024, 16, 1181. https://doi.org/10.3390/w16081181
Zhu Y, Bi J, Xing H, Peng M, Huang Y, Wang K, Pan X. Stability Analysis of Cofferdam with Double-Wall Steel Sheet Piles under Wave Action from Storm Surges. Water. 2024; 16(8):1181. https://doi.org/10.3390/w16081181
Chicago/Turabian StyleZhu, Yan, Jingchao Bi, Haofeng Xing, Ming Peng, Yu Huang, Kaifang Wang, and Xinyu Pan. 2024. "Stability Analysis of Cofferdam with Double-Wall Steel Sheet Piles under Wave Action from Storm Surges" Water 16, no. 8: 1181. https://doi.org/10.3390/w16081181
APA StyleZhu, Y., Bi, J., Xing, H., Peng, M., Huang, Y., Wang, K., & Pan, X. (2024). Stability Analysis of Cofferdam with Double-Wall Steel Sheet Piles under Wave Action from Storm Surges. Water, 16(8), 1181. https://doi.org/10.3390/w16081181