Sustainable Distribution Network Planning for Enhancing PV Accommodation: A Source–Network–Storage Coordinated Stochastic Approach
Abstract
1. Introduction
2. Source Load Temporal–Spatial Correlation Scenarios
2.1. Probabilistic Model of Source Load Temporal–Spatial Correlation Based on Copula Theory
2.2. Scenario Generation Based on the Monte Carlo Method
- (1)
- Randomly generate numbers within the interval [0, 1].
- (2)
- represent the marginal distribution function value of one random variable, and represent the marginal distribution function value of another random variable. can be obtained by the pre-selected optimal Copula function C, calculated by Equation (7):
- (3)
- is the value of the n-th function, which can be determined using Equation (8):
- (4)
- Repeating the above process k times, it is able to obtain k sets of peripheral distribution function values containing n random variables.
- (5)
- can be transformed into a joint distribution function scenario by solving the inverse function , where , and T is the total number of days.
2.3. Scenario Reduction Based on the K-Means Clustering Algorithm
3. Source–Network–Storage Collaborative Planning Model Based on Stochastic Scenarios
3.1. Objective Function
3.2. Constraints
3.2.1. Constraints of Distributed PV
- Constraints of Operation
- Constraints of Nominal Capacity
- Constraints of the Number of PV
3.2.2. Constraints of ESS
- Constraints of Operation
- Constraints of the Rated Power
- Constraints of the Rated Capacity
- Constraints of the Number of ESS
3.2.3. Constraints of Grid Expansion
- Single-Commodity Flow Constraints
- Constraints of the Quantitative Relationship Between Nodes and Edges
- Constraints of Grid Expansion
3.2.4. Constraints of Power Flow
- Power Flow Model
- Constraints of the Voltage
- Constraints of the Current
- Constraints of the Power
- Constraints of the Branch Circuit Power
3.2.5. Constraints of Other Equipment
- Constraints on the Operation of Group-Cutting Capacitors (CBs)
- Constraints on the Operation of Static Var Compensation (SVC)
- Constraints on the Operation of the On-load Tap Changer (OLTC)
4. Case Study
4.1. System Setup for the Case Study
4.2. Analysis of Stochastic Scenarios
4.3. Analysis of the 25-Bus System Planning Results
4.4. Analysis of the 54-Bus System Planning Results
4.5. Sensitivity Analysis
4.5.1. Analysis of the Impact of PV and Load Forecasting Errors
- (1)
- +10% Error Scenario (Pessimistic forecast): Actual PV output is 10% higher and load demand is 10% lower than forecasted.
- (2)
- −10% Error Scenario (Optimistic forecast): Actual PV output is 10% lower and load demand is 10% higher than forecasted.
4.5.2. Comparative Analysis of Different Scenario Reduction Methods
4.5.3. Analysis of the Impact of Cost Coefficients
5. Conclusions
- (1)
- By establishing a source load temporal–spatial correlation probabilistic model based on Copula theory and applying the Monte Carlo method and K-means clustering algorithm for scenario generation and reduction, four typical daily scenarios were obtained while preserving the variability of PV output and load demand. The results demonstrate that a small number of typical daily scenarios can effectively describe the uncertainty and temporal–spatial correlation of PV output and load demand variations while avoiding the curse of dimensionality during the solution process, further ensuring the computational efficiency.
- (2)
- Comparing planning schemes with and without considering source load temporal–spatial correlation, the schemes that account for this correlation consistently perform slightly better. They effectively mitigate the impact of PV and load uncertainty on the distribution network, enhance the network’s capacity for PV integration and consumption, reduce the distribution network comprehensive cost, and achieve an increase in economic benefits.
- (3)
- Comparing planning schemes with and without considering source load temporal–spatial correlation, the schemes that account for this correlation consistently perform slightly better. They effectively mitigate the impact of PV and load uncertainty on the distribution network, enhance the network’s PV hosting capacity, reduce the distribution network comprehensive cost, and contribute to the development of more sustainable distribution networks.
Author Contributions
Funding
Institutional Review Board Statement
Informed Consent Statement
Data Availability Statement
Conflicts of Interest
References
- Ding, T.; Li, C.; Yang, Y.; Jiang, J.; Bie, Z.; Blaabjerg, F. A Two-Stage Robust Optimization for Centralized-Optimal Dispatch of Photovoltaic Inverters in Active Distribution Networks. IEEE Trans. Sustain. Energy 2017, 8, 744–754. [Google Scholar] [CrossRef]
- Jafari, M.R.; Parniani, M.; Ravanji, M.H. Decentralized Control of OLTC and PV Inverters for Voltage Regulation in Radial Distribution Networks with High PV Penetration. IEEE Trans. Power Deliv. 2022, 37, 4827–4837. [Google Scholar] [CrossRef]
- Le, J.; Lang, H.; Liao, X.; Wang, J.; Mao, T. Affinely Adjustable Robust Optimization Method for Active Distribution Network Based on Generalized Linear Polyhedral. Autom. Electr. Power Syst. 2023, 47, 138–148. [Google Scholar]
- Ayalew, M.; Khan, B.; Giday, I.; Mahela, O.P.; Khosravy, M.; Gupta, N.; Senjyu, T. Integration of Renewable Based Distributed Generation for Distribution Network Expansion Planning. Energies 2022, 15, 1378. [Google Scholar] [CrossRef]
- Mahdavi, M.; Kimiyaghalam, A.; Alhelou, H.H.; Javadi, M.S.; Ashouri, A.; Catalão, J.P.S. Transmission Expansion Planning Considering Power Losses, Expansion of Substations and Uncertainty in Fuel Price Using Discrete Artificial Bee Colony Algorithm. IEEE Access 2021, 9, 135983–135995. [Google Scholar] [CrossRef]
- Li, C.; Feng, C.; Li, J.; Hu, D.; Zhu, X. Comprehensive Frequency Regulation Control Strategy of Thermal Power Generating Unit and ESS Considering Flexible Load Simultaneously Participating in AGC. J. Energy Storage 2023, 58, 106394. [Google Scholar] [CrossRef]
- Ye, G.; Qian, X.; Yang, X.; Zhao, L.; Shang, J.; Wu, M.; Zhao, T. Planning of PV-ESS System for Distribution Network Considering PV Penetration. In Proceedings of the 2020 IEEE 3rd International Conference on Electronics Technology (ICET), Chengdu, China, 8–12 May 2020; pp. 339–343. [Google Scholar]
- Memarzadeh, G.; Keynia, F. A New Hybrid CBSA-GA Optimization Method and MRMI-LSTM Forecasting Algorithm for PV-ESS Planning in Distribution Networks. J. Energy Storage 2023, 72, 108582. [Google Scholar] [CrossRef]
- Wang, Y.; Jiang, Y.; Liu, H.; Pan, T. Research on Coordinated Planning for Wind-PV-ESS Integration into the Distribution Grid Based on Presentative Scenarios. In Proceedings of the 2024 7th International Conference on Energy, Electrical and Power Engineering (CEEPE), Yangzhou, China, 26–28 April 2024; pp. 1378–1382. [Google Scholar]
- Cho, K.-H.; Kim, J.; Byeon, G.; Son, W. Optimal Sizing Strategy and Economic Analysis of PV-ESS for Demand Side Management. J. Electr. Eng. Technol. 2024, 19, 2859–2874. [Google Scholar] [CrossRef]
- Bhadoria, V.S.; Pal, N.S.; Shrivastava, V. Artificial Immune System Based Approach for Size and Location Optimization of Distributed Generation in Distribution System. Int. J. Syst. Assur. Eng. Manag. 2019, 10, 339–349. [Google Scholar] [CrossRef]
- Pompern, N.; Premrudeepreechacharn, S.; Siritaratiwat, A.; Khunkitti, S. Optimal Placement and Capacity of Battery Energy Storage System in Distribution Networks Integrated with PV and EVs Using Metaheuristic Algorithms. IEEE Access 2023, 11, 68379–68394. [Google Scholar] [CrossRef]
- Tao, L.; Gao, Y.; Cao, L.; Zhu, H. Distributed Real-Time Pricing for Smart Grid Considering Sparse Constraints and Integration of Distributed Energy and Storage Devices. Compel-Int. J. Comput. Math. Electr. Electron. Eng. 2021, 40, 978–996. [Google Scholar] [CrossRef]
- Zhang, Y.; Ren, S.; Dong, Z.Y.; Xu, Y.; Meng, K.; Zheng, Y. Optimal Placement of Battery Energy Storage in Distribution Networks Considering Conservation Voltage Reduction and Stochastic Load Composition. IET Gener. Transm. Distrib. 2017, 11, 3862–3870. [Google Scholar] [CrossRef]
- Liu, T.; Chen, J.; Zhang, W.; Zhang, Y. Joint Planning for PV-SESS-MESS in Distribution Network towards 100% Self-Consumption of PV via Consensus-Based ADMM. J. Energy Storage 2024, 90, 111747. [Google Scholar] [CrossRef]
- Qi, C.; Wang, K.; Fu, Y.; Li, G.; Han, B.; Huang, R.; Pu, T. A Decentralized Optimal Operation of AC/DC Hybrid Distribution Grids. IEEE Trans. Smart Grid 2018, 9, 6095–6105. [Google Scholar] [CrossRef]
- Mukhopadhyay, B.; Das, D. Multi-Objective Dynamic and Static Reconfiguration with Optimized Allocation of PV-DG and Battery Energy Storage System. Renew. Sustain. Energy Rev. 2020, 124, 109777. [Google Scholar] [CrossRef]
- Gu, G.; Yang, P.; Tang, B.; Wang, D.; Lai, X. A Method for Improving the Balance Ability of Distribution Networks Through Source-Load-Storage Collaborative Optimization. Proc. Chin. Soc. Electr. Eng. 2024, 44, 5097–5109. [Google Scholar] [CrossRef]
- Li, Y.; Feng, B.; Wang, B.; Sun, S. Joint Planning of Distributed Generations and Energy Storage in Active Distribution Networks: A Bi-Level Programming Approach. Energy 2022, 245, 123226. [Google Scholar] [CrossRef]
- Sannigrahi, S.; Ghatak, S.R.; Acharjee, P. Multi-Scenario Based Bi-Level Coordinated Planning of Active Distribution System Under Uncertain Environment. IEEE Trans. Ind. Appl. 2020, 56, 850–863. [Google Scholar] [CrossRef]
- Deng, H.; Zheng, Y.; Zhang, X.; Zeng, F.; Zheng, R. Distributed Power Planning and Reactive Power Optimization Strategies Considering Timing Scenarios. J. Guizhou Univ. (Nat. Sci.) 2023, 40, 74–81. [Google Scholar] [CrossRef]
- Lü, B.; Yan, W.; Zhao, X.; Yu, J. Coordinated Allocation of Tie Lines and DWGs Considering Random Energy. Proc. Chin. Soc. Electr. Eng. 2013, 33, 145–152+23. [Google Scholar] [CrossRef]
- Ji, X.; Li, C.; Xie, B.; Wang, Y.; Wang, Q. A Wind Power Scenario Simulation Method Considering Trend and Randomness. In Proceedings of the 16th Annual Conference of China Electrotechnical Society; Liang, X., Li, Y., He, J., Yang, Q., Eds.; Springer Nature Singapore: Singapore, 2022; pp. 1043–1050. [Google Scholar]
- Xiao, C.; Ye, J.; Esteves, R.M.; Rong, C. Using Spearman′s Correlation Coefficients for Exploratory Data Analysis on Big Dataset. Concurr. Comput. Pract. Exp. 2016, 28, 3866–3878. [Google Scholar] [CrossRef]
- Alzaid, A.A.; Alhadlaq, W.M. A New Family of Archimedean Copulas: The Half-Logistic Family of Copulas. Mathematics 2024, 12, 101. [Google Scholar] [CrossRef]
- Rosenblatt, M. Remarks on Some Nonparametric Estimates of a Density Function. Ann. Math. Stat. 1956, 27, 832–837. [Google Scholar] [CrossRef]
- Zhao, L.; Zeng, Y.; Li, Y.; Peng, D.; Wang, Y. Coordinated Planning of Power Systems under Uncertain Characteristics Based on the Multilinear Monte Carlo Method. Energies 2023, 16, 7761. [Google Scholar] [CrossRef]
- Ebeed, M.; Abdel-Fatah, S.; Kamel, S.; Nasrat, L.; Jurado, F.; Harrison, A. Incorporating Photovoltaic Inverter Capability into Stochastic Optimal Reactive Power Dispatch through an Enhanced Artificial Gorilla Troops Optimizer. IET Renew. Power Gener. 2023, 17, 3267–3288. [Google Scholar] [CrossRef]
- Lavorato, M.; Franco, J.F.; Rider, M.J.; Romero, R. Imposing Radiality Constraints in Distribution System Optimization Problems. IEEE Trans. Power Syst. 2012, 27, 172–180. [Google Scholar] [CrossRef]
- Bobo, L.; Venzke, A.; Chatzivasileiadis, S. Second-Order Cone Relaxations of the Optimal Power Flow for Active Distribution Grids: Comparison of Methods. Int. J. Electr. Power Energy Syst. 2021, 127, 106625. [Google Scholar] [CrossRef]
- Chowdhury, M.M.-U.-T.; Kamalasadan, S.; Paudyal, S. A Second-Order Cone Programming (SOCP) Based Optimal Power Flow (OPF) Model with Cyclic Constraints for Power Transmission Systems. IEEE Trans. Power Syst. 2024, 39, 1032–1043. [Google Scholar] [CrossRef]
- Sarimuthu, C.R.; Ramachandaramurthy, V.K.; Agileswari, K.R.; Mokhlis, H. A Review on Voltage Control Methods Using On-Load Tap Changer Transformers for Networks with Renewable Energy Sources. Renew. Sustain. Energy Rev. 2016, 62, 1154–1161. [Google Scholar] [CrossRef]
Scheme | Grid Expansion | PV Siting and Capacity Setting | ESS Siting and Capacity Setting | Reactive Power Compensation | OLTC |
---|---|---|---|---|---|
1 | √ | — | — | — | — |
2 | √ | √ | — | √ | √ |
3 | √ | — | √ | √ | √ |
4 | √ | √ | √ | √ | √ |
Parameter | 25-Bus System | 54-Bus System |
---|---|---|
Substation active power/kW | [0, 5000] | [0, 10,000] |
Substation reactive power/kW | [0, 2500] | [0, 5000] |
Limit of bus voltage/p.u. | [0.95, 1.05] | [0.95, 1.05] |
Upper limit of branch power/MVA | 10 | 10 |
Upper limit of branch current/p.u. | 1 | 1 |
Reference voltage/kV | 12.66 | 12.66 |
Reference power/MW | 10 | 10 |
Limitations of PV | 25-Bus System | 54-Bus System |
---|---|---|
Installation quantity limit in Scheme 1 | 0 | 0 |
Installation quantity limit in Scheme 2 | [2, 5] | [3, 8] |
Installation quantity limit in Scheme 3 | 0 | 0 |
Installation quantity limit in Scheme 4 | [3, 8] | [5, 10] |
Maximum installation capacity at buses/MW | 1.5 | 3 |
Limitations of ESS | 25-Bus System | 54-Bus System |
---|---|---|
Installation quantity limit in Scheme 1 | 0 | 0 |
Installation quantity limit in Scheme 2 | 0 | 0 |
Installation quantity limit in Scheme 3 | [1, 5] | [1, 8] |
Installation quantity limit in Scheme 4 | [1, 5] | [1, 8] |
Rated power/MW | 2 | 2 |
Charging efficiency | 0.9 | 0.9 |
Discharging efficiency | 1 | 1 |
Limit of SOC | [0.2, 0.9] | [0.2, 0.9] |
Limitations of CB | 25-Bus System | 54-Bus System |
---|---|---|
Buses to be installed in Scheme 1 | — | — |
Buses to be installed in Scheme 2 | 21 | 13 |
Buses to be installed in Scheme 3 | 21 | 13 |
Buses to be installed in Scheme 4 | 21 | 13 |
Reactive power per compensation unit/kVar | 50 | 50 |
Maximum number of compensation units | 4 | 4 |
Maximum number of CB operations per day | 5 | 5 |
Limitations of SVC | 25-Bus System | 54-Bus System |
---|---|---|
Buses to be installed in Scheme 1 | — | — |
Buses to be installed in Scheme 2 | 18 | 6 |
Buses to be installed in Scheme 3 | 18 | 6 |
Buses to be installed in Scheme 4 | 18 | 6 |
Compensation range/kVar | [−200, 300] | [−200, 300] |
Limitations of OLTC | 25-Bus System | 54-Bus System |
---|---|---|
Branches to be installed in Scheme 1 | — | — |
Branches to be installed in Scheme 2 | 1–22, 3–23, 14–24, 21–25 | 5–52, 6–51, 41–53, 50–54 |
Branches to be installed in Scheme 3 | 1–22, 3–23, 14–24, 21–25 | 5–52, 6–51, 41–53, 50–54 |
Branches to be installed in Scheme 4 | 1–22, 3–23, 14–24, 21–25 | 5–52, 6–51, 41–53, 50–54 |
Transformer ratio | [0.95, 1.05] | [0.95, 1.05] |
Tap change step value of the transformer | 0.01 | 0.01 |
Number of taps on the transformer | 10 | 10 |
Costs | Value |
---|---|
PV curtailment penalty/(CNY/kWh) | 3.6 |
Annualized investment cost per unit capacity of ESS/(CNY/kWh) | 1270 |
Annualized investment cost per unit power of ESS/(CNY/kWh) | 1650 |
Unit length construction cost of the line/(CNY10,000/km) | 36.2 |
Normal Copula | t-Copula | Gumbel Copula | Clayton Copula | Frank Copula | Sample Data | |
---|---|---|---|---|---|---|
Kendall rank correlation coefficient | −0.078 | −0.091 | 1.457 × 10−6 | 7.729 × 10−7 | −0.089 | −0.082 |
Spearman rank correlation coefficient | −0.087 | −0.133 | 2.936 × 10−6 | 1.169 × 10−6 | −0.127 | −0.122 |
Squared Euclidean distance | 0.842 | 107.173 | 2.169 | 2.749 | 0.226 | 0 |
Typical Daily Scenarios | Probability |
---|---|
1 | 0.3907 |
2 | 0.0696 |
3 | 0.2444 |
4 | 0.2953 |
System | Scheme | Installed Bus | Installed Capacity/MW | Total Generation/MWh |
---|---|---|---|---|
25-bus system | 2 | 10, 12, 19 | 9.85 | 7019.54 |
4 | 10, 12, 16, 19 | 11.82 | 9502.61 |
System | Scheme | Installed Bus | Total Installed Apparent Power/kVA | Total Installed Capacity/kWh |
---|---|---|---|---|
25-bus system | 3 | 5, 16 | 1100 | 1600 |
4 | 2, 11, 17 | 1700 | 2200 |
Scheme 1 | Scheme 2 | Scheme 3 | Scheme 4 | |
---|---|---|---|---|
ESS investment cost/CNY10,000 | 0 | 0 | 227.3 | 343.13 |
Curtailment penalty cost/CNY10,000 | 0 | 1354.24 | 0 | 42.64 |
Grid expansion cost/CNY10,000 | 618.24 | 589.23 | 640.23 | 589.26 |
Distribution network comprehensive cost/CNY10,000 | 618.24 | 1943.47 | 867.53 | 975.03 |
EENS | 0 | 0 | 0 | 0 |
Solving time/s | 145.27 | 269.27 | 194.94 | 846.69 |
Considering the Source Load Temporal–Spatial Correlation Scenario | Scheme | Distribution Network Comprehensive Cost /CNY10,000 | Installed Capacity of PV/MW | Total PV Generation/MWh |
---|---|---|---|---|
Yes | 1 | 618.24 | 0 | 0 |
2 | 1943.47 | 9.85 | 7019.54 | |
3 | 867.53 | 0 | 0 | |
4 | 975.03 | 11.82 | 9502.61 | |
No | 1 | 624.25 | 0 | 0 |
2 | 2165.97 | 9.06 | 6661.62 | |
3 | 906.87 | 0 | 0 | |
4 | 1193.95 | 11.397 | 8716.16 |
System | Scheme | Installed Bus | Installed Capacity/MW | Total Generation/MWh |
---|---|---|---|---|
54-bus system | 2 | 22, 26, 43 | 17.37 | 14,103.26 |
4 | 3, 25, 22, 27, 43 | 21.73 | 17,975.25 |
System | Scheme | Installed Bus | Total Installed Apparent Power/kVA | Total Installed Capacity/kWh |
---|---|---|---|---|
54-bus system | 3 | 8, 25, 37 | 2000 | 2600 |
4 | 8, 19, 32, 34 | 3200 | 4200 |
Scheme 1 | Scheme 2 | Scheme 3 | Scheme 4 | |
---|---|---|---|---|
ESS investment cost/CNY10,000 | 0 | 0 | 354.62 | 478.16 |
Curtailment penalty cost/CNY10,000 | 0 | 2088.36 | 0 | 102.35 |
Grid expansion cost/CNY10,000 | 1375.24 | 1366.61 | 1469.27 | 1284.51 |
Distribution network comprehensive cost/CNY10,000 | 1375.24 | 3454.97 | 1823.89 | 1865.02 |
EENS | 0 | 0 | 0 | 0 |
Solving time/s | 769.20 | 12 146.62 | 1289.46 | 1753.08 |
Considering the Source Load Temporal–Spatial Correlation Scenarios | Scheme | Distribution Network Comprehensive Cost /CNY10,000 | Installed Capacity of PV/MW | Total PV Generation/MWh |
---|---|---|---|---|
Yes | 1 | 1375.24 | 0 | 0 |
2 | 3454.97 | 17.37 | 14,103.26 | |
3 | 1823.89 | 0 | 0 | |
4 | 1865.02 | 21.73 | 17,975.25 | |
No | 1 | 1441.24 | 0 | 0 |
2 | 3506.60 | 16.24 | 12,462.55 | |
3 | 1923.49 | 0 | 0 | |
4 | 1983.69 | 20.62 | 16,953.81 |
Indicator | Original Scenario | +10% Error Scenario | −10% Error Scenario | |
---|---|---|---|---|
PV | Installed bus | 10, 12, 16, 19 | 10, 12, 16, 19 | 10, 12, 16, 19 |
Installed capacity/MW | 11.82 | 12.15 | 11.60 | |
Total generation/MWh | 9502.61 | 10,570.3 | 8510.2 | |
ESS | Installed bus | 2, 11, 17 | 2, 11, 17 | 2, 11, 17 |
Total installed apparent power/kVA | 1700 | 1780 | 1620 | |
Total installed capacity/kWh | 2200 | 2350 | 2050 | |
Cost comparison | ESS investment cost/CNY10,000 | 343.13 | 365.8 | 320.5 |
Curtailment penalty cost/CNY10,000 | 42.64 | 65.3 | 28.5 | |
Grid expansion cost/CNY10,000 | 589.26 | 598.5 | 580.1 | |
Distribution network comprehensive cost/CNY10,000 | 975.03 | 1029.60 | 929.10 |
Method | Scenario Reduction Computation Time/s | Comprehensive Cost of 25-Bus System/CNY10,000 | Comprehensive Cost of 54-Bus System/CNY10,000 |
---|---|---|---|
K-means | 6.5 | 975.03 | 1865.02 |
SBR | 362.3 | 942.65 | 1808.70 |
Variation in ESS Investment Cost | Installed Capacity of PV/MW | Total Installed Capacity of ESS/kWh | Curtailment Penalty Cost/CNY10,000 | Grid Expansion Cost/CNY10,000 | Distribution Network Comprehensive Cost/CNY10,000 |
---|---|---|---|---|---|
0.5 | 12.85 | 2850 | 20.15 | 575.60 | 791.57 |
0.8 | 12.05 | 2300 | 38.10 | 586.50 | 919.90 |
1.0 | 11.82 | 2200 | 42.64 | 589.26 | 975.03 |
1.2 | 11.75 | 2100 | 48.50 | 591.80 | 1039.00 |
1.5 | 11.25 | 1600 | 75.80 | 601.50 | 1102.95 |
Variation in PV Curtailment Penalty | Installed Capacity of PV/MW | Total Installed Capacity of ESS/kWh | Curtailment Penalty Cost/CNY10,000 | Grid Expansion Cost/CNY10,000 | Distribution Network Comprehensive Cost/CNY10,000 |
---|---|---|---|---|---|
0.5 | 12.50 | 2050 | 25.30 | 580.50 | 930.90 |
0.8 | 11.90 | 2180 | 39.10 | 587.80 | 967.10 |
1.0 | 11.82 | 2200 | 42.64 | 589.26 | 975.03 |
1.2 | 11.75 | 2280 | 48.15 | 592.60 | 996.65 |
1.5 | 11.30 | 2580 | 50.95 | 598.20 | 1047.95 |
Variation in Line Construction Cost | Installed Capacity of PV/MW | Total Installed Capacity of ESS/kWh | Curtailment Penalty Cost/CNY10,000 | Grid Expansion Cost/CNY10,000 | Distribution Network Comprehensive Cost/CNY10,000 |
---|---|---|---|---|---|
0.5 | 12.65 | 1950 | 30.50 | 330.15 | 670.85 |
0.8 | 11.90 | 2150 | 40.70 | 505.60 | 884.10 |
1.0 | 11.82 | 2200 | 42.64 | 589.26 | 975.03 |
1.2 | 11.78 | 2250 | 43.50 | 685.30 | 1079.60 |
1.5 | 11.50 | 2450 | 48.10 | 738.60 | 1168.20 |
Comparison Dimension | Proposed Method in This Paper | General Characteristics of Existing Research Methods (Based on Literature Review) |
---|---|---|
Scope of planning object coordination | Source–network–storage coordinated planning: Unified optimization of PV siting and sizing, ESS siting and sizing, and distribution network expansion, pursuing system-level global optimum. | Focuses on optimizing single types of distributed resources (e.g., DG or ESS) or achieves only source-storage coordination, with insufficient consideration of the expansion and interactive effects of the distribution network, making system-level global optimization difficult. |
Handling of source load temporal–spatial correlation | Explicitly models and accurately captures the complex, non-linear temporal–spatial correlation between PV output and load demand via Copula theory, significantly enhancing scenario realism and planning accuracy. | Ignores complex source load correlations or adopts simplified assumptions of independence or linear correlation, failing to accurately reflect complex interactions in real systems and leading to insufficiently refined uncertainty descriptions. |
Quality of scenario generation and reduction | Generates massive annual random scenarios via Monte Carlo sampling, then efficiently reduces them using K-means clustering to obtain typical daily scenarios that reflect both annual diversity and retain key temporal characteristics. | Scenario generation methods may be simplistic (e.g., typical day method) or, while using random sampling, may not fully account for variations across different periods (e.g., inter-day), resulting in insufficient representativeness and diversity of scenarios. |
Planning objective and overall benefits | Aims to enhance efficient PV accommodation and the overall economics of distribution network planning, striving to achieve dual improvements in the PV hosting capacity and economic benefits through comprehensive coordination and refined modeling. | The objective may focus on local optimization (e.g., specific equipment economics or performance indicators), or due to a lack of comprehensive coordination and refined uncertainty/correlation handling, PV hosting potential may not be fully exploited, and the overall system economics and robustness to uncertainty need improvement. |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2025 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
Wang, J.; Chang, C.; Le, J.; Liao, X.; Wang, W. Sustainable Distribution Network Planning for Enhancing PV Accommodation: A Source–Network–Storage Coordinated Stochastic Approach. Sustainability 2025, 17, 5324. https://doi.org/10.3390/su17125324
Wang J, Chang C, Le J, Liao X, Wang W. Sustainable Distribution Network Planning for Enhancing PV Accommodation: A Source–Network–Storage Coordinated Stochastic Approach. Sustainability. 2025; 17(12):5324. https://doi.org/10.3390/su17125324
Chicago/Turabian StyleWang, Jing, Chenzhang Chang, Jian Le, Xiaobing Liao, and Weihao Wang. 2025. "Sustainable Distribution Network Planning for Enhancing PV Accommodation: A Source–Network–Storage Coordinated Stochastic Approach" Sustainability 17, no. 12: 5324. https://doi.org/10.3390/su17125324
APA StyleWang, J., Chang, C., Le, J., Liao, X., & Wang, W. (2025). Sustainable Distribution Network Planning for Enhancing PV Accommodation: A Source–Network–Storage Coordinated Stochastic Approach. Sustainability, 17(12), 5324. https://doi.org/10.3390/su17125324