Next Article in Journal
Optimisation of the Production Process of Ironing Refractory Products Using the OEE Indicator as Part of Innovative Solutions for Sustainable Production
Previous Article in Journal
A Greener Paradigm Shift: The Moderating Role of Board Independence in Sustainability Reporting
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

A Hybrid Approach Combining Scenario Deduction and Type-2 Fuzzy Set-Based Bayesian Network for Failure Risk Assessment in Solar Tower Power Plants

1
School of Chemical Engineering, Northwest University, Xi’an 710069, China
2
China Special Equipment Inspection and Research Institute, Beijing 100029, China
*
Author to whom correspondence should be addressed.
Sustainability 2025, 17(11), 4774; https://doi.org/10.3390/su17114774
Submission received: 14 April 2025 / Revised: 19 May 2025 / Accepted: 20 May 2025 / Published: 22 May 2025

Abstract

Under extreme operating conditions such as high temperatures, strong corrosion, and cyclic thermal shocks, key equipment in solar tower power plants (STPPs) is prone to severe accidents and results in significant losses. To systematically quantify potential failure risks and address the methodological gaps in existing research, this study proposes a risk assessment framework combining a novel scenario propagation model covering triggering factors, precursor events, accident scenarios, and response measures with an interval type-2 fuzzy set (IT2FS) Bayesian network. This framework establishes equipment failure evolution pathways and consequence evaluation criteria. To address data scarcity, the methodology integrates actual case data and expert elicitation to obtain assessment parameters. Specifically, an IT2FS-based similarity aggregation method quantifies expert opinions for prior probability estimation. Additionally, to reduce computational complexity and enhance reliability in conditional probability acquisition, the IT2FS-integrated best–worst method evaluates the relative importance of parent nodes, combined with a leakage-weighted summation algorithm to generate conditional probability tables. The model was applied to a western Chinese STPP and the results show the probabilities of receiver blockage, pipeline blockage, tank leakage, and heat exchanger blockage are 0.061, 0.059, 0.04, and 0.08, respectively. Under normal operating conditions, the occurrence rates of level II accident consequences for all four equipment types remain below 6%, with response measures demonstrating significant suppression effects on accidents. The research results provide critical decision-making support for risk management and mitigation strategies in STPPs.

1. Introduction

Concentrated solar power (CSP) technology, with its dual capabilities in electricity generation and thermal energy storage, has garnered significant attention in the global energy transition. By early 2024, the cumulative installed capacity of CSP reached 7550 MW [1], highlighting its commercialization potential. However, the prolonged operation of key equipment in solar tower power plants (STPPs) under extreme operating conditions such as high temperatures, strong corrosion, and cyclic thermal shocks has led to frequent catastrophic accidents globally (Table 1). According to the National Renewable Energy Laboratory, over 200 equipment failure incidents have been documented in STPPs [2], resulting in substantial economic losses. Such incidents undermine system reliability and efficiency, posing a critical barrier to STPP large-scale deployment. Therefore, establishing a systematic risk assessment framework to precisely identify failure mechanisms and design targeted mitigation strategies is an urgent priority.
Current risk research in STPP predominantly focuses on elucidating localized failure mechanisms of equipment [7,8,9], yet lacks a holistic framework to model risk propagation chains, thereby obscuring the causal relationships between equipment failures and accident consequences. Traditional risk assessment methods—such as fault tree analysis [10], bow-tie analysis [11], and risk matrix [12]—widely adopted in mature industries like petrochemicals and nuclear power excel in identifying and quantifying failure factors. However, these methods exhibit significant limitations when applied to complex, tightly coupled systems like STPPs. In contrast, the scenario-response model, which presets risk evolution pathways (triggering factor—intermediate events—accident scenario), demonstrates unique potential in extrapolating risk propagation dynamics. For instance, in environmental emergency management, Wang et al. [13] reconstructed accident scenarios using four core elements: disaster-inducing factor, disaster-bearing factor, disaster situation, and emergency. Yuan et al. [14] developed a “pressure–state–response” model for oil and gas fire prediction, integrating historical accident databases with expert knowledge. Similarly, She et al. [15] modeled construction accidents through a “human behavior–hazard formative environments–emergency management–scenario state” framework. These studies achieved notable success in risk prediction.
While scenario-response approaches have proven effective across domains, existing frameworks suffer from a critical flaw: the implicit treatment of precursor events in risk propagation. In most industrial systems, accidents are preceded by observable precursors (e.g., abnormal equipment vibrations, false control signals, or increased operational errors), which manifest as intermediate markers between triggering factors and accident scenario. Conventional scenario deduction methods oversimplify risk propagation into single-step mappings (triggering factors–accident scenario), resulting in fragmented causal chains and reduced interpretability. To address this, the study extracts a four-stage scenario development framework—triggering factors, precursor events, accident scenarios, and response measures—from STPP accident case studies, enabling granular reconstruction of risk pathways and enhancing model transparency.
To enable quantitative risk assessment of potential failures, the transformation of scenario-based evolution models into Bayesian networks (BNs) presents significant parameter estimation challenges under data-scarce conditions [16]. However, in complex systems such as STPPs—characterized by limited accident data and highly coupled risk elements—two critical technical bottlenecks persist:
1. Prior probability acquisition: Reliance on expert elicitation for basic event probabilities introduces individual cognitive biases and group decision inconsistencies.
2. Conditional probability table (CPT) complexity: Exponential growth in parameter estimation demands for large-scale systems.
To overcome prior probability limitations, fuzzy set-BN hybrid methods have gained traction. Tang et al. [17] demonstrated the efficacy of triangular fuzzy number-BN models in water quality assessment. However, traditional fuzzy sets struggle to reconcile heterogeneous expert opinions in multi-stakeholder evaluations. Interval type-2 fuzzy sets (IT2FSs), with superior uncertainty-handling capabilities, offer a robust solution by delineating fuzzy boundaries and accommodating group cognitive diversity. Pioneering work by Yaşlı et al. [18] validated IT2FS-BN models in underground mining risk assessment, while Tang et al. [19] successfully quantified medical waste transport risks using this approach.
When constructing BNs, obtaining the CPTs is another challenge. If expert elicitation is used, it typically involves comparing the comparative significance of parent nodes to child nodes. Typical methods involve multi-criteria decision-making (MCDM) techniques, particularly the analytic hierarchy process (AHP) and the analytic network process (ANP), which employ pairwise comparison strategies. For instance, in risk assessment studies of oil gathering pipelines, Liu et al. [20] utilized AHP pairwise comparisons to derive the relative importance weights of risk factors, while in large-scale construction project management. Erol et al. [21] applied ANP to quantify the relative risk weights of project risk sources. Both methodologies demonstrated promising outcomes in addressing domain-specific challenges. However, when the number of parent nodes is large, such pairwise comparison methods can lead to the following issues: (1) It is prone to inconsistency in group decision-making, leading to significant information loss during the decision process; and (2) the computational burden becomes excessively high. To address these issues, Rezaei [22] introduced the best–worst method (BWM), which establishes a novel pairwise comparison framework. In the BWM, experts are required to conduct pairwise comparisons solely between the best (most ideal, most significant) criterion and all remaining criteria, and between all other criteria and the worst (least ideal, least significant) criterion. This maintains consistency in the judgments of experts at the consistency level [23]. From a computational perspective, if there are n nodes, AHP requires (n2-1)/2 comparisons, while BWM only requires 2n-3 comparisons. when the number of nodes is large, the BWM substantially decreases the required number of comparisons. While the BWM has demonstrated proven efficacy in classical decision-making contexts such as supply chain optimization [24] and sustainability risk quantification [25], its innovative adaptation to resolve computational bottlenecks in BN parameterization—specifically in deriving expert-calibrated relative importance weights for CPT construction.
Building upon prior research foundations, pioneered a hybrid methodology integrating scenario deduction with BN to assess potential failure risks in key STPP equipment. In order to effectively capture the fault evolution process of key equipment, the T (triggering factors)—P (precursors events)—S (accident scenarios)—R (response measures) model has been proposed, allowing the fault progression to be tracked and the accuracy of the reasoning process to be enhanced. Furthermore, both objective failure data and expert opinions have been combined, with IT2FS being employed to incorporate expert insights, thereby addressing the issue of insufficient sample data. To reduce the frequency of expert judgments and improve the consistency of the evaluations, an IT2FS-BWM has been introduced to derive the parameters for the Bayesian network analysis, further improving the precision of the risk assessment.

2. Preliminaries

This section provides a comprehensive introduction to the basic definitions and ideas of BN and IT2FSs, which serve as the theoretical foundation for this study and are indispensable in subsequent analysis and calculations.

2.1. Bayesian Network

BN was first introduced [26] quickly gained widespread attention. A notable advantage of BNs lies in its ability to simultaneously conduct forward causation and backward reason. The former is used for estimating the probabilities of child nodes, while the latter is employed to obtain probabilities, thereby deriving the probabilities of the parent nodes given the evidence. The subsequent Bayesian formula is crucial for BN analysis.
P ( Y ) = i = 1 n P X i P Y X i
P X i Y = P ( X i ) P Y X i P ( Y )
where P(Xi) denotes the prior probability of event X, P(Y) denotes the marginal probability of event Y, P(Y|Xi) indicates the conditional probability of Y assuming that Xi has occurred, P(Xi|Y) and donates the posterior probability of X assuming that Y has occurred.

2.2. Interval Type-2 Fuzzy Sets

In 1965, Zadeh [27] pioneered the concept of fuzzy sets to articulate the vagueness and uncertainty in experts’ interpretation of linguistic terms to describe semantic concepts. This can be quantified through a membership function μ, which ranges from 0 to 1, to measure the uncertainty in experts’ subjective assessments of the semantic concept x. However, to minimize subjective bias, it is common to integrate the opinions of multiple experts. For this purpose, Zadeh [28] further proposed type-2 fuzzy set (T2FS) in 1975 to handle this compound uncertainty. In the T2FS framework, an element x, as part of the universe of discourse X, not only includes its primary membership u but also introduces a secondary membership z, with z ranging from 0 to 1. To simplify complex calculations in practical operations, researchers typically set the secondary membership z of T2FSs to a constant 1, thereby simplifying the complex model parameters to expressions in two-dimensional space.
Definition 1. 
The T2FS  A ˜  is characterized by the type-2 membership function  μ A ˜ x , u , i.e.,
A ˜ = x , u , μ x , u x X , u Q x [ 0 , 1 ]
where  μ A ˜ x , u 0 , 1 , x denotes primary variable, and u denotes the secondary variable of  A ˜  .  A ˜  is also equivalent to
A ˜ = x X u Q x μ A ˜ x , u x , u Q x [ 0 , 1 ]
where  0 Q x 1 ,  x X  and  u Q x μ A ˜ x , u x , u  are the primary and secondary membership functions of x, respectively, and   denotes the union over all admissible x and u.
Definition 2. 
Assuming  μ A ˜ x , u  = 1,  A ˜  is called an IT2FS, and can be denoted as
A ˜ = x X u Q x 1 u x , Q x [ 0 , 1 ]
where  u Q x 1 u x  denotes the secondary membership function of x.
Definition 3. 
If  A ˜  is an interval type-2 fuzzy number (IT2FN), it can be represented as.
A ˜ = A ˜ U , A ˜ L = a 1 U , a 2 U , a 3 U , a 4 U ; H 1 A ˜ U , H 2 A ˜ U , a 1 L , a 2 L , a 3 L , a 4 L ; H 1 A ˜ L , H 2 A ˜ L
where  A ˜ U ,  A ˜ L  represents the upper membership function (UMF) and the lower membership function (LMF) respectively, and the area between them constitutes the footprint of uncertainty (FOU) [29]. Figure 1 illustrates an exemplary of IT2FN.
Definition 4. 
FOU denotes the union of all primary memberships, so
F O U A ˜ = x X Q x
The UMF and LMF are two types of type-1 membership functions. The UMF and LMF represent  A ˜ U ,  A ˜ L  are related to the upper bound and lower bound of  F O U A ˜ , respectively,  x X . i.e., [30].
A ˜ U = F O U A ˜ ¯ , x X
A ˜ L = F O U A ˜ ¯ , x X
As shown in Equations (10) and (11),  μ ¯ A ˜ ( x )  and  μ ¯ A ˜ ( x )  [31] are used to represent the sums of UMF and LMF, respectively, ensuring that the definitions of UMF and LMF depend explicitly on the x.
μ ¯ A ˜ ( x ) = s u p u u [ 0 , 1 ] , μ A ˜ ( x , u ) > 0
μ _ A ˜ ( x ) = i n f u u [ 0 , 1 ] , μ A ˜ ( x , u ) > 0
Definition 5. 
Mendel [29] formulated a formulaic definition for the primary membership Qx, which frequently appears in the definition of T2FSs, with the result as follows:
Q x = ( x , u ) : u [ μ _ A ˜ ( x ) , μ ¯ A ˜ ( x ) ]
Definition 6. 
If there are two IT2FNs of  A ˜ 1   and  A ˜ 2 , let k be a positive real number:
A ˜ 1 = A ˜ 1 U , A ˜ 1 L = a 11 U , a 12 U , a 13 U , a 14 U ; H 1 A ˜ 1 U , H 2 A ˜ 1 U , a 11 L , a 12 L , a 13 L , a 14 L ; H 1 A ˜ 1 L , H 2 A ˜ 1 L
A ˜ 2 = A ˜ 2 U , A ˜ 2 L = a 21 U , a 22 U , a 23 U , a 24 U ; H 1 A ˜ 2 U , H 2 A ˜ 2 U , a 21 L , a 22 L , a 23 L , a 24 L ; H 1 A ˜ 2 L , H 2 A ˜ 2 L
The arithmetic operations of IT2FSs are as follows [32]:
(1)
Addition:
A ˜ 1 + A ˜ 2 = a 11 U + a 21 U , a 12 U + a 22 U , a 13 U + a 23 U , a 14 U + a 24 U ; min H 1 A ˜ 1 U , H 1 A ˜ 2 U , min H 2 A ˜ 1 U , H 2 A ˜ 2 U , a 11 L + a 21 L , a 12 L + a 22 L , a 13 L + a 23 L , a 14 L + a 24 L ; min H 1 A ˜ 1 L , H 1 A ˜ 2 L , min H 2 A ˜ 1 L , H 2 A ˜ 2 L
(2)
Subtraction:
A ˜ 1 A ˜ 2 = a 11 U a 24 U , a 12 U a 23 U , a 13 U a 22 U , a 14 U a 21 U ; min H 1 A ˜ 1 U , H 1 A ˜ 2 U , min H 2 A ˜ 1 U , H 2 A ˜ 2 U , a 11 L a 24 L , a 12 L a 23 L , a 13 L a 22 L , a 14 L a 21 L ; min H 1 A ˜ 1 L , H 1 A ˜ 2 L , min H 2 A ˜ 1 L , H 2 A ˜ 2 L
(3)
Multiplication:
A ˜ 1 × A ˜ 2 = a 11 U × a 21 U , a 12 U × a 22 U , a 13 U × a 23 U , a 14 U × a 24 U ; min H 1 A ˜ 1 U , H 1 A ˜ 2 U , min H 2 A ˜ 1 U , H 2 A ˜ 2 U , a 11 L × a 21 L , a 12 L × a 22 L , a 13 L × a 23 L , a 14 L × a 24 L ; min H 1 A ˜ 1 L , H 1 A ˜ 2 L , min H 2 A ˜ 1 L , H 2 A ˜ 2 L
(4)
Multiplication by crisp number:
k A ˜ 1 = k a 11 U , k a 12 U , k a 13 U , k a 14 U ; H 1 A ˜ 1 U , H 2 A ˜ 1 U , k a 11 L , k a 12 L , k a 13 L , k a 14 L ; H 1 A ˜ 1 L , H 2 A ˜ 1 L

3. Research Framework

The proposed framework of this study for assessing potential accident risk and consequences of equipment in STPPs is depicted in Figure 2 and includes three primary parts:
(1) Scenario deduction: The key elements closely associated with equipment incidents are identified and extracted from past accident cases, including triggering factors (T), precursor events (P), accident scenarios (S), and response measures (R). Based on these elements and potential accident pathways, a scenario deduction model is constructed to describe the accident evolution paths and consequences of the equipment in STPPs, forming the basic structure of the BN.
(2) Probability acquisition: To conduct probabilistic inference and quantitative study of equipment failure using the BN. The prior probabilities of basic nodes and the CPTs of child nodes must be determined. In this framework, the prior and conditional probabilities are obtained using the IT2FS-SAM and the IT2FS-BWM with the leaky-WSA, respectively.
(3) Risk assessment: The quantitative risk assessment model is constructed through the integration of the BN model with a consequence evaluation system. It is used to identify risk factors, estimate accident probabilities, analyze response measures, and comprehensively assess accident consequences.

4. Scenario Deduction

4.1. Analysis of Exemplary Accident Cases in CSPs

Combining the insights from the literature [2] and corporate operational experience [33], Table 1 presents several major accidents that have occurred in STPPs globally.
Based on the operational failure patterns of STPPs, we identify the primary threats to the normal operation of equipment in STPPs as follows [34]:
Direct equipment failures: This includes issues such as the cracking of receiver tubes, freezing and cracking of molten salt pipes, cracking at weld joints of salt tanks, and blockages or cracking of heat exchangers.
Indirect equipment failures: These involve failures such as damage to thermal insulation materials and valve malfunctions leading to leakage. Figure 3 illustrates common failure modes, such as cracks in the absorber tubes, insulation layer damage, and valve leakage.
In STPPs, equipment is highly integrated, and minor faults potentially escalate into major disasters. Different responses can lead to different failure pathways, ultimately resulting in varied accident consequences.

4.2. Identification of Critical Scenario States

To comprehensively describe the potential evolution paths of equipment accidents, a TPSR model for scenario deduction is proposed, as illustrated in Figure 4.
In this model, triggering factors (T) are the risk elements that can lead to accidents, including safety hazards associated with design, installation, operation, maintenance, medium, and environment [36]. These factors have the potential to trigger precursor events. Precursor events (P) are events triggered by triggering factors. when they occur, they are likely to lead to the occurrence of accident scenarios. Accident scenarios (S) represent the actual states in which accidents occur. Response measures (R) are protective strategies established within the system, designed to prevent and control accident. The TPSR model provides a structured approach to understanding and managing the potential evolution paths of equipment accidents in STPPs.

4.3. Analysis of Scenario Evolution Path

Based on accident case of Table 1 and scenario state classification, a TPSR based scenario deduction model can be constructed to describe the evolution paths of equipment failures. Figure 5 shows an exemplary evolution path of equipment accidents (as a part of a scenario deduction model).
As depicted in Figure 5, triggering factor I1 causes a precursor event P1. P1 subsequently leads to the accident scenario S1. If response measure R1 is timely and effective, the accident is mitigated and ended (End). However, if R1 fail to respond in time, S1 continues to occur. In such cases, S1 may interact with other triggering factors Ii, potentially causing additional precursor event Pi. Pi then directly causes accident Si. If response measure Ri effectively mitigate Si, the accident will terminate (End). Otherwise, the accident may escalate along a worsening trajectory, potentially resulting in system collapse Sn, and ultimately ending.

4.4. Determination of Bayesian Network from Scenario Deduction Model

To achieve an accurate understanding and analysis of equipment failures, triggering factors and response measures, the scenario deduction model needs to be further transformed into a BN model for quantitative assessment, Figure 6 shows the transformation process.

5. Probability Acquisition for the Nodes of BN

To implement probabilistic inference using BN, it is essential to acquire the prior probabilities of the basic nodes in the network and the CPTs of the child nodes. Here, the data of the basic nodes are obtained from historical data and expert elicitation. The CPTs are estimated by domain experts based on their expertise. Figure 7 shows the process for acquiring node probabilities in the BN. The details are described in the subsequent sections.

5.1. Forming an Expert Group

In order to conduct a quantitative study of specific failure scenarios in STPPs, expert opinion is employed to derive node probabilities for those nodes that are challenging to quantify. To reduce bias and discrepancies in individual expertise, a set of scoring criteria is utilized to evaluate the weight of each expert. These criteria take into account the expert’s job title, working years, educational level, age, and familiarity with the STPPs. Detailed evaluation criteria are presented in Table 2.

5.2. Obtaining Prior Probabilities of Basic Nodes in BN

This subsection describes the methods used to obtain prior probabilities of basic nodes in BN. Two ways are used for this study: objective data and expert elicitation.

5.2.1. Objective Data

Objective data comes from two main sources: (1) for some nodes involving weather factors, their probability data can be computed through local weather records; (2) database built from lots of factory experiences, including details about failures.

5.2.2. Expert Opinions

The questionnaire approach is used to capture individual expert’s opinions on the likelihoods of the occurrences of basic nodes in the BN. The seven-level linguistic term set is utilized to aid in the expert judgment [38].
(1)
Aggregation of expert opinions
To address individual biases and enhance the integration of expert opinions, the SAM is employed to confirm both varied and unbiased of expert opinions, thereby improving the reliability of aggregation results. Additionally, to capture inherent uncertainty and vagueness in expert opinions, IT2FS are used for a more accurate representation of these uncertainties. Consequently, the paper adopts IT2FS to assess expert opinions and applies the improved SAM, called as IT2FS-SAM, to mitigate potential biases associated with personal differences. The process of the aggregation is as follows:
Step 1: If the opinions of the two experts are A ˜ i and A ˜ j , respectively, their agreement degree (AD), the A D A ˜ i , A ˜ j can be calculated by the following:
A D A ˜ i , A ˜ j = S A i ¯ A j ¯ + S A i ¯ A j ¯ S A i ¯ A j ¯ + S A i ¯ A j ¯ = S A i ¯ A j ¯ + S A i ¯ A j ¯ S A i ¯ + S A j ¯ S A i ¯ A j ¯ + S A i ¯ + S A j ¯ S A i ¯ A j ¯
The similarity of two IT2FNs is calculated using area similarity measure functions, as follows:
S A ¯ = x μ ¯ A ˜ x d x
S A _ = x μ _ A ˜ x d x
where S A ¯ and S A ¯ represent the areas of the closed regions formed by the UMF and LMF with respect to the X-axis, respectively, and S A i ¯ A j ¯ and S A i ¯ A j ¯ represent the areas of the intersections of the two UMFs or the two LMFs.
If there are n experts, a similarity matrix (M) can be obtained using a similarity measure function:
M = 1 m 12 m 1 j m 1 n m i 1 m i 2 m i j m i n m n 1 m n 2 m n j 1
where m i j = m R ˜ i , R ˜ j , if ij and m i j = 1 , if i = j.
Step 2: Obtaining the weighted consensus degree (WAD) by incorporating expert weights, making it more reasonable.
W A D E i = j = 1 j i n w E j m A ˜ i , A ˜ j j = 1 j i n w E j
Step 3: Obtaining the relative agreement degree (RAD(Ei)) of expert Ei.
R A D E i = W A D E i i = 1 n W A D E i
Step 4: Calculating the consensus degree coefficient (CDC(Ei)).
C D C E i = β w E i + ( 1 β ) R A D E i
where β (0 ≤ β ≤ 1) denotes the impact of the AD of experts compared to the RAD. Generally, β is set to 0.5.
Step 5: Calculating the aggregated result A ˜ of the IT2FNs of the experts’ opinions
A ˜ = i = 1 n C D C E i ( ) A ˜ i
(2)
Defuzzify the aggregated result
Once the aggregated result is obtained, it is crucial to determine the crisp value D e f A ˜ through the defuzzification process. The defuzzification formula suitable to IT2FNs is as follows [39].
D e f A ˜ = 1 2 a 1 U + 1 + H 1 A ˜ U × a 2 U + 1 + H 2 A ˜ U × a 3 U + a 4 U 4 + H 1 A ˜ U + H 2 A ˜ U + a 1 L + 1 + H 1 A ˜ L × a 2 L + 1 + H 2 A ˜ L × a 3 L + a 4 L 4 + H 1 A ˜ L + H 2 A ˜ L
To conduct advanced quantitative analysis of the BN, this study utilizes Equations (26) and (27) to convert the crisp value into failure probability (FP) [40]. These refined formulas, specifically tailored for incidents in the petrochemical industry, adhere to a seven-level risk probability classification standard.
F P = 1 10 Z , f o r   Z 0 0 , f o r   Z = 0
and
Z = 0.72 ln D e f A ˜ + 2.839 , 0 D e f A ˜ < 0.2 1 3 × ln D e f A ˜ 14 , 0.2 D e f A ˜ 0.8 1 D e f A ˜ | D e f A ˜ × 3.705 , 0.8 < D e f A ˜ 1

5.3. Obtaining the CPTs of Child Nodes in BN

To facilitate the acquisition of CPTs, the following procedures are implemented: First, the IT2FS-BWM is introduced to derive node weights, which are subsequently normalized by allocating weights to neglected nodes. Second, expert judgments are used to establish node probability distributions. Finally, the CPTs are derived utilizing the leaky-WSA.

5.3.1. Acquisition of Expert Opinions

In order to address the uncertainty and bias inherent in expert opinions, IT2FNs are utilized to express the comparative significance of every parent node in relation to its associated child nodes. A comprehensive description of the IT2FNs scale method for linguistic variables is presented in the literature [41]. The detailed classification criteria are illustrated in Table 3.

5.3.2. Obtaining the Relative Weights of Parent Nodes Using IT2FS-BWM

The BWM is designed to handle multiple criteria. It seeks to ascertain the significance weights of these criteria and rank alternatives through pairwise comparisons. The novel application of IT2FS-BWM for deriving weights of parent nodes obviously reduces the number of required data comparisons and enhances the consistency of these comparisons. The process is as follows:
Step 1: Identify a set of decision criteria, n. Criteria (CR1, CR2, …, CRn) are used for calculating the importance weights.
Step 2: Experts select the best and worst criteria from the set. The criterion with the strongest influence on the target factor is designated as the best criterion, while the criterion with the weakest influence is identified as the worst criterion.
Step 3: The best criterion is compared with the other criteria to form the judgment matrix AB, similarly, comparisons of the other criteria relative to the worst criteria yield the judgment matrix AW. In these matrices,  a B j  indicates that the best criterion B is preferable to criterion j a j W  indicates that criterion j is preferable to the worst criterion W. The scoring scale ranges from 1 to 9, where 1 denotes equal importance between two criteria and 9 represents the highest level of preference between the criteria.
A B n = ( a B 1 , a B 2 , , a B n ) T
A n W = ( a 1 W , a 2 W , , a n W ) T
where a B B = 1 and a W W = 1 .
Step 4: Optimal weights ( ω 1 , ω 2 , , ω n ) are derived in this step using the region center defuzzification method. Additionally, a constrained optimization model, as detailed by [42], was developed. Consistency ratios were also assessed.
min max ω B E | ω j E E B E j , ω j E | ω E W E j E W
s . t . i = 1 n C O A ω j E = 1 ω j E 1 U ω j E 1 L , ω j E 4 L ω j E 4 U , ω j E 1 L ω j E 2 L ω j E 3 L ω j E 4 L , ω j E 1 U ω j E 2 U ω j E 3 U ω j E 4 U ω j E 1 U 0 , j = 1 , 2 , , N
where
ω B E = ω B E U , ω B E L = ω B E 1 U , ω B E 2 U , ω B E 3 U , ω B E 4 U ; H 1 ω B E U , H 2 ω B E U , ω B E 1 L , ω B E 2 L , ω B E 3 L , ω B E 4 L ; H 1 ω B E L , H 2 ω B E L
ω E W = ω E W U , ω E W L = ω W E 1 U , ω E W 2 U , ω E W 3 U , ω E W 4 U ; H 1 ω W E U , H 2 ω W E U , ω E W 1 L , ω E W 2 L , ω E W 3 L , ω E W 4 L ; H 1 ω E W L , H 2 ω E W L
ω j E = ω j E U , ω j E L = ω j E 1 U , ω j E 2 U , ω j E 3 U , ω j E 4 U ; H 1 ω j E U , H 2 ω j E U , ω j E 1 L , ω j E 2 L , ω j E 3 L , ω j E 4 L ; H 1 ω j E L , H 2 ω j E L
To ensure that only a single optimal solution is derived from Equation (30), by minimizing the maximum absolute deviation between ω B E ω j E B E j and ω j E ω EW E j E W . To solve the model, let the maximum absolute deviation be δ * , δ * , δ , * δ * , δ * , δ * , δ * , δ * ; Subsequently, the equation can be transformed into the following programming model [43].
min δ * s . t . ω B E 1 U ω j 1 U ω B E j , 1 U δ * , ω B E 2 U ω j 2 U ω B E j , 2 U δ * , ω B E 3 U ω j 3 U ω B E j , 3 U δ * , ω B E 4 U ω j 4 U ω B E j , 4 U δ * , ω B E 1 L ω j 1 L ω B E j , 1 L δ * , ω B E 2 L ω j 2 L ω B E j , 2 L δ * , ω B E 3 L ω j 3 L ω B E j , 3 L δ * , ω B E 4 L ω j 4 L ω B E j , 4 L δ * , ω j 1 U ω W E 1 U ω j W E , 1 U δ * , ω j 2 U ω W E 2 U ω j W E , 2 U δ * , ω j 3 U ω W E 3 U ω j W E , 3 U δ * , ω j 4 U ω W E 4 U ω j W E , 4 U δ * ω j 1 L ω W E 1 L ω j W E , 1 L δ * , ω j 2 L ω W E 2 L ω j W E , 2 L δ * , ω j 3 L ω W E 3 L ω j W E , 3 L δ * , ω j 4 L ω W E 4 L ω j W E , 4 L δ * j = 1 N C O A ω j E = 1 ω j E 1 U ω j E 1 L , ω j E 4 L ω j E 4 U ω j E 1 L ω j E 2 L ω j E 3 L ω j E 4 L ω j E 1 U ω j E 2 U ω j E 3 U ω j E 4 U ω j E 1 U 0 , j = 1 , 2 , N

5.3.3. Acquiring CPTs Utilizing the Leaky-Weighted Sum Algorithm

Expert elicitation for deriving CPTs in BNs may occasionally overlook certain factors affecting a child node. To address this issue, Das [44] introduced the weighted sum algorithm (WSA), which can reduce the amount of needed probability distributions. Baker [45] evaluated its simplicity and usability. Farsi et al. [46] applied the WSA to STPPs and analyzed the site selection for the power plants. Liu et al. [20] cleverly incorporated the notion of “leakage” into this WSA, accounting for uncertainties and latent flaws in BN model nodes, resulting in favorable assessments.
Initially, weight of the leaky node is calculated according to the views of various experts and their associated weights.
Following, a fresh weight normalization is implemented for both parent nodes and the leaky node, as shown in Equation (32);
i = 1 n ( ω i + ω L ) = 1
where ω i denotes the weight of the i-th parent node; ω L denotes the weight of the leaky node.
Additionally, the CPT of a set of compatible parent nodes can be obtained by the leaky-WSA, the calculation details are shown in Equation (33).
P y l x 1 S 1 , x 2 S 2 , x n S n = i = 1 n ω i P y l C o m p X = x i S i + ω L P y l x L S i
where x represents the parent node; y represents the child node; the number of states of child node is j; l = 0, 1, …, Si (i = 1, 2, …, n) represents the states of the i-th parent node; and ωi signifies the comparative weight of the parent node.

6. Accident Consequence Evaluation

6.1. Consequence Evaluation Criteria

Evaluation criteria for the consequences of equipment accidents have been established. The criteria include three evaluation indicators: direct economic losses (C1), casualties (C2), and equipment damage (C3). Based on “Regulations on the Reporting, Investigation, and Handling of Production Safety Accidents” (State Council Order No. 493) (2007) of the China, accident severity is categorized into general, major, heavy, and mega accidents. The categorization criteria for C1, C2, and C3 are shown in Table 4.

6.2. Accident Consequence Evaluation Model

A consequence evaluation model has been developed by integrating the BN and the consequence evaluation criteria in Section 6.1. The model is shown in Figure 8, emphasizes the severity of consequences arising from critical scenarios, represented by directional lines, with causal relationships denoted by arrows.

7. Case Study

This section applied the proposed approach to evaluate the failure likelihoods and consequences of the equipment in a STPP situated in western China, specifically focusing on the receiver, the salt piping, the salt tanks, and the heat exchangers. Figure 9 illustrates the simplified process flow of the power plant.

7.1. Establishing the Scenario Deduction Model and Bayesian Network of the STPP

7.1.1. Scenario Deduction Model of the STPP

Based on the analysis of the failure scenario and evolutionary processes derived from relevant literature, operational experience, and expert consulting, the potential scenario evolution paths for accident risk evaluation of the equipment in the STPP was established, as shown in Figure 10. The symbols and eanings are detailed in Table 5, Table 6, Table 7 and Table 8.

7.1.2. Description of Accident Scenario Evolution Path

According to the Figure 10, it can be seen that there are two types of accident evolution paths, as shown in Figure 11.
(1) Possible accident paths and consequences for the equipment itself
(a) Receiver: The precursor event A1 due to excessively low temperature or the A2 in the molten salt pose a significant risk of AS1. If AR11 is functioning, or if the AR12 is adequate, the accident may be terminated. If AR11 or AR12 fails to effectively control the accident, AS1 will prevent the molten salt flow in the receiver tube, causing the wall temperature of the affected tube to rise sharply, leading to A3 and AS2. If AR21 and AR22 are activated, the accident is terminated. However, if AS2 occurs, there may be an A4. When the leaked high-temperature molten salt comes into contact with surrounding flammable materials, AS3 may ignite. Subsequently, AR31 are activated, extinguishing the fire and ending the accident.
(b) Salt piping: The piping is susceptible to P1 due to excessive heat loss, which can lead to PS1. If PR11 is activated normally, the accident is terminated. If PR11 fails, P2 may occur, causing PS2. If PR21 is successfully operated, the accident is terminated. If PR21 is ineffective, it can lead to P3 at valves, flanges, etc., resulting in PS3. If PR31 and PR32 are promptly initiated, the PS3 will be terminated. However, if PS3 continues, it may pose a P4. When the molten salt comes into contact with surrounding flammable materials, PS4 may break out. With the effective response of PR41 and PR42, the accident is ultimately ended.
(c) Salt tank: Trigger factors may collectively lead to T1, resulting in TS1. If TR11 and TR12 are handled properly, the accident will be terminated. If not handled properly, the following two paths may occur: (i) The high-temperature molten salt continuously infiltrates the tank foundation, causing T2 and TS2. If TR21 is effective, the accident is terminated. (ii) The leaked molten salt meets surrounding flammable materials, and T3 may develop, leading to TS3. TR31 would address TS3 and terminate the accident. Conversely, if TR31 is ineffective, there is a risk of T4, potentially leading to TS4. By implementing TR41, the accident is ended.
(d) Heat exchanger: Similar to the receiver, ES1 can occur due to E1 or E2. If ER11 and ER12 are timely and effective, the accident is terminated. If ES1 is not addressed, it can lead to E3, causing ES2. If ER2 is effective, the accident is terminated. If ES2 cannot be effectively controlled, it may cause the frictional connection between the tubes and the tube sheet to loosen, leading to E4 and ES3. If the steam comes into contact with the high-temperature molten salt, it can pose E5 or E6. If not promptly addressed, ES4 or ES5 may occur. Ultimately, under the effective response of ER41 and ER51, the accident is ended.
(2) Impact of upstream equipment on downstream equipment
AS1 may induce P2 in the downstream salt piping. If P2 is not effectively mitigated, it poses a risk of T1, leading to TS1. TS1 can result in a disruption of the salt supply, which in turn can cause E3 in the heat exchanger. E3 can directly lead to the shutdown of the power generation system. Although such an accident path is rarely observed under normal operating conditions, it is still possible and should not be overlooked.

7.1.3. Determination of the Bayesian Network from Scenario Deduction Model

To quantitatively assess the potential risks of the equipment, the established scenario deduction model was converted into the BN model based on the rules mentioned in Section 4.4.

7.2. Establishing an Expert Group

Five experts working in the field of STPP, as well as the special equipment inspection industry, were invited to obtain the parameters of the BN. Details of the experts and their corresponding weights are presented in Table 9.

7.3. Acquiring the Prior Probabilities of the Basic Nodes

Due to the limited operational and maintenance data for STPPs, the prior probabilities for some nodes in the BN were derived from environmental data and the statistical incidence of actual events during operation, including accident frequencies. For other nodes, especially those involving large transient temperature fluctuations, the prior probabilities were obtained through expert elicitation.

7.3.1. Objective Data Collection

One year of weather data from the STPP was collected to determine the probabilities of intermittent cloud cover and extreme weather. Additionally, based on the recorded incident frequencies of the equipment from the literature [2], the prior probabilities for the corresponding nodes were calculated using the following formula. The results are shown in Appendix A.
Q ( t ) = 1 e λ t
where Q(t) denotes the failure probability, λ represents the failure frequency, and t is the operational time.

7.3.2. Expert Elicitation

For the nodes lacking objective probability data, expert elicitation was used to quantify them. Here, we illustrate the probability acquisition process using large transient temperature fluctuations (AO4) as an example. Table 10 shows the linguistic terms and the corresponding IT2FNs obtained from a questionnaire administered to the five experts regarding the likelihood of the event (AO4).
Based on the information in Table 10, the IT2FS-SAM was used to calculate the probability of the AO4. First, using Equation (20) the similarity matrix (M) was obtained as.
M = 1 0.0943 0.0943 1 1 0.0943 1 1 0.0943 0.0943 0.0943 1 1 0.0943 0.0943 1 0.0943 0.0943 1 1 1 0.0943 0.0943 1 1
Then, the WAD of five experts were obtained by Equation (21):
WAD(E1) = 0.529, WAD(E2) = 0.227, WAD(E3) = 0.371, WAD(E4) = 0.596, WAD(E5) = 0.574.
Using Equation (22), the RAD were calculated as Equation (22):
RAD(E1) = 0.230, RAD(E2) = 0.099, RAD(E3) = 0.162, RAD(E4) = 0.260, RAD(E5) = 0.249.
Here, β = 0.5, the CDC were obtained by Equation (23):
CDC(E1) = 0.252, CDC(E2) = 0.186, CDC(E3) = 0.134, CDC(E4) = 0.206, CDC(E5) = 0.223.
Then, the AR was obtained with Equation (24).
AR = ((0.364, 0.564, 0.564, 0.764; 1, 1), (0.464, 0.564, 0.564, 0.664; 0.9, 0.9)).
After calculating AR, the crisp value was calculated by using Equation (25).
def (AR) = 0.564
Lastly, the FP of AO4 was calculated with Equation (26).
FP = 1.63 × 10−3
Using the above method, the prior probabilities for other basic nodes were computed, ultimately yielding the prior probabilities for entire basic nodes, as detailed in Appendix B.

7.4. Obtaining the CPTs of the Nodes

The IT2FS-BWM method was employed to obtain the CPTs for the child nodes in the BN. Here, node AO-1 in the receiver is taken as a case to explain the procedure of obtaining its CPT. AO-1 has four parent nodes: AO1 (incomplete salt drainage in the evening), AO2 (insufficient molten salt flow rate), AO3 (insufficient preheating in the morning), and AO4 (large transient temperature fluctuations).

7.4.1. Obtaining Experts’ Opinions

The expert panel compared the comparative significance of the parent nodes to the child node driven by their expertise and background. The comparison results are presented in Table 11.

7.4.2. Obtaining the Weights of Parent Nodes Utilizing IT2FS-BWM

The relative importance values of AO1, AO2, AO3, and AO4 on AO-1 were computed according to each expert opinion. The detailed calculation procedure on expert E1 is as follows:
min δ * s . t ω 11 6 ω 21 δ * , ω 12 7 ω 22 δ * , ω 13 7 ω 23 δ * , ω 14 8 ω 24 δ * , ω 11 6.5 ω 21 δ * , ω 12 7 ω 22 δ * , ω 13 7 ω 23 δ * , ω 14 7.5 ω 24 δ * , ω 11 4 ω 31 δ * , ω 12 5 ω 32 δ * , ω 13 5 ω 33 δ * , ω 14 6 ω 34 δ * , ω 11 4.5 ω 31 δ * , ω 12 5 ω 32 δ * , ω 13 5 ω 33 δ * , ω 14 5.5 ω 34 δ * , ω 11 3 ω 41 δ * , ω 12 4 ω 42 δ * , ω 13 4 ω 43 δ * , ω 14 5 ω 44 δ * , ω 11 3.5 ω 41 δ * , ω 12 4 ω 42 δ * , ω 13 4 ω 43 δ * , ω 14 4.5 ω 44 δ * , ω 31 2 ω 21 δ * , ω 32 3 ω 22 δ * , ω 33 3 ω 23 δ * , ω 34 4 ω 24 δ * , ω 31 2.5 ω 21 δ * , ω 32 3 ω 22 δ * , ω 33 3 ω 23 δ * , ω 34 3.5 ω 24 δ * , ω 41 3 ω 21 δ * , ω 42 4 ω 22 δ * , ω 43 4 ω 23 δ * , ω 44 5 ω 24 δ * , ω 41 3.5 ω 21 δ * , ω 42 4 ω 22 δ * , ω 43 4 ω 23 δ * , ω 44 4.5 ω 24 δ * j = 1 4 C O A ω j E = 1 ω j E 1 U ω j E 1 L , ω j E 4 L ω j E 4 U ω j E 1 L ω j E 2 L ω j E 3 L ω j E 4 L ω j E 1 U ω j E 2 U ω j E 3 U ω j E 4 U ω j E 1 U 0 , j = 1 , 2 , 3 , 4
The ideal solution to the above system of simultaneous equations yields: δ * = 0.01. Expert of E1 evaluation of the parent node weight:
WAO1 (E1) = 0.336, WAO2 (E1) = 0.162, WAO3 (E1) = 0.225, WAO4 (E1) = 0.276
Subsequently, the above calculation steps were repeated to determine the individual rating weights for the other four experts. Using Equation (25), the weighted relative importance values were calculated. The results are as follows:
WAO1 = 0.311, WAO2 = 0.128, WAO3 = 0.443, WAO4 = 0.119

7.4.3. Utilizing the Leaky-Weighted Sum Algorithm to Calculate the CPTs

Experts evaluate of the probability distribution for the parent nodes of the “AO-1” node are presented in Table 12 and Table 13.
Based on the Equation (31), the CPT of the node AO-1 was obtained, refer to Appendix C.

8. Results and Discussion

This section analyzed and discussed the potential risks associated with common accidents of the equipment in the STPP using the established BN model.

8.1. Failure Probabilities of the Equipment in the STPP

Figure 12 shows the failure probabilities of the equipment under normal operating conditions. As shown in Figure 12a, the occurrence probability of AS1 (blockage of the receiver) is 0.06 due to the small diameter of the receiver pipes and their exposure to the harsh external environment. The probability of AS2 (leakage of the receiver) is 0.05. As shown in Figure 12b, the probability of PS1 (blockage of the salt piping) is only 0.06 because of the presence of insulation and heating measures. The subsequent events PS2 (turbulence of the salt piping), PS3 (leakage of the salt piping), and PS4 (fire) have occurrence probabilities of 0.05, 0.02, and 0.01, respectively. For the salt tank, the occurrence probability of TS1 (leakage of the salt tank) is 0.04, and the following TS2 (failure of the salt tank foundation), TS3 (fire), and TS4 (explosion) have probabilities of 0.02, 0.01, and 0.00, respectively (see Figure 12c). For the heat exchanger, the probabilities of ES1 (blockage of the heat exchanger), ES2 (turbulence of the heat exchanger), ES3 (leakage of the heat exchanger), ES4 (explosion), and ES5 (fire) are 0.08, 0.04, 0.02, 0.01, and 0.01, respectively (see Figure 12d).
Compared to the typical failure probability ranges in authoritative petrochemical handbooks (e.g., OREDA [47], API RP 581 [48]), which define pipeline, tank, and heat exchanger failures within the 10−3–10−2/year magnitude, this study’s BN-derived failure probabilities for molten salt piping, thermal storage tanks, and heat exchangers fall within the same order of magnitude (10−2/year) but exhibit slightly higher numerical values. This deviation is attributed to the extreme operational conditions unique to STPP. The alignment with industry benchmarks while reflecting domain-specific stressors underscores the model’s predictive validity and its capacity to capture STPP systems’ heightened risk profiles.
It can be found that the failure probabilities of the four types of equipment (receiver, salt piping, salt tank, and heat exchanger) remain relatively high under normal operating conditions. However, as fault propagation paths evolve, the accident occurrence probability gradually decreases across sequential stages. This aligns with the phased deployment of multi-level safety response mechanisms in existing power plant system designs. During initial failure phases, rapid isolation systems effectively block fault propagation paths. Such progressive protection strategies enable the probability of single equipment failures escalating into severe accident chains to exhibit an exponential decay trend.

8.2. Importance Analysis of Triggering Factors

This section employs a parameter sensitivity analysis based on BNs to quantitatively diagnose the triggering factors of key equipment. Taking the receiver (AS1) as a case study, AS1 is first defined as the target node, and the influence of different parent nodes on AS1 is evaluated through strength analysis (Figure 13). On this basis, the “derivatives” of each factor in the sensitivity tornado are further utilized to rank the importance of various triggering factors.
The results of the sensitivity analysis are summarized in Figure 14, which illustrates the relative importance of various triggering factors contributing to typical equipment failures in the STPP.
From Figure 14a, it is concluded that the primary factors leading to AS1 is AO3 (insufficient preheating in the morning), where low preheating temperature can cause molten salt to condense in the flow areas. AL3 (impurities of the molten salt) is also a significant factor, as corrosion products continuously detach and deposit in the receiver pipes. AO1 (incomplete salt drainage in the evening) leads to incomplete drainage of molten salt, which solidifies in the pipes and cause blockages.
As shown in Figure 14b, for PS1, PO1 (incomplete salt drainage in the evening) has the most severe impact. When the pipe temperature is low at night, residual molten salt that is not fully discharged can solidify and obstruct flow. PM3 (damage of the insulation material), which exposes the pipes to the environment, significantly increases heat loss. PO1 (delayed heating startup) is also noteworthy; if heat tracing measures are not promptly activated, the molten salt may solidify as the pipe temperature drops.
It can be seen in Figure 14c that TPH (poor quality of the weld) is identified as the primary cause of tank cracking, with welding defects leading to stress concentrations that significantly elevate the failure risk. Additionally, TOL (corrosion of the molten salt) accelerates the material cracking process. Temperature-induced TO9 (thermal stress) is another critical factor contributing to material cracking.
As shown in Figure 14d, EL2 (impurities of the molten salt), EO3 (insufficient preheating in the morning), and EO2 (insufficiency of molten salt flow rate) are the main three causes of heat exchanger failure. EL2 can accumulate in the heat exchanger, causing fouling. EO3 may cause temperature unevenness, adversely affecting the fluidity of the molten salt. And EO2 can hinder molten salt circulation and impede heat transfer, leading to localized supercondensation.
The results obtained from the aforementioned sensitivity analysis have been validated in the literature (e.g., salt piping PS1 [2,49], salt tank TS1 [50,51]). In response to the issues raised, propose the following methods: For AS1, incorporate heating systems around the receiver tubes to maintain the temperature of exposed sections. Regarding PS1, adjust pipeline gradient to 3–5° for gravity-driven salt evacuation. For TS1, enhance welding quality and eliminate post-weld residual stresses. Concerning ES1, schedule weekly cleaning cycles to maintain heat transfer efficiency.
Equipment failures are influenced not only by internal factors but can also by cascading effects from upstream equipment failures. Figure 15 illustrates the impact of upstream equipment incidents on downstream equipment and the importance ratios of self-impact factors for downstream equipment. The analysis indicates that external factors, particularly those affecting P2 (obstructed flow of the molten salt), have a significant influence that cannot be overlooked. Conversely, the influence of PS2 on T1 (tank cracking) is negligible and can be disregarded. Furthermore, the occurrence of TS1 in E3 (obstructed flow of the molten salt) leads to a substantial decrease in molten salt, resulting in insufficient supply to the heat exchanger.
In summary, the impact of external factors on equipment is significant and should not be ignored. Therefore, it is strongly recommended to implement isolation measures for equipment. Immediate isolation procedures should be initiated upon the occurrence of an upstream equipment incident to effectively prevent the spread of accidents, ensuring the safety and stable operation of the entire system.

8.3. Effectiveness Analysis of Response Measures

To investigate the effectiveness of various response measures in mitigating accidents, the precursor event (P) is set to true within the potential accident pathway of the equipment, specifically P (precursors) = T. This setup allows us to explore the impact on adjacent events when the precursor occurs. Different states of R (response measures) are then configured to evaluate their effectiveness. Figure 16 shows the extent of influence on relevant nodes under different states of response measures.
As shown in Figure 16a, when the precursor events (A1 and A2 = T) occur while the response measures remain unchanged, the probability of AS1 escalates from 0.06 to 0.39, and A3 concurrently rises from 0.04 to 0.14. Upon detecting molten salt condensation, the company swiftly implements countermeasures and strictly clean the interior of the receiver. Consequently, the probability of AS1 markedly diminishes from 0.39 to 0.22. However, A3 drops only from 0.14 to 0.09. The response measures exert a notable impact on AS1 but exhibit limited efficacy in preventing A3.
Similarly, as shown in Figure 16b, the probability of PS1 escalates from 0.05 to 0.26 and P2 concurrently rises from 0.07 to 0.21. During a rigorous inspection of heating measures’ integrity and upon the occurrence of PS1, if the response measure PR1 is fully activated (PR1 = T), the probability of PS1 will decrease from 0.26 to 0.11, and P2 will drop from 0.21 to 0.08. It is clear that PR1 has a significant restraining effect on both PS1 and P2.
As shown in Figure 16c, the probabilities of TS1, T2, and T3 increase from 0.03 to 0.34, 0.02 to 0.17, and 0.03 to 0.19, respectively. Conversely, if the company rigorously implements all leak prevention measures, accelerates the salt transfer process, and fully activates the response measure TR1 (TR1 = T), the probability decrease as follows: TS1 from 0.34 to 0.28, T2 from 0.17 to 0.11, and T3 from 0.19 to 0.05. It is evident that even with comprehensive response measures, the probability of TS1 remains significantly high. TS1 could potentially lead to T2 or T3, causing permanent damage to the storage tank.
Similarly, as shown in Figure 16d, the probabilities of ES1 and E3 rises from 0.06 to 0.29 and 0.05 to 0.24, respectively. However, when the company strictly adheres to standard operating procedures, promptly inspects and maintains the heating measures, thoroughly cleans various contaminants, and fully activates the response measures ER1 (ER1 = T), the probability of ES1 will decrease from 0.29 to 0.15, and that of E3 will drop from 0.24 to 0.09. It can be seen that the response measures obviously control ES1 and effectively manage E3.
The principle of ‘prevention being superior to cure’ must always be strictly followed in power plant accident prevention and control. First, design and installation should address key triggers to minimize defects and reduce incident likelihood. Secondly, during operation, operation and maintenance standards should be rigorous implemented. Subsequently, comprehensive hazard identification should be conducted, and critical safeguards should be established in key areas to effectively suppress incidents when they occur. Finally, measures should be taken to mitigate potential safety threats in the surroundings of the power plant to prevent the occurrence of external input accidents.

8.4. Prediction of Potential Accident Consequences

8.4.1. Effect of Normal Operating Conditions on Accident Consequences

Figure 17 presents the potential accident consequences for the equipment in the STPP under normal operating conditions. For C1 (direct economic losses), there is a probability of 98% that plant downtime will result in direct electricity sales losses of less than 1 million RMB. In 2% of cases, losses may range from 1 million to 10 million RMB. For C2 (casualties), there is a probability of 98% causing Level I consequence and a 2% chance of Level II consequence. As for C3 (equipment damage), it is estimated that 93% of incidents may require a shutdown, 6% might need a shutdown and inspection, and 1% could involve starting backup equipment.

8.4.2. Effect of Response Measures on Accident Consequences

Figure 18 shows the effect of response measures on accident consequences in the STPP. Figure 18a,b present the potential accident consequences with and without response measures, respectively. Clearly, response measures obviously reduce the probabilities of potential accidents. For C1, Level II consequence decreases from 22% to 3%, and Level III from 2% to zero. For C2, Level II consequence falls from 11% to 2%, and Level III is reduced from 2% to zero. For C3, Level II declines from 28% to 5%, Level III from 11% to 1%, and Level IV from 2% to 0%.
Figure 18c,d show the changes in accident consequences under precursor events, with response measures transiting from a general state to full activation. For C1, Level III consequence decreases from 6% to 1%, while Level II from 30% to 20%. For C2, Level III consequence reduces from 5% to 1%, and Level II from 14% to 10%. For C3, Level IV consequence declines from 10% to 3%, Level III from 25% to 9%, and Level II from 35% to 27%. The implemented measures effectively lower the severity of accident consequences, shifting consequence from higher to lower levels and preventing further progression towards more severe outcomes.

8.4.3. Effect of Accident Scenarios on Accident Consequences

To clarify the severe consequences caused by key equipment failures in STPPs, sets the accident scenario node to true to obtain the probability distribution of accident consequences. Figure 19 illustrates the hierarchical consequence distribution of a salt tank leakage accident (TS1). As shown in Figure 19, for C1, the proportions of Level II, III, and IV are 30%, 45%, and 9%, respectively; for C2, the proportions of Level II, III, and IV are 52%, 10%, and 0%, respectively; and for C3, the proportions of Level II, III, and IV are 8%, 19%, and 73%, respectively. Notably, compared with the average economic loss values of existing molten salt tank leakage cases in Table 1, the economic loss levels in this study are slightly higher. This discrepancy arises because industry-reported data typically include only a single dimension (either power sales loss or maintenance costs), whereas this study incorporates dual-dimensional data (both power sales loss and maintenance costs), yielding more rational results that validate the reliability of the model. Consequence severity distributions for failures of other equipment are provided in Appendix D.

9. Conclusions

This study presents an integrated method that combines scenario deduction with type-2 fuzzy sets-based BN to assess the potential failure risks of equipment in STPPs:
(1) A scenario deduction model has been developed, based on typical accident cases, which incorporates essential elements including triggering factors, precursor events, accident scenarios, and response measures. This model is designed to trace the causes of equipment failures and explore the possible evolution paths.
(2) Addressing the complexity introduced by a large number of nodes in the Bayesian network, an approach integrating both objective data and expert elicitation was employed to derive the necessary analysis parameters. To minimize subjectivity in expert opinions, the IT2FS-SAM was utilized to determine the prior probabilities of nodes. For consistent and simplified decision-making, the IT2FS-BWM is used to determine parent node weights, and the leaky-weighted sum algorithm is applied to optimize the CPTs.
(3) The proposed method was demonstrated through a case study of an STPP in western China, establishing a quantitative risk assessment model for four types of critical equipment: receiver, salt piping, salt tank, and heat exchanger. This model includes 16 typical accident scenarios, 41 triggering factors, 16 precursor events, and 21 response measures. By applying both forward causation and backward reasoning of BN, the failure probabilities of equipment, triggering factors, the effectiveness of response measures, and the potential consequences of accidents were analyzed.
Due to the limited operational data available from STPPs, this study partially relied on expert elicitation for data acquisition, which may introduce some degree of subjectivity. Future work will focus on updating the model parameters with additional operational data as it becomes available, thereby enhancing the accuracy of the assessment outcomes. This continuous improvement will provide stronger support for safety management in STPP operations.

Author Contributions

Conceptualization, T.L.; methodology, T.L.; software, Y.L.; validation, W.W., X.L. (Xiufeng Li) and X.G.; formal analysis, S.Z.; investigation, R.M.; resources, X.L. (Xiufeng Li); data curation, X.L. (Xiaowei Liu); writing—original draft preparation, T.L.; writing—review and editing, W.W.; visualization, M.Z.; supervision, X.L. (Xiufeng Li); project administration, Y.L.; funding acquisition, W.W. All authors have read and agreed to the published version of the manuscript.

Funding

This work was supported by the National Key Research and Development Program of China (Grant No. 2023YFF0614904) and the Natural Science Foundation of Shaanxi Province (No. 2020JM-436).

Institutional Review Board Statement

Not applicable.

Informed Consent Statement

Not applicable.

Data Availability Statement

The original contributions presented in this study are included in the article. Further inquiries can be directed to the corresponding author.

Conflicts of Interest

The authors declare no conflicts of interest.

Abbreviations

Solar tower power plant(s)STPP(s) Interval type-2 fuzzy number(s)IT2FN(s)
Interval type-2 fuzzy set(s)IT2FS(s)Conditional probability table(s)CPT(s)
Bayesian network(s)BN(s)Multi-criteria decision-makingMCDM
Concentrated solar powerCSPUpper membership function(s)UMF(s)
Analytic hierarchy processAHPLower membership function(s)LMF(s)
Analytic network processANPIT2FS-based similarity aggregation methodIT2FS-SAM
Best–worst methodBWMIT2FS-based best–worst methodIT2FS-BWM
Footprint of uncertaintyFOULeaky-weighted sum algorithmLeaky-WSA
Type-2 fuzzy set(s)T2FS(s)

Appendix A. The Prior Probabilities of Basic Nodes in the BN

Table A1. Data related to basic nodes of bad weather.
Table A1. Data related to basic nodes of bad weather.
NodeDayOccurrenceFailure
AV13651500.411
AV23651040.285
Table A2. Prior probabilities of basic nodes in BN.
Table A2. Prior probabilities of basic nodes in BN.
NodeOperational Time/YearOccurrenceFailure
AD171620.002789398
AD230.004181179
AD410.001395673
AM110.001395673
AF120.002789398
PM210.001395673
PM110.001395673
PF120.002789398
PL110.001395673
TD1210.001395673
TM110.001395673
TF120.002789398
TL110.001395673
TL410.001395673
ED1470.009728901
EM110.001395673
EL110.001395673
EF120.002789398
EL410.001395673
AR1140.005571016
AR1220.002789398
PR1180.011110996
PR2140.005571016
PR3110.001395673
PR4210.001395673
TR3171610.001395673
ER1180.011110996
ER1220.002789398
ER2140.005571016
ER5110.001395673

Appendix B. The Prior Probabilities of the Nodes in the BN from Experts

Table A3. Prior probabilities of basic nodes in BN of receiver.
Table A3. Prior probabilities of basic nodes in BN of receiver.
EquipmentPrecursor EventTriggering
Factor
E1E2E3E4E5Prior
Probability
ReceiverA1AO-1AO1HMHMMHML0.00349715
AO2LMHMLML0.00015737
AO3HHVHMHMH0.01425214
AO4MMHMHMM0.00163636
A2AL-2AL3MMMHVHMH0.00222082
A3AD-3AD3LMMLMLM0.00038526
AL-3AL2MHMHHM0.00182
AO-3AO4MMHMHMM0.00163636
AO5VLHMMH0.0033
AO7MLMHHMLMH0.00139
AO8MHHMHML0.00328
AO-3AO9MHMHMHM0.00261
AO11LHHMLM0.00307
AO12MLMMLMM0.00061346
A4AV-4AV3LMMLMML0.00036
Table A4. Prior probabilities of basic nodes in BN of salt piping.
Table A4. Prior probabilities of basic nodes in BN of salt piping.
EquipmentPrecursor EventTriggering
Factor
E1E2E3E4E5Prior
Probability
Salt
piping
P1PO-1PO1HMMHMMH0.00282556
PO2VLLMMLL5.67 × 10−5
PO3MMMLMLM0.00071557
PO4MHMHMMHH0.00497099
PO6HHHMLM0.00993591
PD-1PD4MHVHMHMH0.00685573
PD5MMHMMLML0.00069663
Salt pipingP2PO-2PO4MHMHMMHH0.00497099
PO7LMLLLML9.13 × 10−5
PO8MHMHMH0.00488282
PO9MLMMHML0.00058983
PO11MLMMMLM0.00057442
PO12MLMMLMM0.00061346
P3PO-3PO4MHMHMMHH0.00497099
PO5MMLVLLM0.00043572
PO7MHMHHMH0.0072712
PO8LMLLLML9.13 × 10−5
PO9MHMHMH0.00488282
PO10MMHMLMHM0.00175873
PO11MLMMMLM0.00057442
PO12MLMMLMM0.00061346
PF-3PF2MMMLMML0.00067646
PD-3PD5MMHMMLML0.00069663
PD6MHMMLMML0.0011461
PD7HMMHMML0.0035874
PL-3PL2LMHMMLM0.00066429
P4PV-4PV3MMLMMHM0.00016133
Table A5. Prior probabilities of basic nodes in BN of salt tank.
Table A5. Prior probabilities of basic nodes in BN of salt tank.
EquipmentPrecursor EventTriggering
Factor
E1E2E3E4E5Prior Probability
Salt
tank
T1TO-1TO4MMMLML0.00065613
TO5MLLMMLL0.00011925
TO7LMHLMMH0.00070409
TO8LMMHMML0.00056349
TO9MLMLMML0.00035527
TO10MHMHMMHM0.00314227
TO11MHHMHMM0.00321713
TO12HMHMLMHMH0.00499926
TD-1TD8MLLLMMH0.00015741
Salt
tank
T1TD-1TD9MHMLMHMM0.00150557
TD10LLMLMML0.00010829
TD11MHMLMMML0.00056439
TD-2TD13MLLLLML9.13 × 10−5
TO-2TO4MMMLML0.00065613
TO5MLLMMLL0.00011925
TO8LMMHMML0.00056349
TM-2TM4MMHMHMML0.00155942
T3TV-3TV3LLMLMM0.00016133
T4TL-4TL3LLMLML6.79 × 10−5
Table A6. Prior probabilities of basic nodes in BN of heat exchanger.
Table A6. Prior probabilities of basic nodes in BN of heat exchanger.
EquipmentPrecursor EventTriggering
Factor
E1E2E3E4E5Prior
Probability
Heat
exchanger
E1EO-1EO2MMLMMHM0.00090868
EO3MLLMLMML0.00019768
EO4HMHMMHM0.00349715
EM-1EM3MLMLMLL0.00014309
E2EL-2EL3MMMHVHMH0.00222082
E3EO-3EO4HMHMMHM0.00349715
EO8MLMMMLML0.00035227
E4EO-4EO9VLMLMLM0.00037826
EO10MHMHMHH0.0078315
EO12LMHMLHM0.001075
EL-4EL2MLMMHMMH0.00132528
EO-4EO4HMHMMHM0.00349715
EO5MMHMHMHM0.00249917
EO7MHHMHMLM0.00364236
EO8MLMMMLML0.00035227
EO9VLMLMLM0.00037826
O10MHMHMHH0.0078315
EO11LMHMMHML0.0013009
Heat
exchanger
E5EL-5EL3MMMHVHMH0.00222082
E6EV-6EV3LLMLMM0.00016133
Table A7. Prior probabilities of basic nodes related to response measures.
Table A7. Prior probabilities of basic nodes related to response measures.
EquipmentNodeE1E2E3E4E5Prior Probability
ReceiverAR21HMMHMH0.00483352
AR22VLLMMLL5.67 × 10−5
Salt pipingPR31LLMLMML0.00010829
PR32HMMHMH0.00483352
PR41VLLMMLL5.67 × 10−5
Salt tankTR11MHHMHMM0.00321713
TR12VLLMMLL5.67 × 10−5
TR21HMMHMH0.00483352
TR32VLLMMLL5.67 × 10−5
TR41MHHMLL0.00347908
Heat exchangerER31HMMHMH0.00483352
ER32VLLMMLL5.67 × 10−5
ER41MHHMLL0.00347908

Appendix C. The CPT of the “AO-1” Node

AO1AO2AO3AO4Operation Issues
yn
yyyy0.7415094340.258490566
yyyn0.6816599980.318340002
yyny0.5310908570.468909143
yynn0.4783168930.521683107
ynyy0.6778312590.322168741
ynyn0.6179818230.382018177
ynny0.4744881540.525511846
ynnn0.4146387180.585361282
nyyy0.5966820370.403317963
nyyn0.5368326010.463167399
nyny0.3933389310.606661069
nynn0.3334894950.666510505
nnyy0.5330038620.466996138
nnyn0.4731544260.526845574
nnny0.3296607570.670339243
nnnn0.2698113210.730188679

Appendix D. Failure-Induced Consequences of Critical Equipment

NodeLevelDirect Economic
Losses (C1)
Casualties
(C2)
Equipment Damage (C3)
AS1 = T
(Receiver)
I37%49%27%
II45%38%58%
III18%13%13%
IV0%0%2%
PS1 = T
(Salt piping)
I62%48%16%
II37%34%37%
III1%18%42%
IV0%0%5%
TS1 = T
(Salt tank)
I16%38%0%
II30%52%8%
III45%10%19%
IV9%0%73%
ES1 = T
(Heat exchanger)
I31%48%41%
II51%35%58%
III18%17%1%
IV0%0%0%

References

  1. China Solar Thermal Alliance (CSTA). Blue Book of China’s Concentrating Solar Power Industry 2024; China Solar Thermal Alliance: Beijing, China, 2025; Available online: http://www.cnste.org (accessed on 3 April 2025).
  2. Mehos, M.; Price, H.; Cable, R.; Kearney, D.; Kelly, B.; Kolb, G.; Morse, F. Concentrating Solar Power Best Practices Study; National Renewable Energy Laboratory: Golden, CO, USA, 2020; NREL/TP-5500-75763. Available online: https://docs.nrel.gov/docs/fy20osti/75763.pdf (accessed on 19 December 2024).
  3. Reilly, H.E.; Kolb, G.J. An Evaluation of Molten-Salt Power Towers Including Results of the Solar Two Project; Sandia National Laboratories: Albuquerque, NM, USA, 2002; SAND2002-0120. [Google Scholar]
  4. CSPPLAZA Solar Thermal Power Network. Global Accidents Summary of Concentrated Solar Power Plants: Preventive Measures for Domestic Demonstration Projects. 2017. Available online: https://www.cspplaza.com/article-9101-1.html/ (accessed on 10 March 2017).
  5. National Energy Administration (NEA). Notice from the General Office of the National Energy Administration on Conducting Safety Inspections for Molten Salt Thermal Storage and Other Integrated Energy Utilization Projects. 2023. Available online: https://zfxxgk.nea.gov.cn/2023-05/17/c_1310720738.htm (accessed on 7 January 2025).
  6. CSPPLAZA Solar Thermal Power Network. The Noor Ouarzazate Phase III Concentrated Solar Power Plant in Morocco Has Officially Resumed Operations. 2024. Available online: https://www.cspplaza.com/article-27909-1.html (accessed on 12 February 2025).
  7. Prieto, C.; Ruiz-Cabañas, F.J.; Madina, V.; Fernández, A.I.; Cabeza, L.F. Corrosion performance of alloy 800H and alloy 625 for potential use as molten salts solar receiver materials in concentrating solar power tower plants. J. Energy Storage 2022, 55, 105824. [Google Scholar] [CrossRef]
  8. Wan, Z.J.; Fang, J.B.; Tu, N.; Wei, J.J.; Qaisrani, M.A. Numerical study on thermal stress and cold startup induced thermal fatigue of a water/steam cavity receiver in concentrated solar power (CSP) plants. Sol. Energy 2018, 170, 430–441. [Google Scholar] [CrossRef]
  9. Gonzalez-Gomez, P.A.; Rodriguez-Sanchez, M.R.; Laporte-Azcue, M.; Santana, D. Calculating molten-salt central-receiver lifetime under creep-fatigue damage. Sol. Energy 2020, 213, 180–197. [Google Scholar] [CrossRef]
  10. Lau, M.Y.; Liu, Y.M.; Kaber, D.B. Consequence severity-probability importance measure for fault tree analysis. Int. J. Syst. Assur. Eng. Manag. 2023, 15, 854–870. [Google Scholar] [CrossRef]
  11. Yang, D.D.; Xing, K.X.; Pan, L.D.; Li, N.; Yu, J.X. Sustainable risk management framework for petroleum storage facilities: Integrating bow-tie analysis and dynamic Bayesian networks. Sustainability 2025, 16, 2642. [Google Scholar] [CrossRef]
  12. Hefaidh, H.; Djebabra, M.B. A conceptual framework for risk matrix capitalization. Int. J. Syst. Assur. Eng. Manag. 2020, 11, 755–764. [Google Scholar] [CrossRef]
  13. Wang, D.; Wan, K.; Ma, W. Emergency decision-making model of environmental emergencies based on case-based reasoning method. J. Environ. Manag. 2020, 262, 110382. [Google Scholar] [CrossRef] [PubMed]
  14. Yuan, C.F.; Hu, Y.C.; Zhang, Y.L.; Zuo, T.; Wang, J.H.; Fan, S.J. Evaluation on consequences prediction of fire accident in emergency processes for oil-gas storage and transportation by scenario deduction. J. Loss Prev. Process Ind. 2021, 72, 104570. [Google Scholar] [CrossRef]
  15. She, J.; Guo, Z.; Li, Z.; Liang, S.; Zhou, Y. Research on scenario deduction and emergency decision-making evaluation for construction safety accidents. Reliab. Eng. Syst. Saf. 2024, 251, 110317. [Google Scholar] [CrossRef]
  16. Pang, L.; Zhang, M.X.; Yang, K.; Sun, S.H. Scenario derivation and consequence evaluation of dust explosion accident based on dynamic Bayesian network. J. Loss Prev. Process Ind. 2023, 83, 105055. [Google Scholar] [CrossRef]
  17. Tang, M.; Zeng, H.; Wang, K. Bayesian water quality evaluation model based on generalized triangular fuzzy number and its application. Environ. Process 2022, 9, 6. [Google Scholar] [CrossRef]
  18. Yaşlı, F.; Bolat, B. A novel risk analysis approach for occupational safety using Bayesian network and interval type-2 fuzzy sets: The case of underground mining. J. Intell. Fuzzy Syst. 2022, 42, 265–282. [Google Scholar] [CrossRef]
  19. Tang, J.; Liu, X.W.; Wang, W.Z. COVID-19 medical waste transportation risk evaluation integrating type-2 fuzzy total interpretive structural modeling and Bayesian network. Expert. Syst. Appl. 2023, 213, 118885. [Google Scholar] [CrossRef]
  20. Liu, J.W.; Li, X.F.; Zhang, Y.X.; Li, T.; Wei, L.P.; Wu, W. Failure risk assessment by multi-state dynamic Bayesian network based on interval type-2 fuzzy sets and leaky-weighted sum algorithm: A case study of crude oil pipelines. Expert. Syst. Appl. 2024, 250, 123942. [Google Scholar] [CrossRef]
  21. Erol, H.; Dikmen, I.; Atasoy, G.; Birgonul, M. An analytic network process model for risk quantification of mega construction projects. Expert. Syst. Appl. 2021, 191, 116215. [Google Scholar] [CrossRef]
  22. Rezaei, J. Best-worst multi-criteria decision-making method. Omega 2015, 53, 49–57. [Google Scholar] [CrossRef]
  23. Rezaei, J. Best-worst multi-criteria decision-making method: Some properties and a linear model. Omega 2016, 64, 126–130. [Google Scholar] [CrossRef]
  24. Li, Z.; Xing, Y.P.; Dong, P. A novel q-rung orthopair fuzzy best-worst method, Shannon entropy and MARCOS method for mobile medical app service quality evaluation. Appl. Soft. Comput. 2024, 155, 111417. [Google Scholar] [CrossRef]
  25. He, J.M.; Wu, Y.N.; Yong, X.K.; Ke, Y.M.; Tan, Q.L.; Liu, F.T. Lifecycle risk assessment on the sustainable development of upgrading energy projects using abandoned mines: An ISM-BWM method. Sustain. Energy Technol. Assess. 2022, 54, 102833. [Google Scholar] [CrossRef]
  26. Pearl, J. Fusion, propagation, and structuring in belief networks. Artif. Intell. 1986, 29, 241–288. [Google Scholar] [CrossRef]
  27. Zadeh, L.A. Fuzzy sets. Inf. Control 1965, 8, 338–353. [Google Scholar] [CrossRef]
  28. Zadeh, L.A. The concept of a linguistic variable and its application to approximate reasoning. In Learning Systems and Intelligent Robots; Fu, K.S., Tou, J.T., Eds.; Springer: Boston, MA, USA, 1974; pp. 1–10. [Google Scholar] [CrossRef]
  29. Mendel, J.M. Uncertain Rule-Based Fuzzy Systems: Introduction and New Directions, 2nd ed.; Springer International Publishing: Cham, Switzerland, 2017. [Google Scholar] [CrossRef]
  30. Mendel, J.M.; Rajati, M.R.; Sussner, P. On clarifying some definitions and notations used for type-2 fuzzy sets as well as some recommended changes. Inf. Sci. 2016, 340–341, 337–345. [Google Scholar] [CrossRef]
  31. Aisbett, J.; Rickard, J.T.; Morgenthaler, D.G. Type-2 fuzzy sets as functions on spaces. IEEE Trans. Fuzzy Syst. 2010, 18, 841–844. [Google Scholar] [CrossRef]
  32. Han, S.L.; Wang, W.; Liu, X.W. A new type-2 fuzzy multi-criteria hybrid method for rail transit operation safety assessment. Appl. Soft. Comput. 2021, 113, 107927. [Google Scholar] [CrossRef]
  33. Prieto, C.; Osuna, R.; Fernández, A.I.; Cabeza, L.F. Thermal storage in a MW scale. Molten salt solar thermal pilot facility: Plant description and commissioning experiences. Renew. Energy 2016, 99, 852–866. [Google Scholar] [CrossRef]
  34. Litwin, R. Receiver System: Lessons Learned from Solar Two; Sandia National Laboratories: Albuquerque, NM, USA; Livermore, CA, USA, 2002. [Google Scholar] [CrossRef]
  35. Peiro, G.; Prieto, C.; Gasia, J.; Jove, A.; Miro, L.; Cabeza, L.F. Two-tank molten salts thermal energy storage system for solar power plants at pilot plant scale: Lessons learnt and recommendations for its design, start-up and operation. Renew. Energy 2018, 121, 236–248. [Google Scholar] [CrossRef]
  36. Guijarro-Gil, M.J.; Botejara-Antúnez, M.; Díaz-Parralejo, A.; García-Sanz-Calcedo, J. Selection of Sol-Gel Coatings by the Analytic Hierarchy Process and Life Cycle Assessment for Concentrated Solar Power Plants. Sustainability 2025, 17, 2449. [Google Scholar] [CrossRef]
  37. Ramzali, N.; Lavasani, M.R.M.; Ghodousi, J. Safety barriers analysis of offshore drilling system by employing fuzzy event tree analysis. Saf. Sci. 2015, 78, 49–59. [Google Scholar] [CrossRef]
  38. Yu, J.X.; Ding, H.Y.; Yu, Y.; Wu, S.B.; Zeng, Q.Z.; Ma, W.T. A novel risk analysis approach for FPSO single point mooring system using Bayesian network and interval type-2 fuzzy sets. Ocean Eng. 2022, 266, 113144. [Google Scholar] [CrossRef]
  39. Ghorabaee, M.K.; Amiri, M.; Zavadskas, E.K.; Turskis, Z.; Antucheviciene, J. A new multi-criteria model based on interval type-2 fuzzy sets and EDAS method for supplier evaluation and order allocation with environmental considerations. Comput. Ind. Eng. 2017, 112, 156–174. [Google Scholar] [CrossRef]
  40. Liu, Y.P.; Wang, S.; Liu, Q.; Liu, D.P.; Yang, Y.; Dan, Y.; Wu, W. Failure risk assessment of coal gasifier based on the integration of Bayesian network and trapezoidal intuitionistic fuzzy number-based similarity aggregation method (TpIFN-SAM). Processes 2022, 10, 1863. [Google Scholar] [CrossRef]
  41. Celik, E.; Gul, M.; Aydin, N.; Gumus, A.T.; Guneri, A.F. A comprehensive review of multi criteria decision making approaches based on interval type-2 fuzzy sets. Knowl.-Based Syst. 2015, 85, 329–341. [Google Scholar] [CrossRef]
  42. Wu, Q.; Zhou, L.G.; Chen, Y.; Chen, H.Y. An integrated approach to green supplier selection based on the interval type-2 fuzzy best-worst and extended VIKOR methods. Inf. Sci. 2019, 502, 394–417. [Google Scholar] [CrossRef]
  43. Celik, E. Analyzing the shelter site selection criteria for disaster preparedness using best–worst method under interval type-2 fuzzy sets. Sustainability 2024, 16, 2127. [Google Scholar] [CrossRef]
  44. Das, B. Generating conditional probabilities for Bayesian networks: Easing the knowledge acquisition problem. arXiv 2004, arXiv:cs/0411034. [Google Scholar]
  45. Baker, S.; Mendes, E. Assessing the weighted sum algorithm for automatic generation of probabilities in Bayesian networks. In Proceedings of the 2010 IEEE International Conference on Information and Automation, Harbin, China, 20–23 June 2010; pp. 867–873. [Google Scholar] [CrossRef]
  46. Farsi, H.; Dizene, R.; Flamant, G.; Notton, G. Multi-criteria decision making methods for suitable site selection of concentrating solar power plants. Sustainability 2024, 16, 7673. [Google Scholar] [CrossRef]
  47. OREDA Project Joint Industry Project. Offshore and Onshore Reliability Data (OREDA Handbook), 6th ed.; DNV AS: Oslo, Norway, 2015; Available online: https://oredata.com/ (accessed on 5 December 2024).
  48. American Petroleum Institute (API). API Recommended Practice 581: Risk-Based Inspection Technology. United States. 2016. Available online: https://www.api.org/ (accessed on 29 October 2024).
  49. Niu, D.S.; Zhou, Z.; Xiao, B.; Zhao, L. Research progress on anti-freezing of molten salt pipeline systems in parabolic trough solar thermal power plants. Therm. Power Gener. 2019, 49, 63–86. [Google Scholar] [CrossRef]
  50. CSPPLAZA Solar Thermal Power Network. Seven Root Cause Analysis of Molten Salt Leakage Accident at Crescent Dunes Solar Thermal Power Plant. 2016. Available online: https://guangfu.bjx.com.cn/news/20161207/794644.shtml (accessed on 2 February 2025).
  51. Ye, D.; Zheng, W.; Li, F.; Guo, H.; Zeng, X.; Cai, J. Failure mechanisms and mitigation strategies for leakage in high-temperature molten salt storage tanks. Equip. Manag. Maint. 2023, 57, 149–151. [Google Scholar] [CrossRef]
Figure 1. Uncertainty representation using interval type-2 fuzzy numbers.
Figure 1. Uncertainty representation using interval type-2 fuzzy numbers.
Sustainability 17 04774 g001
Figure 2. Proposed research framework of this work.
Figure 2. Proposed research framework of this work.
Sustainability 17 04774 g002
Figure 3. Some photos of failed components in STPPs. (a) Crack of receiver tubes. (b) Burned insulation [35]. (c) Salt leakage in a valve [35].
Figure 3. Some photos of failed components in STPPs. (a) Crack of receiver tubes. (b) Burned insulation [35]. (c) Salt leakage in a valve [35].
Sustainability 17 04774 g003
Figure 4. Basic elements of TPSR model. (T represents triggering factor, P represents precursor event, S represents accident scenario, R represents response measure).
Figure 4. Basic elements of TPSR model. (T represents triggering factor, P represents precursor event, S represents accident scenario, R represents response measure).
Sustainability 17 04774 g004
Figure 5. An exemplary evolution path of an accident scenario.
Figure 5. An exemplary evolution path of an accident scenario.
Sustainability 17 04774 g005
Figure 6. Transformation rules from scenario deduction model to Bayesian network model.
Figure 6. Transformation rules from scenario deduction model to Bayesian network model.
Sustainability 17 04774 g006
Figure 7. Acquisition process of node probabilities of BN.
Figure 7. Acquisition process of node probabilities of BN.
Sustainability 17 04774 g007
Figure 8. Accident consequence evaluation model of STPPs (C1 denotes direct economic losses; C2 denotes casualties; C3 denotes equipment damage).
Figure 8. Accident consequence evaluation model of STPPs (C1 denotes direct economic losses; C2 denotes casualties; C3 denotes equipment damage).
Sustainability 17 04774 g008
Figure 9. Process flow for a STPP in western China.
Figure 9. Process flow for a STPP in western China.
Sustainability 17 04774 g009
Figure 10. Scenario evolution paths for accident risk evaluation of equipment in STPP.
Figure 10. Scenario evolution paths for accident risk evaluation of equipment in STPP.
Sustainability 17 04774 g010
Figure 11. Two types of accident evolution paths of equipment. (1 denotes the possible accident paths and consequences for equipment itself; 2 denotes impact of upstream equipment failures on downstream equipment).
Figure 11. Two types of accident evolution paths of equipment. (1 denotes the possible accident paths and consequences for equipment itself; 2 denotes impact of upstream equipment failures on downstream equipment).
Sustainability 17 04774 g011
Figure 12. Failure probabilities of equipment in STPP. (a) Receiver; (b) Salt piping; (c) Salt tank; (d) Heat exchanger.
Figure 12. Failure probabilities of equipment in STPP. (a) Receiver; (b) Salt piping; (c) Salt tank; (d) Heat exchanger.
Sustainability 17 04774 g012
Figure 13. Sensitivity analysis diagram for AS1.
Figure 13. Sensitivity analysis diagram for AS1.
Sustainability 17 04774 g013
Figure 14. Ranking of importance of triggering factors of different equipment in STPP. (a) AS1 (Receiver); (b) PS1 (Salt piping); (c) TS1 (Salt tank); (d) ES1 (Heat exchanger).
Figure 14. Ranking of importance of triggering factors of different equipment in STPP. (a) AS1 (Receiver); (b) PS1 (Salt piping); (c) TS1 (Salt tank); (d) ES1 (Heat exchanger).
Sustainability 17 04774 g014
Figure 15. Comparison of risk sources (red bar represents importance of self-triggering factor and green bar represents importance of upstream equipment influence).
Figure 15. Comparison of risk sources (red bar represents importance of self-triggering factor and green bar represents importance of upstream equipment influence).
Sustainability 17 04774 g015
Figure 16. Probability distribution of relevant nodes in different states of response measures. State 1 denotes state of potential accident; State 2 denotes occurrence of precursor incident; State 3 denotes activation of response measures. (a) Receiver; (b) Salt piping; (c) Salt tank; (d) Heat exchanger.
Figure 16. Probability distribution of relevant nodes in different states of response measures. State 1 denotes state of potential accident; State 2 denotes occurrence of precursor incident; State 3 denotes activation of response measures. (a) Receiver; (b) Salt piping; (c) Salt tank; (d) Heat exchanger.
Sustainability 17 04774 g016
Figure 17. Consequence assessment of potential accidents in equipment of STPP in this case.
Figure 17. Consequence assessment of potential accidents in equipment of STPP in this case.
Sustainability 17 04774 g017
Figure 18. Effect of response measures on accident consequences in STPP. (a) No response measures under normal operating conditions; (b) response measures under normal operating conditions; (c) response measures in a general state under precursor events; (d) response measures in full activation under precursor events.
Figure 18. Effect of response measures on accident consequences in STPP. (a) No response measures under normal operating conditions; (b) response measures under normal operating conditions; (c) response measures in a general state under precursor events; (d) response measures in full activation under precursor events.
Sustainability 17 04774 g018
Figure 19. Probability distribution of consequences caused by molten salt storage tank leakage.
Figure 19. Probability distribution of consequences caused by molten salt storage tank leakage.
Sustainability 17 04774 g019
Table 1. Some accidents at CSP plants.
Table 1. Some accidents at CSP plants.
NO.DateCSP PlantAccident TypeAccident CauseConsequence
11996.06The Solar Two Project [3]Cracking of absorber tubeReceiver blockageFive months of downtime
22010.02La Dehesa Solar Thermal Power Plant [4]Molten salt splashingOperational mistakeSix people injured
32015.01Solana Solar Power Plant [4]Two fires occurred within three monthsThermal energy storage system failurePower plant shutdown
42016.05Luanpah Tower 3 Solar Thermal Power Plant [4]FireImproper mirror field focusingTemporary shutdown of the power plant
52016.07Gemasolar Solar Thermal Power Plant [4]Molten salt tank leakageDesign issues of storage tank foundationRepair costs exceeding EUR 9 million, leading to bankruptcy
62016.10Crescent Dunes [4]Small-scale tank leakageWeld qualityUSD 4 million electricity sales loss, bankruptcy
72023.05Fenghe Molten Salt Thermal Energy Storage Project [5]Bursting of high-temperature molten saltMolten salt1 fatality and 13 injuries
82024.11Noor 150 MW [6]Molten salt tank leakageOperations and maintenanceUSD 47 million electricity sales loss
Table 2. Weighting criteria with scores of each expert [37].
Table 2. Weighting criteria with scores of each expert [37].
CategoryClassificationScore
Job titleSenior Executive10
Professor8
Engineer6
Worker4
Student2
Working years≥30 years10
15–28 years8
Working years7–15 years6
3–7 years4
≤3 years2
Education levelDoctor10
Master8
Bachelor6
Higher National Diploma4
School level2
Age≥508
40–496
30–394
<302
FamiliarityVery familiar10
Quite familiar8
Moderately familiar4
Basic familiarity2
Table 3. Linguistic terms and their corresponding IT2FNs.
Table 3. Linguistic terms and their corresponding IT2FNs.
Pairwise Linguistic TermCrisp NumberCorresponding Comparison IT2FNs
Completely equal importance (CEI)1((1, 1,1, 1, 1, 1), (1, 1, 1, 1, 0.9, 0.9))
Weak importance (WI)2((1, 2, 2, 3; 1, 1), (1.5, 2, 2, 2.5; 0.9, 0.9))
Moderate importance (MI)3((2, 3, 3, 4; 1, 1), (2.5, 3, 3, 3.5; 0.9, 0.9))
Moderate plus importance (MPI)4((3, 4, 4, 5; 1, 1), (3.5, 4, 4, 4.5; 0.9, 0.9))
Strong importance (SI)5((4, 5, 5, 6; 1, 1), (4.5, 5, 5, 5.5; 0.9, 0.9))
Strong plus importance (SPI)6((5, 6, 6, 7; 1, 1), (5.5, 6, 6, 6.5; 0.9, 0.9))
Very strong importance (VSI)7((6, 7, 7, 8; 1, 1), (6.5, 7, 7, 7.5; 0.9, 0.9))
Extreme importance (EI)8((7, 8, 8, 9; 1, 1), (7.5, 8, 8, 8.5; 0.9, 0.9))
Extreme more importance (EMI)9((8, 9, 9, 10; 1, 1), (8.5, 9, 9, 9.5; 0.9, 0.9))
Table 4. Assessment criteria of accident consequence.
Table 4. Assessment criteria of accident consequence.
Accident
Severity
Direct Economic
Losses (C1)
Casualties
(C2)
Equipment
Damage (C3)
Level
General accidentEconomic ≤ RMB 10 million Injured: 0 ≤ Person < 10
or death: 0 ≤ Person < 3
No repair requiredI
Major accidentRMB 10 million ≤ Economic < RMB 50 million Injured: 10 ≤ Person < 30
or death: 3 ≤ Person < 10
Shutdown and inspectionII
Heavy accidentRMB 50 million ≤ Economic < RMB 100 million Injured: 30 ≤ Person < 100 or death: 10 ≤ Person < 30Start backupIII
Mega accidentEconomic ≥ RMB 100 millionInjured: Person ≥ 100
or death: Person ≥ 30
Prolonged shut-downIV
Table 5. Meanings of nodes denoting triggering factors in Figure 10.
Table 5. Meanings of nodes denoting triggering factors in Figure 10.
SymbolTriggering Factors
MeaningNodeMeaningNodeMeaning
DDesign issuesD1Failure of the control systemD2Design of the receiver
D3Spot controlD4Improper insulation design improper of the discontinuous areas
D5Improper design of the piping structure D6Excessive design of the measurement points
D7Improper design of the piping support D8Oversizing risk of the tank
D9Restricted of the thermal expansionD10Stress concentration
D11Incomplete standards of the salt tank designD12Improper structural design of the tank foundation
D13Tank foundation location issuesD14Improper structural design of the heat exchanger
FInstallation issuesF1Poor quality of the weldF2Flange of loosening at measurement point
OOperation issuesO1Incomplete salt drainage in the eveningO2Insufficient molten salt flow rate
O3Insufficient preheating in the morningO4Large transient temperature fluctuations
O5Fatigue failureO6Delayed heating startup
O7Operating conditions not met for long-termO8Local overtemperature
O9Thermal stressO10Frequent start-stop
O11overpressureO12Thermal shock
MMaintenance issuesM1Lack of routine maintenanceM2Measurement instrument fault
M3Damage of the insulation material M4Failure of the tank foundation heat dissipation system
LMedium issuesL1Molten salt corrosionL2Erosion of the molten salt
L3Impurities of the molten salt L4Degradation of the molten salt
VEnvironment issuesV1Intermittent cloud coverV2Extreme weather
VEnvironment issuesV3Combustible materials of the surrounding area
Note: XT-n: “X” denotes equipment, including receiver, salt piping, salt tank, heat exchanger; “T” denotes triggering factors, “n” represents serial number connected to precursor event. For example, AD-1, where “A” stands for receive, “D” denotes design issues, and “1” indicates it is connected to node A1.
Table 6. Meanings of nodes denoting precursor events in Figure 10.
Table 6. Meanings of nodes denoting precursor events in Figure 10.
EquipmentPrecursor Events
NodeMeaningNodeMeaning
Receiver A1Freezing of the molten saltA3Cracking of the absorbing tubes
A2Accumulation of the impuritiesA4Fire hazard
Salt piping P1Freezing of the absorbing tubesP3Seals failure
P2Obstructed flow of the molten saltP4Fire hazard
Salt tankT1Tank crackingT3Fire hazard
T2Damage of the tank foundationT4Explosion hazard
Heat exchanger E1Freezing of the molten saltE4Cracking of heat exchanger tube bundles
E2Accumulation of the impuritiesE5Explosion hazard
E3Obstructed flow of the molten saltE6Fire hazard
Table 7. Meanings of nodes denoting accident scenarios in Figure 10.
Table 7. Meanings of nodes denoting accident scenarios in Figure 10.
EquipmentAccident Scenarios
NodeMeaningNodeMeaning
ReceiverAS1Blockage of the receiverAS3Fire
AS2Leakage of the receiver
Salt pipingPS1Blockage of the salt pipingPS3Leakage of the salt piping
PS2Turbulence of the salt pipingPS4Fire
Salt tankTS1Leakage of the salt tankTS3Fire
TS2Failure of the salt tank foundationTS4Explosion
Heat exchangerES1Blockage of the heat exchangerES4Explosion
ES2Turbulence of the heat exchangerES5Fire
ES3Leakage of the heat exchanger
Table 8. Meanings of nodes denoting response measures in Figure 10.
Table 8. Meanings of nodes denoting response measures in Figure 10.
EquipmentResponse Measures
NodeMeaningNodeMeaning
ReceiverAR1Response measuresAR11Heliostats tracking
AR12Routine cleaning
AR2AR21Measures of the leakage prevention
AR22Emergency shutdown
AR3AR31Measures of the firefighting
Salt pipingPR1Response measuresPR11Measures of the heating trace
PR2PR21Adjusting valve
PR3PR31Start backup
PR32Measures of the leakage prevention
PR4PR41Emergency shutdown
PR42Measures of the firefighting
Salt tankTR1TR11Transfer of molten salt
TR12Emergency shutdown
TR2TR21Prevention measures of leakage
TR3TR31Measures of the freighting
TR32Emergency shutdown
TR4TR41Set up isolation zone
Heat exchangerER1ER11Measures of the heating trace
ER12Routine cleaning
ER2ER21Adjusting valve
ER3ER31Prevention measures of leakage
ER32Emergency shutdown
ER4ER41Set up isolation zone
ER5ER51Measures of the firefighting
Table 9. Weights of five experts and their personal information.
Table 9. Weights of five experts and their personal information.
No.Job TitleWorking YearsEducation LevelFamiliarityWeighted ValuesWeighting Factor
E1Senior executive15–28PhDQuite familiar360.273
E2Professor10–15PhDVery familiar360.273
E3Engineer3–7PhDModerately familiar260.197
E4Worker<3BachelorVery familiar200.152
E5Student<3MasterModerately familiar140.106
Table 10. Expert opinions on likelihood of node AO4.
Table 10. Expert opinions on likelihood of node AO4.
NodeExpertJudgmentIT2FNs
AO4E1M((0.3, 0.5, 0.5, 0.7; 1, 1), (0.4, 0.5, 0.5, 0.6; 0.9, 0.9))
E2MH((0.5, 0.7, 0.7, 0.9; 1, 1), (0.6, 0.7, 0.7, 0.8; 0.9, 0.9))
E3MH((0.5, 0.7, 0.7, 0.9; 1, 1), (0.6, 0.7, 0.7, 0.8; 0.9, 0.9))
E4M((0.3, 0.5, 0.5, 0.7; 1, 1), (0.4, 0.5, 0.5, 0.6; 0.9, 0.9))
E5M((0.3, 0.5, 0.5, 0.7; 1, 1), (0.4, 0.5, 0.5, 0.6; 0.9, 0.9))
Table 11. Pairwise comparison for criteria by each expert.
Table 11. Pairwise comparison for criteria by each expert.
ExpertLinguistic VectorCriterion
AO1AO2AO3AO4
E1Best (AO1)-to-others CEIVSISIMPI
Others-to-worst (AO2) VSICEIMIMPI
E2Best (AO1)-to-others CEIMISPIMPI
Others-to-worst (AO2) SPICEIWIMI
E3Best (AO1)-to-others CEIMIWIMPI
Others-to-worst (AO4) MPIWIMICEI
E4Best (AO3)-to-others WISPICEIMI
Others-to-worst (AO2)SICEISPIMPI
E5Best (AO1)-to-others CEIVSIWISI
Others-to-worst (AO2) VSICEIMPIMI
Table 12. Probability distribution over “AO-1” for parent nodes.
Table 12. Probability distribution over “AO-1” for parent nodes.
s = ys = n
P (AO-1 = y|comp = s)
P (AO-1 = n|comp = s)
0.87360.296
0.12740.705
Table 13. Probability distribution over “AO-1” for the leaky node.
Table 13. Probability distribution over “AO-1” for the leaky node.
s = ys = n
P (AO-1 = y|comp = s)
P (AO-1 = n|comp = s)
0.71361.5789
0.28640.8211
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Li, T.; Wu, W.; Li, X.; Li, Y.; Gong, X.; Zhang, S.; Ma, R.; Liu, X.; Zou, M. A Hybrid Approach Combining Scenario Deduction and Type-2 Fuzzy Set-Based Bayesian Network for Failure Risk Assessment in Solar Tower Power Plants. Sustainability 2025, 17, 4774. https://doi.org/10.3390/su17114774

AMA Style

Li T, Wu W, Li X, Li Y, Gong X, Zhang S, Ma R, Liu X, Zou M. A Hybrid Approach Combining Scenario Deduction and Type-2 Fuzzy Set-Based Bayesian Network for Failure Risk Assessment in Solar Tower Power Plants. Sustainability. 2025; 17(11):4774. https://doi.org/10.3390/su17114774

Chicago/Turabian Style

Li, Tao, Wei Wu, Xiufeng Li, Yongquan Li, Xueru Gong, Shuai Zhang, Ruijiao Ma, Xiaowei Liu, and Meng Zou. 2025. "A Hybrid Approach Combining Scenario Deduction and Type-2 Fuzzy Set-Based Bayesian Network for Failure Risk Assessment in Solar Tower Power Plants" Sustainability 17, no. 11: 4774. https://doi.org/10.3390/su17114774

APA Style

Li, T., Wu, W., Li, X., Li, Y., Gong, X., Zhang, S., Ma, R., Liu, X., & Zou, M. (2025). A Hybrid Approach Combining Scenario Deduction and Type-2 Fuzzy Set-Based Bayesian Network for Failure Risk Assessment in Solar Tower Power Plants. Sustainability, 17(11), 4774. https://doi.org/10.3390/su17114774

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop