Article

Critical Behavioral Risk Factors among Principal Participants in the Chinese Construction Industry

1
School of Construction Management and Real Estate, Chongqing University, Chongqing 400045, China
2
Construction Economics and Management Research Center, Chongqing University, Chongqing 400045, China
3
International Research Center for Sustainable Built Environment, Chongqing University, Chongqing 400045, China
*
Author to whom correspondence should be addressed.
Sustainability 2018, 10(9), 3158; https://doi.org/10.3390/su10093158
Submission received: 23 July 2018 / Revised: 22 August 2018 / Accepted: 30 August 2018 / Published: 4 September 2018

Abstract

:
The main participants in construction projects are the client, contractors, material suppliers, and consultants such as the project supervisor. They play the most important roles in implementing construction projects, and their behavior has a significant impact on the project’s performance. Because each participant has their own particular interests, by virtue of proprietary information advantage, each individual participant is driven to achieve maximum benefit, which can result in improper behavior with respect to each other. The risk of this resulting in moral hazard and adverse selection based on information asymmetry is called behavioral risk among principal construction participants. Behavior is affected by various risk factors; successful implementation of construction projects depends on effective management of the key risk factors. This paper identifies and ranks the critical behavioral risk factors from the perspective of principal construction participants in the Chinese construction industry. The data used for analysis is based on an interview and questionnaire survey. Factor analysis is conducted with the assistance of SPSS17.0. Forty-one potential behavioral risk factors are identified, with 30 of those being critical, including “client changes project objective or investment direction”, “designer uses technological capability advantage to obtain profit”, and others. These findings contribute to the understanding of risk management in the construction industry in China. They also serve as a useful reference for further studies on the subject.

1. Introduction

Construction project participants include the client, contractors, material suppliers, the supervisor, and so on, with these representing the most active roles in construction projects. Project participants’ behavior will have a significant impact on project performance [1]. While each participant has their own particular interests, each individual participant is driven by achieving maximum benefit, which can result in improper behavior towards each other. Barnes pointed out that human risk factors in project management should be taken seriously, and behavioral factors in project management play an increasingly important role [2]. For human risk factors, some of these are due to the objective conditions or capability of participants caused by information asymmetry, such as “contractor’s poor technical capability” or “poor management capability”; for the rest of them, due to inconsistency with regard to the target of maximizing benefit between the owner (the principal) and the contractor and supervisor (agents), in order to achieve maximum benefit, the agents would be willing to take action that is not of benefit to the principal, leading to loss of profits by virtue of their proprietary information advantage, such as “client changes project objection or invest direction”, “designer uses technological capabilities advantage to obtain profit”, and so on. The risk of moral hazard and adverse selection based on information asymmetry can be considered behavioral risks for principal participants [3].
Therefore, human risk can be divided into non-malicious factors and malicious factors. Non-malicious factors are mainly caused by non-subjective intention of participants, meaning that the risks result from limitations in terms of capability, resources or hardware of humans, rather than malicious intent. Malicious factors are caused by improper actions taken by participants in order to maximize their own interests. The behavioral risk of principal participants in this article was defined as malicious action taken by project participants [4]. Behavioral risk of principal participants is a component of basic risk, and exists in the behavior of the project participants; and the risk results directly affect the whole project subject group. Therefore, studying and reducing the behavioral risk factors of the principal participants is a prerequisite to achieving a “win-win” or “multi-win” situation [5]. Although there is a lot of research on human risk in construction projects, non-malicious and malicious factors are often considered synthetically, or only a certain kind of malicious factor is studied. There is no systematic identification and analysis of malicious factors, making it unable to provide effective guidance for engineering practice.
This research takes China as an example in order to systematically identify the behavioral risks of the principal participants in construction projects and effectively address this gap in knowledge. Due to the particularity of China’s existing institutional environment, China is in the stage of high-speed development exhibited by developing countries; the Chinese construction market is not yet perfect. Additionally, the educational backgrounds of participants and the overall quality of their contribution is uneven. In fact, the percentage of construction participants in China having a bachelor’s degree or higher is very low [6,7]. Hence, the probability of the behavioral risk among principal construction participants in China is very high. To the best of the authors’ knowledge, little effort has been devoted in research or practice to systematically identifying and managing behavioral risk in the Chinese construction industry, and construction activities in China are exposed to many risks which may be partly—if not completely—neglected, and without proper management. The Chinese construction industry is an important component of the global construction market. Furthermore, the Chinese market is in a special phase of rapid development, which makes it different in many respects, including with regard to participants’ poor education and the uneven level of quality, as well as the imperfection of laws and regulations. Improper behavior by principal participants has become the primary reason for the failure of construction projects. Thus, it is both meaningful and necessary to conduct research on the Chinese construction market, and this will be of benefit to the global construction industry.
To ensure the implementation of construction projects, the identification of risk factors is the first and the most important target. The purpose of this paper is to identify and explore the various components of behavioral risk factors of principal participants in the Chinese construction industry using a factor-analysis approach. The approach was designed to identify the risk factors that affect the completion of the project with regard to its time, its cost, and its specifications. Once the critical behavioral risk factors of principal participants in the Chinese construction industry have been identified, the following steps of evaluation and assessment of risks can be undertaken, and the research findings can be of benefit to risk management in construction project. Therefore, the identification of critical behavioral risk factors of principal participants is not only of theoretical significance, but also has important practical value.

2. A Review on the Existing Study for Behavioral Risk

2.1. Human Risk in the Construction Industry

Risk is defined as “the potential for unwanted or negative consequences of an event or activity” [8], a combination of hazard and exposure. To ensure the implementation of a construction project, identifying risk factors is the first and the most important target. Research on risk of construction projects has a long history, and there have been many useful research methods for analyzing construction project risks, the findings of which can offer good guidance and make important contributions to the Chinese construction industry [9,10,11,12]. However, most of the risk analysis is limited to analyzing non-human factors. Research on human risks appears little in existing studies. In construction projects, in practice, most project losses are due to human risks, which affects risk analysis and evaluation and risk control. Identifying human risk is an important role in construction project risk management. In recent years, scholars have transferred the research focus to human risk factors [2,13,14,15].
Many scholars believe that a large proportion of human risk is dependent on the attitudes of people. Teo and Loosemore suggested that attitudes, subjective norms and perceived behavior control influence behavioral intentions, which in turn determine the likelihood of behavior occurring [16]. The attitude is based on an individual’s positive or negative evaluation of the consequences of a particular type of behavior, as well as personal beliefs or knowledge about those consequences. Therefore, even identical situations, a variety of risk attitudes could be adopted, and these would lead to different actual behavior and consequences. Shen proved that factors influencing the formation of risk perception include educational background, practical experience, an individual’s cognitive characteristics, the availability of information, peer group influence, etc. [17]. These factors will indirectly change the behavior of the principal participants through their risk attitude, and they will ultimately affect the efficiency of construction projects. Therefore, human risk plays an important role in the risk management of construction projects.
Table 1 summarizes the identification of human risks in construction projects based on some existing studies. From the table, it can be seen that human risk in construction projects can be divided into three levels, namely, individual factors, project team factors and organizational factors [15]. The individual’s ability, knowledge, skills and other factors, as well as the level of project management, will directly affect the construction project, and the rules and regulations of the organization will form constraints on individuals and the project team. Construction projects include government, owners, contractors, designers, consultants and many other participants; their risk attitudes and behaviors will have an impact on the project [17,18]. In addition, construction projects also involve human risk in the phases of design, implementation and operation, as well as human risk with respect to safety management, quality management, time management and so on [19,20,21,22]. However, these human risk factors include non-malicious factors, such as personal abilities, rules and regulations, as well as malicious factors, such as delaying the construction period and arbitrarily changing the design. At present, no scholars have identified malicious human risks.

2.2. Behavioral Risk in the Construction Industry

For human risk factors, a part of them are due to the objective conditions or capabilities of participants caused by information symmetry, such as the contractor’s technical capability; however, a part of risk factors is still caused by information asymmetry, and could lead to moral hazard and adverse selection in order to obtain more benefit. The risk factors based on information asymmetry are referred to as the behavioral risk of the principal participants [23,24,25].
Yang is the first person to have proposed the concept of the behavioral risk factors of principal participants. He divided construction risk into objective event risk and subjective behavioral risk, and analyzed the importance and necessity of research on the behavior risk of principal participants; this finding brought fresh impetus to project risk research [5]. However, Yang’s study did not identify the specific behavioral risks for project participants or describe how to prevent such risks.
Sha et al. analyzed the principal-agent relationship and problems between participating subjects from the perspective of information economics, and postulated that the main reason for project risk was the fact that information asymmetry induces the opportunism behavior; namely, that adverse selection and moral hazard are the causes of the anomie of project participants’ subjective behavior [13]. Ren et al. analyzed the behavior of participants in projects and analyzed agency relationships between project participants and existing problems from an information economics perspective. They believed that opportunistic behavior was induced by information asymmetry [14]. That is to say, adverse selection and moral hazard are the reasons for project participants’ misconduct, leading to project risk. Their research gave an economic explanation for the behavior risk of a project’s principal participants.
Adams pointed out that traditional project risk management research generally implies the assumption of the completeness of information; that is to say, that no problems related to information asymmetry exist between principal participants. In fact, information asymmetry between principal participants is a common phenomenon in the real construction market. With respect to the competitive bidding process for projects [26], Adams further proposed the risk of adverse selection faced by the owner due to the bidders’ cheating actions. After the owner has determined the contractor, he faces behavior risk in terms of the contractor potentially making use of their information advantage to harm the owner’s interests. In response to Adams’ research, with regard to the problem of asymmetric information in projects, some scholars introduced principal agent theory into the analysis of principal participants’ behavior risk. Au and Chan discussed the relationship between contractors’ risk perceptions, attitudes and behaviors, concluding that risk behaviors of principal participants in construction projects have a high degree of correlation with their risk perception and risk attitude [27]. Winch analyzed the reasons for leading moral risks in projects and suggested relevant measures based on principal agent theory, including designing an incentive mechanism in contracts, price adjustment mechanisms, conflict resolution mechanisms, and so on [28].
Xiang and Kong used the Delphi expert interview method to extract 10 behavioral risk factors for principal participants, classified into client, contractor and supervisor, the 10 discussed risk factors were “Lack of management ability”, “Poor funding ability”, “Incomplete project plan”, and “Default leading to cannot complete the contract” with respect to the client; “Poor management ability”, “Poor technological ability”, and “Poor goodwill” with respect to contractors; and “Poor management and technological ability”, “Poor ethics” and “Poor sense of service” with respect to the supervisor. However, these behavior risks mainly refer to the participants’ ability and their management skill. They do not reflect the participants’ moral behavior [4].
Shi investigated risk allocation and moral hazard in construction contracts driven by the owners, as well as the contractors. It was shown that the moral hazard produced by the owner, when the excessive cost overruns caused by the owner’s indulgence are transferred to the contractor, may trigger moral hazard in the contractor, and they suggested an optimal risk allocation scheme between the owner and the contractor in developing countries, which could obviate the double moral hazard issue and enhance project efficiency [29]. Jian (2010) pointed out that both project owners and contractors probably have moral hazard during the period of project construction, establishing a bilateral moral hazard model while applying the principal agent theory. The model analysis shows that when information is asymmetrical, applying a linear contract mechanism of cost plus incentive fee is efficient, but that risk-neutral owners and contractors will only implement their second-best level of effort [30]. Liu found that the single low-price competition in the construction tender market leads to serious adverse selection and moral hazard behavior in bidding firms, and they systematically analyzed the evaluation method of the lowest-price-wins bidding policy, which is the fundamental cause of adverse selection and moral hazard problems in the Chinese construction market [31].
From the above discussion, it appears that little study exists on the behavior risks of the principal participants in Chinese construction. Nevertheless, the Chinese construction industry is a major construction market globally. Furthermore, the Chinese construction market is different from other construction industries in many respects, including the participants’ poor education and their uneven level of quality, as well as the imperfection of the laws and regulations [32,33,34,35]. Thus, it is both important and necessary to extract the behavioral risks among principal participants in Chinese construction.

2.3. Method of Identifying Risk Factors

The method used for risk identification has a significant impact on the accuracy of the risk identification results. Choosing the right identification method helps us to correctly understand the behavioral risks of the main participants in a construction project. The general methods for risk identification in construction projects include Delphi, brainstorming, checklist, fault tree, flow chart, SWOT, WBS-RBS, questionnaire survey, literature research, expert interview, and so on [36,37,38,39,40,41,42,43,44]. Table 2 shows the general methods commonly used for risk identification in construction projects. Literature research is the most common method of risk identification in construction projects; however, limited by the research data, the identification results often have very obvious limitations. Therefore, this paper will use the literature research method and the expert interview method to identify the behavior risk factors of the main participants of construction projects.
Determining weights is an important step in identifying risk factors. At present, the methods for determining the weighting of risk factors for construction projects can be roughly divided into two categories: subjective empowerment and objective empowerment. The subjective empowerment method is based on the experience of experts to judge the relative importance of each risk factor relative to the purpose of evaluation, for example, the AHP method and the Delphi method. The objective weighting method is an automatic weighting method for risk factors based on certain rules, such as principal component analysis, factor analysis and the entropy weight method. The weighting coefficient of the risk factor is determined by the subjective weighting method, which reflects the intentions of the decision-maker, but the decision or evaluation result is highly subjective. The results when using objective empowerment methods to determine the weighting coefficient of risk factors have a strong mathematical basis, but do not consider the intentions of decision-makers [45,46,47,48,49]. Table 3 shows the general weighting determination methods in construction projects. This paper will use principal component analysis to determine the weighting of each behavioral risk factor, because principal component analysis can eliminate the correlation between risk factors. In addition, the weighting of the principal components reflects the amount of the original data in the total amount of information, and the weighting is objective and reasonable [50,51].

3. Methodology

This paper aims to identify the behavioral risk factors of the Chinese construction industry. A questionnaire survey method was used in the research. The questionnaire was designed on the basis of comprehensive literature research and expert interviews, and was distributed to 200 Chinese construction industry practitioners from 10 provinces, including officials from government departments, professionals from design institutes, construction clients, building companies, supervision units, and research institutes. A statistical analysis of the effective survey data from the 150 returned questionnaires was conducted, and 30 critical behavioral risk factors were identified.
After a comprehensive literature review and expert interview, a questionnaire including a total of 41 potential behavioral risk factors related to principal participants in construction projects was compiled, with the behavioral risk factors matched to different principal participants and different project stages. The construction project life cycle was divided into four stages—the investment decision stage, the tendering and bidding stage, the construction stage and the completion and acceptance stage—and the magnitude of each potential risk factor was evaluated using a 5-point scale. Then, the questionnaire was distributed, and survey data was collected. With the assistance of SPSS17.0, 32 risk factors were extracted on the basis of principal component analysis, but 2 of them were rejected by convergent validity. Finally, 30 critical behavioral risk factors of principal participants were identified and ranked in importance.

4. Research Process

4.1. Questionnaire Design

4.1.1. Literature Research to Identify Potential Risk Factors

Based on the examination of the existing studies [17,19,20,52], 22 behavioral risk factors of principal participants are listed in Table 4.

4.1.2. Expert Interview to Identify Potential Risk Factors

On the basis of the 22 summarized risk factors identified in the literature review, 10 interview discussions were conducted with relevant personnel with rich backgrounds of work experience, and top experts in this field. The 15 experts consisted of the following: professors who have done research on construction project risk for many years from universities belonging to Project 985 in China; project managers with a rich experience from the China National Building Corporation and its subsidiaries, and China National Railway Corporation and its subsidiaries (which are in range of word 500 top corporations); and engineers from famous real estate development companies ranked in the top 10 in China, as well as some supervisor companies. The experts first listed all of the possible or existing behavioral risk factors of principal participants in construction projects, and then the collected risk factors were discussed by all the experts. Each time that new risk factors were determined on the basis of the discussion, the new factors would be discussed again. Eventually, after several rounds of discussion, 19 risk factors were added to the above 22 behavioral risk factors. The 19 risk factors are listed in Table 5.
It should be noted that the risk “use technological capability advantage to obtain profit”, related to the designer, refers to the fact that when participants are familiar with their business and have years of rich work experience, there exists an information asymmetry between different stakeholders, such that they can obtain unfair advantage with the help of their own information superiority.

4.1.3. Questionnaire Design

In this paper, each different behavioral risk of principal participants was identified in accordance with the project life cycle. The project life cycle was divided into four stages: the investment decision stage, the tendering and bidding stage, the construction stage, and the completion and acceptance stage. For the principal participants of construction projects, we mainly discussed risks from the client, construction contractor and supervisor; in the investment decision stage, we also discussed risks from designer, who is an important participant in the first stage; in the tendering and bidding stage, we also discussed potential risks from the reviewing experts and third parties; in the construction stage, we also took risks from material and equipment suppliers into account; thus, a behavioral risk factors table covering 41 risk factors was concluded.
After the potential 41 behavioral risk factors were listed, a questionnaire was administered. The questionnaire consisted of two sections: Section 1 solicited general information about the respondents, and Section 2 contained a total of 41 behavioral risks associated with the principal participants in construction projects.
The total of 41 risk factors consists of the sum of Table 1 and Table 2, these risk factors are categorized into 4 parts in terms of the project life cycle, with 7 related to the investment decision stage, 9 related to the tendering and bidding stage, 20 related to the construction stage, and 5 related to the completion and acceptance stage. On the other hand, the 41 risks could be categorized into 5 parts, on the basis of their relevant principal participants, with 16 related to the client, 11 related to the construction contractor, 5 related to the supervisor, 3 related to third parties, 3 related to the designer and 3 related to suppliers.
All 41 risk factors included in the questionnaire were set on a five-point scale (5 = extremely important, 4 = very important, 3 = important, 2 = somewhat important, 1 = not important), and these scales were used to conduct factor analysis.

4.2. Sample Size

Although it is difficult to know the exact population size, it is still necessary to determine the sample size in order to ensure the validity of the survey results. Cochran suggested a formula to calculate the appropriate sample size when the data collection takes place on the basis of scaled or ordinal variables [53], as in this study. Accordingly, the minimum sample size required by this formula is 143.
Questionnaires were distributed to 200 construction practitioners in China from 10 provinces, including officials from government departments, professionals from design institutes, construction clients, building companies, supervision units, and research institutes. Of the 200 distributed questionnaires, 174 were returned, of which 150 were considered effective responses for analysis. The number of valid questionnaires meets the minimum sample size requirement. The recovery rate of the questionnaire was calculated to be 75%, which is acceptable according to the theory of Moser and Kalton [54].

4.3. Sample Composition

The respondents were practitioners in the Chinese construction industry. They had an average of 7.12 years’ work experience in construction-related sectors; 32.67% of them worked in construction companies, and another 32.00% worked in building companies; all of them had received professional education. More details of the respondent profiles are presented in Table 6. The respondents’ long work experience, solid educational background and multifaceted involvement in diverse construction-related units imply that the respondents have adequate knowledge of construction project management and the associated risks.

4.4. Questionnaire Analysis

4.4.1. Preliminary Analysis

Factor analysis was initially performed on all 41 variables related to risk factors. The Kaiser–Mayer–Olkin (KMO) test and Bartlett’s test of sphericity were used to check suitability of the factor analysis. Acceptable values of the KMO test should be greater than 0.5, and determine the adequacy of the sample, while Bartlett’s test of sphericity can ensure that the correlation matrix is an identity matrix [55]. The result of the KMO test was 0.835 and Bartlett’s test of sphericity was high, at 2195.992 (associated with a probability value of 0.000), as shown in Table 7. Both tests showed that the variables were suitable for factor analysis.

4.4.2. Factor Extraction

Factor loadings are the correlations of the variables with the factor. High factor loading implies that the factors and variables are critical [56]. In the present study, a sample size of 150 subject to a minimum factor loading of 0.563 was used for factor analysis. To extract critical risk factors, both principal component analysis and correlation value between risk factors approach were used. For the principal component analysis, all of the factors extracted should account for at least 60% of total variance [57], Table 8 shows that the percentage of total variance explained by the 12 extracted components is 69.721%. With respect to our approach to the correlation value between risk factors, factors with relatively high absolute correlation values were retained, and those with relatively low absolute correlation values were ignored [58]. The criterion used in this paper was that for the first component, absolute values for a factor greater than 0.5 should be retained, and for the other 11 components, the maximum absolute value is retained. Table 9 shows that 32 variables were extracted under the above criteria (the extracted variables are marked with *).

4.4.3. Internal Consistency Analysis

Internal consistency reliability is a statement of the stability of individual measurement items across replications from the same source of information. To ensure the reliability of each factor, Cronbach’s coefficient alpha (α) was used to test the internal consistency among the items included in each factor. Nunnally has suggested that a minimum of 0.7 is sufficient [59]. Factor reliability was measured by calculating Cronbach’s α for all factors. The results of factor analysis showed that the final 12 components accounted for 69.721% of total variance explained. Table 7 shows that α value for the 41 variables ranged from 0.918 to 0.923. The α values were at an acceptable level, indicating that all factors were reliable.

4.4.4. Content Validity

Content validity defines how representative and comprehensive the items were in presenting the hypothesis. It is assessed by examining the process that was used in generating the scale item [60]. As the questionnaire was designed based on a literature review and the opinions of interviewed experts, the content validity of the critical risk factors needs be proved. It is believed that the 41 risks listed in the survey were highly comprehensive in terms of representing almost all risks that might occur in construction projects in China.

4.4.5. Convergent Validity

In this study, we followed Straub’s processes for validating instruments in order to test construct validity in terms of convergent and discriminate validity [61]. According to Peter, convergent validity is related to the extent to which different scale items that are assumed to represent a construct converge on the same construct [62]. Convergent validity is useful for measuring the agreement between multiple attempts to measure the same concepts. The item-to-total correlation indicates the correlation of each item to the sum of the remaining items, which can be used for convergent validity. Variables with an item-to-total correlation score lower than 0.4 were removed, as suggested by Park and Kim [63]. Table 10 shows that of the 32 extracted risk factors, 30 factors were retained, with item-to-total correlations ranging from 0.412 to 0.629. The other 2 variables ((CD6) Malicious withholding of wages, leading to the project interruption; and (DA3) Increase the workload of the contractor) were rejected because they had values lower than 0.4 (the retained variables are marked with *).

5. Discussion of the Findings

The findings of the above analysis suggest that the behavior risks among the principal participants in the Chinese construction industry are largely concerned with participants’ moral behaviors. Behavior risks have also been researched in other studies, but these have been more related to management skill and capability. This is well appreciated by Barnes [2].

5.1. Ranking of the Critical Behavioral Risk Factors

To manage behavioral risk effectively, it is important to rank the importance of each risk factor; this is the premise of behavioral risk management. The relative significance among the 30 selected behavioral risks is analyzed by establishing a ranking list among them. The ranking list is generated by calculating the mean score (MS).
Chan and Kumaraswamy adopted the “mean score” method to establish the relative importance index of behavioral risk factors as perceived by the clients, contractors and supervisor, respectively [64]. The data collected from the current questionnaire survey was also analyzed using the same technique. A five-point Likert scale (1 = least important and 5 = most important) was used to calculate the mean score for each risk factor, which was then used to determine its relative ranking in descending order of importance. These rankings made it possible to triangulate the relative importance of the risk factors; the MS value refers to the importance index of the risk factors. The mean score (MS) for each risk factor was computed using the following formula:
M S = ( f × s ) N ( 1 M S 5 )
where s is the score given to each risk factor by the respondents, ranging from 1 to 5 (1 = least important and 5 = most important); f is the frequency of each rating (1–5) for each risk factor; and N is the total number of responses concerning a particular risk factor.
Table 11 presents the degree of importance (i.e., the MS value) assigned to the 30 critical risk factors for the overall project, extracted from the factor analysis.
The key risks related to project stakeholders are discussed to identify appropriate strategies that the stakeholders should take to manage their relevant risks, as elaborated below.

5.2. Discussion

5.2.1. Critical Behavioral Risk Related to the Client

The identified behavioral risks related to the client consist of 11 factors: (1) Change project objectives or investment direction (investment decision stage), ranked 14th with an MS value of 3.673; (2) Evil intention to make unreasonable requests, ranked 27th; (3) Choose a worse designer because of tacit collusion, ranked 7th; (4) Disclose project information because of tacit collusion, ranked 5th; (5) Change project objectives or investment direction (construction stage), ranked second in the list; (6) Error guidance and nonprogrammed interference with instructions, ranked 8th; (7) Defaulting and rejection of compensation, ranked 16th; (8) Evil failure to supply equipment and raw materials in time, ranked 19th; (9) Defaulting on paying project settlement amount, ranked 22th; (10) Collude with other participants to modify the design proposal, ranked 20th; (11) Defaulting on paying project settlement amount, ranked 9th.
Changing project objective or investment direction ranked second, with a high MS value of 3.88, meaning changes in planning and fund supply. The client is the leader and fund supplier of a construction project; any client’s behavior risk is critical to the project. For most Chinese clients, time is money, and because of the high cost of capital, they expect to complete a project as quickly as possible and to realize profit as soon as possible, resulting in sudden changes in project objectives or investment direction during the implementation period. If that occurs, contractors and suppliers could suffer great loss. To solve this problem, contractors should assess a client’s financial capacity and obtain relevant statements that guarantee the progress of payments.

5.2.2. Critical Behavioral Risk Related to Contractors

Behavioral risk related to contractor consists of 9 critical risk factors: (1) Bidders ring, ranked 24th; (2) Bidding with fraudulent qualifications, ranked 23th; (3) Collude to tender or bid, ranked 6th, (4) Arbitrary intent to construct against design intent, ranked 4th; (5) Collude with other participants to modify the design proposal, ranked 10th; (6) Evil intention to require design change, ranked 17th; (7) Illegal subcontracting, ranked the third, with an MS value of 3.847; (8) Unreasonable claims, ranked 29th; (9) Malicious claims, ranked 28th.
A majority of Chinese contractors are either labor or specialist contractors, and they generally lack the managerial skills to contract large projects, if not all types of projects. Hence, the necessary qualifications to bid for construction projects are difficult for them to achieve. This problem is often solved by means of a bidders ring, bidding with fraudulent qualifications, or collusion to tender or bid, which results in poor quality of buildings or even engineering accidents.
Contractor’s illegal subcontracting is ranked third in the list. To save costs or time, multi-level contracting and illegal sub-contracting is chosen; if a subcontractor for any part of the project fails, this is a risk for the whole system. In the Chinese construction industry, contractor’s illegal subcontracting often happens; for example, the main culprit of the heavy “11.15” fire accident in Shanghai, China was the contractor’s illegal subcontracting.

5.2.3. Critical Behavioral Risk Related to the Designer

Behavioral risk related to the designer consists of 3 critical risk factors: (1) Use technological capability advantage to obtain profit, ranked 13th; (2) Evil intention to sub package, ranked the first, with the highest MS value of 3.913; (3) Arbitrary intent to make a design change against client’s intention, ranked 10th.
In the Chinese construction industry, to obtain more profit or to save time in order to contract more work, designers are often driven to deliver sub packages to non-qualified subcontractors, or ask for rebate from the subcontractor. As the design is one of the most important guarantees for the safety of the project, this risk factor should be paid attention.
To obtain more illegal profits, the designer will collude with the contractor and make design changes without permission from the owner, meaning that their own interests are met, but at the expense of seriously damaging the interests of the owner. In the long run, designers will gradually lose more customers because of the credibility problem, and will eventually be eliminated by fierce market competition.

5.2.4. Critical Behavioral Risk Related to the Supervisor

Behavioral risk related to the supervisor consists of 5 critical risk factors: (1) Error guidance and nonprogrammed interference with instruction, ranked 18th; (2) Obtain unreasonable profit because of collusion with contractors, ranked 12th with an MS value of 3.693; (3) Intent to make trouble for suppliers, contractors and so on, ranked 25th; (4) Go places without notice, ranked 30th; (5) Obtain unreasonable profit because of collusion with contractors, ranked 26th.
The most common behavioral risk for supervisors is Obtain unreasonable profit because of collusion with contractors. If this risk happens, the supervisor will shelter contractors’ unethical behavior, resulting in great loss to the project. However, in order to win the owner’s favor, the developer may support the owner in an unprincipled way, negating and blaming contractors’ claims and other reasonable requirements, causing contractor dissatisfaction and leading to many disputes. On the one hand, the contractors do not trust the developer and will not cooperate with their supervision work; on the other hand, this will affect the enthusiasm of the contractors. This is a big risk for both owners and developers.

5.2.5. Critical Behavioral Risk Related to Suppliers

Behavioral risk related to suppliers consists of 2 critical risk factors: (1) Evil intention to raise the price of equipment and raw materials, ranked 21th; (2) Evil lag in supplying equipment and raw materials, ranked 11th. The quality of suppliers has a direct impact on the duration, quality and cost of the project. Cost control is often a very important assessment index for construction projects, and the cost of materials is a large part of the cost of construction projects. In practice, suppliers deliberately delay the time and reduce the quality of materials in order to pursue their own interests, seriously damaging the interests of owners and contractors. For example, the contract promises that material will be supplied at a certain point; when that time arrives, in order to obtain more profit or pursue other own interests, the supplier would look for all sorts of reasons to delay supplying the material. Therefore, research on the selection and optimization of suppliers is very important.

5.3. Comparison between the Behavior Risks from the Perspective of Different Participants

There are two cases from China to illustrate the importance of critical behavioral risk in the Chinese construction industry.
The first one is the “11.15” heavy fire accident in Shanghai, resulting in the deaths of 58 people, and 71 injured, along with a direct economic loss of 158 million yuan.
The accident was due to participants’ behavioral risk: firstly, the client disclosed project information because of tacit collusion; secondly, contractor bidding with fraudulent qualifications and a bidders ring; thirdly, the supervisor obtained unreasonable profit because of collusion with contractors.
The second case happened in 1999, a walking bridge (rainbow bridge) at Qi Jiang, Chong Qing collapsed completely and suddenly, leading to 40 people dead and great economic losses of about 6.31 million Yuan. The essential reason of the accident was collusion of government, designer, construction contractor and supervisor. There were 4 participants who took behavioral risk action leading to the occurrence of the accident: (1) related to the client (this project was a government project; thus, the government was the client): government chose a worse designer because of tacit collusion, and government disclosed project information because of tacit collusion; (2) related to the contractor: bidders ring, bidding with fraudulent qualifications, illegal subcontracting, arbitrary intent to construct against design intent; (3) related to the designer: evil intention to sub package; and (4) related to the supervisor: obtain unreasonable profit because of collusion with contractors.

6. Conclusions and Future

Construction project failure is influenced and determined by many behavioral factors by principal participants. It is neither practical nor necessary to identify and understand all the related factors in order to minimize their influence on construction project. It is a smarter way to identify some critical factors in order to reduce the risk of project failure.
In this paper, we identified 41 behavioral risk factors with the potential to affect successful completion of projects as a result of principal participants’ behavior. Through principal component analysis, 32 factors were extracted based on a correlation value criterion. Finally, however, there were only 30 critical risk factors retained, with corrected item-total correlation values above 0.400, which were deemed to be critical in influencing principal participants’ behavior in construction projects. Finally, those 30 critical factors were ranked by MS value. These findings enrich the theoretical research on risk management of construction projects in China, providing additional guidance for project managers with regard to risk management, not only identifying key points of risk management in construction projects for principal participants, but also serving as a useful reference for further studies on methods to manage these risks.
It is important to note that this paper provides only the critical behavioral risk factors of principal participants in construction projects. Further studies will need to explore how to respond to and manage them. Firstly, the behavioral risk should be assessed and evaluated; following that, further investigation should consider the interrelationships between the identified factors and the dynamic transfer process during the whole life cycle of a construction project; finally, combined with case studies in the Chinese construction industry, a burden-sharing model for the principal participants could be established, which would contribute to human-risk management in construction projects.

Author Contributions

P.X., F.J., X.L. designed the study; P.X. wrote the paper; F.J. and X.L. collected and analyzed the data; P.X. controlled quality assurance.

Funding

The work described in this study is also fully supported by a joint grant from Project No. 2017CDJSK03XK19 and No. 106112016CDJSK03JD01 supported by the Fundamental Research Funds for the Central Universities, and the Project No. CYS17026 of Graduate Student Research Innovation Project of Chongqing University. Any opinions, findings, and conclusions or recommendations expressed in this material are those of the authors.

Conflicts of Interest

The authors declare no conflicts of interest.

References

  1. Xiang, P.C.; Ren, H.; Zhong, Y.; Feng, Y.B. The Behavior Game Analysis for participants in construction project Based on The Theory of Information Asymmetries. J. Chongqing Univ. 2007, 30, 144–151. [Google Scholar]
  2. Barnes, M. A Long Terra View of Project Management—Its Past and Its Likely Future. In Proceedings of the 16th World Congress on Project Management, Berlin, Germany, 20–24 May 2002; pp. 68–78. [Google Scholar]
  3. Xiang, P.C.; Zhou, J.; Zhou, X.Y.; Ye, K.H. Construction Project Risk Management Based on the View of Asymmetric Information. J. Constr. Eng. Manag. 2012, 138, 1303–1311. [Google Scholar] [CrossRef]
  4. Xiang, P.C.; Kong, D.P. A New View of Researching on Construction Project Risk—The Behavioral Risk of Principal Participants in Construction Project. Constr. Econ. 2010, 3, 72–75. [Google Scholar]
  5. Yang, B.J. Several research points about international construction project risk management. Technol. Econ. 2003, 12, 41–48. [Google Scholar]
  6. Wang, N. The role of the construction industry in China’s sustainable urban development. Habitat Int. 2014, 44, 442–450. [Google Scholar] [CrossRef]
  7. Li, L.H. Balancing Rural and Urban Development: Applying Coordinated Urban–Rural Development (CURD) Strategy to Achieve Sustainable Urbanisation in China. Sustainability 2017, 9, 1948. [Google Scholar] [CrossRef]
  8. Rowe, W.D. An Anatomy of Risk; Wiley: Hoboken, NY, USA, 1977; pp. 387–412. [Google Scholar]
  9. Perry, J.G. Risk management—An approach for project managers. Int. J. Proj. Manag. 1986, 4, 211–216. [Google Scholar] [CrossRef]
  10. Akintoye, A.S.; MacLeod, M.J. Risk Analysis and management in construction. Int. J. Proj. Manag. 1997, 15, 31–38. [Google Scholar] [CrossRef]
  11. Dobrovolskienė, N.; Tamošiūnienė, R. An Index to Measure Sustainability of a Business Project in the Construction Industry: Lithuanian Case. Sustainability 2015, 8, 14–28. [Google Scholar] [CrossRef]
  12. Seker, S.; Zavadskas, E. Application of Fuzzy DEMATEL Method for Analyzing Occupational Risks on Construction Sites. Sustainability 2017, 9, 2083. [Google Scholar] [CrossRef]
  13. Sha, K.X.; Song, T.; Zhao, J.K. See the rectifying and standardizing the construction market through asymmetric information. Constr. Econ. 2004, 1, 82–85. [Google Scholar]
  14. Ren, Y.L.; Wu, G.S.; Xu, J.; Zhang, Y. Economic Analysis of Principal Parts of Engineering Project. J. Chongqing Univ. 2004, 27, 142–145. [Google Scholar]
  15. Thevendran, V.; Mawdesley, M.J. Perception of human risk factors in construction projects: An exploratory study. Int. J. Proj. Manag. 2004, 22, 131–137. [Google Scholar] [CrossRef]
  16. Teo, M.M.M.; Loosemore, M. A theory of waste behavior in the construction industry. Constr. Manag. Econ. 2001, 19, 741–751. [Google Scholar] [CrossRef]
  17. Shen, L.Y.; Platten, A.; Deng, X.P. Role of public private partnerships to manage risks in public sector projects in Hong Kong. Int. J. Proj. Manag. 2006, 24, 587–594. [Google Scholar] [CrossRef]
  18. Zavadskas, E.K.; Turskis, Z.; Tamosaitien, J. Risk assessment of construction projects. J. Civ. Eng. Manag. 2010, 16, 33–46. [Google Scholar] [CrossRef]
  19. Ghosh, S.; Jintanapakanont, J. Identifying and assessing the critical risk factors in an underground rail project in Thailand: A factor analysis approach. Int. J. Proj. Manag. 2004, 22, 633–643. [Google Scholar] [CrossRef]
  20. Perry, J.G.; Hayes, R.W. Risk and its management in construction projects. Proc. Inst. Civ. Eng. 1985, 78, 499–521. [Google Scholar] [CrossRef]
  21. Tam, C.M.; Fung, I.W.H.; Chan, A.P.C. Study of attitude changes in people after the implementation of a new safety management system: The supervision plan. Constr. Manag. Econ. 2001, 19, 393–415. [Google Scholar] [CrossRef]
  22. Zou, P.X.W.; Zhang, G.M. Comparative study on the perception of construction safety risks in China and Australia. J. Constr. Eng. Manag. 2009, 7, 620–627. [Google Scholar] [CrossRef]
  23. Man, S.S.; Chan, A.H.; Wong, H.M. Risk-taking behaviors of Hong Kong construction workers—A thematic study. Saf. Sci. 2017, 98, 25–36. [Google Scholar] [CrossRef]
  24. Li, H.; Li, X.; Luo, X.; Siebert, J. Investigation of the causality patterns of non-helmet use behavior of construction workers. Autom. Constr. 2017, 80, 95–103. [Google Scholar] [CrossRef]
  25. Xia, N.; Wang, X.; Griffin, M.A.; Wu, C.; L, B. Do we see how they perceive risk? An integrated analysis of risk perception and its effect on workplace safety behavior. Accid. Anal. Prev. 2017, 106, 234–242. [Google Scholar] [CrossRef] [PubMed]
  26. Adams, F.G. Information asymmetry and competitive bidding in auditing. Econ. Inq. 2004, 43, 417–425. [Google Scholar] [CrossRef]
  27. Au, M.C.Y.; Chan, E.H.W. Attitudes of contractors and employers towards transfer of a time-related risk in construction contracts. In Proceedings of the Construction Research Congress, San Diego, CA, USA, 5–7 April 2005; pp. 1–13. [Google Scholar]
  28. Winch, G.M. Managing Construction Projects: An Information Processing Approach; Blackwell Science: Hoboken, NJ, USA, 2002. [Google Scholar]
  29. Shi, L.; Kobayashi, K.; Miyao, T. Risk allocation and double moral hazard in construction contract. In Proceedings of the IEEE International Conference on Systems Man and Cybernetics, Istanbul, Turkey, 10–13 October 2010; pp. 3315–3320. [Google Scholar]
  30. Jian, Y.H. Study on incentive contract mechanism of construction project under bilateral moral hazard. In Proceedings of the IEEE 17th International Conference on Industrial Engineering and Engineering Management, Xiamen, China, 3–5 September 2010; pp. 269–272. [Google Scholar]
  31. Liu, D.H.; Xu, W.J.; Li, H.Y. Moral hazard and adverse selection in Chinese construction tender market A case of Wenchuan earthquake. Disaster Prev. Manag. 2011, 20, 363–377. [Google Scholar] [CrossRef]
  32. Shen, L.Y.; Wu, G.W.C.; Ng, C.S.K. Risk assessment for construction joint ventures in China. J. Constr. Eng. Manag. 2001, 127, 76–81. [Google Scholar] [CrossRef]
  33. Li, Y.; Lu, Y.; Kwak, Y.H.; Dong, S. Developing a city-level multi-project management information system for Chinese urbanization. Int. J. Proj. Manag. 2015, 33, 510–527. [Google Scholar] [CrossRef]
  34. Xu, Y.; Chan, A.P.C.; Xia, B.; Qian, Q.K.; Liu, Y. Critical risk factors affecting the implementation of PPP waste-to-energy projects in China. Appl. Energy 2015, 158, 403–411. [Google Scholar] [CrossRef]
  35. Liu, Z.; Jiang, W.; Wu, Y.; Peng, Y. Risk Factors of Building Apartments for University Talent through the Agent Construction Mode in China: Interrelationship and Prioritization. Sustainability 2016, 8, 325. [Google Scholar] [CrossRef]
  36. Tavakolan, M.; Etemadinia, H. Fuzzy Weighted Interpretive Structural Modeling: Improved Method for Identification of Risk Interactions in Construction Projects. J. Constr. Eng. Manag. 2017, 143, 04017084. [Google Scholar] [CrossRef]
  37. Xia, N.; Zou, P.X.W.; Griffin, M.A.; Wang, X.; Zhong, R. Towards integrating construction risk management and stakeholder management: A systematic literature review and future research agendas. Int. J. Proj. Manag. 2018, 36, 701–715. [Google Scholar] [CrossRef]
  38. Osei-Kyei, R.; Chan, A.P.C. Review of studies on the Critical Success Factors for Public–Private Partnership (PPP) projects from 1990 to 2013. Int. J. Proj. Manag. 2015, 33, 1335–1346. [Google Scholar] [CrossRef]
  39. Jeelani, I.; Albert, A.; Gambatese, J.A. Why Do Construction Hazards Remain Unrecognized at the Work Interface? J. Constr. Eng. Manag. 2016, 143, 04016128. [Google Scholar] [CrossRef]
  40. Ardeshir, A.; Amiri, M.; Ghasemi, Y.; Errington, M. Risk Assessment of Construction Projects for Water Conveyance Tunnels Using Fuzzy Fault Tree Analysis. Int. J. Civ. Eng. 2014, 12, 396–412. [Google Scholar]
  41. Li, M.; Li, G.; Huang, Y.; Deng, L. Research on investment risk management of Chinese prefabricated construction projects based on a system dynamics model. Buildings 2017, 7, 83. [Google Scholar]
  42. Kasemset, C.; Wannagoat, J.; Wattanutchariya, W.; Tippayawong, K.Y. A Risk Management Framework for New Product Development: A. Case Study. Technol. Forecast. Soc. Chang. 2015, 13, 1339–1354. [Google Scholar] [CrossRef]
  43. Supriadi, L.S.R.; Latief, Y.; Susilo, B.; Rajasa, M. Development of risk-based standardized WBS (Work Breakdown Structure) for cost estimation of apartment’s project. Int. J. Civ. Eng. Technol. 2017, 8, 822–833. [Google Scholar]
  44. Asadi, S.S.; Rao, V.E. An integrated approach to a critical analysis of risk management in construction projects. Int. J. Civ. Eng. Technol. 2018, 9, 20–28. [Google Scholar]
  45. Ameyaw, E.E.; Chan, A.P.C. A Fuzzy Approach for the Allocation of Risks in Public–Private Partnership Water-Infrastructure Projects in Developing Countries. J. Infrastruct. Syst. 2016, 22, 1–13. [Google Scholar] [CrossRef]
  46. Zayed, T.; Amer, M.; Pan, J. Assessing risk and uncertainty inherent in Chinese highway projects using AHP. Int. J. Proj. Manag. 2008, 26, 408–419. [Google Scholar] [CrossRef]
  47. Ameyaw, E.E.; Chan, A.P.C.; Owusumanu, D.G.; Coleman, E. A fuzzy model for evaluating risk impacts on variability between contract sum and final account in government-funded construction projects. J. Facil. Manag. 2015, 13, 45–69. [Google Scholar] [CrossRef]
  48. Shi, Z.; Huang, Z.; Zhu, X.; Liu, J. Modelling integrated risks of overseas power construction project: A case study in Uzbekistan. J. Eng. Sci. Technol. Rev. 2016, 9, 90–97. [Google Scholar]
  49. Tang, L.C.M.; Leung, A.Y.T.; Wong, C.W.Y. Entropic Risk Analysis by a High-Level Decision Support System for Construction SMEs. J. Comput. Civ. Eng. 2010, 24, 81–94. [Google Scholar] [CrossRef]
  50. Ameen, R.F.M.; Mourshed, M. Urban environmental challenges in developing countries—A stakeholder perspective. Habitat Int. 2017, 64, 1–10. [Google Scholar] [CrossRef] [Green Version]
  51. Xiong, B.; Skitmore, M.; Xia, B. Exploring and validating the internal dimensions of occupational stress: Evidence from construction cost estimators in China. Constr. Manag. Econ. 2015, 33, 495–507. [Google Scholar] [CrossRef] [Green Version]
  52. Hwang, B.G.; Shan, M.; Phua, H.; Chi, S. An Exploratory Analysis of Risks in Green Residential Building Construction Projects: The Case of Singapore. Sustainability 2017, 9, 1116. [Google Scholar] [CrossRef]
  53. Cochran, W.G. Sampling Techniques, 3rd ed.; Wiley: Hoboken, NY, USA, 1977. [Google Scholar]
  54. Moser, C.A.; Kalton, G. Survey Methods in Social Investigation; Heinemann Educational Books: London, UK, 1971. [Google Scholar]
  55. Kiefer, C.P.; Carrillo-Hermosilla, J.; Río, P.D. Diversity of eco-innovations: A quantitative approach. J. Clean. Prod. 2017, 166, 1494–1506. [Google Scholar] [CrossRef]
  56. Kline, P. Easy Guide to Factor Analysis; Routledge: Abingdon, UK, 1994. [Google Scholar]
  57. Carmines, E.G.; Zeller, R.A. Reliability and Validity Assessment; Sage Publication: Thousand Oaks, CA, USA, 1979. [Google Scholar]
  58. Kim, J.O.; Mueller, C.W. Factor Analysis: Statistical Methods and Practical Issues; Sage university paper series on quantitative applications in the social sciences; Sage Publication: Thousand Oaks, CA, USA, 1978. [Google Scholar]
  59. Nunnally, J.C. Psychometric Theory, 2nd ed.; McGraw-Hill: New York, NY, USA, 1978. [Google Scholar]
  60. Badri, M.A.; Davis, D.; Davis, D. A study of measuring the critical factors of quality management. Int. J. Qual. Reliab. Manag. 1995, 12, 36–53. [Google Scholar] [CrossRef]
  61. Straub, D.W. Validating instruments in MIS research. Manag. Inf. Syst. Q. 1989, 13, 141–169. [Google Scholar] [CrossRef]
  62. Peter, P.J.; Churchill, G.A.; Brown, T.J. Caution in the use of difference scores in consumer research. J. Consum. Res. 1993, 19, 655–662. [Google Scholar] [CrossRef]
  63. Park, C.H.; Kim, Y.G. Identifying key factors affecting consumer purchase behavior in an online shopping context. Int. J. Retail. Distrib. Manag. 2003, 31, 16–30. [Google Scholar] [CrossRef]
  64. Chan, D.W.M.; Kumaraswamy, M.M. An evaluation of construction time performance in the building industry. Build. Environ. 1996, 31, 569–578. [Google Scholar] [CrossRef]
Table 1. Human risk list for construction projects.
Table 1. Human risk list for construction projects.
ReferenceCategoriesFactors
[15]Individual factorsCapability; Knowledge and skills; Stress; Motivation; Emotional and cultural factors
Project team factorsManagement; Communication and coordination; Task and supervision
Organizational factorsSystems and procedures; Policies and standards
[16]AttitudesFew incentives; Skepticism of waste reduction; Poor knowledge; Belief that waste is inevitable
Subjective NormsCulture; Sense of unfairness/inequity; Inconsistent industry standards; Unclear waste objectives; Low management commitment; Unclear/absent policies; Poor consultation
Perceived Behavioral ControlTime pressures; Cost pressures; Poorly design work processes
[17]Government-related risksInadequate approved project budgets; Delays in obtaining permissions; Changes in Government regulations and laws; Lack of project controls; Administrative interference
Client-related risksVariations in project specifications; Delays in the settlement of contractor’s claims; Lack of project control
Design-related risksInadequate soil investigation; Delays in design; Ambiguities and inconsistencies in design and design changes
Contractor-related risksInadequate estimates; Financial difficulties; Lack of experience; Poor management; Difficult in controlling nominated subcontractors
Consultant-related risksLack of experience; Performance delays; Poor communication with other project parties
[18]Education background; Engineering experience; Social experience; Professional knowledge; Completeness of project information; Interest in the engineering; Sensitivity to external information; Desire for decision objectives; Consequences of decision making; Judgment ability;
[19]Contractual and legal riskDelay in solving contractual issues; Delay in solving disputes; Delay payment on contract and extras; Change order negotiation
Subcontractors-related riskSubcontractor failure; Coordination of subcontractor; Financial failure of subcontractor
Operational riskTreatment of material removed from site
Design riskInadequate specification; Conflict of document; Design change
Delay riskThird party delays
[20]DesignDetail, precision and appropriateness of specifications; Design risks arising from surveys, investigations; Interaction of design with method of construction
LogisticsLoss or damage in the transportation of materials and equipment; Organizational interfaces
FinancialAdequate provision of cash flow; Losses due to default of contractors, suppliers
LegalLiability for acts of others, direct liabilities; Local law, legal differences between home country contractors, designers
ConstructionFeasibility of construction methods, safety; Quality and availability of management and supervision
OperationalFluctuations in market demand for product or service; Maintenance needs
[21]Attitude towards general site safetyEveryone has responsibility in safety; Attitude in reporting risk; Safety versus site progress; Conflict with the senior relating safety; Attitude to follow safety
Attitude towards Factories and Industrial UndertakingsFamiliarity with F&IU; Effectiveness in reducing accidents
Attitude towards regulation: Supervision PlanFamiliarity with SP; Effectiveness in reducing accidents; Legal liability makes SP more effective
Attitude towards current company policyFully comply with F&IU; Fully comply with SP; Provide sufficient safety information; Safety meetings improve safety
Attitude towards senior management commitmentAttitude of senior management towards safety
Attitude towards site safety trainingProvision of sufficient training; Awareness of basic training; Upgrade safety standard reduces accidents
[22]Low/no safety education/training; Lack of poor crisis preparedness emergency plans; Low hazard awareness from upper management
Table 2. General risk identification methods in construction projects.
Table 2. General risk identification methods in construction projects.
ReferenceMethodPurpose
[36]DelphiA two-round Delphi method was applied by asking 10 experts to specify the importance of each risk interaction.
[37]Literature reviewLiterature review was used to identify risks associated with stakeholders in construction projects.
[38]ChecklistA risk checklist for public-private partnerships was developed and could be adopted for further empirical studies.
[39]BrainstormingBrainstorming sessions were conducted with the workers to identify why certain hazards remained unrecognized.
[40]Fault treeA fault tree method was applied in order to identify the main causes of events and incidents.
[41]Flow chartThis study built a risk identification feedback chart and risk flow chart to comprehensively identify investment risks that projects in China may face.
[42]SWOTSeventeen risk agents with 17 risk events were identified based on SWOT analysis through the process of planning.
[43]WBS-RBSThe WBS-RBS was used to identify the possible risks that may arise in project implementation and then considered those risks for the estimation process.
[44]Questionnaire surveyA questionnaire survey was conducted totaling 50 questions, of which 47 questions were related to risk and three questions were related to personal details and risks faced on the work site.
Table 3. General weighting determination methods in the construction project.
Table 3. General weighting determination methods in the construction project.
ReferenceMethodPurpose
[45]DelphiTo explore how the risks should be allocated, three rounds of a Delphi questionnaire survey was conducted.
[46]AHPAHP was used to identify typical risks associated with PPP projects in the Chinese water supply sector.
[47]Principal component analysisPrincipal component factor analysis methods were adopted to evaluate and classify the critical risk factors.
[48]Entropy weight methodShannon Entropy and statistical methods of calculating and ranking analysis were implemented for modelling the integrated risks of a power construction project.
[49]Factor analysisCritical risk factors obtained through factor analysis were assessed to gain a better understanding of their importance and impact on project management.
Table 4. Potential behavioral risk factors of principal participants based on literature research.
Table 4. Potential behavioral risk factors of principal participants based on literature research.
Construction Project Stage Principal ParticipantsBehavioral Risk Factors
(A) Investment decision stage (A) Client (AA1) Change project objective or investment direction
(AA2) Default payment for design fee
(AA3) Choose the worse designer because of tacit collusion
(B) Designer (AB1) Evil intention to sub package
(AB2) Arbitrary intent to make a design change against the client’s intention
(B) Tendering and bidding stage (C) Consultant(BC1) Expert is unfair
(BC2) Expert takes bribes
(BC3) Malfeasance of conduct department
(C) Construction stage (A) Client (CA1) Change project objective or investment direction
(CA2) Error guidance and nonprogrammed interference with instruction
(CA3) Defaulting and rejection of compensation
(CA4) Evil failure to supply equipment and raw material in time
(CA5) Defaulting in payment of project settlement amount
(D) Contractor (CD1) Arbitrary intent to construct against intended design
(CD2) Evil intention to require design change
(E) Supplier (CE1) Evil intention to raise price of equipment and raw materials
(CE2) Evil lag in supplying equipment and raw material
(F) Supervisor(CF1) Error guidance and nonprogrammed interference with instructions
(CF2) Intent to make trouble for suppliers, contractors, and so on
(CF3) Go places without notice
(D) Completion and acceptance stage (A) Client (DA1) Default paying project settlement amount
(DA2) Delay acceptance time
Table 5. Potential behavioral risk factors of principal participants based on expert interview.
Table 5. Potential behavioral risk factors of principal participants based on expert interview.
Construction Project Stage Principal ParticipantsBehavioral Risk Factors
(A) Investment decision stage(A) Client (AA4) Evil intention to make unreasonable requests
(B) Designer(AB3) Use technological capability advantage to obtain profit
(B) Tendering and bidding stage(A) Client(BA1) Establish an obstruction to reject others
(BA2) Disclose project information because of tacit collusion
(D) Contractor(BD1) Bidders ring
(BD2) Bidding with fraudulent qualifications
(BD3) Collude to tender or bid
(BD4) Bribes to experts
(C) Construction stage(A) Client(CA6) Evil intention to make unreasonable construction requests
(CA7) Collude with other participants to modify the design proposal
(D) Contractor(CD3) Collude with other participants to modify the design proposal
(CD4) Illegal subcontracting
(CD5) Unreasonable claims
(CD6) Malicious withholding of wages, leading to project interruption
(E) Supplier(CE3) Supplying shoddy equipment and material instead of good ones
(F) Supervisor(CF4) Obtain unreasonable profit because of collusion with contractors
(D) Completion and acceptance stage(A) Client(DA3) Increase the workload of the contractor
(D) Contractor(DD1) Malicious claims
(F) Supervisor(DF1) Obtain unreasonable profit because of collusion with contractors
Table 6. Profiles of the survey respondents.
Table 6. Profiles of the survey respondents.
Respondent ProfilesCategorization and Percentages
Type of unit worked inGovernment department3.33%Design institute6.67%
Construction company32.67%Building company32.00%
Supervision company8.00%Research institute17.33%
Years of work experienceLess than 2 years12.67%2–5 years30.00%
5–10 years38.00%10–15 years16.67%
More than 15 years2.67%
Table 7. KMO and Bartlett’s Test.
Table 7. KMO and Bartlett’s Test.
Statistical Test of DataResults
Kaiser-Meyer-Olkin Measure of Sampling Adequacy0.801
Bartlett’s Test of SphericityApprox. Chi-Square2977.860
df820
Sig.0
Table 8. Total variance explained.
Table 8. Total variance explained.
ComponentInitial EigenvaluesExtraction of Load
TotalVariance Explained Percentage (%)Cumulative Percentage (%)TotalVariance Explained Percentage (%)Cumulative Percentage (%)
110.48925.58425.58410.48925.58425.584
22.6576.4832.0642.6576.4832.064
32.5336.17738.2412.5336.17738.241
42.0494.99843.2392.0494.99843.239
51.7614.29547.5351.7614.29547.535
61.5433.76351.2971.5433.76351.297
71.4523.54254.8391.4523.54254.839
81.3483.28858.1281.3483.28858.128
91.3423.27461.4021.3423.27461.402
101.2353.01164.4131.2353.01164.413
111.12.68367.0951.12.68367.095
121.0772.62669.7211.0772.62669.721
130.9572.33572.056
140.9022.19974.255
150.7951.9476.195
160.7661.86878.063
170.6981.70379.766
180.6451.57381.339
190.6221.51682.855
200.5971.45684.311
210.5631.37485.685
220.5081.23986.925
230.4741.15688.081
240.4441.08289.163
250.4321.05390.217
260.3970.96891.185
270.3880.94792.131
280.3540.86392.994
290.350.85493.848
300.3080.75194.599
310.3010.73395.332
320.2910.71196.043
330.2560.62496.667
340.2290.55897.225
350.2220.54297.767
360.2150.52398.29
370.1770.43398.723
380.1680.4199.133
390.1350.32999.462
400.1130.27699.737
410.1080.263100
Table 9. Correlations between the risk factors.
Table 9. Correlations between the risk factors.
Variables Component
123456789101112
* (AA1) Change project objective or investment direction0.313−0.047−0.3180.3010.0940.0930.041−0.5000.2490.1340.0400.404 *
(AA2) Defaulting on payment for design fee0.286−0.1240.003−0.159−0.3520.4140.197−0.0320.2420.0510.345−0.065
* (AA3) Choose a worse designer because of tacit collusion0.551 *0.011−0.383−0.231−0.1270.3970.169−0.016−0.187−0.031−0.107−0.065
* (AA4) Evil intention to make unreasonable requests0.480−0.223−0.255−0.133−0.1580.506 *0.0560.176−0.181−0.0140.053−0.334
* (AB1) Evil intention to sub package0.636*−0.021−0.2730.1720.052−0.0420.096−0.263−0.1890.052−0.0280.179
* (AB2) Arbitrary intent to make a design change against client’s intention0.617 *0.112−0.4520.126−0.1990.057−0.090−0.072−0.0280.0230.105−0.032
* (AB3) Use technological capability advantage to obtain profit0.469−0.110−0.0760.0520.3790.0610.0480.047−0.368 *0.4130.102−0.184
(BA1) Establish an obstruction to reject others0.3560.1360.2350.277−0.285−0.1050.0600.040−0.321−0.0280.064−0.124
* (BA2) Disclose project information because of tacit collusion0.591 *0.2170.0600.162−0.2210.1270.214−0.194−0.289−0.0500.0720.209
(BC1) Expert is unfair0.2940.4110.342−0.1490.2040.241−0.143−0.0640.105−0.0470.1720.034
(BC2) Expert takes bribes0.338−0.3810.138−0.0320.1850.1730.0810.1640.247−0.179−0.288−0.030
(BC3) Malfeasance of conduct department 0.3290.3160.110−0.4440.2100.2740.0010.207−0.120−0.084−0.1100.226
* (BD1) Bidders ring0.4300.3870.404 *0.306−0.0330.050−0.0050.124−0.176−0.048−0.1060.042
* (BD2) Bidding with fraudulent qualifications0.557 *0.4320.0030.237−0.1010.110−0.0520.0490.2130.0940.0590.098
* (BD3) Collude to tender or bid0.594 *0.4030.1200.071−0.125−0.081−0.100−0.186−0.1790.1140.1170.171
(BD4) Bribes to experts0.4010.5020.3090.0140.1950.017−0.1960.138−0.1740.0890.233−0.074
* (CA1) Change project objective or investment direction0.4550.052−0.2230.482*0.351−0.2340.192−0.0080.301−0.0740.1190.002
* (CA2) Error guidance and nonprogrammed interference with instructions 0.608 *−0.121−0.2610.2060.049−0.0240.0000.1900.102−0.180−0.0010.055
* (CA3) Defaulting and rejection to compensation0.562 *−0.3620.1110.223−0.072−0.012−0.1590.1810.197−0.207−0.087−0.102
* (CA4) Evil failure to supply equipment and raw materials in time0.480−0.3820.0680.0480.0180.013−0.490 *0.196−0.1320.009−0.0940.138
* (CA5) Defaulting on paying project settlement amount0.4940.593 *0.3230.0370.1190.1200.068−0.0960.023−0.2650.0630.207
(CA6) Evil intention to make unreasonable construction requests 0.271−0.4120.2420.197−0.0070.1400.1750.338−0.012−0.1970.2550.257
* (CA7) Collude with other participants to modify the design proposal0.204−0.2680.029−0.0440.124−0.1660.3290.535 *−0.0180.3590.1090.256
* (CD1) Arbitrary intent to construct against design intention0.682 *0.045−0.4610.0140.078−0.065−0.1150.213−0.072−0.022−0.056−0.024
* (CD2) Evil intention to require design change0.634 *0.124−0.419−0.0510.021−0.084−0.1280.0890.1590.102−0.1630.044
* (CD3) Collude with other participants to modify the design proposal0.622 *0.011−0.2560.2130.366−0.061−0.0400.0290.019−0.074−0.078−0.036
* (CD4) Illegal subcontracting0.584 *0.052−0.174−0.148−0.275−0.234−0.056−0.0760.048−0.3290.250−0.022
* (CD5) Unreasonable claims0.497−0.0240.109−0.255−0.440 *−0.177−0.3910.0680.2280.050−0.0010.168
* (CD6) Malicious withholding of wages, leading to the project interruption0.4180.0150.216−0.035−0.054−0.428−0.1150.0230.0480.0000.469 *−0.297
* (CE1) Evil intention to raise price of equipment and raw materials0.589 *−0.2470.163−0.2040.2040.014−0.244−0.254−0.0450.276−0.0210.114
* (CE2) Evil lag in supplying equipment and raw materials0.612 *−0.2370.081−0.2800.1890.022−0.321−0.130−0.095−0.040−0.013−0.082
(CE3) Supplying shoddy equipment and materials instead of good ones0.357−0.2010.0990.0720.3970.388−0.167−0.0660.273−0.0220.205−0.219
* (CF1) Error guidance and nonprogrammed interference with instruction0.621 *−0.120−0.212−0.093−0.173−0.1760.1000.073−0.1050.105−0.081−0.002
* (CF2) Intent to make trouble for suppliers, contractors and so on 0.559 *0.1160.071−0.4410.092−0.1920.375−0.0330.1050.1360.0770.005
* (CF3) Go places without notice0.550 *0.0220.173−0.364−0.065−0.1400.258−0.0160.2580.252−0.002−0.070
* (CF4) Obtain unreasonable profit because of collusion with contractors0.507 *0.0760.007−0.1550.273−0.2130.334−0.060−0.016−0.401−0.040−0.125
* (DA1) Defaulting on paying project settlement amount0.521 *−0.3820.4650.0200.0130.0290.167−0.261−0.042−0.067−0.2200.015
(DA2) Delay acceptance time0.386−0.1980.3530.4110.0410.0380.193−0.0560.0280.129−0.141−0.346
* (DA3) Increase the workload of the contractor0.3610.1330.1330.333−0.2760.107−0.0200.1800.3630.308 *−0.235−0.084
* (DD1) Malicious claims0.613 *−0.1770.355−0.156−0.184−0.1100.033−0.1490.0620.129−0.2530.015
* (DF1) Obtain unreasonable profit because of collusion with contractors0.667 *0.0080.071−0.203−0.221−0.1350.0160.029−0.114−0.224−0.229−0.159
Table 10. Internal consistency analysis and convergent validity.
Table 10. Internal consistency analysis and convergent validity.
VariablesScale Average Value if Item DeletedScale Variance if Item DeletedCorrected Item-Total CorrelationSquare of the Multi-CorrelationCronbach’s Alpha if Item Deleted
* (AA1) Change project objective or investment direction141.17425.3140.410 *0.4210.923
(AA2) Defaulting on payment for design fee141.82428.7100.2670.4920.922
* (AA3) Choose a worse designer because of tacit collusion141.10415.9390.507 *0.6730.920
* (AA4) Evil intention to make unreasonable requests141.50419.9450.435 *0.5900.920
* (AB1) Evil intention to sub package140.93415.4960.589 *0.6520.919
* (AB2) Arbitrary intent to make a design change against client’s intention141.18410.1290.565 *0.6830.919
* (AB3) Use technological capability advantage to obtain profit141.16421.5270.435 *0.5680.920
(BA1) Establish an obstruction to reject others141.52424.8870.3290.5120.922
* (BA2) Disclose project information because of tacit collusion141.06414.4330.563 *0.5860.919
(BC1) Expert is unfair141.60429.0470.2840.5080.922
(BC2) Expert takes bribes141.47426.1960.3210.5860.922
(BC3) Malfeasance of conduct department 141.35427.4440.3020.5430.922
* (BD1) Bidders ring141.38421.4620.412 *0.6760.921
* (BD2) Bidding with fraudulent qualifications141.36414.9480.534 *0.6430.919
* (BD3) Collude to tender or bid141.09416.2500.558 *0.6690.919
(BD4) Bribes to experts141.50421.9100.3790.5590.921
* (CA1) Change project objective or investment direction140.96420.3330.419 *0.4730.921
* (CA2) Error guidance and nonprogrammed interference with instructions 141.12417.6810.563 *0.6030.919
* (CA3) Defaulting and rejection to compensation141.18419.4620.526 *0.6100.920
* (CA4) Evil failure to supply equipment and raw materials in time141.26421.5070.432 *0.6030.920
* (CA5) Defaulting on paying project settlement amount141.31418.6950.459 *0.5740.920
(CA6) Evil intention to make unreasonable construction requests 141.40431.2500.2580.4530.922
* (CA7) Collude with other participants to modify the design proposal141.27432.5000.408 *0.3680.923
* (CD1) Arbitrary intent to construct against design intention141.02411.3920.629 *0.7740.918
* (CD2) Evil intention to require design change141.22413.8380.580 *0.6580.919
* (CD3)Collude with other participants to modify the design proposal141.13416.0850.581 *0.6800.919
* (CD4) Illegal subcontracting141.00417.7340.526 *0.5800.919
* (CD5) Unreasonable claims141.61420.7510.450 *0.6300.920
* (CD6) Malicious withholding of wages, leading to the project interruption141.40427.1270.3810.4350.921
* (CE1) Evil intention to raise price of equipment and raw materials141.28417.7250.543 *0.6690.919
* (CE2) Evil lag in supplying equipment and raw materials141.14417.5800.562 *0.6600.919
(CE3) Supplying shoddy equipment and materials instead of good ones141.50425.3030.3370.4570.921
* (CF1) Error guidance and nonprogrammed interference with instruction141.24415.9200.570 *0.6580.919
* (CF2) Intent to make trouble for suppliers, contractors and so on 141.40416.3750.515 *0.6800.920
* (CF3) Go places without notice141.82419.9180.511 *0.6390.920
* (CF4) Obtain unreasonable profit because of collusion with contractors141.15421.1170.463 *0.5270.920
* (DA1) Defaulting on paying project settlement amount141.12418.4400.484 *0.6990.920
(DA2) Delay acceptance time141.56424.9670.3650.4940.921
* (DA3) Increase the workload of the contractor141.48425.5740.3410.4610.921
* (DD1) Malicious claims141.50416.6020.574 *0.6520.919
* (DF1) Obtain unreasonable profit because of collusion with contractors141.45412.1270.611 *0.6650.918
Table 11. Ranking of the critical behavioral risk factors.
Table 11. Ranking of the critical behavioral risk factors.
Construction Project Stage Principal ParticipantBehavioral Risk FactorTotal Number of ResponsesMS ValueRanking
12345Total
(A) Investment decision stage (A) Client (AA1) Change project objectives or investment direction8194128541503.67314
(A) Investment decision stage (A) Client (AA3) Choose a worse designer because of tacit collusion8133450451503.7407
(A) Investment decision stage (A) Client (AA4) Evil intention to make unreasonable requests 11194851211503.34727
(A) Investment decision stage (B) Designer(AB1) Evil intention to sub package582961471503.9131
(A) Investment decision stage (B) Designer(AB2) Arbitrary intent to make a design change against client’s intention10222740511503.66715
(A) Investment decision stage (B) Designer(AB3) Use technological capability advantage to obtain profit5143762321503.68013
(B) Tendering and bidding stage (A) Client (BA2) Disclose project information because of tacit collusion6114045481503.7875
(B) Tendering and bidding stage (D) Contractor(BD1) Bidders ring4235437321503.46724
(B) Tendering and bidding stage (D) Contractor(BD2) Bidding with fraudulent qualifications8204644321503.48023
(B) Tendering and bidding stage (D) Contractor(BD3) Collude to tender or bid4124251411503.7536
(C) Construction stage (A) Client (CA1) Change project objective or investment direction6113443561503.8802
(C) Construction stage (A) Client (CA2) Error guidance and nonprogrammed interference with instructions484757341503.7278
(C) Construction stage (A) Client (CA3) Defaulting and rejection of compensation1164755311503.66016
(C) Construction stage (A) Client (CA4) Evil failure to supply equipment and raw materials in time2224549321503.58019
(C) Construction stage (A) Client (CA5) Defaulting on paying project settlement amount7213853311503.53322
(C) Construction stage (A) Client (CA7) Collude with other participants to modify the design proposal2185052281503.57320
(C) Construction stage (D) Contractor(CD1) Arbitrary intent to construct against design intent4153741531503.8274
(C) Construction stage (D) Contractor(CD2) Evil intention to require design change8153560321503.62017
(C) Construction stage (D) Contractor(CD3) Collude with other participants to modify the design proposal773966311503.71310
(C) Construction stage (D) Contractor(CD4) Illegal subcontracting3143157451503.8473
(C) Construction stage (D) Contractor(CD5) Unreasonable claims7256336191503.23329
(C) Construction stage (E) Supplier(CE1) Evil intention to raise the price of equipment and raw materials1234651291503.56021
(C) Construction stage (E) Supplier (CE2) Evil lag in supplying equipment and raw materials574858321503.70111
(C) Construction stage (F) Supervisor(CF1) Error guidance and nonprogrammed interference with instruction5164159291503.60718
(C) Construction stage (F) Supervisor(CF4) Obtain unreasonable profit because of collusion with contractors664858321503.69312
(C) Construction stage (F) Supervisor(CF2) Intend to make trouble for suppliers, contractors and so on 5274543301503.4425
(C) Construction stage (F) Supervisor(CF3) Go places without notice737603881503.0230
(D) Completion and acceptance stage (A) Client (DA1) Defaulting on paying project settlement amount5173159381503.729
(D) Completion and acceptance stage (D) Contractor (DD1) Malicious claims7215058141503.3428
(D) Completion and acceptance stage (F) Supervisor(DF1) Obtain unreasonable profit because of collusion with contractors8273558221503.39326

Share and Cite

MDPI and ACS Style

Xiang, P.; Jia, F.; Li, X. Critical Behavioral Risk Factors among Principal Participants in the Chinese Construction Industry. Sustainability 2018, 10, 3158. https://doi.org/10.3390/su10093158

AMA Style

Xiang P, Jia F, Li X. Critical Behavioral Risk Factors among Principal Participants in the Chinese Construction Industry. Sustainability. 2018; 10(9):3158. https://doi.org/10.3390/su10093158

Chicago/Turabian Style

Xiang, Pengcheng, Fuyuan Jia, and Xiaohui Li. 2018. "Critical Behavioral Risk Factors among Principal Participants in the Chinese Construction Industry" Sustainability 10, no. 9: 3158. https://doi.org/10.3390/su10093158