Next Article in Journal
Entrepreneurial Factors Affecting the Sustainable Growth and Success of a South African Construction Company
Previous Article in Journal
Evaluation of Corporate Websites and Their Influence on the Performance of Olive Oil Companies
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Scenario Aggregation-Based Grid-Connected Photovoltaic Plant Design

by
Ahmad Abuelrub
1,*,
Osama Saadeh
2 and
Hussein M. K. Al-Masri
3
1
Department of Electrical Engineering, Jordan University of Science and Technology, Irbid 22110, Jordan
2
Department of Energy Engineering, German Jordanian University, Amman 11180, Jordan
3
Department of Electrical Power Engineering, Yarmouk University, Irbid 21163, Jordan
*
Author to whom correspondence should be addressed.
Sustainability 2018, 10(4), 1275; https://doi.org/10.3390/su10041275
Submission received: 14 March 2018 / Revised: 11 April 2018 / Accepted: 12 April 2018 / Published: 20 April 2018
(This article belongs to the Section Energy Sustainability)

Abstract

:
As the global population continues to increase and living standards in developing countries continue to improve, the demand for energy is surging. This is also coupled with technological advances, which are leading to the increased electrification of transportation, manufacturing, and home appliance. Classical fossil fuel-based energy generation is unsustainable and a significant cause of air pollution. Therefore, clean, local, and sustainable sources of energy, such as solar energy, have recently been receiving more attention. In this paper, a complete design approach for grid-connected photovoltaic (PV) plants is developed. Jordan University of Science and Technology (JUST) is presented as a case study. The design is formulated as an optimization problem to find the optimal PV plant size needed to minimize the system cost and meet the design constraints. The uncertainties of solar radiation and temperature are considered using appropriate stochastic models. The optimization problem is solved using the Scenario Aggregation technique. The results show the financial and environmental feasibility of the proposed system. The optimal PV plant size which meets the annual demand of JUST is found and the financial and environmental benefits derived from executing the proposed system are emphasized.

1. Introduction

Energy stored in fossil fuels that is released by human activity causes environmental pollution. Furthermore, fossil fuel energy resources are exhaustible, and alternatives will be needed in the near future. On the other hand, renewable energy resources are clean and cannot be depleted [1]. Photovoltaic energy is one of the most sustainable forms of energy, as it harvests energy from the sun. It is silent, ecological, local, and economically feasible. So, market expansion in PV technologies has rapidly increased due to reduced initial capital investment in addition to the urgency of realizing energy access in remote areas, as this technology does not require transmission lines. In essence, PV technology promotes sustainable local energy generation.
The published literature is rich with research projects studying PV energy. In Reference [2], a stochastic method is involved in order to size an off-grid PV system with energy storage. This includes Markov chain and beta probability density function (pdf). The stochastic results are compared with a deterministic method. The stochastic solution provides more reliable and realistic results. In Reference [3], an off-grid PV/diesel battery is discussed and designed for a village in Russia as a case study. The levelized cost of energy (LCOE) and the CO2 emissions are calculated to indicate the economical and the environmental feasibility of the proposed configuration. Results show savings in both fuel and oil cost (7.8%) and emissions (51.0%) compared with a conventional fossil fuel plant. The authors of Reference [4] evaluated the investment in a multi-site photovoltaic plant as a profitability analysis with an objective to maximize the net return. In a techno-economic study [5], numerous PV configurations are investigated. The LCOE is calculated, which includes capital cost, as well as operation and maintenance costs over the project lifetime. Also, the economic impacts of using batteries or not are discussed. In Reference [6], a stochastic programming model for the optimal scheduling of a distributed energy system with multiple energy devices including renewables, considering economic and environmental aspects, is presented. The results give the optimized operation strategies which reduce the expected energy costs and CO2 emissions. In Reference [7], the authors discuss the feasibility of a grid-connected rooftop/building integrated photovoltaic system for the electrification of consumption with incorporating feed-in tariffs/net metering process regulation in New Delhi, India.
Jordan’s area is about 89,200 km2, with 80% of its 9.5 million inhabitants living predominantly in urban centers in the northwest of the country in areas that amount to approximately 10% of the total available land. As 96% of all energy in Jordan is imported, the country is highly affected by the cost of energy imports, which have been a major burden on its economy. Volatile fuel prices are expected to cost Jordan $3.21 billion annually, representing 19.5% of the GDP. This has a financial impact on the country, as well as a political impact. In particular, Jordan’s potential for renewable energy is significant, but its generation represents less than 5% of current electrical energy production.
To encourage the deployment of renewable energy systems, the government has approved a net-metering scheme, as shown in Figure 1 below. This scheme employs a net-meter, which in essence is a bidirectional kWh counter. Any excess energy generated by the system that is not consumed locally at the load is injected into the grid, and at the end of a specific contract period, the net consumption is billed. In Jordan, the contract period is annual, which allows consumers to generate excess energy during the high radiation summer months that can later be retrieved during low generation winter months.
This is especially true for large universities such as Jordan University of Science and Technology (JUST), which are considered large energy consumers. JUST consumed 33.4 GWh in 2016, at a cost of $12.25 million, which represents 12% of the university’s annual budget. This is a huge burden that affects potential development and expansion of the university.
Universities and institutes of higher education are expected to be community role models and lead change in their local surroundings. This is especially true for developing countries were universities house unique intellect and expertise. The United Nations Decade of Education for Sustainable Development (2005–2014) resulted in more attention being directed toward higher education institutions and the sustainability of their operations. In addition students, alumni, and governments are pressuring universities to lead local, national, and international efforts toward increased integration of renewable energy.
In this paper, a full optimized PV system design for JUST is presented. In Section 2, detailed mathematical modeling of the proposed system is presented. Section 3 provides a complete PV plant sizing procedure which is implemented as a stochastic optimization problem solved using a scenario aggregation technique. The case study of the PV plant at JUST is considered and a detailed design of the PV plant, which includes its main components, is illustrated in Section 4. In Section 5, a detailed financial and environmental benefit analysis of the suggested PV plant is presented. Finally, Section 6 draws conclusions and shows the financial and environmental feasibility of the proposed system.

2. Mathematical Modeling of the PV System

Mathematical modeling is considered a crucial step in predicting the behavior of a system using a list of inputs, a list of outputs, and the algorithm needed to find the optimal output function. In other words, mathematical modeling is used to evaluate the system performance for various inputs and conditions. Therefore, it is an essential process especially for large utility scale systems, such as photovoltaic renewable energy systems, which have high initial investment. Detailed mathematical modeling for the components of the proposed PV system is presented in this section.

2.1. PV Plant Output Power

The electrical power generated from one PV panel (PDC) depends on the global solar radiation and the panel cell temperature and can be calculated using (1) [8]:
P D C = P S T C × G A G S T C × [ 1 + ( T C T S T C ) C T ]
where PSTC is the power of the PV module under STC conditions in Watts. GA is the total in-plane irradiance on the surface of the PV module in Watt/m2. GSTC is the STC irradiance (1000 Watt/m2). TC is the temperature of the PV cell. TSTC is the STC temperature (25 °C); CT is the manufacturer’s temperature power coefficient. The cell temperature of the PV system operation can be estimated using (2) [9,10]:
T C = T a + G a ( T N O C T 20 800 )
where Ta is the ambient temperature in °C. TNOCT is the PV cell temperature at an irradiance of 800 Watt/m2 and an air temperature of 20 °C.

2.2. Uncertainty in Solar Radiation

The solar radiation is random in its nature; therefore, a stochastic model is needed to model its uncertainty. In the published literature, Beta distribution is widely used to model solar radiation uncertainty, as in References [11,12]. In this paper, the Beta distribution for each time step is used to model the solar irradiance. The probability density function of the Beta distribution is given in (3):
f b ( S I ) = { Γ ( α i + β i ) S I α i 1 ( 1 S I ) β i 1 Γ ( α i ) Γ ( β i ) 0 S I 1 0 O t h e r w i s e }
where fb(SI) is the Beta distribution function of SI. αi,, βi are Beta distribution parameters for time step i. The parameters of the Beta distribution can be estimated from the historical solar radiation data using (4) and (5):
β i = ( 1 μ s i ) ( μ s i ( 1 + μ s i ) σ s i 2 1 )
α i = μ s i β i 1 μ s i
where µsi and σsi are the mean and the standard deviation of the solar radiation data for time step i, respectively.

2.3. Uncertainty in Temperature

The daily temperature variation over a long period is usually modeled using Normal probability distribution [13]. The Normal distribution is defined by two parameters: the mean value µt and the standard deviation σt. Temperature data is used to create the Normal distribution for each time step in order to model the uncertainty in ambient temperature. The PDF of the Normal distribution is given in (6):
f ( T a ) = 1 σ t i 2 π e ( l μ t i ) 2 2 σ t i 2
where Ta is the ambient temperature, µti is the mean value of Ta for time step i, and σti is the standard deviation.

2.4. PV Plant Area

The panels of the PV array should be installed at an optimal distance (dopt), minimizing the required land area of the PV plant and taking into account the prohibition of shading between rows of the PV array. As a matter of fact, to ensure zero shading, dopt is calculated at the time when the sunrise angle is at the minimum (γs) [14]. Note that dopt depends on the module angle of dip (β), the sunrise angle, and the dimensions of the PV panel. It is calculated in the project’s location at noon of the winter solstice to be 2.6 m. Then, the optimal total area required to install the PV plant can be calculated using (7):
A P V P l a n t = A N c o l cos β + W ( N P V N c o l ) d o p t
where NPV is the number of PV panels. Ncol is the number of columns in a rectangular PV array. Finally, A and W are the area and the width of the PV panel used in this project.

3. PV Plant Sizing Procedure

In this section, a mathematical formulation of the proposed system will be presented for optimization. The objective function measures the total cost of the proposed system, which is the capital cost of the installed PV plants. The optimization problem constraints are as follows: the energy generated from the PV plant is equal to load requirements, and the total PV plant area is less than the dedicated land area at JUST. It is assumed that load will be fully supplied by the PV plant, which will result in zero energy consumption from the grid. The optimization problem is proposed as a stochastic optimization problem to find the optimal size of PV plant needed to minimize the cost of the system and to meet the problem constraints.
The total system cost is a function of the PV plant size, since as the installed capacity increases the total system capital cost increases. As shown in Equation (1), the total energy generated from the PV plant can be expressed as in (8):
E P V = i S P V × S I i S S T C × [ 1 + ( T C i T S T C ) T C P ] × t i
where EPV is the total energy generated from the PV plant in MWh, SPV is the plant size in MW, i is the index of the time step, and ti is the time step in hours. The problem constraints mentioned above are shown in (9) and (10), respectively.
E P V = i = 1 8760 S P V × S I i S S T C × [ 1 + ( T C i T S T C ) T C P ] × t i = D y r
A P V s A max
where Dyr is the total energy demand for one year, ti is one hour, and Amax is the available area in m2.
Since the problem has stochastic variables, a stochastic optimization technique must be applied. In the published literature, different methodologies of stochastic optimization have been suggested to solve problems with uncertainties. In Reference [15], a stochastic optimal sizing of a rural mini-grid composed by a photovoltaic (PV) plant, lithium battery storage, a diesel generator, and a fuel tank is proposed. The problem is formulated as an optimization problem to minimize the net present cost of the mini-grid components. A particle swarm optimization (PSO) procedure integrated with Monte-Carlo simulation is used to solve the optimization problem. PSO is used in Reference [16] to find the optimal hybrid PV/wind configuration. However, in this paper, a simpler scenario aggregation approach for stochastic optimization, which is presented in Reference [17], is used to solve the optimization problem. The main advantage of this method is that it is able to capture system uncertainties in addition to being simple to implement. The mathematical model for the stochastic optimization is shown in (11):
min p s f ( x , s s ) s . t . x s C s
where scenario s is assigned with probability ps. The optimal solution of this problem is denoted by x*. In the optimization problem of the proposed system represented by (8)–(10), the scenario s involves solar radiation SIi and ambient temperature TCi. The optimal solution x* is the optimal size of the PV plant SPV. The scenarios are assumed to be uniformly distributed, therefore ps is the reciprocal of the total simulated scenarios (ns) as in (12):
p s = 1 n s
Then, the optimal solution of the stochastic optimization problem given in (11) can be approximated over ns simulated scenarios by (13), as shown in the scenario aggregation methodology [17].
x * ^ = s S p s x s
where xs is the optimal solution for scenario s. The convergence is verified by limiting the coefficient of variation (COV) of the optimal vector of solutions x*, as shown in (14):
C O V = σ s μ s C O V min
where σs is the standard deviation and µs is the mean of the vector of solutions x*. Solving the optimization problem gives the optimal size of the PV plant needed to minimize the system cost (i.e., PV plant size in (8)) and meet the problem constraints defined in (9) and (10). The PV plant sizing procedure can be summarized by the flow chart shown in Figure 2.

4. Case Study and PV Plant Design

4.1. Case Study

In this case study, the plan of a grid-connected PV plant in JUST is presented. It is worth noting that licensing for renewable energy projects in Jordan is done through the Energy and Minerals Regulatory Commission (EMRS). The latest regulations governing large net-metering project only allow installing a PV system to meet demand, and no oversizing is allowed. A license is only granted after a thorough review of annual consumption analysis, and at the end of the billing year any excess generation is forfeit. An overview of JUST is shown in the following discussion.

4.1.1. About JUST

JUST is a comprehensive, state-supported university located on the outskirts of Irbid. It was established in 1986. Today, JUST has more than 1000 full-time faculty members, with 24,000 undergraduate and 1800 graduate students, in contrast to 2300 students in the 1986/1987 academic year. This increase has led to increased construction and the establishment of more facilities to conform to JUST’s ambitious strategy to extend all possible means to ensure distinctive graduates. This, in turn, has driven the energy demand of JUST to higher levels.

4.1.2. Energy Demand

Due to the rapid increase in the JUST community, more energy resource planning is needed to meet the increasing demand. However, energy resource planning requires careful load study to ensure that the installed capacity of the suggested power system is sufficient to meet the load demand. Therefore, a thorough investigation of JUST’s energy demand during the last five years was conducted and the results are summarized in Table 1. This table shows the monthly electricity demand of JUST during the last five years. The main contributors to electricity consumption at JUST are the air conditioning, lighting, and water pumping systems, in addition to other minor applications.
As can be seen in the table, the energy demand decreased from September 2014 through April 2015. This is predominately due to the implementation of an energy efficiency program at the university. Building operations implemented a temperature control strategy for all air conditioning systems and installed motion sensors in bathrooms and hallways for lighting control. The increase in consumption afterward is due to the commission of a new building at the university.

4.1.3. Solar Radiation and Temperature

Jordan has, in general, a hot, dry climate characterized by long, hot, dry summers and short, cool winters. The summer season, from late April to October, is hot and dry, with high temperatures averaging around 32 °C. The winter, lasting from November to March, is relatively cool, with high temperatures averaging around 13 °C [18]. The solar radiation at JUST’s location (32.4950437, 35.989037) is abundant for most of the year, whereas cloudy days amount to less than 10% of the year. One year of solar radiation and ambient temperature data averaged over a one-hour time interval were obtained from the weather station at JUST. The data are shown in Figure 3 below.

4.2. Simulation Results

The uncertainties in solar radiation and ambient temperature were modeled using Beta and Normal probability distribution functions. These PDFs were built using one year of historical data (2016) that were collected from JUST’s weather station. The mean and standard deviation for each time step were calculated. Then, Beta and Normal distributions were created for each time segment of each day as described in Section 2. The available area for the PV plant at JUST is 250,000 m2.
The parameters of the optimization procedure presented in Section 3 were chosen such that ns = 5000, and COVmin = 0.05. After running the PV plant sizing procedure, illustrated in Figure 4, on MATLAB with these selected parameters, the optimal size of the PV plant was found to be 19.64 MW. However, this installed DC capacity does not include electrical losses in the transformer, inverters, or the cables, which are presented in the next subsection.
The accuracy of the solution obtained from the PV plant sizing procedure depends on the number of the sampled scenarios (ns) and the coefficient of variation (COVmin). As the COVmin gets smaller, the number of the required samples increases and the accuracy of the optimal solution increases. Figure 4 shows the relationship between COVmin and optimal PV plant size.

4.3. PV Plant Design

JUST is supplied from the national electric grid by Irbid District Electricity Company (IDECO) through three dedicated 33 kV feeders, namely: Techno1, Techno2, and Hassan. A grid impact study (GIS) was carried out by IDECO to assist the suitability of the connecting grid to handle connecting the PV system with a net-metering scheme. It was found that, due to reverse current limits, all three feeders must be utilized to connect the PV system. The connection scheme recommendation was 8 MWp on Techno1, 8 MWp on Techno2, and 4 MWp on Hassan. Therefore, it was decided to divide the plant into five equal zones of 3.928 MWp, with each zone supplying a separate circuit to the associated 33 kV bus. This required five transformers rated at 5 MW. As transformer efficiency is best at 80% loading, and transformer loss calculations are not easily computed. This is due to the fact that the rated PV generation only occurs for a short time during daytime generation. This dictates that the worse-case transformer efficiency should be used for calculations. According to PVSYST, one of the leading PV system simulation software, the major transformer losses that affect PV system design include iron losses, ohmic losses, and night disconnect. This may be estimated to approximately 1% of transformer rating. In our case, this results in 1.3% of the PV plant size.
According to utility standards, MV power cable losses should not exceed 1% of power. The GIS also requires a wide range of power factor (PF) control, which is implemented by the inverters. Top of the line on-grid inverters, that have a wide range of PF set points, have an efficiency of 98.5%. Therefore, the plant should be oversized by 3.8% to meet load demand. The new system size is 20.39 MWp, with a new zone size of 4.08 MWp.
Jenko Solar “JKM265P-60” PV modules were chosen for this project. Jenko has been constantly ranked over the past few years by Bloomberg as a Tier 1 PV module manufacturer. The Jenko PV panel parameters are given in Table 2.
The SMA Solar Technology “STP 60-10” inverter is chosen for this design. SMA is chosen as it is the lead PV inverter technology in the Jordanian market. This inverter requires a DC input voltage in the range of 565–1000 Vdc with 60 kW rated power. As each of the zones is identical. Thus, for a total generation capacity of 20.39 MWp, 68 inverters are required per zone. Each inverter requires modules arranged in series and parallel combinations to meet inverter voltage and power demands. Each PV string was chosen to consist of 24 modules with a string voltage of 753.6 V, which ideally lays in the middle of the inverter voltage range. Each string provides a peak power of 6144 Wp, and a DC combiner box combines 10 strings per inverter. The DC to AC ratio at the inverter is approximately 1.024 to 1. The complete plant has 340 inverters and 81,600 PV modules for 20.89 MWp and 20.4 MWac planet capacity. Figure 5 shows the layout of a three-inverter section, detailing PV string connection up to the transformer connection. The rest of the system online diagram is repeatable as the overall plant is scalable.

5. Financial and Environmental Benefits

5.1. Financial Analysis

JUST electricity is billed based on a bracket scheme, as shown in Table 3.
As JUST consumes much more than 1000 kWh each month, most of the energy consumed is priced at the highest billing bracket. The average kWh cost for 2016 was calculated to be $0.366, with an annual electrical bill of $12.23 million USD. The latest government PV tenders have been awarded a price of $986 per kWp. Therefore, the designed system will cost approximately $21 million. The payback period of this project will include the capital cost in addition to the operational and maintenance costs. These calculations are illustrated in the following discussion.

Payback Period Analysis

The payback period analysis includes the investment cost of the PV plant and the operational and maintenance (O&M) costs. The (O&M) costs used in this discussion are obtained from similar PV plant projects which are currently operational in Jordan. These costs are summarized in Table 4.
PV modules’ cleaning is necessary to enhance the PV plant yield. This is especially important in the summer months, as dust buildup affects performance. Landscape maintenance is needed to keep landscape healthy and facilitate the maintenance of the plant; this includes weeding, which is important during the spring, when weed height actually introduces shading to the lower part of the panel. Generic maintenance refers to the periodic preventative maintenance needed to keep the plant working satisfactorily. Finally, a typical inverter lifetime is eight to 10 years, and the PV plant project lifetime is 25 years. Therefore, it is assumed that the inverters need to be replaced at years 9 and 18 of the project lifespan.
In order to determine the payback period of this project, the net present value of the project must be calculated. The net present value includes the plant capital cost (initial cost) and the total O&M costs reflected into the present year. The present worth of the total O&M costs can be calculated using (15):
O & M n w c = j = 1 N D F j * O & M j
where O&Mnwc is the present worth cost of the total O&M costs, DFj is the discount factor for year j, and O&Mj is the O&M cost for year j. It is worth mentioning that the inverter replacement cost is calculated for years 9 and 18 only. The discount factor for year j is a function of the nominal interest rate i and the inflation rate f and can be calculated using (16):
D F = ( 1 + f 1 + i ) j
In this paper, the nominal interest rate is 7% and the inflation rate is 3%. Using (16) and (17), the net present cost of the O&M costs is found to be equal to $20.7 million. Hence, the net present cost is equal to $41.7 million USD.
The expected PV plant generation in is shown in Table 5. The generation will decrease with time, as expected, due to the degradation phenomena of the PV modules.
Using the same nominal interest rate used above the estimated payback period of the PV plant is around four years and five months.

5.2. Environmental Benefits

According to the US Environmental Protection Agency (EPA), using eGRID, the US annual non-base load CO2 output emission rate, considered an accurate “Emission Factor” for electrical consumption, can be calculated using the following rate:
Electrical Consumption: 7.03 × 10−4 metric tons CO2/kWh
Therefore, the annual CO2 emissions due to electric consumption at JUST is equal to:
33,425,000 × 7.03 × 10−4 = 23,497.775 metric tons or 25.9 k t US equivalent.
As with any other higher education institution, not all students and academic staff are on campus on a daily basis. Thus, for a complete assessment of the impact of installing the PV plant, the Full-Time Equivalent (FTE) of students and employees was determined to normalize the campus CO2 reduction. A survey of the number of students registered per semester in 2016, in addition to course schedule, employee work hours, and academic staff course load for the different semesters were all considered in the FTE calculation, and the FTE for the university community (students, faculty, and staff) was calculated to be 16110 FTEs. Therefore, the installed PV plant reduces CO2 emissions by 1.6 t per FTE.
The maximum amount of CO2 a person should produce per year in order to halt climate change is 2.0 t CO2. The world average is 5 t, the average in Europe is 6.7 t, the average in the US is 16.5 t, and the average in Jordan is 3.4. These are country averages that include CO2 emission from work, public operations, and home. The CO2 emission reduction due to the JUST PV system brings the universities’ community average to below the 2.0 t limit.
So, installing this PV system not only saves a great deal of financial resources, but also has a tremendous environmental impact, with huge CO2 reduction.

6. Conclusions

This paper aims to meet JUST’s electrical energy demand by considering PV plant installation connected to the electrical grid using a net-metering technique. This was achieved by formulating an optimization problem in which the objective is to find the optimal PV plant size needed to meet JUST’s electricity demand and minimize the system cost. A detailed mathematical model of the PV plant was presented. The system uncertainties inherent in solar radiation and ambient temperature were modeled using Beta and Normal distributions. This stochastic optimization problem was solved using the Scenario Aggregation procedure. The optimal size of the proposed PV plant was found to be 19.64 MW. When considering MV losses, as well as commercial components, a 20.98 MW system was proposed. The proposed PV plant was found to be financially and environmentally efficient, with a payback period of four years and five months as well as a considerable reduction in CO2 emissions. The project was divided into two phases. The 5 MW Phase I has been completed and is operating according to design. Phase II is under tender and work should commence in the next few months.

Acknowledgments

We gratefully thank Jordan University of Science and Technology (JUST) for providing the data used for this study.

Author Contributions

H.A. derived the mathematical modeling; A.A. conceived the PV plant sizing procedure and performed the optimization; O.S. performed the plant design and the environmental benefits analysis; A.A. performed financial analysis.

Conflicts of Interest

The authors declare no conflict of interest.

References

  1. Bostan, I.; Gheorghe, A.V.; Dulgheru, V.; Sobor, I.; Bostan, V.; Sochirean, A. Resilient Energy Systems: Renewables: Wind, Solar, Hydro; Springer Science & Business Media: Berlin, Germany, 2012. [Google Scholar]
  2. Cabral, C.V.T.; Filho, D.O.; Diniz, A.S.A.C.; Martins, J.H.; Toledo, O.M.; Machado Neto, L.V.B. A stochastic method for stand-alone photovoltaic system sizing. Sol. Energy 2010, 84, 1628–1636. [Google Scholar]
  3. Bortolini, M.; Gamberi, M.; Graziani, A.; Pilati, F. Economic and environmental bi-objective design of an off-grid photovoltaic–battery–diesel generator hybrid energy system. Energy Convers. Manag. 2015, 106, 1024–1038. [Google Scholar] [CrossRef]
  4. Bendato, I.; Cassettari, L.; Mosca, R.; Williams, E.; Mosca, M. A stochastic methodology to evaluate the optimal multi-site investment solution for photovoltaic plants. J. Clean. Product. 2017, 151, 526–536. [Google Scholar] [CrossRef]
  5. De Prada-Gil, M.; Domínguez-García, J.L.; Trilla, L.; Gomis-Bellmunt, O. Technical and economic comparison of various electrical collection grid configurations for large photovoltaic power plants. IET Renew. Power Gener. 2016, 11, 226–236. [Google Scholar] [CrossRef]
  6. Di Somma, M.; Graditi, G.; Heydarian-Forushani, E.; Shafie-khah, M.; Siano, P. Stochastic optimal scheduling of distributed energy resources with renewables considering economic and environmental aspects. Renew. Energy 2018, 116, 272–287. [Google Scholar] [CrossRef]
  7. Tomar, V.; Tiwari, G. Techno-economic evaluation of grid connected PV system for households with feed in tariff and time of day tariff regulation in New Delhi–A sustainable approach. Renew. Sustain. Energy Rev. 2017, 70, 822–835. [Google Scholar] [CrossRef]
  8. Thomson, M.; Infield, D. Impact of widespread photovoltaics generation on distribution systems. IET Renew. Power Gener. 2007, 1, 33–40. [Google Scholar] [CrossRef]
  9. Skoplaki, E.; Boudouvis, A.; Palyvos, J. A simple correlation for the operating temperature of photovoltaic modules of arbitrary mounting. Sol. Energy Mater. Sol. Cells 2008, 92, 1393–1402. [Google Scholar] [CrossRef]
  10. Meral, M.E.; Dinçer, F. A review of the factors affecting operation and efficiency of photovoltaic based electricity generation systems. Renew. Sustain. Energy Rev. 2011, 15, 2176–2184. [Google Scholar] [CrossRef]
  11. Graham, V.; Hollands, K. A method to generate synthetic hourly solar radiation globally. Sol. Energy 1990, 44, 333–341. [Google Scholar] [CrossRef]
  12. Ettoumi, F.Y.; Mefti, A.; Adane, A.; Bouroubi, M.Y. Statistical analysis of solar measurements in Algeria using beta distributions. Renew. Energy 2002, 26, 47–67. [Google Scholar] [CrossRef]
  13. Klein Tank, A.; Können, G. Trends in indices of daily temperature and precipitation extremes in Europe, 1946–99. J. Clim. 2003, 16, 3665–3680. [Google Scholar] [CrossRef]
  14. Mertens, K. Photovoltaics: Fundamentals, Technology and Practice; John Wiley & Sons: Hoboken, NJ, USA, 2013. [Google Scholar]
  15. Fioriti, D.; Giglioli, R.; Poli, D.; Lutzemberger, G.; Vanni, A.; Salza, P. Optimal sizing of a mini-grid in developing countries, taking into account the operation of an electrochemical storage and a fuel tank. In Proceedings of the 6th International Conference on Clean Electrical Power (ICCEP), Santa Margherita Ligure, Italy, 27–29 June 2017. [Google Scholar]
  16. Askarzadeh, A.; dos Santos Coelho, L. A novel framework for optimization of a grid independent hybrid renewable energy system: A case study of Iran. Solar Energy 2015, 112, 383–396. [Google Scholar] [CrossRef]
  17. Wets, R.J. The aggregation principle in scenario analysis and stochastic optimization. In Algorithms and Model Formulations in Mathematical Programming; Springer: Berlin, Germany, 1989. [Google Scholar]
  18. Philip, G. Water, Life and Civilization: Climate, Environment and Society in the Jordan Valley|Water, Life and Civilization: Climate, Environment and Society in the Jordan Valley; International Hydrology Series; Mithen, S., Black, E., Eds.; Cambridge University Press: Cambridge, UK, 2012. [Google Scholar]
Figure 1. Grid-connected PV plant using the net-metering system.
Figure 1. Grid-connected PV plant using the net-metering system.
Sustainability 10 01275 g001
Figure 2. PV plant sizing procedure flow chart.
Figure 2. PV plant sizing procedure flow chart.
Sustainability 10 01275 g002
Figure 3. (a) Solar radiation average for one year; (b) average temperature for four seasons.
Figure 3. (a) Solar radiation average for one year; (b) average temperature for four seasons.
Sustainability 10 01275 g003
Figure 4. The relationship between coefficient of variation (COV) and optimal PV plant size.
Figure 4. The relationship between coefficient of variation (COV) and optimal PV plant size.
Sustainability 10 01275 g004
Figure 5. PV plant connection diagram.
Figure 5. PV plant connection diagram.
Sustainability 10 01275 g005
Table 1. Energy consumption of Jordan University of Science and Technology (JUST) for the last five years in GWh.
Table 1. Energy consumption of Jordan University of Science and Technology (JUST) for the last five years in GWh.
Month20122013201420152016
Jan2.5742.3942.2372.1452.338
Feb2.3962.4642.2772.1392.329
Mar2.3392.3052.4742.4852.527
Apr2.8332.7442.6852.6442.292
May2.8012.6032.8842.8632.910
Jun2.6263.4013.0083.1032.899
Jul3.4843.5463.6212.8823.310
Aug2.8482.7562.8323.3843.788
Sep3.1143.2492.6603.0942.968
Oct2.6012.3082.7622.4262.848
Nov2.4822.9042.7652.3042.695
Dec2.4152.4962.3042.4502.521
Total32.51333.17132.50831.91933.425
Table 2. Jenko PV module ratings.
Table 2. Jenko PV module ratings.
Rated power256 W
Max power voltage31.4 V
Max power current8.44 A
Table 3. JUST electricity billing brackets.
Table 3. JUST electricity billing brackets.
Consumption Bracket (kWh)Rate ($)
1–1600.059
161–3000.129
301–5000.153
501–6000.204
601–7500.238
751–10000.268
above 10000.375
Table 4. Summary of operational and maintenance (O&M) costs.
Table 4. Summary of operational and maintenance (O&M) costs.
Type of ServiceCost
PV modules cleaning$400/MWp/month
Landscape maintenance$700/MWp/month
Generic maintenance3% of the capital cost/year
Inverters replacement20% of the capital cost/nine years
Table 5. Expected lifetime PV plant yield.
Table 5. Expected lifetime PV plant yield.
YearGeneration kWhYield in m$YearGeneration kWhYield m$
132,760,00011.991427,518,40010.07
231,777,20011.631527,190,8009.95
331,122,00011.391626,863,2009.83
430,794,40011.271726,535,6009.71
530,466,80011.151826,208,0009.59
630,139,20011.031925,880,4009.47
729,811,60010.912025,552,8009.35
829,484,00010.792125,225,2009.23
929,156,40010.672224,897,6009.11
1028,828,80010.552324,570,0008.99
1128,501,20010.432424,242,4008.87
1228,173,60010.312523,914,8008.75
1327,846,00010.19

Share and Cite

MDPI and ACS Style

Abuelrub, A.; Saadeh, O.; Al-Masri, H.M.K. Scenario Aggregation-Based Grid-Connected Photovoltaic Plant Design. Sustainability 2018, 10, 1275. https://doi.org/10.3390/su10041275

AMA Style

Abuelrub A, Saadeh O, Al-Masri HMK. Scenario Aggregation-Based Grid-Connected Photovoltaic Plant Design. Sustainability. 2018; 10(4):1275. https://doi.org/10.3390/su10041275

Chicago/Turabian Style

Abuelrub, Ahmad, Osama Saadeh, and Hussein M. K. Al-Masri. 2018. "Scenario Aggregation-Based Grid-Connected Photovoltaic Plant Design" Sustainability 10, no. 4: 1275. https://doi.org/10.3390/su10041275

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop