3.1.2. Constraints
Before talking about the constraints of the multi-period coordinated load restoration model, it is necessary to introduce the branch flow model.
Figure 2 is the single-line topology diagram of the branch flow model, and the specific parameters are detailed in [
28]:
Vm and Vn are the voltage of the m-bus and the n-bus; Pmn and Qmn are the active power and reactive power at the m-bus side; zmn, rmn and xmn are the impedance, resistance and reactance of the branch mn; Imn is the current of the branch mn; Pin,m and Qin,m are the inject active power and reactive power of m-bus, respectively; Pin,n and Qin,n are the inject active power and reactive power of n-bus, respectively.
Then, the constraint conditions of the multi-period load restoration model mainly include the radial topology constraints of the distribution network, the operation constraints of the distribution network, the energy limit constraints of power supply sources, and the constraints of the switching number of load states.
After the fault occurs, some branches in the distribution network system are disconnected. Therefore, to restore as many critical loads as possible, it needs to rely on the switches in the distribution network to reconstruct the topology of the distribution network. At this time, it is necessary to ensure that the reconstructed distribution network maintains a radial topology. According to the graph theory, the radial topology constraints of the distribution network are as follows:
where
is the set of all buses adjacent to bus
i.
N1 is the set of all buses without bus 1 and
E is the set of all branches.
is the connection state of branch(
i,j) which is a 0–1 variable.
means the branch(
i,j) is connected and
means the branch(
i,j) is not connected.
and
are 0–1 variables which demonstrate the parent or child relationship between bus
i and
j. If bus
i is the parent bus of bus
j,
and
. If bus
i is the child bus of bus
j,
and
. If bus
i and bus
j are not connected,
.
Equation (4) describes the relationship between the parent-child bus variables and the connection states of branches. Equation (5) means every bus except the root bus has only a parent bus and the root bus of the distribution system in this paper is bus 1. Equation (6) means the root bus has no parent buses.
The constraints of distribution network mathematical model based on branch flow model are shown below:
where
N is the set of all buses.
vi,t is the square of the voltage magnitude of
i-bus at time
t.
Pij,t and
Qij,t are the active power and reactive power of branch(
i,j) at time
t.
rij and
xij are the resistance and reactance of branch(
i,j).
iij,t is the square of the current magnitude of the branch(
i,j) at time
t.
Sij,t and
si,t are the complex power of branch(
i,j) and the injected complex power of bus
i at time
t, respectively.
j:
ij represents the set of all buses
j which are downstream of bus
i.
zhi is the impedance of branch(
h,i) and
M is a large positive value.
and
are the complex power supplied by the power sources in bus
i and the complex load demand of bus
i, respectively, at time
t.
Equations (7) and (8) describe the relationship between the square of voltage magnitude of two buses. Equation (9) guarantees the complex power balance of every bus. Equation (10) shows that the injected complex power of the bus equals to the power source output minus the load demand. Equation (11) is the transformation of the power definition equation and Equation (12) is the calculation formula of the network loss.
Since Equation (11) is a nonconvex and nonlinear constraint which is difficult to guarantee the global optimal solution, the SOCR method is introduced to transform the constraint into:
The schematic diagram of SOCR is shown in
Figure 3.
Coriginal is the feasible region of the non-convex constraint before transformation, which is Equation (11).
CSOC is the convex feasible region after relaxation, which is Equation (13). If the relaxation process is accurate, Equation (11) is equivalent to Equation (13). The specific proof process is shown in paper [
29] and the error analysis of SOCR is shown in
Section 4.1.
A feasible load restoration strategy needs to ensure that the system is in a safe and stable status during the restoration process. The safe operation constraints that need to be considered are as follows:
where
Iij,max is the allowed maximum current of branch(
i,j).
Vi,max and
Vi,min are the allowed maximum and minimum voltage of bus
i.
G and
CS are the sets of buses, which have distributed generators and EV charging stations, respectively.
and
are the maximum active power and maximum reactive power which could be supplied by the distributed generators in bus
i, respectively.
Pdismax and
Pchamax are the maximum discharging and charging power of each EV.
Numi is the number of EVs in the charging station in bus
i.
Equations (14) and (15) guarantee that the branch currents and bus voltages are limited within the allowed range. Equation (16) describes that if branch(i,j) is not connected, the complex power of the branch is zero. Equations (17) and (18) show the upper limit and lower limit of the output of distributed generators and charging stations, respectively.
where
Ei,total is the total energy of the distributed generator in bus
i.
Ecar is the total battery capacity of each EV.
SOC is the interval length of state of charge (SOC), which could be used to restore the critical load and it is 0.6 (0.8–0.2) in this paper.
The distributed generators used to restore critical loads are mostly diesel generators or gas turbines with stable output, and their available energy is limited by reserved diesel or gas. Equation (19) guarantees the total output of distributed generators does not exceed the energy which could be supplied by the stored diesel oil or gas. After the EVs arrive at the charging stations and supply power to the distribution network, it is necessary to ensure that enough electric energy is reserved for the EVs to leave the charging stations and reach the destination. In the first stage of the model, assuming that the SOC of the EVs when reaching the charging stations is 0.8, Equation (20) ensures that the output of the charging stations during the blackout will not decrease the SOC of any EV to less than 0.2, to ensure the electric energy for the return travels of EVs.
In order to ensure the users’ electric power consumption experience, this paper assumes that after the load of a certain bus is restored, it will not be cut off until the blackout is over.
where
L is the set of the load buses and
T1 is the set of time period except the first time period.