Next Article in Journal
Evaluation of Structure and Corrosion Behavior of FeAl Alloy after Crystallization, Hot Extrusion and Hot Rolling
Next Article in Special Issue
Development of Bonded/Riveted Steel Anchorages of Prestressed CFRP Strips for Concrete Strengthening
Previous Article in Journal
Hot Deformation Behavior and Microstructure Evolution of Cu–Ni–Co–Si Alloys
Previous Article in Special Issue
Characteristics of Recycled Polypropylene Fibers as an Addition to Concrete Fabrication Based on Portland Cement
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Experimental Study on a Novel Shear Connection System for FRP-Concrete Hybrid Bridge Girder

Department of Roads & Bridges, Rzeszow University of Technology, 35-959 Rzeszow, Poland
*
Author to whom correspondence should be addressed.
Materials 2020, 13(9), 2045; https://doi.org/10.3390/ma13092045
Submission received: 23 March 2020 / Revised: 17 April 2020 / Accepted: 22 April 2020 / Published: 27 April 2020
(This article belongs to the Special Issue Polymer in/on Concrete)

Abstract

:
The study presents experimental results of an investigation on a novel shear connection system for hybrid bridge girders composed of laminated composite beams and concrete slabs. The special connector comprised of a steel plate and welded bolts is attached to beam’s top flange by adhesive bonding and with a preset torque of nuts. The study’s purpose is to check ductility, safety, reliability and robustness of the shear connection before its implementation in the first Polish composite bridge. Three static push-out tests and fatigue test were performed to evaluate the shear connection behavior under static and cyclic loading. The load–slip curves, shear capacity, fatigue strength and failure mechanisms of the novel shear connectors are discussed. The high-slip modulus indicates that the connectors can very efficiently promote the composite action. The ultimate resistance and the fatigue strength obtained from the test was about 12% and 66% higher than the characteristic resistance and the fatigue strength of common headed studs, according to Eurocode 4, respectively. An estimated global safety factor of 3.67 showed the high safety, reliability and robustness of the novel connection system. The study discusses the structural performance of the proposed connection system, demonstrating its technical suitability.

1. Introduction

Since the beginning of the XXI century, fiber-reinforced polymer (FRP) composites have become an integral part of the construction industry because of their versatility, high strength-to-weight ratio, enhanced durability, resistance to fatigue and corrosion, accelerated construction as well as lower maintenance and life-cycle costs. Due to these excellent performance characteristics FRP composites offer very promising options for a wide range of civil infrastructure applications, particularly in bridge engineering [1,2,3,4,5,6,7,8]. However, FRP composites in bridge application are also faced with several challenges [9]. These include relatively low stiffness, existence of brittle failure modes and high initial cost. To address these challenges hybrid FRP–concrete bridges have been designed and constructed since the end of XX century [10,11,12,13,14]. The motivation for the design approach is to fully utilize the respective material properties of FRP and concrete, i.e., concrete’s stiffness and high compressive strength and FRP’s high tensile strength. In fact, there are several advantages with the FRP–concrete hybrid girders, referring to the increase of flexural stiffness thus reducing deformability and preventing the buckling phenomena of the FRP profiles or shells. Moreover, the “pseudo-ductile” behavior, necessary for bridges and the existence of composite action between the FRP beam and the concrete slab are a serious advantage of these girders [15,16,17,18,19,20].
In these hybrid systems, a strong FRP–concrete connection is an indispensable prerequisite to achieve structural integrity. The design of efficient slab-to-beam connection is the most challenging topic in the development of hybrid bridge girders. The efficiency of slab-to-beam joint governs the overall behavior of the formed bridge superstructure. Composite action, structural redundancy and system ductile characteristic are main objectives when designing connections for hybrid girders. In connections with composite action, the efficiency of shear transfer and constructability are major factors directing the connection design. The need for efficient and reliable load carrying joints that can endure long-term fatigue and environmental attacks has become apparent.
Concluding from the existing literatures, several types of shear connections have been researched, listed as follow: coated sand layer [21], adhesive [22], ribs and indents [23,24], steel studs or bolts [19,25,26], FRP dowels [27], FRP shear key [28] and perforated FRP rib [29]. Hence, far, most FRP–concrete connections have utilized joining in which conventional steel shear studs or bolts are used to provide composite action. These types of connections have a proven history in the civil engineering domain, therefore are generally accepted by bridge engineers. However, these connections are developed for common steel–concrete composite bridge girders. Since FRP beams are different from steel beams in constitutive materials and structural forms, efforts shall be taken to develop adapted connection techniques for hybrid FRP–concrete girders. The steel shear studs have relatively high shear capacity, but large slippage occurred along the interface, i.e., a lower composite action was obtained. Moreover, in shear stud connections holes are often required at some desired spacing in the top flanges of the FRP beam. The cut-outs bring concerns about the stress concentrations and possible vulnerability to fatigue loads and environmental attacks in the FRP beams cut-out regions. Efforts must be taken to protect the cut-out regions from environmental attacks. Although several connections which resemble steel shear studs have been proposed and tested, the lack of test data and design recommendations limits the use of FRP–concrete hybrid girders. To address the above mentioned concerns the modified connection system comprising welded bolts and epoxy adhesive was developed and implemented in the first Polish FRP composite bridge.
The innovative hybrid idea of a FRP composite–lightweight concrete structural system for the heaviest traffic load class bridges has been proposed and accepted as the subject of the demonstrative R&D project ComBridge, performed by the research-industry consortium led by Mostostal Warszawa S.A., one of the biggest Polish contractor in the field of civil infrastructure. As a result, the first Polish FRP bridge was developed and built in late autumn 2015 [14]. Due to the lack of commonly accepted design procedures, the whole designing process was strongly supported by laboratory testing. The comprehensive material testing and the structural tests were carried out, comprising among others: the evaluation of strength and stiffness of a lightweight concrete (LWC) deck slab reinforced with glass fiber-reinforced polymer (GFRP) composite bars [30], the strength and fatigue tests on connections between LWC slab and FRP beam (reported in this study), the comprehensive research on the structural behavior of the full-scale hybrid FRP composite–concrete bridge girder [20] and finally the field evaluation of the hybrid FRP–concrete road bridge [31].
This study presents the results of experimental research concerning the shear behavior of the novel connection system between the FRP beam and the concrete slab. The special connector comprised of a steel plate and welded bolts is attached to beam’s top flange by adhesive bonding and with a preset torque of nuts. Several push-out tests were performed on connector’s specimens made of composite laminates connected to concrete slabs. The connection performance is studied with particular relevance to slip behavior and shear capacity. Further analysis reveals the failure mechanism and the fatigue strength of the connection system as well. The study summarizes the results of the static and fatigue tests and discusses the structural performance of the proposed connection system, demonstrating its technical suitability. Furthermore, the estimated global safety factor shows the high safety, reliability and robustness of the novel connection system. The applicability of Eurocode 4 [32] procedures to predict static and fatigue strength of the connection and to check its ULS/SLS design provisions is also demonstrated.

2. FRP-Concrete Hybrid Bridge Girder and Shear Connection System

The novel hybrid FRP-concrete bridge girder was designed to be used in the first Polish road bridge made of FRP composites [14]. The hybrid girder consists of two main parts: a FRP composite beam with open, trapezoidal cross-section and a concrete slab (Figure 1). The FRP composite beam is 1025 mm deep, 1550 mm wide at the top and 621 mm wide at the bottom. The both top flanges of beam are 301 mm wide and are integrated with the bottom plate by means of two slightly inclined webs. The individual laminates have the thickness of about 25 mm, 22 mm and 19 mm for top flanges, webs and bottom plate, respectively. The top flanges and webs are made of solid and sandwich GFRP laminates, respectively, whereas the bottom plate has a hybrid glass/carbon fiber-reinforced polymer solid structure [20]. On two top flanges the stay-in-place (SIP) formwork is supported to facilitate concrete slab casting. The SIP formwork is made of a 33.4 mm thick sandwich plate built alike webs.
The 180 mm thick slab was made of 35/38 class LWC based on the lytag type aggregate with density ρ = 1968 kg/m3. The slab was reinforced longitudinally and transversally with two grids made of 12 mm ribbed GFRP rebars spaced every 120 mm in each direction. The LWC slab was connected to FRP beam by means of novel shear connectors made of M20 class 4.8 bolts welded to a rectangular steel plate (Figure 2). The single connector consisted of 8 bolts welded in two rows to 10 mm thick steel plate of 240 × 660 mm in plan. The connectors were attached to bottom surface of beam’s top flanges with epoxy adhesive.
The developed shear connection system combines two convectional means used for slab-to-beam connections in hybrid FRP-concrete girders: studs and adhesive [29]. For studs the typical M20 bolts are used with belonging nuts and washers. Several bolts are welded to a steel plate in one or two rows with transverse and longitudinal spacing according to an appropriate design (Figure 2). The connector is deep galvanized to achieve protection against corrosion compared to FRP composite. To fasten the connector to the beam’s top flange, holes drilling is required in laminate, and the number, arrangement and diameter of holes correspond to design layout of studs. Subsequently the adhesive layer is place on the relevant areas from the bottom of the girder’s top flange and the connector is attached to laminate by bonding. Finally, steel washer and two nuts are installed on each bolt: the first screwed with a preset torque helps a proper bonding, the latter is placed on the top of the bolt to create a headed stud and to increase tear-out capacity of the connection (Figure 2).
The novel connection system differs from common studs in steel–concrete composite systems and bolts in FRP-concrete hybrid systems. In steel-concrete composite systems the headed studs are usually welded to top flange of steel girder. In FRP-concrete hybrid systems shear connectors are usually bolted to the FRP top flange using a preset torque. Here, combining welded headed bolts with a preset torque and adhesive in the connection a relatively high shear capacity is ensured and slippage along the interface is expected to be considerably limited. Moreover, epoxy placed around the laminate holes and at the interface protects the cut-out regions from environmental attacks and stress release is also induced in the laminate around the hole.

3. Shear Connection Design

Despite the load-slip behavior of the shear FRP-concrete hybrid connections is different from that in steel-concrete composite systems [19,25,26], the conventional design method provided in Eurocode 4 [32] was used in bridge design. It was assumed, that the welded bolts transmitted the longitudinal shear force between the concrete and the FRP beam, ignoring the effect of natural bond between the two and neglecting adhesive bond as well. The push-out testing reported in this study was undertaken to check if such an assumption were valid for the novel connection system, which could facilitate its further design. Thus, the applicability of Eurocode 4 [32] procedures to predict static and fatigue strength of the connection and to check its ULS/SLS design provisions was also examined.
The design procedure (described in Appendix A) based on Eurocode 4 [32] provisions was applied to determine the exact number and spacing of shear studs in the hybrid girder taking into account the size and strength of M20 bolts chosen for studs. As a result, along the girder with the length of 21.0 m the total number of 480 studs were mounted in 4 rows (two rows per a flange) with longitudinal spacing of 180 mm. For such a stud arrangement the relevant shear forces per unit length vL,Ed and corresponding shear forces VEd were determined according to Formulas (A6)–(A8) in Appendix A and thus the shear force per one stud was established to be assumed in testing program (Table 1).

4. Static Tests

To evaluate the strength of shear connection system the push-out tests were carried out on full-scale specimens of shear connectors. Since there is no standard for testing this type of joints with FRP elements, it was decided to use the specimen presented in the main part of Eurocode 4 [33] for joints validation in steel–concrete composite structures. Specific push-out tests were carried out and the slabs and the reinforcement were suitably dimensioned in comparison with the girders for which the test was designed. The bonding at the interface between GFRP flanges of the beam and the concrete slab was not prevented as did actually on-site. From these push-out tests the load-slip and load-displacement performance, the failure load and the mode of failure were obtained.

4.1. Specimens’ Fabrication

The specimens for push-out tests were composed of two GFRP C-sections, bonded together to create a rectangular tube, and two concrete slabs joined to GFRP by shear connectors (Figure 3). Fabrication of specimens included: (a) manufacturing GFRP sections and bonding them in the shape of rectangular tube, (b) drilling holes in relevant laminates of the tube with predefined spacing and diameter, (c) fabricating two steel connectors by welding bolts to steel plates, (d) setting and bonding the steel connectors inside the tube with epoxy adhesive, (e) making the plywood formwork and setting the embedded GFRP reinforcing bars; (f) casting and curing the concrete (Figure 4). The total of 6 specimens were prepared: three for static tests (denoted S1–S3) and the subsequent three for fatigue test (denoted F4–F6).
The GFRP C-type sections were fabricated by infusion and their laminates had the same thickness and stacking sequence as the top flange of the girder. Structural epoxy adhesive was used to join both sections in a rectangular tube with the outer dimensions of 535 × 390 × 303 mm. The steel connectors were made of two M20 class 4.8 normal strength bolts spaced at 100 mm and welded to S355 class steel plate of 250 × 240 × 10 mm. The connectors were attached by bonding to the GFRP tube with structural epoxy adhesive SPABOND 340 LV HT with 3 mm bondline. The bolts were embedded in the concrete slab on the length of 150 mm. The relevant steel washers were used to disperse the stress caused by torqueing nuts. Additional nuts were screwed at bolts’ top to serve as a head. Two 390 × 375 × 180 mm concrete slabs were made of the LWC class 35/38 reinforced with two grids (per slab) made of 12 mm ribbed GFRP bars with spacing of 80 × 80 mm.
The basic material properties of GFRP’s laminas and LWC used for specimens’ elements were determined by testing and are listed in Table 2 and Table 3. The basic material properties of steel bolts class 4.8 were taken from the relevant code [34] as follows: tensile strength fu = 400 MPa, yield strength fy = 320 MPa and modulus of elasticity E = 200 GPa.

4.2. Test Setup

The specimens were tested in the universal test machine Schenck with 630-kN capacity. During the static tests, the rotation of the two lateral LWC blocks was prevented. Load was applied to the specimens by a hydraulic actuator. To prevent local failure of laminates the load was applied to the specimens through a set of steel plates placed on the laminates by epoxy layer (Figure 5). The loading sequence of each specimen was as follows: five cycles of loading up to characteristic load level of PEd,k = 87.92 kN, subsequently five cycles of loading up to design load level of PEd,d = 125.36 kN, and finally loading up to specimen’s failure. The both intermediate load levels were determined taking into account the maximum shear force per stud (Table 1) multiplied by four studs of the specimen. The loading rate was 2.0 kN/s.
Four linear variable differential transducers (LVDTs) were installed to measure the relative slip between the GFRP and the concrete. Figure 6 shows the location of these LVDTs on the specimen (measurement points P1/1, P1/2, P3/1 and P3/2). Additionally, two LVDTs were installed to check the loading conditions and displacement of the specimen’s center (measurement points P2/1 and P2/2). The HBM Spider Quantum X acquisition system was used to record the measurement data with 2 Hz frequency.

4.3. Test Results

The basic outcome of the push-out test is a load-relative slip curve. This plot (typically average of all slip measurements) enables us to determine the first slip load Ps and corresponding slip value δ1, both necessary for slip modulus kslip estimation. Ultimate load Pu and corresponding ultimate slip δu let us to determine shear connecting capacity. The failure mode indicates the weakest elements of the connection. All of these outcomes are described and illustrated below for all specimens tested.
In specimen S1 a cracking sound was heard at a total load level of 255 kN. It was the first relative slip of 0.12 mm, when the adhesion between the GFRP and the concrete was lost (hereafter named debonding). As load continues, the second cracking sound and slip were noted at almost the same load level and finally two bolts on one side suddenly fractured at approximately 311 kN (Figure 7). Bolts on the other side of the specimen did not fail. Figure 8 shows the average load–slip curve of specimen S1. As far as the specimen’s failure mode is considered, the pure shear failure of both bolts were observed and neither concrete cracking nor bearing or shear-out failure of the laminate were exhibited (Figure 9).
In specimen S2, the loading phenomenon was very similar to that in S1, initial cracking sound was heard, and the first slip occurred at approximately 245 kN and the ultimate load was 315 kN. The bolts on one side suddenly fractured, while bolts on the other side did not fail. Concrete cracking and bearing or shear-out failure of the laminate were not observed on the respective surfaces of the specimen S2. However, two times bigger first slip value of 0.30 mm was observed in this case, due to premature slip of 0.065 mm that occurred at about 160 kN (Figure 10). This is probably attributed to the worse GFRP surface condition and induced that the bolts gradually slipped into a bearing region around the holes in the GFRP (Figure 11).
In contrary to the specimens S1 and S2, the S3 specimen exhibited almost no slip until the load of 405 kN was reached and the first significant slip took place. After that the specimen behaved almost linearly until the second debonding between the GFRP and LWC slab occurred at 458 kN. However, the careful checking of the specimen after failure revealed that the load applied to the specimen was transferred to the LWC slab mostly by the concrete surface protrusion (Figure 12). The protrusion was made during concrete casting due to false formwork execution. The slight initial slip at 140 kN occurred only on one side of the specimen due to initial crushing of protrusion and was negligible (Figure 13). When the protrusion had crushed at 458 kN, the load rapidly decreased to 281 kN and the specimen behavior came back to the expected one (as for specimens S1 and S2). The bolts on one side suddenly fractured at the ultimate load of 342 kN, while bolts on the other side did not fail. Concrete cracking and bearing or shear-out failure of the laminate were not observed on the respective surfaces of the specimen S3. The specimen S3 had higher ultimate shear capacity and smaller slip than S1 and S2, which is attributed to different performance in early load stage due to concrete surface protrusion.
The push-out experiment demonstrated that there were no significant differences between the behaviors of three specimens S1–S3 except concrete protrusion effect in specimen S3. The load–displacement curves of three specimens were almost parallel up to first slip (debonding), resulting in a similar stiffness of three specimens (Figure 14). (Note: the initial displacement in the range of 0–50 kN is due to steel package load adjustment). After two slips attributed to two slip planes of specimens, the load was transferred to the slabs solely by bolts. The behavior after debonding was always nonlinear up to the failure, attributed to yielding of bolts. Specimens finally failed due to pure shear fracture of bolts and no cracking, bearing or shear-out failure around the holes of the GFRP and concrete were observed. The results showed that the capacity of the bolts were sufficient to provide reverse strength after debonding and therefore the specimens did not fail immediately after debonding. The main quantitative outcomes of the push-out tests are provided in Table 3. As can be seen in this table the ultimate failure force was between 311–342 kN with a maximum difference of a 9.9%.

5. Fatigue Test

5.1. Test Setup

The main purpose of the fatigue test was to determine the fatigue life and a possible reduction of static strength of the shear connection subjected to unidirectional cyclic loading. The experimental program consisted of a series of 3 specimens F4–F6 tested with constant amplitude loading. The specimens manufactured for the fatigue test exhibited identical geometry to those of the static strength determination. The effect of fatigue loading were investigated with varying parameters: minimum load Fmin, peak load Fmax and loading range ΔF. During the cyclic test, the load from the actuator load cell and the displacement of the specimen were measured, the latter by four LVDT’s in P1 and P3 measurement points. Cyclic tests were conducted under sinusoidal control waveforms with a load frequency of 2 Hz.
In three static tests performed previously (S1–S3) the mean value of the ultimate static load Pu,av was determined (Table 4). This value represented the reference parameter for the relative values of loading required for cyclic tests. Cyclic tests were conducted for loading range approximately 30%–60% of Pu,av with the stress ratio R = 0.1. Three load controlled cyclic tests on specimens F4, F5 and F6 were performed to determine the fatigue life N of the shear connection. The loading parameters of fatigue test are summarized in Table 5. After reaching the design number of cycles (2 million) one of these three test specimens did not fail and it was statically loaded to failure under displacement control to obtain the reduced static strength after high cycle preloading.

5.2. Test Results

During the cycling tests, the displacement range of the specimens was recorded while keeping the load range constant. The displacement was increasing rapidly due to crack initiation at the welding region as shown in Figure 15. Numbers of cycles at crack initiation and at failure are summarized in Table 6.
The general view of the fatigue failure mode of the specimen F4 is shown in Figure 7. Almost vertical displacement of one slab due to sudden fracture of two bolts was exhibited without affecting the second slab at all. To investigate failure mode, the concrete slab was separated from the GFRP tube and the fractured surfaces were examined. Fatigue failures occurred at weld toes (Figure 16). The examined fracture surfaces consisted of the typical dull fatigue fracture formed by propagating cracks and no bright forced fracture zones due to forced shear fracture were visible. The thorough examination revealed the crack initiation at point at the bolt shank in the heat affected zone above the melting line and successive horizontal crack propagation through the shank. In Figure 16 the GFRP laminate shear-out failure around the predrilled holes is also shown.
Since the specimen F6 did not fail after 2 million cycles of loading, the fatigue test was stopped and the specimen was loaded statically in the same way as specimens S1–S3 to evaluate possible reduction of the static strength of the shear connection subjected to fatigue loading. The specimen F6 exhibited no slip until the load of 320 kN was reached (Table 4). Similar to specimen S3 the load applied was transferred initially by the concrete surface protrusion. The protrusion was crushed at 365 kN, the load rapidly decreased, and the specimen started to transfer the load only by bolts. The bolts suddenly fractured at the ultimate load of 315 kN, what was similar ultimate value as for specimens S1 and S2. Failure mode was similar as well. Hence no reduction of the static strength of the shear connection was revealed when subjected to cyclic loading (Figure 17).

6. Discussion

6.1. Load-Slip Behavior

The load-slip curves based on push-out tests are evaluated to assess the shear capacity and the ductility of the novel shear connectors. The load-slip curve can be divided into three stages (Figure 8). Linear behavior of the load-slip curve was observed for the first stage up to the first slip. The second stage showed a sudden load reduction caused by loss of the adhesion (or debonding) between the GFRP and the concrete (however, no adhesive was applied). The linear increase and sudden decrease were exhibited the second time in specimens S1, S3 and F6 due to the second slab debonding. Nonlinear behavior of the load-slip curve was observed in the third stage, attributed to the hardening of the connector. In contrary to typical stud connection behavior the final stage showed no softening and no stiffness reduction after the load exceeded the ultimate resistance of the bolts. It can be seen from Figure 8 that the load-slip behavior of the GFRP-concrete specimens are more ductile than that of the typical steel concrete specimens. This may be a preferable failure mode for designing of FRP–concrete hybrid girders with the use of the novel shear connectors.
The load-slip behavior of the connector is an important parameter to calculate the hybrid girder overall deformation considering the slip effect [17] and to assess the composite action. The comparison of the slip modulus kslip is often used to evaluate shear connections. The slip modulus is given as follows:
kslip = Ps/n δ1
where: kslip is the slip modulus for a single bolt, n is the number of bolts in the specimen (here n = 4) and δ1 is the slip at the load of Ps, after which the nonlinear behavior becomes notable.
The outcome of kslip for the novel connector is listed in Table 4. For specimen 2 in parenthesis kslip value is also given after deducting the premature slip 0.065 mm (Figure 10), which was rather untypical behavior of the specimen. The average slip modulus kslip is approximately 523 kN/mm, indicating that the connectors can promote the composite action very efficiently, than other solutions, where kslip was obtained in the range of –200 kN/mm [25,29,35].

6.2. Failure Mechanism

According to the findings published in the existing literature, there have been two typical failure modes in the push-out specimens [17,19,25,26]: bolt shank shear (mode 1) and FRP flange shear-out (mode 2). The first mode is similar as in steel–concrete connections in composite beams, the latter is commonly observed in FRP composite connections due to a relatively low shear strength of FRPs. Only first failure mode, bolt shank fracture, was found in the current tests, which revealed bolt shank fracture to be determined by cross-sectional area and material strength. These results match well with previous findings [19,25,26], allowing us to deduce that the use of steel studs in FRP and concrete connections is similar to their use in steel–concrete composite beams. The guidelines in the relevant codes (for example [32,33]) can be used to predict the strength of the novel shear connection.
Due to small modulus of elasticity of GFRP, the hybrid girder may have problems with serviceability limit states and especially in deflection. Therefore, the behavior of the connection should be rigid. Solution of connection with steel bolt shear connectors reached ductile behavior but the debonding between surface of GFRP and concrete slab occurred before the maximum load was reached. In order to increase the initial stiffness of the connection, coarse sand coating of the GFRP surface can be applied.
The weld toe fracture in welds joining shear bolts to steel plate was the crucial failure mode in fatigue. In Figure 16 the GFRP laminate shear-out failure around the predrilled holes is also shown. This failure mode exhibited in cyclic loading. Despite this mode was not decisive for the fatigue life of a specimen, an effective way to improve shear capacity is to add additional fiber layers (preferably 45°) to top flange’s laminate.

6.3. Shear Capacity

Experimentally obtained ultimate resistance of the shear connector per bolt (at failure load Pr) was defined by Equation (2):
Pr = Pu/n
where: Pu—experimentally obtained maximum load of push-out tested specimens; n-total number of bolts in specimen (here n = 4).
The average ultimate resistance of the shear connector per bolt is 80.67 kN and minimum / maximum values are −3.6%/+6.0%, respectively (Table 4). The relevant values from the literature were typically in the range of 20–50 kN, depending on stud’s steel or bolt class and concrete class [17,19,25,26,35]. This difference indicates that the use of either welding or bonding improved the novel connection capacity. To predict the ultimate load of failure mode 1, the literature (e.g., [17,25,26]) and current design codes, including Eurocode 4 [32], have provided Equation (2) in Appendix A for similar failure in a steel–concrete composite beam. Because tensile strength could not be directly used to calculate shear failure, the reduction factor ψ (usually 0.6–0.8) was introduced to compute the shear strength of the connector; in Eurocode 4 ψ = 0.8 [32]. In the present study the average ψ was obtained as 0.9. However, test data from [17] and [26] suggest ψ = 0.6 for FRP–concrete shear bolt connections. The reason of this difference can be the combined use of bolts and epoxy adhesive in the novel connection, what may result in an increase in ultimate resistance of the bolts. The authors of [17] and [26] determined this reduction factor to be 0.6 for the bolted only specimens, not for those with the bolted—bonded connection. On the other hand, according to [25] the comparison of specimens with and without epoxy suggests that ψ is larger than 1.0 in the combined joints, which does not agree with current theory, but supports the abovementioned reason.
The ultimate strength of shear connection obtained from static tests was also compared with those calculated by design codes of Eurocode 4 [32]. In terms of bolt shank shear capacity, the average ultimate resistance obtained in the test is 11.8% higher (80.67/72.15 = 1.118) than the characteristic resistance of one headed stud according to Eurocode 4 [32]. Nevertheless, the code slightly underestimates the shear capacity of the connection, it can be used to predict the static strength of the connection and to check its ULS/SLS design provisions.
Taking into account test limitations it can be said that the design code estimates the shear strength of the novel connection quite properly, with acceptable accuracy and on safe side. When compared to maximum characteristic shear force per stud obtained in bridge design PEd = 21.98 kN (Table 1) the global safety factor of the shear connection can be estimated as follows: 80.67/21.98 = 3.67 showing the high safety, reliability and robustness of the novel connection system.

6.4. Fatigue Strength

Eurocode 4 [32] specifies the fatigue strength curve of an automatically welded headed stud as follows:
(ΔτR)m·NR = (Δτc)m × Nc
where: ΔτR is the stress range; m is the slope of the fatigue strength curve with the value m equal to 8; NR is the number of stress-range cycles; Δτc is the reference value at Nc = 2 million cycles with Δτc equal to 90 MPa.
For studs in lightweight concrete the fatigue strength should be determined in accordance with Equation (3) but with ΔτR replaced by ηE ΔτR and Δτc replaced by ηE Δτc, where ηE is given in Eurocode 2 [34] as 0.955.
A comparison between test results and design values according to Eurocode 4 [32] is summarized in Table 6 and presented in Figure 18. The test results are in good agreement with the given prediction according to Eurocode 4 [32]. The fatigue life of the novel shear connection is slightly longer than the design value for typical shear studs, especially for higher stress range. From a linear regression analysis of the test results, the slope of the fatigue strength curve m and the reference value at two million cycles Δτc are calculated as 12.95 and 142.6 MPa, respectively. Thus, the fatigue strength obtained from the fatigue test is 142.6/(0.955· 90) = 1.66 higher when compared to the fatigue strength according to Eurocode 4 [32].

7. Conclusions

A reliable connection between FRP and concrete slab in hybrid bridge girders is important to prevent sudden and brittle failure. The use of steel shear connectors can reach this robustness. This study demonstrated the feasibility of the connection by shear bolt connectors between concrete slab and GFRP beam. Bolts together with adhesive achieved great properties in performed push out tests.
This study presents experimental results of push-out and fatigue tests on a novel shear connection system joining the GFRP laminated beam and the concrete slab of the hybrid bridge girder. Three static push-out tests and fatigue test were performed to evaluate advantages of steel shear connectors in promoting the connecting of GFRP girder and concrete slab. The load–slip curves, shear capacity, fatigue strength and failure mechanism of the novel shear connectors are discussed. The following conclusions can be drawn from this study:
the load—slip behavior of the GFRP–concrete specimens is more ductile than that of typical steel-concrete specimens;
the average slip modulus kslip value is approximately 523 kN/mm, indicating that the connectors can promote the composite action very efficiently;
bolt shank fracture is the only failure mode, found in the static tests, while the weld toe fracture in welds joining shear bolts to steel plate was the failure mode in fatigue; these may be a preferable failure modes for designing of FRP–concrete hybrid girders with the use of the novel shear connectors;
the average ultimate resistance obtained from the test is about 12% higher than the characteristic resistance of shear studs according to Eurocode 4 [32];
the fatigue strength curve slope m = 12.95 and the reference value Δτc = 42.6 MPa at two million cycles are determined; thus, the fatigue strength obtained from the test is 1.66 higher when compared to the fatigue strength of shear studs according to Eurocode 4 [32];
the global safety factor of the shear connection is estimated as 3.67 showing the high safety, reliability and robustness of the novel connection system,
Eurocode 4 [32] slightly underestimates the shear capacity and the fatigue strength of the novel connection; however, despite this conservatism this code can be used to predict the strength of the connection and to check its ULS/SLS design provisions.
The results of experimental research concerning the shear behavior of the novel connection system between the GFRP beam and the concrete slab revealed, that galvanized steel headed bolt connectors combined with epoxy adhesive may be a very good option to obtain ductile, safe, reliable and robust behavior for the shear connections of GFRP-LWC hybrid bridge girders subjected to static as well as fatigue loading. Therefore, it was decided to implement it as the shear connection in hybrid girders for the first Polish FRP bridge.

8. Patents

Patent No. 231211: “Road bridge superstructure”, E01D2/04, Polish Patent Office, Warsaw, Poland, 02/2019.

Author Contributions

Conceptualization, M.R. and M.K. and T.S.; methodology, M.R. and M.K.; code analysis, M.R.; investigation, M.R. and M.K.; resources, M.R. and T.S.; data curation, M.R.; writing—original draft preparation, M.R. and T.S.; writing—review & editing, T.S.; visualization, M.R.; supervision, T.S.; project administration, T.S.; funding acquisition, T.S. All authors have read and agreed to the published version of this manuscript.

Funding

This research was funded by the National Centre for Research and Development, Poland as well as the industry partners: Mostostal Warszawa S.A. and Promost Consulting, Rzeszow (Contract No. DEM-1–041/001).

Acknowledgments

This research was carried out within the framework of the R&D project: “ComBridge—An innovative FRP composite road bridge”. The project was implemented as part of a pilot program entitled: “Support for research and development works in the demonstrative scale DEMONSTRATOR +”.

Conflicts of Interest

The authors declare no conflict of interest.

Appendix A

To determine the number and the longitudinal arrangement of shear connectors for the hybrid bridge girder the characteristic resistance of the headed stud PRk was calculated according to Eurocode 4 [32] as:
PRk = min(PRk1,PRk2),
where:
PRk1 = 0.8 × fu × ( πds2)/4—shear resistance of stud’s shank,
PRk2 = 0.29 × αs × d s2 × √(fck × Ecm)—concrete crushing resistance,
and fu—specified ultimate tensile strength of stud’s material, fck—characteristic cylinder compressive strength of concrete at the age considered, Ecm—secant modulus of elasticity of concrete, ds—nominal diameter of bolt shank, while αs:
αS = 0.2 × (hsc/ds + 1) for 3 ≤ hsc/ds ≤ 4 or αs = 1 for hsc/ds > 4a = 1,
and hsc—the overall nominal height of the stud.
Taking into account the following parameters assumed in bridge design [14]:
fu = 400 MPa—for 4.8 class bolt acc. to Eurocode 3–1-8 [34],
fck = 35.0 MPa—approved by testing for 35/38 class LWC acc. to Eurocode 2–1-1 [36],
Ecm = 26.968 GPa—determined by testing for 35/38 class LWC acc. to Eurocode 2–1-1 [36] and for concrete density ρ = 1968 kg/m3,
d = 16.94 mm—nominal dimeter for M20 bolt acc. to [37],
hsc = 150 mm,
and the following factors according to [32]:
γV = 1.25—the partial factor for ultimate limit states (ULS),
ks = 0.75—the reduction factor for serviceability limit states (SLS),
the design resistances of one headed stud are given as follows:
PRd,ULS = PRk/1.25,
PRd,SLS = 0.75 × PRd,ULS,
thus finally:
PRk1 = 72.15 kN—shear resistance of stud’s shank,
PRk2 = 80.91 kN—concrete crushing resistance,
PRd,ULS = 57.72 kN—design resistance for ULS verification,
PRd,SLS = 43.29 kN design resistance for SLS verification.
To check if the proposed shear connection system is appropriate for the bridge in question the static analysis of the bridge span was carried out to determine the longitudinal shear forces between the concrete slab and the GFRP beam. The model of orthotropic plate was applied for the static analysis, in which the hybrid girders are treated as trapezoidal ribs [38]. The bridge loads and their combinations were taken according to Eurocode 1 [39]. The resultant maximum inner forces (MEd, VEd) were determined and considered to prepare the test program for the structural performance verification of shear connection system as described below.
The longitudinal shear force per unit length vL,Ed at the interface between the concrete slab and the FRP beam was determined as follows:
vL,Ed (x) = VEd (x) × (Sc/Ic),
where: VEd (x)—shear force for the considered load case, Sc—static moment of area of concrete slab with respect to the center of gravity of the composite cross-section and un-cracked cross-section properties; Ic—second moment of area (moment of inertia) of the hybrid (composite) cross-section.
The maximum shear forces from static analysis of the bridge span for the worst load combination (including shrinkage and temperature) were as follows [31]:
VEd,k = 21.98 kN—maximum characteristic shear force for SLS checking,
VEd,d = 31.34 kN—maximum design shear force for ULS checking.
The modular ratio used in the calculation of Sc and Ic is the same as the one used to calculate the corresponding shear force contribution for each single load case. Taking into account the following values [31,38] we obtained:
EFRP = 71.924 GPa—equivalent modulus of elasticity of FRP beam with respect to bottom edge,
Ecz (t) = 26.986—short term modulus of elasticity of concrete slab,
Ecw (t) = 18.549—long term modulus of elasticity of concrete slab,
nLz = EFRP/Ecz (t) = 71.924/26.986 = 2.665—modular ratio for short term loads,
nLw = EFRP/Ecw (t) = 71.924/18.549 = 3.878—modular ratio for long term loads including creep,
and:
Ac = 0.18 × 2.62 = 0.472 m2—cross-section area of concrete slab,
zz = 97.18 mm—distance between gravity center of concrete slab and neutral axis of hybrid (composite) girder for short term loads,
zw = 133.20 mm—distance between gravity center of concrete slab and neutral axis of hybrid (composite) girder for long term loads including creep,
The final values of the relevant moments and the corresponding maximum shear forces per unit length vL,Ed are as follows:
Scz = 0.0172 m3—static moment of area for short term loads,
Scw = 0.0162 m3—static moment of area for long term loads,
Icz = 0.0188 m4—second moment of area for short term loads,
Icw = 0.0180 m4—second moment of area for short term loads.
Finally:
max (vL,Ed,k) = 488.40 kN/m,
max (vL,Ed,d) = 696.43 kN/m.
In max (vL,Ed,k) and max (vL,Ed,d) values shrinkage is also included. In each cross-section of the girder there should be enough studs to take up all the shear force per unit length. The following should be therefore verified at all abscissa x:
vL,Ed,k (x) ≤ (Ni/li) × PRd,SLS—for SLS verification,
vL,Ed,d (x) ≤ 1.1 × (Ni/li) × PRd,ULS—for ULS verification,
where:
li—length of segment (the girder total length is divided into n segments),
Ni—number of studs per row in segment (constant density per segment).

References

  1. Burgoyne, C. Advanced composites in civil engineering in Europe. Struct. Eng. Int. 1999, 9, 267–273. [Google Scholar] [CrossRef]
  2. Holloway, L.C.; Head, P.R. Advanced Polymer Composites and Polymers in the Civil Infrastructure; Elsevier Science Ltd.: London, UK, 2001. [Google Scholar]
  3. Keller, T. Overview of fibre-reinforced polymers in bridge construction. Struct. Eng. Int. 2002, 12, 66–70. [Google Scholar] [CrossRef]
  4. O’Connor, J.S. GRP bridge decks and superstructures in the USA. Reinf. Plast. 2008, 52, 26–31. [Google Scholar] [CrossRef]
  5. Kendall, D. Developments in FRP bridge design. Reinf. Plast. 2010, 54, 38–42. [Google Scholar] [CrossRef]
  6. Zoghi, M. (Ed.) The International Handbook of FRP Composites in Civil Engineering; CRC Press, Taylor & Francis Group: Abington, UK, 2013. [Google Scholar]
  7. Chróścielewski, J.; Miśkiewicz, M.; Pyrzowski, Ł.; Sobczyk, B.; Wilde, K. A novel sandwich footbridge—Practical application of laminated composites in bridge design and in situ measurements of static response. Compos. B Eng. 2017, 126, 153–161. [Google Scholar] [CrossRef]
  8. Siwowski, T.; Kaleta, D.; Rajchel, M. Structural behaviour of an all-composite road bridge. Compos. Struct. 2018, 192, 555–567. [Google Scholar] [CrossRef]
  9. Hollaway, L.C. A review of the present and future utilisation of FRP composites in the civil infrastructure with reference to their important in-service properties. Constr. Build. Mater. 2010, 24, 2419–2445. [Google Scholar] [CrossRef]
  10. Cheng, L.; Karbhari, V.M. New bridge systems using FRP composites and concrete: A state-of-the-art review. Prog. Struct. Eng. Mater. 2006, 8, 143–154. [Google Scholar] [CrossRef]
  11. Gutiérrez, E.; Primi, S.; Mieres, J.M.; Calvo, I. Structural testing of a vehicular carbon fiber bridge: Quasi-static and short-term behavior. J. Bridge Eng. 2008, 13, 271–281. [Google Scholar] [CrossRef]
  12. Ziehl, P.H.; Engelhardt, M.D.; Fowler, T.J.; Ulloa, F.V.; Medlock, R.D.; Schell, E. Design and field evaluation of hybrid FRP/reinforced concrete superstructure system. J. Bridge Eng. 2009, 14, 309–318. [Google Scholar] [CrossRef]
  13. Yang, L. Research status of FRP-concrete composite beam/bridge deck systems. Appl. Mech. Mater. 2014, 587–589, 1424–1429. [Google Scholar] [CrossRef]
  14. Siwowski, T.; Kaleta, D.; Rajchel, M.; Własak, L. The first Polish road bridge made of FRP composites. Struct. Eng. Int. 2017, 27, 308–314. [Google Scholar] [CrossRef]
  15. Deskovic, N.; Triantafillou, T.C.; Meier, U. Innovative design of FRP combined with concrete: Short term behavior. J. Struct. Eng. 1995, 121, 1069–1078. [Google Scholar] [CrossRef]
  16. Kitane, Y.; Aref, A. Static and fatigue testing of hybrid fiber-reinforced polymer—Concrete bridge superstructure. J. Compos. Constr. 2004, 8, 182–190. [Google Scholar] [CrossRef]
  17. Correia, J.R.; Branco, F.A.; Ferreira, J.G. Flexural behaviour of GFRP-concrete hybrid beams with interconnection slip. Compos. Struct. 2007, 77, 66–78. [Google Scholar] [CrossRef]
  18. Chakrabortty, A.; Khennane, A.; Kayali, O.; Morozov, E. Performance of outside filament-wound hybrid FRP-concrete beams. Compos. B Eng. 2011, 42, 907–915. [Google Scholar] [CrossRef]
  19. Manalo, A.C.; Aravinthan, T.; Mutsuyoshi, H.; Matsui, T. Composite behaviour of a hybrid FRP bridge girder and concrete deck. Adv. Struct. Eng. 2012, 15, 589–600. [Google Scholar] [CrossRef] [Green Version]
  20. Siwowski, T.; Rajchel, M. Structural performance of a hybrid FRP composite—Lightweight concrete bridge girder. Compos. B Eng. 2019, 174, 107055. [Google Scholar] [CrossRef]
  21. Cho, K.; Park, S.Y.; Kim, S.T. Shear connection system and performance evaluation of FRP-concrete composite deck. KSCE J. Civ. Eng. 2010, 14, 855–865. [Google Scholar] [CrossRef]
  22. Nordin, H.; Täljsten, B. Testing of hybrid FRP composite beams in bending. Compos. B Eng. 2004, 35, 27–33. [Google Scholar] [CrossRef]
  23. Nelson, M.; Fam, A. Structural GFRP permanent forms with T-shape ribs for bridge decks supported by precast concrete girders. J. Bridge Eng. 2012, 18, 813–826. [Google Scholar] [CrossRef]
  24. Canning, L.; Hollaway, L.; Thorne, A.M. An investigation of the composite action of an FRP/concrete prismatic beam. Constr. Build. Mater. 1999, 13, 417–426. [Google Scholar] [CrossRef]
  25. Nguyen, H.; Mutsuyoshi, H.; Zatar, W. Push-out tests for shear connections between UHPFRC slabs and FRP girder. Compos. Struct. 2014, 118, 528–547. [Google Scholar] [CrossRef]
  26. Zou, X.; Feng, P.; Wang, J. Bolted shear connection of FRP-concrete hybrid beams. J. Compos. Constr. 2018, 22, 04018012. [Google Scholar] [CrossRef]
  27. Fam, A.; Skutezky, T. Composite T-beams using reduced-scale rectangular FRP tubes and concrete slabs. J. Compos. Constr. 2006, 10, 172–181. [Google Scholar] [CrossRef]
  28. Honickman, H.N. Pultruded GFRP Sections as Stay-in-Place Structural Open Formwork for Concrete Slabs and Girders. Master’s Thesis, Queen’s University, Kingston, ON, Canada, July 2008. [Google Scholar]
  29. Zou, X.; Feng, P.; Wang, J. Perforated FRP ribs for shear connecting of FRP-concrete hybrid beams/decks. Compos. Struct. 2016, 152, 267–276. [Google Scholar] [CrossRef]
  30. Wiater, A.; Rajchel, M.; Siwowski, T. Research on deck slabs made of lightweight concrete and reinforced with GFRP bars. J. Civ. Eng. Env. Arch. 2015, XXXII, 469–492. (In Polish) [Google Scholar]
  31. Siwowski, T.; Rajchel, M.; Kulpa, M. Design and field evaluation of a hybrid FRP composite—Lightweight concrete road bridge. Compos. Struct. 2019, 230, 111504. [Google Scholar] [CrossRef]
  32. Eurocode 4: Design of Composite Steel and Concrete Structures—Part 2: General Rules and Rules for Bridges; EN 1994-2; European Committee for Standardization: Brussels, Belgium, 2005.
  33. Eurocode 4: Design of Composite Steel and Concrete Structures—Part 1-1: General Rules and Rules for Buildings; EN 1994-1-1; European Committee for Standardization: Brussels, Belgium, 2004.
  34. Eurocode 3: Design of Steel Structures—Part 1-8: Design of Joints; EN 1993-1-8; European Committee for Standardization: Brussels, Belgium, 2005.
  35. Zou, X.; Feng, P.; Wang, J.; Wu, Y.; Feng, Y. FRP stay-in-place form and shear key connection for FRP-concrete hybrid beams/decks. Compos. Struct. 2018, 192, 489–499. [Google Scholar] [CrossRef]
  36. Eurocode 2: Design of Concrete Structures—Part 1-1: General Rules and Rules for Buildings; EN 1992-1-1; European Committee for Standardization: Brussels, Belgium, 2004.
  37. ISO General Purpose Metric Screw Threads—General Plan; PN ISO 261:2001; Polish Committee for Standardization: Warsaw, Poland, 2001.
  38. Rajchel, M.; Siwowski, T. Live load transverse distribution in a road slab-girder bridge made of FRP composite girders. Road Bridge 2017, 16, 131–145. [Google Scholar] [CrossRef]
  39. Eurocode 1: Actions on Structures—Part 2: Traffic Loads on Bridges; EN 1991-2; European Committee for Standardization: Brussels, Belgium, 2003.
Figure 1. Bridge girder’s cross-section: (a) fiber-reinforced polymer (FRP) beam; (b) hybrid FRP- lightweight concrete (LWC) girder (unit: mm).
Figure 1. Bridge girder’s cross-section: (a) fiber-reinforced polymer (FRP) beam; (b) hybrid FRP- lightweight concrete (LWC) girder (unit: mm).
Materials 13 02045 g001
Figure 2. Idea and elements of novel shear connection system.
Figure 2. Idea and elements of novel shear connection system.
Materials 13 02045 g002
Figure 3. Geometry of push-out test specimen.
Figure 3. Geometry of push-out test specimen.
Materials 13 02045 g003
Figure 4. Specimen’s fabrication: (a) glass fiber-reinforced polymer (GFRP) reinforcement of concrete slab; (b) steel connectors inside the tube; (c) ready specimen.
Figure 4. Specimen’s fabrication: (a) glass fiber-reinforced polymer (GFRP) reinforcement of concrete slab; (b) steel connectors inside the tube; (c) ready specimen.
Materials 13 02045 g004
Figure 5. Push-out test set up.
Figure 5. Push-out test set up.
Materials 13 02045 g005
Figure 6. Location of linear variable differential transducer (LVDT) measurement points on specimen.
Figure 6. Location of linear variable differential transducer (LVDT) measurement points on specimen.
Materials 13 02045 g006
Figure 7. Failure modes: (a) static failure of specimen S1; (b) fatigue failure of specimen F4.
Figure 7. Failure modes: (a) static failure of specimen S1; (b) fatigue failure of specimen F4.
Materials 13 02045 g007
Figure 8. Load–relative slip curves of specimen S1.
Figure 8. Load–relative slip curves of specimen S1.
Materials 13 02045 g008
Figure 9. Failure mode of specimen S1: concrete surface—no cracks (top); GFRP surface—no bearing or shear-out failure (bottom).
Figure 9. Failure mode of specimen S1: concrete surface—no cracks (top); GFRP surface—no bearing or shear-out failure (bottom).
Materials 13 02045 g009
Figure 10. Load–slip curves of specimen S2 in the range of 0–200 kN: premature slip at 160 kN.
Figure 10. Load–slip curves of specimen S2 in the range of 0–200 kN: premature slip at 160 kN.
Materials 13 02045 g010
Figure 11. Failure mode of specimen S2: (a) general mode; (b) concrete surface—no cracks; (c) GFRP surface—initial bearing (right).
Figure 11. Failure mode of specimen S2: (a) general mode; (b) concrete surface—no cracks; (c) GFRP surface—initial bearing (right).
Materials 13 02045 g011
Figure 12. Failure mode of specimen S3: (a) concrete surface protrusion crushed; (b) concrete surface—no cracks.
Figure 12. Failure mode of specimen S3: (a) concrete surface protrusion crushed; (b) concrete surface—no cracks.
Materials 13 02045 g012
Figure 13. Load–slip curves of specimen S3 in the range of 0–200 kN: premature slip at 140 kN (one side only).
Figure 13. Load–slip curves of specimen S3 in the range of 0–200 kN: premature slip at 140 kN (one side only).
Materials 13 02045 g013
Figure 14. Load–displacement curves of three specimens.
Figure 14. Load–displacement curves of three specimens.
Materials 13 02045 g014
Figure 15. Load–displacement behavior of specimen F4 under cyclic loading (final range).
Figure 15. Load–displacement behavior of specimen F4 under cyclic loading (final range).
Materials 13 02045 g015
Figure 16. Fatigue failure mode of specimen F4: (a) fracture at weld toe on steel plate; (b) fractured bolt shanks; (c) slight shear-out failure in GFRP laminate.
Figure 16. Fatigue failure mode of specimen F4: (a) fracture at weld toe on steel plate; (b) fractured bolt shanks; (c) slight shear-out failure in GFRP laminate.
Materials 13 02045 g016
Figure 17. Load–displacement curves of specimens S1 and F6.
Figure 17. Load–displacement curves of specimens S1 and F6.
Materials 13 02045 g017
Figure 18. Standard and experimental S–N curves for shear studs (bolts).
Figure 18. Standard and experimental S–N curves for shear studs (bolts).
Materials 13 02045 g018
Table 1. Shear forces according to bridge design.
Table 1. Shear forces according to bridge design.
LoadTotal Shear Force Per Unit Length vL,EdMaximum Shear Force VEdMaximum Shear Force Per Study PEd
[kN/m][kN][kN]
Characteristic488.40349.4421.98
Design SLS488.40349.4421.98
Design ULS696.43523.0231.34
Table 2. Mechanical properties of laminas used in specimen fabrication.
Table 2. Mechanical properties of laminas used in specimen fabrication.
Constant, ParameterUnitSymbol, Direction Lamina
X-E ±45°B-E 0/90°U-E 0° (90°)
1210 g/m2800 g/m21210 g/m2
Longitudinal modulus of elasticityGPaEx20.5020.0042.13
Ey20.5020.0010.87
Transverse modulus of elasticityGPaGxy3.903.904.40
Gyz3.042.832.71
Gxz3.042.832.71
Poisson’s ratio-νxy0.0190.0290.29
νyz0.0190.0290.075
νxz0.0190.0290.075
Tensile strengthMPaXt520.0522.0855.0
Yt520.0522.044.0
Compressive strengthMPaXc320.0321.0537.0
Yc320.0321.084.0
Shear strengthMPaSxy60.060.051.0
Syz30.030.025.0
Sxz30.030.025.0
Table 3. Mechanical properties and density of LWC 35/38 class.
Table 3. Mechanical properties and density of LWC 35/38 class.
Constant, ParameterUnitSymbol, DirectionValue
Modulus of elasticityGPaEc26.986
Tensile strengthMPaft2.46
Compressive strengthMPafc25.76
Ultimate compressive strain[‰]εlcu11.749
Densitykg/m3ρ1968
Table 4. Outcomes of push-out tests.
Table 4. Outcomes of push-out tests.
SpecimenFirst SlipFailure
Slip Load PsFirst Slip δ1Modulus kslipUltimate Load PuUltimate Slip δuUltimate Resistance PrMode
[kN][mm][kN/mm][kN][mm][kN]
S12550.12531.33114.277.75bolt shank fracture
S22450.30
(0.235)
204.2
(260.6)
3154.378.75bolt shank fracture
S34050.16632.83424.585.50bolt shank fracture
F63200.12666.73154.978.75bolt shank fracture
Average 1 522.8322.67 80.67
1 Without specimen F6.
Table 5. Fatigue test parameters.
Table 5. Fatigue test parameters.
SpecimenFminFmaxR = Fmin/FmaxΔFΔF/Pu,av
[kN][kN][kN][%]
F422.2222.20.120061.9
F516.6166.60.115046.5
F611.0111.00.110031.0
Table 6. Fatigue test results.
Table 6. Fatigue test results.
SpecimenStress Range ΔτRCrack InitiationNumber of Cycles at Failure NRLog (NR)/Log (Nc) acc. to [32]
[MPa][cycles][cycles]
F4217.78.384 × 1038.412 × 103
F5163.32.945 × 1053.488 × 1051.66
F6108.9run-out

Share and Cite

MDPI and ACS Style

Rajchel, M.; Kulpa, M.; Siwowski, T. Experimental Study on a Novel Shear Connection System for FRP-Concrete Hybrid Bridge Girder. Materials 2020, 13, 2045. https://doi.org/10.3390/ma13092045

AMA Style

Rajchel M, Kulpa M, Siwowski T. Experimental Study on a Novel Shear Connection System for FRP-Concrete Hybrid Bridge Girder. Materials. 2020; 13(9):2045. https://doi.org/10.3390/ma13092045

Chicago/Turabian Style

Rajchel, Mateusz, Maciej Kulpa, and Tomasz Siwowski. 2020. "Experimental Study on a Novel Shear Connection System for FRP-Concrete Hybrid Bridge Girder" Materials 13, no. 9: 2045. https://doi.org/10.3390/ma13092045

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop