Regional Role Matching and Energy Temporal Coupling-Based Coordinated Dispatch of Multiple Pumped Storage Plants Under Zonal Transmission Constraints
Abstract
1. Introduction
- The functional roles of zones (renewable-rich, load center, hub) are not mapped into distinct operation modes of PSPs, so the model cannot actively generate strategies that match each zone’s positioning.
- The coupling mechanism between section constraints and the temporal energy behavior of PSPs remains unrevealed. How section congestion forces PSPs to adjust their inter-temporal energy shift plans lacks a quantitative model.
- There is no adaptive rule for PSP charging/discharging that responds to section congestion, making it difficult for dispatch schedules to remain both economic and reliable when sections become tight.
- (i)
- A “zonal role–PSP behavior” matching mechanism is established. Based on zonal functional attributes, PSPs located in different zones are assigned differentiated characteristics: in a renewable-rich zone, priority is given to pumping during renewable surplus periods and generating for export during off-peak hours or when sections permit (encouraging “low-price storage and delayed export” through low opportunity costs); in a load center, priority is given to generation during evening peaks; in a hub zone, the model allows both pumping using power from the renewable-rich zone and discharging to the load center, using bidirectional power variables to achieve “energy interchange.” Through this differentiated modeling, the optimization automatically generates charging/discharging patterns that match each zone’s role.
- (ii)
- A coordination framework coupling inter-zonal sections and PSP energy balance is developed. The energy balance equations of PSPs in each node and the power flow constraints of inter-zonal sections are unified into a single optimization model. This framework quantifies for the first time how section congestion restricts the “cross-zone energy shifting” efficiency of PSPs, and provides guidance information for section capacity expansion or PSP capacity addition.
- (iii)
- Based on the above framework, an intuitive congestion-response rule is derived. If the sending-zone → receiving-zone section is saturated, the sending-zone PSP should maintain or increase pumping (to absorb surplus local power and reduce export demand), or if generating, switch to pumping; the receiving-zone PSP should stop pumping using imported power and switch to local generation. If the reverse direction is saturated, the original receiving-zone PSP should maintain or increase pumping, or if generating, switch to pumping; the original sending-zone PSP should stop pumping using imported power, or if pumping, switch to generation. This rule can be directly embedded into a decision support system, providing operators with clear operational guidelines.
2. Coordinated Dispatch Modeling of Multiple PSPs Considering Zonal Differences
2.1. Objective Function with Zonal Differentiation
2.2. Inter-Zonal Constraints
2.2.1. System-Wide Nodal Power Balance
2.2.2. Section Capacity Constraints
2.3. Intra-Zonal Constraints
2.3.1. Pumped Storage Plant Constraints
2.3.2. Renewable Generation Constraints
2.3.3. Thermal Unit Constraints
2.3.4. Spinning Reserve Constraints
3. Mathematical Derivation of the Congestion-Response Rule and PSP Action Rules Under Section Saturation
3.1. Mathematical Derivation of the Congestion-Response Rule
- (i)
- For the PSP generation variable in Zone A (sending zone), since (increasing generation in Zone A increases the A → B power flow), and , the first-order optimality condition implies that continuing to increase generation in Zone A would violate the optimality condition. Therefore, generation should be reduced or switched to pumping.
- (ii)
- For the PSP pumping variable in Zone A, since (increasing pumping in Zone A acts as a local load and reduces the power flow leaving the zone), increasing pumping helps restore the first-order condition. Therefore, pumping should be maintained or increased.
- (iii)
- For the PSP pumping variable using imported power in Zone B (receiving zone), since (pumping in Zone B using power from Zone A increases the A → B power flow), it should be stopped or switched to generation.
- (iv)
- For the PSP generation variable in Zone B, since (increasing local generation in Zone B replaces imported power and reduces the A → B power flow), generation should be maintained or increased.
3.2. PSP Action Rules Under Section Saturation
3.2.1. A → B Direction Section Saturation
3.2.2. B → A Direction Section Saturation (Reverse)
3.3. Mathematical Essence of the KKT Conditions
- (i)
- Section saturation indicates that this constraint has become the primary bottleneck of the system economic dispatch. The multiplier quantifies the system cost reduction that could be achieved by increasing the section capacity by 1 MW; therefore, dispatch decisions must prioritize the reduction in section power flow.
- (ii)
- In the gradient direction, section saturation “penalizes” all variables that increase the section power flow in that direction. In the KKT conditions, the gradient term of the section constraint is added with a positive sign to the first-order derivatives of the corresponding variables, meaning further increases in these variables no longer satisfy the optimality conditions—they must be adjusted in the reverse direction.
- (iii)
- The signs of the action rules are determined by the signs of the partial derivatives . For the A→B direction,
- Sending-zone generation : → should be reduced.
- Receiving-zone pumping : → should be reduced.
- Sending-zone pumping : → should be increased.
- Receiving-zone generation : → should be increased.
- (iv)
- This rule is equivalent to a sensitivity analysis of the section constraint at the optimal solution. When the section is saturated, increasing pumping (in the sending zone) or increasing generation (in the receiving zone) is equivalent to “substituting” for section transmission, while reducing generation (in the sending zone) or reducing pumping (in the receiving zone) is equivalent to “reducing” section transmission—this is precisely the natural correction direction of the optimal dispatch solution under section congestion within the KKT framework.
4. Case Study and Results Analysis
4.1. Test System Description
4.2. Scenario Settings
4.3. Results Analysis for Base Scenario
4.3.1. Operational Characteristics of Zonal Pumped Storage
4.3.2. Zonal Power Exchange
- (i)
- During the early morning to early morning (0–5 h), wind power output is high: Zone 3 net exports 370–451 MW, Zone 2 net imports about 600–676 MW, and Zone 1 net exports 225–259 MW. At this time, the section powers are relatively low on Zone 1 → Zone 2 (169–210 MW), large in absolute value on Zone 2 → Zone 3 (412–487 MW), and small on Zone 1 → Zone 3 (35–57 MW). The system is mainly supplied by wind power from Zone 3, which is transmitted through the hub Zone 1 to Zone 2.
- (ii)
- From morning to noon (6–13 h), load increases and PV output rises. Zone 3 becomes a net importer from 8 h onward (maximum import 259 MW), Zone 1’s net export rapidly increases to 998 MW (10 h), and Zone 2’s net import also rises to 859 MW (9 h). On the sections, the power on the Zone 1 → Zone 2 section increases to 338–702 MW, the absolute value on the Zone 2 → Zone 3 section drops sharply to 42–101 MW, and the power on the Zone 1 → Zone 3 section rises to 250–302 MW. This indicates that during this period, Zone 1 not only directly sends power to Zone 3 to compensate for the power deficit caused by low wind output in Zone 3 but also sends power to Zone 2 to meet the increasing load demand in Zone 2.
- (iii)
- In the afternoon to evening (14–19 h), PV output declines. Zone 3 briefly exports during 14–15 h (360 MW and 102 MW) but then switches back to net import during 16–19 h (111–266 MW). The power on the Zone 1 → Zone 2 section first increases and then decreases (189–627 MW), the absolute value on the Zone 2 → Zone 3 section first decreases and then increases (450–24 MW), and the power on the Zone 1 → Zone 3 section stays in the range of 89–289 MW, showing bidirectional power exchange between Zone 3 and Zones 1 and 2.
- (iv)
- During the night (20–23 h), wind power output recovers. Zone 3 net export rises from 136 MW to 352 MW, and Zone 1 net import falls from 545 MW to 211 MW. On the sections, the power on the Zone 1 → Zone 2 section drops to 99–377 MW, the absolute value on the Zone 2 → Zone 3 section rises again to 303–411 MW, and the power on the Zone 1 → Zone 3 section stays at 58–167 MW. The system returns to the pattern where Zone 2 is mainly supplied by Zone 1 and Zone 3.
4.3.3. Power Generation Structure
- (i)
- Early morning (0–5 h): High wind output, zero PV, low load. Zone 3 PSH units pump heavily (PSH 105: 541.51 MWh; PSH 106 during 1–4 h: 757.90 MWh; total ~1299.41 MWh). Zone 3 is a net exporter, supplying power via Zone 1 to Zone 2.
- (ii)
- Morning (8–12 h): Load rises to the daily peak, and PV output increases. Zone 3 PSH units start generating (PSH 105 at 8 h and 12 h: 132.97 MWh; PSH 106 at 9 h and 10 h: 411.08 MWh). Zone 2’s PSH 17 provides an additional 162.00 MW at 9 h. Zone 3 turns into a net importer, receiving power from Zone 1.
- (iii)
- Afternoon to evening (14–19 h): PV drops to zero, wind gradually recovers. Zone 3 PSH units discharge heavily (PSH 105: 492.02 MWh; PSH 106: 712.80 MWh). Zone 3 briefly becomes a net exporter but returns to net import during 16–19 h. Thermal generation ramps up to its evening peak (2185.45 MW at 18 h).
- (iv)
- Night (20–23 h): Wind output recovers to a high level. PSH 106 pumps again at 22–23 h (443.11 MWh) to restore its reservoir energy for the next day’s cycle. Zone 3 returns to net export, and thermal output decreases.
5. Discussion
5.1. Core Indicator Comparison of Five Scenarios
5.2. Tie-Line Transmission Capacity Sensitivity Analysis
5.2.1. Variation Characteristics of Inter-Zonal Power Exchange in Scenarios A, B, and C
5.2.2. Operational Patterns of Pumped Storage Units in Scenarios A, B, and C
- Unit PSH 17 (Zone 2): Generates only at hour 9 (162 MW) for the morning peak, with no pumping. Its stored energy decreases from 900 MWh to 720 MWh and then remains constant.
- Unit PSH 38 (Zone 1): Pumps only at hours 3–4 (35.44 MW and 14.81 MW). Its stored energy rises from 900 MWh to 947.74 MWh, indicating absorption of surplus wind power during off-peak hours.
- Unit PSH 105 (Zone 3): Generates during the daytime (hours 8, 12, 14, 15, 17), with a peak of 240.48 MW (hour 14); pumps during the night and early morning (hours 1–2, 5), with a peak of 300 MW (hour 1). Its stored energy rises through pumping to the upper limit of 1414.43 MWh, then decreases to 720 MWh through generation.
- Unit PSH 106 (Zone 3): Generates at hours 9, 10, 14, 15, 16, 20 (maximum 300 MW); pumps at hours 1–4 and 22–23 (maximum 295.77 MW). Its stored energy increases from 900 MWh to 1620 MWh (fully charged at hour 4), then discharges to 720 MWh (at hour 23).
- PSH 17: Generates 162 MW at hour 8 (morning peak)—similar to Scenario A, with no pumping.
- PSH 38: Generates 162 MW at hour 6 (early morning), which is a new operating point compared to Scenario A (where PSH 38 only pumped). Its reservoir energy drops from 900 MWh to 720 MWh at hour 6 and remains at that level. This indicates that under the constrained tie-line condition, Zone 1 cannot import surplus renewable power and uses pumped storage to convert the excess renewable energy into stored energy.
- PSH 105: Pumps heavily during hours 1–4 (265.40 MW, 152.10 MW, 294.12 MW, 46.28 MW) and generates during hours 9–19 (multiple periods, with a maximum of 257.71 MW at hour 16). Its reservoir energy rises to 1620 MWh (fully charged) by hour 4, then gradually discharges to 720 MWh by hour 23.
- PSH 106: Pumps during hours 2–5 and 22–23 (maximum 300 MW), and generates during hours 8–13 (maximum 300 MW). Its reservoir energy increases from 900 MWh to 1620 MWh by hour 5; after generation, it drops to 180 MWh at hour 13 and remains low until hour 22, when it slightly recharges.
- PSH 17: Pumps during hours 1–2 (108.49 MW and 213.66 MW) and generates during hours 6–7 (137.44 MW and 300 MW). Its reservoir energy increases from 900 MWh to 1206 MWh (pumping) and then decreases to 720 MWh after generation. This is a clear daily cycle.
- PSH 38: Generates 52.63 MW at hour 8 and 109.37 MW at hour 22, with no pumping. Its reservoir energy decreases slightly from 900 MWh to 841.52 MWh after generation, and then remains constant.
- PSH 105: Pumps during hours 1–4 (195.55 MW, 27.77 MW, 300 MW, 234.57 MW) and generates at hours 6, 8, 9, and 10 (maximum 300 MW). Its reservoir energy rises to 1620 MWh by hour 4, then discharges to 594 MWh by hour 10 and stays at that level until hour 21. During hours 22–23, it pumps 12.97 MW and 119.61 MW, and its reservoir energy jumps to 720 MWh.
- PSH 106: Pumps during hours 2–3 (130.19 MW and 31.21 MW). Its reservoir energy increases from 900 MWh to 1053 MWh. At hour 8, it generates 300 MW, and its reservoir energy drops to 720 MWh.
5.3. Installed Wind Power Capacity Sensitivity Analysis
5.3.1. Variation Characteristics of Inter-Zonal Power Exchange in Scenarios A, D, and E
5.3.2. Operational Patterns of Pumped Storage Units in Scenarios A, D, and E
- (i)
- Scenario A (Baseline Wind Power, 2400 MW)
- (ii)
- Scenario D (Wind Power Reduced by 20%, 1920 MW)
- Unit PSH 17: Generates a small amount during hours 9–10 (61.57 MW and 6.77 MW) and hours 16–18 (63.93 MW, 10.50 MW and 19.23 MW). Its reservoir energy drops from 900 MWh to 824.06 MWh, and then to 720 MWh.
- Unit PSH 38: Generates intermittently during hours 2–19 (peak 80.29 MW). Its reservoir energy decreases from 900 MWh to 720 MWh.
- Unit PSH 105: Pumps only during nighttime hours 3 and 4 (97.96 MW and 300 MW, respectively). Its reservoir energy rises from 900 MWh to 1278.06 MWh and remains constant until hour 15, then discharges during hours 16–19, and its reservoir energy drops to 720 MWh.
- Unit PSH 106: No pumping record. It generates 63.34 MW, 62.38 MW and 36.28 MW at hours 9, 10 and 16, respectively. Its reservoir energy stays at 900 MWh (hours 0–8) and then drops to 720 MWh by hour 16.
- (iii)
- Scenario E (Wind Power Increased by 20%, 2880 MW)
- Unit PSH 17: Pumps during hours 1–3 (6.16 MW, 170.68 MW, and 170.14 MW). Its reservoir energy rises from 900 MWh to 1229.64 MWh. It generates 158.67 MW at hour 9 and 300 MW at hour 12, and its reservoir energy drops to 720 MWh.
- Unit PSH 38: Generates only 162 MW at hour 7, with its reservoir energy decreasing from 900 MWh to 720 MWh.
- Unit PSH 105: Pumps intensively during hours 1–5 (300 MW at hour 1, 71.89 MW at hour 2, 300 MW at hour 4, and 86 MW at hour 5). Its reservoir energy rises from 900 MWh to the upper limit of 1620 MWh. It generates heavily during daytime hours 8–14 (300 MW at hour 8, 300 MW at hour 9, 155.46 MW at hour 11, 240.54 MW at hour 12, and 300 MW at hour 14), discharging its reservoir energy to 180 MWh (the deepest discharge among all scenarios). It pumps again during hours 22–23 (268.42 MW and 300 MW), recovering its reservoir energy to 720 MWh.
- Unit PSH 106: Pumps during hours 1–4 (202.96 MW at hour 1, 129.06 MW at hour 2, 161.06 MW at hour 3, and 264.82 MW at hour 4). Its reservoir energy rises from 900 MWh to 1620 MWh. It generates during daytime hours 8–13 and hour 17 (87.98 MW at hour 8, 68.89 MW at hour 9, 300 MW at hour 10, 300 MW at hour 11, 179.79 MW at hour 12, 150.45 MW at hour 13, and 208.89 MW at hour 17), discharging its reservoir energy to 180 MWh. It pumps again during hours 22–23 (268.42 MW and 300 MW), recovering its reservoir energy to 720 MWh.
5.4. PSP Capacity Sensitivity Analysis
- (i)
- Capacity expansion has limited impact on PSP operational intensity under baseline conditions. In Scenario A (baseline), the variations in TDP and TDG across different capacity schemes are minimal, indicating that under the baseline configuration of 2400 MW wind power and 500 MW tie-line capacity, the existing 250 MW PSP capacity is already sufficient to absorb the available surplus renewable energy. Further capacity expansion does not increase PSP utilization, as the system’s renewable surplus is the binding constraint rather than PSP capacity.
- (ii)
- Capacity expansion has a more pronounced effect under tightened section constraints. In Scenario B (tightened section, 400 MW tie-line capacity), increasing PSP capacity from 250 MW to 300 MW increases TDP from 2454.49 MWh to 2493.76 MWh (a 1.60% increase) and TDG from 2746.59 MWh to 2780.16 MWh (a 1.22% increase), while the curtailment rate drops from 2.448% to 2.373% (a reduction of 0.075 percentage points). This indicates that under transmission-constrained conditions, a larger PSP capacity can partially compensate for the limited export capability by storing more surplus renewable energy locally. However, further increasing capacity from 300 MW to 400 MW or 425 MW yields no additional improvement—all indicators remain nearly identical to the 300 MW case. This suggests that 300 MW is the saturation point beyond which additional capacity provides no further benefit under the given section limit.
- (iii)
- Capacity expansion yields limited curtailment reduction benefits in most scenarios. In Scenario A, CRE remains nearly constant (294.80 MWh for 250 MW vs. approximately 292.67 MWh for 300–425 MW), indicating that once the PSP capacity reaches 250 MW, additional capacity contributes little to further curtailment reduction. In Scenario B, CRE decreases from 908.41 MWh (250 MW) to 880.52 MWh (300–425 MW), a reduction of approximately 27.89 MWh (3.07%), but no further reduction is observed beyond 300 MW. In Scenario E, CRE decreases slightly from 2386.49 MWh (250 MW) to 2384.71 MWh (425 MW), a reduction of only 1.78 MWh over a 175 MW capacity increase, confirming that the curtailment reduction benefit of capacity expansion is marginal and subject to diminishing returns.
- (iv)
- Capacity benefits are constrained by renewable availability and transmission limits. In Scenario D (wind capacity reduced by 20%), curtailment is zero across all capacity schemes, and TDP decreases as capacity increases (from 420.22 MWh at 250 MW to 397.96 MWh at 300–425 MW), indicating that when renewable energy is insufficient, larger PSP capacity is underutilized and does not provide any additional benefit. In Scenario E (wind capacity increased by 20%), the curtailment rate remains high across all capacity schemes (5.56–5.61%), and the differences among capacity schemes are negligible (CR varies by only 0.05 percentage points). This suggests that the primary limitations to curtailment reduction are not PSP capacity but rather the tie-line transmission capacity and the temporal mismatch between renewable generation and load.
5.5. PSP Efficiency Sensitivity Analysis
- (i)
- Proportional efficiency improvement significantly enhances generation output. As efficiency increases proportionally from ES1 to ES3, total daily generation (TDG) increases substantially across all scenarios. In Scenario A, TDG increases from 1983.92 MWh (ES1) to 2180.81 MWh (ES3), representing an increase of approximately 9.9%, while TDP remains nearly constant (around 1793 MWh). In Scenario B, the improvement is even more pronounced: TDG increases from 2584.15 MWh (ES1) to 2780.16 MWh (ES3), an increase of approximately 7.6%. This indicates that the same amount of pumped water produces more electricity at higher efficiency, directly improving the economic value of PSP operations.
- (ii)
- Isolated pumping efficiency vs. generation efficiency effects (ES4 vs. ES5). Schemes ES4 (pumping efficiency low, generation efficiency baseline) and ES5 (pumping efficiency baseline, generation efficiency low) have similar round-trip efficiencies (0.810 vs. 0.8075), enabling a direct comparison of their distinct impacts. In Scenario A, ES4 achieves 2100.42 MWh of TDG, while ES5 achieves only 2060.14 MWh—a difference of 40.28 MWh. This indicates that under comparable round-trip efficiency, generation efficiency has a more significant impact on total generation output than pumping efficiency. The reason is that generation efficiency directly determines the conversion of stored hydraulic energy into electricity, whereas pumping efficiency only affects the energy input side. A 5% reduction in generation efficiency (ES5, 0.85 vs. 0.90) causes a 5.5% reduction in TDG compared to ES3, while a 5% reduction in pumping efficiency (ES4, 0.90 vs. 0.95) causes only a 3.7% reduction in TDG. This pattern holds consistently across all scenarios.
- (iii)
- Efficiency improvements enable deeper reservoir utilization. As efficiency increases from ES1 to ES3, minimum reservoir energy (MRE) generally decreases, indicating that the reservoir is discharged more deeply. In Scenario A, MRE decreases from 320.66 MWh (ES1) to 299.05 MWh (ES3), a reduction of approximately 6.7%. In Scenario E, MRE remains at 180.00 MWh across all schemes, indicating that under high renewable penetration, the PSP is consistently called upon for deep discharge regardless of efficiency, because the abundant surplus renewable energy fully utilizes the available storage capacity.
- (iv)
- Efficiency benefits are magnified under high renewable penetration. In Scenario E (Wind +20%), the TDG difference between ES1 and ES3 is 212.80 MWh (2999.87 vs. 3212.67 MWh), compared to 196.89 MWh in Scenario A and 196.01 MWh in Scenario B. This indicates that the value of efficiency improvement increases with renewable penetration—the more surplus renewable energy is available, the greater the benefit of higher efficiency in converting it to usable electricity. In Scenario D (Wind −20%), curtailment is zero across all schemes, and the variations in TDP and TDG are minimal. The TDG difference between ES1 and ES3 is only 19.78 MWh (968.48 vs. 988.26 MWh), confirming that when renewable energy is insufficient, PSP efficiency improvement provides little additional benefit.
- (v)
- Efficiency benefits are constrained by section capacity. When comparing Scenario B (tightened section) and Scenario C (relaxed section), the TDG improvements from ES1 to ES3 are 196.01 MWh in Scenario B and 159.66 MWh in Scenario C. The smaller improvement under relaxed section conditions suggests that when transmission is not a bottleneck, the system has more alternatives (e.g., direct renewable export) and thus relies less on PSP efficiency. Conversely, under tightened section constraints, higher PSP efficiency becomes more valuable because it allows the more effective utilization of locally stored energy that cannot be exported.
5.6. PSP Initial Water Level Sensitivity Analysis
- (i)
- Higher initial water levels generally increase total daily generation but reduce pumping demand. In Scenario A, as the initial water level increases from 40% to 60%, TDG increases substantially from 1795.31 MWh to 2720.65 MWh (an increase of 51.5%), while TDP exhibits a non-monotonic pattern: it increases from 1534.99 MWh (40%) to 1795.71 MWh (45%), remains relatively stable at 1792.76–1792.20 MWh (50–55%), and then decreases to 1666.25 MWh (60%). This indicates that higher initial water levels provide PSPs with greater discharge capacity, enabling more generation during peak demand periods. However, when the initial water level is already high (60%), the PSP has less available storage space, reducing the need for pumping during off-peak periods. In the 45–55% range, each 5% increase in initial water level yields approximately 321–324 MWh of additional generation.
- (ii)
- The impact of the initial water level on curtailment varies across scenarios. In Scenario A, CRE remains nearly constant (292.67–294.80 MWh) across the 40–55% range but jumps sharply to 381.20 MWh at 60%. This counterintuitive increase occurs because at the 60% initial water level, the reservoir is already nearly full, leaving insufficient storage capacity to absorb surplus renewable energy during high-output periods. The PSP’s pumping capability is constrained by the limited available reservoir space, resulting in increased curtailment despite the higher initial water level. This reveals a trade-off: while higher initial water levels enhance generation capacity, they may reduce the PSP’s ability to absorb renewable surplus when the reservoir is already near full capacity. In Scenario B (tightened section), CRE increases monotonically with the initial water level: from 617.64 MWh (40%) to 1145.91 MWh (60%). Under tightened section constraints, higher initial water levels mean that the PSP has limited capacity to pump surplus renewable energy from the renewable-rich zone, as the reservoir is already partially filled. This forces more renewable energy to be curtailed because it cannot be exported through the congested section or stored locally. In Scenario E (Wind +20%), CRE also increases with the initial water level: from 2125.11 MWh (40%) to 2645.31 MWh (60%). The same mechanism applies—higher initial water levels reduce the available storage space, limiting the PSP’s ability to absorb the abundant wind power, and thus leading to higher curtailment.
- (iii)
- The trade-off between generation enhancement and curtailment reduction is scenario-dependent. In Scenario A (baseline conditions), higher initial water levels (50–60%) enhance TDG (from 2180.81 MWh at 50% to 2720.65 MWh at 60%) while slightly increasing CRE (from 292.67 MWh to 381.20 MWh). The net benefit depends on the relative value of additional generation versus the cost of increased curtailment. In Scenario B (tightened section), higher initial water levels substantially increase both TDG and CRE: TDG increases from 2780.16 MWh (50%) to 3104.16 MWh (60%), while CRE increases significantly from 880.52 MWh to 1145.91 MWh. Under section constraints, the value of additional generation from the load-center PSP must be weighed against the increased curtailment in the renewable-rich zone. In Scenario E (high renewable penetration), higher initial water levels increase both TDG and CRE, with the magnitude of both effects amplified by the abundant renewable supply.
- (iv)
- The optimal initial water level depends on the specific system conditions. Under baseline conditions (Scenario A), the 50% initial water level provides a good balance between generation (2180.81 MWh) and curtailment (292.67 MWh). Under tightened section constraints (Scenario B), the 40% or 45% initial water level may be preferable to reduce curtailment, despite a lower TDG. Under high renewable penetration (Scenario E), the lower initial water levels (40–45%) are more effective at reducing curtailment. Under low renewable availability (Scenario D), higher initial water levels (55–60%) are preferable to maximize generation without causing curtailment.
5.7. PSP Operating Cost Sensitivity Analysis
- (i)
- Changes in pumping and generation totals: Tightened inter-zonal transmission capacity (Scenario B) and high wind power penetration (Scenario E) lead to substantial increases in total daily pumping (TDP), rising by 39.1% and 66.8%, respectively, compared to the baseline Scenario A. In these two scenarios, Zone 3 (the low-cost zone) serves as the primary pumping hub. By contrast, a loosened section capacity (Scenario C) and reduced wind output (Scenario D) decrease pumping demand, with TDP in Scenario D dropping to 22.2% of the baseline level.
- (ii)
- Reservoir energy utilization: In Scenarios B and E, the minimum reservoir energy (MRE) reaches its lower bound of 180 MWh (10% of storage capacity), indicating deep utilization of the reservoirs, while the maximum reservoir energy (XRE) hits its upper limit of 1620 MWh (90% of capacity), implying saturated energy storage. In Scenarios C and D, MRE remains relatively high (720 MWh), providing ample operational margin.
- (iii)
- The curtailment rate is positively correlated with renewable energy surplus. Due to the tightened section capacity, Scenario B exhibits a curtailment rate of 2.37%, whereas Scenario E, with massive wind injection, reaches 5.57%. No curtailment occurs in Scenario D. The low marginal cost of Zone 3 effectively incentivizes renewable absorption; compared with the uniform-cost case, the differentiated cost structure leaves curtailment indicators broadly unchanged across Scenarios A–D.
- (iv)
- Economic performance: Overall, compared with the uniform-cost benchmark (TC2), the differentiated cost structure leads to a modest increase in total system cost (TC) across all scenarios, with increments ranging from 0.30% to 2.07%—the largest increase occurring in Scenario E (2.07%) due to frequent PSP calls under high wind penetration, and the smallest in Scenario D (0.30%), where PSP utilization is minimal. This cost rise primarily stems from the higher absolute pumping costs set for the load center (Zone 2) and the hub zone (Zone 1), which are disproportionately incurred in scenarios with heavy PSP usage, thereby amplifying the cost difference. More importantly, all operational indicators—including total daily pumping (TDP), total daily generation (TDG), and curtailment rates—remain broadly consistent with those under the uniform-cost scheme, confirming that the differentiated cost structure effectively signals regional resource scarcity without significantly altering the physical dispatch solution.
6. Conclusions
- (i)
- Effectiveness of the regional role matching mechanism. By assigning differentiated objective and operational constraints to PSPs located in renewable-rich zones, load centers, and hub zones, the model automatically generates charging/discharging strategies that match the functional positioning of each zone. In the renewable-rich zone, PSPs prioritize pumping during wind/solar curtailment periods and delay power export when section conditions permit, effectively reducing local curtailment rates. In the load center, PSPs focus on generation during evening peak hours, significantly alleviating power supply pressure. In the hub zone, PSPs provide bidirectional flexible regulation, promoting cross-regional energy exchange.
- (ii)
- Quantitative analysis of the coupling between section constraints and the temporal energy shifting of PSPs. By integrating section power flow constraints with the energy balance equations of PSPs in each zone into a unified model, we reveal how section congestion restricts the “cross-zone energy shifting” efficiency of PSPs: when a section reaches its transfer limit, increasing pumping (or reducing generation) of the PSP in the sending zone is equivalent to increasing generation (or reducing pumping) of the PSP in the receiving zone. This finding provides valuable information for capacity expansion of sections or PSPs.
- (iii)
- Congestion-driven adaptive strategy. Based on the above coupling framework, we derive an adaptive congestion-response rule: when the sending-zone to receiving-zone section is saturated: if the sending-zone PSP is generating, it should switch to shutdown or increase pumping; if it is pumping, it should maintain or increase pumping; if it is idle, it should start pumping or remain idle. The receiving-zone PSP, if pumping using imported power, should stop pumping or switch to generation; if generating, it should maintain or increase generation; if idle, it should start generation or remain idle. The opposite actions apply when the reverse section is saturated. This rule can provide real-time decision support for dispatchers, ensuring both economic efficiency and security under tight section conditions. Case studies verify that the proposed strategy eliminates the risk of section overloading and avoids curtailment or load shedding caused by congestion.
Author Contributions
Funding
Data Availability Statement
Conflicts of Interest
Abbreviations
| Total number of time intervals | |
| Time index | |
| Duration of each time interval (hours) | |
| Set of zones (e.g., renewable-rich zone, load center, hub zone) | |
| Index of zone | |
| Index of thermal unit | |
| Set of thermal units in zone | |
| Fuel cost of thermal unit in zone ($/MWh) | |
| Power output of thermal unit in zone at time (MW) | |
| Startup cost of thermal unit in zone ($/start-up) | |
| Startup indicator of thermal unit in zone at time (1 if startup occurs) | |
| Shutdown cost of thermal unit in zone ($/shut-down) | |
| Shutdown indicator of thermal unit in zone at time (1 if shutdown occurs) | |
| Index of pumped storage plant (PSP) | |
| Set of pumped storage plants in zone | |
| Pumping cost of PSP in zone ($/MWh) | |
| Pumping power of PSP in zone at time (MW) | |
| Generation cost of PSP in zone ($/MWh) | |
| Generation power of PSP in zone at time (MW) | |
| Index of wind plant | |
| Set of wind plants in zone | |
| Variable O&M cost of wind plant in zone ($/MWh) | |
| Actual power output of wind plant in zone at time (MW) | |
| Index of solar plant | |
| Set of solar plants in zone | |
| Variable O&M cost of solar plant in zone ($/MWh) | |
| Actual power output of solar plant in zone at time (MW) | |
| Set of electrical nodes in zone | |
| Penalty cost for renewable curtailment ($/MWh) | |
| Curtailed renewable power at node in zone at time (MW) | |
| Penalty cost for load shedding ($/MWh) | |
| Load shedding amount at node in zone at time (MW) | |
| Load demand at node in zone at time (MW) | |
| Set of thermal units at node in zone | |
| Set of PSPs at node in zone | |
| Set of wind plants at node in zone | |
| Set of solar plants at node in zone | |
| Set of lines entering node | |
| Set of lines leaving node | |
| Index of individual line | |
| Power flow on individual line at time (MW) | |
| Index of inter-zonal section | |
| Set of tie lines belonging to section | |
| Total power flow on section at time (MW) | |
| Maximum total transfer capacity of section (MW) | |
| Maximum power transfer capacity of individual tie line (MW) | |
| Sending node on individual line | |
| Ending node on individual line | |
| Stored energy of PSP in zone at time (MWh) | |
| Pumping efficiency of PSP (p.u.) | |
| Generation efficiency of PSP (p.u.) | |
| Min. stored energy (MWh) | |
| Max. stored energy (MWh) | |
| Target stored energy at end of horizon (MWh) | |
| Maximum number of mode switches allowed for PSP over the dispatch horizon | |
| Maximum number of complete cycles allowed for PSP over the dispatch horizon | |
| Auxiliary binary variable indicating transition to pumping mode at time | |
| Auxiliary binary variable indicating transition to generating mode at time | |
| Maximum pumping power of PSP in zone (MW) | |
| Maximum generation power of PSP in zone (MW) | |
| Curtailed wind power of wind plant w in zone z at time t (MW) | |
| Curtailed solar power of solar plant s in zone z at time t (MW) | |
| Forecast available wind power of wind plant w in zone z at time t (MW) | |
| Forecast available solar power of solar plant s in zone z at time t (MW) | |
| Maximum allowed curtailment ratio in zone (0–1) | |
| Forecast available power of wind plant w and solar plant s in zone z at time t (MW) | |
| Maximum curtailed power in zone z (MW) | |
| Ramp-up rate of thermal unit (MW/h) | |
| Ramp-down rate of thermal unit (MW/h) | |
| Minimum up-time of thermal unit (hours) | |
| Minimum down-time of thermal unit (hours) | |
| Minimum thermal output (MW) | |
| Maximum thermal output (MW) | |
| Commitment status of thermal unit (1 = online) | |
| PSP pumping mode indicator (1 = active) | |
| PSP generating mode indicator (1 = active) | |
| Upward reserve requirement in zone at time (MW) | |
| Downward reserve requirement in zone at time (MW) | |
| Load reserve coefficient (fraction of load) | |
| Reserve coefficient for wind forecast error | |
| Reserve coefficient for solar forecast error | |
| Total load demand in zone at time (MW) |
References
- Wu, H.; Liao, S.; Ke, D.; Xu, J.; Song, L.; Sun, Y.; Fang, K. A novel stochastic unit commitment characterized by closed-loop forecast-and-decision for wind integrated power systems. IEEE Trans. Power Syst. 2024, 39, 2570–2586. [Google Scholar] [CrossRef] [Scilit]
- Zappa, W.; Junginger, M.; van den Broek, M. Is a 100% renewable European power system feasible by 2050? Appl. Energy 2019, 233, 1027–1050. [Google Scholar] [CrossRef] [Scilit]
- China National Energy Administration. The Operation Situation of Grid-Connected Renewable Energy in 2024. 2025. Available online: https://www.nea.gov.cn/20250221/e10f363cabe3458aaf78ba4558970054/c.html (accessed on 14 July 2026).
- Yang, B.; Zhao, Z. Energy storage overcapacity can cause power system instability and blackouts, too. Nature 2024, 633, 286. [Google Scholar] [CrossRef] [Scilit] [PubMed]
- Raynaud, D.; Hingray, B.; François, B.; Creutin, J.D. Energy droughts from variable renewable energy sources in European climates. Renew. Energy 2018, 125, 578–589. [Google Scholar] [CrossRef] [Scilit]
- Pan, X.; Yang, B.; Shao, D.; Zhang, M.; Shi, M.; Wu, Y.; Li, D. Multi-source coordinated supply-guarantee dispatch strategy under consecutive-day renewable energy drought. Energies 2026, 19, 3205. [Google Scholar] [CrossRef] [Scilit]
- Koholé, Y.W.; Ngouleu, C.A.W.; Fohagui, F.C.V.; Tchuen, G. A comprehensive comparison of battery, hydrogen, pumped-hydro and thermal energy storage technologies for hybrid renewable energy systems integration. J. Energy Storage 2024, 93, 112299. [Google Scholar] [CrossRef] [Scilit]
- Xu, L.; Yang, B.; Wang, Y.; Huang, Z.; Xi, J.; Luo, S.; Chen, J.; Chen, R. Impact of transmission line capacity variability on pumped storage scheduling strategies: Analysis of static vs. time-varying congestion scenarios. Energies 2026, 19, 3335. [Google Scholar] [CrossRef] [Scilit]
- Basu, M.; Das, S. Short-term pumped storage hydrothermal generation scheduling considering uncertainty of load demand and renewable energy sources. J. Energy Storage 2023, 70, 107933. [Google Scholar] [CrossRef] [Scilit]
- Nezhad, A.E.; Jowkar, S.; Sabour, T.T.; Rahimi, E.; Ghanavati, F.; Esmaeilnezhad, F. A short-term wind-hydrothermal operational framework in the presence of pumped-hydro storage. e-Prime-Adv. Electr. Eng. Electron. Energy 2024, 8, 100577. [Google Scholar] [CrossRef] [Scilit]
- Yoosefdoost, I.; Basirifard, M.; Álvarez-García, J. Reservoir operation management with new multi-objective (MOEPO) and metaheuristic (EPO) algorithms. Water 2022, 14, 2329. [Google Scholar] [CrossRef] [Scilit]
- Hu, Y.; Jiang, H.; Zhang, C.; Yuan, J.; Zhang, M.; Yao, L.; Chen, Q.; Wu, J.; Zhang, H.; Ma, S.; et al. Advancing solar and wind penetration in China through energy complementarity. Nature 2026, 653, 1060–1068. [Google Scholar] [CrossRef] [Scilit]
- Xia, Z.; Li, Y.; Chen, R.; Sengupta, D.; Guo, X.; Xiong, B.; Niu, Y. Mapping the rapid development of photovoltaic power stations in northwestern China using remote sensing. Energy Rep. 2022, 8, 4117–4127. [Google Scholar] [CrossRef] [Scilit]
- Chen, Y.; Zhou, J.; Ge, Y.; Dong, J. Uncovering the rapid expansion of photovoltaic power plants in China from 2010 to 2022 using satellite data and deep learning. Remote Sens. Environ. 2024, 305, 114100. [Google Scholar] [CrossRef] [Scilit]
- Ren, G.; Wan, J.; Liu, J.; Yu, D. Spatial and temporal assessments of complementarity for renewable energy resources in China. Energy 2019, 177, 262–275. [Google Scholar] [CrossRef] [Scilit]
- China National Energy Administration. Typical Load Profiles of Provincial Power Grid. 2020. Available online: https://www.ndrc.gov.cn/xwdt/tzgg/202012/P020201202546044875868.pdf (accessed on 14 July 2026).
- Al-Oweiti, Q.N.; Kaoud, O.G.; Elbassoussi, M.H.; Rehman, S.; Zubair, S.M. Comparative assessment of battery and pumped hydro storage for renewable-powered reverse osmosis desalination in Saudi Arabia. J. Energy Storage 2026, 144, 119808. [Google Scholar] [CrossRef] [Scilit]
- Tipán-Salazar, L.; Naval, N.; Yusta, J.M. An optimal dispatch model of renewable generation and pumped hydro energy storage for green hydrogen production. Renew. Energy 2025, 246, 122939. [Google Scholar] [CrossRef] [Scilit]
- Serat, Z. Optimizing renewable energy systems for 100% clean energy target: A comparative study of solar, hydro, pumped hydro, and battery storage technologies. J. Energy Storage 2024, 104, 114441. [Google Scholar] [CrossRef] [Scilit]
- Kien, L.C.; Pham, L.H.; Duong, M.P.; Phan, T.M. Maximizing the Total Profit of Combined Systems with a Pumped Storage Hydropower Plant and Renewable Energy Sources Using a Modified Slime Mould Algorithm. Energies 2024, 17, 6323. [Google Scholar] [CrossRef] [Scilit]
- Yan, Y.; Shaheen, H.I.; Yang, B.; Gharehpetian, G.B.; Zuo, Y.; Rashed, G.I. Carbon-Cap-Feasible Robust Capacity Planning of Wind–PV–Thermal–Storage Systems with Fixed Energy-to-Power Ratios. Energies 2026, 19, 546. [Google Scholar] [CrossRef] [Scilit]
- Liu, B.; Liu, T.; Liao, S.; Lu, J.; Cheng, C. Short-term coordinated hybrid hydro-wind-solar optimal scheduling model considering multistage section restrictions. Renew. Energy 2023, 217, 119160. [Google Scholar] [CrossRef] [Scilit]
- Du, E.; Zhang, N.; Kang, C.; Xia, Q. A high-efficiency network-constrained clustered unit commitment model for power system planning studies. IEEE Trans. Power Syst. 2019, 34, 2498–2508. [Google Scholar] [CrossRef] [Scilit]
- Xavier, Á.S.; Qiu, F.; Wang, F.; Thimmapuram, P.R. Transmission constraint filtering in large-scale security-constrained unit commitment. IEEE Trans. Power Syst. 2019, 34, 2457–2460. [Google Scholar] [CrossRef] [Scilit]











| Zone | PSP Current State | Recommended Action | Nodal Power Balance Analysis |
|---|---|---|---|
| Zone A (sending) | Generating | Switch to shutdown or increase pumping | Reduced generation in Zone A → decreased local injection → reduced A → B power flow, alleviating section pressure; increased pumping adds local load → increased local consumption → reduced export power |
| Pumping | Maintain or increase pumping | Pumping is a local load in Zone A; increasing pumping increases local consumption → reduces export power | |
| Idle | Start pumping or remain idle | Starting pumping can absorb surplus local power, reducing export pressure | |
| Zone B (receiving) | Pumping using imported power | Stop pumping or switch to generation | Stopping pumping reduces load in Zone B → reduces demand for imported power → reduces A → B power flow; switching to generation increases local supply → replaces imported power |
| Generating | Maintain or increase generation | Increasing local generation in Zone B reduces dependence on imported power → reduces A → B power flow | |
| Idle | Start generation or remain idle | Starting generation can replace imported power, reducing section occupancy |
| Zone | PSP Current State | Recommended Action | Nodal Power Balance Analysis |
|---|---|---|---|
| Zone B (sending) | Generating | Switch to shutdown or increase pumping | Reduced generation in Zone B → reduced export power; increased local pumping adds local load → reduces export power |
| Pumping | Maintain or increase pumping | Pumping is a local load in Zone B; increasing pumping increases local consumption → reduces export power | |
| Idle | Start pumping or remain idle | Starting pumping can absorb surplus power in Zone B | |
| Zone A (receiving) | Pumping using imported power (from Zone B) | Stop pumping or switch to generation | Stopping pumping reduces Zone A’s demand for imported power → reduces B → A power flow; switching to generation increases local supply → replaces imported power |
| Generating | Maintain or increase generation | Increasing local generation in Zone A reduces dependence on imported power | |
| Idle | Start generation or remain idle | Starting generation replaces imported power, reducing section occupancy |
| Scenario | Line Capacity Limitation in Zonal Section | Total Wind Capacity | Description |
|---|---|---|---|
| A | 500 MW | 2400 MW | Baseline |
| B | 400 MW | 2400 MW | Tightened section capacity |
| C | 600 MW | 2400 MW | Loosened section capacity |
| D | 500 MW | 1920 MW | Reduced wind output |
| E | 500 MW | 2880 MW | Increased wind output |
| Scenario | Wind Installed Capacity (MW) | Thermal Generation (MWh) | Wind Generation (MWh) | Renewable Penetration (%) | Total Curtailment (MWh) | Curtailment Rate (%) | System Operation Cost ($) |
|---|---|---|---|---|---|---|---|
| A | 2400 | 36,385.04 | 28,709.44 | 50.03 | 292.67 | 0.7887 | 1,887,316.44 |
| B | 2400 | 37,074.53 | 28,121.59 | 49.23 | 880.52 | 2.3729 | 1,919,907.16 |
| C | 2400 | 36,324.33 | 28,709.44 | 50.03 | 292.67 | 0.7887 | 1,884,384.27 |
| D | 1920 | 41,690.55 | 23,201.68 | 42.54 | 0.00 | 0.00 | 2,142,087.44 |
| E | 2880 | 32,852.15 | 32,417.32 | 55.07 | 2385.21 | 5.5589 | 1,717,112.77 |
| Indicator | Unit | Scenario A | Scenario B | Scenario C |
|---|---|---|---|---|
| Total daily pumping (TDP) | MWh | 1792.76 | 2493.76 | 1374.03 |
| Total daily generation (TDG) | MWh | 2180.81 | 2780.16 | 1822.80 |
| Minimum reservoir energy (MRE) | MWh | 299.05 | 180 | 594.04 |
| Maximum reservoir energy (XRE) | MWh | 1620 | 1620 | 1620 |
| Curtailed renewable energy (CRE) | MWh | 292.67 | 880.52 | 292.67 |
| Curtailment rate (CR) | % | 0.7887 | 2.3729 | 0.7887 |
| PSH operation | Peak shaving | Deep discharge | Peak shaving |
| Indicator | Unit | Scenario A | Scenario D | Scenario E |
|---|---|---|---|---|
| TDP | MWh | 1792.76 | 397.96 | 2999.62 |
| TDG | MWh | 2180.81 | 988.26 | 3212.67 |
| MRE | MWh | 299.05 | 720 | 180 |
| XRE | MWh | 1620 | 1278.06 | 1620 |
| CRE | MWh | 292.67 | 0 | 2385.21 |
| CR | % | 0.7887 | 0 | 5.5589 |
| PSH Operation | Peak shaving | Peaking shaving | Renewable energy accommodation |
| Indicator | Scenario A | Scenario B | Scenario C | Scenario D | Scenario E | |||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 250 | 300 | 400 | 425 | 250 | 300 | 400 | 425 | 250 | 300 | 400 | 425 | 250 | 300 | 400 | 425 | 250 | 300 | 400 | 425 | |
| TDP | 1795.31 | 1792.76 | 1795.13 | 1795.13 | 2454.49 | 2493.76 | 2493.76 | 2493.76 | 1374.03 | 1374.03 | 1346.29 | 1374.03 | 420.22 | 397.96 | 397.96 | 397.96 | 2999.62 | 2999.62 | 2976.80 | 2999.62 |
| TDG | 2182.99 | 2180.81 | 2182.84 | 2182.84 | 2746.59 | 2780.16 | 2780.16 | 2780.16 | 1822.80 | 1822.80 | 1799.08 | 1822.80 | 1007.28 | 988.26 | 988.26 | 988.26 | 3212.67 | 3212.67 | 3193.17 | 3212.67 |
| MRE | 303.14 | 299.05 | 720.00 | 720.00 | 237.93 | 180.00 | 180.00 | 330.93 | 594.04 | 594.04 | 594.04 | 594.04 | 720.00 | 720.00 | 720.00 | 720.00 | 180.00 | 180.00 | 180.00 | 180.00 |
| XRE | 1612.50 | 1620.00 | 1557.28 | 1620.00 | 1620.00 | 1620.00 | 1620.00 | 1620.00 | 1582.30 | 1620.00 | 1608.89 | 1620.00 | 1112.93 | 1278.06 | 1278.06 | 1278.06 | 1620.00 | 1620.00 | 1620.00 | 1620.00 |
| CRE | 294.80 | 292.67 | 292.67 | 292.67 | 908.41 | 880.52 | 880.52 | 880.52 | 292.67 | 292.67 | 320.41 | 292.67 | 0 | 0 | 0 | 0 | 2386.49 | 2385.21 | 2407.53 | 2384.71 |
| CR | 0.7944 | 0.7887 | 0.7887 | 0.7887 | 2.448 | 2.3729 | 2.3729 | 2.3729 | 0.7887 | 0.7887 | 0.8635 | 0.7887 | 0 | 0 | 0 | 0 | 5.5619 | 5.5589 | 5.6109 | 5.5578 |
| Scheme | Pumping Efficiency | Generation Efficiency | Round-Trip Efficiency | Description |
|---|---|---|---|---|
| ES1 | 0.90 | 0.85 | 0.765 | Low-efficiency condition |
| ES2 | 0.925 | 0.875 | 0.809 | Moderately low-efficiency condition |
| ES3 | 0.95 | 0.90 | 0.855 | Baseline condition |
| ES4 | 0.90 | 0.90 | 0.81 | Pumping efficiency independently low |
| ES5 | 0.95 | 0.85 | 0.8075 | Generation efficiency independently low |
| Indicator | Scenario A | Scenario B | Scenario C | Scenario D | Scenario E | ||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| ES1 | ES2 | ES3 | ES4 | ES5 | ES1 | ES2 | ES3 | ES4 | ES5 | ES1 | ES2 | ES3 | ES4 | ES5 | ES1 | ES2 | ES3 | ES4 | ES5 | ES1 | ES2 | ES3 | ES4 | ES5 | |
| TDP | 1793.36 | 1793.21 | 1792.76 | 1793.12 | 1793.36 | 2577.97 | 2534.73 | 2493.76 | 2577.97 | 2493.76 | 1374.03 | 1374.03 | 1374.03 | 1374.03 | 1374.03 | 400.31 | 431.63 | 397.96 | 420.07 | 443.89 | 3121.40 | 3058.86 | 2999.62 | 3121.40 | 2999.62 |
| TDG | 1983.92 | 2081.38 | 2180.81 | 2100.42 | 2060.14 | 2584.15 | 2681.54 | 2780.16 | 2736.16 | 2625.71 | 1663.14 | 1742.11 | 1822.80 | 1760.97 | 1721.53 | 968.48 | 979.35 | 988.26 | 988.26 | 970.44 | 2999.87 | 3105.76 | 3212.67 | 3176.33 | 3034.19 |
| MRE | 320.66 | 309.71 | 299.05 | 320.88 | 298.48 | 180.00 | 180.00 | 180.00 | 180.00 | 180.00 | 600.67 | 597.35 | 594.04 | 600.67 | 594.04 | 720.00 | 395.00 | 720.00 | 720.00 | 720.00 | 180.00 | 180.00 | 180.00 | 180.00 | 180.00 |
| XRE | 1620.00 | 1620.00 | 1620.00 | 1560.58 | 1620.00 | 1620.00 | 1620.00 | 1620.00 | 1620.00 | 1620 | 1585.96 | 1543.30 | 1620.00 | 1570.93 | 1620.00 | 1168.63 | 1299.26 | 1278.06 | 1278.06 | 1321.70 | 1620.00 | 1620.00 | 1620.00 | 1620.00 | 1620.00 |
| CRE | 292.67 | 292.67 | 292.67 | 292.67 | 292.67 | 821.41 | 851.76 | 880.52 | 821.30 | 880.63 | 292.67 | 292.67 | 292.67 | 292.67 | 292.67 | 0 | 0 | 0 | 0 | 0 | 2282.74 | 2335.36 | 2385.21 | 2282.54 | 2385.41 |
| CR | 0.7887 | 0.7887 | 0.7887 | 0.7887 | 0.7887 | 2.2136 | 2.2954 | 2.3729 | 2.2133 | 2.3732 | 0.7887 | 0.7887 | 0.7887 | 0.7887 | 0.7887 | 0 | 0 | 0 | 0 | 0 | 5.3201 | 5.4427 | 5.5589 | 5.3196 | 5.5594 |
| Scheme | Initial Water Level (% Capacity) | Initial Storage (MWh) | Description |
|---|---|---|---|
| WL1 | 40% | 720 | Low water level |
| WL2 | 45% | 810 | Moderately low water level |
| WL3 | 50% | 900 | Baseline water level |
| WL4 | 55% | 990 | Moderately high water level |
| WL5 | 60% | 1080 | High water level |
| Indicator | Scenario A | Scenario B | Scenario C | Scenario D | Scenario E | ||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 40% | 45% | 50% | 55% | 60% | 40% | 45% | 50% | 55% | 60% | 40% | 45% | 50% | 55% | 60% | 40% | 45% | 50% | 55% | 60% | 40% | 45% | 50% | 55% | 60% | |
| TDP | 1534.99 | 1795.71 | 1792.76 | 1792.20 | 1666.25 | 2456.28 | 2683.23 | 2493.76 | 2304.29 | 2114.81 | 1174.80 | 1374.03 | 1374.03 | 1374.03 | 1374.03 | 732.68 | 589.37 | 397.96 | 206.55 | 15.14 | 2790.22 | 3173.14 | 2999.62 | 2867.72 | 2735.82 |
| TDG | 1795.31 | 1859.33 | 2180.81 | 2504.33 | 2720.65 | 2872.84 | 2618.16 | 2780.16 | 2942.16 | 3104.16 | 1374.03 | 1498.80 | 1822.80 | 2146.80 | 2470.80 | 856.93 | 827.92 | 988.26 | 1148.60 | 1308.94 | 3263.41 | 3037.04 | 3212.67 | 3423.90 | 3635.13 |
| MRE | 296.63 | 296.24 | 299.05 | 299.58 | 299.28 | 180.00 | 180.00 | 180.00 | 180.00 | 180.00 | 594.04 | 594.04 | 594.04 | 594.04 | 629.59 | 640.72 | 720.00 | 720.00 | 720.00 | 720.00 | 180.00 | 180.00 | 180.00 | 180.00 | 180.00 |
| XRE | 1557.28 | 1620.00 | 1620.00 | 1620.00 | 1620.00 | 1620.00 | 1488.32 | 1620.00 | 1620.00 | 1620.00 | 1414.99 | 1504.99 | 1620.00 | 1539.38 | 1516.93 | 1454.81 | 1369.91 | 1278.06 | 1186.22 | 1094.38 | 1620.00 | 1620.00 | 1620.00 | 1620.00 | 1620.00 |
| CRE | 294.80 | 292.67 | 292.67 | 292.67 | 381.20 | 617.64 | 748.96 | 880.52 | 1013.10 | 1145.91 | 292.67 | 292.67 | 292.67 | 292.67 | 292.67 | 0 | 0 | 0 | 0 | 0 | 2125.11 | 2254.53 | 2385.21 | 2515.26 | 2645.31 |
| CR | 0.7944 | 0.7887 | 0.7887 | 0.7887 | 1.0273 | 1.6645 | 2.0184 | 2.3729 | 2.7302 | 3.0881 | 0.7887 | 0.7887 | 0.7887 | 0.7887 | 0.7887 | 0 | 0 | 0 | 0 | 0 | 4.9527 | 5.2544 | 5.5589 | 5.862 | 6.1651 |
| Indicator | Scenario A | Scenario B | Scenario C | Scenario D | Scenario E |
|---|---|---|---|---|---|
| TDP | 1793.12 | 2493.76 | 1374.03 | 397.96 | 2990.43 |
| TDG | 2181.11 | 2780.16 | 1822.80 | 988.26 | 3204.82 |
| MRE | 298.71 | 180.00 | 720.00 | 720.00 | 180 |
| XRE | 1557.28 | 1620.00 | 1505.53 | 1278.06 | 1620 |
| CRE | 292.67 | 880.52 | 292.67 | 0 | 2387.82 |
| CR | 0.7887 | 2.3729 | 0.7887 | 0 | 5.565 |
| TC | 1,907,379.95 | 1,947,274.75 | 1,900,454.60 | 2,148,497.06 | 1,752,645.34 |
| TC2 | 1,887,316.44 | 1,919,907.16 | 1,884,384.27 | 2,142,087.44 | 1,717,112.77 |
| TCR | 1.063 | 1.425 | 0.853 | 0.299 | 2.069 |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2026 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license.
Share and Cite
Pan, X.; Yang, B.; Shao, D.; Zhang, M.; Shi, M.; Wu, Y.; Li, D. Regional Role Matching and Energy Temporal Coupling-Based Coordinated Dispatch of Multiple Pumped Storage Plants Under Zonal Transmission Constraints. Energies 2026, 19, 4188. https://doi.org/10.3390/en19174188
Pan X, Yang B, Shao D, Zhang M, Shi M, Wu Y, Li D. Regional Role Matching and Energy Temporal Coupling-Based Coordinated Dispatch of Multiple Pumped Storage Plants Under Zonal Transmission Constraints. Energies. 2026; 19(17):4188. https://doi.org/10.3390/en19174188
Chicago/Turabian StylePan, Xiaojie, Bo Yang, Dejun Shao, Mujie Zhang, Mengxuan Shi, Yajun Wu, and Dongsheng Li. 2026. "Regional Role Matching and Energy Temporal Coupling-Based Coordinated Dispatch of Multiple Pumped Storage Plants Under Zonal Transmission Constraints" Energies 19, no. 17: 4188. https://doi.org/10.3390/en19174188
APA StylePan, X., Yang, B., Shao, D., Zhang, M., Shi, M., Wu, Y., & Li, D. (2026). Regional Role Matching and Energy Temporal Coupling-Based Coordinated Dispatch of Multiple Pumped Storage Plants Under Zonal Transmission Constraints. Energies, 19(17), 4188. https://doi.org/10.3390/en19174188

