Next Article in Journal
Data-Driven Visualization of the Dynamics of Geothermal Energy and Hot Dry Rock Research
Previous Article in Journal
Thermal Management and Energy Recovery in Commercial Dishwashers: A Theoretical and Experimental Study
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Optimal Siting and Sizing of Battery Energy Storage System in Distribution System in View of Resource Uncertainty

by
Gauri Mandar Karve
1,*,
Mangesh S. Thakare
1 and
Geetanjali A. Vaidya
2
1
Electrical Engineering Department, Pune Vidhyarthi Griha’s College of Engineering and Technology and G K Pate (Wani) Institute of Management, Pune 411009, India
2
Electrical Consultant, SAS Powertech Pvt Ltd., Pune 411045, India
*
Author to whom correspondence should be addressed.
Energies 2025, 18(9), 2340; https://doi.org/10.3390/en18092340
Submission received: 30 March 2025 / Revised: 29 April 2025 / Accepted: 29 April 2025 / Published: 3 May 2025

Abstract

:
The integration of intermittent Distributed Generations (DGs) like solar photovoltaics into Radial Distribution Systems (RDSs) reduces system losses but causes voltage and power instability issues. It has also been observed that seasonal variations affect the performance of such DGs. These issues can be resolved by placing optimum-sized Battery Energy Storage (BES) Systems into RDSs. This work proposes a new approach to the placement of optimally sized BESSs considering multiple objectives, Active Power Losses, the Power Stability Index, and the Voltage Stability Index, which are prioritized using the Weighted Sum Method. The proposed multi-objectives are investigated using the probabilistic and Polynomial Multiple Regression (PMR) approaches to account for the randomness in solar irradiance and its effect on BESS sizing and placements. To analyze system behavior, simultaneous and sequential strategies considering aggregated and distributed BESS placement are executed on IEEE 33-bus and 94-bus Portuguese RDSs by applying the Improved Grey Wolf Optimization and TOPSIS techniques. Significant loss reduction is observed in distributed BESS placement compared to aggregated BESSs. Also, the sequentially distributed BESS stabilized the RDS to a greater extent than the simultaneously distributed BESS. In view of the uncertainty, the probabilistic and PMR approaches require a larger optimal BESS size than the deterministic approach, representing practical systems. Additionally, the results are validated using Improved Particle Swarm Optimization–TOPSIS techniques.

1. Introduction

The addition of Renewable Energy Resources (RERs), like wind generators and solar photovoltaics (PV), into Radial Distribution Systems (RDSs) minimizes system losses and reduces the dependence on fossil fuels. The increased integration of irregular and uncontrollable RERs into RDSs leads to voltage and power instability. This variability and instability can be reduced by properly placing optimally sized Battery Energy Storage (BES) Systems into RDSs for smooth power generation from RERs. So, as the level of PV penetration increases, BES becomes more important [1]. Numerous researchers have addressed challenges associated with PV-integrated RDSs and proposed BES as a potential solution for various objective functions with several IEEE standard RDSs [1,2,3,4] and real-time case studies [1,2,3,4,5].
The BES System (BESS) is an essential asset that contributes significantly to various operational domains such as stationary and mobile applications [6]. In the electrical power system, it supports distribution services such as upgrade deferral and voltage stability. In addition, the BESS plays a vital role in ancillary services, encompassing congestion management, frequency regulation, and the provision of both spinning and non-spinning reserves. The BESS also enhances energy services through its supply and arbitrage and assists with the limitation of RE outputs. Moreover, the BESS is effective in energy management services by enhancing power quality and ensuring reliability [7,8]. The most common and beneficial utilization of the BESS can be improving system voltage [1,9], reducing system losses [1,10], congestion management [3,11], load leveling, and peak shaving using different optimization techniques [1,5,9,10,11,12]. To provide all the above-mentioned services satisfactorily, the OPSBESS is crucial. Installing the BESS in suboptimum places may lead to increased costs as well as system losses, thereby reducing system reliability.
While most of the research has centered on the sizing of the BESS, there is relatively less research on siting. The research on siting has focused on a single-objective function [13,14]. Few researchers have used multiple objectives for the OPSBESS, such as voltage deviations and power losses [5,15,16], voltage improvement, and congestion management [11]. Zhengmao et al. proposed a methodology for voltage restoration and load current sharing in multi-bus microgrids over directed networks [17]. It is reported in the literature that losses, power stability, and voltage stability are affected by the integration of PV and BESSs into RDSs [15,18,19]. Therefore, in this work, a new approach based on the Power Stability Index (PSI), along with objectives indicating Active Power Losses (APLs) and the Voltage Stability Index (VSI), is considered and optimized simultaneously. Hence, this work focuses on the multiple objectives of siting and sizing the BESS while minimizing the APL and PSI and maximizing the VSI for a grid-connected PV-BES System. These objectives are assigned with suitable weights using the Weighted Sum Method (WSM) and are then optimized simultaneously using the Improved Grey Wolf Optimization (IGWO) technique and ‘The Technique for Order of Preference by Similarity to the Ideal Solution’ (TOPSIS).
Earlier studies showed that the OPSBESS problem for RDSs has been predominantly addressed using a deterministic approach without considering variability in the resource. However, considering uncertainties in RESs is crucial for analyzing system behavior under real-world conditions. In the literature, it is found that the uncertainties associated with PV are addressed using the Beta Probability Density Function (β-PDF) [20,21]. In the proposed work, the uncertainties in PV irradiance for ten years are addressed with the β-PDF and Polynomial Multiple Regression (PMR) techniques [22]. The results of deterministic along with β-PDF and PMR approaches are compared to predict solar PV irradiance to determine the OPSBESS for a modified IEEE 33-bus RDS (MBRDS) and a modified real 94-bus Portuguese RDS (MRBPRDS)[23].
In addition to this, the problem of optimal-sized BESS placement can be analyzed using the simultaneous and sequential placement of BESSs in RDSs. It is observed that the comparison of simultaneously and sequentially distributed BESS placement is less addressed in the literature. Hence, considering lithium-ion battery chemistry, the logic of the simultaneous and sequential placement of optimally sized distributed BESSs is implemented and compared using two RDSs.
The significant contributions of this paper are as follows:
  • Proposal of a multiple-objective function (MOF) based on minimizing the APL and PSI and maximizing the VSI for the OPSBESS.
  • Incorporation of uncertainties in the resource for the OPSBESS using probabilistic and PMR approaches for MBRDSs.
  • Analysis of simultaneously and sequentially distributed BESS placement to understand the system behavior using IGWO and TOPSIS (IGT). The results are validated using Improved Particle Swarm Optimization–TOPSIS (IPT) techniques.
This paper is structured as follows: Section 2 describes the grid-connected PV-BES System with its mathematical modeling. Section 3 formulates a multi-objective problem along with the constraints. Section 4 details IGWO, the optimization technique. Section 5 presents a detailed analysis of the results derived from the proposed work, whereas Section 6 offers the concluding remarks of this paper.

2. Grid-Connected PV-BES System

The problem of the OPSBESS is solved for a grid-connected PV-BES System for the MOF by minimizing the APL and PSI and maximizing the VSI simultaneously using the WSM-IGWO-TOPSIS methods. The MBRDSs test the logic of the simultaneous and sequential placements of the distributed BESS. The schematic of the system under study consists of a solar PV system, utility grid, BESS, inverter, and load (Figure 1).
A detailed description of the system components with mathematical modelling is provided below.

2.1. Solar PV System

This study evaluated the strategic placement of three PV systems at designated locations, focusing on the criteria of loss minimization and voltage enhancement for two RDSs. In the case of the standard IEEE 33-bus RDS, these PV systems are placed at bus numbers 18, 25, and 30, with the size of each PV system set as 600 kW. Therefore, the PV system has a total power rating of 1.8 MW.
In the case of the real 94-bus Portuguese RDS, these PV systems are placed at bus numbers 19, 58, and 84, with the size of each PV system set as 800 kW. Therefore, the PV system has a total power rating of 2.4 MW. The system load is supplied by PV, utility grid, and BESS power. Three approaches, deterministic, probabilistic, and PMR, are considered to determine the profiles of solar irradiance and calculate the output of the PV systems for 24 h. The output power of each PV panel and the whole PV system can be found by taking into account the solar irradiance received by the PV panels at that site. The solar irradiance for ten years is considered for a specific location (Portugal—latitude 39.99° N and longitude 8.22° W) [22]. The detailed mathematical modeling for these approaches is as follows.

2.1.1. Deterministic Approach

This approach focuses on matching the estimated PV generation with the expected demand under the assumption that all input variables are known with certainty. It does not need past power measurements and detailed information regarding the PV panel set-up, such as geographic position, electrical configuration, etc. In the deterministic approach, the individual PV panel’s output power is ascertained from Equation (1), while the aggregate power generated by the entire PV system can be determined using Equation (2).
p P V s i n g l e = P R S s 2 R S R S R C R   if   0   s R C R   P R S s R S R S   i f   R C R   s R S R S   P R S   i f   R S R S s  
P P V = p P V s i n g l e × N P V
where the following variables are used:
PRS: rated PV power (W);
s: solar irradiance (W/m2);
RSRS: solar irradiance under the standard environment set as 1000 W/m2;
RCR: certain solar irradiance point (W/m2);
p_(PV-single): power rating of a PV panel (W);
Ppv: total power output of all PV panels (W);
NPV: number of PV panels.

2.1.2. Probabilistic Approach

Probabilistic models offer valuable insights into the influence of various factors on outcomes, enabling the identification of data patterns and relationships. This approach is applied to account for uncertainties in solar PV irradiance to study the system dynamics for the OPSBESS. Detailed information about the PV system, such as the geographic position, voltage and current temperature coefficients, and electrical configuration (voltage and current under maximum power point conditions, short circuit, open circuit, etc.), is needed for a probabilistic approach. After ten years of solar PV irradiance data collection in Portugal [22], statistical analysis was conducted utilizing EasyFit 5.5 (EasyFit 5.5, Informer Technologies, Inc., Los Angeles, CA, USA) to ascertain the most suitable PDF for the observed data pattern. The analysis revealed that the Beta PDF (β-PDF) is the most appropriate for the dataset in question. Furthermore, the uncertainties associated with PV irradiance were modeled using the β-PDF, as outlined in Equations (3)–(14), ultimately providing the output for a single PV panel [5,8,20,21]. The overall output of the PV system is assessed based on the number of PV panels installed in the system.
The β-PDF for solar irradiance (s), established within the limits of 0 ≤ s ≤ 1, is characterized by the shape parameters α and β, both of which are greater than zero. This function is represented as beta (s) and defined by Equation (3). Equations (3)–(14) are derived from [8,21]. These equations incorporate the effects of seasonal changes as well as daily variations in temperature and solar irradiance. The various parameters of solar irradiance (α, β: shape, mean (μ), and standard deviation (σ)) are computed for each hour of each day over a span of ten years.
b e t a s = Γ α + β Γ α Γ β . s α 1 . 1 s β 1   0     s     1 ,   α ,   β     0 0   otherwise
The mean (µ) and standard deviation (σ) are used to derive the shape parameters (α and β) of solar irradiance over a period of ten years, as below.
β = ( 1 μ ) [ μ 1 + μ σ 2 1 ]
α = [ ( μ × β ) ( 1 μ )   ]
For any specific hour, the probability of solar irradiance is calculated as
p ( s ) = s 1 s 2 [ ( b e t a ( s ) . d s ) ]
where the two solar irradiance limits are s1 and s2.
Equations (7)–(14) are used to calculate the PV panel’s output for a given time (h).
0 1 [ s ( p ( s ) . d s ) ] = 0 1 [ [ s Γ ( α + β ) Γ ( α ) Γ ( β ) . s α 1 . ( 1 s ) β 1 ] d s ]
The probabilistic output of a single PV panel for an hour (h) is found by
P V O U T h = 0 1 P V N E T × p s . d s   w a t t
The net output of a single PV panel (PVNET) can be found by multiplying the Fill Factor (FF), net voltage (VNET), and net current (INET), as given by Equation (9).
PVNET = [FF × VNET × INET] watt
The FF serves as an indicator of the efficiency of a PV module, as defined by Equation (10).
FF = {[VMPP × IMPP]/[VOC x ISC]}
VNET = [VOC + Kv (Tc)] volts
INET = s [ISC + Ki (Tc − 25)] amperes
0 1 [ s ( p ( s ) . d s ) ] = 0 1 s [ ( b e t a ( s ) . d s ) ]
TC = TA + s [(TNOCT − 20)/0.8] °C
where the following variables are used:
s1 and s2: solar irradiance limits (W/m2);
α and β: shape parameters of solar irradiance (W/m2);
µ and σ: mean and standard deviation of solar irradiance (W/m2);
p(s): probability of solar irradiance (W/m2);
s: solar irradiance (W/m2);
Γ: gamma function;
TC: cell temperature (°C);
TA: ambient temperature (°C);
TNOCT: temperature at Nominal Operating Cell Temperature (NOCT) (°C).
The following specifications of the solar PV panel [24] are used to calculate the probabilistic output of a single PV panel for an hour as ‘PVOUT (h)’ given by Equation (8).
The total probabilistic output power of the whole PV system is found by multiplying Equation (8) with the daily hours of available solar irradiance and the number of PV panels installed in the system, as given by Equation (2) [25]. The solar irradiance for one day is calculated from the total probabilistic PV power output given by Equation (2) and by knowing the area of the PV panel and its efficiency (Table 1).
The solar irradiance for a specific time (t) is expressed in Equation (15).
s(t) = Ppv(t)/(ηPV × A)
where the following variables are used:
  • s(t): solar irradiance (W/m2) at ‘t’;
  • Ppv(t): total power output of PV panels at ‘t’(W);
  • ηPV: efficiency of PV panel (%);
  • A: area of PV panel (m2).

2.1.3. Polynomial Multiple Regression Approach (PMRA)

The PMRA is one of the proven ways to account for the randomness in system behavior. It is a regression analysis that finds one dependent variable against multiple independent variables which share non-linearity among them. In this case, solar irradiance is the dependent variable and is estimated against three independent variables: the wind velocity, cell temperature, and ambient temperature over 10 years. To establish the PMR model among these variables, the solar irradiance of Portugal is considered for ten years [22]. From the given solar irradiance data, the mean square error (mse) and root mean square error (rmse) are found using the sklearn.metrics library of Python programs (Polynomial Regression In Python, n.d.).
The best-fit curve of solar irradiance with the PMRA is obtained for Portugal for 24 h. Utilizing this best-fitted curve of solar irradiance, the output of three solar PV systems is determined with an accuracy level of 0.99 and compared with deterministic and probabilistic approaches for finding the OPSBESS.
The solar irradiance obtained using deterministic, probabilistic, and PMR approaches is depicted in Figure 2. The total output of three PV systems for three sets of solar irradiances is calculated to determine the OPSBESS.

2.2. Load

The load demand data for Portugal are derived by calculating the average annual load demand values, which are subsequently averaged daily, as depicted in Figure 3. The load demand curves considered for the IEEE 33-bus and 94-bus Portuguese RDSs are shown in Figure 3a,b, respectively [23].

2.3. BESS

Depending on the State of Charge (SOC), the BESS stores excess power if the generated power surpasses the load demand (charge) and supplies the load when there is a shortage of electricity (discharge). In this work, lithium-ion battery chemistry is considered with an SOC range of 20% to 100%. The charging mode energy and discharging mode energy of the BESS at a specific time ‘t’ are determined by Equations (16) and (17) [25].
Charging mode:
E B E S S t = E B E S S t 1 × 1 ρ + E p v t E l o a d t ɳ i n v × ɳ B E S S
Discharging mode:
E B E S S t = E B E S S t 1 × 1 ρ E l o a d t ɳ i n v E p v t × ɳ B E S S
where the following variables are used:
  • EPV(t): energy generated by the solar PV at instant t (kWh);
  • Eload(t): energy required by the load at instant t (kWh);
  • EBESS(t): energy stored by the BESS at instant t (kWh);
  • ρ: self-discharge rate of the BESS;
  • ηBESS: charging and discharging efficiencies of the BESS;
  • ηinv: efficiency of the inverter.

3. Multi-Objective Problem Formulation and Constraints

Integrating BESSs, along with their optimal placement and sizing within the RDS, significantly impacts the system’s power flow, losses, voltage stability, and overall power stability. Therefore, this study aims to simultaneously optimize three key objectives: the minimization of the APL and PSI and the maximization of the VSI. Simultaneous and sequential strategies for BESS placement with their optimal sizes are executed on two MBRDSs considering lithium-ion battery chemistry.

3.1. Minimization of APL (F1)

In conventional power systems, significant power losses are primarily observed in the delivery phase, thereby adversely affecting the annual revenue generated by utilities within Distribution Systems (DSs). Therefore, the primary objective is to deliver power at minimum losses, which is expressed by Equation (18) and referred from [12].
F 1 = M i n i m i z a t i o n   o f i = 1 N j = 1 N α i j P i P j + Q i Q j + β i j ( Q i P j P i Q j )
where the following variables are used:
−αij = [Rij cos(δi − δj)/ViVj] and βij = [Rij sin(δi − δj)/ViVj]
  • N: number of buses in the system;
  • Rij: resistance of branch between bus i and bus j (Ω);
  • Pi: injected active power at the ith bus (watt);
  • Pj: injected active power at the jth bus (watt);
  • Qi: injected reactive power at the ith bus (VAR);
  • Qj: injected reactive power at the jth bus (VAR);
  • Vi: voltage magnitude at sending end voltage at the ith bus (volts);
  • Vj: voltage magnitude at receiving end voltage at the jth bus (volts);
  • δi: phase angle at the ith bus (radians);
  • δj: phase angle at the jth bus (radians).

3.2. Minimization of PSI (F2)

The PSI serves as a measure of line voltage stability within the system. It assists in identifying the most vulnerable bus, which may be susceptible to line voltage instability when an increase in load demand occurs [26]. Better line voltage stability of the system is achieved if the PSI value is closer to zero (PSI ≤ 0). When a PV system is added to the RDS, it affects the line voltage stability. Therefore, to maintain line voltage stability, the PSI is incorporated in this study for BESS placement. It is also equally important as the APL and VSI. Initially, the PSI values for all buses are calculated without the integration of the BESS and are subsequently arranged in descending order. The optimization process is designed to minimize this index. Therefore, the BESS is installed on the bus, which demonstrates the highest PSI value.
The PSI framework is developed based on a two-bus system that operates with a stability margin of less than one to ensure proper voltage stability, as outlined in Equation (20) [26].
P S I = [ 4 R i j ( P L P G ) ]   [ | V i | c o s ( θ δ ) ] 2 1
F 2 = M i n i m i z a t i o n   o f   P S I = M i n i m i z a t i o n   o f   [ 4 R i j ( P L P G ) ]   [ | V i | c o s ( θ δ ) ] 2 1
where the following variables are used:
  • Rij: resistance of branch between bus i and bus j (Ω);
  • PL: active power at the load bus (watt);
  • PG: injected active power into the system (watt);
  • Vi: sending end voltage (volts);
  • θ: angle of line impedance (radians);
  • δ: phase angle (radians).

3.3. Maximization of VSI (F3)

Maximizing the VSI of a system branch with the minimum VSI value improves the VSM of the complete system. The system is stable when the VSI is less than one and unstable when it is more than one. A VSI closer to one indicates higher voltage stability. The proposed objective function for the maximization of the VSI and, hence, the maximization of the VSM can be expressed by Equation (22). It is developed according to a quadratic equation for the bus ‘j’ in a power system, which is referred from [12,27] as
VSIj = [|Vi|4 − 4(PjRij + QjXij)|Vi|2 − 4(PjXij − QjRij)2]
where the following variables are used:
  • VSIi: Voltage Stability Index of bus ‘j’;
  • Pj: (sum of the active power loads of all the buses beyond bus j) + (active power load of bus j itself) + (sum of the Active Power Losses of all the branches beyond bus j) (watt);
  • Qj: (sum of the reactive power loads of all the buses beyond bus j) + (reactive power load of bus j itself) + (sum of the reactive power losses of all the branches beyond bus j) (VAR);
  • Rij: resistance of the branch connecting bus i and bus j (Ω);
  • Xij: reactance of the branch connecting bus i and bus j (Ω);
  • Vi: sending end voltage (volts).
If the calculated VSI for all buses (except the slack bus) to the last bus is greater than zero, the studied DS has stable performance conditions. The bus with the lowest VSI is more sensitive to voltage collapse and is the most suitable bus for installing the BESS to achieve better stability conditions for the system. The bus with the lowest VSI has the worst stability; hence, this index is proposed inversely, as given in Equation (23). Therefore, the objective function becomes VSIj.
F3 = Maximization of VSI = Maximization of VSIj
Therefore, by combining Equations (18)–(23), the minimum of the MOF can be formulated. The OPSBESS is calculated after satisfying all the constraints mentioned below.

3.4. Multi-Objective Problem Formulation

The problem of the OPSBESS in grid-connected or islanded energy systems is important. A minor adjustment in the number and placement of BESSs can influence the overall sizing and efficiency of the system. Such changes have a significant impact on performance, investment, and operating costs.
In this work, two Multiple-Criteria Decision-Making (MCDM) techniques are implemented: the WSM and TOPSIS [28]. The WSM prioritizes the objectives, while the combination of the TOPSIS and IGWO techniques yields better results.
The MOF is formulated as illustrated in Equations (24)–(27). The weights can be determined as per the priority of the objective function. After systematically adjusting the weights W1, W2, and W3 from 0 to 1 in steps of 0.1, it was determined that variations in the APL exhibit greater sensitivity to minor changes in the size of the BESS compared to the PSI and VSI. As a result, the APL is assigned the highest priority in this analysis, leading to the final weights of W1 = 0.4 and W2 = W3 = 0.3 for the optimal sizing of the BESS. The MOF is utilized to ascertain the most advantageous location for the BESS, as mathematically represented in Equation (27). Accordingly, the bus associated with the lowest value of the MOF is identified as the most appropriate site for the installation of the BESS.
i = 1 n W i = i = 1 3 W i = 1
where W1, W2, and W3 represent the weights associated with the objective functions.
(W1 + W2 + W3) = (0.4 + 0.3 + 0.3) = 1
Equation (25) is used to find the optimum solution.
Minimization of MOF = Min [(W1 × F1) + (W2 × F2) + (W3/F3)]
where F1 and F2 represent the minimization of the APL and PSI, respectively, and F3 signifies the maximization of the VSI.
Therefore, from Equation (25), Equation (26) becomes
Minimization of MOF = Min [(0.4 × APL) + (0.3 × PSI) + (0.3/VSI)]
Constraints: The following constraints are applied to Equation (27):
Equations (28) and (29) represent the active and reactive power balance at the ith bus.
P i = V i j = 1 N V j Y i j c o s ( θ i j + δ j δ i ) i
Q i = V i j = 1 N V j Y i j s i n ( θ i j + δ j δ i ) i
The bounds on the maximum installation size of an individual PV panel at the ith bus are
0 ≤ NPV ≤ NPVmax ∀ i
The constraints pertaining to the maximum allowable installation size of an individual BESS at the ith bus have been defined.
SBESSi ≤ SBESS max ∀ i
The integration of the solar PV and BESS into the RDS causes an inrush current and reverse power flow into the system, leading to a rise in voltage at the buses. Therefore, the minimum and maximum voltage at each bus for all cases should satisfy the following limits:
Vi(min) ≤ Vi ≤ Vi(max) ∀ i
where Vi represents the voltage magnitude at the ith bus. Vi(min) and Vi(max) are assumed to be 0.95 pu and 1.05 pu, respectively, considering the allowable variation as ±5% of the rated voltage.
Consequently, after fulfilling all stipulated constraints, Equation (27) is solved by applying the IGWO algorithm to determine the optimum size of the BESS to be implemented at the maximum MOF value. The optimization methodology is elaborated upon in the subsequent section.

4. IGWO for OPSBESS

The multiple objectives of minimizing the APL and PSI and maximizing the VSI, each with distinct weights, are systematically analyzed and implemented in the context of the MBRDS to identify the OPSBESS. To solve this multi-objective problem, it is necessary to run the load flow many times with all objective functions and their constraints. Therefore, the use of the optimization algorithm is necessary. The IGWO method is selected for the said problem because it is suitable for solving various problems of engineering design [29] as well as electrical power systems. IGWO is implemented for the optimal allocation of Distributed Generation [30], economic dispatch [31], intelligent energy management and battery sizing [32], the OPSBESS [33], etc. In addition to this, IGWO has the distinct advantages of simple principles, fewer parameters, easy implementation, convergence speed, convergence precision, and robustness compared with other algorithms and the ability to resolve the problem of instability compared with other algorithms [34,35]. To decide the preferences of objective functions, the WSM assigns different weights to them. To analyze system behavior, simultaneous and sequential strategies of BESS locations are executed on the MBRDS by combining IGWO with the TOPSIS for better-optimized results. Hwang and Yoon invented the TOPSIS in 1981 [36]. The technique identifies the most favorable alternatives based on their proximity to the positive ideal solution while maintaining the greatest distance from the negative ideal solution. It is combined with different optimization techniques for solving various engineering problems [12,37] for better system performance. This technique emphasizes the significance of proximity to the positive ideal solution, and as such, it has been incorporated into this work.
The proposed IGWO algorithm aims to achieve the optimized solution in the shortest time possible with the most accuracy based on local and global searches. The flow chart for determining the OPSBESS in a grid-connected PV-BES System using IGWO is described in Figure 4.
This study applies IGWO-TOPSIS to solve the OPSBESS by satisfying the MOF along with the constraints. This study is implemented in the MBRDS and MRBPRDS, considering deterministic, probabilistic, and PMR approaches. In this algorithm, each wolf (α, β, δ, ω) is the feasible solution for the optimal BESS size and its placement. After obtaining optimal values for the size and placement of the BESS, its simultaneous and sequential placements are carried out using IGWO-TOPSIS techniques. The system behaviour is analyzed for different cases, which are explained in Section 5.

5. Results and Discussion

The randomness in the solar PV irradiance is considered for ten years, and its effect on the OPSBESS is analyzed for the probabilistic and PMR approaches. The results of the OPSBESS of these approaches are compared with the deterministic approach. The size of the BESS and the performance of the system will vary according to the approach used. The OPSBESS has been optimized for the MOF and executed on two RDSs: standard IEEE 33-bus and real 94-bus Portuguese, considering all relevant constraints through the application of the IGWO-TOPSIS techniques.

5.1. IEEE 33-Bus RDS

The proposed work of the OPSBESS is analyzed for various cases with placements of the PV and BESS (Case I to Case V), as explained below.
Case I: standard IEEE 33-bus RDS.
The problem of the OPSBESS is framed and solved using the standard IEEE 33-bus RDS. It is a 12.66 kV, 100 MVA system with active and reactive power demands of 3.715 MW and 2.3 MVAR, respectively [23].
Case II: standard IEEE 33-bus RDS with placements of PV systems (modified IEEE 33-bus RDS—MBRDS without BESS).
With voltage improvement and loss reduction as prime objectives, three PV systems are placed on specific buses (18, 25, and 30) of the IEEE 33-bus RDS. Thus, the system formed is termed a modified IEEE 33-bus system (MBRDS). Each PV system has a power rating of 600 kW. Consequently, the aggregate capacity of the three PV systems is 1.8 MW. The addition of three PV systems to the standard IEEE 33-bus RDS changed the load flow, reduced the system losses, and improved the voltage profiles of the buses.
Case III: MBRDS with aggregated BESS.
In this case, the load flow is run to satisfy the MOF and the constraints to find the optimal BESS size and candidate bus for the BESS location after placing three PV systems. Following the initial load flow analysis, Bus 26 was identified as the priority site for the deployment of the aggregated BESS. This strategic placement effectively minimized both the APL and PSI while concurrently maximizing the VSI at the optimal capacity. Bus 26 was identified as the candidate bus for placing an aggregated BESS with a size of 2.3 MW for the deterministic approach, 2.42 MW for the B-PDF approach, and 2.4 MW for the PMR approach. Case III is depicted in Figure 5.

5.2. Analysis of MBRDS Using Simultaneous and Sequential BESS Placements

The optimally sized BESS is placed in the MBRDS simultaneously and sequentially. For aggregated BESS placement (Case III), as only one unit of the BESS needs to be placed after the first load flow run in the system after PV placement, there is no difference between the logic for the simultaneous and sequential placements of the BESS. The logic of the OPSBESS changes for Case IV and Case V. In these cases, the optimal size of the aggregated BESS unit is distributed optimally into multiple smaller units based on the system’s requirements. The BESS placement process varies between the simultaneous and sequential strategies.

5.2.1. Simultaneous BESS Placements

In the simultaneous placement strategy, all BESS units are placed at once, with load flow calculations run only once, irrespective of the number of BESS units required within the system. This analysis is essential for determining key parameters, including the APL, PSI, and VSI. In a specific case involving the placement of two BESS units following an initial load flow analysis with three PV systems, the first BESS unit was strategically located at the weakest bus (Bus 26), and at the same time, the second BESS unit, optimally sized, was subsequently positioned at the next weakest bus. This deliberate placement is intended to significantly enhance the overall performance and reliability of the system.

5.2.2. Sequential BESS Placements

In the sequential placement strategy, the BESS units are placed one by one, with the load flow recalculated after each placement to determine the next weakest bus for BESS allocation. For example, when placing two BESS units—one at a specific bus (Bus 26) and the other BESS unit at the optimal capacity—the process begins with a load flow analysis that accounts for the integration of three PV systems. The first BESS unit is strategically placed at the weakest bus, identified as Bus 26. Following this placement, the load flow analysis is repeated to identify the next weakest bus, which is Bus 18, for the installation of the second BESS unit. This sequential approach is repeated until all required BESS units are effectively integrated into the system.
For illustration purposes, Case IV and Case V are explained for the sequential OPSBESS.
Case IV: MBRDS with two BESS units.
To improve the system performance, the aggregated BESS (optimal size) is distributed optimally into two suitable sizes of BESSs. The major portion of the optimal BESS size is strategically allocated to the first location, with the residual capacity assigned to the second location. The first location of the BESS is the weakest bus in the system (Bus 26), and the second location of the BESS is the second weakest bus in the system after running the load flow by placing the first BESS at Bus 26.
Case V: MBRDS with three BESS units.
For further improvement in the system performance, the aggregated BESS (optimal size) is distributed into three suitable sizes of BESSs. The optimal BESS size is placed at the first location (weakest bus in the system—Bus 26). Then, the load flow is run, and the second optimal size of the BESS is placed at the second weakest bus (Bus 18). Again, the load flow is run with these two BESSs to obtain the third weakest bus. The remaining optimal size of the BESS is placed at this third weakest bus of the system. Thus, this process is repeated as per the BESS units required to be installed in the system.
Similarly, the BESS can be distributed into four (Case VI—four BESS units of optimal size), five (Case VII—five BESS units of optimal size), or six (Case VIII—six BESS units as of optimal size) units or as per the requirement for BESS units in the system. For Case IV to Case VIII, the OPSBESS logic is applied sequentially, optimizing the placement of two to six BESS units across different buses. Each BESS unit is placed at the weakest bus in the system based on load flow analysis. The system’s performance improves as more BESS units are optimally placed in sequence, following the priorities of the APL, PSI, and VSI.
In the same way, the results for these five cases (Case I to Case V) are obtained for probabilistic and PMR approaches with simultaneous and sequential BESS placements. The outcomes covering all three approaches are summarized in Table 2 for comprehensive comparison and the performance assessment of the modified IEEE 33-bus RDS.
In these five cases, Table 2 shows a significant loss reduction in sequentially distributed BESS placement compared to simultaneously distributed BESS placement for all three approaches, which is graphically presented in Figure 6.
The loss reduction is obtained for the five cases (Case I to Case V) using deterministic, probabilistic, and PMR approaches with simultaneous and sequential BESS placements. It is presented in Table 2 and graphically shown in Figure 6. The comprehensive loss comparison for the modified IEEE 33-bus RDS is given in Figure 6.
It is noted from Figure 6a–c that the loss reduction in the case of sequential BESS placements for all approaches is more significant compared to the simultaneous BESS placements. It is observed from Figure 6d that the loss reduction in the case of sequential BESS placements for the probabilistic approach is greater compared to the other two approaches due to the larger BESS size. The observed reduction in losses may seem marginal; however, it represents a daily decrease in megawatt-hours (MWh) with an aggregated BESS capacity of 2.3 MW for the deterministic approach, 2.42 MW for the probabilistic (β-PDF) approach, and 2.4 MW for the PMR approach. Over the course of a year, this loss reduction will accumulate significantly, particularly with larger BESS capacities implemented in more extensive system configurations.

5.3. Analysis of System Parameters for Probabilistic Approach (Beta PDF) for MBRDS

This work analyzes the optimization of multiple objectives, minimizing the APL and PSI and maximizing the VSI for the OPSBESS for the MBRDS. Probabilistic (Beta PDF) and PMR approaches account for uncertainties in solar irradiance, and then they are evaluated against a deterministic approach. The analysis encompasses a variety of system parameters, including the APL, PSI, VSI, voltage profiles, overall system power profiles, and convergence curve of IGWO, for all three approaches. However, for the purpose of understanding, the results are shown for the aggregated OPSBESS (Case III) for the probabilistic approach in Figure 7, Figure 8, Figure 9, Figure 10, Figure 11, Figure 12, Figure 13 and Figure 14. These figures illustrate three scenarios: the base case (standard IEEE 33-bus RDS—Case I), the PV case (modified IEEE 33-bus RDS with three PV placements—Case II), and the PV + BESS case (MBRDS with aggregated BESS integration—Case III).
Figure 7 shows that the system losses are highest in the base case. In the PV case, the system losses decrease with the availability of PV power and reach their lowest when both the PV and battery are utilized. Placing the PV systems near the maximum load or at the farthest end reduced the system losses. Adding three PV systems into the standard IEEE 33-bus RDS (MBRDS) changed the load flow. The load flow is run considering the APL minimization, PSI minimization, and VSI maximization criteria to identify the weakest bus for aggregated BESS placement. This addition of an aggregated BESS into the MBRDS reduced system losses, irrespective of its charging–discharging cycles.
Figure 7 shows a sudden rise in the system losses when the BESS acts as a load and is charged by the PV or grid power in the morning. The system losses decrease when the BESS is discharged in the evening. The net result of the charging and discharging of the BESS throughout the day, along with the PV, reduces the system losses to a greater extent.
A PSI value approaching zero (PSI ≤ 0) signifies enhanced line voltage stability within the system. The bus with the highest PSI value is the most suitable for BESS placement. The IGWO-TOPSIS techniques minimized this index after placing an optimum-sized BESS. As depicted in Figure 8, the buses with the PV + BESS result in the lowest PSI values, while the base case (Case I) and the case with PV placement (Case II) exhibit changes in PSI values at a few buses.
Figure 8 indicates that the combination of the PV and BESS provides greater system stability compared to the base case or the PV case alone, as the maximum PSI value obtained is 0.01 pu.
Figure 9 indicates that the PV + BESS has higher voltage stability than the base case (Case I) and the system with the PV case (Case II). The system is stable when the VSI is less than one and unstable when it is more than one. A VSI closer to one indicates higher voltage stability. After PV placement, the VSI values for all buses (except the slack bus) are computed without the integration of the BESS and arranged in ascending order. The bus exhibiting the lowest VSI demonstrates an increased sensitivity to voltage collapse and is the most appropriate candidate bus for the installation of the BESS. This installation is expected to enhance the stability conditions of the overall system effectively. The IGWO-TOPSIS process maximized this index after placing an optimum-sized BESS.
Figure 10 shows the system’s voltage profiles for three scenarios: the base case (Case I), the case involving PV placements (Case II), and the case incorporating both PV and BESS placements (Case III). In the base case, which utilizes the standard IEEE 33-bus RDS, it has been observed that the system voltage is at its lowest across all buses. After adding three PV systems to the standard IEEE 33-bus RDS, the system voltage at all buses is improved. The system voltage is further enhanced by adding an aggregated BES System. A notable enhancement in the system voltage profile has been observed when utilizing the combined PV and BESS, in comparison to the other two scenarios.
Figure 11 presents a comprehensive overview of the power flow within the system, demonstrating how the PV power, grid power, and BESS power collectively fulfill the system load profile. During the first hour to the sixth hour (initial six hours), when PV power is unavailable, the BESS is charged utilizing the power from the grid. In the period from the 6th hour to the 7th hour, both the grid and BESS contribute to managing the system load in the absence of PV power. From the 7th hour to the 17th hour, the combination of solar PV power and grid power sufficiently meets the load demands while simultaneously charging the BESS. Between the 17th hour and the 19th hour, the system load is adequately supported by PV power, grid power, and BESS power. Notably, the majority of the load from the 20th hour to the 24th hour is handled by the BESS in conjunction with grid power. After the 24th hour, from the 1st hour to the 6th hour (initial 6 hours), the load fulfillment sequence is repeated for the complete day. This indicates a reduced reliance on grid power when PV power and BESS power are available.
Figure 7, Figure 8, Figure 9, Figure 10 and Figure 11 suggest that although the introduction of PV reduces power losses and enhances the voltage profile, the integration of both PV and BESS leads to even more significant improvements in system performance.
The IGWO technique used to determine the OPSBESS has considered 50 populations and 100 iterations to reach the optimal value of the MOF. Figure 12a,b display the convergence curves of the IGWO and IPSO techniques for Case III for the MBRDS.
The above five cases (Case I to V) are presented for the modified IEEE 33-bus RDS. The results of the real 94-bus Portuguese RDS are presented in the next section.

5.4. Real 94-Bus Portuguese RDS

The proposed work of the OPSBESS is implemented in the real 94-bus Portuguese RDS and analyzed for various cases with placements of the PV and BESS (Case I to Case V), as explained below.
Case I: real 94-bus Portuguese RDS.
A single-line diagram of a 15 kV, 100 MVA, 94-bus real RDS located in Portugal is shown in Figure 13 [23,38]. It has a base active and reactive load of 4.797 MW and 2.323 MVAR, respectively [39].
Case II: real 94-bus Portuguese RDS with placements of PV systems (modified real 94-bus Portuguese RDS—MRBPRDS without BESS).
With voltage improvement and loss reduction as prime objectives, three PV systems are placed at specific buses (19, 58, 84) of the real 94-bus Portuguese RDS described in Case I. Thus, the system formed is termed as a modified real 94-bus Portuguese RDS (MRBPRDS). Each PV system has a power rating of 800 kW. Consequently, the aggregate capacity of the three PV systems is 2.4 MW. The addition of three PV systems to the real 94-bus Portuguese RDS changed the load flow, reduced the system losses, and improved the voltage profile of each bus.
Case III: MRBPRDS with aggregated BESS.
In this case, load flow is run to satisfy the MOF and the constraints to find the optimal BESS size and candidate bus for BESS placement after placing three PV systems. Upon conducting the initial load flow analysis, it was determined that Bus 20 emerged as the highest priority location for the installation of the aggregated BESS. This strategic placement of the optimally sized BESS effectively minimized both the APL and PSI while simultaneously maximizing the VSI. Bus 20 was identified as the candidate bus for placing an aggregated BESS with a size of 1.8 MW for the deterministic approach, 1.96 MW for the B-PDF approach, and 1.84 MW for the PMR approach. Figure 14 shows the MRBPRDS with the placement of an aggregated BESS—Case III.

5.4.1. Analysis of MRBPRDS Using Simultaneous and Sequential BESS Placements

Two strategies, simultaneous and sequential BESS placements, are applied to the MRBPRDS, considering their optimal size. For aggregated BESS placement (Case III), as only one unit of the BESS needs to be placed after the first load flow run in the system, there is no difference between the logic for simultaneous and sequential placements of the BESS. This logic of BESS placement is explained in Section 5.2.1 and Section 5.2.2 for the modified IEEE 33-bus RDS. Similarly, it is applied to the MRBPRDS. In these cases, the optimal size of the aggregated BESS unit is distributed optimally into multiple smaller units based on the system’s requirements. The logic of the OPSBESS changes for Case IV and Case V. This logic is implemented in the MRBPRDS for deterministic, probabilistic (Beta PDF), and PMR approaches. The outcomes are presented in Table 3.
The results of the simultaneous and sequential OPSBESS for the MRBPRDS under resource uncertainty are shown in Table 3. The base case load flow is run using the forward–backward sweep method to obtain the system losses. IGT and IPT are applied to multi-objective functions. It is observed that IGT Case III B converges earlier than IPT. It shows a reduction in losses compared to IPT, whereas in the single-objective function (Case III A), IPT gives better results than IGT. This shows that IGT handles the MOF better than IPT, and the same can be visualized from the convergence curves shown in Figure 12a,b.
The loss reduction is obtained for five cases (Case I to Case V) using deterministic, probabilistic, and PMR approaches with simultaneous and sequential BESS placements. It is presented in Table 3 and graphically shown in Figure 15. The comprehensive loss comparison for the modified IEEE 33-bus RDS is given in Figure 15.
It is noted from Figure 15a–c that the loss reduction in the case of sequential BESS placements for all approaches is more significant compared to the simultaneous BESS placements. It is observed from Figure 15d that the loss reduction in the case of sequential BESS placements for the probabilistic approach is greater compared to the other two approaches due to the larger BESS size. The observed reduction in losses may seem marginal; however, it represents a daily decrease in megawatt-hours (MWh) with an aggregated BESS capacity of 1.8 MW for the deterministic approach, 1.96 MW for the probabilistic (β-PDF) approach, and 1.84 MW for the PMR approach. Over the course of a year, this loss reduction will accumulate significantly, particularly with larger BESS capacities implemented in more extensive system configurations. It is observed from Figure 15d that the loss reduction in the case of sequential BESS placements for the probabilistic approach is greater compared to the other two approaches due to the larger BESS size.

5.4.2. Analysis of System Parameters for Probabilistic (Beta PDF) Approach for Real 94-Bus Portuguese RDS

This work analyzes the optimization of multiple objectives, minimizing the APL and PSI and maximizing the VSI for the OPSBESS for the MRBPRDS. The probabilistic approach, specifically the Beta PDF and PMR approach, effectively accounts for uncertainties in solar irradiance and is subsequently compared with a deterministic method. The results include a comprehensive analysis of various system parameters, such as the APL, PSI, VSI, voltage profile, and overall system profile for all three approaches, along with the convergence curve of IGWO. However, for the purpose of understanding, the results are shown for the aggregated OPSBESS (Case III) for the probabilistic approach in Figure 16, Figure 17, Figure 18, Figure 19 and Figure 20.
These figures illustrate three scenarios: the base case (real 94-bus Portuguese RDS—Case I), the PV case (real 94-bus Portuguese RDS with three PV placements—Case II), and the PV + BESS case (MRBPRDS with aggregated BESS integration—Case III).
Figure 16 shows that the system losses are highest in the base case. In the PV case, the system losses decrease with the availability of PV power and reach their lowest when both the PV and BESS are utilized. Placing the PV systems near the maximum load or the farthest end reduced the system losses. Adding three PV systems into the standard real 94-bus Portuguese RDS (MRBPRDS) changed the load flow. The load flow is run considering the APL minimization, PSI minimization, and VSI maximization criteria to identify the weakest bus for aggregated BESS placement. This addition of an aggregated BESS into the MBRDS reduced system losses, irrespective of its charging–discharging cycles. Figure 16 shows a sudden rise in the system losses when the BESS acts as a load and is charged by the PV or grid power in the morning. The system losses decrease when the BESS is discharged in the evening. The net result of the charging and discharging of the BESS throughout the day, along with the PV, reduces the system losses to a greater extent.
The above five cases (Case I to V) for the RDS are analyzed for solar PV irradiance in Portugal. However, depending upon seasonal variations in the solar PV irradiance of a particular location, there may be significant differences in the profiles of solar irradiance. This results in a change in the OPSBESS, which considerably changes the performance of the PV-BES System.
A PSI value nearer to zero (PSI ≤ 0) reflects the improved stability of the line voltage within the system. The bus with the highest PSI value is the most suitable for BESS placement. The IGWO-TOPSIS techniques tried to reduce the PSI values to near to zero along with reducing the APL and maximizing the VSI values. The nature of the PSI changes as per the system characteristics. In the case of the IEEE 33-bus system (Figure 8), the PSI values decreased with PV placement (Case II) and PV + BESS placements (Case III). The PSI values are quite small (PSI ≤ 0) for the base case (Case I); however, these values are further reduced with PV placement and PV + BESS placements.
From Figure 17, it is seen that in the case of the real 94-bus Portuguese RDS, the PSI values are quite small (PSI ≤ 0), and at a few buses, the PSI values merge with the values of the PV and PV + BESS cases. But the PSI values increase at a few buses where the PV and BESS are installed. The combination of the PV and BESS provides greater system stability, with a maximum PSI value of 0.01 p.u.
Figure 18 indicates that the PV + BESS has higher voltage stability than the base case (Case I) and the system with the PV case (Case II). The system is stable when the VSI is less than one and unstable when it is more than one. A VSI closer to one indicates higher voltage stability. After PV placement, the VSI values for all buses (except the slack bus) are computed without the integration of the BESS and arranged in ascending order. The bus that demonstrates the lowest VSI is particularly sensitive to voltage collapse. Consequently, it is identified as the most suitable candidate for the installation of the BESS, which can facilitate improved stability conditions within the system. The IGWO-TOPSIS process maximized this index after placing an optimum-sized BESS.
Figure 19 outlines the system’s voltage profiles for three scenarios: the base case (Case I), the case involving PV placements (Case II), and the case incorporating both PV and BESS placements (Case III). For the base case (94-bus Portuguese RDS), the system voltage is found to be the lowest for all buses. After adding three PV systems to the 94-bus Portuguese RDS, the system voltage at all buses is improved. The system voltage is further enhanced by adding an aggregated BES System. A notable enhancement in the system voltage profile has been observed when utilizing the combined PV and BESS, in comparison to the other two scenarios.
Figure 20 gives the complete power flow of the system and illustrates how solar PV power, grid power, and BESS power collectively meet the system load profile. The load is supplied by the grid and BESS in the first hour and the second hour (initial two hours).
During the third hour to the fifth hour (initial three hours), when PV power is unavailable, the grid supplies power to the load and simultaneously charges the BESS. In the period from the 5th hour to the 8th hour, both the grid and BESS contribute to managing the system load in the absence of PV power. From the 8th hour to the 17th hour, the combination of solar PV power and grid power sufficiently meets the load demands while simultaneously charging the BESS. Between the 17th hour and the 19th hour, the system load is adequately supported by PV power, grid power, and BESS power. Notably, the majority of the load during the 20th hour to the 24th hour and the initial 2 hours is handled by the BESS in conjunction with grid power.
After the third hour to the fifth hour (initial three hours), the load fulfillment sequence is repeated for the complete day. This indicates a reduced reliance on grid power when PV and BESS power are available.
Figure 16, Figure 17, Figure 18, Figure 19 and Figure 20 suggest that although the introduction of the PV reduces power losses and enhances the voltage profile, the integration of both the PV and BESS leads to even more significant improvements in system performance.
The IGWO technique considered 50 populations and 100 iterations to reach the optimal value of the MOF. Figure 21a,b display the convergence curves of the IGWO and IPSO techniques for Case III for the 94-bus Portuguese RDS.
The above five cases (Case I to Case V) implemented in the MBRDS and MRBPRDS indicate that the system losses are minimal for the probabilistic approach (β-PDF). This study shows that the integration of both PV and BES Systems results in more pronounced enhancements in overall system performance.
Resource uncertainty in relation to the optimal planning of Distributed Generations (DGs) or BESSs aimed at minimizing system losses remains relatively underexplored by researchers. This study presents a comparative analysis of existing research outcomes with the proposed work, which specifically focuses on the IEEE 33-bus and 94-bus Portuguese systems, as detailed in Table 4. The proposed work is examined in comparison to prior studies in several key areas, including test systems, the modeling of resource uncertainty, objective functions, optimization techniques, system losses (APLs), the VSI, and the sizing and locations of DGs or BESSs. Furthermore, while the PSI has received limited attention in the literature, this work advocates for its inclusion due to its innovative potential.
These VSI values are notably high for both the IEEE 33-bus and the actual 94-bus Portuguese systems, which can be attributed to the larger PV installations, measuring 6.3985 MW and 5.604 MW, respectively. The dimensions of Distributed Generations (DGs) or BESSs and the corresponding system parameters depicted in this table are associated with the differing objective functions and the varying percentage levels of PV penetration. It is observed that the variations in PV sizes have a significant impact on the sizes of the BESS and influence system parameters such as the APL and VSI.
In this paper, the results derived from the probabilistic approach utilizing the Beta PDF for the MBRDS and the MRBPRDS, which take into account resource uncertainty, are comprehensively discussed. However, the findings associated with the deterministic and PMR approaches are presented in the Appendix A for a better understanding of the importance of the probabilistic approach.

6. Conclusions

The impact of the randomness in solar irradiance and its effect on BESS sizing and placements is analyzed with the help of two RDSs. This work proposes a new approach to the placement of optimally sized BESSs with the prioritized multiple-objective functions of the integrated APL, PSI, and VSI. The function is prioritized using the WSM and simultaneously optimized using the IGT technique. Additionally, the results are validated using the IPT technique.
This study presents five cases (Case I to Case V) for the modified IEEE 33-bus and modified real 94-bus Portuguese RDSs. The presented RDS results are analyzed for solar PV irradiance in Portugal using three approaches. The system losses are minimal for the probabilistic approach compared to the other two approaches due to the largest BESS size. This study suggests that although the introduction of the PV reduces power losses and enhances the voltage profile, the integration of both the PV and BESS leads to even more significant improvements in system performance. In addition to this, the effectiveness and robustness of the sequential and simultaneous BESS placements have been comparatively tested and validated on both RDSs. The sequentially distributed BESS stabilizes the system more than the simultaneously distributed BESS. The distributed BESS placement reduces the system loss significantly compared to the aggregated BESS.
It is observed that system losses are minimal for the probabilistic approach compared to the other two approaches due to the largest BESS size. However, the deterministic approach reflects the results without accounting for variability in the resource. The results indicate that the probabilistic and PMR approaches need larger BESS sizes but give practical solutions to PV-BES Systems, considering the uncertainty in solar irradiance. Therefore, this study shows the importance of using probabilistic and PMR approaches over a deterministic approach for the OPSBESS. The results emphasize that, in practice, for a large BESS capacity, significant loss reduction can be observed along with improved system performance. This study can be extended to various energy resources, such as PV–wind turbine–BESS or PV–wind turbine–fuel cell, for different RDSs.

Author Contributions

Conceptualization, G.M.K. and M.S.T.; methodology, G.M.K.; software, G.M.K.; validation, G.M.K., M.S.T. and G.A.V.; formal analysis, G.M.K.; investigation, G.M.K.; resources, G.M.K.; data curation, G.M.K.; writing—original draft preparation, G.M.K.; writing—review and editing, G.M.K., M.S.T. and G.A.V.; visualization, G.M.K.; supervision, G.M.K., M.S.T. and G.A.V.; project administration, G.M.K. All authors have read and agreed to the published version of the manuscript.

Funding

This research received no external funding.

Data Availability Statement

The raw data supporting the conclusions of this article will be made available by the authors on request.

Conflicts of Interest

Author Geetanjali A. Vaidya was employed by the company Electrical Consultant, SAS Powertech Pvt Ltd. The remaining authors declare that the research was conducted in the absence of any commercial or financial relationships that could be construed as a potential conflict of interest.

Abbreviations

Nomenclature
PRSRated PV power (kW)
sSolar irradiance (kW/m2)
RSRSSolar radiation with the standard environment (kW/m2)
RCRCertain solar irradiance (kW/m2)
Ppv-singlePower rating of single PV panel (kW)
NPVNumber of PV panels
PpvTotal power output of all PV panels (kW)
ΓGamma function
α, βShape parameters of the β-PDF
μ and σMean and standard deviation
p(s) Probability of solar irradiance (W/m2)
tParticular instant
TNOCTTemperature at Nominal Operating Cell Temperature (°C)
TaAmbient temperature (°C)
TcCell temperature (°C)
VMPP Voltage at Maximum Power Point (V)
IMPPCurrent at Maximum Power Point (A)
KVVoltage temperature coefficient (V/°C)
KiCurrent temperature coefficient (A/°C)
VNETNet voltage (V)
VOCOpen-Circuit Voltage (V)
INETNet current (A)
ISCShort-Circuit Current (A)
Fill FactorEfficiency of PV panel (%)
AArea of PV panel (m2)
ηPVEfficiency of PV panel (%)
ρSelf-discharge rate of BESS
EPV(t)Energy generated by PV (kWh)
Eload(t)Energy required by load (kWh)
EBESS(t)Energy stored in battery/BESS (kWh)
ɳBESSEfficiency of BESS (%)
ɳinvEfficiency of inverter (%)
NNumber of buses
Pi and QiActive (W) and reactive (VAR) power injections at the ith bus
Pj and Qj Active (W) and reactive (VAR) power injections at the jth bus
Rij and XijResistance and reactance of the branch connecting ith and jth buses (Ω)
Vi and δiVoltage magnitude (volts) and angle (radians) at the ith bus
Vj and δjVoltage magnitude (volts) and angle (radians) at the jth bus
Yij and θijElements of Y-bus matrix (siemens) and impedance angles (radians)
δPhase angle (radians)
PLActive power at load bus (W)
PGGenerated active power of the system (W)
AbbreviationsFull Form
DGsDistributed Generations
RDSsRadial Distribution Systems
BESBattery Energy Storage
PMRPolynomial Multiple Regression
RERsRenewable Energy Resources
PVPhotovoltaic
BESSBattery Energy Storage System
OPSBESSOptimal Placement and Sizing of BESS
PSIPower Stability Index
APLActive Power Loss
VSIVoltage Stability Index
WSMWeighted Sum Method
IGWOImproved Grey Wolf Optimization
IPSOImproved Particle Swarm Optimization
TOPSISTechnique for Order of Preference by Similarity to the Ideal Solution
β-PDFBeta Probability Density Function
MBRDSModified IEEE 33-bus Radial Distribution System
MRBPRDSModified real 94-bus Portuguese Radial Distribution System
MOFMulti-objective function
PMRAPolynomial Multiple Regression Approach
SOCState of Charge
DSsDistribution Systems
MCDMMulti-Criteria Decision-Making

Appendix A

A.1. Comparison of System Parameters for Deterministic and Polynomial Multiple Regression (PMR) Approaches for Modified IEEE 33-Bus RDS (MBRDS)

The findings of the probabilistic approach (Beta PDF) for the MBRDS, accounting for the resource uncertainty, are thoroughly examined in the main manuscript PDF in Section 5.3. However, due to constraints regarding page limits, the results pertaining to the deterministic and PMR approaches are included in the Appendix.
The various performance parameters of the system, including the system losses (APLs), PSI, VSI, bus voltage profile, and overall system profile, are specifically presented within the probabilistic framework utilizing the Beta PDF in Section 5.3. Figure 6a–c illustrate the system losses (APLs) associated with both the deterministic and PMR approaches. Moreover, a comparative analysis of the APL across the three approaches, given the sequential placement of the BESS, is depicted in Figure 6d. The results encompassing the system performance parameters, excluding the APL, for the deterministic and PMR approaches concerning the MBRDS are tabulated below.
Additional system performance parameters, including the PSI, VSI, system profile, and bus voltage profile, are detailed in Table A1 for the MBRDS. The maximum PSI values obtained for the deterministic and PMR approaches are 0.013 and 0.01 pu, respectively, whereas for probabilistic Beta PDF, this value is 0.01 pu. The VSI values obtained at Bus 18 for the deterministic and PMR approaches are 0.719 and 0.73 pu, respectively, whereas for probabilistic Beta PDF, this value is 0.73 pu. The voltage at Bus 18 obtained for the deterministic and PMR approaches is 0.95 and 0.958 pu, respectively, whereas for probabilistic Beta PDF, the voltage is 0.958 pu.
Table A1. Results of Case III B of MOF for MBRDS using IGT.
Table A1. Results of Case III B of MOF for MBRDS using IGT.
ParametersDeterministic Approach (BESS Size = 2.3 MW)PMR Approach (BESS Size = 2.4 MW)
PSIEnergies 18 02340 i001Energies 18 02340 i002
VSIEnergies 18 02340 i003Energies 18 02340 i004
Bus voltage
profile
Energies 18 02340 i005Energies 18 02340 i006
System profileEnergies 18 02340 i007Energies 18 02340 i008
The variations in the system performance parameters and BESS sizing are influenced by the output from the photovoltaic (PV) system, which fluctuates based on the adopted solar irradiance modeling approach. It is important to note that these variations may be minimal for smaller systems with smaller BESS sizes, whereas more pronounced changes in BESS sizes and corresponding system performance parameters are anticipated for larger systems.

A.2. Comparison of System Parameters for Deterministic and Polynomial Multiple Regression (PMR) Approaches for Modified Real 94-Bus Portuguese RDS (MRBPRDS)

The results obtained from the probabilistic approach utilizing the Beta Probability Density Function, which accounts for resource uncertainty, are comprehensively discussed within the main manuscript for the MRBPRDS in Section 5.4.2. However, due to limitations imposed by page constraints, the results concerning the deterministic and PMR approaches have been relegated to the Appendix.
The various performance parameters of the system, including the system losses (APLs), PSI, VSI, bus voltage profile, and overall system profile, are specifically presented within the probabilistic framework utilizing the Beta PDF in Section 5.4.2. Figure 15a–c illustrate the system losses (APLs) associated with both the deterministic and PMR approaches. Moreover, a comparative analysis of the APL across the three approaches, for the sequential placement of the BESS, is depicted in Figure 15d. The results encompassing the system performance parameters, excluding the APL, for the deterministic and PMR approaches concerning the MRBPRDS are tabulated below.
Additional system performance parameters, including the PSI, VSI, system profile, and bus voltage profile, are detailed in Table A2 for the MRBPRDS. The maximum PSI values obtained for the deterministic and PMR approaches are 0.099 and 0.01 pu, respectively, whereas for probabilistic Beta PDF, this value is 0.01 pu. The VSI values obtained at Bus 33 for the deterministic and PMR approaches are 0.78 and 0.8 pu, respectively, whereas for probabilistic Beta PDF, this value is 0.8 pu. The voltage at Bus 33 obtained for deterministic and PMR approaches is 0.91 and 0.91 pu, respectively, whereas for probabilistic Beta PDF, the voltage is 0.92 pu.
Table A2. Results of Case III B of MOF for MRBPRDS using IGT.
Table A2. Results of Case III B of MOF for MRBPRDS using IGT.
ParametersDeterministic Approach (BESS Size = 1.8 MW)PMR Approach (BESS Size = 1.84 MW)
PSIEnergies 18 02340 i009Energies 18 02340 i010
VSIEnergies 18 02340 i011Energies 18 02340 i012
Bus voltage profileEnergies 18 02340 i013Energies 18 02340 i014
System
profile
Energies 18 02340 i015Energies 18 02340 i016
The sizing of the BESS and the performance parameters of systems are significantly affected by the output from PV systems, which can vary according to the selected solar irradiance modeling approach. It is important to acknowledge that while these variations may be minimal for smaller systems with smaller BESS sizes, more significant adjustments in BESS sizing and related performance parameters are expected for larger systems.

References

  1. Alzahrani, A.; Alharthi, H.; Khalid, M. Minimization of Power Losses through Optimal Battery Placement in a Distributed Network with High Penetration of Photovoltaics. Energies 2020, 13, 140. [Google Scholar] [CrossRef]
  2. Alshahrani, A.; Omer, S.; Su, Y.; Mohamed, E.; Alotaibi, S. The Technical Challenges Facing the Integration of Small-Scale and Large-scale PV Systems into the Grid: A Critical Review. Electronics 2019, 8, 1443. [Google Scholar] [CrossRef]
  3. Hameed, Z.; Hashemi, S.; Træholt, C. Site Selection Criteria for Battery Energy Storage in Power Systems. In Proceedings of the 2020 IEEE Canadian Conference on Electrical and Computer Engineering (CCECE), London, ON, Canada, 30 August–2 September 2020; pp. 1–7. [Google Scholar]
  4. Mohamad, F.; Teh, J.; Lai, C.-M.; Chen, L.-R. Development of Energy Storage Systems for Power Network Reliability: A Review. Energies 2018, 11, 2278. [Google Scholar] [CrossRef]
  5. Abdolahi, A.; Salehi, J.; Samadi Gazijahani, F.; Safari, A. Probabilistic multi-objective arbitrage of dispersed energy storage systems for optimal congestion management of active distribution networks including solar/wind/CHP hybrid energy system. J. Renew. Sustain. Energy 2018, 10, 045502. [Google Scholar] [CrossRef]
  6. Zhengmao, L.; Yan, X.; Sidun, F.; Yu, W. Multi-objective Coordinated Energy Dispatch and Voyage Scheduling for a Multi-energy Cruising Ship. In Proceedings of the 2019 IEEE/IAS 55th Industrial and Commercial Power Systems Technical Conference (I&CPS), Calgary, AB, Canada, 5–8 May 2019; pp. 1–8. [Google Scholar]
  7. Matthiss, B.; Momenifarahani, A.; Binder, J. Storage Placement and Sizing in a Distribution Grid with High PV Generation. Energies 2021, 14, 303. [Google Scholar] [CrossRef]
  8. Nor, N.M.; Ali, A.; Ibrahim, T.; Romlie, M.F. Battery Storage for the Utility-Scale Distributed Photovoltaic Generations. IEEE Access 2018, 6, 1137–1154. [Google Scholar] [CrossRef]
  9. Szultka, A.; Szultka, S.; Czapp, S.; Lubosny, Z.; Malkowski, R. Integrated Algorithm for Selecting the Location and Control of Energy Storage Units to Improve the Voltage Level in Distribution Grids. Energies 2020, 13, 6720. [Google Scholar] [CrossRef]
  10. Yuan, Z.; Wang, W.; Wang, H.; Yildizbasi, A. A new methodology for optimal location and sizing of battery energy storage system in distribution networks for loss reduction. J. Energy Storage 2020, 29, 101368. [Google Scholar] [CrossRef]
  11. Mohamed, A.A.R.; Morrow, D.J.; Best, R.J.; Bailie, I.; Cupples, A.; Pollock, J. Battery Energy Storage Systems Allocation Considering Distribution Network Congestion. In Proceedings of the 2020 IEEE PES Innovative Smart Grid Technologies Europe (ISGT-Europe), Hague, The Netherlands, 26–28 October 2020; pp. 1015–1019. [Google Scholar]
  12. Meena, N.K.; Parashar, S.; Swarnkar, A.; Gupta, N.; Niazi, K.R. Improved Elephant Herding Optimization for Multiobjective DER Accommodation in Distribution Systems. IEEE Trans. Ind. Inform. 2018, 14, 1029–1039. [Google Scholar] [CrossRef]
  13. Zhang, Y.; Ren, S.; Dong, Z.Y.; Xu, Y.; Meng, K.; Zheng, Y. Optimal placement of battery energy storage in distribution networks considering conservation voltage reduction and stochastic load composition. IET Gener. Transm. Dis. 2017, 11, 3862–3870. [Google Scholar] [CrossRef]
  14. Shafiq, S.; Khan, B.; Al-Awami, A.T. Optimal Battery Placement in Distribution Network Using Voltage Sensitivity Approach. In Proceedings of the 2019 IEEE Power and Energy Conference at Illinois (PECI), Champaign, IL, USA, 28 February–1 March 2019; p. 8698781. [Google Scholar]
  15. Khunkitti, S.; Boonluk, P.; Siritaratiwat, A. Optimal Location and Sizing of BESS for Performance Improvement of Distribution Systems with High DG Penetration. Int. Trans. Electr. Energy Syst. 2022, 2022, 6361243. [Google Scholar] [CrossRef]
  16. Damian, S.; Wong, L.A. Optimal Energy Storage Placement and Sizing in Distribution System. In Proceedings of the 2022 IEEE International Conference in Power Engineering Application (ICPEA), Shah Alam, Malaysia, 7–8 March 2022; pp. 1–6. [Google Scholar]
  17. Li, X.; Hu, C.; Luo, S.; Lu, H.; Piao, Z.; Jing, L. Distributed Hybrid-Triggered Observer-Based Secondary Control of Multi-Bus DC Microgrids Over Directed Networks. IEEE Trans. Circuits Syst. I Regul. Pap. 2025, 1–14. [Google Scholar] [CrossRef]
  18. López, L.; López, I.; Gomez-Cornejo, J.; Aranzabal, I.; Eguia, P. Analysis of impact for PV-BES strategies in low-voltage distribution system. Electr. Eng. 2024, 107, 2147–2162. [Google Scholar] [CrossRef]
  19. Till, J.; You, S.; Liu, Y.; Du, P. Impact of High PV Penetration on Voltage Stability. In Proceedings of the 2020 IEEE/PES Transmission and Distribution Conference and Exposition (T&D), Chicago, IL, USA, 12–15 October 2020. [Google Scholar]
  20. Abdel-Mawgoud, H.; Kamel, S.; Tostado-Véliz, M.; Elattar, E.E.; Hussein, M.M. Optimal Incorporation of Photovoltaic Energy and Battery Energy Storage Systems in Distribution Networks Considering Uncertainties of Demand and Generation. Appl. Sci. 2021, 11, 8231. [Google Scholar] [CrossRef]
  21. Khasanov, M.; Kamel, S.; Hassan, M.H.; Domínguez-García, J.L. Maximizing renewable energy integration with battery storage in distribution systems using a modified Bald Eagle Search Optimization Algorithm. Neural Comput. Appl. 2024, 36, 8577–8605. [Google Scholar] [CrossRef]
  22. NASA. NASA Prediction Of Worldwide Energy Resources (POWER). Available online: https://power.larc.nasa.gov/data-access-viewer/ (accessed on 29 March 2025).
  23. Dehnavi, E.; Afsharnia, S.; Gholami, K. Optimal allocation of unified power quality conditioner in the smart distribution grids. Electr. Eng. 2019, 101, 1277–1293. [Google Scholar] [CrossRef]
  24. Hi-MO 5m (G2). LR5-72HPH 540~560M; LONGi: Shanghai, China, 2022. [Google Scholar]
  25. Maleki, A.; Askarzadeh, A. Comparative study of artificial intelligence techniques for sizing of a hydrogen-based stand-alone photovoltaic/wind hybrid system. Int. J. Hydrogen Energy 2014, 39, 9973–9984. [Google Scholar] [CrossRef]
  26. Aman, M.M.; Jasmon, G.B.; Mokhlis, H.; Bakar, A.H.A. Optimal placement and sizing of a DG based on a new power stability index and line losses. Int. J. Electr. Power Energy Syst. 2012, 43, 1296–1304. [Google Scholar] [CrossRef]
  27. Danish, M.S.S.; Senjyu, T.; Danish, S.M.S.; Sabory, N.R.; K, N.; Mandal, P. A Recap of Voltage Stability Indices in the Past Three Decades. Energies 2019, 12, 1544. [Google Scholar] [CrossRef]
  28. Kolios, A.; Mytilinou, V.; Lozano-Minguez, E.; Salonitis, K. A Comparative Study of Multiple-Criteria Decision-Making Methods under Stochastic Inputs. Energies 2016, 9, 566. [Google Scholar] [CrossRef]
  29. Qiu, Y.; Yang, X.; Chen, S. An improved gray wolf optimization algorithm solving to functional optimization and engineering design problems. Sci. Rep. 2024, 14, 14190. [Google Scholar] [CrossRef] [PubMed]
  30. Altayara, I.A.; Al-Ammar, E.A.; Ghazi, G.A.; Katheri, A.A.A. Optimal Allocation of Distributed Generation Using Modified Grey Wolf Optimizer. In Proceedings of the 2022 International Conference on Automation, Computing and Renewable Systems (ICACRS), Pudukkottai, India, 13–15 December 2022; pp. 884–889. [Google Scholar]
  31. Gandhi, K.J.; Patil, N. Solving Economic Load Dispatch Problem using Grey Wolf Optimizer Method. Int. J. Recent Technol. Eng. 2019, 8, 684–688. [Google Scholar] [CrossRef]
  32. Nimma, K.S.; Al-Falahi, M.D.A.; Nguyen, H.D.; Jayasinghe, S.D.G.; Mahmoud, T.S.; Negnevitsky, M. Grey Wolf Optimization-Based Optimum Energy-Management and Battery-Sizing Method for Grid-Connected Microgrids. Energies 2018, 11, 847. [Google Scholar] [CrossRef]
  33. Miao, D.; Hossain, S. Improved gray wolf optimization algorithm for solving placement and sizing of electrical energy storage system in micro-grids. ISA Trans. 2020, 102, 376–387. [Google Scholar] [CrossRef] [PubMed]
  34. Mirjalili, S.; Mirjalili, S.M.; Lewis, A. Grey Wolf Optimizer. Adv. Eng. Softw. 2014, 69, 46–61. [Google Scholar] [CrossRef]
  35. Hou, Y.; Gao, H.; Wang, Z.; Du, C. Improved Grey Wolf Optimization Algorithm and Application. Sensors 2022, 22, 3810. [Google Scholar] [CrossRef]
  36. Hwang, C.-L.; Yoon, K. Methods for Multiple Attribute Decision Making. In Multiple Attribute Decision Making: Methods and Applications A State-of-the-Art Survey; Springer: Berlin/Heidelberg, Germany, 1981; pp. 58–191. [Google Scholar]
  37. Galgali, V.S.; Ramachandran, M.; Vaidya, G.A. Multi-Objective Optimal Placement and Sizing of DGs by Hybrid Fuzzy TOPSIS and Taguchi Desirability Function Analysis Approach. Electr. Power Compon. Syst. 2021, 48, 2144–2155. [Google Scholar] [CrossRef]
  38. Elkadeem, M.R.; Elaziz, M.A.; Ullah, Z.; Wang, S.; Sharshir, S.W. Optimal Planning of Renewable Energy-Integrated Distribution System Considering Uncertainties. IEEE Access 2019, 7, 164887–164907. [Google Scholar] [CrossRef]
  39. Malik, M.Z.; Kumar, M.; Soomro, A.M.; Baloch, M.H.; Farhan, M.; Gul, M.; Kaloi, G.S. Strategic planning of renewable distributed generation in radial distribution system using advanced MOPSO method. Energy Rep. 2020, 6, 2872–2886. [Google Scholar] [CrossRef]
Figure 1. Schematic of grid−connected PV−BES System.
Figure 1. Schematic of grid−connected PV−BES System.
Energies 18 02340 g001
Figure 2. Profiles of solar irradiance in Portugal.
Figure 2. Profiles of solar irradiance in Portugal.
Energies 18 02340 g002
Figure 3. Average daily load curves for (a) IEEE 33-bus and (b) 94-bus Portuguese RDSs.
Figure 3. Average daily load curves for (a) IEEE 33-bus and (b) 94-bus Portuguese RDSs.
Energies 18 02340 g003
Figure 4. Flow chart of IGWO for OPSBESS.
Figure 4. Flow chart of IGWO for OPSBESS.
Energies 18 02340 g004
Figure 5. MBRDS with an aggregated BESS placement—Case III (Red arrows indicate the load at that bus).
Figure 5. MBRDS with an aggregated BESS placement—Case III (Red arrows indicate the load at that bus).
Energies 18 02340 g005
Figure 6. System losses (APLs) for (a) deterministic, (b) probabilistic, and (c) Polynomial Multiple Regression approaches and (d) sequential BESS placements for three approaches.
Figure 6. System losses (APLs) for (a) deterministic, (b) probabilistic, and (c) Polynomial Multiple Regression approaches and (d) sequential BESS placements for three approaches.
Energies 18 02340 g006
Figure 7. System Active Power Loss (APL) for base, PV, and PV + BESS cases for MBRDS.
Figure 7. System Active Power Loss (APL) for base, PV, and PV + BESS cases for MBRDS.
Energies 18 02340 g007
Figure 8. PSI for base, PV, and PV + BESS cases for MBRDS.
Figure 8. PSI for base, PV, and PV + BESS cases for MBRDS.
Energies 18 02340 g008
Figure 9. VSI for base, PV, and PV + BESS cases for MBRDS.
Figure 9. VSI for base, PV, and PV + BESS cases for MBRDS.
Energies 18 02340 g009
Figure 10. Voltage profile for base, PV, and PV + BESS cases for MBRDS.
Figure 10. Voltage profile for base, PV, and PV + BESS cases for MBRDS.
Energies 18 02340 g010
Figure 11. System profile with solar PV power, BESS power, grid power, and system load for MBRDS.
Figure 11. System profile with solar PV power, BESS power, grid power, and system load for MBRDS.
Energies 18 02340 g011
Figure 12. Convergence curves of (a) IGWO and (b) IPSO for MBRDS.
Figure 12. Convergence curves of (a) IGWO and (b) IPSO for MBRDS.
Energies 18 02340 g012
Figure 13. Single-line diagram of real 94-bus RDS, Portugal (Red arrows indicate the load at that bus) [23].
Figure 13. Single-line diagram of real 94-bus RDS, Portugal (Red arrows indicate the load at that bus) [23].
Energies 18 02340 g013
Figure 14. MRBPRDS with aggregated BESS placement—Case III (Red arrows indicate the load at that bus).
Figure 14. MRBPRDS with aggregated BESS placement—Case III (Red arrows indicate the load at that bus).
Energies 18 02340 g014
Figure 15. System losses for (a) deterministic, (b) probabilistic, and (c) Polynomial Multiple Regression approaches and (d) sequential BESS placements for three approaches.
Figure 15. System losses for (a) deterministic, (b) probabilistic, and (c) Polynomial Multiple Regression approaches and (d) sequential BESS placements for three approaches.
Energies 18 02340 g015
Figure 16. System active power loss (APL) for base, PV, and PV + BESS cases for MRBPRDS.
Figure 16. System active power loss (APL) for base, PV, and PV + BESS cases for MRBPRDS.
Energies 18 02340 g016
Figure 17. PSI for base, PV, and PV + BESS cases for MRBPRDS.
Figure 17. PSI for base, PV, and PV + BESS cases for MRBPRDS.
Energies 18 02340 g017
Figure 18. VSI for base, PV, and PV + BESS cases for MRBPRDS.
Figure 18. VSI for base, PV, and PV + BESS cases for MRBPRDS.
Energies 18 02340 g018
Figure 19. Voltage profile for base, PV, and PV + BESS cases for MRBPRDS.
Figure 19. Voltage profile for base, PV, and PV + BESS cases for MRBPRDS.
Energies 18 02340 g019
Figure 20. System profile with solar PV power, BESS power, grid power, and system load for MRBPRDS.
Figure 20. System profile with solar PV power, BESS power, grid power, and system load for MRBPRDS.
Energies 18 02340 g020
Figure 21. Convergence curves of (a) IGWO and (b) IPSO for MRBPRDS.
Figure 21. Convergence curves of (a) IGWO and (b) IPSO for MRBPRDS.
Energies 18 02340 g021
Table 1. Specifications of 550Wp solar PV panel [24].
Table 1. Specifications of 550Wp solar PV panel [24].
Sr. No.Parameter (Symbol)ValueUnit
1Rated power of solar PV panel (PRS)550Wp
2Ambient temperature (TA)19.19°C
3Cell temperature (TC)25°C
4Normal Operating Cell Temperature (TNOCT)45°C
5Short-Circuit Current (ISC)11.29A
6Current at Maximum Power Point (IMPP)10.51A
7Current temperature coefficient (Ki)0.05A/°C
8Open-Circuit Voltage (Voc)46.82V
9Voltage at Maximum Power Point (VMPP)39.14V
10Voltage temperature coefficient (Kv)−0.265V/°C
11Efficiency of PV panel21.3%
12Length of PV panel2.278M
13Width of PV panel1.134M
Table 2. Simultaneous and sequential OPSBESS for MBRDS.
Table 2. Simultaneous and sequential OPSBESS for MBRDS.
Case NumberDeterministic ApproachProbabilistic Beta PDF ApproachPolynomial Multiple Regression Approach
Simultaneous OPSBESSSequential
OPSBESS
Simultaneous OPSBESSSequential
OPSBESS
Simultaneous OPSBESSSequential
OPSBESS
BESS Location (Size, MW)System Losses (MWh)BESS Location (Size, MW)System Losses (MWh)BESS Location (Size, MW)System Losses (MWh)BESS Location (Size, MW)System Losses (MWh)BESS Location (Size MW)System Losses (MWh)BESS Location (Size, MW)System Losses (MWh)
Case INo PV and No BESS (W1 = 1, W2 = W3 = 0)
IGT -2.649-2.649-2.649-2.649-2.649-2.649
IPT-2.649-2.649-2.649-2.649-2.649-2.649
Case IIWith 3 PV Systems and No BESS (W1 = 1, W2 = W3 = 0)
IGT No BESS2.170No BESS2.170No BESS2.064No BESS2.064No BESS2.162No BESS2.162
IPTNo BESS2.170No BESS2.170No BESS2.064No BESS2.064No BESS2.162No BESS2.162
Case III AWith 3 PV Systems and 1 BESS Unit (Aggregated BESS) (W1 = 1, W2 = W3 = 0)
IGT 30(2.326)2.21230(2.326)2.21229(2.414)2.01729(2.414)2.01730(2.324)2.18630 (2.324)2.186
IPT 30(2.270)2.16830(2.270)2.16829(2.356)1.98029(2.356)1.98030(2.266)2.14030 (2.266)2.140
Case III BWith 3 PV Systems and 1 BESS Unit (Aggregated BESS) (W1 = 0.4, W2 = W3 = 0.3)
IGT 26 (2.30)1.89026 (2.30)1.89026 (2.42)1.78526 (2.42)1.78526 (2.40)1.87126 (2.40)1.871
IPT26 (2.26)1.89926 (2.26)1.89926 (2.36)1.86726 (2.36)1.86726 (2.27)1.88226 (2.27)1.882
Case IVWith 3 PV Systems and 2 BESS Units (W1 = 0.4, W2 = W3 = 0.3)
IGT14 (1.60)1.83226 (1.89)1.8107 (0.65)1.76926 (2.09)1.7357 (0.98)1.83526 (1.99)1.812
30 (0.70)18 (0.43)26 (1.77)18 (0.33)25 (1.51)18 (0.45)
IPT14 (0.55)1.86726 (1.98)1.86015 (0.55)1.85026 (1.80)1.84514 (0.49)1.86026 (1.98)1.855
27 (1.71)18 (0.28)27 (1.81)30 (0.56)19 (1.77)18 (0.29)
Case VWith 3 PV Systems and 3 BESS Units (W1 = 0.4, W2 = W3 = 0.3)
IGT18 (0.58)1.73726 (1.67)1.71912 (0.64)1.72426 (1.51)1.6317 (0.67)1.74126 (1.60)
26 (1.16)18 (0.44)26 (1.36)18 (0.63)26 (1.24)18 (0.50)1.702
30 (0.57)25 (0.21)32 (0.41)30 (0.26)30 (0.51)32 (0.21)
IPT15 (0.47)1.75526 (1.54)1.74115 (0.39)1.73526 (1.75)1.68525 (0.43)1.75026 (1.66)1.739
26 (0.94)18 (0.49)19 (0.83)18 (0.33)26 (1.09)18 (0.39)
30 (0.85)25 (0.23)26 (1.13)30 (0.28)30 (0.74)30 (0.22)
IGT: Improved Grey Wolf Optimization—Technique for Order of Preference by Similarity to the Ideal Solution, IPT: Improved Particle Swarm Optimization—Technique for Order of Preference by Similarity to the Ideal Solution. Deterministic Aggregated Optimal BESS Size = 2.3 MW (IGT), 2.26 MW (IPT), Probabilistic Beta PDF Aggregated Optimal BESS Size = 2.42 MW (IGT), 2.36 MW (IPT), Polynomial Multiple Regression Aggregated Optimal BESS Size = 2.4 MW (IGT), 2.27 MW (IPT).
Table 3. Simultaneous and sequential OPSBESS for MRBPRDS.
Table 3. Simultaneous and sequential OPSBESS for MRBPRDS.
Case NumberDeterministic Approach Probabilistic Beta PDF ApproachPolynomial Multiple Regression Approach
Simultaneous OPSBESSSequential
OPSBESS
Simultaneous OPSBESSSequential
OPSBESS
Simultaneous OPSBESSSequential
OPSBESS
BESS Location (Size, MW)System Losses (MWh)BESS Location (Size, MW)System Losses (MWh)BESS Location (Size, MW)System Losses (MWh)BESS Location (Size, MW)System Losses (MWh)BESS Location (Size MW)System Losses (MWh)BESS Location (Size, MW)System Losses (MWh)
Case INo PV and No BESS (W1 = 1, W2 = W3 = 0)
IGT-6.772-6.772-6.772-6.772-6.772-6.772
IPT-6.772-6.772-6.772-6.772-6.772-6.772
Case IIWith 3 PV Systems and No BESS (W1 = 1, W2 = W3 = 0)
IGTNo BESS5.382No BESS5.382No BESS5.108No BESS5.108No BESS5.378No BESS5.378
IPTNo BESS5.382No BESS5.382No BESS5.108No BESS5.108No BESS5.378No BESS5.378
Case III AWith 3 PV Systems and 1 BESS Unit (Aggregated BESS) (W1 = 1, W2 = W3 = 0)
IGT19 (1.8)4.83719 (1.8)4.83819 (1.96)4.55219 (1.96)4.55219 (1.84)4.84619 (1.84)4.846
IPT19 (1.8)4.83819 (1.8)4.83819 (1.96)4.55319 (1.96)4.55319 (1.84)4.84719 (1.84)4.847
Case III BWith 3 PV Systems and 1 BESS Unit (Aggregated BESS) (W1 = 0.4, W2 = W3 = 0.3)
IGT20 (1.8)4.90220 (1.8)4.90220 (1.96)4.58020 (1.96)4.61720 (1.84)4.86920 (1.84)4.869
IPT20 (1.8)4.90220 (1.8)4.90220 (1.96)4.58020 (1.96)4.55320 (1.84)4.87020 (1.84)4.870
Case IVWith 3 PV Systems and 2 BESS Units (W1 = 0.4, W2 = W3 = 0.3)
IGT77 (1.09)4.63920 (1.00)4.62077 (1.21)4.35620 (1.37)4.32577 (1.38)4.68120 (1.67)4.621
61 (0.75)58 (0.8)88 (0.74)58 (0.58)61 (0.45)58 (0.17)
IPT58 (1.44)4.64020 (1.09)4.63958 (1.17)4.35620 (1.25)4.33977 (1.38)4.70320 (1.37)4.693
77 (0.40)58 (0.75)77 (0.79)58 (0.71)61 (0.47)58 (0.48)
Case VWith 3 PV Systems and 3 BESS Units (W1 = 0.4, W2 = W3 = 0.3)
IGT20 (1.02)4.61320 (0.87)4.61658 (0.68)4.39120 (1.26)4.33520 (0.92)4.63220 (1.56)4.612
58 (0.1)58 (0.72)77 (0.75)58 (0.54)58 (0.52)58 (0.20)
77 (0.72)84 (0.23)84 (0.52)84 (0.15)77 (0.40)84 (0.07)
IPT20 (0.45)4.63120 (1.058)4.61558 (1.22)4.36520 (1.35)4.35220 (0.87)4.70420 (1.35)4.703
27 (0.78)50 (0.04)77 (0.72)58 (0.53)59 (0.58)58 (0.42)
59 (0.61)58 (0.75)84 (0.02)92 (0.08)84 (0.40)92 (0.08)
IGT: Improved Grey Wolf Optimization—Technique for Order of Preference by Similarity to the Ideal Solution, IPT: Improved Particle Swarm Optimization—Technique for Order of Preference by Similarity to the Ideal Solution. Deterministic Aggregated Optimal BESS Size = 1.8 MW (IGT, IPT), Probabilistic Beta PDF Aggregated Optimal BESS Size = 1.96 MW (IGT, IPT), Polynomial Multiple Regression Aggregated Optimal BESS Size = 1.84 MW (IGT, IPT).
Table 4. Table of comparison for resource uncertainty.
Table 4. Table of comparison for resource uncertainty.
Sr. No.PaperResource UncertaintyMOFOptimization TechniquesAPL
(kW)
PSI
(pu)
VSI
(pu)
DG/BESS Size (MW) and Location
IEEE 33-bus RDS
1Arya Abdolahi [5]PV by Beta PDF; wind by
Weibull PDF
Congestion alleviation and procurement cost minimizationMOPSONot mentioned--2 PVs @ Bus 11, 22; 2 WTs @ Bus 6, 32; 2 CHP @ Bus 16, 26; 6 BESSs @ Bus 5, 10, 14, 20, 24,31.
Total DG Size = not mentioned.
2Mohd Nor [7]PV by Beta PDFELI and VDGA14,773.75--PV of 3.3 @ Bus 6; BESS of 1.84 @ Bus 6.
Total DG Size = 3.3 MW.
3Elkadeem [36]PV by Beta PDFLoss, VSI, VD, and AELHHO83.0964-(28.828) or 0.9 *3 PVs (0.761 @ Bus 14;
1.0947 @ Bus 24; 1.0684 @ Bus 30); 3 WTs (0.8204 @ Bus 14; 1.173 @ Bus 24; 1.481 @ Bus 30). Total DG Size = 6.3985 MW.
4Proposed WorkPV by Beta PDF and PMRAPL, PSI, and VSI (W1 = 0.4, W2 = W3 = 0.3)IGWO74.3750.010.8PV of 0.6 MW @ Bus 18, 25, 30; BESS of 2.42 @ Bus 26.
Total DG Size = 1.8 MW.
Real 94-bus Portuguese RDS
5Elkadeem [36]PV by Beta PDFLoss, VSI, VD, and AELHHO213.661-(76.384) or 0.82 *1 PV (2.636 @ Bus 19); 1 WT (2.968 @ Bus 19).
Total DG Size = 5.604 MW.
6Proposed WorkPV by Beta PDF and PMRAPL, PSI, and VSI (W1 = 0.4, W2 = W3 = 0.3)IGWO192.3750.010.62PV of 0.8 MW @ Bus 19, 58, 84; BESS of 1.96 @ Bus 20.
Total DG Size = 2.4 MW.
APL: Active Power Loss; PSI: Power Stability Index; VSI: Voltage Stability Index; DG/BESS: Distributed Generation/Battery Energy Storage System; MOPSO: Multi-Objective Particle Swarm Optimization; WT: wind turbine; CHP: Combined Heat Power; ELI: Energy Loss Index; VD: voltage deviation; GA: Genetic Algorithm; AEL: Annual Economic Loss; HHO: Harris Hawk Optimizer; PMR: Polynomial Multiple Regression; IGWO: Improved Grey Wolf Optimization. * Overall VSI (OVSI) = ( i = 2 N B | O V S I | ) at all buses except the slack bus.
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Karve, G.M.; Thakare, M.S.; Vaidya, G.A. Optimal Siting and Sizing of Battery Energy Storage System in Distribution System in View of Resource Uncertainty. Energies 2025, 18, 2340. https://doi.org/10.3390/en18092340

AMA Style

Karve GM, Thakare MS, Vaidya GA. Optimal Siting and Sizing of Battery Energy Storage System in Distribution System in View of Resource Uncertainty. Energies. 2025; 18(9):2340. https://doi.org/10.3390/en18092340

Chicago/Turabian Style

Karve, Gauri Mandar, Mangesh S. Thakare, and Geetanjali A. Vaidya. 2025. "Optimal Siting and Sizing of Battery Energy Storage System in Distribution System in View of Resource Uncertainty" Energies 18, no. 9: 2340. https://doi.org/10.3390/en18092340

APA Style

Karve, G. M., Thakare, M. S., & Vaidya, G. A. (2025). Optimal Siting and Sizing of Battery Energy Storage System in Distribution System in View of Resource Uncertainty. Energies, 18(9), 2340. https://doi.org/10.3390/en18092340

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop